1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing Evidence The questions are used to evaluate the quality of the deliverable attached to the element. Typical aspects of the deliverable to be evaluated through the questions are: 1. Quality/availability of the inputs needed to build the deliverable 2. Cross-functional approach to answer the deliverables 3. Quality /conformity to a standard if any or to best practices 4. control of the outcome of the deliverable (e.g. action plan)
Input evidence of the answer to the question (e.g.: document reference) here. If an "X" is in the preceding N column (column D) then describe the issue here including root cause in order to identify proper actions . Y* - Put an "X" if complete and is OK or "IP" if in-progress as planned. N - Put an "X" if it is Not OK . N/A - Put an "X" if you have agreed with your customer that this question is Not Applicable. RYG - Put an "R" here if the answer to the question is not acceptable and there is no recovery plan. Put a "Y" here if there are problems with the question but is recoverable with an action plan inplace. Put a "G" if it is on track or satisfactorily complete. When you put an "R" or "Y" you will need to complete the "Actions Required" and subsequent columns.
User Guide # Question 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed The questions are used to evaluate the quality of the deliverable attached to the element. Typical aspects of the deliverable to be evaluated through the questions are: 1. Quality/availability of the inputs needed to build the deliverable 2. Cross-functional approach to answer the deliverables 3. Quality /conformity to a standard if any or to best practices 4. control of the outcome of the deliverable (e.g. action plan)
Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible Actions identified based on the root cause described in the Evidence column when the RYG column is Red or Yellow. These are typical action management milestones . The due date should be aligned with the closure date of the deliverable as planned in the APQP timing. In cases where the due date is not aligned with APQP timing, the RYG status is most likely Red . Date of revision for the provided status and 1.01 Project Inputs # Question Y* N N/A RYG 1 Was a a cross-functional team used to gather project inputs including the following as applicable: Program Management, Quality, Design Engineering, Manufacturing Engineering, Marketing and Sales, Procurement? 2 Are applicable regulatory requirements available? 3 Are customer requirements available including: Project milestones and product delivery date Projected volumes Project lifecycle Product and process assumptions 4 Are all internal data to build product performance expectations available including: Historical problems internal and external Warranty Reliability requirements Quality requirements Technical Requriements 5 Have lesson learned been conducted including: Best Practices Project management Quality issues Product design guidelines Process design guidelines 6 Is the company strategy available including: Business plan Marketing strategy Industrial strategy Technical strategy 7 Have the resulting project/product requirements been referenced/recorded into a repository, including supporting data? Data is made available to be used by the project team? 8 Is there a process to keep formal requirements document up-to-date? 9 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 10 11 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing Green: All questions have a positive answer (Y) and are ongoing normal program development Evidence 1.01 Project Inputs # Question Y* N N/A RYG Evidence 1.01 Project Inputs # Question 1 Was a a cross-functional team used to gather project inputs including the following as applicable: Program Management, Quality, Design Engineering, Manufacturing Engineering, Marketing and Sales, Procurement? 2 Are applicable regulatory requirements available? 3 Are customer requirements available including: Project milestones and product delivery date Projected volumes Project lifecycle Product and process assumptions 4 Are all internal data to build product performance expectations available including: Historical problems internal and external Warranty Reliability requirements Quality requirements Technical Requriements 5 Have lesson learned been conducted including: Best Practices Project management Quality issues Product design guidelines Process design guidelines 6 Is the company strategy available including: Business plan Marketing strategy Industrial strategy Technical strategy 7 Have the resulting project/product requirements been referenced/recorded into a repository, including supporting data? Data is made available to be used by the project team? 8 Is there a process to keep formal requirements document up-to-date? 9 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 10 11 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.01 Project Inputs # Question Open Date Due Date Status % Actual End Date Actions Required Responsible 1.02 Technical Design Requirements # Question Y* N N/A RYG 1 Have all project inputs (lessons learned, strategies,customer needs, product performance) been taken into account when defining the requirements? 2 Has the requirements set been built by a cross functional team involving engineering, sales, manufacturing engineering, procurement, quality and production? 3 Are all requirements traceable (identifier, author, rationale, source, requirement owner, allocation and stakeholder)? 4 Has the requirements set been validated and approved by identified personnel? 5 Are requirements recorded into the program applicable database? 6 Are all design and product verifications planned and their respective evidence managed in a database? 7 Have allocated requirements been understood and accepted by all the recipients? 8 Is there is a robust requirements change management process in place? 9 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 10 11 12 13 14 15 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing Evidence 1.02 Technical Design Requirements # Question 1 Have all project inputs (lessons learned, strategies,customer needs, product performance) been taken into account when defining the requirements? 2 Has the requirements set been built by a cross functional team involving engineering, sales, manufacturing engineering, procurement, quality and production? 3 Are all requirements traceable (identifier, author, rationale, source, requirement owner, allocation and stakeholder)? 4 Has the requirements set been validated and approved by identified personnel? 5 Are requirements recorded into the program applicable database? 6 Are all design and product verifications planned and their respective evidence managed in a database? 7 Have allocated requirements been understood and accepted by all the recipients? 8 Is there is a robust requirements change management process in place? 9 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 10 11 12 13 14 15 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.03 Reliability and Quality Goals # Question Y* N N/A RYG 1 Were the quality and reliability goals created by a cross functional team including members from quality,design engineering, manufacturing engineering, customer support, reliability engineer)? 2 Are there quality goals covering the product lifecycle (concept, design, production and service)? 3 Are reliability goals covering all project aspects (product lifetime, Operational Reliability, Repairs and breakdowns (e.g.:MTBR, MTBUR,MTBF), performance stability, performance forecast)? 4 Are quality and reliability goals covering Customer requirements, Regulatory and internal operations requirements? 5 Are quality and reliability goals consistent with overall company , customer and program objectives? 6 Are quality and reliability goals SMART (Specific, Measurable, Achievable, Reachable yet Challenging and Timebound)? 7 Does each goal have an accountable leader and commitment obtained ? 8 Are metrics and targets effectively communicated and cascaded? 9 Do metrics and targets drive specific action plans towards continuous improvement? 10 Have all potential risks affecting the element been identified? 11 12 13 14 15 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing Evidence 1.03 Reliability and Quality Goals # Question 1 Were the quality and reliability goals created by a cross functional team including members from quality,design engineering, manufacturing engineering, customer support, reliability engineer)? 2 Are there quality goals covering the product lifecycle (concept, design, production and service)? 3 Are reliability goals covering all project aspects (product lifetime, Operational Reliability, Repairs and breakdowns (e.g.:MTBR, MTBUR,MTBF), performance stability, performance forecast)? 4 Are quality and reliability goals covering Customer requirements, Regulatory and internal operations requirements? 5 Are quality and reliability goals consistent with overall company , customer and program objectives? 6 Are quality and reliability goals SMART (Specific, Measurable, Achievable, Reachable yet Challenging and Timebound)? 7 Does each goal have an accountable leader and commitment obtained ? 8 Are metrics and targets effectively communicated and cascaded? 9 Do metrics and targets drive specific action plans towards continuous improvement? 10 Have all potential risks affecting the element been identified? 11 12 13 14 15 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.04 Preliminary Listing of Critical Items (CTIs) and Key Characteristics (KCs) # Question Y* N N/A RYG 1 Has a Cross functional team been set and led by Design engineering reponsible for all considered products. Team includes representatives from all of the key involved domains (Quality, Manufacturing engineering, production, )? 2 Is there a method in place to determine CTI and KC in line with the aplicable international norm 9103? 3 Are necessary inputs identified including: product performance requirements (eg. interchangeability), product risk analysis on similar products, manufacturing requirements, existing data on manufacturing process performance, failures and their resolution at customers and throughout product lifecycle? 4 Can identified CTI/KC be justified? CTI/KC come from experience or are determined using clear methodologies such as Quality Function Deployment Matrices. 5 Is the preliminary listing signed off by all of the team members? Suggested - written evidence of the agreement 6 Has this list been communicated to the activities downstream to continue with the CTI / KC cascade? It is recommended that this list is incorporated into the product specification and process specification. 7 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 8 9 10 11 12 13 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing Evidence 1.04 Preliminary Listing of Critical Items (CTIs) and Key Characteristics (KCs) # Question 1 Has a Cross functional team been set and led by Design engineering reponsible for all considered products. Team includes representatives from all of the key involved domains (Quality, Manufacturing engineering, production, )? 2 Is there a method in place to determine CTI and KC in line with the aplicable international norm 9103? 3 Are necessary inputs identified including: product performance requirements (eg. interchangeability), product risk analysis on similar products, manufacturing requirements, existing data on manufacturing process performance, failures and their resolution at customers and throughout product lifecycle? 4 Can identified CTI/KC be justified? CTI/KC come from experience or are determined using clear methodologies such as Quality Function Deployment Matrices. 5 Is the preliminary listing signed off by all of the team members? Suggested - written evidence of the agreement 6 Has this list been communicated to the activities downstream to continue with the CTI / KC cascade? It is recommended that this list is incorporated into the product specification and process specification. 7 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 8 9 10 11 12 13 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.05 Manufacturer Product Specification # Question Y* N N/A RYG 1 Are all necessary input documents available and released (Design technical requirement documents, Quality and reliability goals, process constraints)? 2 Are all requirements from input documents cascaded into the product specification, traced and recorded? 3 Has the design team verified that product specification requirements are addressing the right level of the system breakdown.(e.g.: do not require a component supplier to meet an Aircraft level requirement or impose an equipement specification 4 Is each requirement validated? Has the means of validating each requirement been defined? In case of no agreement on the requirement with customer impacts are measured and actions described accordingly. 5 Have the proof-reading and review process been successfully completed? (internal by supplier and with customer)? 6 Are CI/KC properly integrated into product specification? 7 Is there consistency with other contractual requirement documents (e.g.: SOW)? 8 Are there any changes foreseen (Change requests...) which could impact product development agreed schedules? Is there a mitigation action plan to guarantee that the agreed schedule is met? 9 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 10 11 12 13 14 15 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Evidence Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing 1.05 Manufacturer Product Specification # Question 1 Are all necessary input documents available and released (Design technical requirement documents, Quality and reliability goals, process constraints)? 2 Are all requirements from input documents cascaded into the product specification, traced and recorded? 3 Has the design team verified that product specification requirements are addressing the right level of the system breakdown.(e.g.: do not require a component supplier to meet an Aircraft level requirement or impose an equipement specification 4 Is each requirement validated? Has the means of validating each requirement been defined? In case of no agreement on the requirement with customer impacts are measured and actions described accordingly. 5 Have the proof-reading and review process been successfully completed? (internal by supplier and with customer)? 6 Are CI/KC properly integrated into product specification? 7 Is there consistency with other contractual requirement documents (e.g.: SOW)? 8 Are there any changes foreseen (Change requests...) which could impact product development agreed schedules? Is there a mitigation action plan to guarantee that the agreed schedule is met? 9 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 10 11 12 13 14 15 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.06 Bill of Material (BOM) # Question Y* N N/A RYG 1 Are the technical/process requirements available? 2 Is the production startegy considered into establishing the preliminary BOM/Product Break down Structure? 3 Have benchmarks been conducted on similar and competitor products? 4 Have cost targets been taken into account to establish the PBS? 5 Have enviromental/regulatory requirements been considered when establishing the preliminary BOM/PBS? 6 Has the Bill Of Material been reviewed with procurement, in order to integrate opportinities from supply chain innovation or risks from it? 7 Has the preliminary Bill Of Material been agreed by all project stakeholders (Engineering, manufacturing engineering, procurement, Production)? 8 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 9 10 11 12 13 14 15 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Evidence Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing 1.06 Bill of Material (BOM) # Question 1 Are the technical/process requirements available? 2 Is the production startegy considered into establishing the preliminary BOM/Product Break down Structure? 3 Have benchmarks been conducted on similar and competitor products? 4 Have cost targets been taken into account to establish the PBS? 5 Have enviromental/regulatory requirements been considered when establishing the preliminary BOM/PBS? 6 Has the Bill Of Material been reviewed with procurement, in order to integrate opportinities from supply chain innovation or risks from it? 7 Has the preliminary Bill Of Material been agreed by all project stakeholders (Engineering, manufacturing engineering, procurement, Production)? 8 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 9 10 11 12 13 14 15 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.07 Preliminary Process Flow Chart # Question Y* N N/A RYG 1 Was the manufacturing process flow chart created by a cross functional team including Manufacturing Engineering, Production and Quality (including others as applicable)? 2 Is enough information available to create the process flow chart? All input data to the manufacturing flow chart are avaiblable such as: preliminary design drawings, preliminary bill of material, process specificatioin/requirements, Preliminary Key Characteristics and Critical Items, material/ components introduction points.. 3 Is the process flow chart applicable to the product in question? At this stage generic process flow can be used . 4 Does the manufacturing flow chart include manufacturing, inspection and test phases for subassemblies and finished product? The manufacturing process flow chart is not limited to final assembly, it combines final assembly and construction of all the subasseblies required to make the product. 5 Does the manufacturing flow chart include subcontracted activities? The manufacturing process flow requirement is cascaded to them. 6 Does the manufacturing flow chart include critical process steps (e.g.: long lead time equipement, processes requiring operators to be certified by external parties)? 7 Does the process flow chart include Preliminary Key Characteristics and their monitoring? 8 Does the process flow chart include means (machine, equipment) & tools used? In so far as they are identified. 9 Is the process flow chart kept up-to-date and configuration managed? 10 Have all potential risks affecting the element been identified? 11 12 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Evidence Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing 1.07 Preliminary Process Flow Chart # Question 1 Was the manufacturing process flow chart created by a cross functional team including Manufacturing Engineering, Production and Quality (including others as applicable)? 2 Is enough information available to create the process flow chart? All input data to the manufacturing flow chart are avaiblable such as: preliminary design drawings, preliminary bill of material, process specificatioin/requirements, Preliminary Key Characteristics and Critical Items, material/ components introduction points.. 3 Is the process flow chart applicable to the product in question? At this stage generic process flow can be used . 4 Does the manufacturing flow chart include manufacturing, inspection and test phases for subassemblies and finished product? The manufacturing process flow chart is not limited to final assembly, it combines final assembly and construction of all the subasseblies required to make the product. 5 Does the manufacturing flow chart include subcontracted activities? The manufacturing process flow requirement is cascaded to them. 6 Does the manufacturing flow chart include critical process steps (e.g.: long lead time equipement, processes requiring operators to be certified by external parties)? 7 Does the process flow chart include Preliminary Key Characteristics and their monitoring? 8 Does the process flow chart include means (machine, equipment) & tools used? In so far as they are identified. 9 Is the process flow chart kept up-to-date and configuration managed? 10 Have all potential risks affecting the element been identified? 11 12 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.08 Statement of Work (SOW) # Question Y* N N/A RYG 1 Is the Statement Of Work specific to the product? Each of the requirements written in the SOW are unique to the product, it is not a generic document which refers to standard requirements. 2 Are all deliverables and inputs from the customer listed, with expected maturity (e.g. draft, final), due date and contributor (internal - external)? 3 Are assumptions, constraints and top the risks identified in the SOW? 4 Is program timing for the product complete and identified in the SOW and complete? 5 Are all applicable standards and procedures identified int the SOW? 6 Are all technical/process requirements referenced int the SOW? The SOW describes the non technical requirements and makes reference to the technical ones (see element 1.02 and 1.05). 7 Are logistics requirements identified in the SOW? 8 Are quality and reliability targets identified in the SOW? 9 Has the Statement Of Work covering all tasks been formally approved by all affected functions and team members and under change control? 10 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 11 12 13 14 15 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Evidence Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing 1.08 Statement of Work (SOW) # Question 1 Is the Statement Of Work specific to the product? Each of the requirements written in the SOW are unique to the product, it is not a generic document which refers to standard requirements. 2 Are all deliverables and inputs from the customer listed, with expected maturity (e.g. draft, final), due date and contributor (internal - external)? 3 Are assumptions, constraints and top the risks identified in the SOW? 4 Is program timing for the product complete and identified in the SOW and complete? 5 Are all applicable standards and procedures identified int the SOW? 6 Are all technical/process requirements referenced int the SOW? The SOW describes the non technical requirements and makes reference to the technical ones (see element 1.02 and 1.05). 7 Are logistics requirements identified in the SOW? 8 Are quality and reliability targets identified in the SOW? 9 Has the Statement Of Work covering all tasks been formally approved by all affected functions and team members and under change control? 10 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 11 12 13 14 15 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.09 Sub-tier Selection and Management Plan # Question Y* N N/A RYG 1 Does the Make/Buy decision process cover the full scope of the Product Breakdown and statement of work? 2 Does the make/buy decision incorprate the production startegy and supply chain capability analysis? 3 Does the supplier selection process involve key functions (quality, engineering, procurement and logistics) and balance the decision between all parties? Supplier performance is a key input to selection process 4 Are all selected suppliers on the Approved Supplier List/Preferred Supplier List and if not specific actions are launched to make sure the supplier will meet customer expectations? 5 Is there a plan (schedule and activies) for supplier sourcing in place and aligned with program timing needs? 6 Are the results of the selection for each item formalized, including action decided during sourcing? 7 Is the list of requirements and objectives to be cascaded to suppliers validated by all involved parties and formalized? 8 Is there a process in place to monitor the supplier performance compared to the cascaded objectives (quality and delivery objectives)? 9 Can the supplier demonstrate that this cascade is complete? 10 Is there a specific process to monitor subtier during the industrailization phase and a dedicated organization/infrastructure driven by program to manage them? 11 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 12 13 14 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Evidence Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing 1.09 Sub-tier Selection and Management Plan # Question 1 Does the Make/Buy decision process cover the full scope of the Product Breakdown and statement of work? 2 Does the make/buy decision incorprate the production startegy and supply chain capability analysis? 3 Does the supplier selection process involve key functions (quality, engineering, procurement and logistics) and balance the decision between all parties? Supplier performance is a key input to selection process 4 Are all selected suppliers on the Approved Supplier List/Preferred Supplier List and if not specific actions are launched to make sure the supplier will meet customer expectations? 5 Is there a plan (schedule and activies) for supplier sourcing in place and aligned with program timing needs? 6 Are the results of the selection for each item formalized, including action decided during sourcing? 7 Is the list of requirements and objectives to be cascaded to suppliers validated by all involved parties and formalized? 8 Is there a process in place to monitor the supplier performance compared to the cascaded objectives (quality and delivery objectives)? 9 Can the supplier demonstrate that this cascade is complete? 10 Is there a specific process to monitor subtier during the industrailization phase and a dedicated organization/infrastructure driven by program to manage them? 11 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 12 13 14 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible 1.10 APQP Timeline # Question Y* N N/A RYG 1 Does a formal APQP planning process exist? 2 Was the timing plan created by a cross functional team including members from all activitities involved (e.g., Quality, Engineering, Project Management, Manufacturing Engineering)? 3 Is there a clear definition for when the product must be delivered? 4 Have key milestones been established, including external and internal program reviews ? 5 Have the necessary APQP Elements been agreed upon by the project team? 6 Is there a start and an end date for each APQP activity? 7 Have all necessary Interdependencies / clashes been identified and agreed upon with related customer / supplier? 8 Have the critical path(s) identified and optimized in the plan from both time and risk perspectives and in line with the APQP time plan? 9 Has the APQP timeline been validated by the Customer,and committed to by all team members, & Suppliers? 10 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 11 12 13 14 15 X 25% N/A IP 50% Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed 75% R 100% Y G Evidence Green: All questions have a positive answer (Y) and are ongoing normal program development Deliverable RYG Rating Red: Some questions have a negative answer and no recovery plan is in place or the plans identified will have an impact in program timing. Support is required. When an item is highlighted Red an assessment on the impact to the WP timing needs to be provided. Yellow: Some questions have a negative answer but a recovery plan is in place which will prevent impact on timing 1.10 APQP Timeline # Question 1 Does a formal APQP planning process exist? 2 Was the timing plan created by a cross functional team including members from all activitities involved (e.g., Quality, Engineering, Project Management, Manufacturing Engineering)? 3 Is there a clear definition for when the product must be delivered? 4 Have key milestones been established, including external and internal program reviews ? 5 Have the necessary APQP Elements been agreed upon by the project team? 6 Is there a start and an end date for each APQP activity? 7 Have all necessary Interdependencies / clashes been identified and agreed upon with related customer / supplier? 8 Have the critical path(s) identified and optimized in the plan from both time and risk perspectives and in line with the APQP time plan? 9 Has the APQP timeline been validated by the Customer,and committed to by all team members, & Suppliers? 10 Has (Have) any potential risk(s) not highlighted by previous question been identified? If no, describe this risks? 11 12 13 14 15 X IP Status (%): 25% - Action Identified 50% - Owner Identified 75% - Action in Progress 100% - Action Closed Open Date Due Date Status % Actual End Date Location: / Site: Reviewed by: Reviewed with: Date : Actions Required Responsible