Niko Manalili

Karen Barrozo
Sunny Ballesteros
The Bloodless Coup Concert
Activity Time: 18 Days
Code
a
b
c
d
e
f
g
h
i
j
k
l

Activity Description

Predecessor

Print Tickets
a
Hotel and Transportation arrangements
a
Negotiate with Local union
a
Hire Stagehand
d
Get some student ushers
d
Arrange Press Conference
c
Set up the Stage
e
Assign Ushers
f
Advertising and Promotion
b
Hiring another act
Sell tickets
b
Find a place: Get an auditorium

Time Estimate (in Days)


a
m
b
t
ES
2
4
7
4.17
0.00000
1
2
4
2.17
4.16667
3
5
10
5.50
4.16667
1
3
8
3.50
4.16667
2
4
7
4.17
7.66667
1
3
5
3.00
7.66667
3
2
4
2.50
9.66667
2
3
6
3.33
11.83333
1
2
3
2.00
10.66667
2
6
12
6.33
6.33333
4
5
8
5.33
0.00000
1
5
12
5.50
6.33333
Project Duration
Critical Path

EF
4.16667
6.33333
9.66667
7.66667
11.83333
10.66667
12.16667
15.16667
12.66667
12.66667
5.33333
11.83333
15.1667
A,D,E,H

LS
0.00000
6.66667
7.16667
4.16667
7.66667
10.16667
12.66667
11.83333
13.16667
8.83333
4.33333
9.66667

LF
Slack Variance
4.16667
0
0.69
8.83333
3
12.66667
3
7.66667
0
1.36
11.83333
0
0.69
13.16667
3
15.16667
3
15.16667
0
0.44
15.16667
3
15.16667
3
9.66667
4
15.16667
3
Project Variance 3.19444444
Project std Dev 1.78730088

Z=(Sample Mean-overall mean)/overall SD


Z=(18-15.1667)/1.7873
Z=
1.585258
Probability 0.943546 or
94.35%

Niko Manalili
Karen Barrozo
Sunny Ballesteros

Gantt Chart
a
b
c
d
e
f
g
h
i
j
k
l
0

10

12

Time
Critical Activity

Noncritical Activity

Slack

14

16