Tests Time Estimate

Sr. E. Tech.
Plumbing:
Sanitary Pumps (8) 2 2
Domestic Water Heaters and recirculation pumps 2 2
Mechanical
Chilled Water and Hot Water Building Entrance 3 3
Med Temp HW to Hot Water Heat Exchangers HX-1, 2 2 2
Heating Hot Water Pumps and Controls, P-1, 2 2 2
Steam System 2 2
Dehumidification Units DU-1-1, DU-2-1 and DU-A-1 8 8
Air Handling Units (AHU 1-1, 1-2, 2-1, 2-2, 2-3, A-1) 24 24
Zone Constant Volume and Variable Volume Terminals (11 VAV and 13 Constant Volume) 12 12
Zone Humidifiers (H1-1, 1-2, 1-3, 2-1 ,2-2 ,2-3 ,2-4 ,2-5 ,2-6 ,2-7) 10 10
Fans (GX2-1, TX2-1, EF 2-1, TXA-1) 1.5 1.5
Miscellaneous Terminal Equipment (unit heaters, radiation, etc. - 15 units) 5 5
Digital Building Automation System Front End 8 8
Contingency 8 8
Subtotal 89.5 89.5
Misc. and TAB Validation 12 12
Total 101.5 101.5
Page 1
Commissioning
MAN-HOUR ESTIMATING FORM
Proposal : UVA - Special Collections Library Date : 3/20/2001
Dept : All Estimated by : TMS
DEPT. MAN-HOURS BY EMPLOYEE CLASSIFICATION
WORK ACTIVITY SENIOR SENIOR SENIOR TECH. TOTAL Trips Total Days Nights
PM ENGR 1 ENGR 2 Techn. DES. DRAFTS. CLERK on site Lodging
Initial meeting (Kickoff, and review comments) 10 10 1 1
Prepare Draft Commissioning Plan 16
Review Contract Documents (100%CD's) 16
Prepare Commissioning Specifications 16
Attend Meeting to review commissioning plan 10 10 2 2
Answer Commissioning Related Questions 2 2
Attend early construction mtg to review commissioning plan 4 4 1 1
Review submittal data 24 24
Visit project site at selected times (2 progress trips) 16 16 32 2 1
Review equipment start-up checklists 6 6
Review BAS system test plans 6 6
Prepare Final FPT's 16 16 32
attend BAS demonstration and direct FPT 90 90 180 24 24
Review BAS system trend logs 12 12
Attend BAS system opposite season test 16 16 32
Review opposite season trend logs 12 12
Prepare final commissioning report 12 12
Attend selected operator training sessions 8 8 16 2 2
Spot Check TAB 16 16 32 4 2
Warranty Visit 12 8 20 2 2
Electrical Engineer Site Visit 16 16 1 2
TOTAL MANHOURS 336 170 458 39 37
RATE $130.00 $117.50 $117.50 $110.00 $127.03
SALARY COST $39,480 $18,700 $58180
242318014.xls.ms_office 8/27/2014 2:50 AM page 2 of 3
Commissioning
EXPENSE SUMMARY
1 TRAVEL - Mileage 39 TRIPS@ 40 MILES PER TRIP =1560 mi at .31 =$484
TRAVEL - Air 39 TRIPS@ Dollars Per Trip
TRAVEL - Rental Car 37 Days@ Dollars per day
2 LODGING Nights@ 150 Dollars per nite
3 MEALS 37 Days@ 10 Dollars per day =$370
4 TELEPHONE $200
5 REPRODUCTION - XEROX $75
6 REPRODUCTION - PRINTS
7 POSTAGE $100
8
9 MISCELLANEOUS $50
10 subcontractor
Expense Total $1,279
Labor Total $58,180
TOTAL FEE $59,459
242318014.xls.ms_office 8/27/2014 2:50 AM page 3 of 3