Professional Documents
Culture Documents
x+y
1 +
R
100
y
Where
A = Total ESA / day
R = Traffic growth rate which is taken as 4.5% per annum
x = design life in years taken as 5 years
y = number of years before start of design life
=
107 365 100
4.5
1 +
4.5
100
10+1
1 +
4.5
100
1
= 501,512
CESAL= 0.502 MESAs
FINAL YEAR PROJECT 2011/2012
18 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Thence the Cumulative Equivalent Standard Axle Loads applied on the road is 0.502 Million
ESAs
4.2.3 Traffic classification:
From the TRL road note 31, the traffic class is obtained depending on the number of Equivalent
Standard Axles as can be shown in the table 6 below
Table 6 Traffic classification basing on the range of ESAs
(MoWT Road Design Manual, 2010)
The traffic classification of the road is LV6 T2 as the CESALs is 501,512 ESA
4.3 Rainfall Assessment
Annual rainfall estimates and maximum evaporation data obtained from the Meteorological
Department is indicated in appendix II and the maximum evaporation in the hottest month was
found as 180mm and the average annual rainfall over the last five years was found as 1387.4
mm.
4.3.1 Weinert Value
This value is computed from the equation below;
= 12
(MELTC, 2011)
Where E
y
is the evaporation in the hottest month of the year; in mm which
according to the Kituuza Meteorological centre data is found to be 180mm
and
P
a
is the annual precipitation; in mm which is 1387.4 mm
FINAL YEAR PROJECT 2011/2012
19 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
= 12
180
1387.4
= 1.56
Thus the Weinert number is less than 4.
4.4 Laboratory tests
The laboratory results obtained from the testing of samples obtained from the road to ascertain if
the current material is suitable for re-use or modification or has to be removed entirely from the
road and new material imported is shown in the appendix III.
Three samples were obtained and thoroughly tested for the tests indicated in the methodology
and they are all indicated in the appendix III
4.4.1 MDD results:
Chainage 0+010
Figure 3 Proctor curve for chainage 0+010
Max. Dry Density (MDD) = 1,775 Kg/m3
Optimum Moisture Content (OMC) = 13.6 %
1700
1710
1720
1730
1740
1750
1760
1770
1780
9 10 11 12 13 14 15
D
r
y
D
e
n
s
i
t
y
(
K
g
/
m
3
)
Moisture Content %
Proctor Curve
Series1
FINAL YEAR PROJECT 2011/2012
20 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+110
Figure 4 Proctor curve for chainage 0+110
Max. Dry Density (MDD) = 1,704 Kg/m3
Optimum Moisture Content (OMC) = 12.1%
Chainage 0+300:
Max. Dry Density (MDD) = 1,660 Kg/m3
Optimum Moisture Content OMC = 12.3%
1,500
1,520
1,540
1,560
1,580
1,600
1,620
1,640
1,660
1,680
1,700
1,720
9.0 10.0 11.0 12.0 13.0 14.0 15.0
D
r
y
D
e
n
s
i
t
y
(
K
g
/
m
3
)
Moisture Content %
Proctor Curve
Series1
FINAL YEAR PROJECT 2011/2012
21 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Figure 5 Proctor curve for Chainage 0+300
4.4.2 Gradation Results:
Chainage 0+010
Figure 6 Sieve analysis for chainage 0+010
1,560
1,570
1,580
1,590
1,600
1,610
1,620
1,630
1,640
1,650
1,660
1,670
9.0 10.0 11.0 12.0 13.0 14.0 15.0
A
x
i
s
T
i
t
l
e
Axis Title
Proctor Curve
Series1
0.0
20.0
40.0
60.0
80.0
100.0
120.0
0.010 0.100 1.000 10.000
P
e
r
c
e
n
t
a
g
e
p
a
s
s
i
n
g
Diameter of particles (mm)
Sieve analysis graph for chainage 0+010
FINAL YEAR PROJECT 2011/2012
22 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+110
Figure 7 Sieve analysis results for chainage 0+110
Chainage 0+300
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
0.010 0.100 1.000 10.000
P
e
r
c
e
n
t
a
g
e
P
a
s
s
i
n
g
%
Diameter of particles (mm)
Sieve Analysis graph for sample from chainage 0+110
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
0.010 0.100 1.000 10.000
P
a
s
s
i
n
g
%
Diameter (mm)
Sieve analysis graph for chainage 0+300
FINAL YEAR PROJECT 2011/2012
23 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
4.4.3 Plasticity Index results:
Chainage 0+010:
Figure 8 Plasticity Index results for chainage 0+010
RESULTS
Liquid Limit ( LL ) = 48.5%
Plastic Limit ( PL ) = 34.6%
Plasticity Index ( PI=LL-PL ) = 13.9%
44.0
45.0
46.0
47.0
48.0
49.0
50.0
51.0
52.0
53.0
0 10 20 30 40 50
M
o
i
s
t
u
r
e
c
o
n
t
e
n
t
Number of blows
FINAL YEAR PROJECT 2011/2012
24 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+110
Figure 9 Plasticity index results for chainage 0+110
RESULTS
Liquid Limit ( LL ) = 44.3%
Plastic Limit ( PL ) = 30.6%
Plasticity Index ( PI=LL-PL ) = 13.7%
42.5
43.0
43.5
44.0
44.5
45.0
45.5
46.0
0 10 20 30 40 50
M
o
i
s
t
u
r
e
c
o
n
t
e
n
t
Number of blows
FINAL YEAR PROJECT 2011/2012
25 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+300
Figure 10 Plasticity index results for chainage 0+300
RESULTS
Liquid Limit ( LL ) = 33.4%
Plastic Limit ( PL ) = 21.0%
Plasticity Index ( PI=LL-PL ) = 12.4%
4.5 Analysis: Layer thickness Design
Basing on the following results obtained in from the tests carried out above the base following
design parameters were obtained;
The range of the Weinert value is less than 4,
The design cumulative equivalent standard axle loads (CESALs) was obtained as 0.502
MESAs thus traffic class of LV6 T2
The subgrade CBR was obtained in the range of 15-29.
30.0
31.0
32.0
33.0
34.0
35.0
36.0
37.0
38.0
0 10 20 30 40 50
M
o
i
s
t
u
r
e
c
o
n
t
e
n
t
Number of blows
FINAL YEAR PROJECT 2011/2012
26 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
CHAPTER 5.0 CONCLUSIONS AND RECOMMNEDATIONS
5.1 Summary
This chapter has put into consideration the tests carried out and the results obtained the with the
aid of design manuals and specifications, it has given the design suitable for this road of a sand
seal as can be shown below;
5.2 Conclusions:
5.2.1 Inventory of the existing road condition
The general condition of the road was in a very good condition thus in case of carrying out the
sand seal, there will be need of slight reshaping.
5.2.2 Traffic usage of the road:
From the traffic flow analysis the traffic class of the road obtained in the results section is T2 is
Low Volume LV6 hence LV6 T2 as the CESALs is 501,512 ESA
5.2.3 Subgrade characteristics of the existing road
The in-situ CBR values of the subgrade are generally good. If in-situ CBR values obtained from
the DCP tests exceed 10% then the road foundation should be strong enough to carry traffic load
on low volume roads. Hence the fact that the CBR values are in the range of 15-29 then subgrade
is adequate and design Subgrade strength class S5. Below is figure 11 which shows the variation
of CBR for the subgrade and base;
.
Figure 11 CBR variation with the chainage along the road
0
20
40
60
80
100
120
140
0 100 200 300 400 500 600
C
B
R
(
%
)
Chainage (m)
CBR values for DCP test
Subgrade
Base
Linear (Subgrade)
Linear (Base)
FINAL YEAR PROJECT 2011/2012
27 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
The CBR values for the base layer are of concern because, on low volume roads, the minimum
allowable soaked CBR is 40%. The results show that the in-situ CBR values obtained average
approximately 78% which is significantly higher than the minimum required soaked CBR; where
the values are very low such as at chainage 0+010 being 40 there is need for strengthening and
some modification may be necessary to improve the material characteristics.
5.2.4 The design of the appropriate sand seal
New Pavement Structure
Given the above traffic, Weinert number, subgrade and sub-base CBRs and using the design
chart in appendix III for N<4 (TRL, 2007), the desired surfacing structure is obtained using the
Design charts in Table 7 of pavement catalogue (N<4) as below:
Table 7 Proposed New Pavement Structure of the road
Position Thickness CBR
Bituminous surfacing
Base 200 65
Sub-base 120 30
Sub-grade 15-29
Figure 12 Diagramatic representation of the new pavement structure
FINAL YEAR PROJECT 2011/2012
28 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
From the laboratory tests, the material used for the construction of the Base and sub-base gives
desired properties of MDD, plasticity Index and gradation thus there is no need to import
material and in cases of shortage the borrow pits where the material was initially obtained can be
used to obtain more gravel material.
The proposed surfacing is as shown in the table 8 below:
Table 8 Proposed surfacing options
Material Surfacing Binder to be used
Quarry fines from
Kira Town Council
Sand Seal with Quarry fines Bitumen Emulsion K1-60 (80-
100 Pen Base Bitumen)
River Sand Sand Seal Bitumen Emulsion K1-60 (80-
100 Pen Base Bitumen)
New Pavement Structure
Given the above traffic, Weinert number, subgrade and sub-base CBRs and using the design
chart in appendix III for N<4 below, the desired surfacing structure is obtained using the Design
charts in Table 3.3-1 of pavement catalogue (N<4) (TRL, 2007)
Table 9 Thickness and required CBR values of the new pavement strcuture
Position Thickness CBR
Bituminous surfacing
Base 200 65
Sub-base 120 30
Sub-grade 15-29
Drainage
There is currently grass growing in most of the side drains. This will help prevent scouring from
the increased run-off that will result once the sections are surfaced. The grass should be trimmed
so that its growth is controlled. Also, on the judgment of the centre trainers, scour checks should
be constructed on certain steep sections to prevent the erosion that might arise from the increase
in run-off that will result once the sections are surfaced.
FINAL YEAR PROJECT 2011/2012
29 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
REFERENCES
Archondo-Callao, R.S. (1999). Paving of Unpaved Roads. Economically - Justified Paving Cost.
Infrastructure
BEUSCH A, HARTMANN P, PETTS R C, WINKELMANN P, (1997). Low cost road
construction in Indonesia - Labor-Based Road Projects in Manggaria District.
GIUMMARRA G (2001). Road Classifications, Geometric Designs and Maintenance Standards
for Low Volume Roads. Research Report AR354, ARRB Transport Research Ltd,
Vermont South, Victoria.
Guidelines for the Geometric Design of Very Low Volume Local Roads (ADT<400), AASHTO,
USA
NATIONAL INSTITUTE FOR TRANSPORT AND ROAD RESEARCH (1971) Bituminous
surface treatments for newly constructed rural roads. South African Council for Scientific
and Industrial Research, TRH 3, Pretoria, (National Institute for Road Research)
OVERBY, C. 1982. Material and Pavement Design for Sealed Low Traffic Roads in Botswana.
Norwegian Road Research Laboratory.Report no. 1042, Oslo 44 pp.
SATCC, South African Transport And Communications Commission (2003) Guideline: Low
Volume Sealed Roads. Southern African Development Community (SADC).SADC House,
Gaborone, Botswana.
TRL Overseas Road Note 31: A guide to the structural design of bitumen surfaced roads in
tropical and subtropical countries (1993)
TRL, Colin Jones (2004): Improved Measurement of Pavement Strength by Dynamic Cone
Penetrometer
TRL, PROME CONSULTANTS LTD, MELTC Development of training modules, conducting
training and establishment of demonstration sites for low-cost sealing of roads in Uganda
(May, 2010)
FINAL YEAR PROJECT 2011/2012
30 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
APPENDICES
Appendix I: DCP Test Data and Results:
DCP test Data:
Table 10 UK DCP test results for all the chainages (0+010 to 0+500)
UK DCP Test Data Sheet
Project name Design of a Sand Seal for a Low Volume gravel Road; Case study: Kira-Kito Road
Test number 1 2 3
Chainage (km) 10 110 200
Location Carriageway Shoulder Carriageway
Lane number 0 0
Offset (m) 0 0 0
Direction
Zero error (mm) 11 11 11
Test date 17/04/2012 17/04/2012 17/04/2012
Remarks Left hand side Right hand side Centreline
Layers removed 0 0 0
Surface type Unpaved Unpaved Unpaved
Surface moisture Dry Dry Dry
Surface thickness (mm)
Surface condition
Surface strength
coefficient
Base thickness (mm)
Base condition
Blows Depth (mm) Blows Depth
(mm)
Blows Depth
(mm)
FINAL YEAR PROJECT 2011/2012
31 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
0 32 0 25 0 17
1 42 2 37 1 28
2 47 2 42 1 34
2 56 2 46 2 41
2 63 3 52 2 46
3 75 3 55 3 50
3 86 5 65 5 58
3 97 5 76 5 63
3 110 5 90 5 69
3 120 5 105 5 80
3 134 5 110 5 93
3 147 5 135 5 110
3 158 5 150 5 124
3 172 5 163 3 135
3 185 5 175 3 145
3 198 5 186 3 153
3 212 5 199 3 160
3 226 5 215 3 169
3 241 5 243 3 175
3 260 2 264 3 181
3 282 2 278 3 189
2 303 2 290 3 195
2 328 2 300 3 205
2 345 2 310 3 213
2 359 2 320 3 222
2 371 3 334 3 234
2 384 3 343 3 248
2 399 3 350 3 267
2 412 3 356 2 280
2 426 3 360 2 294
FINAL YEAR PROJECT 2011/2012
32 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
2 443 3 364 2 308
2 465 5 370 2 324
1 490 5 373 2 340
1 526 5 377 2 360
1 566 7 380 1 386
1 582 7 382 1 419
1 590 10 389 1 442
2 604 10 397 1 457
2 615 10 406 1 470
2 626 10 424 1 485
2 634 10 443 1 495
2 645 10 465 1 507
2 654 10 487 1 520
2 663 10 520 1 530
2 672 5 540 1 542
2 680 5 565 1 555
2 690 3 583 1 569
2 699 2 595 1 584
2 709 2 607 1 600
2 619 1 615
3 635 1 630
3 655 1 645
2 666 1 660
2 679 1 674
2 689 1 690
2 699 1 704
2 710 1 718
2 721 1 729
2 730 1 742
2 740 1 755
FINAL YEAR PROJECT 2011/2012
33 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
2 750 1 768
2 760 1 783
2 769 1 795
2 779 1 810
UK DCP Test Data Sheet
Project name Design of a Sand Seal for a Low Volume gravel Road; Case study: Kira-Kito Road
Test number 4 5 6
Chainage (km) 300 400 500
Location Carriageway Shoulder Carriageway
Lane number 0 0
Offset (m) 0 0 0
Direction
Zero error (mm) 11 11 11
Test date (dd/mm/yyyy) 17/04/2012 17/04/2012 17/04/2012
Remarks Left hand side Right hand side Centreline
Layers removed 0 0 0
Surface type Unpaved Unpaved Unpaved
Surface moisture Very Dry Dry Moderate
Surface thickness (mm)
Surface condition
Surface strength
coefficient
Base type
Base thickness (mm)
Base condition
Blows Depth (mm) Blows Depth (mm) Blows Depth (mm)
0 15 0 11 0 22
2 26 2 20 2 36
2 34 2 26 2 45
2 42 2 34 2 55
FINAL YEAR PROJECT 2011/2012
34 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
2 51 2 40 2 61
2 58 3 45 2 69
2 67 5 51 2 75
2 72 5 55 2 84
3 80 10 68 2 92
3 89 10 81 2 102
3 96 10 101 2 111
3 105 10 127 2 120
3 113 7 150 2 130
3 121 7 166 2 140
3 130 7 186 2 147
3 140 7 217 2 156
3 150 5 242 2 165
3 158 3 259 2 175
3 167 3 280 2 185
3 176 2 295 2 194
3 186 2 308 2 205
3 197 2 324 2 214
3 211 2 343 2 225
3 223 1 352 2 237
3 245 1 373 2 253
3 260 1 384 2 265
3 272 1 395 2 279
3 286 1 406 2 295
3 302 1 419 2 309
3 319 1 430 2 324
3 337 1 440 2 340
3 358 1 440 2 355
2 375 1 450 2 373
1 402 1 460 2 390
FINAL YEAR PROJECT 2011/2012
35 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
1 445 1 470 2 405
1 465 1 480 2 423
1 480 1 490 2 438
1 495 1 500 2 454
1 509 1 510 2 470
1 523 1 520 1 475
1 538 1 530 1 482
1 550 1 541 1 488
1 564 1 554 1 495
1 576 1 569 1 502
1 590 1 580 1 510
1 603 1 594 1 515
1 615 1 608 1 523
1 627 1 620 1 523
1 639 1 633 1 530
1 652 1 647 1 537
1 665 1 662 2 552
1 675 1 675 2 568
1 689 1 690 2 581
1 702 1 703 2 600
1 715 1 715 2 618
1 725 1 725 2 635
1 725 1 739 2 654
1 740 1 750 2 670
1 755 1 762 2 689
1 769 1 774 2 707
1 785 1 785 2 729
1 800 1 796 2 729
1 815 1 809 2 751
2 774
FINAL YEAR PROJECT 2011/2012
36 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Layer boundary graphs and CBR graphs
Chainage 0+010:
Figure 13 Layer boundaries and CBR variation for chainage 0+010
Chainage 0+110:
Figure 14 Layer boundaries and CBR variation for chainage 0+110
FINAL YEAR PROJECT 2011/2012
37 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+210:
Figure 15 boundaries and CBR variation for chainage 0+210
Chainage 0+300:
Figure 16 boundaries and CBR variation for chainage 0+300
FINAL YEAR PROJECT 2011/2012
38 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Chainage 0+400:
Figure 17 boundaries and CBR variation for chainage 0+400
Chain age 0+500:
Figure 18 boundaries and CBR variation for chainage 0+500
FINAL YEAR PROJECT 2011/2012
39 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Histogram to indicate the Base CBR
Figure 19 Histogram showing the base SBR (%)
FINAL YEAR PROJECT 2011/2012
40 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Appendix II: Kituza Coffee Research Meteorological Station Data
Long Term Mean (LTM) Monthly Evaporation (mm) (PAN TYPE ....A........)
Table 11 Monthly evaporation data for Kituza coffee research station
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Mean 138 122 147 122 120 110 100 105 124 134 122 128
Highest 163 144 169 138 140 129 115 134 154 180 139 175
Lowest 87 101 124 113 107 94 76 78 95 104 111 97
Monthly Maximum Fall of Rainfall (mm)
Table 12 Monthly Maximum fall of rainfall for Kituza Station
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2007 24.0 17.0 29.5 31.0 30.3 45.0 16.5 26.2 55.5 54.0 37.0 30.5
2008 91.0 14.0 38.0 93.0 30.2 20.0 13.8 14.3 21.2 35.0 22.0 6.5
2009 19.0 25.0 16.0 34.0 37.0 12.0 19.0 38.0 32.5 58.0 53.2 31.5
2010 22.5 95.0 60.0 63.0 20.0 22.0 28.5 20.5 62.5 31.0 45.0 40.5
2011 15.0 16.0 35.0 30.4 25.5 7.8 18.0 54.0 29.5 30.6 58.0 68.0
Monthly Rainfall Totals (mm)
Table 13 Montly Rainfall totals of Kituza station
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2007 133.3 64.2 69.5 140.8 106.3 119.0 82.3 81.1 234.0 157.8 151.5 48.0
2008 154.4 47.2 191.9 348.2 103.3 33.3 39.1 43.7 83.4 184.8 82.4 17.3
2009 34.1 73.8 26.0 204.8 157.0 35.0 34.1 124.8 96.8 232.1 232.4 126.2
2010 51.5 273.3 258.5 191.1 104.5 70.8 47.8 48.4 118.1 110.2 111.2 110.2
2011 22.2 24.2 161.9 137.7 90.1 14.8 21.7 135.7 142.8 102.8 289.3 204.3
FINAL YEAR PROJECT 2011/2012
41 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Appendix III Laboratory tests data:
Table 14 Test results from Maximum Dry Density of the soil for chainage 0+010\
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
Project Road: Kira-Kito Road
DATA SHEET FOR MOISTURE - DENSITY RELATIONS OF SOILS
USING 4.54 KG. RAMMER ( OMC & MDD TEST ) As per BS 1377:Part 4
Sample No: 1 Sampling Date: 17 -04-12
Source/Location of Sample: Kira Kito Testing Date: 25 -04-12
Km 0+100 LHS
Sample Description : Red Gravel Material Technician: Iga Dan
Proposed Use: Wearing C
Mass of mould (g): 5,120 Volume (cm
3
): 2,299
Specimen Number/Mould No. 1 2 3 4 5
Mass of mould+base+compacted specimen ( m2
) 9,480 9,640 9,758 9,730 9,680
Mass of mould + base (m1) 5,120 5,120 5,120 5,120 5,120
Mass of compacted specimen(m2-m1) 4,360 4,520 4,638 4,610 4,560
Bulk Density = (m2-m1) x mould factor 1.896 1.966 2.017 2.005 1.983
Moisture content container No
Weight of wet soil + container m1 153.40 154.10 206.00 166.33 132.15 147.11 190.80 128.96 190.42 129.98
FINAL YEAR PROJECT 2011/2012
42 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Weight of dry soil + container m2 143.81 142.24 187.23 150.97 119.96 133.11 169.90 117.00 169.90 117.00
Mass of container m3 30.39 30.99 31.42 30.71 30.74 30.71 30.56 29.00 30.56 29.00
Weight of water (m1-m2) 9.6 11.9 18.8 15.4 12.2 14.0 20.9 12.0 20.5 13.0
Weight of dry sample (m2-m3) 113.4 111.3 155.8 120.3 89.2 102.4 139.3 88.0 139.3 88.0
8.5 10.7 12.0 12.8 13.7 13.7 15.0 13.6 14.7 14.8
Moisture content w (m1-m2)/(m2-m3) x 100 9.6 12.4 13.7 14.3 14.7
Dry density = (100x bulk density)/(100+w) kg/m3 1,731 1,749 1,775 1,754 1,729
FINAL YEAR PROJECT 2011/2012
43 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Table 15 Test results for Particle size analysis test (BS 1377: Part 2) for chainage 0+010
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
PROJECT: Kira-Kito Road
PARTICLE SIZE ANALYSIS (BS 1377:Part 2)
Sample reference :1 Sampling Date: 17
-04-
12
Location Kira Kito Testing Date: 25
-04-
12
Km 0+100 LHS
Sample Description Red Gravel Material
Initial wt before washing : Moisture Content :
Dry wt after washing : Initial Dry Weight 1300
Grading Modulus = 2.02
Diameter Partial Cumulative Cumulative % Passing Grading Limits
Retained Retained Retained
(mm) Mass(g) Mass (g) (%) (%) (%)
50.000 0.00 0.0 0.0 100.0
37.500 0.00 0.0 0.0 100.0
20.000 96.98 97.0 7.5 92.5
10.000 24.85 121.8 9.4 90.6
5.000 59.10 180.9 13.9 86.1
2.360 247.12 428.1 32.9 67.1
1.180 227.07 655.1 50.4 49.6
0.500 286.22 941.3 72.4 27.6
0.425 49.91 991.3 76.3 23.8
0.300 92.04 1083.3 83.3 16.7
0.150 104.59 1187.9 91.4 8.6
0.075 14.82 1202.7 92.5 7.5
Pan 2.49
FINAL YEAR PROJECT 2011/2012
44 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Table 16 Test results for the Moisture-Density Relatios of the soil (BS 1377: Part 4) for chainage 0+210
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
Project Road: Kira-Kito Road
DATA SHEET FOR MOISTURE - DENSITY RELATIONS OF SOILS
USING 4.54 KG. RAMMER ( OMC & MDD TEST ) As per BS 1377: Part4
Sample No:
Sampling Date: 17 -04-12
Source/Location of Sample:
Kira Kito
Km 0+200 LHS
Testing Date: 25 -04-12
Sample Description : Red Gravel Material
Proposed Use: W.C
Mass of mould (g): 5,120 Volume (cm
3
): 2,299
Specimen Number/Mould No. 1 2 3 4 5
Mass of mould+base+compacted specimen ( m2
) 8,950 9,235 9,500 9,404 9,350
Mass of mould + base (m1) 5,120 5,120 5,120 5,120 5,120
Mass of compacted specimen(m2-m1) 3,830 4,115 4,380 4,284 4,230
Bulk Density = (m2-m1) x mould factor 1.666 1.790 1.905 1.863 1.840
Moisture content container No
FINAL YEAR PROJECT 2011/2012
45 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Weight of wet soil + container m1 103.27 115.98 149.51 144.15 134.14 151.57 168.74 128.96 208.60 129.98
Weight of dry soil + container m2 97.02 108.45 138.21 133.46 123.08 138.42 153.22 117.00 186.14 117.00
Mass of container m3 30.39 30.99 31.42 30.71 30.45 30.56 30.56 29.00 30.56 29.00
Weight of water (m1-m2) 6.3 7.5 11.3 10.7 11.1 13.2 15.5 12.0 22.5 13.0
Weight of dry sample (m2-m3) 66.6 77.5 106.8 102.8 92.6 107.9 122.7 88.0 155.6 88.0
9.4 9.7 10.6 10.4 11.9 12.2 12.7 13.6 14.4 14.8
Moisture content w (m1-m2)/(m2-m3) x 100 9.6 10.5 12.1 13.1 14.6
Dry density =(100x bulk density)/(100+w) Kg/m3 1,521 1,620 1,700 1,647 1,606
FINAL YEAR PROJECT 2011/2012
46 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Table 17 Test results for Particle size analysis test (BS 1377: Part 2) for chainage 0+210
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
PROJECT: Kira-Kito Road
PARTICLE SIZE ANALYSIS (BS 1377:Part 2)
Sampling Date: 17
-04-
12
Location Kira Kito Testing Date: 17
-04-
12
Km 0+200 LHS
0 Technician:
Iga
Dan
Sample Description Red Gravel Material
Initial wt before washing : Moisture Content :
Dry wt after washing : Initial Dry Weight 1200
Grading Modulus = 1.57
Diameter Partial Cumulative Cumulative % Passing Grading Limits
Retained Retained Retained
(mm) Mass(g) Mass (g) (%) (%) (%)
50.000 0.00 0.0 0.0 100.0
37.500 0.00 0.0 0.0 100.0
20.000 40.90 40.9 3.4 96.6
10.000 28.71 69.6 5.8 94.2
5.000 31.80 101.4 8.5 91.5
2.360 41.32 142.7 11.9 88.1
1.180 90.53 233.3 19.4 80.6
0.500 327.50 560.8 46.7 53.3
0.425 119.43 680.2 56.7 43.3
0.300 161.70 841.9 70.2 29.8
0.150 195.79 1037.7 86.5 13.5
0.075 28.77 1066.5 88.9 11.1
Pan 2.86
FINAL YEAR PROJECT 2011/2012
47 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Table 18 Test results for the Moisture-Density Relatios of the soil (BS 1377: Part 4) for chainage 0+300
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
Project Road: Kira-Kito Road
DATA SHEET FOR MOISTURE - DENSITY RELATIONS OF SOILS
USING 4.54
KG. RAMMER ( OMC & MDD
TEST )
As per BS 1377: Part4
Sample No: Sampling Date: 17 -04-12
Source/Location of Sample: Kira Kito Testing Date: 25 -04-12
Km 0+300 LHS
Sample Description : Red Gravel Material Technician:
Iga
Dan
Proposed Use: Wearing Course
Mass of mould
(g): 5,120
Volume
(cm
3
): 2,299
Specimen Number/Mould
No. 1 2 3 4 5
Mass of mould+base+compacted specimen ( m2
) 9,030 9,190 9,380 9,400 9,370
Mass of mould + base (m1) 5,120 5,120 5,120 5,120 5,120
Mass of compacted specimen(m2-m1) 3,910 4,070 4,260 4,280 4,250
Bulk Density = (m2-m1) x mould factor 1.701 1.770 1.853 1.862 1.849
Weight of wet soil +
container m1 140.32
115.9
8
208.6
0
129.9
8 161.75 153.30
138.7
4
128.9
6 149.51
144.1
5
Weight of dry soil + container
m2 132.02
109.7
5
192.0
1
120.4
5 147.61 140.49
126.5
2
117.0
0 134.91
129.4
6
Mass of container m3 30.39 30.99 31.42 30.71 30.90 30.52 30.56 27.00 33.56 29.00
Weight of water (m1-m2) 8.3 6.2 16.6 9.5 14.1 12.8 12.2 12.0 14.6 14.7
Weight of dry sample (m2-
m3) 101.6 78.8 160.6 89.7 116.7 110.0 96.0 90.0 101.4 100.5
8.2 7.9 10.3 10.6 12.1 11.6 12.7 13.3 14.4 14.6
Moisture content w (m1-m2)/(m2-m3) x 100 8.0 10.5 11.9 13.0 14.5
Dry density = (100x bulk density)/(100+w) kg/m3 1,574 1,602 1,656 1,647 1,614
FINAL YEAR PROJECT 2011/2012
48 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Table 19 Test results for Particle size analysis test (BS 1377: Part 2) for chainage 0+300
DESIGN OF A SAND SEAL FOR A LOW VOLUME GRAVEL ROAD
PROJECT: Kira-Kito Road
PARTICLE SIZE ANALYSIS (BS 1377:Part 2)
Sampling Date: 17
-04-
12
Location Kira Kito Testing Date: 25
-04-
12
Km 0+300 LHS
#REF! Technician:
Iga
Dan
Sample Description Red Gravel Material
Initial wt before washing : Moisture Content :
Dry wt after washing : Initial Dry Weight 1800
Grading Modulus = 1.98
Diameter Partial Cumulative Cumulative % Passing Grading Limits
Retained Retained Retained
(mm) Mass(g) Mass (g) (%) (%) (%)
50.000 0.00 0.0 0.0 100.0
37.500 50.60 0.0 0.0 100.0
20.000 279.80 50.6 2.8 97.2
10.000 261.28 330.4 18.4 81.6
5.000 237.76 591.7 32.9 67.1
2.360 129.85 829.4 46.1 53.9
1.180 79.85 959.3 53.3 46.7
0.500 212.30 1039.1 57.7 42.3
0.425 80.00 1251.4 69.5 30.5
0.300 79.83 1331.4 74.0 26.0
0.150 71.25 1411.3 78.4 21.6
0.075 10.62 1482.5 82.4 17.6
Pan 1.52
FINAL YEAR PROJECT 2011/2012
49 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Appendix IV: Design Charts
FINAL YEAR PROJECT 2011/2012
50 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
FINAL YEAR PROJECT 2011/2012
51 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
FINAL YEAR PROJECT 2011/2012
52 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
FINAL YEAR PROJECT 2011/2012
53 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
FINAL YEAR PROJECT 2011/2012
54 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
FINAL YEAR PROJECT 2011/2012
55 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Appendix IV: Photographs of the project execution
Figure 20Assembling of the DCP test equipment
Figure 21 Applying blows to the soil to get penetrations
Figure 22 Recording of pentrations
Figure 23 Measuring of the distances from one chainage
to another
Figure 24 The Kira-Kito road condition
FINAL YEAR PROJECT 2011/2012
56 | P a g e
Iga Dan 08/U/481 Bsc. Civil Engineering
Figure 25 Ruler used to measure the penetration
Figure 26 Sampling to obtain samples for laboratory
tests