MMC GAMUDA JOINT VENTURE

METHOD STATEMENT
FOR

TRIAL LOADING FOR ROB 8


REF. NO: DTP/MMCG (BM)/N5/S18/MS/BR/0105

ELECTRIFIED DOUBLE TRACK PROJECT


IPOH TO PADANG BESAR
Document Review Status
CODE 1: APPROVED (Work May Proceed)
CODE 2: APPROVED WITH COMMENT (Work May Proceed
Subject To Incorporation of Comments Indicated)
CODE 3: RESUBMIT (Physical Work Cannot Proceed)

Infra
Rev

Date

Description

06/07/12

1ST ISSUE

Reviewed By

Approved

Prepared By

Reviewed /
Verified By

Supervising
Engineer

Safety

QAQC

Phang Yuen
Seng

Poh Chia
Ching

Devendran

Shaiful
Izzuan

JV (Infra)

JV (Infra)

RE (HSSI)

Section Head

Sheng
Kheng Lian
Sr. QA/QC
Manager

MMC - GAMUDA Joint Venture


1 of 5
REF. NO: DTP-MMCG(BM)/N5/S18/MS/BR/0105

TRT

Zamzuri Ab
Rahim

Sr. TRT Eng

TABLE OF CONTENTS

1.0

INTRODUCTION

2.0

REFERENCES

3.0

MATERIAL

4.0

PLANT AND MACHINERY

5.0

MANPOWER

6.0

PROCEDURE FOR TRIAL LOADING

7.0

SAFETY, HEALTH AND ENVIRONMENTAL REQUIREMENTS

8.0

QUALITY ASSURANCE

9.0

APPENDICES

MMC - GAMUDA Joint Venture


2 of 5
REF. NO: DTP-MMCG(BM)/N5/S18/MS/BR/0105

1.0 INTRODUCTION
When the beams for mid span of ROB 8 were delivered to site, cracks were noticed on 3 of
the beams. The cracks were patched up using Sika 215 non-shrink grout and were
launched. During subsequent inspection, cracks were noticed not only on the said 3 beams
but also on another 6 beams. The cracks were all in the order of 0.1 0.15 mm and can be
categorized as hair line cracks but however, as a pre-cautionary measure to rule out that the
cracks are structural in nature, it is proposed to carry out a trial loading of the above
mentioned span.
2.0 REFERENCES
The following approved method statements shall form part of reference documents:-

Nil

3.0 MATERIAL
The materials proposed to be used for this work, but not limited as listed below:a.
b.
c.

2 Part thioxotropic epoxy adhesive Sikadur -31 CF Normal (Product data sheet
enclosed as appendix C)
Very Low Viscoscity Injection Resin Silkadur-52 LVMY (Product data sheet enclosed
as appendix D)
Injection packer

4.0 PLANT AND MACHINERY


The proposed plant, machinery and equipment to be used for demolition and removal works
are as follow:No.
1
2

Plant and machinery


Skylift
Scaffolding

Drill

Pump

Truck with Crusher-run

Job Function
For inspection of the beam
To provide platform for patching and for
inspection
To drill hole for injection grouting of the
crack
To pump low viscosity epoxy crack injection
resin to the crack
To provide loading for the trial loading

5.0 MANPOWER
Work force that will be mobilized for demolition and removal works is:No. Type of Manpower
1

Site engineer / Site


supervisors

2
3

Grout Injection Specialist


Truck Drivers

Job Function
Planning, coordinating and supervision the demolition
and lifting operation.
For traffic management
To carry out grout injection works
To drive truck onto the bridge

MMC - GAMUDA Joint Venture


3 of 5
REF. NO: DTP-MMCG(BM)/N5/S18/MS/BR/0105

6.0 PROCEDURE FOR TRIAL LOADING


6.1 General
The trial load sequence is generally as follow:
i.
ii.
iii.
iv.
v.
vi.

Repair all the cracks using grout injection method.


Wait for 24 hours curing period.
Load the bridge.
Inspect whether cracks reappear on the beams (every 3 hours for 24
hours).
Monitor daily until traffic diversion.
Thereafter monitor weekly for 2 months.

6.2 Detail Procedure


6.2.1 Methodology for repairing cracks
i.
ii.

Method statement for crack repair shall be as per manufacturers


recommended method for grout injection stipulated in Sikadur 52 LVMY
data sheet (enclosed as appendix D) and approved by the Engineer.
During the course of repair works, all beams to be thoroughly checked and
any cracks found to be patched up.

6.2.2 Curing Period


i.

Wait for 24 hours.

6.2.3 Load the bridge for 24 hours


i.
ii.

Drive the trucks onto the bridge deck as per appendix E.


Maintain and inspect for 24 hours.

6.2.4 Inspection
i.
ii.

Inspect all the repair area as well as the other area of all the beams every 3
hours.
If any cracks are found, record down the crack length, width and location.

6.2.5 Monitoring
i.
ii.

Monitor daily until traffic diversion.


Monitor for 2 months on a weekly basis.

SAFETY, HEALTH AND ENVIRONMENTAL REQUIREMENTS

MMC - GAMUDA Joint Venture


4 of 5
REF. NO: DTP-MMCG(BM)/N5/S18/MS/BR/0105

7.2 Hazards and Risk


The specific hazards, risk and associated control measures of the work described
in the document are detailed in the Job Risk Assessment (appendix B).
7.3 Potential Environment Impacts and Control Measures
No potential environmental Impact
7.4 Reference Document
i.
ii.
iii.
8

EDTP Project Safety and Health Plan


DTP-MMCG(HQ)-SHP-OP-001
EDTP Project Emergency Response Plan
DTP-MMCG(HQ)-ERP-OP-001
EDTP Environmental Management Plan (EMP)

QUALITY ASSURANCE

Not relevant
9

APPENDICES

a) Appendix A
i.

Comments from reviewers.

b) Appendix B
i.

Job Risk Assessment

c) Appendix C
i.

Data sheet Sikadur 31 CF - Normal

d) Appendix D
i.

Data sheet Sikadur 52

e) Appendix E
i.

Load distribution layout for trial loading

MMC - GAMUDA Joint Venture


5 of 5
REF. NO: DTP-MMCG(BM)/N5/S18/MS/BR/0105