THE INDUSTRIAL POLLUTION PREVENTION TECHNOLOGY INSTITUTE

PROPOSAL
2012
1. PROGRAM TITLE :
IMPLEMENTING

ENERGY

CONSERVATION

SCHEME

ON

INDUSTRIES

THROUGH BUILDING CAPACITY AND TRANSFER TECHNOLOGY


2. IMPLEMENTING INSTITUTION
THE INDUSTRIAL POLLUTION PREVENTION TECHNOLOGY INSTITUTE
(Balai Besar Teknologi Pencegahan Pencemaran Industri)
(Under Ministry of Industry)
Jl. Ki Mangunsarkoro No. 6, Semarang, Central Java
Phone (024) 831 6315, Fax (024) 8414811
e-mail : BBTPPI_smg@yahoo.com
3. PROJECT DURATION : 10 MONTHS
4. PROJECT DIGEST DESCRIPTION :
a. Industrial sectors consume the largest part of energy than commercial building,
household and transportion.
b. Their energy cost component is about 20% of total production cost.
c. The surpassing of oil price push the industry to more conserve energy
d. Indonesia energy elasticity (ratio between energy consumption growth rate to
economic growth rate) is still high, at 1.84. Therefore, there are potential opportunity
to save energy by implementing energy conservation scheme
e. More efficient the industry in consuming energy will more competitive in world
market

5. Problem to be solved
External Factor Condition
a. Higher production cost due to higher energy price tend to weaken competitiveness
b. CO2 reduction road map by MOI
c. Stabilizing concentration of green house gases (GHG) to the safe level due to
Indonesia commitment to Framework Climate Change Convention.
d. PP. 70/2009 : Government Regulation on Energy Conservation.
The problem faced by Industry to develop ENERGY CONSERVATION are :
a. Lack of competent of Engineers to implement Energy Conservation scheme.
b. Lack of Education for Employees.
c. Lack of Finance / Fund
d. Most equipment are old and obsolete
e. Lack of Measurement Equipment
f. Insufficiency of infrastructures : databases, standards and manuals
6. ACTION PLAN
A. Capacity building of government officer especially MOI
Capacity building consists of :
-

Training or study of Energy conservation to be implemented by industries


This training will be conducted and held in Korea, in hope that learning directly
from the origin source will be more effective and efficient.
The Study content :

Energy conservation effort in steam generation and distribution system

Energy conservation effort in electricity

Energy conservation effort in machinery operation


a). Survey on existing energy conservation
b). Audit energy
c). Recommendation

Aid of monitoring equipments for energy conservation


The monitoring equipments were used to conduct audit energy as preliminary step
to energy conservation.

B. Technical Assistance to Industry in Conservation technology


Target : Industries especially Korea exports oriented industries and Korea owners
industries.
7. GOAL OF THE PROGRAM
a). To increase the competitiveness of industries, especially Korea export oriented
industries and Korea owner industries.
b). To support CO2 reduction road map by MOI, and Indonesias commitment to
Framework Climate Change Convention on GHG reduction.

TIME SCHEDULE
IMPLEMENTING ENERGY CONSERVATION SCHEMES ON INDUSTRIES

Year of 2013
No

Activity

Preparation
Introduction and preliminary approach

to korea exports oriented industries

and Korea owners industries


Pilot plants selection
Training and study of

5
6

Assistance

on

10

11

12

Energy

conservation to be implemented by
industries
Technical

Month
6
7

Energy

conservation scheme implementation


Compose and set up final report