Pioneer House Woolpit Road Rattlesden Bury St Edmunds IP30 0RZ UK Tel: +44 (0) 1449 736777 Fax: +44 (0) 1449 737322 enquiries@pioneerpump.co.uk www.pioneerpump.co.uk Powering performance demands Pioneer Pumps The Norwegian contractor Secora SA completed a challenging project on the island of Vry, off the coast of Norway, 130 kilometres north of the Arctic Circle. To accommodate larger fishing vessels and ferries, the harbour needed to be deepened. Normally dredgers would have been used for this task, but the basalt granite floor of the harbour at Srlands meant that the only way is to excavate the additional 3m depth was by drilling and blasting. Although it was possible to drill and blast under water, the simplest solution in this instance was to seal off the harbour entrance and drain the harbour. However, because of the location, the contractors were racing against time to complete the project before winter set in. The Overall Project The total project, at a value of 115 million Norwegian krones, involved deepening Rstnesvgen and Srlandsvgen including the approaches to Srlandsvgen. There was some 5,000 m 3 of loose material and 3,000 m 3 of rock to be excavated from an area of 7,000 m 2 at Rstnesvgen. Works at Srlandsvgen involved 170,000 m 3 of loose material plus 150,000 m 3 of rock in an area of approximately 130,000 m 2 . 1,200,000m 3 in 14 days A priority was to drain the 1.2 million cubic meters of water in just 14 days. The demand was for high performance pumpsets that could cope with the volumes involved, have proven reliability and were able to meet strict environmental conditions. Because the pumps had to be mounted on barges, the number of pumpsets had to be kept to a minimum and be able to run for long periods of time between refuelling. The original consideration was to use six 12" submersible pumps but Pioneer Pump, working through their Norwegian distributor, Intec Pumper, was able to demonstrate that the high performance efficiency of Pioneers vacuum assisted self priming pumps meant that the work could be completed with just two 18" pumpsets. Because of the limited work space and refuelling considerations, this was considered the best solution. On being awarded the contract, Pioneer had just nine weeks to design, build and deliver the custom PP450 high flow pumpsets based on the Pioneer Prime vacuum assisted self-priming pump powered by Caterpillar C9 ACERT Tier III emission compliant diesel engines. They were mounted on skids with an integral fuel tank of 2000 litres, sufficient for 24-hour operation. Successful Operation Once a box dam had sealed the harbour entrance, the pump barge was deployed. With a total dynamic head (TDH) of 18 m, and a static lift of 2.5 meters, the Pioneer pumps maintained a daily output of 3,000 m 3 per hour per pumpset operating at an economical 1800 rpm through discharge piping that ran over the harbour wall to the sea. The Pioneer solution completed the dewatering of the harbour in just 11 days, pumping a total volume of water in excess of 1.4 million cubic meters or 370 million gallons allowing the main contractor to begin excavating 3-days ahead of schedule. Pioneer dewater North Sea arctic harbour in two weeks of continuous pumping www.pioneerpump.co.uk Picture far left Shows the sheer size of the project involved with moving almost one and a half million cubic meters of water in less than two weeks. Picture left Shows the two Caterpillar C9 powered pumpsets located on the custom built barge with 450mm pipe work and non- return valves. Picture left Shows the barge after the pump job with the pumps located at the entrance to the harbour ready to pump out any leakages from the dam. The pumps are managed by a custom design Pioneer Pump control panel with integrated auto-start/stop module in conjunction with GSM remote monitoring. Picture left Shows the Caterpillar earth moving equipment operating in the recently dewatered harbour removing 320,000m 3 of material required to deepen the harbour by an additional 3m. Pioneer Pump Limited, working through their Norwegian distributor, Intec Pumper, was able to demonstrate that the high performance efficiency of Pioneers pumps meant that the work was completed with just two 18" pumpsets in 11 days. PIONEER PUMPS