Professional Documents
Culture Documents
Enterprises)
3. SIZING CALCULATIONS FOR CAPACITOR
BANKS
The optimal sizing calculation is done with the help of
various proposed mathematical models & procedures
[1]-[10]. We can calculate the size of capacitor bank
for given electrical substation as mentioned. 1 is the
lowest power factor of the total construction power
network which is to be improving up to [2].
International Journal of Emerging Technologies and Engineering (IJETE)
Volume 1 Issue 5, June 2014, ISSN 2348 8050
137
www.ijete.org
Fig Vector diagram for compensated kvar.
The sizing calculation is done on the basis of example
below.
For 630kVA Substation, let us consider maximum load
current is 1250A & power factor of source which is a
630kVA transformer is 0.8. First step is to calculate
the initial power factor. For this we have consider that
the load on the substation is consist of motors&
welding machines. We will take the average power
factor from the table 1 & 2[2].
Table 1
Typical Motor Power Factors
Power
(hp)
Speed
(rpm)
Power Factor
1/2
load
3/4
load
full
load
0 - 5 1800 0.72 0.82 0.84
5-20 1800 0.74 0.84 0.86
20 - 100 1800 0.79 0.86 0.89
100 - 300 1800 0.81 0.88 0.91
Average P.f = 0.765 0.85 0.875
1 hp = 745.7 Watt
As per table 1, the values of power factor vs load chart
is given. On the basis of that we will calculate the
average power factor for the typical motor loads. In
table 2 shows welding machine from various
manufacturers with model no & power factor.
The initial power factor is taken as 0.76 against the
lowest average power factor is 0.765 (Cos 40.536
0
).
Table 2
Welding Machine
Vendor Model p.f Reference links
Weld-man
TIG160S 0.73
http://www.wel
dman.in/62.htm
l
TIG200S 0.73
TIG250S 0.73
TIG300S 0.73
ELECTR
A
MIG200 0.85 http://electrawel
ding.com/invert
erweldingmach
ines.
Html
MIG250 0.93
WELDAR
C
IGBT
MIG 350
0.87
http://www.wel
darcindia.com/
Afzal%20
%20weldarc/zip
1/MIG%20SER
IES%20350.pdf
IGBT
MIG 500
0.87
Average P.f = 0.805
Calculation:
Total output of source
kW = kVA * p.f
kW = 630kVA * 0.8
kW = 504kW
For improved power factor upto 0.95 (Cos 18.195
0
)
Compensated kVAR = kVAR1-kVAR2
= kW tan 1 kW tan 2
= kW [tan1 tan 2]
= 504 [tan 40.536
0
tan 18.195
0
]
= 504 x 0.526
= 265.1 kVAR.
Hence 265.1kVAR capacitor bank is sufficient. So the
customer must be choosing equal or more than 265.1.
The nearly available capacitor bank is 270kVAR.
4. CONCLUSION
The optimal sizing calculation is done with the
knowledge of various parameters like capacity of
substation, power factor of overall plant. Welding
machines & motors are widely used for construction
process of Thermal Power Plant (TPP). With the
knowledge of technical parameters of various
switchgears one can find out the initial & operated (or
improved) power factor or the operated power factor
can also be included as the part of technical
specification of distributed power network of TPP. The
International Journal of Emerging Technologies and Engineering (IJETE)
Volume 1 Issue 5, June 2014, ISSN 2348 8050
138
www.ijete.org
sizing of capacitor bank is purely depending upon the
minimum power factor of the load.
REFERENCES
[1]. Journal on Improvement of the Power
Transmission ofDistribution Feeders by Fixed
Capacitor Banks by AbdellatifHamouda and
KhaledZehar.
[2]. International Journal of Computer Science And
Technology on Optimal Placement with Different
Number of CapacitorBanks for Voltage Profile
Improvement and Loss Reductionbased on Simulated
Annealing by Mohammad Hadimolaeiardakani,
Ehsanrastayesh, Azimkhodadadi.
[3]. Journal on Electrical systems on Optimal Sitting
and Sizing of CapacitorBanks in Distribution
Networks usingHeuristic Algorithms by
A.A.E.Shammah,Ahmed M.Azmy,A. Abou El-Ela.
[4]. International Journal onTechnical and Physical
Problems of EngineeringonWIND FARM
TRANSIENT BEHAVIOROPTIMIZING BY
CAPACITORBANKS SWITCHING by Gh. Ahrabian,
A. RoshanMilani&A. LafziAizad.
[5]. Electrical Review on Design and investigation of a
15-kVAR reactive powercompensation unit for
different load byEngin CETIN, Pamukkale University.
[6]. International Conference on PowerSystem
Technology2006 on TemperatureEffect to Distribution
Feeder LoadProfiles and Losses by C.H. Lin, C. S.
Chen, M. S. Kang, T.T. Ku, J.S. Huang, Z.S. Chiou,
and C.W. Huang.
[7]. IOSR Journal of Electrical and Electronics
Engineering on Analysis for Size of Ultra-Capacitor
Bank to be Installed on 1.5kV System for Energy
Storage during Regenerative Braking DC Drives by
Ms. PoonamSarawgi, Mrs. ShaliniVaishya& Mr. S.K.
Bajpai.
[8]. Electrical installation guide2008Chapter L on
Power factor correction andharmonic filtering by
Schneider Electric.
[9]. A manual on 63PFC POWER FACTOR
CONTROL RELAY BY CELEC ENTERPRISES.
[10]. Leonardo Electronic Journal of Practices and
Technologies on Optimal Placement and Sizing of
Capacitor Banks Using Fuzzy-Ant Approach in
Electrical Distribution Systems by Brahim
GASBAOUI, Abdelkader CHAKER, Abdellah
LAOUFI, AbdessalamABDERRAHMANIand
BoumedineALLAOUA.