Construction Status Up to 2-3-2014

General

Site Leveling for the Site. (100%)
Transport Palm trees outside the site (100%)
Constructing the wooden fences for the site (100%)
Prepare site office (100 %)
Prepare the site layout facilities (100%)
Operation for the Dewatering System (100%)


Transformer boxes (2 No)

Install the earthing cable Box (100%)
Back filling the earthing trench (100%)
Pouring Concrete grade 40 for base slab (100 %)
Pouring concrete for Internal & External Walls till +4.2 (100%)
Grinding & Repair for Internal Wall (100%)
Grinding & Repair for External Wall (25%)



Transformer boxes (6 No)

Install the earthing cable Box (100%)
Back filling the earthing trench (100%)
Pouring Concrete grade 40 for base slab (100 %)
Pouring concrete for Internal & External Walls till +4.2 (100%)
Grinding & Repair for Internal Wall (100%)
Grinding & Repair for External Wall (25%)






Electrical & Control Building

Install the earthing cable Box (100%)
Pouring RC base slab (100%)
Pouring concrete for basement Walls & columns (100%)
Pouring Concrete for ground floor slab (100%)
Pouring Columns ground floor columns (100%)
Pouring roof slab from axis 1E to axis 17E (100%)
Water proofing for walls & columns (100%)
Basement Surface finishing from axis 1E to axis 17E (100%)
Formwork for slope screed inside the basement (60%)
Pouring Concrete for Parapet from axis 1E to 1.5m after axis 8E
(100%)
Formwork for Parapet from axis 1.5m after axis 8E to axis 17E
(100%)
Steel fixing for Parapet from axis 1.5m after axis 8E to axis 17E
(50%)
Repair & finishing from axis 1E to axis 9E (100%)
Installation for angles of the drain channel (100%)
Installation of the Frame of the drain pit (100%)
Oil Paint for basement Walls from axis 1E to axis 9E (5%)
Block work Mockup for internal wall (100%)



Pump House

Install the Earthing Cable (100%)
Pouring concrete for RC basement (100%)
Install Sylomer for PG1 & PG2 (100%)
Pouring concrete for RC foundation for pump (100%)
Pouring Concrete for Walls & Columns (100%)
Pouring Concrete for laydown area (100%)
Water proofing for walls & columns (100%)
Backfilling in front of axis J (50%)




Utility Building

Pouring RC isolated footings (100%)
Pouring Concrete for columns & ground beams (100%)
Formwork for Roof slab (30%)


Surge Vessel (For PG1)

Excavation for Surge Vessel basement (100%)
Pouring blinding concrete (100%)
Water proofing for blinding concrete (100%)
Formwork for R.C foundation (70%)
Steel Fixing for R.C foundation (30%)

Surge Vessel (For PG2)

Excavation for Surge Vessel basement (100%)
Pouring blinding concrete (70%)
Water proofing for blinding concrete (100%)
Formwork for R.C foundation (50%)
Steel Fixing for R.C foundation (20%)