You are on page 1of 13

Applied Soft Computing 11 (2011) 31863198

Contents lists available at ScienceDirect


Applied Soft Computing
j our nal homepage: www. el sevi er . com/ l ocat e/ asoc
Multiple-colony ant algorithm for parallel assembly line balancing problem
Lale Ozbakir
a
, Adil Baykasoglu
b,
, Beyza Gorkemli
a
, Latife Gorkemli
a
a
Erciyes University, Faculty of Engineering, Department of Industrial Engineering, Kayseri, Turkey
b
University of Gaziantep, Faculty of Engineering, Department of Industrial Engineering, Gaziantep, Turkey
a r t i c l e i n f o
Article history:
Received 16 June 2009
Received in revised form 26 July 2010
Accepted 12 December 2010
Available online 17 December 2010
Keywords:
Line balancing
Parallel assembly lines
Ant colony optimization
Meta-heuristics
a b s t r a c t
Assembly lines are designed as ow oriented production systems which perform operations on stan-
dardized products in a serial manner. Balancing of assembly lines is one of the most important problems
among the other problems of assembly lines like designing and managing. In todays highly competitive
manufacturing environment increasing systemexibility, reducing failure sensitivity, improving system
balance and productivity are crucial. Parallel assembly lines provide some opportunities in improving
these objectives especially when the capacity of production system is insufcient. Unlike the traditional
assembly lines there are a few studies on balancing parallel assembly lines in the present literature.
Parallel assembly line balancing is a NP-hard problem similar to other assembly lines. In this paper, a
novel multiple-colony ant algorithm is developed for balancing bi-objective parallel assembly lines. The
proposed algorithm is also one of the rst attempts in modeling and solving the present problem with
swarm intelligence based meta-heuristics. The proposed approach is extensively tested on the bench-
mark problems and performance of the approach is compared with existing algorithms. It is shown that
the proposed approach is very effective.
2010 Elsevier B.V. All rights reserved.
1. Introduction
Assembly lines consist of serial workstations connected with
conveyor belts or other material handling systems to produce high
quantity standardized products. Operations of the work pieces are
performed by highly specialized operators on these workstations
repeatedly. The main purpose of such systems is to reduce the
costs for mass production of standardized products. However, the
requirements of todays manufacturing systems are changing as
customer needs diversifying. Increasing product variety causes to
take over the concept of assembly to order. This means that the
highly efcient and exible assembly lines must be designed and
balanced in order to produce different products. As discussed by
some authors efciency of assembly lines can be further improved
by considering neighboring lines together while balancing them
[13]. In order to reduce failure sensitivity, increase exibility
in terms of capacity and product variety balancing parallel lines
together is recently attracting the attentionof researchers inindus-
tryandacademia. Traditionallystraight assemblylines arebalanced
separately by assigning operations to workstations considering the
precedence relations and cycle time to minimize the number of
workstations. This is the most frequently studiedassembly line bal-

Corresponding author. Tel.: +90 3423604383; fax: +90 3423604383.


E-mail addresses: baykasoglu@gantep.edu.tr,
baykasoglu@gmail.com (A. Baykasoglu).
ancing problem in the literature (SALBP). In addition to the well
known simple assembly lines, researchers and practitioners devel-
oped several other assembly line designs and balancing techniques
such as mixed and multi model lines, Ushaped lines, assembly
line with parallel workstations or tasks, etc. For an excellent and
detailed explanation and classication of assembly lines with dis-
cussions on existing solution procedures refer to Boysen et al. [4,5].
A survey is also presented by Lusa [6] in terms of parallel assem-
bly lines. This paper is a good survey presenting different types
of parallel assembly lines along with discussions on their main
advantages and disadvantages. Parallel Assembly Line Balancing
Problem (PALBP) has initially been considered by Gokcen et al. [1]
in the literature. Scholl and Boysen [2] presented a detailed deni-
tion of PALBP. They entitled this problem as Multiproduct Parallel
Assembly Line Balancing Problem(MPALBP) anddividedit into two
connected sub-problems; assignment of the products to parallel
lines and balancing the lines simultaneously.
It has been proven in the literature that meta-heuristic
approaches are quite effective in handling NP-hard problems [7].
Ant Colony Optimization (ACO), which is one of the swarm intel-
ligence based meta-heuristic algorithms, is successfully applied to
several other types of assembly line balancing problems in the lit-
erature. Bautista and Pereira [8] applied ACO to time and space
constrained assembly lines. Baykasoglu and Dereli [9] proposed
an algorithm based on ACO for two sided assembly line balancing
problem. McMullen and Tarasewich [10] employed ACOfor solving
the multi-objective assembly line balancing problem. Sabuncuoglu
1568-4946/$ see front matter 2010 Elsevier B.V. All rights reserved.
doi:10.1016/j.asoc.2010.12.021
L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198 3187
et al. [11] developedanACOalgorithmfor U-type assemblyline bal-
ancing problem. Vilarinho and Simaria [12] proposed an ACObased
balancing procedure for mixed-model assembly lines with parallel
workstations. Simaria and Vilarinho [13] developed an ACO algo-
rithm for two sided assembly line balancing problems. Based on
the motivation of the previous successful applications and encour-
aging results of our preliminary studies with ACO for PALBP [14]
we decided to develop a new and improved ACO algorithm which
also extends our previous work. The proposed ACO algorithm is a
multiple colony type and multiple criteria are considered in eval-
uating the performance of the generated solutions. The remainder
of this paper is organized as follows: PALBP is explained in Section
2. The proposed multiple colony ant algorithm and components of
this algorithm is presented in Section 3. In Section 4, the perfor-
mance of the proposed algorithm is tested and compared with the
published results. Finally, the conclusions are given in Section 5.
2. Problem denition
PALBP consists of a number of serial assembly lines arranged in
a parallel form. Different products and/or models can be assigned
to different serial lines by considering a joint cycle time. Although
the concept of parallel assembly lines is known in the industry and
academia [15], there are just a few research papers on their bal-
ancing in the existing literature. The problem is rst introduced by
Gokcen et al. [1]. They proposed several procedures and a mathe-
matical programming model for assembly line balancing problem
which contains parallel lines. The objective of their study was
to minimize the number of stations while balancing more than
one assembly line together. Ozcan et al. [16] developed a multi-
objective tabu search algorithm for solving PALBP with the aim of
maximizing line efciency and minimizing variation of workloads.
Benzer et al. [17] proposeda network model for PALBP. Their model
is basedonthe shortest route formulationwhichwas developedfor
single model assembly line. Kara et al. [18] proposed a fuzzy goal
programming model that can be used for balancing parallel assem-
bly lines. Scholl and Boysen [2] modeled the problem as a binary
linear programming problem and proposed an exact solution pro-
cedure based on the branch and bound algorithm. In a later work,
Scholl and Boysen [3] mentioned that the original objective func-
tion (minimizing number of workstations alone) seems not totally
sufcient for obtaining a competitive line design as it might lead to
inefciencies (i.e. longer lines). They advisedtouse the termwork-
place instead of workstation and dened the split workplace
concept as a place where onlydirectlyopposite workstations canbe
linked to forma workplace where workers can also work in parallel
(back to back). They tried to achieve this by dening the property
of active multi-line balances and adding a second-order termto the
original objective function which might results in a more compact
multi-line layout. However, we should mention here that allow-
ing workers to work in parallel (back to back) may reduce the total
line length but this in turn will necessitate more space between
the parallel lines in most of the applications. This also means more
walking distance for an operator who is working on two lines.
There are two basic sub-problems in PALBP; matching mod-
els/products with lines and balancing adjacent lines together.
Traditionally, each line is balanced separately considering the
precedence relations between the tasks and cycle time in order
to minimize the total number of workstations. But, parallel design
of lines can offer a reduced number of workstations by taking into
account the neighboring lines. If neighboring lines are settled in
such a way that a single worker can operate in both directions then
it is possible to reduce the number of workstations. In other words,
the main purpose of PALBP is to balance multiple serial assembly
lines simultaneously. This is achievedbyassigningtask(s) fromsev-
Station-4
2,1- 2,2
1,1 1,7 - 1,3
2,4
1,5 1,4 - 1,2
Line-2
Line-1
Station-5
Station-6 Station-7
Station-3
1,6
2,6 2,5 - 2,3
Station-1
Station-2
Fig. 1. Schematic representation of a typical parallel assembly line.
eral neighboring lines to a multi-skilled operator. Such a design
with two parallel lines is schematically represented in Fig. 1, work-
ers 1 and 3 can operate on both neighboring lines (in Fig. 1, 1
st
operation of product one and, 1
st
and 2
nd
operations of product two
are assigned to worker one).
Similar to previous studies, the following assumptions are made
in this study for modeling and solving the present PALBP [13]:

Precedence diagrams of each model produced on each line are


known.

Cycles times of each line are known and identical.

The task times of each product are known.

The number of parallel lines is dened as equal to number of


products.

Operators are multi-skilled.

Operator transfer times between two adjacent lines are ignored.


3. Development of multiple-colony ant algorithm for
PALBP
One of the most efcient meta-heuristic algorithms on combi-
natorial optimization problems is known as ACO. This is especially
true if the problem has an inherently network structure [19]. The
ACO meta-heuristic mimics the foraging behavior of natural ant
colonies which share the central information called pheromone
trail. Observation of ants in nature shows that ants are very suc-
cessful in nding shortest path between food sources and their
nest by depositing pheromone and choosing their way by using
the pheromone concentration. The probability of choosing paths is
increased by having strong pheromone concentration [20]. There
are two main parts in ant colony algorithms; solution construction
and pheromone update. In the rst stage ants select one operation
from a candidate list until a complete solution is obtained. In the
second stage ants deposit the pheromone on the way of its com-
pletedsolution. Ant density, ant quantity andant cycle are the
basic ant algorithms which have different pheromone trail update
strategies. In this study ant cycle algorithm which implies that
ants deposit pheromone after they have built a complete tour is
employed. The basic ant cycle steps are as follows [21]:
Initialize parameters and pheromone trails
Until the termination criteria is satised
For each ant in the colony
Build a new solution according to the pheromone trail and heuristic information
Update the pheromone trail
The main idea behind the multiple-colony ant algorithm is due
to ACOs suitable structure for parallelization. In the present study,
each colony is located on different processors and during search
process they exchange information within predetermined periods.
Thus the main purpose of the multiple-colony ant algorithms is to
search different regions of search space by the colonies cooperat-
ing to nd good solutions by information exchange. In developing
the present multiple-colony ant algorithm we motivated from the
Udomsakdigool and Kachitvichyanukuls [22] study. They devel-
oped a multiple-colony ant algorithm which consists of multiple
3188 L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198
Fig. 2. Schematic representation of multiple-colony ant system.
colonies within a single processor for solving the job shop schedul-
ing problem [22].
As it is portrayedinFig. 2multiple ant colonies are designedas to
have different characteristics to explore the different regions in the
search space. Different heuristics are assigned to these colonies in
order to achieve a more diversied search. In general execution of
the multiple-colony ACOis initialized by assigning ants and heuris-
tics to sub-colonies. Each ant of a sub-colony construct a complete
solution by using heuristic information and pheromone trail as
explained in Section 3.1. After all ants in a sub-colony complete
their tour, pheromone amounts in the local pheromone matrix
is updated. This step is repeated for all sub-colonies and all ants
are ranked according to the tness values. After all sub-colonies
complete their tours, global pheromone matrix is updated by a
number of best ants. Global pheromone matrix provides the inter-
action among sub-colonies which explore the different regions of
the search space. In the present research, three sub-colonies are
denedandthree different priority heuristics (Maximumtotal num-
ber of successor task, Maximum total time of successor tasks, Longest
processing time) are assigned to these sub-colonies.
3.1. Solution construction
In each step of the proposed algorithm, ant determines the new
task-workstation assignment by using a candidate list strategy.
Candidate list consists of tasks in which immediate predecessors
have already been assigned and the remaining time of current sta-
tion is sufcient for processing the available tasks. Ant applies a
probabilistic task selection strategy until all tasks are assigned to
a workstation to generate a complete solution for PALBP. Bautista
et al. [23] presented three different trail information usage policies
in modeling of assembly lines with ACO; task to task, task to
workstation and task to position. In the present study the trail
is deposited between a task and its assigned workstation. While
depositing pheromone between task and workstation pair, earliest
and latest possible stations for each task are determined by equa-
tions 1 and 2 as advised by Saltzman and Baybars [24] in order to
avoid extra computation.
E
(p,j)
=

(p,j)
+

qP

(p,j)

(p,q)

(1)
L
(p,j)
=

K +1

(p,j)
+

qF

(p,j)

(p,q)

(2)
where pP, j J
p
(P: set of products; J
p
: set of tasks for product P).
E
(p,j)
, L
(p,j)
are the earliest and latest stations for task (p,j), respec-
tively.

K denotes the maximum number of stations.
(p,j)
=t
(p,j)
/c.
t
(p,j)
is the task time of task j of product p and c is the cycle time of
the lines. P

(p,j)
denotes the set of direct and indirect predecessors
of task (p,j). F

(p,j)
denotes the set of direct and indirect successors
of task (p,j).
Under these explanations, assignment of all tasks to worksta-
tions is performed by using the following steps:
L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198 3189
START
Initilization
Assign ants to
sub-colonies
Compute quality
function
Calculate heuristic
values
Update candidate
task list
Select task-station
pair
Generate candidate
task list
Open new station
Initialize ant
t(p,j)=Station
remaining time
Is iteration
limit reached?
All sub-colonies
completed?
Are all ants
completed tour?
Are all
tasks assigned?
Is candidate
task list empty?
Assign heuristics to
sub-colonies
Update global
best solution
Update global
pheremone matrix
Update local
pheremone matrix
Return the best
solution
END
J1: Exploitation
J2: Biased
Exploitation
Calculate earliest & latest station
for each task
Assign Rand(0.1, 0.5) pheromone
amount to each possible
task-station pair
PALBP Data
Yes
Yes
Yes
Yes
No
No
No
No
No
Yes
Fig. 3. Flowchart of the multiple-colony ant algorithm.
3190 L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198
Repeat (until all tasks have been assigned)
Open a new station
Determine candidate task list by considering neighboring assembly lines.
Candidate task list contains available tasks.
Available task: immediate predecessors must be assigned and its task time must
be less than or equal to remaining station time.
Select task-workstation pair by using the ant cycle algorithm
Assign the selected task to the station
Until all tasks have been assigned
3.1.1. Task selection strategy
The task selection from the set of candidate tasks depends on
the pheromone trail between the task and previously assigned sta-
tions and the information provided by the heuristic for each task
in the candidate list. Similar to Vilarinho and Simaria [12] equa-
tions 3-4 are employed as task selection strategy. Eq. (3) is used for
exploitation and equation 4 is used to enable biased exploration.
J
1
= arg max
(p,j) A
k
(p,j)
{[
(p,j),z
]

[
(p,j)
]

} if r 0.5 (3)
J
2
= p((p, i), (p, J
2
)) =
[
(p.J
2
),z
]

[
(p,J
2
)
]

(p,j) A
k
(p,i)
[
(p.j),z
]

[
(p,j)
]

if r > 0.5 (4)


where; r is a random number between 0 and 1. z is the set of
workstations which task (p,j) can be assigned.
(p,j)
is the heuris-
tic information of task (p,j). A
n
(p,i)
indicates candidate task list for
ant n after selection of task (p,i). Ants use both local and global
pheromone information during the task selection in order to pro-
vide interaction among sub-colonies by making use of Eq. (5). w
in Eq. (5) denotes the effect of global pheromone information with
respect to local pheromone information [22].

k
(p,j),z
(t) = (1 w)
k
local(p,j),z
(t) +w
k
global(p,j),z
(t) w[0, 1] (5)
Heuristic information is obtained from the priority rules
assigned to eachsub-colony. Instead of assigning static priority val-
ues to tasks, a rank based structure is implemented. The priority
values of tasks are updated when a task is assigned and candidate
task list is updated. The priority values of tasks incandidate list vary
between1for the least desirable task andthe number of tasks inthe
candidate list for the most desirable task. This structure increased
the importance of heuristic information when the priority values
are close to each other.
The operation of the proposed algorithm is depicted in a
owchart in Fig. 3. In the owchart rst ants and heuristics are
assigned to sub-colonies. After obtaining problem data and cycle
time information, earliest and latest assignable workstations are
determined for each task. Random(0.1, 0.5) amount of pheromone
is assigned between tasks and workstations. Ants in each sub-
colony complete their tours based on their own heuristic rule and
pheromone amount. Local pheromone matrices are updated. After
all sub-colony tours are completed global pheromone matrix and
the best solution is updated.
Assigning tasks to workstations: Open a workstation, generate
assignable tasks list from the tasks whose predecessors were
assigned and their processing times t into remaining worksta-
tion time. If there is a task with a processing time equal to the
remaining station time, assign this task. Otherwise, select the
task to be assigned based on the pheromone information in the
global/local pheromone matrices and heuristic knowledge (Eqs.
(3)(5)). Update the assignable tasks list and heuristic values.
By this way an ant completes its tour and its tness (see Section
3.2) is computed, local pheromone matrix is updated. After all ants
in all sub-colonies nish their tours global pheromone matrix is
updated.
Table 1
Parameter setting.
Parameters level
Number of ants 30, 9
Number of iterations 100, 250
Q 5
Constant pheromone amount between iterations 1
Importance of pheromone intensity () 1
Importance of heuristic information () 5
Pheromone evaporation coefcient 0.1
w (Importance of global pheromone) 0.7
R number of iteration for restart 25
3.2. Fitness function
In this study, two different performance criteria are taken into
consideration, minimizing the idle time of workstations and
maximizing the line efciency. The function f
1
(Eq. (6)) repre-
sents the line efciency. The function f
2
(Eq. (7)) as proposed by
Leu et al. [25] is adopted for minimizing the idle time. This function
aims tominimizethenumber of workstations andstationidletimes
in order to obtain a balanced solution. These objective functions
are combined into a single objective function by using Minimum
Deviation Method (MDM). MDM tries to nd the best compromise
solution by minimizing the sum of the fractional deviations of the
objective functions [26]. In relation to MDM approach the tness
of a solution is computed by using Eq. (8). f
max
1
and f
min
2
in Eq. (8)
are target values. The target value of line efciency is set to 100 and
the target value of total idle time is set to 0. f
0
1
and f
0
2
are the least
desired values. The least desired value of f
0
1
and f
0
2
are obtained
from the initial ant tour.
f
1
=
(

m
s=1
(ST
s
)) 100
(m c)
(6)
f
2
=

m
s=1
((c ST
s
)
2
)
m
+

m
s=1
(c ST
s
)
m
(7)
Minimize f =
f
max
1
f
1
f
max
1
f
0
1
+
f
min
2
f
2
f
min
2
f
0
2
(8)
3.3. Pheromone trail update
In general, initialization of the pheromone on every arc is set
to a constant initial value. In this study a random number in the
interval (0.1, 0.5) is determined as the initial pheromone value
on each path in order to enforce the diversication at the begin-
ning of the algorithm. After the ants in a sub-colony complete their
tours, the pheromone amount on the explored paths is updated.
The pheromone amount that ant k deposit to arc ((p,i),z) is dened
by Eq. (9). f
k
denotes the tness function value of ant k and Q
is the predened constant for pheromone update. The amount of
pheromone deposition after iteration is computed by Eqs. (10) and
(11), respectively. is the pheromone evaporation coefcient and
Q is the predened constant for pheromone update.

k
(p,i),z
(t, t +n) =
Q
f
k
(9)

(p,i),z
(t, t +n) =
m

k=1

k
(p,i),z
(t, t +n) (10)

(p,i),z
(t +n) = (1 )
(p,i),z
(t) +
(p,i),z
(t, t +n) (11)
After completion of iteration, constant amount of pheromone is
depositedtoall arcs toprevent the premature convergence. Manual
solution of a small sized sample problem is shown in Appendix A
L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198 3191
Table 2
Comparative results for PALBP.
Test problems # Tasks (Line1-Line2) Cycle time Theoretical min Independent balance GOK MOD ABS TS mc-ACO
Merten 7 9 6 4+3 7 7 7 7
6 11 5 3+3 5 5 5 5
13 5 3+2 5 5 5 5
17 4 2+2 4 4 4 4
Jaeschke 9 9 8 5+4 8 8 8 8
8 11 7 4+4 7 7 7 7
13 6 3+3 6 6 6 6
15 5 3+3 5 5 5 5
17 4 3+2 4 4 4 4
Jackson 11 8 11 7+6 13 13 13 13
10 10 9 5+5 9 9 9 9
13 7 4+4 7 7 7 7
15 6 4+3 6 6 6 6
19 5 3+3 5 5 5 5
Roszieg 25 14 18 10+10 18 20 18 18
24 16 16 8+8 16 16 16 16
17 15 8+8 15 16 15 15
22 12 6+6 12 12 12 12
30 9 5+5 9 9 9 9
Sawyer 30 25 26 14+13 26 28 26 26
28 27 24 13+12 25 26 24 24
30 22 12+11 22 23 22 22
36 18 10+9 18 19 18 18
41 16 8+8 16 16 16 16
54 12 7+6 12 12 12 12
Kilbridge 45 57 20 10+10 20 20 20 20 20
43 79 14 7+7 14 15 14 14 14
92 12 6+6 12 12 12 12 12
110 10 6+5 10 10 10 10 10
138 8 4+4 8 8 8 8 8
184 6 3+3 6 6 6 6 6
Hahn 53 2004 14 8+7 14 17 14 14 14
51 2338 12 7+7 12 15 12 12 12
2806 10 6+5 10 11 10 10 10
3507 8 5+4 8 9 8 8 8
4676 6 4+3 6 7 6 6 6
Tonge 70 160 43 23+22 45 46 44 44
66 168 41 22+22 43 45 42 42
207 34 18+17 34 35 34 34
234 30 16+15 30 32 30 30
270 26 14+13 26 27 26 26
293 24 13+12 24 25 24 24
Wee-Mag 75 28 105 63+60 123 123 123 123 123
71 29 102 63+60 123 123 123 123 123
31 95 62+60 121 122 121 121 121
33 89 61+59 119 120 119 119 119
34 87 61+59 119 120 119 119 119
41 72 59+57 116 116 116 116 116
42 70 55+53 107 108 107 107 107
43 69 50+48 98 98 98 98 98
49 60 32+31 62 63 62 63 62
54 55 31+30 60 61 60 60 60
Arcus1 83 3786 39 21+19 40 42 40 40 40
79 3985 37 20+19 38 40 37 38 38
4206 35 19+17 36 38 36 36 36
4454 33 18+17 34 35 34 34 34
4732 31 17+16 32 33 32 32 32
5853 25 14+12 26 26 25 26 25
6842 22 12+11 22 23 22 22 22
7571 20 11+10 20 21 20 20 20
8412 18 10+9 18 19 18 18 18
10816 14 8+7 14 14 14 14 14
Lutz2 89 11 86 49+46 90 97 88 88
85 12 79 44+41 82 88 79 80
13 73 40+38 75 81 73 73
14 68 37+35 71 79 69 68
15 63 34+32 64 68 63 63
16 59 31+30 60 66 59 59
17 56 29+28 56 60 56 56
19 50 26+25 50 53 50 50
3192 L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198
Table 2 (Continued)
Test problems # Tasks (Line1-Line2) Cycle time Theoretical min Independent balance GOK MOD ABS TS mc-ACO
20 47 25+24 48 51 47 48
Lutz3 89 75 43 23+22 45 46 44 44 44
85 79 41 22+22 43 45 41 42 41
83 39 21+21 40 43 39 40 39
87 37 20+19 38 40 37 38 38
92 35 19+18 36 37 35 36 35
Mukherje 94 176 47 25+24 48 49 48 48 47
90 183 45 24+23 46 47 45 46 45
192 43 23+21 44 44 43 44 43
201 41 22+20 42 44 41 42 41
211 39 21+19 40 40 39 40 39
222 37 20+18 38 40 38 38 37
234 35 19+18 36 37 36 36 35
248 33 18+17 34 35 33 34 33
263 31 17+16 32 33 32 32 32
281 29 16+15 30 31 30 30 29
301 27 15+14 28 29 28 28 28
324 26 14+13 26 27 26 26 26
351 24 13+12 24 25 24 24 24
Arcus2 111 5785 52 27+28 55 54 53 54 53
107 6016 50 26+27 53 52 51 51 51
6267 48 25+26 50 50 49 50 49
6540 46 24+25 48 50 47 48 47
6837 44 23+24 46 48 45 45 45
7162 42 22+22 44 44 43 43 43
in order to provide a more detailed explanation of the proposed
algorithm.
4. Computational study
In order to analyze the efciency of the multi-colony ACO
algorithm, test problems from the literature are solved. The data
set for the test problems can be obtained from www.assembly-
line-balancing.de. The performance of the proposed algorithm is
comparedwiththe heuristic of Gokcenet al. [1] (GOKfor short); the
mathematical programming model of Scholl and Boysen [3] which
was solved by XPressMP solver (MOD for short) and the branch
and bound based exact solution procedure of Scholl and Boysen
[2,3] (ABS for short) and tabu search algorithm of Ozcan et al. [16]
(TS for short). For GOK, MOD and ABS, 95 common cycle times are
taken into consideration. For TS, since Ozcan et al. [16] reported the
results for 55 cycle times, the comparisons are achieved on these
cycle times. The proposed multiple-colony ACOalgorithmis imple-
mented by C# programming language and runs are performed on a
Intel Core 2 Duo 2.4GHz computer with 2 GB RAM. The parameter
values of the proposed algorithm for solving the test problems are
shown in Table 1.
Number of ants in ACO directly affects the performance of the
algorithm. Dorigo and Sttzle [27] presented that the number of
ants must be greater than 1. Dorigo et al. [21] suggested that the
performance of the algorithmgetting better as number of ants close
to number of cities in travelling salesmen problem. In this study,
test problems are divided into two groups as small and large sized
problems. Small sized problems are the test problems which have
13136 tasks. Large sized problems have 146217 tasks. Usually,
the number of ants is suggested to be less than 10 for large sized
problems due to the excessive computation time [11]. Since we
have 3 sub-colonies in this study, the number of ants is determined
as 9 and 30 for large and small sized problems, respectively.
For parameters , , Q and w; different combinations of the
={1,2,5}, ={1,2,5}, Q={1,5,10} w = {0.5, 0.7} are evaluated.
Different combinations of these parameters yield better results
for different problems. But the differences are not distinctive, so
similar parameters setting is used for all problems as shown in
Table 1.
Adirect comparison of the results is given in Table 2 and Table 3.
In Gokcen et al. [1] and Ozcan et al. [16] computation times for their
procedures GOK and TS are not given. Since they only present the
number of workstations, wecomparedthesolutions withrespect to
number of workstations. In Table 2, results are presented in terms
on minimum number of workstations obtained from each algo-
rithm (GOK, MOD, ABS, TS and multiple-colony ACO: mc-ACO).
Scholl and Boysen [2,3] were run their algorithms on a personal
computer withanIntel PentiumIVprocessor of 3.0GHz clock speed
and 1.5 GByte of RAM. For each MPALBP-instance a time limit of
500s was set for their procedures MODand ABS. Therefore making
a one-to-one comparison in terms of computational time perfor-
mance is not possible. However, we can say that our algorithm
generates high quality solutions in very short CPU times, much
smaller than 500 cpu sec. In Table 3 we presented details of the
computational time performance and results for 10 independent
runs of the proposed algorithm.
Theresults of mc-ACOarecomparedwithGOK, MOD, ABSandTS
by using statistical tests. In this study paired-t test is used as a para-
metric test in order to compare the means of two samples. The test
computes the differences between values of the two samples for
each case and test whether the average differs from 0. The paired-
t test procedure is used to test the hypothesis of no difference
between two samples. The results of the paired-t test are presented
inTable4. InTable4therst columnrepresents thecomparedpairs.
Mean difference column displays the average difference between
mc-ACO and the compared results. N and df columns represent the
sample size anddegree of freedom, respectively. The Sig (p) column
displays the probability of obtaining a t statistics whose absolute
value is equal to or greater than the obtained t statistics. Since the
signicance value for pair mc-ACO-GOK is less than 0.05 (=0.05)
we canconclude that there is a signicant difference betweenthese
pairs. The negative sign of average difference between mc-ACO-
GOK means that mc-ACO consists of less number of workstations
than GOK. Similar conclusions are repeated for mc-ACO-MOD and
mc-ACO-TS pairs. The differences between these pairs are also sig-
nicant. And the negative sign of mean difference values denotes
L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198 3193
Table 3
Detailed results of multiple-colony ACO.
Test problems Cycle time CPU time (seconds) Fitness function value Number of stations
Average Average Min Max
Merten 9 0.001 2.040 7/10
11 0.002 2.000 5/10
13 0.002 2.063 5/10
17 0.001 2.067 4/10
Jaeschke 9 0.002 2.034 8/10
11 0.001 2.000 7/10
13 0.002 2.110 6/10
15 0.002 2.088 5/10
17 0.002 0.000 4/10
Jackson 8 0.004 2.012 13/10
10 0.049 1.528 9/10
13 0.002 2.000 7/10
15 0.002 2.026 6/10
19 0.004 2.048 5/10
Roszieg 14 0.027 2.000 18/10
16 0.020 2.076 16/10
17 0.509 1.672 15/10
22 0.016 2.057 12/10
30 0.011 2.047 9/10
Sawyer 25 12.943 0.919 26/3 27/7
27 78.478 0.881 24/5 25/5
30 0.152 2.010 22/10
36 0.217 1.364 18/10
41 0.031 2.149 16/10
54 0.022 2.034 12/10
Kilbridge 57 0.084 2.125 20/10
79 0.055 2.024 14/10
92 0.047 2.095 12/10
110 0.038 2.034 10/10
138 0.038 2.054 8/10
184 0.025 2.094 6/10
Hahn 2004 0.067 2.066 14/10
2338 0.064 2.049 12/10
2806 0.038 2.074 10/10
3507 0.039 2.166 8/10
4676 0.031 2.033 6/10
Tonge 160 21.047 1.140 44/10
168 22.655 1.094 42/10
207 10.470 1.687 34/10
234 0.297 2.058 30/10
270 0.213 2.075 26/10
293 0.202 2.063 24/10
Wee-Mag 28 1.806 2.001 123/10
29 1.783 2.002 123/10
31 6.458 2.002 121/10
33 1.720 2.001 119/10
34 1.686 2.000 119/10
41 1.689 2.000 116/10
42 1.664 2.001 107/10
43 1.497 2.001 98/10
49 1.603 2.016 62/10
54 13.636 2.002 60/10
Arcus1 3786 1.053 1.959 40/10
3985 4.622 1.999 38/10
4206 0.264 2.018 36/10
4454 0.394 2.035 34/10
4732 0.203 2.069 32/10
5853 212.449 0.634 25/4 26/6
6842 0.142 2.065 22/10
7571 0.114 2.064 20/10
8412 0.109 2.150 18/10
10816 0.081 2.096 14/10
Lutz2 11 335.672 0.618 88/4 89/6
12 208.594 0.548 80/2 81/8
13 243.544 0.425 73/6 74/4
14 272.620 0.499 68/6 69/4
15 205.817 0.364 63/7 64/3
16 123.772 0.374 59/5 60/5
17 2.939 0.961 56/10
3194 L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198
Table 3 (Continued)
Test problems Cycle time CPU time (seconds) Fitness function value Number of stations
Average Average Min Max
19 6.239 0.561 50/10
20 1.117 2.087 48/10
Lutz3 75 0.516 1.045 44/10
79 230.516 0.771 41/4 42/6
83 105.656 0.672 39/3 40/7
87 0.458 1.022 38/10
92 124.953 0.437 35/2 36/8
Mukherje 176 0.484 1.000 47/10
183 158.534 0.580 45/10
192 42.752 0.546 43/10
201 227.448 0.416 41/10
211 331.078 0.401 39/8 40/2
222 2.617 0.863 37/10
234 55.513 0.334 35/10
248 210.097 0.258 33/10
263 0.298 1.109 32/10
281 152.75 0.262 29/2 30/8
301 0.247 1.129 28/10
324 0.228 1.048 26/10
351 0.200 1.129 24/10
Arcus2 5785 26.603 0.868 53/10
6016 200.231 0.658 51/10
6267 126.925 0.733 49/10
6540 20.858 0.894 47/10
6837 13.681 0.934 45/10
7162 0.602 1.059 43/10
Table 4
Paired-t test results of comparisons.
Pair Mean difference N df Sig.(p)
mc-ACO-GOK 0.38947 95 94 9.80641E08
mc-ACO-MOD 1.58947 95 94 2.02711E11
mc-ACO-ABS 0.01053 95 94 0.740803
mc-ACO-TS 0.30909 55 54 8.65235E06
that mc-ACO generates better results than MOD and TS. Since the
signicance value for pair mc-ACO-ABS is greater than 0.05, the
difference between this pair is not statistically signicant. But the
negative sign of average difference denotes that mc-ACOgenerates
better values than ABS. ABS was proposed as an exact solution pro-
cedure byScholl andBoysen[2,3]. The proposedalgorithmis able to
ndthe same solutions withABS for all of the smaller size test prob-
lems. For larger size problems ABS generated better solutions for
four problems andACOgeneratedbetter solutions for ve problems
(however the difference between themis very small, i.e. 1 worksta-
tion for all cases, moreover ACO seems better for relatively larger
problems). A similar comparison is performed on TS and mc-ACO.
Because these two solution approaches are meta-heuristic search
algorithms. mc-ACOalgorithmgenerates better results for 17 of 55
test problems than TS. The results of remainder test problems are
the same.
Table 5 presents the summary of the results for all compared
algorithms. These results denote the average deviationratios (ADR)
which are calculated by using equation 12. For each test case, the
Table 5
Summary of results.
Algorithms #Test cases Average deviation
ratio (Opt/LB)
GOK 95 0.013888
MOD 95 0.049722
ABS 95 0.005734
TS 55 0.011373
mc-ACO 95 0.005333
ratio of deviation from optimum or lower bound is calculated and
average of all test cases is reported.
ADR :

#testcases
i=1
(WS
i
Opt
i
)/Opt
i
#testcases
(12)
where: WS
i
represents the number of workstation found by the
algorithmfor test casei, Opt
i
denotes theoptimumnumber of work-
stations. If the optimumis not provenfor this test case, lower bound
value is taken. These optimum and lower bound values were pre-
sented by Scholl and Boysen [2,3]. As it can be seen from Table 5,
mc-ACOalgorithmgenerates the minimumaverage deviationratio.
Based on the computational results we can safely conclude that
the proposedmc-ACOalgorithmis a very promising meta-heuristic
approach for solving the multi product PALBP.
5. Conclusion
In this paper, an ACO is proposed for balancing multi product
parallel assembly lines. The proposed ACO algorithm is a multi-
ple colony type and multiple criteria (minimizing the idle time
of workstations and maximizing the line efciency) are consid-
ered in evaluating the performance of the generated solutions.
The proposed ACO algorithm is also one of the rst meta-heuristic
approaches for solving the present problem which is known as a
NP-hard problem. The proposed algorithm is also compared with
four other existing approaches form the literature. After statisti-
cal analyses it is found out that the proposed algorithm is very
competitive and eligible solution approach for solving the present
problem. It is able to generate high quality solutions in very short
CPU times.
Acknowledgements
Prof. Dr. Adil Baykasoglu is grateful to Turkish Academy of Sci-
ences (TBA) for supporting his scientic studies.
L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198 3195
1,1
1,2
1,3
1,5
1,4
5
4
3
1
3
2,1
2,2
2,3
1
5
3
Fig. A1. Precedence diagrams and task times of the sample problem.
Appendix A.
A.1. Sample problem
A sample problem is used to present how the proposed algo-
rithm works. Precedence diagrams and task times of the sample
problem for two parallel lines are illustrated in Fig. A1. Cycle time
for assembly lines is set to 12.
A.2. Solution
Parameter setting for the sample problemis shown in Table A1.
A.2.1. Initial solution generation

Determine the earliest and latest possible stations for each task
by using equations 1 and 2. For task 1,1 earliest station is 1, latest
station is 2. And for the other tasks, earliest station is 1, latest
station is 3.

Assign Rand [0.1, 0.5] pheromone amount to each task station


pair for the initialization of arcs. Table A2 shows the local and
global pheromone matrices.

Generate solutions for each colony. Tables A3A5 show the solu-
tionstrings andtness functions of solutions whichare generated
by ants for each colony.

Using the initial solutions, determine f


0
1
and f
0
2
by using Eqs. (6)
and (7), respectively. f
0
1
= 69.44444, f
0
2
= 8.32141.
Table A1
Parameter setting for the sample problem.
Parameters level
Number of ants 6
Number of iterations 50
Q 5
Constant pheromone amount between iterations 1
Importance of pheromone intensity () 1
Importance of heuristic information () 5
Pheromone evaporation coefcient 0.1
w (Importance of global pheromone) 0.7
R number of iteration for restart 25

Update the local bests and the global best, and pheromone
amount of the arcs. The pheromone amount on the arcs is given
in Table A6.
A.2.2. New solution generation
Assignment of the rst task (for the rst ant of the rst colony):

Generate candidate task list: {1,1-2,1}.

Calculate the heuristic values: Heuristic information of task 1,1


and 2,1 is 2 and 1, respectively.

Select a task for assignment.

Generate a random number (0,1) r. (r =0.36).

Determine the task selection strategy using r: Exploitation strat-


egy is determined.

Calculate the
k
(1,1),1
(t) by using Eq. (5).

k
(1,1),1
(t) = (1 0.7) 8.8 +0.7 8.7 = 8.7

k
(2,1),1
(t) = (1 0.7) 8.5 +0.7 8.5 = 8.5

Since 8.7 is maximum, select task 1,1 for the assignment.


After the assignment of all tasks, obtained solution strings of
ants are given in Tables A7A9.
Pheromone trail update (for arc 1,1-1 of the rst local
pheromone matrix):

Calculations are given below using Eqs. (9)(11).

k
(1,1),1
(t, t +n) =
5
2

k
(1,1),1
(t, t +n) = 7.4

(1,1),1
(t +n) = (1 0.1)8.8 +7.4 = 15.3

Control the thresholdof pheromone amount: Since 0.5<15.3, con-


tinue.

Add the constant pheromone amount: 15.3+1=16.3.


After updating all the arcs, obtained pheromone matrices are
given in Table A10.
Behaviors of the ants are depicted in Fig. A2.
A.2.3. Final solution
After the termination criterion is satised, the best obtained
solution is given in Table A11 and shown Fig. A3.
Table A2
Local and global pheromone matrices.
Colony Local pheromonematrix(colony1) Local pheromonematrix(colony2) Local pheromonematrix(colony3) Global pheromone matrix
Station/task 1 2 3 1 2 3 1 2 3 1 2 3
1,1 0.5 0.5 0.3 0.3 0.2 0.5 0.4 0.1
1,2 0.4 0.1 0.1 0.5 0.2 0.4 0.4 0.5 0.3 0.2 0.2 0.5
1,3 0.5 0.4 0.5 0.1 0.1 0.2 0.5 0.5 0.4 0.3 0.1 0.4
1,4 0.3 0.5 0.2 0.2 0.1 0.3 0.5 0.3 0.3 0.2 0.5 0.3
1,5 0.1 0.3 0.4 0.1 0.4 0.4 0.2 0.1 0.2 0.2 0.3 0.5
2,1 0.2 0.4 0.2 0.3 0.2 0.5 0.3 0.4 0.3 0.1 0.5 0.5
2,2 0.3 0.2 0.2 0.5 0.2 0.1 0.2 0.1 0.5 0.1 0.3 0.2
2,3 0.5 0.1 0.1 0.2 0.3 0.4 0.3 0.3 0.1 0.2 0.5 0.1
3196 L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198
Table A3
Solution strings of colony 1.
Ant # Colony 1 solution strings Fitness function
1 1,1-1 2,1-1 2,3-1 1,2-1 1,3-1 1,5-2 1,4-2 2,2-3 2.0
2 1,1-1 2,1-1 2,2-1 1,3-1 1,2-2 1,4-2 2,3-2 1,5-3 2.07272
Table A4
Solution strings of colony 2.
Ant # Colony 2 solution strings Fitness function
1 2,1-1 2,3-1 1,1-1 1,3-1 1,2-1 1,4-2 2,2-2 1,5-3 2.08029
2 1,1-1 1,3-1 1,2-1 2,1-1 1,5-1 1,4-2 2,2-2 2,3-3 2.08029
Table A5
Solution strings of colony 3.
Ant # Colony 3 solution strings Fitness function
1 1,1-1 1,2-1 1,4-1 1,5-2 2,1-2 2,2-2 2,3-2 1,3-3 2.20382
2 1,1-1 1,2-1 1,4-1 1,5-2 2,1-2 2,2-2 2,3-2 1,3-3 2.20382
Table A6
Local and global pheromone matrices.
Colony Local pheromonematrix(colony1) Local pheromonematrix(colony2) Local pheromonematrix(colony3) Global pheromone matrix
Station/task 1 2 3 1 2 3 1 2 3 1 2 3
1,1 8.8 1.5 8.4 1.5 7.9 1.5 - 8.7 1.5
1,2 6.3 3.5 1.5 1.5 1.5 1.5 8.1 1.5 1.5 6.1 3.5 1.5
1,3 8.8 1.5 1.5 8.3 1.5 1.5 1.5 1.5 8.1 8.6 1.5 1.5
1,4 1.5 8.8 1.5 1.5 8.3 1.5 8.2 1.5 1.5 1.5 8.8 1.5
1,5 1.5 6.2 3.7 5.8 1.5 3.7 1.5 7.8 1.5 1.5 6.2 3.8
2,1 8.5 1.5 1.5 8.4 1.5 1.5 1.5 8.1 1.5 8.5 1.5 1.5
2,2 3.6 1.5 6.1 1.5 8.3 1.5 1.5 7.8 1.5 3.5 1.5 6.1
2,3 6.4 3.5 1.5 3.5 1.5 6.1 1.5 8.0 1.5 6.1 3.8 1.5
Table A7
Solution strings of colony 1.
Ant # Colony 1 solution strings Fitness function
1 1,1-1 2,1-1 1,2-1 1,3-1 2,3-1 1,4-2 1,5-2 2,2-3 2.0
2 1,1-1 1,2-1 1,4-1 2,1-2 1,5-2 1,3-2 2,2-2 2,3-3 2.08029
Table A8
Solution strings of colony 2.
Ant # Colony 2 solution strings Fitness function
1 1,1-1 1,2-1 1,4-1 2,1-2 2,2-2 1,5-2 2,3-2 1,3-3 2.20382
2 1,1-1 1,2-1 1,4-1 2,1-2 2,2-2 2,3-2 1,5-2 1,3-3 2.20382
Table A9
Solution strings of colony 3.
Ant # Colony 3 solution strings Fitness function
1 1,1-1 1,2-1 1,4-1 1,5-2 1,3-2 2,1-2 2,2-2 2,3-3 2.08029
2 1,1-1 1,2-1 1,4-1 1,5-2 2,1-2 2,2-2 2,3-2 1,3-3 2.20382
Table A10
Local and global pheromone matrices.
Colony Local pheromonematrix(colony1) Local pheromonematrix(colony2) Local pheromonematrix(colony3) Global pheromone matrix
Station/task 1 2 3 1 2 3 1 2 3 1 2 3
1,1 16.3 2.3 15.5 2.3 15.2 2.3 16.2 2.3
1,2 14.1 4.1 2.3 15.7 2.3 2.3 15.4 2.3 2.3 13.9 4.2 2.3
1,3 13.9 4.7 2.3 10.8 2.3 6.8 2.3 7.1 10.6 13.8 4.7 2.3
1,4 4.7 13.9 2.3 6.8 10.8 2.3 15.5 2.3 2.3 4.7 13.9 2.3
1,5 2.3 14.0 4.3 8.7 6.8 4.3 2.3 15.1 2.3 2.3 14.0 4.4
2,1 13.7 4.7 2.3 11.0 6.8 2.3 2.3 15.4 2.3 13.6 4.7 2.3
2,2 4.3 4.7 11.5 2.3 15.4 2.3 2.3 15.1 2.3 4.1 4.7 11.5
2,3 11.8 4.1 4.7 4.2 6.8 8.9 2.3 10.5 7.1 11.5 4.4 4.7
Table A11
The best solution after 50 iteration.
Solution string Fitness function
1,1-1 2,1-1 2,3-1 1,2-1 1,3-1 1,5-2 1,4-2 2,2-3 2.0
L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198 3197
Fig. A2. Behavior of the ants.
2,1-2,3
1,1-1,2-1,3
2,2
1,5-1,4
Station-3
Station-1
Station-2
Line-1
Line-2
Fig. A3. Assembly line arrangement for the best solution.
References
[1] H. Gokcen, K. Agpak, R. Benzer, Balancing of parallel assembly lines, Interna-
tional Journal of Production Economics 103 (2006) 600609.
[2] A. Scholl, N. Boysen, The multiproduct parallel assembly lines balancing prob-
lem: model and optimization procedure, Working and Discussion Paper Series
School of Economics andBusiness AdministrationFriedrich-Schiller-University
Jena, ISSN 1864-3108, 2008.
[3] A. Scholl, N. Boysen, Designing parallel assembly lines with split workplaces:
Model and optimization procedure, International Journal of Production Eco-
nomics 119 (2009) 90100.
[4] N. Boysen, M. Fliedner, A. Scholl, A classication of assembly line balancing
problems, European Journal of Operational Research 183 (2007) 674693.
[5] N. Boysen, M. Fliedner, A. Scholl, Assembly line balancing: which model to use
when? International Journal of Production Economics 111 (2008) 509528.
[6] A. Lusa, A survey of the literature on the multiple or parallel assembly lines
balancing problem, European Journal of Industrial Engineering 2 (2008) 5072.
[7] A. Baykasoglu, Multi-rule multi-objective simulated annealing algorithm for
straight and U type assembly line balancing problems, Journal of Intelligent
Manufacturing 17 (2006) 217232.
[8] J. Bautista, J. Pereira, Ant algorithms for a time and space constrained assembly
line balancing problem, European Journal of Operational Research 177 (2007)
20162032.
[9] A. Baykasoglu, T. Dereli, Two-sided assembly line balancing using ant-colony
based heuristic, International Journal of Advanced Manufacturing Technology
36 (2008) 582588.
[10] P.R. McMullen, P. Tarasewichz, Multi-objective assembly line balancing via a
modied ant colony optimization technique, International Journal of Produc-
tion Research 44 (2006) 2742.
[11] I. Sabuncuoglu, E. Erel, A. Alp, Ant colony optimization for the single model
U-type assembly line balancing problem, International Journal of Production
Economics 20 (2) (2009) 287300.
[12] P.M. Vilarinho, A.S. Simaria, ANTBAL: an ant colony optimization algo-
rithm for balancing mixed-model assembly lines with parallel work-
stations, International Journal of Production Research 44 (2006) 291
303.
[13] A.S. Simaria, P.M. Vilarinho, 2-ANTBAL: an ant colony optimization algorithm
for balancing two-sided assembly lines, Computers and Industrial Engineering
56 (2009) 489506.
[14] A. Baykasoglu, L. Ozbakir, L. Gorkemli, B. Gorkemli, Balancing parallel assembly
lines via ant colony optimization CIE39, in: International Conference on Com-
puters and Industrial Engineering, University of Technology of Troyes, France,
July 68, 2009.
[15] G.A. Suer, Designing parallel assembly lines, Computers and Industrial Engi-
neering 35 (1998) 467470.
[16] U. Ozcan, H. Cercioglu, H. Gokcen, B. Toklu, A tabu search algorithm for the
parallel assembly line balancing problem, Gazi University Journal of Science 22
(4) (2009) 313323.
[17] R. Benzer, H. Gokcen, T. Cetinyokus, H. Cercioglu, A network model
for parallel line balancing Problem, Mathematical Problems in
Engineering 2007: Article ID 10106, Vol. 2007, doi:10.1155/2007/
10106.
[18] Y. Kara, H. Gokcen, Y. Atasagun, Balancing parallel assembly lines with precise
and fuzzy goals, International Journal of Production Research 48 (6) (2010)
16851703.
[19] A. Baykasoglu, T. Dereli, I. Sabuncu, An ant colony based algorithm for
solving budget constrained and unconstrained dynamic facility layout prob-
lems, Omega: International Journal of Management Science 34 (2006) 385
396.
[20] M. Dorigo, V. Maniezzo, A. Colorni, Positive feedback as a search strategy, Tech-
nical Report N.91-016 Politecnico di Milano, 1991.
[21] M. Dorigo, V. Maniezzo, A. Colorni, The ant system: optimization by a colony of
cooperating agents, IEEE Transactions on Systems, Man and Cybernetics-Part
B 26 (1996) 2941.
3198 L. Ozbakir et al. / Applied Soft Computing 11 (2011) 31863198
[22] A. Udomsakdigool, V. Kachitvichyanukul, Multiple colony ant algorithm for
job-shop scheduling problem, International Journal of Production Research 46
(2008) 41554175.
[23] J. Bautista, J. Pereira, Ant algorithms for assembly line balancing, Lecture Notes
in Computer Science 2463 (2002) 6575.
[24] M.J. Saltzman, I. Baybars, A two-process implicit enumeration algorithm for
simple assembly line balancing problem, European Journal of Operational
Research 32 (1987) 118129.
[25] Y.Y. Leu, L.A. Matheson, L.P. Rees, Assembly line balancing using genetic
algorithms with heuristic generated initial populations and multiple criteria,
Decision Sciences 15 (1994) 581 606.
[26] M.T. Tabucanon, Multiple Criteria Based Decision Making in Industry, Elsevier,
New York, 1988.
[27] M. Dorigo, T. Sttzle, The ant colony optimization metaheuristic: algorithms,
applications, and advances, Technical Report, IRIDIA/2000-32, University Libre
de Bruxelles, Belgium, 2000.

You might also like