You are on page 1of 616

I.

II.

LAYOUT OF THE BUILDING

sq.m.

25.00

15.00

10.00

CARPENTRY WORKS
A. Formworks
1. Using Lumber (incl.stripping,formoil application & nail ext.)

a. Columns/Pedestal
i.Spiral
sq.m.
275.00
250.00
230.00
ii.Tied
sq.m.
250.00
240.00
225.00
b. Footing Tie Beams & Pile Caps
sq.m.
200.00
180.00
160.00
c. Floor Beams
sq.m.
240.00
220.00
200.00
d. Floor Slab
sq.m.
235.00
210.00
185.00
e. Floor Beams (Above 4.00m high)
sq.m.
250.00
240.00
230.00
f. Floor Slab (Above 4.00m high)
sq.m.
245.00
235.00
200.00
g. Roof Beams
sq.m.
255.00
240.00
230.00
h. Gutter w/ parapet
sq.m.
260.00
250.00
240.00
i. Roof Deck (if coverage is not the same as floorsq.m.
slabs below)
245.00
225.00
200.00
j. Shearwalls
sq.m.
250.00
235.00
210.00
k. Stair & Bleacher
sq.m.
275.00
270.00
260.00
l. Dentils
sq.m.
265.00
250.00
240.00
m. Parapet
sq.m.
250.00
240.00
210.00
n. Waffles
sq.m.
275.00
260.00
250.00
o. Stair on Fill
lm.
110.00
105.00
85.00
p. Lintel Beams & Stiff. Columns
sq.m.
210.00
205.00
200.00
q. Pavement
lm.
75.00
60.00
50.00
r. Slab on Fill
lm.
60.00
55.00
45.00
s. When forms used are scrap wood & lumber
plus 15.00 plus 15.00plus 15.00
2. Using Steel Forms

Installation
Small Sc. Big Scale

Stripping

165.00
160.00
155.00
160.00
155.00
185.00
180.00
165.00
180.00
160.00
160.00

80.00
80.00
75.00
80.00
80.00
85.00
85.00
80.00
85.00
80.00
80.00

a. Columns/Pedestal
i.Spiral
sq.m.
175.00
ii.Tied
sq.m.
180.00
b. Footing Tie Beams & Pile Caps
sq.m.
160.00
c. Floor Beams
sq.m.
175.00
d. Floor Slab
sq.m.
165.00
e. Floor Beams (Above 4.00m high)
sq.m.
200.00
f. Floor Slab (Above 4.00m high)
sq.m.
185.00
g. Roof Beams
sq.m.
180.00
h. Gutter w/ parapet
sq.m.
190.00
i. Roof Deck (if coverage is not the same as floorsq.m.
slabs below)
175.00
j. Shearwalls
sq.m.
165.00
3. Using Table Forms

sq.m.

220.00

4. H-Frames Installation/Dismantling (Steel Scaffoldings)


a. Floor / Roof Beams (including Straight Props)

i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers

1 of 616

sq.m.
sq.m.
sq.m.
sq.m.

17.50
20.00
25.00
30.00

10.00
15.00
17.50
20.00

7.50
10.00
15.00
17.50

v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers

sq.m.
sq.m.
sq.m.
sq.m.

35.00
40.00
45.00
50.00

25.00
30.00
35.00
40.00

20.00
25.00
30.00
35.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

12.50
17.50
22.50
25.00
30.00
35.00
40.00
45.00
20.00

10.00
15.00
20.00
22.50
25.00
30.00
35.00
40.00
15.00

7.50
10.00
15.00
17.50
20.00
25.00
30.00
35.00
10.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

17.50
20.00
25.00
30.00
35.00
40.00
45.00
50.00

15.00
17.50
20.00
25.00
30.00
35.00
40.00
45.00

10.00
15.00
17.50
20.00
25.00
30.00
35.00
40.00

b. Floor Slabs

i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers
v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers
ix. For Straight Props as Scaffoldings
c. Concrete Gutter Parapets (incl. Straight Props)

i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers
v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers
d. If H-Frame is to rest on soil
i. For Compacted Soil
ii. For Muddy/Loose Soil
e. Supporting Steel Deck

sq.m.
sq.m.
sq.m.

5. Retouching, Grinding & Preparation (Ready to accept Paints)


sq.m.
a. Columns
sq.m.
b. Beams
sq.m.
c. Slabs
sq.m.
d. Walls
sq.m.
e. Parapets
B.

I.

2 of 616

40.00
50.00
60.00
45.00
50.00

35.00
45.00
45.00
40.00
45.00

40.00
45.00

35.00
40.00

30.00
35.00

sq.m.
sq.m.
sq.m.
set
set
set

105.00
110.00
175.00
330.00
385.00
275.00

85.00
105.00
110.00
275.00
360.00
220.00

70.00
80.00
85.00
250.00
330.00
200.00

set
set
set

500.00
650.00
450.00

450.00
600.00
400.00

400.00
450.00
350.00

lm.
lm.

Window Jambs Installation

a. On Double Walls
b. On Concrete Walls
D.
E.
F.
G.
H.

50.00
60.00
65.00
50.00
65.00

Door Jambs Installation

a. On Double Walls
b. On Concrete Walls
C.

Additional of P 5.00/sq.m.
Additional of P15.00/sq.m.
100.00
80.00
75.00

Steel Window Installation


Flush Door Installation
Panel Door Installation
Bar Door Installation
Steel Door Installation
Single Leaf
Double Leaf
PVC Door (incl. Jambs)

J.
K.

Steel Louver Installation


Wooden Roof Framing

a. Fabrication & Installation


L.

O.
P.
Q.
R.
S.

Installation of wooden stair handrail (narra)


Cabinets & Shelves
Quarter C Moulding
2" x 3" Wood Mouldings
Others
Hardwares
Door Lockset
Door Closer
Flush & Head Bolts
Panic Exit Device
Push Plates
Door Stops
Threshold
T. Installation of Vinyl Tiles
U. Installation of Rubber Tiles (500 x 500mm)
V. Installation of Carpet Tiles (500 x 500mm)

3 of 616

150.00

25.00

20.00

15.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

200.00
185.00
200.00
185.00
275.00
250.00
(By Negotiation)
160.00
150.00
185.00
175.00

175.00
175.00
200.00
135.00
160.00

lm.
lm.
lm.

30.00
35.00
15.00

25.00
30.00
12.50

20.00
25.00
10.00

sq.m.
sq.m.
sq.m.
sq.m.

210.00
190.00
245.00
110.00

200.00
185.00
235.00
105.00

185.00
160.00
210.00
85.00

sq.m.
sq.m.

110.00
100.00

100.00
85.00

85.00
75.00

set
set
lm.
set

165.00
185.00
30.00
20.00

160.00
175.00
25.00
15.00

140.00
140.00
22.50
12.50

Ceiling

a. 1/4" Plywood Ceiling (Ordinary)


i. w/ ceiling truss
ii. w/o ceiling truss
b. T&G, S-cut & V-cut
c. Installation of Accoustic board
d. Ceiling Board only
i. w/ V-cut
ii.Open joint
e. Covelights (Fabrication & Installation)
i.On Ordinary Ceiling
ii.On Wood Moulding(Fiberglass Ceiling)
iii.Alum.T-runner Installation
iiii. Diffuser Installation
f. Other Ceiling
i. Ord.Plywood ceiling @ Eaves
ii. Wood Slats w/ Insect Screen (W=0.30m)

III.

175.00

Baseboard

a. Kd. Tanguile
b. Narra
c. Vinyl
N.

bft.

185.00

Double Wall Partitions

a. 1/4"thk.Ply.on 2"x3"studs(V-cut & Open Joint)


b. Narra Ply.on 2"x3"studs(V-cut & Open Joint)
c. Narra Ply.on 2"x3"studs(Open Joint @ 0.30)
d. Other Kind of D/W Partition
e. 1/4"thk.Marine Plywood Panelling w/o groove
f. 1/4"thk.Narra Plywood Panelling w/ groove
M.

sq.m.

MASONRY WORKS (incl. hauling)

sq.m.
210.00
lm.
115.00
lm.
135.00
by negotiation (30
lm.
25.00
lm.
45.00

set
set
set
set
set
set
lm.
pc.
pc.
pc.

200.00
185.00
110.00
100.00
125.00
110.00
% of materials)
20.00
15.00
40.00
35.00

200.00
175.00
125.00
500.00
125.00
125.00
75.00
6.50
17.50
17.50

A.
B.

C.

Hauling of materials if far from bldg.


CHB Laying

sq.m.

25.00

22.50

20.00

a. 8" CHB
b. 6" CHB
c. 4" CHB

sq.m.
sq.m.
sq.m.

185.00
165.00
155.00

175.00
155.00
150.00

165.00
135.00
125.00

sq.m.
sq.m.

175.00
165.00

165.00
160.00

160.00
155.00

sq.m.
sq.m.

200.00
185.00

175.00
165.00

160.00
155.00

sq.m.
sq.m.

155.00
185.00

150.00
175.00

145.00
165.00

sq.m.
175.00
(w/ scaffoldings)

165.00

160.00

CHB Laying @ Roof Beams (needs Scaffolding)

a. 6" CHB
b. 4" CHB
D.

CHB Laying (irregular shape)

a. 6" CHB
b. 4" CHB
E.

Plain Cement Plaster Finish

a. by area (interior CHB walls)


b. by area (ext. CHB walls)needs scaffolding
c. by area (conc.walls & parapet)
i. Ordinary Concrete Walls (Interior Walls)
ii. Exterior Concrete & CHB Walls & Parapets
1. Ground to Fourth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
2. Fourth to Seventh Floor
Up to 2-1/2" thk.
For every add'l. 1" thk.
3. Seventh to Tenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
4. Tenth to Fourteenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
5. Above Fourteenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
d. by area (irregular CHB walls)
e. Overhead
f. by lm.(vertical & horizontal)
g. by lm.(overhead)
h. Spiral columns
i. Beam plastering (sides)
j. Beam plastering (bottom)
k. Tool Joint Finish
l. Kustura Finish
m. Exterior Grooves
n. Plastering of Louver Blocks
F.

200.00
35.00

sq.m.
sq.m.

220.00
45.00

sq.m.
sq.m.

270.00
55.00

sq.m.
sq.m.

285.00
65.00

sq.m.
sq.m.
sq.m.
sq.m.
lm.
lm.
lm.
lm.
lm.
sq.m.
sq.m.
lm.
sq.m.

200.00
210.00
100.00
125.00
200.00
145.00
165.00
160.00
150.00
100.00
330.00

300.00
85.00
185.00
190.00
85.00
110.00
185.00
135.00
160.00
150.00
110.00
65.00
260.00

165.00
175.00
80.00
100.00
165.00
110.00
125.00
110.00
75.00
35.00
225.00

sq.m.

250.00

240.00

225.00

sq.m.

325.00

300.00

285.00

Boracay Finish (incl.liston,& other acc.)

a. By area
i.Flooring
ii.Walls
* w/scaffolding

4 of 616

sq.m.
sq.m.

* w/o scaffolding
b. by lm
G.

Sandblasting
Corduroy finish
Marble Finish / Granite Finish

a. 4"x8"Marble tiles
b. Marble @ Walls
c. Marble @ Floors

5 of 616

250.00
285.00
165.00

225.00
275.00
150.00

215.00
270.00
125.00

lm.
lm.
lft.

110.00
140.00
-

100.00
120.00
10.00

85.00
100.00
-

sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.

80.00
150.00
125.00
160.00
260.00
325.00

75.00
145.00
110.00
150.00
250.00
300.00

65.00
120.00
80.00
140.00
235.00
275.00

sq.m.
sq.m.
sq.m.

300.00
265.00
250.00

285.00
250.00
245.00

265.00
245.00
220.00

sq.m.
sq.m.
sq.m.
sq.m.
lm.
lm.

265.00
245.00
220.00
220.00
90.00
-

245.00
230.00
205.00
205.00
80.00
120.00

235.00
220.00
185.00
185.00
75.00
-

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

270.00
265.00
245.00
230.00
220.00
200.00
265.00
165.00
265.00

260.00
240.00
220.00
220.00
200.00
185.00
240.00
150.00
240.00

240.00
220.00
185.00
200.00
185.00
165.00
220.00
125.00
225.00

sq.m.
sq.m.
sq.m.
sq.m.

300.00
465.00
80.00
500.00

270.00
415.00
75.00
480.00

240.00
350.00
70.00
450.00

sq.m.
sq.m.
sq.m.

425.00
415.00
415.00

385.00
385.00
360.00

360.00
350.00
350.00

Brickworks

a. 1"x2"x8"Red bricks
b. 4"x8"Clay tiles
c. 12"x12"Red cement tiles
d. 8"x8"Clay tiles
e. 6"x6"x12"Louver blocks
f. 4"x12"x12"Decorative blocks
g. Mactan stone
h. Adobe blocks
i. Ashlar stone
j. Urra Tiles
* Ordinary Layout
* Extra-ordinary Layout (w/ many cuts)
L.
M.
N.

sq.m.
sq.m.
lm.

Tileworks

a. Glazed Tiles incl. rough plaster


i. 4-1/4"x4-1/4" Glazed Tiles
ii. 4"x8"
-doiii. Others
b. Vit.floor tiles incl. topping
i. 4-1/4"x4-1/4" Glazed Tiles
ii. 4"x8"
-doiii. Others
c. Mosaic floor tiles incl. topping
d. Tile fittings
e. Stair Treads & Risers
K.

265.00
165.00

Topping

a. Straight to finish
b. Plain Cement finish
Stair Tread Topping
c. Red cement w/ V-cut
d. Deck Topping (including Cant,etc.)
e. Ramp Topping w/ Groove
J.

275.00
185.00

Stair Nosing Installation (incl. preparation)

a. Brass, Angular & Checkered Plate


b. Carborandum Strip
c. Vinyl Stair Nosing
I.

285.00
200.00

Pebble Washout Finish(incl.liston & other acc.)

a. by area
i.Flooring
ii.Walls
b. by lm
H.

sq.m.
lm.

d. Granite @ Counters
lm.
e. Granite Splashboard
lm.
f. Granite Fascia Board
lm.
g. Opening for Lavatory
set
h. Rounding of Edges
lm.
i. Faucet Hole
set
j. Granite @ Walls including Anchors (Dry Anchors)
sq.m.
k. Granite @ Floors
sq.m.
l. Granolithic Flooring
sq.m.
O.

Rip-rapping
Synthetic Finish

a. by area
i. w/ scaffolding
ii. w/o scaffolding
b. by lm
R. Keyhole Pattern Bricks
S. 4"x8"Tiles w/ Pebble Washout Pattern
T. 200 x 200 Glass Blocks
U. Lime Stucco Finish
V. Skim Coating
L & M = 45.00/sq.m. (Gray)
L & M = 55.00/sq.m. (White)
W. Shotcreting
a. 6" thk.
b. 4" thk.
c. Exterior Walls
d. Opening
e. Grooves
IV.
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.

6 of 616

###
550.00
550.00
###
385.00
###
###
385.00
385.00

350.00
-

sq.m.
sq.m.
lm.
lm.
cu.m.

40.00
80.00
70.00
70.00
510.00

35.00
65.00
50.00
60.00
480.00

30.00
55.00
40.00
50.00
415.00

sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

400.00
375.00
245.00
275.00
400.00
480.00
80.00
-

365.00
330.00
220.00
235.00
350.00
415.00
70.00
45.00
55.00

320.00
290.00
200.00
200.00
330.00
350.00
55.00
-

Retouching

a. by area
i. Walls
ii.Exposed slab
b. by lm.(corners only)
c. Curbs & Gutter
P.
Q.

385.00
-

sq.m.
sq.m.
sq.m.
lm.
lm.

REINFORCING BARS (incl.supply of M-gas & Oxygen)


RCRCC to supply Rebar Cutter & Rebar Bender if necessary
kg.
Footing & Tie Beams
kg.
Columns & Pedestal
kg.
Floor beams
kg.
Floor slab
kg.
Shearwalls
kg.
Slab on fill
kg.
Lavatory counter
kg.
Roof Beams
kg.
Gutter & Parapet
kg.
Wall footings
kg.
Stair
kg.
Lintel beams & Stiff.columns
kg.
Parapet

3.85
4.15
4.40
4.95
4.20
5.50
7.15
4.95
5.15
6.60
5.15
8.80
5.15

800.00
740.00
###
550.00
400.00

3.30
3.85
4.00
4.05
3.90
4.95
6.60
4.15
4.80
5.80
4.40
7.70
4.80

3.05
3.30
3.50
3.60
3.45
4.40
5.50
3.85
4.20
5.25
3.85
6.60
4.40

N.
O.
P.
Q.
R.

Dentils (including welding)


Waffles
Tie wires
Welded Wire Mesh
Hauling of Rebars
a. If Construction Start from Third Floor
b. If Construction Start from Fourth Floor
c. Loading & Unloading to Trucks
S. Subcon Rebars (incl. supply of tie wires)

V.
A.

Backfilling
Levelling
Excavation of Ftg. Tie Beam & Wall Footings
Compaction
Basecoarse
Soil Poisoning
Polyethelene sheets
PVC Waterstop
Chipping

cu.m.
cu.m.
cu.m.
cu.m.
sq.m.
cu.m.
sq.m.
cu.m.
sq.m.
sq.m.
lm.
lm.
lm.

4.40
4.40
5.15
20.00

0.40
0.50
0.45
###

3.00

220.00
200.00
160.00
380.00
350.00
300.00
600.00
450.00
385.00
(By Administration)
160.00
145.00
120.00
50.00
40.00
35.00
415.00
365.00
350.00
50.00
40.00
35.00
185.00
145.00
110.00
20.00
15.00
12.50
15.00
12.50
10.00
25.00
15.00
12.50
20.00
40.00

17.50
35.00

15.00
30.00

175.00
600.00
385.00
650.00
650.00

150.00
550.00
350.00
600.00
600.00

120.00
475.00
275.00
550.00
550.00

135.00
420.00
650.00

150.00
350.00
600.00

120.00
325.00
550.00

250.00
650.00
500.00

200.00
600.00
450.00

165.00
550.00
420.00

120.00

150.00
100.00

75.00

Pouring/Concreting

a. Floor beams, Slab & columns


i. Pumpcrete
cu.m.
ii. Jobmix
cu.m.
iii. Ready mix
cu.m.
b. Columns-(Job mix)
cu.m.
c. Wall footings (Job mix)
cu.m.
d. Shearwall / Retaining Walls
i. Pumpcrete
cu.m.
ii. Ready Mix
cu.m.
iii. Job mix
cu.m.
e. Roof beams, Gutter & Parapet
i. Pumpcrete
cu.m.
ii. Job mix
cu.m.
iii. Ready mix
cu.m.
f. Footings, Pedestals & Tie Beams
i. Pumpcrete
* Volume < 200.00 cu.m.
cu.m.
* Volume = 200-300 ; 300-400 ; 400 & above
cu.m.
cu.m.
ii. Ready mix

7 of 616

4.80
4.80
###
27.50

Excavation

a. From 0.01-0.10
b. From 0.11-0.20
K.

kg.
kg.
kg.
kg.

5.50
5.50
5.15
38.50

LABOR WORKS

a. Ordinary Soil
* Bulk
* Manual
b. Adobe
c. Dewatering
B.
C.
D.
E.
F.
G.
H.
I.
J.

kg.
kg.
kg.
sq.m.

L.
M.
N.
O.
P.
Q.
VI.
A.

* Using Buggy
cu.m.
300.00
* Direct Pouring
* Volume < 200.00 cu.m.
cu.m.
* Volume = 200-300 ; 300-400 ; 400 & above
cu.m. cu.m.
100.00
iii. Job mix
cu.m.
600.00
g. Dentils (All levels)
i. Pumpcrete
cu.m.
200.00
ii. Job mix
cu.m.
750.00
h. Slab on Fill/Pavement
i. Job mix
cu.m.
385.00
ii. Ready mix
* Using Buggy
cu.m.
300.00
* Direct Pouring
cu.m.
135.00
iii. Pumpcrete
cu.m.
175.00
i. Curbs & Gutter
i. Ready mix
cu.m.
360.00
ii. Job mix
cu.m.
600.00
j. Lintel Beams, Stiff. Columns & counters
cu.m.
750.00
k. Stair
i. Pumpcrete
cu.m.
175.00
ii. Job mix
cu.m.
600.00
l. Cistern, Septic Tank, etc.
i. Pumpcrete
cu.m.
165.00
ii. Job mix
cu.m.
1,100.00
m. Floor Slabs only
i. Placing of Concrete
cu.m.
ii. Straight to Finish
sq.m.
pp
650.00
Cutting of Prestress Concrete Piles
sq.m.
175.00
Trimming of Mechanically Excavated Soil
lm.
75.00
Cutting of Concrete using Concrete Saw
pp
400.00
Cutting of Concrete Sheet Piles
pp
2,500.00
Cutting of Bored Piles
sq.m.
65.00
Steel Deck Installation

Long span Coloroof


a. Using G.I. Straps/teksrew

B.
C.
D.
E.
VII.

DEMOLITION / DISMANTLING

8 of 616

200.00

100.00
65.00
550.00

60.00
450.00

165.00
650.00

150.00
600.00

350.00

300.00

275.00
110.00
150.00

250.00
100.00
100.00

350.00
550.00
700.00

275.00
500.00
650.00

150.00
550.00

110.00
500.00

150.00
850.00

120.00
650.00

50.00
85.00
500.00
150.00
65.00
350.00
###
50.00

400.00
125.00
60.00
250.00
###
40.00

7.50
60.00
7.50
20.00
150.00
275.00
85.00

6.50
55.00
6.00
17.50
145.00
250.00
65.00

TINSMITHRY WORKS

b. Using Roof Nails


Plain G.I.Shts.on roof vents
Ridge rolls,Flashings & Gutters
Ducts for Exhaust Fans
Roof Insulation

A.
B.

250.00

Concrete
CHB Walls

lft.
sq.m.
lft.
lft.
pc.
pc.
sq.m.

10.00
65.00
8.50
25.00
175.00
300.00
100.00

cu.m.
sq.m.

2,750.00

###
###

###

C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.
S.
T.
U.
V.
W.
X.

9 of 616

Corr. G.I. Sheets


Asbestos Roofing
Steel Roof Framing
Wooden Roof Framing
Wooden Floor Framing
Steel Windows
Doors
Double Wall Partition
Ceiling
Gutter & Flashing
Chipping of Floor topping
Cabinets,counters & shelves
Chipping of tiles
Scraping of vinyl tiles
Wood parquet
Chipping of Synthetic Finish
Alum. Framed Glass
Blasting of Footings (by Dynamite)
Blasting of Walls (by Dynamite)
Cutting of Concrete
Electrical
Plumbing

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
cu.m.
cu.m.
lm.
lot
lot

55.00
40.00
50.00
60.00
50.00
55.00
35.00
60.00
30.00
30.00
20.00
75.00
35.00
90.00
30.00
40.00
35.00
60.00
-

###
50.00
35.00
40.00
50.00
40.00
50.00
30.00
50.00
20.00
20.00
15.00
65.00
30.00
65.00
20.00
35.00
30.00
50.00
###

40.00
30.00
35.00
40.00
30.00
40.00
20.00
40.00
15.00
17.50
12.50
50.00
20.00
50.00
15.00
30.00
20.00
40.00
-

PRICE LIST
SIZE
(mm)

MASS
(kg/lm)

6.0

7.5

Grade 230 ( Structural Grade )

LENGTH ( M )
9.0

10.5

ASTM / GRADE 33

12.0
%age

10

0.616

73.92

92.4

110.88

129.36

147.84

12

0.888

106.56

133.2

159.84

186.48

213.12

16

1.578

189.36

236.7

284.04

331.38

378.72

20

2.466

295.92

369.9

443.88

517.86

591.84

25

3.853

462.36

577.95

693.54

809.13

924.72

Grade 275 ( Intermediate )

ASTM / GRADE 40

%age

10

0.616

81.31

101.64

121.97

142.3

162.62

12

0.888

117.22

146.52

175.82

205.13

234.43

16

1.578

206.4

258

309.6

361.2

412.8

20

2.466

322.55

403.19

483.83

564.47

645.11

25

3.853

503.97

629.97

755.96

881.95

1007.94

28

4.834

632.29

790.36

948.43

1106.5

1264.57

32

6.313

833.32

1041.65

1249.97

1458.3

1666.83

36

7.990

1054.68

1318.35

1582.02

1845.69

2109.36

Grade 415 ( Hard Grade )

ASTM / GRADE 60

%age

10

0.616

83.9

104.87

125.85

146.82

167.8

12

0.888

120.95

151.18

181.42

211.65

241.89

16

1.578

213.03

266.29

319.55

372.8

426.06

20

2.466

332.91

416.14

499.37

582.59

665.82

25

3.853

520.16

650.19

780.23

910.27

1040.31

28

4.834

652.59

815.74

978.89

1142.03

1305.18

32

6.313

859.83

1074.79

1289.75

1504.7

1719.66

36

7.990

1088.24

1360.3

1632.36

1904.42

2176.48

40

9.865

1373.21

1716.51

2059.81

2403.11

2746.42

50

15.413

2191.73

2739.66

3287.59

3835.53

4383.46

%age
ASTM Grade 40
Base Price

1.61

%age

1.58

ASTM Grade 60
Base Price
Steel Asia, Pag-asa
%age

22

22.6

1.61

ASTM Grade 40
Base Price
%age
ASTM Grade 60
Base Price

21.9
1.58
22.6

Kg / Pc.
6.0

Unit Cost
mftg
kg. / m

1.5
3.696

20.00

30.00

5.328

20.00

30.00

9.468

20.00

30.00

14.796

20.00

30.00

23.118

20.00

30.00

3.696

22.00

28.60

5.328

22.00

28.60

119.75
33.00

1.3

9.468

21.80

28.34

14.796

21.80

28.34

23.118

21.80

28.34

29.004

21.80

28.34

37.878

22.00

28.60

47.94

22.00

28.60

3.696

22.70

29.06

5.328

22.70

29.06

9.468

22.50

28.80

14.796

22.50

28.80

23.118

22.50

28.80

29.004

22.50

28.80

37.878

22.70

29.06

47.94

22.70

29.06

59.19

23.20

29.70

92.478

23.70

30.34

1.28

35.42

35.708

296.72
31.34

106.92

35.259

35.708

FORMWORKS MATERIALS PRICE LISTS (Panel Forms)


Date (Updated): May 11,2010

Unit Cos
Unit
I. Rentals
1. Metal Forms

a. Metal Panels
i.
750 x 1800mm
ii.
750 x 1200mm
iii.
750 x 900mm
iv.
650 x 1800mm
v.
650 x 1500mm
vi.
650 x 1200mm
vii. 600 x 1800mm
viii. 600 x 1500mm
ix.
600 x 1200mm
x.
600 x 900mm
xi.
600 x 600mm
xii. 550 x 1800mm
xiii. 550 x 1500mm
xiv. 550 x 1200mm
xv.
550 x 900mm
xvi. 500 x 1800mm
xvii 500 x 1500mm
xviii. 450 x 1800mm
xix. 450 x 1500mm
xx.
450 x 900mm
xxi 400 x 1800mm
xxii 400 x 1500mm
xxii 400 x 1200mm
xxiv. 400 x 900mm
xxv. 400 x 600mm
xxvi. 350 x 1800mm
xxvii. 350 x 1500mm
350 x 1200mm
300 x 1800mm
300 x 1500mm
300 x 900mm
300 x 600mm
250 x 1800mm
250 x 1500mm
250 x 900mm
200 x 1800mm
200 x 1200mm
150 x 1800mm
150 x 1500mm
150 x 1200mm
150 x 600mm
100 x 1500mm
1.80 Corner Section
1.50 Corner Section
1.20 Corner Section
0.90 Corner Section
0.60 Corner Section
1.80 Exterior Angle

Supplier A
Rate/Day

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 4.00
PHP 3.00
PHP 2.33
PHP 3.50
PHP 3.00
PHP 2.67
PHP 3.33
PHP 2.83
PHP 2.50
PHP 1.83
PHP 1.58
PHP 3.08
PHP 2.67
PHP 2.33
PHP 1.67
PHP 2.83
PHP 2.50
PHP 2.58
PHP 2.33
PHP 1.42
PHP 2.33
PHP 2.17
PHP 1.83
PHP 1.33
PHP 1.25
PHP 2.17
PHP 2.00
PHP 1.67
PHP 2.00
PHP 1.83
PHP 1.17
PHP 1.00
PHP 1.83
PHP 1.67
PHP 1.08
PHP 1.67
PHP 1.17
PHP 1.50
PHP 1.33
PHP 1.00
PHP 0.67
PHP 1.17
PHP 1.67
PHP 1.67
PHP 1.17
PHP 0.92
PHP 0.67
PHP 0.50

Supplier name
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

Supplier B
Rate/Day
13

1.50 Exterior Angle


1.20 Exterior Angle
0.90 Exterior Angle
0.60 Exterior Angle
0.30 Exterior Angle
1.80 Edge Section
1.50 Edge Section
1.20 Edge Section
0.90 Edge Section
1.50 Interior Corner
b. Metal Form Accessories
Panel Clips
J Bolt 1-1/2"
Waler Washer
Coil Bolt 300mm
Coil Bolt 200mm
c. Panel Frame
600 x 2000mm
600 x 1800mm
600 x 1500mm
600 x 1200mm
600 x 900mm
550 x 1800mm
550 x 1500mm
550 x 900mm
550 x 600mm
500 x 1800mm
500 x 1500mm
500 x 1200mm
500 x 900mm
450 x 1800mm
450 x 1500mm
450 x 1200mm
450 x 900mm
400 x 2400mm
400 x 1800mm
400 x 1500mm
400 x 1200mm
400 x 900mm
400 x 600mm
350 x 1800mm
350 x 1500mm
350 x 1200mm
350 x 900mm
350 x 600mm
300 x 2400mm
300 x 1800mm
300 x 1500mm
300 x 1200mm
300 x 900mm
300 x 600mm
250 x 2400mm
250 x 1800mm
250 x 1500mm
250 x 1200mm

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 0.42
PHP 0.33
PHP 0.25
PHP 0.17
PHP 0.12
PHP 0.30
PHP 0.30
PHP 0.25
PHP 0.20
PHP 1.42
PHP 0.05
PHP 0.03
PHP 0.02
PHP 0.03
PHP 0.03
PHP 3.50
PHP 3.33
PHP 0.90
PHP 2.50
PHP 0.54
PHP 3.08
PHP 0.83
PHP 1.67
PHP 1.50
PHP 2.83
PHP 2.50
PHP 2.17
PHP 1.50
PHP 2.58
PHP 2.33
PHP 2.00
PHP 1.42
PHP 3.10
PHP 2.33
PHP 2.17
PHP 1.83
PHP 1.83
PHP 1.25
PHP 2.17
PHP 2.00
PHP 1.67
PHP 1.25
PHP 1.17
PHP 2.33
PHP 2.00
PHP 1.83
PHP 1.50
PHP 1.17
PHP 1.00
PHP 2.17
PHP 1.83
PHP 1.67
PHP 1.33

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

c
o
r
r
e
c
t
e
d
u
n
i
t
c
o
s

250 x 900mm
200 x 1800mm
200 x 1500mm
200 x 1200mm
200 x 900mm
200 x 600mm
150 x 1800mm
150 x 1500mm
150 x 1200mm
150 x 900mm
100 x 1800mm
100 x 1500mm
100 x 1200mm
100 x 900mm
1.80 Outer Angle
1.50 Outer Angle
1.20 Outer Angle
0.90 Outer Angle
0.60 Outer Angle
1.80 Inside Corner
1.50 Inside Corner
0.90 Inside Corner
1.50 Filler Angle
1.20 Filler Angle
0.60 Filler Angle
1.80 Inside Corner for Slab
0.90 Inside Corner for Slab
0.60 Inside Corner for Slab
d. Gang Form
D-Beam x 3.30m (2.5mm thk)
D-Beam x 2.40m (2.5mm thk)
D-Beam x 1.40m (2.5mm thk)
D-Beam x 1.20m (2.5mm thk)
D-Beam x 0.60m (2.5mm thk)
Splice Plate
Cast Plate
Wing Nut 21mm
Wing Nut 17mm
Wing Nut 12mm
Tie Rod - 17mm x 300mm
e. Other Accessories
Wedge Pin
C-Purlins
2. Scaffoldings
a. H-Frames
i.
1.70 x 1.20m H-Frame (G.I.)
ii.
1.20 x 1.20m H-Frame (G.I.)
iii.
0.90 x 1.20m H-Frame (G.I.)
iv.
1.70 x 1.20m H-Frame (B.I.)
v.
1.20 x 1.20m H-Frame (B.I.)
vi.
0.90 x 1.20m H-Frame (B.I.)
vii. 1.70 x 0.90m H-Frame (G.I.)
viii. 1.20 x 0.90m H-Frame (B.I.)
ix.
0.90 x 0.90m H-Frame (B.I.)
b. Other Accessories

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 1.08
PHP 1.67
PHP 0.30
PHP 1.17
PHP 1.00
PHP 0.83
PHP 1.50
PHP 0.23
PHP 1.00
PHP 0.14
PHP 0.18
PHP 0.15
PHP 0.12
PHP 0.09
PHP 0.50
PHP 0.42
PHP 0.33
PHP 0.25
PHP 0.17
PHP 1.67
PHP 1.42
PHP 0.92
PHP 0.33
PHP 0.20
PHP 0.15
PHP 1.67
PHP 0.25

PHP 0.16
PHP 1.68

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 1.70
PHP 0.92
PHP 0.83
PHP 1.70
PHP 0.92
PHP 0.83
PHP 1.00
PHP 0.75
PHP 0.67

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

PHP 2.99
PHP 2.18
PHP 1.27
PHP 1.09
PHP 0.54
PHP 0.18
PHP 0.18
PHP 0.11
PHP 0.11
PHP 0.11
PHP 0.50

u
n
i
t
c
o
s
t

i.
2.50m Cross Brace
ii.
2.25m Cross Brace
iii.
2.00m Cross Brace
iv.
1.80m Cross Brace
v.
1.70m Cross Brace
vi.
1.50m Cross Brace
vii. Straight Props (outer pipe)
viii. Straight Props (inner pipe)
ix.
Fixed U-head 2"
x.
Fixed U-head 4"
xi.
Adjustable U-head 2"
xii. Adjustable U-head 3"
xii. Adjustable U-head 4"
xiv. Adjustable Base Jack
xv.
Joint Pin
c. Waller Pipe & Accessories
1" x 6.00m GI Pipe
i.
1" x 5.50m GI Pipe
ii.
1" x 5.00m GI Pipe
iii.
1" x 4.50m GI Pipe
iv.
1" x 4.00m GI Pipe
v.
1" x 3.00m GI Pipe
vi.
vii. 1" x 2.50m GI Pipe
viii. 1" x 2.40m GI Pipe
1" x 2.00m GI Pipe
ix.
1" x 1.85m GI Pipe
x.
1" x 1.60m GI Pipe
xi.
xii. 1" x 1.50m GI Pipe
xiii. 1" x 1.00m GI Pipe
xiv. 1" x 0.80m GI Pipe
1" x 0.70m GI Pipe
xv.
xvi. 1" x 0.50m GI Pipe
xvii 1" x 0.40m GI Pipe
xviii. Swivel Clamp
xix. Fixed Clamp
1" x 6.00m Double Pipe
xx.
xxi 1" x 5.00m Double Pipe
xxii 1" x 4.00m Double Pipe
xxii 1" x 3.00m Double Pipe
xxiv. 1" x 2.50m Double Pipe
xxv. 1" x 2.00m Double Pipe
xxvi. 1" x 1.50m Double Pipe
xxvii. 1" x 1.00m Double Pipe
d. Steel Headers
i.
2" x 4" BI Steel Headers x 3.00m
ii.
2" x 4" BI Steel Headers x 2.44m
iii.
2" x 4" BI Steel Headers x 2.00m
iv.
2" x 4" BI Steel Headers x 1.80m
v.
2" x 4" BI Steel Headers x 1.50m
vi.
2" x 4" BI Steel Headers x 1.20m
vii. 2" x 4" I-beam Steel Headers x 3.00m
viii. 2" x 4" I-beam Steel Headers x 1.50m
d. Hanging Steel Scaffolds
i.
Gondola
ii.
Gondola Bracket 0.40

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.67
PHP 0.67
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.07

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 2.33
PHP 2.17
PHP 2.00
PHP 1.83
PHP 1.67
PHP 1.33
PHP 1.17
PHP 1.09
PHP 1.00
PHP 0.93
PHP 0.90
PHP 0.83
PHP 0.83
PHP 0.81
PHP 0.80
PHP 0.78
PHP 0.77
PHP 0.29
PHP 0.29
PHP 4.66
PHP 4.00
PHP 3.34
PHP 2.66
PHP 2.34
PHP 2.00
PHP 1.66
PHP 1.34

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

piece
piece
piece
piece
piece
piece
piece
piece

PHP 1.17
PHP 1.00
PHP 1.00
PHP 0.83
PHP 0.67
PHP 0.50
PHP 4.59
PHP 4.20

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

piece
piece

PHP 3.17
PHP 5.67

FEMD
FEMD

iii.
Gondola Bracket 0.55
iv.
Steel Platform (CP) 0.40 x 2.00m
v.
Steel Platform (EW) 0.40 x2.00m
vi.
Steel Ladder (Expanded Metal)
vii. Double C-Purlins Flatform x 3.00m
d. Others
i.
Caster Wheel (Swivel)

piece
piece
piece
piece
piece
piece
piece

PHP 4.79
PHP 1.67
PHP 5.79
PHP 21.58
PHP 2.94
PHP 1.95

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

LABOR RATES
Unit Cost
Supplier B
Supplier name

Supplier C
Rate/Day
14

Applied Rate

Supplier name
14.00
3.00
2.33
3.50
3.00
2.67
3.33
2.83
2.50
1.83
1.58
3.08
2.67
2.33
1.67
2.83
2.50
2.58
2.33
1.42
2.33
2.17
1.83
1.33
1.25
2.17
2.00
1.67
2.00
1.83
1.17
1.00
1.83
1.67
1.08
1.67
1.17
1.50
1.33
1.00
0.67
1.17
1.67
1.67
1.17
0.92
0.67
0.50

Item
I. Indirect Manpower
1. Accountant
2. Cadet Engineer
3. Carpenter
4. Cost Engineer
5. Driver
6. Electrician
7. Field Engineer
8. Foreman
9. Glass Installer
10. Guard
11. Heavy Equipment Operator
12. Laborer
13. Leadman
14. Mason
15. Mechanic
16. Messenger
17. Mixer Operator
18. Painter
19. Plumber
20. Project In-charge
21. Screeder Operator
22. Steelman
23. Surveying Aide
24. Surveyor
25. Tile Setter
26. Timekeeper
27. Utility
28. Utility
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32.
33.

1
Provincia
Minimum
PHP 400.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

0.42
0.33
0.25
0.17
0.12
0.30
0.30
0.25
0.20
1.42
0.05
0.03
0.02
0.03
0.03
3.50
3.33
0.90
2.50
0.54
3.08
0.83
1.67
1.50
2.83
2.50
2.17
1.50
2.58
2.33
2.00
1.42
3.10
2.33
2.17
1.83
1.83
1.25
2.17
2.00
1.67
1.25
1.17
2.33
2.00
1.83
1.50
1.17
1.00
2.17
1.83
1.67
1.33

1.08
1.67
0.30
1.17
1.00
0.83
1.50
0.23
1.00
0.14
0.18
0.15
0.12
0.09
0.50
0.42
0.33
0.25
0.17
1.67
1.42
0.92
0.33
0.20
0.15
1.67
0.25
2.99
2.18
1.27
1.09
0.54
0.18
0.18
0.11
0.11
0.11
0.50
0.16
1.68

1.70
0.92
0.83
1.70
0.92
0.83
1.00
0.75
0.67

0.33
0.33
0.33
0.33
0.33
0.33
0.67
0.67
0.50
0.50
0.50
0.50
0.50
0.50
0.07
2.33
2.17
2.00
1.83
1.67
1.33
1.17
1.09
1.00
0.93
0.90
0.83
0.83
0.81
0.80
0.78
0.77
0.29
0.29
4.66
4.00
3.34
2.66
2.34
2.00
1.66
1.34
1.17
1.00
1.00
0.83
0.67
0.50
4.59
4.20
3.17
5.67

4.79
1.67
5.79
21.58
2.94
1.95

1
Provincial Rate
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

2
Manila Rate
Minimum
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

PHP 700.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

Applied Rate

600
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Location of Project:

5
4
3
2
1

HILMARC'S CONSTRUCTION CORPORATION


1835 E. Rodriguez Sr. Ave.,Cubao,Q.C.
Tel.Nos. 726-94-71 to 73; 726-94-75 to 77;
723-84-76; 723-84-79
Fax No. 724-86-14; 723-85-39
SUB-CONTRACTORS LABOR UNIT COSTS

AS

OF

A P R I L

SCOPE OF WORKS

I.

LAYOUT OF THE BUILDING

II.
CARPENTRY WORKS
A. Formworks
1. Using Lumber (incl.stripping,formoil application & nail ext.)
a. Columns/Pedestal
i.Spiral
ii.Tied
b. Footing Tie Beams & Pile Caps
c. Floor Beams
d. Floor Slab
e. Floor Beams (Above 4.00m high)
f. Floor Slab (Above 4.00m high)
g. Roof Beams
h. Gutter w/ parapet
i. Roof Deck (if coverage is not the same as floor slabs below)
j. Shearwalls
k. Stair & Bleacher
l. Dentils
m. Parapet
n. Waffles
o. Stair on Fill
p. Lintel Beams & Stiff. Columns
q. Pavement
r. Slab on Fill
s. When forms used are scrap wood & lumber
2. Using Steel Forms
a. Columns/Pedestal
i.Spiral
ii.Tied
b. Footing Tie Beams & Pile Caps
c. Floor Beams
d. Floor Slab

2001

UNITS

sq.m.

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
lm.
sq.m.
lm.
lm.

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

SMALL
SCALE

18.50

MEDIUM
SCALE

12.50

220.00
190.00
195.00
185.00
155.00
140.00
190.00
175.00
185.00
165.00
200.00
190.00
195.00
185.00
200.00
190.00
205.00
200.00
190.00
175.00
195.00
180.00
220.00
210.00
205.00
200.00
195.00
185.00
205.00
200.00
85.00
80.00
165.00
160.00
55.00
45.00
45.00
40.00
plus 15.00 plus 15.00
Installation
Small Sc. Big Scale
135.00
130.00
140.00
125.00
125.00
120.00
135.00
125.00
130.00
120.00

SCOPE OF WORKS
e. Floor Beams (Above 4.00m high)
f. Floor Slab (Above 4.00m high)
g. Roof Beams
h. Gutter w/ parapet
i. Roof Deck (if coverage is not the same as floor slabs below)
j. Shearwalls
3. H-Frames Installation/Dismantling only (Steel Scaffoldings)
a. Steel Scaffoldings
i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers
v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers
b. If H-Frame is to rest on soil
i. For Compacted Soil
ii. For Muddy/Loose Soil
c. Supporting Steel Deck
4. Retouching, Grinding & Preparation (Ready to accept Paints)
a. Columns
b. Beams
c. Slabs
d. Walls
e. Parapets
B. Door Jambs Installation
a. On Double Walls
b. On Concrete Walls
C. Window Jambs Installation
a. On Double Walls
b. On Concrete Walls
D. Steel Window Installation
E. Flush Door Installation
F. Panel Door Installation
G. Bar Door Installation
H. Steel Door Installation
Single Leaf
Double Leaf
I. Steel Louver Installation
J. Wooden Roof Framing
a. Fabrication & Installation
K. Double Wall Partitions
a. 1/4"thk.Ply.on 2"x3"studs(V-cut & Open Joint)
b. Narra Ply.on 2"x3"studs(V-cut & Open Joint)
c. Narra Ply.on 2"x3"studs(Open Joint @ 0.30)
d. Other Kind of D/W Partition

UNITS
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

SMALL
SCALE
150.00
145.00
140.00
145.00
135.00
130.00

MEDIUM
SCALE
140.00
135.00
130.00
135.00
125.00
125.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

14.00
15.00
18.50
22.50
25.00
27.50
30.00
35.00

7.00
10.50
14.00
15.00
20.00
22.50
25.00
30.00

sq.m.
sq.m.
sq.m.

Additional of P 5.00/sq.m.
Additional of P15.00/sq.m.
70.00
50.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

37.50
45.00
50.00
37.50
50.00

27.50
37.50
47.50
35.00
40.00

lm.
lm.

27.50
32.50

22.50
30.00

sq.m.
sq.m.
sq.m.
set
set
set

80.00
85.00
135.00
220.00
290.00
175.00

65.00
80.00
75.00
200.00
275.00
150.00

set
set
sq.m.

350.00
485.00
140.00

350.00
450.00
125.00

bft.

12.50

12.50

sq.m.
sq.m.
sq.m.

145.00
140.00
145.00
140.00
190.00
175.00
(By Negotiation)

L.

M.

N.
O.
P.
Q.
R.

III.

SCOPE OF WORKS
e. 1/4"thk.Marine Plywood Panelling w/o groove
f. 1/4"thk.Narra Plywood Panelling w/ groove
Baseboard
a. Kd. Tanguile
b. Narra
c. Vinyl
Ceiling
a. 1/4" Plywood Ceiling (Ordinary)
i. w/ ceiling truss
ii. w/o ceiling truss
b. T&G, S-cut & V-cut
c. Installation of Accoustic board
d. Ceiling Board only
i. w/ V-cut
ii.Open joint
e. Covelights (Fabrication & Installation)
i.On Ordinary Ceiling
ii.On Wood Moulding(Fiberglass Ceiling)
iii.Alum.T-runner Installation
iiii. Diffuser Installation
f. Other Ceiling
i. Ord.Plywood ceiling @ Eaves
ii. Wood Slats w/ Insect Screen (W=0.30m)
Installation of wooden stair handrail (narra)
Cabinets & Shelves
Quarter C Moulding
2" x 3" Wood Mouldings
Others
Hardwares
Door Lockset
Door Closer
Flush & Head Bolts
Panic Exit Device
Push Plates
Door Stops

SMALL
SCALE
120.00
140.00

MEDIUM
SCALE
110.00
135.00

lm.
lm.
lm.

21.50
25.00
10.00

18.50
22.50
8.00

sq.m.
sq.m.
sq.m.
sq.m.

160.00
140.00
190.00
85.00

150.00
135.00
180.00
80.00

sq.m.
sq.m.

80.00
70.00

75.00
65.00

set
set
lm.
set

130.00
140.00
21.50
13.50

120.00
135.00
18.50
10.50

UNITS
sq.m.
sq.m.

sq.m.
160.00
150.00
lm.
90.00
85.00
lm.
100.00
95.00
by negotiation (30 % of materials)
lm.
16.50
14.50
lm.
32.50
28.50

set
set
set
set
set
set

150.00
125.00
65.00
350.00
65.00
65.00

MASONRY WORKS (incl. hauling)

A. Hauling of materials if far from bldg.


B. CHB Laying
a. 8" CHB
b. 6" CHB
c. 4" CHB
C. CHB Laying @ Roof Beams (needs Scaffolding)
a. 6" CHB
b. 4" CHB
D. CHB Laying (irregular shape)
a. 6" CHB
b. 4" CHB
E. Plain Cement Plaster Finish

sq.m.

18.50

16.50

sq.m.
sq.m.
sq.m.

140.00
130.00
120.00

135.00
120.00
115.00

sq.m.
sq.m.

135.00
130.00

130.00
125.00

sq.m.
sq.m.

145.00
140.00

135.00
130.00

F.

G.

H.

I.

SCOPE OF WORKS
a. by area (interior CHB walls)
b. by area (ext. CHB walls)needs scaffolding
c. by area (conc.walls & parapet)
i. Ordinary Concrete Walls (Interior Walls)
ii. Exterior Concrete & CHB Walls & Parapets (w/ scaffoldings)
1. Ground to Fourth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
2. Fourth to Seventh Floor
Up to 2-1/2" thk.
For every add'l. 1" thk.
3. Seventh to Tenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
4. Tenth to Fourteenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
5. Above Fourteenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
d. by area (irregular CHB walls)
e. Overhead
f. by lm.(vertical & horizontal)
g. by lm.(overhead)
h. Spiral columns
i. Beam plastering (sides)
j. Beam plastering (bottom)
k. Tool Joint Finish
l. Kustura Finish
m. Exterior Grooves
n. Plastering of Louver Blocks
Boracay Finish (incl.liston,& other acc.)
a. By area
i.Flooring
ii.Walls
* w/scaffolding
* w/o scaffolding
b. by lm
Pebble Washout Finish(incl.liston & other acc.)
a. by area
i.Flooring
ii.Walls
b. by lm
Stair Nosing Installation (incl. preparation)
a. Brass, Angular & Checkered Plate
b. Carborandum Strip
c. Vinyl Stair Nosing
Topping
a. Straight to finish
b. Plain Cement finish

UNITS
sq.m.
sq.m.

SMALL
SCALE
130.00
160.00

MEDIUM
SCALE
125.00
145.00

sq.m.

135.00

130.00

sq.m.
sq.m.

155.00
22.50

sq.m.
sq.m.

180.00
35.00

sq.m.
sq.m.

210.00
45.00

sq.m.
sq.m.

220.00
55.00

sq.m.
sq.m.
sq.m.
sq.m.
lm.
lm.
lm.
lm.
lm.
sq.m.
sq.m.
lm.
sq.m.

150.00
155.00
75.00
95.00
155.00
110.00
130.00
125.00
115.00
70.00
260.00

240.00
65.00
140.00
145.00
65.00
85.00
140.00
100.00
120.00
115.00
85.00
45.00
200.00

sq.m.

195.00

185.00

sq.m.
sq.m.
lm.

250.00
220.00
160.00

230.00
210.00
140.00

sq.m.
sq.m.
lm.

190.00
220.00
130.00

175.00
215.00
110.00

lm.
lm.
lft.

80.00
105.00

75.00
90.00
8.00

sq.m.
sq.m.

60.00
115.00

55.00
110.00

J.

K.

L.
M.
N.

O.

P.
Q.

SCOPE OF WORKS
Stair Tread Topping
c. Red cement w/ V-cut
d. Deck Topping (including Cant,etc.)
e. Ramp Topping w/ Groove
Tileworks
a. Glazed Tiles incl. rough plaster
i. 4-1/4"x4-1/4" Glazed Tiles
ii. 4"x8"
-doiii. Others
b. Vit.floor tiles incl. topping
i. 4-1/4"x4-1/4" Glazed Tiles
ii. 4"x8"
-doiii. Others
c. Mosaic floor tiles incl. topping
d. Tile fittings
Brickworks
a. 1"x2"x8"Red bricks
b. 4"x8"Clay tiles
c. 12"x12"Red cement tiles
d. 8"x8"Clay tiles
e. 6"x6"x12"Louver blocks
f. 4"x12"x12"Decorative blocks
g. Mactan stone
h. Adobe blocks
i. Ashlar stone
j. Urra Tiles
* Ordinary Layout
* Extra-ordinary Layout (w/ many cuts)
Sandblasting
Corduroy finish
Marble Finish / Granite Finish
a. 4"x8"Marble tiles
b. Marble @ Walls
c. Marble @ Floors
d. Marble @ Counters
e. Opening for Lavatory
f. Rounding of Edges
g. Faucet Hole
h. Granite @ Walls including Anchors (Dry Anchors)
i. Granite @ Floors
j. Granolithic Flooring
Retouching
a. by area
i. Walls
ii.Exposed slab
b. by lm.(corners only)
c. Curbs & Gutter
Rip-rapping
Synthetic Finish
a. by area

UNITS
lm.
sq.m.
sq.m.
sq.m.

SMALL
SCALE
95.00
120.00
200.00
255.00

MEDIUM
SCALE
80.00
115.00
190.00
235.00

sq.m.
sq.m.
sq.m.

230.00
205.00
195.00

220.00
200.00
185.00

sq.m.
sq.m.
sq.m.
sq.m.
lm.

205.00
185.00
165.00
165.00
65.00

190.00
180.00
160.00
160.00
60.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

210.00
205.00
190.00
180.00
170.00
150.00
205.00
125.00
205.00

200.00
185.00
165.00
170.00
150.00
140.00
185.00
115.00
185.00

sq.m.
sq.m.
sq.m.
sq.m.

230.00
360.00
60.00
385.00

210.00
320.00
55.00
375.00

sq.m.
sq.m.
sq.m.
lm.
set
lm.
set
sq.m.
sq.m.
sq.m.

330.00
320.00
320.00
300.00
525.00
215.00
180.00

300.00
300.00
280.00
260.00
450.00
180.00
150.00
2,000.00
280.00
280.00

sq.m.
sq.m.
lm.
lm.
cu.m.

30.00
60.00
50.00
50.00
400.00

25.00
50.00
40.00
45.00
375.00

SCOPE OF WORKS
i. w/ scaffolding
ii. w/o scaffolding
b. by lm
R. Keyhole Pattern Bricks
S. 4"x8"Tiles w/ Pebble Washout Pattern
T. 200 x 200 Glass Blocks
IV.
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.

V.

UNITS
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.

SMALL
SCALE
310.00
290.00
185.00
210.00
310.00
375.00

MEDIUM
SCALE
285.00
250.00
165.00
180.00
275.00
325.00

REINFORCING BARS (incl.supply of M-gas & Oxygen)


HCC to supply Rebar Cutter & Rebar Bender if necessary but maintenance shall be by subcon
Footing & Tie Beams
kg.
3.00
2.45
Columns & Pedestal
kg.
3.20
2.70
Floor beams
kg.
3.30
2.80
Floor slab
kg.
3.50
2.90
Shearwalls
kg.
3.25
2.75
Slab on fill
kg.
4.00
3.75
Lavatory counter
kg.
5.35
4.75
Roof Beams
kg.
3.75
3.00
Gutter & Parapet
kg.
4.00
3.75
Wall footings
kg.
5.25
4.50
Stair
kg.
4.00
3.50
Lintel beams & Stiff.columns
kg.
7.00
6.00
Parapet
kg.
4.00
3.75
Dentils (including welding)
kg.
4.30
3.75
Waffles
kg.
4.30
3.75
Tie wires
kg.
4.00
4.00
Welded Wire Mesh
sq.m.
30.00
20.00
Hauling of Rebars
a. If Construction Start from Third Floor
kg.
0.30
b. If Construction Start from Fourth Floor
kg.
0.35
c. Loading & Unloading to Trucks
kg.
0.35
LABOR WORKS

A. Excavation
a. Ordinary Soil
* Bulk
* Manual
b. Adobe
c. Dewatering
B. Backfilling
a. Manual
b. by Equipment
C. Levelling
D. Excavation of Ftg. Tie Beam & Wall Footings
E. Compaction
F. Basecoarse
a. Manual
b. by Equipment
G. Soil Poisoning
H. Polyethelene sheets

cu.m.
cu.m.
cu.m.

175.00
140.00
295.00
265.00
480.00
350.00
(By Administration)

cu.m.
cu.m.
sq.m.
cu.m.
sq.m.

120.00
85.00
37.50
325.00
37.50

110.00
65.00
30.00
285.00
30.00

cu.m.
cu.m.
sq.m.
sq.m.

120.00
85.00
13.50
10.75

110.00
65.00
10.00
7.50

SCOPE OF WORKS
I. PVC Waterstop
J. Chipping
a. From 0.01-0.10
b. From 0.11-0.20
K. Pouring/Concreting
a. Floor beams, Slab & columns
i. Pumpcrete
ii. Jobmix
iii. Ready mix
b. Columns-(Job mix)
c. Wall footings (Job mix)
d. Shearwall / Retaining Walls
i. Pumpcrete
ii. Ready Mix
iii. Job mix
e. Roof beams, Gutter & Parapet
i. Pumpcrete
ii. Job mix
iii. Ready mix
f. Footings, Pedestals & Tie Beams
i. Pumpcrete
* Volume < 200.00 cu.m.
* Volume = 200-300 ; 300-400 ; 400 & above cu.m.
ii. Ready mix
* Using Buggy
* Direct Pouring
* Volume < 200.00 cu.m.
* Volume = 200-300 ; 300-400 ; 400 & above cu.m.
iii. Job mix
g. Dentils (All levels)
i. Pumpcrete
ii. Job mix
h. Slab on Fill/Pavement
i. Job mix
ii. Ready mix
* Using Buggy
* Direct Pouring
iii. Pumpcrete
i. Curbs & Gutter
i. Ready mix
ii. Job mix
j. Lintel Beams, Stiff. Columns & counters
k. Stair
i. Pumpcrete
ii. Job mix
l. Cistern, Septic Tank, etc.
i. Pumpcrete
ii. Job mix
L. Cutting of Prestress Concrete Piles
M. Trimming of Mechanically Excavated Soil

SMALL
SCALE
16.00

MEDIUM
SCALE
10.00

lm.
lm.

14.50
30.00

12.50
25.00

cu.m.
cu.m.
cu.m.
cu.m.
cu.m.

150.00
650.00
450.00
800.00
750.00

135.00
600.00
375.00
700.00
650.00

cu.m.
cu.m.
cu.m.

150.00
500.00
800.00

135.00
435.00
700.00

cu.m.
cu.m.
cu.m.

300.00
800.00
650.00

225.00
700.00
550.00

cu.m.
cu.m.

115.00

130.00
85.00

cu.m.

350.00

275.00

cu.m.
cu.m.
cu.m.

0.00
105.00
700.00

120.00
80.00
600.00

cu.m.
cu.m.

235.00
900.00

200.00
750.00

cu.m.

465.00

375.00

cu.m.
cu.m.
cu.m.

350.00
150.00
145.00

300.00
130.00
125.00

cu.m.
cu.m.
cu.m.

425.00
700.00
900.00

375.00
620.00
800.00

cu.m.
cu.m.

160.00
650.00

135.00
600.00

cu.m.
cu.m.
pp

185.00
1,350.00
500.00

150.00
1,000.00
350.00

UNITS
lm.

SCOPE OF WORKS
a. Manual
b. by Equipment
N. Cutting of Concrete using Concrete Saw
O. Cutting of Concrete Sheet Piles
P. Cutting of Bored Piles

UNITS
sq.m.
sq.m.
lm.
pp
pp

SMALL
SCALE
120.00
100.00
55.00
300.00
1,800.00

MEDIUM
SCALE
110.00
85.00
45.00
250.00
1,500.00

lft.
lft.
lft.
pc.
pc.
sq.m.

6.50
6.00
18.50
135.00
235.00
75.00

5.50
5.00
15.00
120.00
200.00
65.00

cu.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
cu.m.
cu.m.
lm.
lot
lot

1,750.00
40.00
30.00
35.00
45.00
35.00
40.00
25.00
45.00
20.00
20.00
15.00
60.00
25.00
65.00
20.00
30.00
25.00
45.00

1,000.00
35.00
25.00
30.00
35.00
30.00
35.00
20.00
35.00
15.00
15.00
10.00
45.00
20.00
50.00
15.00
25.00
20.00
35.00
1,200.00
350.00
40.00

VI. TINSMITHRY WORKS


A. Long span Coloroof
a. Using G.I. Straps
b. Using Roof Nails
B. Plain G.I.Shts.on roof vents
C. Ridge rolls,Flashings & Gutters
D. Ducts for Exhaust Fans
E. Roof Insulation
VII. DEMOLITION / DISMANTLING
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.
S.
T.
U.
V.
W.
X.

Concrete
CHB Walls
Corr. G.I. Sheets
Asbestos Roofing
Steel Roof Framing
Wooden Roof Framing
Wooden Floor Framing
Steel Windows
Doors
Double Wall Partition
Ceiling
Gutter & Flashing
Chipping of Floor topping
Cabinets,counters & shelves
Chipping of tiles
Scraping of vinyl tiles
Wood parquet
Chipping of Synthetic Finish
Alum. Framed Glass
Blasting of Footings (by Dynamite)
Blasting of Walls (by Dynamite)
Cutting of Concrete
Electrical
Plumbing

NOTES :
All tools,equipments,scaffolding installation,accessories,hauling & other miscellaneous
shall be shouldered by the sub-contractors.
Hauling costs are included in above unit costs up to fourth floor if it will be done
starting to ground floor,however if works started from third or fourth floor,

SMALL
MEDIUM
SCOPE OF WORKS
UNITS
SCALE
SCALE
additional hauling cost will be given to the subcontractors.
For High Rise Building, Hauling shall be done by Tower Crane but with the help of Subcon labor.
Add 10% VAT to all labor unit costs only.
Add 5%-10% to all labor unit costs if work is outside Metro-Manila. (Optional)
Add 10% to all Materials supplied by the Sub-contractors.
All unit cost includes deliveries within Metro-Manila only.
(Painting) All lineal meters shall be computed once,(ex.Z-bar & sq.bar=total length=lm)
New unit costs are based on a minimum salary of P250.00/day
New unit costs are based if material is within the periphery of the building,if not
make an additional hauling costs to be computed by PE.
All items not included in above items of work shall be the responsibility of the Project
Engineer to compute and award to the contractors.
Formworks Unit Costs are based on A-Frames & Eco-forms to be used,when scaffold use is
lumber add an additional of P10.00 per sq.m. of beams,slabs,Shearwall or RC Walls.
All unit costs are based on the standard construction procedures,any actual works that
deviates on standard shall be the responsibility of the PE concerned.
Differentiating Small to Medium and Large Scale construction shall be the responsibility
of the Project Job Captain involved.
Bar Bender & Bar Cutter are not the obligation of the Company but if provided, repair & maintenance
shall be shouldered by subcon.
C O N S U MAB LE S :
^^^^^^^^^^ ^^^^^^^^^^^^^^ ^^^^^^^^^^^^^^^
BF
Nails =
-------------------- = No. of kegs.
40 X 45

Total bft. =

Vt x 192
-------------------- (For Ftb, Lintel beams & Stiff.columns)
2.40

Vt x 192
-------------------- (for all other structures)
1.60
Wt
G.I. Wires #16 =
--------------------------------------65x45

Total bft. =

(For Big Scale Projects)

SCOPE OF WORKS

UNITS

SMALL
SCALE

MEDIUM
SCALE

G.I. Wires #16 =

Wt
--------------------------------------60x45

(For Medium Scale Projects)

G.I. Wires #16 =

Wt
--------------------------------------50x45

(For Small Scale Projects)

LARGE
SCALE

7.00

180.00
175.00
125.00
155.00
145.00
180.00
160.00
180.00
185.00
155.00
160.00
200.00
185.00
160.00
195.00
65.00
150.00
40.00
35.00
plus 15.00
Stripping
40.00
40.00
35.00
40.00
40.00

LARGE
SCALE
45.00
45.00
40.00
50.00
40.00
40.00

4.00
7.00
10.00
14.00
15.00
18.50
22.50
25.00

f P 5.00/sq.m.
P15.00/sq.m.
45.00

22.50
35.00
32.50
30.00
35.00

20.00
27.50
50.00
60.00
50.00
150.00
225.00
125.00
300.00
350.00
105.00
10.50
135.00
135.00
160.00

LARGE
SCALE
95.00
125.00
15.00
17.50
5.00

140.00
125.00
160.00
65.00
65.00
55.00
95.00
100.00
17.50
8.50
140.00
75.00
85.00

materials)
10.50
22.50

14.50
130.00
100.00
95.00
125.00
120.00
125.00
120.00

LARGE
SCALE
120.00
135.00
125.00

130.00
135.00
60.00
80.00
125.00
85.00
95.00
80.00
55.00
25.00
175.00

175.00
220.00
205.00
130.00

165.00
210.00
95.00
65.00
70.00

50.00
90.00

LARGE
SCALE
60.00
105.00
180.00
210.00

200.00
185.00
170.00
180.00
160.00
140.00
140.00
55.00
180.00
170.00
130.00
150.00
140.00
130.00
170.00
95.00
175.00
185.00
265.00
50.00
325.00
280.00
260.00
260.00
240.00
350.00
165.00
140.00

20.00
45.00
30.00
40.00
320.00

LARGE
SCALE
250.00
220.00
150.00
150.00
250.00
275.00

2.30
2.45
2.50
2.60
2.50
3.20
4.25
2.75
3.25
4.00
3.00
5.00
3.50
3.50
3.50
4.00
15.00

120.00
230.00
300.00

85.00
45.00
25.00
275.00
25.00
85.00
45.00
7.50
5.00

LARGE
SCALE
7.50
10.00
20.00

125.00
500.00
325.00
650.00
600.00
125.00
375.00
650.00
200.00
650.00
525.00

65.00
220.00
0.00
65.00
550.00
165.00
700.00
325.00
275.00
120.00
120.00
325.00
600.00
700.00
125.00
550.00
135.00
750.00
300.00

LARGE
SCALE
80.00
65.00
40.00
150.00
1,200.00

5.00
4.50
12.50
110.00
165.00
50.00

750.00
25.00
20.00
25.00
30.00
20.00
30.00
15.00
25.00
10.00
12.50
7.50
35.00
15.00
35.00
10.00
20.00
15.00
30.00

LARGE
SCALE

LARGE
SCALE

e Projects)

rojects)

R.C.Ramos Construction
SUB-CONTRACTORS LABOR UNIT COSTS

SCOPE OF WORKS

I.

LAYOUT OF THE BUILDING

II.
CARPENTRY WORKS
A. Formworks
1. Using Lumber (incl.stripping,formoil application & nail ext.)
a. Columns/Pedestal
i.Spiral
ii.Tied
b. Footing Tie Beams & Pile Caps
c. Floor Beams
d. Floor Slab
e. Floor Beams (Above 4.00m high)
f. Floor Slab (Above 4.00m high)
g. Roof Beams
h. Gutter w/ parapet
i. Roof Deck (if coverage is not the same as floor slabs below)
j. Shearwalls
k. Stair & Bleacher
l. Dentils
m. Parapet
n. Waffles
o. Stair on Fill
p. Lintel Beams & Stiff. Columns
q. Pavement
r. Slab on Fill
s. When forms used are scrap wood & lumber
2. Using Steel Forms
a. Columns/Pedestal
i.Spiral
ii.Tied
b. Footing Tie Beams & Pile Caps
c. Floor Beams
d. Floor Slab
e. Floor Beams (Above 4.00m high)

UNITS

sq.m.

7.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
lm.
sq.m.
lm.
lm.

180.00
175.00
125.00
155.00
145.00
180.00
160.00
180.00
185.00
155.00
160.00
200.00
185.00
160.00
195.00
65.00
150.00
40.00
35.00
plus 15.00
Stripping

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

40.00
40.00
35.00
40.00
40.00
45.00

f. Floor Slab (Above 4.00m high)


g. Roof Beams
h. Gutter w/ parapet
i. Roof Deck (if coverage is not the same as floor slabs below)
j. Shearwalls
3. H-Frames Installation/Dismantling only (Steel Scaffoldings)
a. Steel Scaffoldings
i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers
v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers
b. If H-Frame is to rest on soil
i. For Compacted Soil
ii. For Muddy/Loose Soil
c. Supporting Steel Deck
4. Retouching, Grinding & Preparation (Ready to accept Paints)
a. Columns
b. Beams
c. Slabs
d. Walls
e. Parapets
B. Door Jambs Installation
a. On Double Walls
b. On Concrete Walls
C. Window Jambs Installation
a. On Double Walls
b. On Concrete Walls
D. Steel Window Installation
E. Flush Door Installation
F. Panel Door Installation
G. Bar Door Installation
H. Steel Door Installation
Single Leaf
Double Leaf
I. Steel Louver Installation
J. Wooden Roof Framing
a. Fabrication & Installation
K. Double Wall Partitions
a. 1/4"thk.Ply.on 2"x3"studs(V-cut & Open Joint)
b. Narra Ply.on 2"x3"studs(V-cut & Open Joint)
c. Narra Ply.on 2"x3"studs(Open Joint @ 0.30)
d. Other Kind of D/W Partition
e. 1/4"thk.Marine Plywood Panelling w/o groove

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

45.00
40.00
50.00
40.00
40.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

4.00
7.00
10.00
14.00
15.00
18.50
22.50
25.00

sq.m.
sq.m.
sq.m.

45.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

22.50
35.00
32.50
30.00
35.00

lm.
lm.

20.00
27.50

sq.m.
sq.m.
sq.m.
set
set
set

50.00
60.00
50.00
150.00
225.00
125.00

set
set
sq.m.

300.00
350.00
105.00

bft.

10.50

sq.m.
sq.m.
sq.m.

135.00
135.00
160.00

sq.m.

95.00

f. 1/4"thk.Narra Plywood Panelling w/ groove


L. Baseboard
a. Kd. Tanguile
b. Narra
c. Vinyl
M. Ceiling
a. 1/4" Plywood Ceiling (Ordinary)
i. w/ ceiling truss
ii. w/o ceiling truss
b. T&G, S-cut & V-cut
c. Installation of Accoustic board
d. Ceiling Board only
i. w/ V-cut
ii.Open joint
e. Covelights (Fabrication & Installation)
i.On Ordinary Ceiling
ii.On Wood Moulding(Fiberglass Ceiling)
iii.Alum.T-runner Installation
iiii. Diffuser Installation
f. Other Ceiling
i. Ord.Plywood ceiling @ Eaves
ii. Wood Slats w/ Insect Screen (W=0.30m)
N. Installation of wooden stair handrail (narra)
O. Cabinets & Shelves
P. Quarter C Moulding
Q. 2" x 3" Wood Mouldings
R. Others
Hardwares
Door Lockset
Door Closer
Flush & Head Bolts
Panic Exit Device
Push Plates
Door Stops

sq.m.

125.00

lm.
lm.
lm.

15.00
17.50
5.00

sq.m.
sq.m.
sq.m.
sq.m.

140.00
125.00
160.00
65.00

sq.m.
sq.m.

65.00
55.00

set
set
lm.
set

95.00
100.00
17.50
8.50

sq.m.
140.00
lm.
75.00
lm.
85.00
by negotiation (30 % of materials)
lm.
10.50
lm.
22.50

set
set
set
set
set
set

III. MASONRY WORKS (incl. hauling)


A. Hauling of materials if far from bldg.
B. CHB Laying
a. 8" CHB
b. 6" CHB
c. 4" CHB
C. CHB Laying @ Roof Beams (needs Scaffolding)
a. 6" CHB
b. 4" CHB
D. CHB Laying (irregular shape)
a. 6" CHB
b. 4" CHB
E. Plain Cement Plaster Finish
a. by area (interior CHB walls)

sq.m.

14.50

sq.m.
sq.m.
sq.m.

130.00
100.00
95.00

sq.m.
sq.m.

125.00
120.00

sq.m.
sq.m.

125.00
120.00

sq.m.

120.00

F.

G.

H.

I.

b. by area (ext. CHB walls)needs scaffolding


c. by area (conc.walls & parapet)
i. Ordinary Concrete Walls (Interior Walls)
ii. Exterior Concrete & CHB Walls & Parapets (w/ scaffoldings)
1. Ground to Fourth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
2. Fourth to Seventh Floor
Up to 2-1/2" thk.
For every add'l. 1" thk.
3. Seventh to Tenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
4. Tenth to Fourteenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
5. Above Fourteenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
d. by area (irregular CHB walls)
e. Overhead
f. by lm.(vertical & horizontal)
g. by lm.(overhead)
h. Spiral columns
i. Beam plastering (sides)
j. Beam plastering (bottom)
k. Tool Joint Finish
l. Kustura Finish
m. Exterior Grooves
n. Plastering of Louver Blocks
Boracay Finish (incl.liston,& other acc.)
a. By area
i.Flooring
ii.Walls
* w/scaffolding
* w/o scaffolding
b. by lm
Pebble Washout Finish(incl.liston & other acc.)
a. by area
i.Flooring
ii.Walls
b. by lm
Stair Nosing Installation (incl. preparation)
a. Brass, Angular & Checkered Plate
b. Carborandum Strip
c. Vinyl Stair Nosing
Topping
a. Straight to finish
b. Plain Cement finish
Stair Tread Topping

sq.m.

135.00

sq.m.

125.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
lm.
lm.
lm.
lm.
lm.
sq.m.
sq.m.
lm.
sq.m.

130.00
135.00
60.00
80.00
125.00
85.00
95.00
80.00
55.00
25.00
175.00

sq.m.

175.00

sq.m.
sq.m.
lm.

220.00
205.00
130.00

sq.m.
sq.m.
lm.

165.00
210.00
95.00

lm.
lm.
lft.

65.00
70.00

sq.m.
sq.m.
lm.

50.00
90.00
60.00

J.

K.

L.
M.
N.

O.

P.
Q.

c. Red cement w/ V-cut


d. Deck Topping (including Cant,etc.)
e. Ramp Topping w/ Groove
Tileworks
a. Glazed Tiles incl. rough plaster
i. 4-1/4"x4-1/4" Glazed Tiles
ii. 4"x8"
-doiii. Others
b. Vit.floor tiles incl. topping
i. 4-1/4"x4-1/4" Glazed Tiles
ii. 4"x8"
-doiii. Others
c. Mosaic floor tiles incl. topping
d. Tile fittings
Brickworks
a. 1"x2"x8"Red bricks
b. 4"x8"Clay tiles
c. 12"x12"Red cement tiles
d. 8"x8"Clay tiles
e. 6"x6"x12"Louver blocks
f. 4"x12"x12"Decorative blocks
g. Mactan stone
h. Adobe blocks
i. Ashlar stone
j. Urra Tiles
* Ordinary Layout
* Extra-ordinary Layout (w/ many cuts)
Sandblasting
Corduroy finish
Marble Finish / Granite Finish
a. 4"x8"Marble tiles
b. Marble @ Walls
c. Marble @ Floors
d. Marble @ Counters
e. Opening for Lavatory
f. Rounding of Edges
g. Faucet Hole
h. Granite @ Walls including Anchors (Dry Anchors)
i. Granite @ Floors
j. Granolithic Flooring
Retouching
a. by area
i. Walls
ii.Exposed slab
b. by lm.(corners only)
c. Curbs & Gutter
Rip-rapping
Synthetic Finish
a. by area
i. w/ scaffolding

sq.m.
sq.m.
sq.m.

105.00
180.00
210.00

sq.m.
sq.m.
sq.m.

200.00
185.00
170.00

sq.m.
sq.m.
sq.m.
sq.m.
lm.

180.00
160.00
140.00
140.00
55.00

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

180.00
170.00
130.00
150.00
140.00
130.00
170.00
95.00
175.00

sq.m.
sq.m.
sq.m.
sq.m.

185.00
265.00
50.00
325.00

sq.m.
sq.m.
sq.m.
lm.
set
lm.
set
sq.m.
sq.m.
sq.m.

280.00
260.00
260.00
240.00
350.00
165.00
140.00

sq.m.
sq.m.
lm.
lm.
cu.m.

20.00
45.00
30.00
40.00
320.00

sq.m.

250.00

ii. w/o scaffolding


b. by lm
R. Keyhole Pattern Bricks
S. 4"x8"Tiles w/ Pebble Washout Pattern
T. 200 x 200 Glass Blocks
IV.
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
Q.

REINFORCING BARS (incl.supply of M-gas & Oxygen)


Footing & Tie Beams
Columns & Pedestal
Floor beams
Floor slab
Shearwalls
Slab on fill
Lavatory counter
Roof Beams
Gutter & Parapet
Wall footings
Stair
Lintel beams & Stiff.columns
Parapet
Dentils (including welding)
Waffles
Welded Wire Mesh

V.

LABOR WORKS

A. Excavation
a. Ordinary Soil
* Bulk
* Manual
b. Adobe
c. Dewatering
B. Backfilling
a. Manual
b. by Equipment
C. Levelling
D. Excavation of Ftg. Tie Beam & Wall Footings
E. Compaction
F. Basecoarse
a. Manual
b. by Equipment
G. Soil Poisoning
H. Polyethelene sheets
I. PVC Waterstop
J. Chipping
a. From 0.01-0.10
b. From 0.11-0.20
K. Concreting
i. Pumpcrete
ii. Job mix

sq.m.
lm.
sq.m.
sq.m.
sq.m.

220.00
150.00
150.00
250.00
275.00

kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
sq.m.

2.30
2.45
2.50
2.60
2.50
3.20
4.25
2.75
3.25
4.00
3.00
5.00
3.50
3.50
3.50
15.00

cu.m.
cu.m.
cu.m.

120.00
230.00
300.00

cu.m.
cu.m.
sq.m.
cu.m.
sq.m.

85.00
45.00
25.00
275.00
25.00

cu.m.
cu.m.
sq.m.
sq.m.
lm.

85.00
45.00
7.50
5.00
7.50

lm.
lm.

10.00
20.00

cu.m.
cu.m.

80.00
700.00

L. Cutting of Prestress Concrete Piles


M. Trimming of Mechanically Excavated Soil
a. Manual
b. by Equipment
N. Cutting of Concrete using Concrete Saw
O. Cutting of Concrete Sheet Piles
P. Cutting of Bored Piles

pp

300.00

sq.m.
sq.m.
lm.
pp
pp

80.00
65.00
40.00
150.00
1,500.00

lft.
lft.
lft.
pc.
pc.
sq.m.

5.00
4.50
12.50
110.00
165.00
50.00

cu.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
cu.m.
cu.m.
lm.
lot
lot

750.00
25.00
20.00
25.00
30.00
20.00
30.00
15.00
25.00
10.00
12.50
7.50
35.00
15.00
35.00
10.00
20.00
15.00
30.00

VI. TINSMITHRY WORKS


A. Long span Coloroof
a. Using G.I. Straps
b. Using Roof Nails
B. Plain G.I.Shts.on roof vents
C. Ridge rolls,Flashings & Gutters
D. Ducts for Exhaust Fans
E. Roof Insulation
VII. DEMOLITION / DISMANTLING
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.
S.
T.
U.
V.
W.
X.

Concrete
CHB Walls
Corr. G.I. Sheets
Asbestos Roofing
Steel Roof Framing
Wooden Roof Framing
Wooden Floor Framing
Steel Windows
Doors
Double Wall Partition
Ceiling
Gutter & Flashing
Chipping of Floor topping
Cabinets,counters & shelves
Chipping of tiles
Scraping of vinyl tiles
Wood parquet
Chipping of Synthetic Finish
Alum. Framed Glass
Blasting of Footings (by Dynamite)
Blasting of Walls (by Dynamite)
Cutting of Concrete
Electrical
Plumbing

NOTES :
All tools,equipments,scaffolding installation,accessories,hauling & other miscellaneous
shall be shouldered by the sub-contractors.

Hauling costs are included in above unit costs up to fourth floor if it will be done
starting to ground floor,however if works started from third or fourth floor,
additional hauling cost will be given to the subcontractors.
For High Rise Building, Hauling shall be done by Tower Crane but with the help of Subcon labor.
Add 10% VAT to all labor unit costs only.
Add 5%-10% to all labor unit costs if work is outside Metro-Manila. (Optional)
Add 10% to all Materials supplied by the Sub-contractors.
All unit cost includes deliveries within Metro-Manila only.
(Painting) All lineal meters shall be computed once,(ex.Z-bar & sq.bar=total length=lm)
New unit costs are based on a minimum salary of P250.00/day
New unit costs are based if material is within the periphery of the building,if not
make an additional hauling costs to be computed by PE.
All items not included in above items of work shall be the responsibility of the Project
Engineer to compute and award to the contractors.
Formworks Unit Costs are based on A-Frames & Eco-forms to be used,when scaffold use is
lumber add an additional of P10.00 per sq.m. of beams,slabs,Shearwall or RC Walls.
All unit costs are based on the standard construction procedures,any actual works that
deviates on standard shall be the responsibility of the PE concerned.
Differentiating Small to Medium and Large Scale construction shall be the responsibility
of the Project Job Captain involved.
Bar Bender & Bar Cutter are not the obligation of the Company but if provided, repair & maintenance
shall be shouldered by subcon.
C O N S U MAB LE S :
^^^^^^^^^^ ^^^^^^^^^^^^^ ^^^^^^^^^^^^^^^
BF
Nails =
-------------------- = No. of kegs.
40 X 45

Total bft. =

Vt x 192
-------------------- (For Ftb, Lintel beams & Stiff.columns)
2.40

Vt x 192
-------------------- (for all other structures)
1.60
Wt
G.I. Wires #16 =
---------------------------------------

Total bft. =

65x45

G.I. Wires #16 =

Wt
--------------------------------------60x45

G.I. Wires #16 =

Wt
--------------------------------------50x45

n (30 % of materials)

maintenance

A. GENERAL REQUIREMENTS
A.1 Mobilization/Demobilization
a. Mobilization
5 t/l @
b. Demobilization
5 t/l @

5,000.00

25,000.00

5,000.00

25,000.00

A.2 Bonds and Insurance


a. Performance Bond (20%)
TOTAL COST =
750,000,000.00 = A
Premium
=
A x 0.20 x 0.005
=
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

b. Surety Bond (Downpayment)


Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Municipality Tax
=

1,050,000.00
131,266.50
70.00
50.00
105,000.00
52,500.00
1,155.00
1,340,041.50

1,125,000.00
140,641.50
70.00
50.00
112,500.00
56,250.00
1,237.50
1,435,749.00

=
=
=

20%
A x 0.20 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011

=
=

c. Surety ,Warranty & Guarantee Bond (Retention) 30%


Premium
=
A x 0.30 x 0.005
=
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

d. Bid Bond 5%
Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=

750,000.00
93,766.50
70.00
50.00
75,000.00
37,500.00
825.00
957,211.50

=
=
=

A x 0.05 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=

262,500.00
32,829.00
70.00
50.00
26,250.00

Premium Tax
Municipality Tax

=
=

Premium x 0.05
Premium x 0.0011

e. Contractor's All Risk Insurance 100%


Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Municipality Tax
=

=
=
P

13,125.00
288.75
335,112.75

1,875,000.00
234,391.50
70.00
50.00
187,500.00
93,750.00
2,062.50
2,392,824.00

87,500.00
10,954.00
70.00
50.00
8,750.00
4,375.00
96.25
111,795.25

A x 0.0025
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011

=
=

A = 20,000,000.00
f. Comprehensive General Liability Insurance 100%
Premium
= For 3 m = 10,000.00
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

=
=
=

A.3 Building and Occupancy Permits


a. Building Permit
54,730.62 sq.m. @

45.00 /sq.m.

2,462,877.90

b. Occupancy Permit
54,730.62 sq.m.

25.00 /sq.m.

1,368,265.50

c. Sidewalk & Road Permit


300.00 sq.m.

750.00 /sq.m.

225,000.00

150.00 sq.m. @

500.00 /cu.m.

75,000.00

d. Temfacil Permit

A.4 Temporary Facilities


a. Contractor's Field Office
b. CM Temporary Office
c. Bunkhouses
d. Kitchen
e. CR
f. Billboard
g. Safety Net
h. Portalet
A.5 Power and Water Consumptions

40.00 sq.m. @

3,500.00

400.00 sq.m. @
36.00 sq.m. @
18.00 sq.m. @

500.00
500.00
10,000.00

5.00 rental/mo.

7,500.00

=
=
=
=
=
=
=
=

140,000.00
250,000.00
200,000.00
18,000.00
180,000.00
120,000.00
37,500.00

Thi
insu
ma
nat

T
in
p
a

a.
b.
c.
c.

Power Consumptions
Water Consumptions
Deepwell Construction
Telephone Bill

A.6 Equipment Utilization


a. Tower Crane
b. Lifting Machine
c. Garbage Chute
d. Tamaraw

10,000.00
2,500.00

for
for

19.00 mos. =
19.00 mos. =

2,000.00

for

19.00 mos. =

180,000.00
54,000.00
30,000.00
108,000.00

for
for
for
for

16.00
8.00
8.00
4.00

mos.
mos.
mos.
mos.

190,000.00
47,500.00
100,000.00
38,000.00

=
=
=
=

2,880,000.00
432,000.00
240,000.00
432,000.00

B. SITEWORKS
Item 102-2
Grade Line Cut (Ord. Soil)
A. Equipment
1.00 - Bulldozer D80A-12, 180 HP
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1.00
5.00
2.00
3.00

B. Labor

C. Output

- Foreman
- Laborer
- Operator
- Driver
VAT, 10%
Sub-total

100.00 cu.m./hr.

D. Fuel & Oil


Bulldozer
Payloader
Dumptruck

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
DIRECT UNIT COST
Item Backfilling
104-3
& Compaction

COST

24.125 lit.
10.00 lit.
27.75 lit.

=
=
=

117.38 liters
11.74 liters

=
P

P
45.91 /cu.m.

A. Equipment
3 - Dump Truck
1 - Road Roller
1 - Payloader
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

65.00 cu.m./hr.

D. Fuel & Oil


Dump Truck
Road Roller
Payloader

27.75 lit.
14.00 lit.
2.28 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

99.53 liters
9.95 liters

T O TAL

COST

LABOR UNIT COST

65.00
55.04

*****
DIRECT UNIT COST =

55.04 /cu.m.

Item 102-3
Excavation (Adobe)
A. Equipment
1.00 - Backhoe
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1.00 - Foreman
5.00 - Laborer
2.00 - Operator

B. Labor

3.00 - Driver
VAT, 10%
Sub-total
C. Output

60.00 cu.m./hr.

D. Fuel & Oil


Backhoe
Payloader
Dumptruck

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL

COST

24.125 lit.
10.00 lit.
27.75 lit.

=
=
=

117.38 liters
11.74 liters

DIRECT UNIT COST =

P
71.93 /cu.m.

TRIMMING
A. Labor
1.00 - Foreman
5.00 - Laborer
VAT, 10%
B. Output

2.00 sq.m./hr.

DIRECT UNIT COST =

64.97 /sq.m.

Item Aggregate
200-1
Sub-Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

50.00 cu.m./hr.

D. Fuel & Oil


Road Grader
Road Roller
Water Truck

8.00 lit.
14.00 lit.
5.44 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

27.44 liters
2.74 liters

E. Materials, Aggregate Sub-Base Coarse with 20% shrinkage factor


60.00 cu.m. Agg.Sub-base Coarse
Sub-total
T O TAL

COST

DIRECT UNIT COST =

P
332.97 /cu.m.

Item Aggregate
201-1
Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

50.00 cu.m./hr.

D. Fuel & Oil


Road Grader
Road Roller
Water Truck

8.00 lit.
14.00 lit.
5.44 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

27.44 liters
2.74 liters

E. Materials, Aggregate Sub-Base Coarse with 20% shrinkage factor

60.00 cu.m. Agg.Base Coarse


Sub-total
T O TAL

COST

DIRECT UNIT COST =

P
356.97 /cu.m.

Item Portland
311-2
Cement Concrete Pavement PCCP

0.15 mthick)

Assume Quantity
L
W
A
V

=
=
=
=

100.00
6.00
600.00
90.00

m.
m.
sq.m.
cu.m.

A. Materials:
a. Concrete Mix delivered @ jobsite
90.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12

6.00 in.

For 100.00m Preparation


No.of Center forms & key =
No.of Side forms
=
Total no.of bft.
=
For
100.00 m.preparation =
For 3 times usage
=
Sub-total
c.Steel bars
i.Dowels: 5/8"dia. x0.76m @ 0.75 moc
Wt/pc. = 0.76x1.57
=
No.of pcs. = 100.00/0.75 =
For width,every 100.00m (4 pcs.)
(100/100)x4x2
=
Total no.of dowels =
Wt
=
ii.Steel Pins : 1/2"dia. x 0.20m @ 0.75 moc
Wt.of/pc. = 0.20 x 0.888 =
No. of Pins =(100/0.75)x2 =
For 5 times usage=
Total Wt
=
Sub-total
d.Diamond Blade

10.00 bft.
3.33
10.00

444.33
333.33
777.67
777.67
259.22 bft.

1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.

0.18
266.67
53.33
9.47

kgs.
pcs.
pcs.
kgs.

Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=
No. of blades = 133.33/350 =
Sub-total

133.33
0.38 blades

e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total

0.0040 m
467.33 m
1.88 cu.m.
0.44 MT

f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total

266.67
88.89
2.22 kgs.

g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost

21.43 gals.

Output = 77.00 cu.m./day or 513.00 sq.m./day


No.of days = 3,000/513.00 6
=.00
days
B. Manpower:
1.00
2.00
2.00
4.00
5.00
7.00

- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost

220.00 /day
175.00
175.00
175.00
175.00
145.00

6.00
6.00
6.00
6.00
6.00
6.00

56.25 /day
60.00 /day
1,200.00 /day

4.00
4.00
1.00

C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost

T O TAL

COST

DIRECT UNIT COST =

P
361.31 /sq.m.

Item Portland
311-2
Cement Concrete Pavement PCCP

0.2 mthick)

Assume Quantity
L
W
A
V

=
=
=
=

100.00
6.00
600.00
120.00

m.
m.
sq.m.
cu.m.

A. Materials:
a. Concrete Mix delivered @ jobsite
120.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12

6.00 in.

For 100.00m Preparation


No.of Center forms & key =
No.of Side forms
=
Total no.of bft.
=
For
100.00 m.preparation =
For 3 times usage
=
Sub-total
c.Steel bars
i.Dowels: 5/8"dia. x0.76m @ 0.75 moc
Wt/pc. = 0.76x1.57
=
No.of pcs. = 100.00/0.75 =
For width,every 100.00m (4 pcs.)
(100/100)x4x2
=
Total no.of dowels =
Wt
=
ii.Steel Pins : 1/2"dia. x 0.20m @ 0.75 moc
Wt.of/pc. = 0.20 x 0.888 =
No. of Pins =(100/0.75)x2 =
For 5 times usage=
Total Wt
=
Sub-total
d.Diamond Blade
Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=

10.00 bft.
3.33
10.00

444.33
333.33
777.67
777.67
259.22 bft.

1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.

0.18
266.67
53.33
9.47

kgs.
pcs.
pcs.
kgs.

133.33

No. of blades = 133.33/350 =


Sub-total

0.38 blades

e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total

0.0040 m
467.33 m
1.88 cu.m.
0.44 MT

f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total

266.67
88.89
2.22 kgs.

g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost

21.43 gals.

Output = 77.00 cu.m./day or 513.00 sq.m./day


No.of days = 3,000/513.00 6
=.00
days
B. Manpower:
1.00
2.00
2.00
4.00
5.00
7.00

- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost

220.00 /day
175.00
175.00
175.00
175.00
145.00

6.00
6.00
6.00
6.00
6.00
6.00

56.25 /day
60.00 /day
1,200.00 /day

4.00
4.00
1.00

C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
DIRECT UNIT COST =

COST

=
P

P
456.31 /sq.m.

ITEMConcrete
502
Curbs & Gutter
1.Materials:
a.Forms : 100 bft.(Good for 60.00 m)
b.C.W.Nails:20 kgs.(Good for 60.00 m)
c.Concrete Volume = (0.15x0.15)+(0.00x0.00)=0.025 cu.m.
Cement = 0.09 x 9 =
Sand = 0.09 x 0.50 =
Gravel = 0.09 x 1.00 =
Sub-total

1.67 @
0.33

24.00
24.00

0.81
0.05
0.09

125.00
200.00
440.00

A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total

50.00

1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total

27.50
21.875
18.125

2.Manpower:

3.Fuel and Oil


Plate Compactor
Oil,10 % of fuel =
Sub-total
4.Output =

1.05 liters
0.11 liters

10.00
45.00

20.00 lm./hr.
Direct Cost =

11.21 /lm.

B.Placing and removal of Forms

1.Manpower:
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
2.Output =

27.500
21.875
18.125

11.00 lm./hr.
Direct Cost =

14.38 /lm.

C.Pouring and Finishing


1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total

45.00
60.00

2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total

27.50
21.88
18.13

3.Fuel and Oil


1-Bagger Mixer
Concrete Vibrator

3.00
1.05
4.05 liters
0.41 liters

Oil,10 % of fuel =
Sub-total
4.Output =

10.00
45.00

10.00 lm./hr.
Direct Cost =

DIRECT UNIT COST =

ITEMConcrete
601
Sidewalk
Assume Quantity = 100.00 sq.m.
Thickness =
0.10 m
1.Materials:
a.Forms : 4 bft./sq.m. x 100/3
Used 3 times
b.C.W.Nails:0.02 kgs./bft.x4x100 =
Cement = 10.00 x 9 =
Sand = 10.00 x 0.45 =
Gravel = 10.00 x 0.90 =
Sub-total

33.24 /lm.
P

256.67 /lm.

Volume =
133.33 @
8.00
90.00
4.50
9.00

10.00
24.00
24.00
125.00
200.00
440.00

A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total

50.00 /day

1.00

220.00 /day
175.00
145.00

1.00
1.00
1.00

2.Manpower:
1.00 Foreman
1.00 Operator
5.00 Laborers

VAT, 10%
Sub-total
3.Fuel and Oil
Vibrator Plate =
Oil,10 % of fuel =
Sub-total
4.Output =

1.05 liters
0.11 liters

10.00
45.00

20.00 lm./hr.

B.Placing and removal of Forms


1.Manpower:

Output =

60.00 sq.m./day
220.00 /day
175.00
145.00

1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
C.Pouring and Finishing
1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total

1.75
1.75
1.75

45.00 /hr.
60.00

2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total

220.00 /day
175.00
145.00

1.75
1.75
1.75

3.00
1.05
4.05 liters
0.41 liters

10.00
45.00

3.Fuel and Oil


1-Bagger Mixer
Concrete Vibrator
Oil,10 % of fuel =
Sub-total
DIRECT UNIT COST =

250.93 /sq.m.

C. MASONRY WORKS
a. 6" CHB (750 psi) Load Bearing
a.Materials
12.50 pcs. 6" CHB (Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand

@
@

10.50
125.00
200.00

3.00 kgs. Grade 33 Rebars


0.05 Ga.# 16 GI Wires

b. 4" CHB (750 psi) Load Bearing


a.Materials
12.50 pcs. 4"CHB (Load Bearing)
0.54 bags Cement
0.05 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

c. 6" CHB (400 psi) Non-Load Bearing


a.Materials
12.50 pcs. 6" CHB (Non-Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

d. 4" CHB (400 psi) Non-Load Bearing


a.Materials
12.50 pcs. 4"CHB (Non-Load Bearing)
0.54 bags Cement
0.05 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

e. 6"x6"x12" Louver Blocks


a.Materials
24.00
0.49
0.04
2.25
0.04

pcs. 6"x6"x12" Louver Blocks


bags Cement
cu.m. Sand
kgs. Grade 33 Rebars
Ga.# 16 GI Wires

10.30
125.00
200.00
12.00
36.00
M=

@
@

7.80
125.00
200.00
12.00
36.00
M=

@
@

7.50
125.00
200.00
12.00
36.00
M=

@
@

10.50
125.00
200.00
12.00
36.00
M=

@
@

f. Lightweight Concrete (fc' = 1,200 psi) Density = 80 to 100 pcf


a.Materials (Job Mixed)
8.00 bag Cement (Portland)
(8-18 bags/cm)
4.00 bag Perlite Concrete Grade (12 kgs./bag)
4.00 bag Light Aggregates (Dead Gravel)
0.68 cu.m. Sand (24 cu.ft.)
0.70 gal. Air Entraining Agent
1.00 bag Fibrin (2 lbs./bag)
b. Labor (Job Mixed Concrete)

12.00
36.00
M=

125.00
130.00
120.00
200.00
135.00
600.00
M=
L=

For One (1) Bagger Mixer (V = 0.125 cu.m.)


1.00 bag Portland Cement
1/2 bag Perlite Concrete Grade
3.00 cu.ft. Sand
1/2 pint Air Entraining Agent
1/8 bag Fibrin
g. Glass Block (8" x 8")
a. Materials
25.00 pcs. 8" x 8" Glass Block
12.50 kls. ABC Grout

150.00
30.00
M=

125.00
200.00
M=

125.00
200.00
M=

125.00
200.00
900.00
M=

125.00
200.00
900.00
M=

125.00
200.00
80.00
M=

FLOOR FINISHES
a. Patterned Cement Finish
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand

b. Plain Cement Floor Topping


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand

c. Plain Cement Floor Topping w/ Hardener


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
0.100 bag Floor Hardener
4 kls./sq.m.- 40 kls. /bag
d. Straight to Finish Floor Topping w/ Hardener
a.Materials
0.140 bag Cement(Portland)
0.011 cu.m. Sand
0.100 bag Floor Hardener
4 kls./sq.m.- 40 kls. /bag
e. Red Cement Topping
a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
0.250 kgs. Red Cement

f. Beige Peeble Washout Finish(By Area)

a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding

125.00
200.00
3.50

ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles

g. Beige Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.147 bag Cement(Portland)
0.011 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Beige Pebbles

h. Black Peeble Washout Finish(By Area)


a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Black Pebbles

i. Black Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.147 bag Cement(Portland)
0.011 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Black Pebbles

j. Beige Peeble Washout Finish(By Area) Deck w/ wire mesh


a.Materials
i.Scratch Coat
0.700 bag Cement(Portland)
0.054 cu.m. Sand
1.000 sq.m. Wire Mesh
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)

125.00
90.00
M=

125.00
200.00
125.00
90.00
M=

125.00
200.00
3.50
125.00
45.00
M=

125.00
200.00
125.00
45.00
M=

125.00
200.00
45.00
3.50
125.00

1.250 cans #10 Beige Pebbles

k. Plain Cement Finish w/ Peeble Washout Nosing


a.Materials
i.Scratch Coat
0.168 bag Cement(Portland)
0.013 cu.m. Sand
1.640 lft.kd Tang.moulding
ii.Final Coat
0.031 bag Cement(Portland)
0.063 cans #10 Ass. Pebbles

l. Peeble Washout Finish w/ 8"x8" Tile Pattern


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.625 bag Cement(Portland)
4.000 pcs.8"x8"Floor Tiles
0.100 kls. ABC Grout
1.250 cans #10 Ass. Pebbles

l. 12"x12" Vigan Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.219 bag Cement(Portland)
12.000 pcs.12"x12"Vigan Tiles
0.250 kls. Colored Cement
0.438 cans #10 Ass. Pebbles

m. 8" x 8" Vit. Floor Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.150 bag Cement(Portland)
9.000 pcs.8"x8"Vit. Floor Tiles
0.375 kls. ABC Grout
0.300 cans #10 Ass. Pebbles

90.00
M=

125.00
200.00
3.50
125.00
45.00
M=

125.00
200.00
125.00
14.00
30.00
45.00
M=

125.00
200.00
125.00
10.00
80.00
65.00
M=

125.00
200.00
125.00
14.00
30.00
45.00
M=

n. 25mm thk. Granite Slab


a.Materials
0.490
0.037
1.000
10.000

bag Cement (Portland)


cu.m. Sand
sq.m. Granite Slab
% Consumables
Materials
Labor

o. 300x300 Ceramic Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.150 bag Cement(Portland)
9.000 pcs.12"x12"Ceramic Tiles
0.375 kls. ABC Grout
0.300 cans #10 Ass. Pebbles

125.00
200.00
4,500.00

125.00
200.00
125.00
35.00
30.00
45.00
M=

p. Vinyl Tiles (Tajima)


a. Materials
12.00 pcs. 12"x12"x3.0 mmthk. Vinyl Tiles
0.060 gal. Vinyl Adhesives

28.00
550.00

12.00 pcs. 12"x12"x3.0 mmthk. Vinyl Tiles


0.060 gal. Vinyl Adhesives

24.00
550.00

r. 200x200 Non skid Tiles


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
25.000 pcs.8"x8"Non skid Tiles

125.00
200.00
11.00
M=

s. Concrete Paving Block (Keyhole Pattern)


a.Materials
0.490 bag Cement(Portland)
0.037 cu.m. Sand
40.000 pcs. Keyhole Pattern Bricks

125.00
200.00
10.50
M=

125.00

q. Vinyl Tiles (Matico)


a. Materials

t. 150x150 Ceramic Unglazed Floor Tiles


a.Materials
0.490 bag Cement(Portland)

0.500 kls. ABC Grout


0.037 cu.m. Sand
45.000 pcs.6"x6"Floor Tiles

u. 101x101 Vitrified Floor Tiles (Piedra Tiles)


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
90.000 pcs.4-1/4"x4-1/4"Floor Tiles

v. 200x200 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
25.000 pcs.8"x8"Floor Tiles

w. 100x200 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
50.000 pcs.4"x8"Floor Tiles

x. 450x450 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
5.000 pcs.18"x18"Floor Tiles

y. 300x300 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
12.000 pcs.12"x12"Floor Tiles

z. 300x300 Cotto Homogeneous Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand

30.00
200.00
10.50
M=

125.00
30.00
200.00
6.00
M=

125.00
30.00
200.00
14.00
M=

125.00
30.00
200.00
10.50
M=

125.00
30.00
200.00
75.00
M=

125.00
30.00
200.00
28.00
M=

125.00
30.00
200.00

12.000 pcs.12"x12"Floor Tiles

aa. 300x300 Synthetic Granite Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
12.000 pcs.12"x12"Floor Tiles

ab. 600x600mm x19mm thk. Marble @ Counters w = 0.60m


a. Materials
0.294 bag Cement (Portland)
0.022 cu.m. Sand
0.600 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor

150.00
M=

125.00
30.00
200.00
120.00
M=

125.00
200.00
900.00

ac. 600x600mm x19mm thk. Marble @ Counters (Splashboard) w = 0.35m


a. Materials
0.172 bag Cement (Portland)
@
0.013 cu.m. Sand
0.350 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ad. 600x600mm x19mm thk. Marble @ Counters (Splashboard) w = 0.20m
a. Materials
0.098 bag Cement (Portland)
@
0.007 cu.m. Sand
0.200 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ae. 600x600mm x19mm thk. Marble @ Counters (Fascia Board) w = 0.15m
a. Materials
0.074 bag Cement (Portland)
@
0.006 cu.m. Sand
0.150 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
af. 600x600mm x19mm thk. Marble Slabs
a. Materials
0.490 bag Cement (Portland)

125.00
200.00
900.00

125.00
200.00
900.00

125.00
200.00
900.00

125.00

0.037 cu.m. Sand


1.000 sq.m. 0.60x0.60 Marbles
10.000 % Consumables
Materials
Labor
ag. 600x600mm x19mm thk. Lavatory Sidings w = 0.30m
a. Materials
0.147 bag Cement (Portland)
0.011 cu.m. Sand
0.300 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ah. Plain Cement Floor Topping w/ Chicken Wire Mesh
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand
1.000 sq.m. Chicken Wiremesh

ai. 2"x12" Ceramic Tile Nosing


a. Materials
12.000 pcs. Ceramic Tile nosing
10.000 % Consumables

200.00
950.00

125.00
200.00
900.00

125.00
200.00
45.00
M=

25.00
M=

aj. Expansion Joint and Contraction Joints (1/2"thk.)


a. Materials
3.280 lft. x 1/2"x6" Non-extruding Joint Fiiler (Cork type)
0.081 liter Sealant

ak. Expansion Joint and Contraction Joints (3/4"thk.)


a. Materials
3.280 lft. x 3/4"x6" Non-extruding Joint Fiiler (Cork type)
0.121 liter Sealant

al. Expansion Joint and Contraction Joints (1"thk.)


a. Materials
3.280 lft. x 1"x6" Non-extruding Joint Fiiler (Cork type)
0.161 liter Sealant

WALL FINISHES
a. 300x300 Synthetic Granite
a.Materials

25.00
880.00
M=

50.28
880.00
M=

50.43
880.00
M=

0.450
0.250
0.027
12.000

bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs. 12"x12" Granite Tiles
Materials

b. 101x101 Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
90.000 pcs.4-1/4"x4-1/4"Wall Tiles

c. 100x200 Vit. Wall Tiles


a.Materials
0.450
0.250
0.027
50.000

bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs.4"x8"Wall Tiles

d. 200x200 Ceramic Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
25.000 pcs.8"x8"Wall Tiles

d. 300x300 Ceramic Vit. Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
12.000 pcs.12"x12"Wall Tiles

e. 450x450 Ceramic Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
5.000 pcs.18"x18"Wall Tiles

125.00
30.00
200.00
120.00

125.00
30.00
200.00
2.50
M=

125.00
30.00
200.00
10.50
M=

125.00
30.00
200.00
14.00
M=

125.00
30.00
200.00
28.00
M=

125.00
30.00
200.00
75.00
M=

f. Ordinary Bricks 2"x8"x1/2" (on Exterior Wall)


a.Materials
97.00 pcs. 2"x8"x1/2" Ordinary Bricks

2.50

0.424 bag Cement(Portland)


0.032 cu.m. Sand

1. Exterior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.424 bag Cement(Portland)
0.032 cu.m. Sand

b. Plain Cement Plaster Finish (By Area)RC Walls


a.Materials
0.150 gal. Cement Gum
0.501 bag Cement(Portland)
0.038 cu.m. Sand

2. Interior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.350 bag Cement(Portland)
0.027 cu.m. Sand

b. Plain Cement Plaster Finish (By Area)RC Walls


a.Materials
0.150 gal. Cement Gum
0.420 bag Cement(Portland)
0.032 cu.m. Sand

c. Plain Cement Plaster Finish (By LM) w = 0.50m.


a.Materials
0.245 bag Cement(Portland)
0.019 cu.m. Sand

d. Plain Cement Plaster Finish (By LM) w = 0.30m.


a.Materials
0.147 bag Cement(Portland)
0.011 cu.m. Sand

e. Plain Cement Plaster Finish (By LM) w = 0.15m.


a.Materials
0.074 bag Cement(Portland)
0.006 cu.m. Sand

125.00
200.00
M=

125.00
200.00
M=

208.00
125.00
200.00
M=

125.00
200.00
M=

208.00
125.00
200.00
M=

125.00
200.00
M=

125.00
200.00
M=

125.00
200.00

M=
f. Plain Cement Plaster Finish (By LM) w = 0.60m.
a.Materials
0.294 bag Cement(Portland)
0.022 cu.m. Sand

g. Plain Cement Plaster Finish (By Area) on Louver Blocks


a.Materials
0.054 bag Cement(Portland)
0.004 cu.m. Sand

h. Beige Peeble Washout Finish(By Area)


a.Materials
i.Scratch Coat
0.350 bag Cement(Portland)
0.027 cu.m. Sand
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles

i. Beige Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.105 bag Cement(Portland)
0.008 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Beige Pebbles

125.00
200.00
M=

125.00
200.00
M=

125.00
200.00
3.50
125.00
90.00
M=

125.00
200.00
125.00
90.00
M=

CEILING FINISHES
a. 1/4"thk.Marine Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)
w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@
0.375 pcs. 1/4"x4'x8'Marine Plywood
0.400 kls. Assorted Nails
0.050 gal. Solignum

b. 1/4"thk.Ordinary Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@

24.00
355.00
24.00
525.00
M=

24.00

0.375 pcs. 1/4"x4'x8'Ordinary Plywood


0.400 kls. Assorted Nails
0.050 gal. Solignum

200.00
24.00
525.00
M=

c. 1/2"thk.Gypsum Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 1/2"x4'x8'Gypsum Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

c. 5/8"thk.Gypsum Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 5/8"x4'x8'Gypsum Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

c. 1/2"thk. Ficem Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 1/2"x4'x8' Ficem Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

d. Retouching of Exposed Slab


a.Materials
0.014 bag Cement(Portland)
0.001 cu.m. Sand

e.5/8" thk. RH-90 Non-sagging Acoustic Tiles on Baked Enamel T-runners


a. Materials
13.500 lft. 15/16" Baked enamel T-runners
@
11.500 sq.ft. 5/8" x 24"x24" RH - 90 Non-sagging

f.5/8" thk. Minaboard Fissured Acoustic Tiles on Baked Enamel T-runners


a. Materials
13.500 lft. 15/16" Baked enamel T-runners
@
11.500 sq.ft. 5/8" x 24"x24" Minaboard Fissured

24.00
295.00
24.00
525.00
M=

24.00
296.00
24.00
525.00
M=

24.00
1,150.00
10.50
175.00
M=

125.00
200.00
M=

10.00
22.50
M=

300.00
20.00
M=

g. Cemboard Ceiling on Furring Channel


a. Materials
0.375 pc. 3/16"x4'x8' Cemboard
0.120 pc. x 10' Carrying Channel
0.200 pc. Metal Furring Channel x 12'
0.150 pc. Alum. Wall Angle x 10'
0.040 gal. RM Joint Compound
0.100 gross Buglehead self tapping screw

h. Gypsum Board Ceiling on Furring Channel


a. Materials
0.375 pc. 1/2"x4'x8' Gypsum Board
0.120 pc. x 10' Carrying Channel
0.200 pc. Metal Furring Channel x 12'
0.150 pc. Alum. Wall Angle x 10'
0.013 roll Gypsum Joint Tape
0.040 gal. RM Joint Compound
0.100 gross Buglehead self tapping screw

700.00
175.00
145.00
125.00
250.00
260.00
M=

295.00
175.00
145.00
125.00
300.00
250.00
260.00
M=

1,665.00
12.50
M=

770.00
5.50
137.50
M=

1,665.00
12.50
M=

770.00
5.50
137.50
M=

CONCRETE WORKS
a. Lintel Beams (For 6" CHB)
a. Materials
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
b. Labor
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks

b. Lintel Beams (For 4" CHB)


a. Materials
0.0350 cu.m. Concrete
3.3000 kg. Rebars
0.8000 sq.m. Formworks
b. Labor
0.0350 cu.m. Concrete
3.3000 kg. Rebars
0.8000 sq.m. Formworks

c. Stiffener Columns (For 6" CHB)


a. Materials
0.0250 cu.m. Concrete

1,665.00

2.0000 kg. Rebars


0.3000 sq.m. Formworks

12.50
M=

b. Labor
0.0250 cu.m. Concrete
2.0000 kg. Rebars
0.3000 sq.m. Formworks

d. Stiffener Columns (For 4" CHB)


a. Materials
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks

770.00
5.50
137.50
M=

1,665.00
12.50
M=

770.00
5.50
137.50
M=

275.00
18.125

275.00
18.125

250.00
120.00
Equipment Cost
10% VAT

20.63

b. Labor
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks

Item SP- 3 Hauling Works


a. Rebars
1 ELF
10 Laborers

Production
Unit Cost

=
=

b. Forms
1 ELF
10 Laborers

20,000.00 kgs./day
P

Production
Unit Cost

=
=

Demolition Works
a. Equipment (Demolition)
1.00 Compressor
2.00 Jackhammer

12.00 hrs./day
12.00

0.30 /kg.

12.00 hrs./day
12.00
750.00 sq.m./day
7.88 /sq.m.

b. Manpower
20.00 Laborers

Labor Cost
10% VAT
Total Cost / hr.
Duration =
c. Equipment (Hauling & Disposal)
1.00 Loader
2.00 Dump Truck

Duration =

12 hrs. for 15 days

700.00
500.00
Equipment Cost
10% VAT
6 hrs. for 6 days
Total Cost =

Item SP- 4 Cleaning,Hauling & Disposal of Debris

1 Dumptruck
10 Laborers

8.00 hrs./day
8.00

450.00
18.125

10 times per month for 8 months


Item SP- 5 Dewatering Works
Pump Rental
Fuel
Operator

1.00 hr.

Unit Cost
Item SP - 6 G.I. Sheet Temporary Fence (H = 3.00m)
a. Materials
20.00 bft. Coco Lumber
15.00 lft. Ga. # 26 Pre-painted Corrugated GI Sheets
0.015 kegs CW Nails
0.10 kgs. Roof Nails

Item SP - 7 Protection of Adjacent Properties


a. Materials
30.00 lft. Corr. G.I.Sheets
2.00 pcs.62mm dia. GI Pipes
6.00 pcs. Pipe Clamp
0.25 pc.32mmdia. Plain Round Bars
1.00 pc.10mmdia.
-do2.00 pcs. Coil bolt w/ waler washer
b. Labor (Installation)

50.00
15.00
20.00
=

6.00
40.00
950.00
85.00
Unit Cost =

26.00
525.00
75.00
475.00
45.00
25
Unit Cost (M & L) =

Item SP - 8 Construction Safety Net


a. Materials
For 3.50 x 9 floors x 30.00 =
8.50
950.00
25.00
33.00
b. Labor (Installation)

945.00 sq.m.

lm. Ga. # 12 G.I. Wires


sq.m. Nylon Net (1/4" x 2.00 x 90.00m)
pcs. 10mm x 6.00m Plain Round Bars
pcs. 12mm x 6.00m
-do-

1.50
12.50
45.00
65.00

Unit Cost (M & L) =


Item SP - 9 100mm thk Wall w/ 50mm Rigid Insulation Welded Wire w/ 25mm thk. Plaster on Both Sides
a. Materials
4.00 lm. Carrying Channel
@
58.33
15.00 lm. Furring Channel
40.28
2.20 sq.m. Ga. # 22 Expanded Metal Lathe
140.00
2.50 lm. 16mm dia. Plain Round Bar
25.00
0.75 bag Cement
125.00
0.06 cu.m. Sand
200.00
1.10 sq.m. Rigid Insulation
140.00
Materials
Labor

Morales Shopping Mall


A. Vinyl Tiles

2 x 300 x 300 Vinyl Tiles


Vinyl Adhesive
Armstrong Imperial Series

12.00 pcs.
0.06 gal.

Installation
Polishing

12.00 tiles
12.00 tiles

Vinyl Cove Baseboard


Consumables

B. Plain Cement Floor Topping

3.28 ln.ft.
1.00 lot

23.00
525.00
Materials

3.50
2.40
Sub Total
VAT
Labor

26.50
3.08
Materials
Labor

P
P

Cement
Sand

II. Walls and Wall Finishes


A. 6" CHB Wall
6" CHB 350 psi
Cement
Sand
Grade 33 Rebars
GI Wires

B. 4" CHB Wall


4" CHB 350 psi
Cement
Sand
Grade 33 Rebars
GI Wires

0.70 bags
0.06 cu.m.

12.50
1.05
0.09
2.50
0.04

12.50
0.54
0.04
2.50
0.04

pcs.
bags
cu.m.
kgs.
kgs.

pcs.
bags
cu.m.
kgs.
kgs.

125.00
300.00
Materials
Labor

P
P

7.50
125.00
300.00
12.20
30.20
Materials
Labor

P
P

7.30
125.00
300.00
12.20
30.20
Materials
Labor

P
P

125.00
300.00
80.00
148.00
Materials
Labor

P
P

125.00
300.00
80.00
Materials
Labor

P
P

C. Exterior Plastering

Cement
Sand
ME 602 Mortar Enhancer
Sealopruf Integral Waterproofing

0.50
0.06
0.13
0.05

bags
cu.m.
liters
gal

D. Interior Plastering

Cement
Sand
ME 602 Mortar Enhancer

0.30 bags
0.03 cu.m.
0.08 liters

C.MATERIALS

50,000.00

4,179,910.00
0.5573%

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
45.
46.
47.

Premium Fuel
Diesel
Lubricating Oil
Gravel Fill
Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
CW Nails
Cement
Gravel
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)

This insurance is used to


insured construction
materials damaged by
natural calamity

This insurance is used to


insured critical adjacent
properties which might be
affected during construction.

4,131,143.40

945,500.00

Assume 1.50m per personnel/laborer


Assume 2.00m per unit

375,500.00

48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.

300x300x3.0mm Vinyl Tiles (Matico)


16x600x600 RH-90 Non-sagging Acoustic
16x600x600 Minaboard Fissured Acousti
19x600x600 Marble Slab incl. Polishing
CDS Marble
ABC Grout
6"x6" Louver Blocks
Beige Pebbles # 10
Beige Pebbles # 5
Black Pebbles # 10
Black Pebbles # 5
Assorted Pebbles
CW Nails
Concrete Paving Blocks (Keyhole Pattern
Solignum
Vinyl Adhesive
Ga. # 16 GI Wires
Kd Tanguile Moulding
Suspension Grid System
Boulders
1/2" x 1200 x 2400 Gypsum Board
5/8" x 1200 x 2400 Gypsum Board
1/2" x 1200 x 2400 Ficem Board
x 10' Carrying Channel
x 12' Furring Channel
x 10' Alum. Wall Angle
Gypsum Joint Tape
Ready Mix Joint Compound
Self Tapping Screw
4.5 x 1200 x 2400 Ficem Board
2mm x 100mm Flexible Vinyl Baseboard
3mm x 1/2" Brass Strip
Hanger rods
Chicken Wire Mesh
2"x12" Ceramic Tile Nosing
1/2"x3'x10' Joint Filler (Cork type)
3/4"x3'x10'
-do1"x3'x10'
-doSealant
Perlite Concrete Grade (CG) (12 kgs./bag
Air Entraining Agent (AEA)
Fibrin (2 lbs./ bag)
Light Aggregates (Dead Gravel)
8" x 8" Glass Block
300x300 Vigan Tiles
19x150 Wood Parquet
Flarefloor Rubber Tiles
3/4" Ord. Plywood
2"x8"x1/2" Ordinary Bricks

98.
99.
100.

3,984,000.00
A.EQUIPMENTS:

1,000.00 =
500.00 =
400.00 =
=
=

27.50
18.13
21.88
20.00

=
=
=
=
=

1,000.00
500.00
1,200.00
24.41
272.44
2,996.85 /hr.

27.50
90.63
43.75
60.00
22.19
244.06 /hr.

24.125
10.00
83.25
117.38 liters
7.00 =
45.00 =

4,590.72 /hr.

821.63
528.19
1,349.81 /hr.

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.

Dozer D8H w/ ripper


Payloader
Dump trucks
Grader
Roller
Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump
Screeder
Vibrator
Concrete Cutter
1-Bagger Mixer
Chainsaw
Portalift
Concrete Breaker
Backhoe
Trencher
B.MANPOWER:

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.

Foreman
Leadman
Timekeeper
Carpenter
Mason
Steelman
Laborer
Floater
Mixer Operator
Painter
Welder
HE Operator
Driver
Screeder Operator

400.00 =
350.00 =
500.00 =
=
=

27.50
18.13
21.88
20.00

=
=
=
=
=

1,200.00
350.00
500.00
16.02
206.60
2,272.62 /hr.

27.50
54.38
43.75
20.00
14.56
160.19 /hr.

83.25
14.00
2.28
99.53 liters
7.00 =
45.00 =

696.71
447.89
1,144.60 /hr.

3,577.40 /hr.
/CU.M.
/CU.M.

750.00 =
500.00 =
400.00 =
=
=

750.00
500.00
1,200.00
24.41
247.44
2,721.85 /hr.

27.50 =
18.13 =
21.88 =

27.50
90.63
43.75

20.00 =
=

60.00
22.19
244.06 /hr.

24.125
10.00
83.25
117.38 liters
7.00 =
45.00 =

821.63
528.19
1,349.81 /hr.

4,315.72 /hr.

27.50 =
18.13 =
=

27.50
90.63
11.81
129.94 /hr.

400.00 =
350.00 =
300.00 =
=
=

400.00
350.00
300.00
16.02
106.60
1,172.62 /hr.

27.50
18.13
21.88
20.00

=
=
=
=
=

27.50
54.38
43.75
20.00
14.56
160.19 /hr.

8.00
14.00
5.44
27.44 liters
7.00 =
45.00 =

192.08
123.48
315.56 /hr.

250.00 =

15,000.00
15,000.00 /hr.

16,648.37 /hr.

400.00 =
350.00 =
300.00 =
=
=

27.50
18.13
21.88
20.00

=
=
=
=
=

400.00
350.00
300.00
16.02
106.60
1,172.62 /hr.

27.50
54.38
43.75
20.00
14.56
160.19 /hr.

8.00
14.00
5.44
27.44 liters
7.00 =
45.00 =

192.08
123.48
315.56 /hr.

270.00 =

16,200.00
16,200.00 /hr.

17,848.37 /hr.

1,900.00

171,000.00
171,000.00

24.00 =

6,221.33
6,221.33

12.00 =

2,035.20

12.00 =

113.66
2,148.86

m.

days

day
day
day

10,400.00 =

3,961.90
3,961.90

13,500.00 =

5,976.45
5,976.45

24.00 =

53.33
53.33

40.00 =

857.14
857.14
P 190,219.03

317.03

1,320.00
2,100.00
2,100.00
4,200.00
5,250.00
6,090.00
2,106.00
23,166.00
23,166.00

38.61

450.00
240.00
2,400.00
309.00
3,399.00
3,399.00

5.67

=
=
=
=
=
=
=

=
=
=
=

216,784.03

1,900.00

m.

228,000.00
228,000.00

24.00 =

6,221.33
6,221.33

12.00 =

2,035.20

12.00 =

113.66
2,148.86

10,400.00 =

3,961.90
3,961.90

13,500.00 =

5,976.45
5,976.45

24.00 =

53.33
53.33

40.00 =

857.14
857.14
P 247,219.03

412.03

1,320.00
2,100.00
2,100.00
4,200.00
5,250.00
6,090.00
2,106.00
23,166.00
23,166.00

38.61

450.00
240.00
2,400.00
309.00
3,399.00
3,399.00

5.67

days

=
=
=
=
=
=
=

day
day
day

=
=
=
=

273,784.03

=
=

40.00
8.00

=
=
=
P

101.25
9.00
39.60
197.85

=
=
P

50.00
5.00
55.00

=
=
=
=

27.50
21.88
90.63
14.00
154.00

=
=
P

10.50
4.73
15.23

=
=
=
=
P

27.50
43.75
72.50
14.38
158.13

=
=
=
P

45.00
60.00
10.50
115.50

=
=
=
=
P

27.50
43.75
72.50
14.38
158.13

=
=
P

40.50
18.23
58.73

cu.m.
=

3,200.00

=
=
=
=
P

192.00
11,250.00
900.00
3,960.00
19,502.00

195.02

day

=
=
P

50.00
5.00
55.00

day

=
=
=

220.00
175.00
725.00

days
days
days

days
days
days

=
=
=

=
P

0.00
1,120.00

=
=
P

10.50
4.73
15.23

=
=
=
=
P

385.00
612.50
1,015.00
201.25
2,213.75

=
=
=
P

45.00
60.00
10.50
115.50

=
=
=
=
P

385.00
612.50
1,015.00
0.00
2,012.50

=
=
P

40.50
18.23
58.73

131.25
127.50
18.19

=
=
P

36.00
1.80
314.74 /sq.m.

=
=
=
=
=
P

128.75
67.50
9.63
36.00
1.80
243.68 /sq.m.

=
=
=
=
=
P

97.50
127.50
18.19
36.00
1.80
280.99 /sq.m.

=
=
=
=
=
P

93.75
67.50
9.63
36.00
1.80
208.68 /sq.m.

=
=
=
=
=
P

252.00
61.25
7.40
27.00
1.26
348.91 /sq.m.

=
=
=
=
=
=
P
P

1,000.00
520.00
480.00
136.05
94.50
600.00
2,830.55 /cu.m.
770.00 /cu.m.

=
=
P

3,750.00
375.00
4,125.00 /cu.m.

=
=
P

87.50
10.70
98.20 /sq.m.

=
=
P

70.00
8.56
78.56 /sq.m.

=
=
=
P

70.00
8.56
90.00
168.56 /sq.m.

=
=
=
P

17.50
2.14
90.00
109.64 /sq.m.

=
=
=
P

70.00
8.56
20.00
98.56 /sq.m.

=
=
=
=
=
P

61.25
7.49
10.50
78.13
112.50
269.87 /sq.m.

=
=

18.38
2.25

=
=
P

23.44
33.75
77.81 /lm.

=
=
=

61.25
7.49
10.50

=
=
P

78.13
56.25
213.62 /sq.m.

=
=

18.38
2.25

=
=
P

23.44
16.88
60.93 /lm.

=
=
=
=

87.50
10.70
45.00
10.50

78.13

=
P

112.50
344.33 /sq.m.

=
=
=

21.00
2.57
5.74

=
=
P

3.91
2.81
36.03 /lm.

=
=

70.00
8.56

=
=
=
=
P

=
=
=
=
=
=
P

=
=
=
=
=
=
P

78.13
56.00
3.00
56.25
271.94 /lm.

70.00
8.56
27.34
120.00
20.00
28.44
274.34 /lm.

70.00
8.56
18.75
126.00
11.25
13.50
248.06 /lm.

=
=
=
=
P
P

=
=

61.25
7.49
4,500.00
450.00
5,018.74 /lm.
220.00 /lm.

70.00
8.56

=
=
=
=
P

18.75
315.00
11.25
13.50
437.06 /lm.

=
=
P

336.00
33.00
369.00 /sq.m.

=
=
P

288.00
33.00
321.00 /sq.m.

=
=
=
P

70.00
8.56
275.00
353.56 /sq.m.

=
=
=
P

61.25
7.49
420.00
488.74 /sq.m.

61.25

=
=
=
P

15.00
7.49
472.50
556.24 /sq.m.

=
=
=
=
P

61.25
15.00
7.49
540.00
623.74 /sq.m.

=
=
=
=
P

61.25
15.00
7.49
350.00
433.74 /sq.m.

=
=
=
=
P

61.25
15.00
7.49
525.00
608.74 /sq.m.

=
=
=
=
P

61.25
15.00
7.49
375.00
458.74 /sq.m.

=
=
=
=
P

61.25
15.00
7.49
336.00
419.74 /sq.m.

=
=
=

61.25
15.00
7.49

=
P

1,800.00
1,883.74 /sq.m.

=
=
=
=
P

61.25
15.00
7.49
1,440.00
1,523.74 /sq.m.

=
=
=
=
P
P

36.75
4.49
540.00
54.00
635.24 /lm.
200.00 /lm.

=
=
=
=
P
P

21.44
2.62
315.00
31.50
370.56 /lm.
185.00 /lm.

=
=
=
=
P
P

12.25
1.50
180.00
18.00
211.75 /lm.
185.00 /lm.

=
=
=
=
P
P

9.19
1.12
135.00
13.50
158.81 /lm.
185.00 /lm.

61.25

=
=
=
P
P

7.49
950.00
95.00
1,113.74 /lm.
185.00 /lm.

=
=
=
=
P
P

18.38
2.25
270.00
27.00
317.62 /lm.
185.00 /lm.

=
=
=
P

87.50
10.70
45.00
143.20 /sq.m.

=
=
P

300.00
30.00
330.00 /sq.m.

=
=
P

82.00
70.94
152.94 /lm.

=
=
P

164.93
106.41
271.33 /lm.

=
=
P

165.42
141.87
307.29 /lm.

=
=
=
=
P

56.25
7.50
5.35
1,440.00
1,509.10 /lm.

=
=
=
=
P

56.25
7.50
5.35
225.00
294.10 /sq.m.

=
=
=
=
P

56.25
7.50
5.35
525.00
594.10 /sq.m.

=
=
=
=
P

56.25
7.50
5.35
350.00
419.10 /sq.m.

=
=
=
=
P

56.25
7.50
5.35
336.00
405.10 /sq.m.

=
=
=
=
P

56.25
7.50
5.35
375.00
444.10 /sq.m.

242.50

=
=
P

52.94
6.47
301.91 /sq.m.

=
=
P

52.94
6.47
59.41 /sq.m.

=
=
=
P

31.20
62.56
7.65
101.41 /sq.m.

=
=
P

43.75
5.35
49.10 /sq.m.

=
=
=
P

31.20
52.50
6.42
90.12 /sq.m.

=
=
P

30.63
3.75
34.37 /lm.

=
=
P

18.38
2.25
20.62 /lm.

=
=

9.19
1.12

10.31 /lm.

=
=
P

36.75
4.49
41.24 /lm.

=
=
P

6.75
0.80
7.55 /lm.

=
=
=
=
=
P

43.75
5.35
10.50
78.13
112.50
250.23 /sq.m.

=
=

13.13
1.61

=
=
P

23.44
33.75
71.92 /lm.

=
=
=
=
P

300.00
133.13
9.60
26.25
468.98 /sq.m.

300.00

=
=
=
P

75.00
9.60
26.25
410.85 /sq.m.

=
=
=
=
P

240.00
110.63
9.60
26.25
386.48 /sq.m.

=
=
=
=
P

240.00
111.00
9.60
26.25
386.85 /sq.m.

=
=
=
=
P

240.00
431.25
4.20
8.75
684.20 /sq.m.

=
=
P

1.75
0.21
1.96 /sq.m.

=
=
P

135.00
258.75
393.75 /sq.m.

=
=
P

4,050.00
230.00
4,280.00 /sq.m.

=
=
=
=
=
=
P

262.50
21.00
29.00
18.75
10.00
26.00
367.25 /sq.m.

=
=
=
=
=
=
=
P

110.63
21.00
29.00
18.75
3.75
10.00
26.00
219.13 /sq.m.

=
=
=
P

62.44
40.00
102.44 /l.m.

=
=
=
P

28.88
17.60
89.38
135.85 /l.m.

=
=
=
P

58.28
41.25
99.53 /l.m.

=
=
=
P

26.95
18.15
110.00
155.10 /l.m.

41.63

=
=
P

25.00
66.63 /l.m.

=
=
=
P

19.25
11.00
41.25
71.50 /l.m.

=
=
=
P

49.95
25.00
74.95 /l.m.

=
=
=
P

23.10
11.00
82.50
116.60 /l.m.

3,300.00
2,610.00
5,910.00

3,300.00
2,610.00
5,910.00

/hr.
/hr.

250.00
240.00
490.00
49.00
539.00 /hr.

/hr.

412.50

412.50
41.25
453.75
992.75 /hr.
180.00 hours
178,695.00
/hr.
/hr.

700.00
1,000.00
1,700.00
170.00
1,870.00 /hr.
36.00
67,320.00
246,015.00

3,600.00
1,740.00
5,340.00
427,200.00

/hr.
/hr.
/hr.

=
=
=

50.00
15.00
20.00
85.00 /hr./pump

=
=
=
=

120.00
600.00
14.25
8.50
742.75 /lm.

=
=
=
=
=
=
=
ost (M & L) =

780.00
1,050.00
450.00
118.75
45.00
50.00
997.50
3,491.25 /lm.

say

=
=
=
=
=

3,500.00 /lm.

12.75
11,875.00
1,125.00
2,145.00
7,578.88
22,736.63
24.06
25.00 /sq.m.

ost (M & L) =

=
=
=
=
=
=
=

233.33
604.17
308.00
62.50
93.75
12.00
154.00
1,467.75 /sq.m.
733.88 /sq.m.

276.00
31.50
307.50
42.00
28.80
70.80
7.08
77.88
86.92
3.08
90.00
22.00

87.50
16.50
104.00
104.00

93.75
131.25
27.00
30.50
1.21
283.71
110.00

91.25
67.50
12.00
30.50
1.21
202.46
104.00

62.50
16.50
10.00
7.40
96.40
139.00

37.50
9.90
6.00
53.40
115.50

UNIT COST
Premium Fuel
Lubricating Oil

Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade

Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)

10.00
7.00
45.00
440.00
150.00
250.00
270.00
1,900.00
24.00
12.00
40.00
13,500.00
10,400.00
24.00
125.00
440.00
300.00
200.00
355.00
375.00
38.00
17.50
10.50
10.30
7.80
7.50
80.00
900.00
10.50
6.00
35.00
28.00
10.50
14.00
75.00
150.00
4,500.00
11.00
120.00
10.50
14.00
2.50
28.00
75.00
4.00
25.00
6.00
28.00

/lit.
/lit.
/lit.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bft.
/kg.
/gal.
/MT
/pc.
/kl.
/bag
/cu.m.
/cu.m.
/cu.m.
/pc.
/pc.
/bft.
/pc.
/pc.
/pc.
/pc.
/pc.
/kl.
/kl.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.

300x300x3.0mm Vinyl Tiles (Matico)


16x600x600 RH-90 Non-sagging Acoustic Board
16x600x600 Minaboard Fissured Acoustic Board
19x600x600 Marble Slab incl. Polishing
CDS Marble
ABC Grout
6"x6" Louver Blocks
Beige Pebbles # 10
Beige Pebbles # 5
Black Pebbles # 10
Black Pebbles # 5
Assorted Pebbles
Concrete Paving Blocks (Keyhole Pattern)
Vinyl Adhesive
Ga. # 16 GI Wires
Kd Tanguile Moulding
Suspension Grid System
1/2" x 1200 x 2400 Gypsum Board
5/8" x 1200 x 2400 Gypsum Board
1/2" x 1200 x 2400 Ficem Board
x 10' Carrying Channel
x 12' Furring Channel
x 10' Alum. Wall Angle
Gypsum Joint Tape
Ready Mix Joint Compound
Self Tapping Screw
4.5 x 1200 x 2400 Ficem Board
2mm x 100mm Flexible Vinyl Baseboard
3mm x 1/2" Brass Strip
Hanger rods
Chicken Wire Mesh
2"x12" Ceramic Tile Nosing
1/2"x3'x10' Joint Filler (Cork type)
3/4"x3'x10'
-do1"x3'x10'
-do2,200.00/pack (2.50 liters)
Perlite Concrete Grade (CG) (12 kgs./bag)
Air Entraining Agent (AEA)
Fibrin (2 lbs./ bag)
Light Aggregates (Dead Gravel)
8" x 8" Glass Block
300x300 Vigan Tiles
19x150 Wood Parquet
Flarefloor Rubber Tiles
3/4" Ord. Plywood
2"x8"x1/2" Ordinary Bricks

24.00
90.00
80.00
950.00
900.00
30.00
10.50
90.00
90.00
45.00
45.00
65.00
24.00
10.50
525.00
550.00
36.00
3.50
10.00
300.00
295.00
296.00
1,150.00
175.00
145.00
125.00
300.00
250.00
260.00
700.00
23.00
30.00
25.00
45.00
25.00
1,500.00
3,017.00
3,026.00
880.00
130.00
135.00
600.00
120.00
150.00
10.00
60.00
1,300.00
1,100.00
2.50

/pc.
/pc.
/pc.
/sq.m.
/sq.m.
/kl.
/pc.
/can
/can
/can
/can
/can
/kl.
/pc.
/gal.
/gal.
/kl.
/lft.
/lft.
/cu.m.
/pc
/pc
/pc
/pc
/pc
/pc
/roll
/gal.
/gross
/pc.
/lft.
/lft.
/pc.
/sq.m.
/pc.
/pc.
/pc.
/pc.
/liter
/bag
/gal.
/bag
/bag
/pc.
/pc.
/sq.ft.
/sq.m.
/pc.
/pc.

275.00 /bag

38pcs./sq.m.

Labor
25.00 /sq.ft.
80.00 /sq.m.

RENTALS

Dozer D8H w/ ripper


Dump trucks

Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump

Concrete Cutter
1-Bagger Mixer

Concrete Breaker

1,000.00
500.00
400.00
400.00
350.00
300.00
300.00
20.00
50.00
20.00
56.25
60.00
1,200.00
45.00
20.00
75.00
900.00
750.00
500.00

/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.

DAILY RATES

Timekeeper

Mixer Operator

HE Operator
Screeder Operator

220.00
200.00
150.00
175.00
175.00
185.00
145.00
175.00
160.00
185.00
185.00
175.00
160.00
175.00

/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day

A. GENERAL REQUIREMENTS
A.1 Mobilization/Demobilization
a. Mobilization
5 t/l @
b. Demobilization
5 t/l @

5,000.00

25,000.00

5,000.00

25,000.00

A.2 Bonds and Insurance


a. Performance Bond (20%)
TOTAL COST =
750,000,000.00 = A
Premium
=
A x 0.20 x 0.005
=
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

b. Surety Bond (Downpayment)


Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Municipality Tax
=

1,050,000.00
131,266.50
70.00
50.00
105,000.00
52,500.00
1,155.00
1,340,041.50

1,125,000.00
140,641.50
70.00
50.00
112,500.00
56,250.00
1,237.50
1,435,749.00

=
=
=

20%
A x 0.20 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011

=
=

c. Surety ,Warranty & Guarantee Bond (Retention) 30%


Premium
=
A x 0.30 x 0.005
=
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

d. Bid Bond 5%
Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=

750,000.00
93,766.50
70.00
50.00
75,000.00
37,500.00
825.00
957,211.50

=
=
=

A x 0.05 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=

262,500.00
32,829.00
70.00
50.00
26,250.00

Premium Tax
Municipality Tax

=
=

Premium x 0.05
Premium x 0.0011

e. Contractor's All Risk Insurance 100%


Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Municipality Tax
=

=
=
P

13,125.00
288.75
335,112.75

1,875,000.00
234,391.50
70.00
50.00
187,500.00
93,750.00
2,062.50
2,392,824.00

87,500.00
10,954.00
70.00
50.00
8,750.00
4,375.00
96.25
111,795.25

A x 0.0025
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011

=
=

A = 20,000,000.00
f. Comprehensive General Liability Insurance 100%
Premium
= For 3 m = 10,000.00
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

=
=
=

A.3 Building and Occupancy Permits


a. Building Permit
54,730.62 sq.m. @

45.00 /sq.m.

2,462,877.90

b. Occupancy Permit
54,730.62 sq.m.

25.00 /sq.m.

1,368,265.50

c. Sidewalk & Road Permit


300.00 sq.m.

750.00 /sq.m.

225,000.00

150.00 sq.m. @

500.00 /cu.m.

75,000.00

d. Temfacil Permit

A.4 Temporary Facilities


a. Contractor's Field Office
b. CM Temporary Office
c. Bunkhouses
d. Kitchen
e. CR
f. Billboard
g. Safety Net
h. Portalet
A.5 Power and Water Consumptions

40.00 sq.m. @

3,500.00

400.00 sq.m. @
36.00 sq.m. @
18.00 sq.m. @

500.00
500.00
10,000.00

5.00 rental/mo.

7,500.00

=
=
=
=
=
=
=
=

140,000.00
250,000.00
200,000.00
18,000.00
180,000.00
120,000.00
37,500.00

Thi
insu
ma
nat

T
in
p
a

a.
b.
c.
c.

Power Consumptions
Water Consumptions
Deepwell Construction
Telephone Bill

A.6 Equipment Utilization


a. Tower Crane
b. Lifting Machine
c. Garbage Chute
d. Tamaraw

10,000.00
2,500.00

for
for

19.00 mos. =
19.00 mos. =

2,000.00

for

19.00 mos. =

180,000.00
54,000.00
30,000.00
108,000.00

for
for
for
for

16.00
8.00
8.00
4.00

mos.
mos.
mos.
mos.

190,000.00
47,500.00
100,000.00
38,000.00

=
=
=
=

2,880,000.00
432,000.00
240,000.00
432,000.00

B. SITEWORKS
Item 102-2
Grade Line Cut (Ord. Soil)
A. Equipment
1.00 - Bulldozer D80A-12, 180 HP
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1.00
5.00
2.00
3.00

B. Labor

C. Output

- Foreman
- Laborer
- Operator
- Driver
VAT, 10%
Sub-total

100.00 cu.m./hr.

D. Fuel & Oil


Bulldozer
Payloader
Dumptruck

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
DIRECT UNIT COST
Item Backfilling
104-3
& Compaction

COST

24.125 lit.
10.00 lit.
27.75 lit.

=
=
=

117.38 liters
11.74 liters

=
P

P
45.91 /cu.m.

A. Equipment
3 - Dump Truck
1 - Road Roller
1 - Payloader
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

65.00 cu.m./hr.

D. Fuel & Oil


Dump Truck
Road Roller
Payloader

27.75 lit.
14.00 lit.
2.28 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

99.53 liters
9.95 liters

T O TAL

COST

LABOR UNIT COST

65.00
55.04

*****
DIRECT UNIT COST =

55.04 /cu.m.

Item 102-3
Excavation (Adobe)
A. Equipment
1.00 - Backhoe
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1.00 - Foreman
5.00 - Laborer
2.00 - Operator

B. Labor

3.00 - Driver
VAT, 10%
Sub-total
C. Output

60.00 cu.m./hr.

D. Fuel & Oil


Backhoe
Payloader
Dumptruck

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL

COST

24.125 lit.
10.00 lit.
27.75 lit.

=
=
=

117.38 liters
11.74 liters

DIRECT UNIT COST =

P
71.93 /cu.m.

TRIMMING
A. Labor
1.00 - Foreman
5.00 - Laborer
VAT, 10%
B. Output

2.00 sq.m./hr.

DIRECT UNIT COST =

64.97 /sq.m.

Item Aggregate
200-1
Sub-Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

50.00 cu.m./hr.

D. Fuel & Oil


Road Grader
Road Roller
Water Truck

8.00 lit.
14.00 lit.
5.44 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

27.44 liters
2.74 liters

E. Materials, Aggregate Sub-Base Coarse with 20% shrinkage factor


60.00 cu.m. Agg.Sub-base Coarse
Sub-total
T O TAL

COST

DIRECT UNIT COST =

P
332.97 /cu.m.

Item Aggregate
201-1
Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

50.00 cu.m./hr.

D. Fuel & Oil


Road Grader
Road Roller
Water Truck

8.00 lit.
14.00 lit.
5.44 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

27.44 liters
2.74 liters

E. Materials, Aggregate Sub-Base Coarse with 20% shrinkage factor

60.00 cu.m. Agg.Base Coarse


Sub-total
T O TAL

COST

DIRECT UNIT COST =

P
356.97 /cu.m.

Item Portland
311-2
Cement Concrete Pavement PCCP

0.15 mthick)

Assume Quantity
L
W
A
V

=
=
=
=

100.00
6.00
600.00
90.00

m.
m.
sq.m.
cu.m.

A. Materials:
a. Concrete Mix delivered @ jobsite
90.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12

6.00 in.

For 100.00m Preparation


No.of Center forms & key =
No.of Side forms
=
Total no.of bft.
=
For
100.00 m.preparation =
For 3 times usage
=
Sub-total
c.Steel bars
i.Dowels: 5/8"dia. x0.76m @ 0.75 moc
Wt/pc. = 0.76x1.57
=
No.of pcs. = 100.00/0.75 =
For width,every 100.00m (4 pcs.)
(100/100)x4x2
=
Total no.of dowels =
Wt
=
ii.Steel Pins : 1/2"dia. x 0.20m @ 0.75 moc
Wt.of/pc. = 0.20 x 0.888 =
No. of Pins =(100/0.75)x2 =
For 5 times usage=
Total Wt
=
Sub-total
d.Diamond Blade

10.00 bft.
3.33
10.00

444.33
333.33
777.67
777.67
259.22 bft.

1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.

0.18
266.67
53.33
9.47

kgs.
pcs.
pcs.
kgs.

Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=
No. of blades = 133.33/350 =
Sub-total

133.33
0.38 blades

e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total

0.0040 m
467.33 m
1.88 cu.m.
0.44 MT

f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total

266.67
88.89
2.22 kgs.

g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost

21.43 gals.

Output = 77.00 cu.m./day or 513.00 sq.m./day


No.of days = 3,000/513.00 6
=.00
days
B. Manpower:
1.00
2.00
2.00
4.00
5.00
7.00

- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost

220.00 /day
175.00
175.00
175.00
175.00
145.00

6.00
6.00
6.00
6.00
6.00
6.00

56.25 /day
60.00 /day
1,200.00 /day

4.00
4.00
1.00

C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost

T O TAL

COST

DIRECT UNIT COST =

P
496.31 /sq.m.

Item Portland
311-2
Cement Concrete Pavement PCCP

0.2 mthick)

Assume Quantity
L
W
A
V

=
=
=
=

100.00
6.00
600.00
120.00

m.
m.
sq.m.
cu.m.

A. Materials:
a. Concrete Mix delivered @ jobsite
120.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12

6.00 in.

For 100.00m Preparation


No.of Center forms & key =
No.of Side forms
=
Total no.of bft.
=
For
100.00 m.preparation =
For 3 times usage
=
Sub-total
c.Steel bars
i.Dowels: 5/8"dia. x0.76m @ 0.75 moc
Wt/pc. = 0.76x1.57
=
No.of pcs. = 100.00/0.75 =
For width,every 100.00m (4 pcs.)
(100/100)x4x2
=
Total no.of dowels =
Wt
=
ii.Steel Pins : 1/2"dia. x 0.20m @ 0.75 moc
Wt.of/pc. = 0.20 x 0.888 =
No. of Pins =(100/0.75)x2 =
For 5 times usage=
Total Wt
=
Sub-total
d.Diamond Blade
Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=

10.00 bft.
3.33
10.00

444.33
333.33
777.67
777.67
259.22 bft.

1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.

0.18
266.67
53.33
9.47

kgs.
pcs.
pcs.
kgs.

133.33

No. of blades = 133.33/350 =


Sub-total

0.38 blades

e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total

0.0040 m
467.33 m
1.88 cu.m.
0.44 MT

f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total

266.67
88.89
2.22 kgs.

g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost

21.43 gals.

Output = 77.00 cu.m./day or 513.00 sq.m./day


No.of days = 3,000/513.00 6
=.00
days
B. Manpower:
1.00
2.00
2.00
4.00
5.00
7.00

- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost

220.00 /day
175.00
175.00
175.00
175.00
145.00

6.00
6.00
6.00
6.00
6.00
6.00

56.25 /day
60.00 /day
1,200.00 /day

4.00
4.00
1.00

C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
DIRECT UNIT COST =

COST

=
P

P
636.31 /sq.m.

ITEMConcrete
502
Curbs & Gutter
1.Materials:
a.Forms : 100 bft.(Good for 60.00 m)
b.C.W.Nails:20 kgs.(Good for 60.00 m)
c.Concrete Volume = (0.15x0.15)+(0.00x0.00)=0.025 cu.m.
Cement = 0.09 x 9 =
Sand = 0.09 x 0.50 =
Gravel = 0.09 x 1.00 =
Sub-total

1.67 @
0.33

24.00
24.00

0.81
0.05
0.09

225.00
600.00
950.00

A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total

50.00

1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total

27.50
21.875
18.125

2.Manpower:

3.Fuel and Oil


Plate Compactor
Oil,10 % of fuel =
Sub-total
4.Output =

1.05 liters
0.11 liters

10.00
45.00

20.00 lm./hr.
Direct Cost =

11.21 /lm.

B.Placing and removal of Forms

1.Manpower:
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
2.Output =

27.500
21.875
18.125

11.00 lm./hr.
Direct Cost =

14.38 /lm.

C.Pouring and Finishing


1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total

45.00
60.00

2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total

27.50
21.88
18.13

3.Fuel and Oil


1-Bagger Mixer
Concrete Vibrator

3.00
1.05
4.05 liters
0.41 liters

Oil,10 % of fuel =
Sub-total
4.Output =

10.00
45.00

10.00 lm./hr.
Direct Cost =

DIRECT UNIT COST =

ITEMConcrete
601
Sidewalk
Assume Quantity = 100.00 sq.m.
Thickness =
0.10 m
1.Materials:
a.Forms : 4 bft./sq.m. x 100/3
Used 3 times
b.C.W.Nails:0.02 kgs./bft.x4x100 =
Cement = 10.00 x 9 =
Sand = 10.00 x 0.45 =
Gravel = 10.00 x 0.90 =
Sub-total

33.24 /lm.
P

401.57 /lm.

Volume =
133.33 @
8.00
90.00
4.50
9.00

10.00
24.00
24.00
225.00
600.00
950.00

A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total

50.00 /day

1.00

220.00 /day
175.00
145.00

1.00
1.00
1.00

2.Manpower:
1.00 Foreman
1.00 Operator
5.00 Laborers

VAT, 10%
Sub-total
3.Fuel and Oil
Vibrator Plate =
Oil,10 % of fuel =
Sub-total
4.Output =

1.05 liters
0.11 liters

10.00
45.00

20.00 lm./hr.

B.Placing and removal of Forms


1.Manpower:

Output =

60.00 sq.m./day
220.00 /day
175.00
145.00

1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
C.Pouring and Finishing
1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total

1.75
1.75
1.75

45.00 /hr.
60.00

2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total

220.00 /day
175.00
145.00

1.75
1.75
1.75

3.00
1.05
4.05 liters
0.41 liters

10.00
45.00

3.Fuel and Oil


1-Bagger Mixer
Concrete Vibrator
Oil,10 % of fuel =
Sub-total
DIRECT UNIT COST =

404.83 /sq.m.

C. MASONRY WORKS
a. 6" CHB (750 psi) Load Bearing
a.Materials
12.50 pcs. 6" CHB (Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand

@
@

10.50
225.00
600.00

3.00 kgs. Grade 33 Rebars


0.05 Ga.# 16 GI Wires

b. 4" CHB (750 psi) Load Bearing


a.Materials
12.50 pcs. 4"CHB (Load Bearing)
0.54 bags Cement
0.05 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

c. 6" CHB (400 psi) Non-Load Bearing


a.Materials
12.50 pcs. 6" CHB (Non-Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

d. 4" CHB (400 psi) Non-Load Bearing


a.Materials
12.50 pcs. 4"CHB (Non-Load Bearing)
0.54 bags Cement
0.05 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

e. 6"x6"x12" Louver Blocks


a.Materials
24.00
0.49
0.04
2.25
0.04

pcs. 6"x6"x12" Louver Blocks


bags Cement
cu.m. Sand
kgs. Grade 33 Rebars
Ga.# 16 GI Wires

10.30
225.00
600.00
12.00
36.00
M=

@
@

7.80
225.00
600.00
12.00
36.00
M=

@
@

7.50
225.00
600.00
12.00
36.00
M=

@
@

10.50
225.00
600.00
12.00
36.00
M=

@
@

f. Lightweight Concrete (fc' = 1,200 psi) Density = 80 to 100 pcf


a.Materials (Job Mixed)
8.00 bag Cement (Portland)
(8-18 bags/cm)
4.00 bag Perlite Concrete Grade (12 kgs./bag)
4.00 bag Light Aggregates (Dead Gravel)
0.68 cu.m. Sand (24 cu.ft.)
0.70 gal. Air Entraining Agent
1.00 bag Fibrin (2 lbs./bag)
b. Labor (Job Mixed Concrete)

12.00
36.00
M=

225.00
130.00
120.00
600.00
135.00
600.00
M=
L=

For One (1) Bagger Mixer (V = 0.125 cu.m.)


1.00 bag Portland Cement
1/2 bag Perlite Concrete Grade
3.00 cu.ft. Sand
1/2 pint Air Entraining Agent
1/8 bag Fibrin
g. Glass Block (8" x 8")
a. Materials
25.00 pcs. 8" x 8" Glass Block
12.50 kls. ABC Grout

150.00
30.00
M=

225.00
600.00
M=

225.00
600.00
M=

225.00
600.00
900.00
M=

225.00
600.00
900.00
M=

225.00
600.00
80.00
M=

FLOOR FINISHES
a. Patterned Cement Finish
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand

b. Plain Cement Floor Topping


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand

c. Plain Cement Floor Topping w/ Hardener


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
0.100 bag Floor Hardener
4 kls./sq.m.- 40 kls. /bag
d. Straight to Finish Floor Topping w/ Hardener
a.Materials
0.140 bag Cement(Portland)
0.011 cu.m. Sand
0.100 bag Floor Hardener
4 kls./sq.m.- 40 kls. /bag
e. Red Cement Topping
a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
0.250 kgs. Red Cement

f. Beige Peeble Washout Finish(By Area)

a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding

225.00
600.00
3.50

ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles

g. Beige Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.147 bag Cement(Portland)
0.011 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Beige Pebbles

h. Black Peeble Washout Finish(By Area)


a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Black Pebbles

i. Black Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.147 bag Cement(Portland)
0.011 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Black Pebbles

j. Beige Peeble Washout Finish(By Area) Deck w/ wire mesh


a.Materials
i.Scratch Coat
0.700 bag Cement(Portland)
0.054 cu.m. Sand
1.000 sq.m. Wire Mesh
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)

225.00
90.00
M=

225.00
600.00
225.00
90.00
M=

225.00
600.00
3.50
225.00
45.00
M=

225.00
600.00
225.00
45.00
M=

225.00
600.00
45.00
3.50
225.00

1.250 cans #10 Beige Pebbles

k. Plain Cement Finish w/ Peeble Washout Nosing


a.Materials
i.Scratch Coat
0.168 bag Cement(Portland)
0.013 cu.m. Sand
1.640 lft.kd Tang.moulding
ii.Final Coat
0.031 bag Cement(Portland)
0.063 cans #10 Ass. Pebbles

l. Peeble Washout Finish w/ 8"x8" Tile Pattern


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.625 bag Cement(Portland)
4.000 pcs.8"x8"Floor Tiles
0.100 kls. ABC Grout
1.250 cans #10 Ass. Pebbles

l. 12"x12" Vigan Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.219 bag Cement(Portland)
12.000 pcs.12"x12"Vigan Tiles
0.250 kls. Colored Cement
0.438 cans #10 Ass. Pebbles

m. 8" x 8" Vit. Floor Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.150 bag Cement(Portland)
9.000 pcs.8"x8"Vit. Floor Tiles
0.375 kls. ABC Grout
0.300 cans #10 Ass. Pebbles

90.00
M=

225.00
600.00
3.50
225.00
45.00
M=

225.00
600.00
225.00
14.00
30.00
45.00
M=

225.00
600.00
225.00
10.00
80.00
65.00
M=

225.00
600.00
225.00
14.00
30.00
45.00
M=

n. 25mm thk. Granite Slab


a.Materials
0.490
0.037
1.000
10.000

bag Cement (Portland)


cu.m. Sand
sq.m. Granite Slab
% Consumables
Materials
Labor

o. 300x300 Ceramic Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.150 bag Cement(Portland)
9.000 pcs.12"x12"Ceramic Tiles
0.375 kls. ABC Grout
0.300 cans #10 Ass. Pebbles

225.00
600.00
4,500.00

225.00
600.00
225.00
35.00
30.00
45.00
M=

p. Vinyl Tiles (Tajima)


a. Materials
12.00 pcs. 12"x12"x3.0 mmthk. Vinyl Tiles
0.060 gal. Vinyl Adhesives

28.00
550.00

12.00 pcs. 12"x12"x3.0 mmthk. Vinyl Tiles


0.060 gal. Vinyl Adhesives

24.00
550.00

r. 200x200 Non skid Tiles


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
25.000 pcs.8"x8"Non skid Tiles

225.00
600.00
11.00
M=

s. Concrete Paving Block (Keyhole Pattern)


a.Materials
0.490 bag Cement(Portland)
0.037 cu.m. Sand
40.000 pcs. Keyhole Pattern Bricks

225.00
600.00
10.50
M=

225.00

q. Vinyl Tiles (Matico)


a. Materials

t. 150x150 Ceramic Unglazed Floor Tiles


a.Materials
0.490 bag Cement(Portland)

0.500 kls. ABC Grout


0.037 cu.m. Sand
45.000 pcs.6"x6"Floor Tiles

u. 101x101 Vitrified Floor Tiles (Piedra Tiles)


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
90.000 pcs.4-1/4"x4-1/4"Floor Tiles

v. 200x200 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
25.000 pcs.8"x8"Floor Tiles

w. 100x200 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
50.000 pcs.4"x8"Floor Tiles

x. 450x450 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
5.000 pcs.18"x18"Floor Tiles

y. 300x300 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
12.000 pcs.12"x12"Floor Tiles

z. 300x300 Cotto Homogeneous Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand

30.00
600.00
10.50
M=

225.00
30.00
600.00
6.00
M=

225.00
30.00
600.00
14.00
M=

225.00
30.00
600.00
10.50
M=

225.00
30.00
600.00
75.00
M=

225.00
30.00
600.00
28.00
M=

225.00
30.00
600.00

12.000 pcs.12"x12"Floor Tiles

aa. 300x300 Synthetic Granite Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
12.000 pcs.12"x12"Floor Tiles

ab. 600x600mm x19mm thk. Marble @ Counters w = 0.60m


a. Materials
0.294 bag Cement (Portland)
0.022 cu.m. Sand
0.600 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor

150.00
M=

225.00
30.00
600.00
120.00
M=

225.00
600.00
900.00

ac. 600x600mm x19mm thk. Marble @ Counters (Splashboard) w = 0.35m


a. Materials
0.172 bag Cement (Portland)
@
0.013 cu.m. Sand
0.350 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ad. 600x600mm x19mm thk. Marble @ Counters (Splashboard) w = 0.20m
a. Materials
0.098 bag Cement (Portland)
@
0.007 cu.m. Sand
0.200 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ae. 600x600mm x19mm thk. Marble @ Counters (Fascia Board) w = 0.15m
a. Materials
0.074 bag Cement (Portland)
@
0.006 cu.m. Sand
0.150 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
af. 600x600mm x19mm thk. Marble Slabs
a. Materials
0.490 bag Cement (Portland)

225.00
600.00
900.00

225.00
600.00
900.00

225.00
600.00
900.00

225.00

0.037 cu.m. Sand


1.000 sq.m. 0.60x0.60 Marbles
10.000 % Consumables
Materials
Labor
ag. 600x600mm x19mm thk. Lavatory Sidings w = 0.30m
a. Materials
0.147 bag Cement (Portland)
0.011 cu.m. Sand
0.300 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ah. Plain Cement Floor Topping w/ Chicken Wire Mesh
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand
1.000 sq.m. Chicken Wiremesh

ai. 2"x12" Ceramic Tile Nosing


a. Materials
12.000 pcs. Ceramic Tile nosing
10.000 % Consumables

600.00
950.00

225.00
600.00
900.00

225.00
600.00
45.00
M=

25.00
M=

aj. Expansion Joint and Contraction Joints (1/2"thk.)


a. Materials
3.280 lft. x 1/2"x6" Non-extruding Joint Fiiler (Cork type)
0.081 liter Sealant

ak. Expansion Joint and Contraction Joints (3/4"thk.)


a. Materials
3.280 lft. x 3/4"x6" Non-extruding Joint Fiiler (Cork type)
0.121 liter Sealant

al. Expansion Joint and Contraction Joints (1"thk.)


a. Materials
3.280 lft. x 1"x6" Non-extruding Joint Fiiler (Cork type)
0.161 liter Sealant

WALL FINISHES
a. 300x300 Synthetic Granite
a.Materials

25.00
880.00
M=

50.28
880.00
M=

50.43
880.00
M=

0.450
0.250
0.027
12.000

bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs. 12"x12" Granite Tiles
Materials

b. 101x101 Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
90.000 pcs.4-1/4"x4-1/4"Wall Tiles

c. 100x200 Vit. Wall Tiles


a.Materials
0.450
0.250
0.027
50.000

bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs.4"x8"Wall Tiles

d. 200x200 Ceramic Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
25.000 pcs.8"x8"Wall Tiles

d. 300x300 Ceramic Vit. Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
12.000 pcs.12"x12"Wall Tiles

e. 450x450 Ceramic Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
5.000 pcs.18"x18"Wall Tiles

225.00
30.00
600.00
120.00

225.00
30.00
600.00
2.50
M=

225.00
30.00
600.00
10.50
M=

225.00
30.00
600.00
14.00
M=

225.00
30.00
600.00
28.00
M=

225.00
30.00
600.00
75.00
M=

f. Ordinary Bricks 2"x8"x1/2" (on Exterior Wall)


a.Materials
97.00 pcs. 2"x8"x1/2" Ordinary Bricks

2.50

0.424 bag Cement(Portland)


0.032 cu.m. Sand

1. Exterior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.424 bag Cement(Portland)
0.032 cu.m. Sand

b. Plain Cement Plaster Finish (By Area)RC Walls


a.Materials
0.150 gal. Cement Gum
0.501 bag Cement(Portland)
0.038 cu.m. Sand

2. Interior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.350 bag Cement(Portland)
0.027 cu.m. Sand

b. Plain Cement Plaster Finish (By Area)RC Walls


a.Materials
0.150 gal. Cement Gum
0.420 bag Cement(Portland)
0.032 cu.m. Sand

c. Plain Cement Plaster Finish (By LM) w = 0.50m.


a.Materials
0.245 bag Cement(Portland)
0.019 cu.m. Sand

d. Plain Cement Plaster Finish (By LM) w = 0.30m.


a.Materials
0.147 bag Cement(Portland)
0.011 cu.m. Sand

e. Plain Cement Plaster Finish (By LM) w = 0.15m.


a.Materials
0.074 bag Cement(Portland)
0.006 cu.m. Sand

225.00
600.00
M=

225.00
600.00
M=

208.00
225.00
600.00
M=

225.00
600.00
M=

208.00
225.00
600.00
M=

225.00
600.00
M=

225.00
600.00
M=

225.00
600.00

M=
f. Plain Cement Plaster Finish (By LM) w = 0.60m.
a.Materials
0.294 bag Cement(Portland)
0.022 cu.m. Sand

g. Plain Cement Plaster Finish (By Area) on Louver Blocks


a.Materials
0.054 bag Cement(Portland)
0.004 cu.m. Sand

h. Beige Peeble Washout Finish(By Area)


a.Materials
i.Scratch Coat
0.350 bag Cement(Portland)
0.027 cu.m. Sand
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles

i. Beige Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.105 bag Cement(Portland)
0.008 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Beige Pebbles

225.00
600.00
M=

225.00
600.00
M=

225.00
600.00
3.50
225.00
90.00
M=

225.00
600.00
225.00
90.00
M=

CEILING FINISHES
a. 1/4"thk.Marine Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)
w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@
0.375 pcs. 1/4"x4'x8'Marine Plywood
0.400 kls. Assorted Nails
0.050 gal. Solignum

b. 1/4"thk.Ordinary Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@

24.00
355.00
24.00
525.00
M=

24.00

0.375 pcs. 1/4"x4'x8'Ordinary Plywood


0.400 kls. Assorted Nails
0.050 gal. Solignum

600.00
24.00
525.00
M=

c. 1/2"thk.Gypsum Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 1/2"x4'x8'Gypsum Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

c. 5/8"thk.Gypsum Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 5/8"x4'x8'Gypsum Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

c. 1/2"thk. Ficem Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 1/2"x4'x8' Ficem Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

d. Retouching of Exposed Slab


a.Materials
0.014 bag Cement(Portland)
0.001 cu.m. Sand

e.5/8" thk. RH-90 Non-sagging Acoustic Tiles on Baked Enamel T-runners


a. Materials
13.500 lft. 15/16" Baked enamel T-runners
@
11.500 sq.ft. 5/8" x 24"x24" RH - 90 Non-sagging

f.5/8" thk. Minaboard Fissured Acoustic Tiles on Baked Enamel T-runners


a. Materials
13.500 lft. 15/16" Baked enamel T-runners
@
11.500 sq.ft. 5/8" x 24"x24" Minaboard Fissured

24.00
295.00
24.00
525.00
M=

24.00
296.00
24.00
525.00
M=

24.00
1,150.00
10.50
175.00
M=

225.00
600.00
M=

10.00
22.50
M=

300.00
20.00
M=

g. Cemboard Ceiling on Furring Channel


a. Materials
0.375 pc. 3/16"x4'x8' Cemboard
0.120 pc. x 10' Carrying Channel
0.200 pc. Metal Furring Channel x 12'
0.150 pc. Alum. Wall Angle x 10'
0.040 gal. RM Joint Compound
0.100 gross Buglehead self tapping screw

h. Gypsum Board Ceiling on Furring Channel


a. Materials
0.375 pc. 1/2"x4'x8' Gypsum Board
0.120 pc. x 10' Carrying Channel
0.200 pc. Metal Furring Channel x 12'
0.150 pc. Alum. Wall Angle x 10'
0.013 roll Gypsum Joint Tape
0.040 gal. RM Joint Compound
0.100 gross Buglehead self tapping screw

700.00
175.00
145.00
125.00
250.00
260.00
M=

295.00
175.00
145.00
125.00
300.00
250.00
260.00
M=

3,275.00
12.50
M=

770.00
5.50
137.50
M=

3,275.00
12.50
M=

770.00
5.50
137.50
M=

CONCRETE WORKS
a. Lintel Beams (For 6" CHB)
a. Materials
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
b. Labor
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks

b. Lintel Beams (For 4" CHB)


a. Materials
0.0350 cu.m. Concrete
3.3000 kg. Rebars
0.8000 sq.m. Formworks
b. Labor
0.0350 cu.m. Concrete
3.3000 kg. Rebars
0.8000 sq.m. Formworks

c. Stiffener Columns (For 6" CHB)


a. Materials
0.0250 cu.m. Concrete

3,275.00

2.0000 kg. Rebars


0.3000 sq.m. Formworks

12.50
M=

b. Labor
0.0250 cu.m. Concrete
2.0000 kg. Rebars
0.3000 sq.m. Formworks

d. Stiffener Columns (For 4" CHB)


a. Materials
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks

770.00
5.50
137.50
M=

3,275.00
12.50
M=

770.00
5.50
137.50
M=

275.00
18.125

275.00
18.125

250.00
120.00
Equipment Cost
10% VAT

20.63

b. Labor
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks

Item SP- 3 Hauling Works


a. Rebars
1 ELF
10 Laborers

Production
Unit Cost

=
=

b. Forms
1 ELF
10 Laborers

20,000.00 kgs./day
P

Production
Unit Cost

=
=

Demolition Works
a. Equipment (Demolition)
1.00 Compressor
2.00 Jackhammer

12.00 hrs./day
12.00

0.30 /kg.

12.00 hrs./day
12.00
750.00 sq.m./day
7.88 /sq.m.

b. Manpower
20.00 Laborers

Labor Cost
10% VAT
Total Cost / hr.
Duration =
c. Equipment (Hauling & Disposal)
1.00 Loader
2.00 Dump Truck

Duration =

12 hrs. for 15 days

700.00
500.00
Equipment Cost
10% VAT
6 hrs. for 6 days
Total Cost =

Item SP- 4 Cleaning,Hauling & Disposal of Debris

1 Dumptruck
10 Laborers

8.00 hrs./day
8.00

450.00
18.125

10 times per month for 8 months


Item SP- 5 Dewatering Works
Pump Rental
Fuel
Operator

1.00 hr.

Unit Cost
Item SP - 6 G.I. Sheet Temporary Fence (H = 3.00m)
a. Materials
20.00 bft. Coco Lumber
15.00 lft. Ga. # 26 Pre-painted Corrugated GI Sheets
0.015 kegs CW Nails
0.10 kgs. Roof Nails

Item SP - 7 Protection of Adjacent Properties


a. Materials
30.00 lft. Corr. G.I.Sheets
2.00 pcs.62mm dia. GI Pipes
6.00 pcs. Pipe Clamp
0.25 pc.32mmdia. Plain Round Bars
1.00 pc.10mmdia.
-do2.00 pcs. Coil bolt w/ waler washer
b. Labor (Installation)

50.00
15.00
20.00
=

6.00
40.00
950.00
85.00
Unit Cost =

26.00
525.00
75.00
475.00
45.00
25
Unit Cost (M & L) =

Item SP - 8 Construction Safety Net


a. Materials
For 3.50 x 9 floors x 30.00 =
8.50
950.00
25.00
33.00
b. Labor (Installation)

945.00 sq.m.

lm. Ga. # 12 G.I. Wires


sq.m. Nylon Net (1/4" x 2.00 x 90.00m)
pcs. 10mm x 6.00m Plain Round Bars
pcs. 12mm x 6.00m
-do-

1.50
12.50
45.00
65.00

Unit Cost (M & L) =


Item SP - 9 100mm thk Wall w/ 50mm Rigid Insulation Welded Wire w/ 25mm thk. Plaster on Both Sides
a. Materials
4.00 lm. Carrying Channel
@
58.33
15.00 lm. Furring Channel
40.28
2.20 sq.m. Ga. # 22 Expanded Metal Lathe
140.00
2.50 lm. 16mm dia. Plain Round Bar
25.00
0.75 bag Cement
225.00
0.06 cu.m. Sand
600.00
1.10 sq.m. Rigid Insulation
140.00
Materials
Labor

Morales Shopping Mall


A. Vinyl Tiles

2 x 300 x 300 Vinyl Tiles


Vinyl Adhesive
Armstrong Imperial Series

12.00 pcs.
0.06 gal.

Installation
Polishing

12.00 tiles
12.00 tiles

Vinyl Cove Baseboard


Consumables

B. Plain Cement Floor Topping

3.28 ln.ft.
1.00 lot

23.00
525.00
Materials

3.50
2.40
Sub Total
VAT
Labor

26.50
3.08
Materials
Labor

P
P

Cement
Sand

II. Walls and Wall Finishes


A. 6" CHB Wall
6" CHB 350 psi
Cement
Sand
Grade 33 Rebars
GI Wires

B. 4" CHB Wall


4" CHB 350 psi
Cement
Sand
Grade 33 Rebars
GI Wires

0.70 bags
0.06 cu.m.

12.50
1.05
0.09
2.50
0.04

12.50
0.54
0.04
2.50
0.04

pcs.
bags
cu.m.
kgs.
kgs.

pcs.
bags
cu.m.
kgs.
kgs.

125.00
300.00
Materials
Labor

P
P

7.50
125.00
300.00
12.20
30.20
Materials
Labor

P
P

7.30
125.00
300.00
12.20
30.20
Materials
Labor

P
P

125.00
300.00
80.00
148.00
Materials
Labor

P
P

125.00
300.00
80.00
Materials
Labor

P
P

C. Exterior Plastering

Cement
Sand
ME 602 Mortar Enhancer
Sealopruf Integral Waterproofing

0.50
0.06
0.13
0.05

bags
cu.m.
liters
gal

D. Interior Plastering

Cement
Sand
ME 602 Mortar Enhancer

0.30 bags
0.03 cu.m.
0.08 liters

C.MATERIALS

50,000.00

4,179,910.00
0.5573%

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
45.
46.
47.

Premium Fuel
Diesel
Lubricating Oil
Gravel Fill
Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
CW Nails
Cement
Gravel
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)

This insurance is used to


insured construction
materials damaged by
natural calamity

This insurance is used to


insured critical adjacent
properties which might be
affected during construction.

4,131,143.40

945,500.00

Assume 1.50m per personnel/laborer


Assume 2.00m per unit

375,500.00

48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.

300x300x3.0mm Vinyl Tiles (Matico)


16x600x600 RH-90 Non-sagging Acoustic
16x600x600 Minaboard Fissured Acousti
19x600x600 Marble Slab incl. Polishing
CDS Marble
ABC Grout
6"x6" Louver Blocks
Beige Pebbles # 10
Beige Pebbles # 5
Black Pebbles # 10
Black Pebbles # 5
Assorted Pebbles
CW Nails
Concrete Paving Blocks (Keyhole Pattern
Solignum
Vinyl Adhesive
Ga. # 16 GI Wires
Kd Tanguile Moulding
Suspension Grid System
Boulders
1/2" x 1200 x 2400 Gypsum Board
5/8" x 1200 x 2400 Gypsum Board
1/2" x 1200 x 2400 Ficem Board
x 10' Carrying Channel
x 12' Furring Channel
x 10' Alum. Wall Angle
Gypsum Joint Tape
Ready Mix Joint Compound
Self Tapping Screw
4.5 x 1200 x 2400 Ficem Board
2mm x 100mm Flexible Vinyl Baseboard
3mm x 1/2" Brass Strip
Hanger rods
Chicken Wire Mesh
2"x12" Ceramic Tile Nosing
1/2"x3'x10' Joint Filler (Cork type)
3/4"x3'x10'
-do1"x3'x10'
-doSealant
Perlite Concrete Grade (CG) (12 kgs./bag
Air Entraining Agent (AEA)
Fibrin (2 lbs./ bag)
Light Aggregates (Dead Gravel)
8" x 8" Glass Block
300x300 Vigan Tiles
19x150 Wood Parquet
Flarefloor Rubber Tiles
3/4" Ord. Plywood
2"x8"x1/2" Ordinary Bricks

98.
99.
100.

3,984,000.00
A.EQUIPMENTS:

1,000.00 =
500.00 =
400.00 =
=
=

27.50
18.13
21.88
20.00

=
=
=
=
=

1,000.00
500.00
1,200.00
24.41
272.44
2,996.85 /hr.

27.50
90.63
43.75
60.00
22.19
244.06 /hr.

24.125
10.00
83.25
117.38 liters
7.00 =
45.00 =

4,590.72 /hr.

821.63
528.19
1,349.81 /hr.

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.

Dozer D8H w/ ripper


Payloader
Dump trucks
Grader
Roller
Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump
Screeder
Vibrator
Concrete Cutter
1-Bagger Mixer
Chainsaw
Portalift
Concrete Breaker
Backhoe
Trencher
B.MANPOWER:

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.

Foreman
Leadman
Timekeeper
Carpenter
Mason
Steelman
Laborer
Floater
Mixer Operator
Painter
Welder
HE Operator
Driver
Screeder Operator

400.00 =
350.00 =
500.00 =
=
=

27.50
18.13
21.88
20.00

=
=
=
=
=

1,200.00
350.00
500.00
16.02
206.60
2,272.62 /hr.

27.50
54.38
43.75
20.00
14.56
160.19 /hr.

83.25
14.00
2.28
99.53 liters
7.00 =
45.00 =

696.71
447.89
1,144.60 /hr.

3,577.40 /hr.
/CU.M.
/CU.M.

750.00 =
500.00 =
400.00 =
=
=

750.00
500.00
1,200.00
24.41
247.44
2,721.85 /hr.

27.50 =
18.13 =
21.88 =

27.50
90.63
43.75

20.00 =
=

60.00
22.19
244.06 /hr.

24.125
10.00
83.25
117.38 liters
7.00 =
45.00 =

821.63
528.19
1,349.81 /hr.

4,315.72 /hr.

27.50 =
18.13 =
=

27.50
90.63
11.81
129.94 /hr.

400.00 =
350.00 =
300.00 =
=
=

400.00
350.00
300.00
16.02
106.60
1,172.62 /hr.

27.50
18.13
21.88
20.00

=
=
=
=
=

27.50
54.38
43.75
20.00
14.56
160.19 /hr.

8.00
14.00
5.44
27.44 liters
7.00 =
45.00 =

192.08
123.48
315.56 /hr.

250.00 =

15,000.00
15,000.00 /hr.

16,648.37 /hr.

400.00 =
350.00 =
300.00 =
=
=

27.50
18.13
21.88
20.00

=
=
=
=
=

400.00
350.00
300.00
16.02
106.60
1,172.62 /hr.

27.50
54.38
43.75
20.00
14.56
160.19 /hr.

8.00
14.00
5.44
27.44 liters
7.00 =
45.00 =

192.08
123.48
315.56 /hr.

270.00 =

16,200.00
16,200.00 /hr.

17,848.37 /hr.

2,800.00

252,000.00
252,000.00

24.00 =

6,221.33
6,221.33

12.00 =

2,035.20

12.00 =

113.66
2,148.86

m.

days

day
day
day

10,400.00 =

3,961.90
3,961.90

13,500.00 =

5,976.45
5,976.45

24.00 =

53.33
53.33

40.00 =

857.14
857.14
P 271,219.03

452.03

1,320.00
2,100.00
2,100.00
4,200.00
5,250.00
6,090.00
2,106.00
23,166.00
23,166.00

38.61

450.00
240.00
2,400.00
309.00
3,399.00
3,399.00

5.67

=
=
=
=
=
=
=

=
=
=
=

297,784.03

2,800.00

m.

336,000.00
336,000.00

24.00 =

6,221.33
6,221.33

12.00 =

2,035.20

12.00 =

113.66
2,148.86

10,400.00 =

3,961.90
3,961.90

13,500.00 =

5,976.45
5,976.45

24.00 =

53.33
53.33

40.00 =

857.14
857.14
P 355,219.03

592.03

1,320.00
2,100.00
2,100.00
4,200.00
5,250.00
6,090.00
2,106.00
23,166.00
23,166.00

38.61

450.00
240.00
2,400.00
309.00
3,399.00
3,399.00

5.67

days

=
=
=
=
=
=
=

day
day
day

=
=
=
=

381,784.03

=
=

40.00
8.00

=
=
=
P

182.25
27.00
85.50
342.75

=
=
P

50.00
5.00
55.00

=
=
=
=

27.50
21.88
90.63
14.00
154.00

=
=
P

10.50
4.73
15.23

=
=
=
=
P

27.50
43.75
72.50
14.38
158.13

=
=
=
P

45.00
60.00
10.50
115.50

=
=
=
=
P

27.50
43.75
72.50
14.38
158.13

=
=
P

40.50
18.23
58.73

cu.m.
=

3,200.00

=
=
=
=
P

192.00
20,250.00
2,700.00
8,550.00
34,892.00

348.92

day

=
=
P

50.00
5.00
55.00

day

=
=
=

220.00
175.00
725.00

days
days
days

days
days
days

=
=
=

=
P

0.00
1,120.00

=
=
P

10.50
4.73
15.23

=
=
=
=
P

385.00
612.50
1,015.00
201.25
2,213.75

=
=
=
P

45.00
60.00
10.50
115.50

=
=
=
=
P

385.00
612.50
1,015.00
0.00
2,012.50

=
=
P

40.50
18.23
58.73

131.25
229.50
54.57

=
=
P

36.00
1.80
453.12 /sq.m.

=
=
=
=
=
P

128.75
121.50
28.89
36.00
1.80
316.94 /sq.m.

=
=
=
=
=
P

97.50
229.50
54.57
36.00
1.80
419.37 /sq.m.

=
=
=
=
=
P

93.75
121.50
28.89
36.00
1.80
281.94 /sq.m.

=
=
=
=
=
P

252.00
110.25
22.20
27.00
1.26
412.71 /sq.m.

=
=
=
=
=
=
P
P

1,800.00
520.00
480.00
408.16
94.50
600.00
3,902.66 /cu.m.
770.00 /cu.m.

=
=
P

3,750.00
375.00
4,125.00 /cu.m.

=
=
P

157.50
32.10
189.60 /sq.m.

=
=
P

126.00
25.68
151.68 /sq.m.

=
=
=
P

126.00
25.68
90.00
241.68 /sq.m.

=
=
=
P

31.50
6.42
90.00
127.92 /sq.m.

=
=
=
P

126.00
25.68
20.00
171.68 /sq.m.

=
=
=

110.25
22.47
10.50

=
=
P

140.63
112.50
396.35 /sq.m.

=
=

33.08
6.74

=
=
P

42.19
33.75
115.75 /lm.

=
=
=

110.25
22.47
10.50

=
=
P

140.63
56.25
340.10 /sq.m.

=
=

33.08
6.74

=
=
P

42.19
16.88
98.88 /lm.

=
=
=
=

157.50
32.10
45.00
10.50

140.63

=
P

112.50
498.23 /sq.m.

=
=
=

37.80
7.70
5.74

=
=
P

7.03
2.81
61.09 /lm.

=
=

126.00
25.68

=
=
=
=
P

140.63
56.00
3.00
56.25
407.56 /lm.

=
=

126.00
25.68

=
=
=
=
P

49.22
120.00
20.00
28.44
369.34 /lm.

=
=

126.00
25.68

=
=
=
=
P

33.75
126.00
11.25
13.50
336.18 /lm.

=
=
=
=
P
P

110.25
22.47
4,500.00
450.00
5,082.72 /lm.
220.00 /lm.

=
=

126.00
25.68

=
=
=
=
P

33.75
315.00
11.25
13.50
525.18 /lm.

=
=
P

336.00
33.00
369.00 /sq.m.

=
=
P

288.00
33.00
321.00 /sq.m.

=
=
=
P

126.00
25.68
275.00
426.68 /sq.m.

=
=
=
P

110.25
22.47
420.00
552.72 /sq.m.

110.25

=
=
=
P

15.00
22.47
472.50
620.22 /sq.m.

=
=
=
=
P

110.25
15.00
22.47
540.00
687.72 /sq.m.

=
=
=
=
P

110.25
15.00
22.47
350.00
497.72 /sq.m.

=
=
=
=
P

110.25
15.00
22.47
525.00
672.72 /sq.m.

=
=
=
=
P

110.25
15.00
22.47
375.00
522.72 /sq.m.

=
=
=
=
P

110.25
15.00
22.47
336.00
483.72 /sq.m.

=
=
=

110.25
15.00
22.47

=
P

1,800.00
1,947.72 /sq.m.

=
=
=
=
P

110.25
15.00
22.47
1,440.00
1,587.72 /sq.m.

=
=
=
=
P
P

66.15
13.48
540.00
54.00
673.63 /lm.
200.00 /lm.

=
=
=
=
P
P

38.59
7.86
315.00
31.50
392.95 /lm.
185.00 /lm.

=
=
=
=
P
P

22.05
4.49
180.00
18.00
224.54 /lm.
185.00 /lm.

=
=
=
=
P
P

16.54
3.37
135.00
13.50
168.41 /lm.
185.00 /lm.

110.25

=
=
=
P
P

22.47
950.00
95.00
1,177.72 /lm.
185.00 /lm.

=
=
=
=
P
P

33.08
6.74
270.00
27.00
336.82 /lm.
185.00 /lm.

=
=
=
P

157.50
32.10
45.00
234.60 /sq.m.

=
=
P

300.00
30.00
330.00 /sq.m.

=
=
P

82.00
70.94
152.94 /lm.

=
=
P

164.93
106.41
271.33 /lm.

=
=
P

165.42
141.87
307.29 /lm.

=
=
=
=
P

101.25
7.50
16.05
1,440.00
1,564.80 /lm.

=
=
=
=
P

101.25
7.50
16.05
225.00
349.80 /sq.m.

=
=
=
=
P

101.25
7.50
16.05
525.00
649.80 /sq.m.

=
=
=
=
P

101.25
7.50
16.05
350.00
474.80 /sq.m.

=
=
=
=
P

101.25
7.50
16.05
336.00
460.80 /sq.m.

=
=
=
=
P

101.25
7.50
16.05
375.00
499.80 /sq.m.

242.50

=
=
P

95.29
19.42
357.21 /sq.m.

=
=
P

95.29
19.42
114.71 /sq.m.

=
=
=
P

31.20
112.61
22.95
166.76 /sq.m.

=
=
P

78.75
16.05
94.80 /sq.m.

=
=
=
P

31.20
94.50
19.26
144.96 /sq.m.

=
=
P

55.13
11.24
66.36 /lm.

=
=
P

33.08
6.74
39.82 /lm.

=
=

16.54
3.37

19.91 /lm.

=
=
P

66.15
13.48
79.63 /lm.

=
=
P

12.15
2.40
14.55 /lm.

=
=
=

78.75
16.05
10.50

=
=
P

=
=

140.63
112.50
358.43 /sq.m.

23.63
4.82

=
=
P

42.19
33.75
104.38 /lm.

=
=
=
=
P

300.00
133.13
9.60
26.25
468.98 /sq.m.

300.00

=
=
=
P

225.00
9.60
26.25
560.85 /sq.m.

=
=
=
=
P

240.00
110.63
9.60
26.25
386.48 /sq.m.

=
=
=
=
P

240.00
111.00
9.60
26.25
386.85 /sq.m.

=
=
=
=
P

240.00
431.25
4.20
8.75
684.20 /sq.m.

=
=
P

3.15
0.64
3.79 /sq.m.

=
=
P

135.00
258.75
393.75 /sq.m.

=
=
P

4,050.00
230.00
4,280.00 /sq.m.

=
=
=
=
=
=
P

262.50
21.00
29.00
18.75
10.00
26.00
367.25 /sq.m.

=
=
=
=
=
=
=
P

110.63
21.00
29.00
18.75
3.75
10.00
26.00
219.13 /sq.m.

=
=
=
P

122.81
40.00
162.81 /l.m.

=
=
=
P

28.88
17.60
89.38
135.85 /l.m.

=
=
=
P

114.63
41.25
155.88 /l.m.

=
=
=
P

26.95
18.15
110.00
155.10 /l.m.

81.88

=
=
P

25.00
106.88 /l.m.

=
=
=
P

19.25
11.00
41.25
71.50 /l.m.

=
=
=
P

98.25
25.00
123.25 /l.m.

=
=
=
P

23.10
11.00
82.50
116.60 /l.m.

3,300.00
2,610.00
5,910.00

3,300.00
2,610.00
5,910.00

/hr.
/hr.

250.00
240.00
490.00
49.00
539.00 /hr.

/hr.

412.50

412.50
41.25
453.75
992.75 /hr.
180.00 hours
178,695.00
/hr.
/hr.

700.00
1,000.00
1,700.00
170.00
1,870.00 /hr.
36.00
67,320.00
246,015.00

3,600.00
1,740.00
5,340.00
427,200.00

/hr.
/hr.
/hr.

=
=
=

50.00
15.00
20.00
85.00 /hr./pump

=
=
=
=

120.00
600.00
14.25
8.50
742.75 /lm.

=
=
=
=
=
=
=
ost (M & L) =

780.00
1,050.00
450.00
118.75
45.00
50.00
997.50
3,491.25 /lm.

say

=
=
=
=
=

3,500.00 /lm.

12.75
11,875.00
1,125.00
2,145.00
7,578.88
22,736.63
24.06
25.00 /sq.m.

ost (M & L) =

=
=
=
=
=
=
=

233.33
604.17
308.00
62.50
168.75
36.00
154.00
1,566.75 /sq.m.
783.38 /sq.m.

276.00
31.50
307.50
42.00
28.80
70.80
7.08
77.88
86.92
3.08
90.00
22.00

87.50
16.50
104.00
104.00

93.75
131.25
27.00
30.50
1.21
283.71
110.00

91.25
67.50
12.00
30.50
1.21
202.46
104.00

62.50
16.50
10.00
7.40
96.40
139.00

37.50
9.90
6.00
53.40
115.50

UNIT COST
Premium Fuel
Lubricating Oil

Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade

Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)

10.00
7.00
45.00
440.00
150.00
250.00
270.00
2,800.00
24.00
12.00
40.00
13,500.00
10,400.00
24.00
225.00
950.00
500.00
600.00
355.00
375.00
38.00
17.50
10.50
10.30
7.80
7.50
80.00
900.00
10.50
6.00
35.00
28.00
10.50
14.00
75.00
150.00
4,500.00
11.00
120.00
10.50
14.00
2.50
28.00
75.00
4.00
25.00
6.00
28.00

/lit.
/lit.
/lit.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bft.
/kg.
/gal.
/MT
/pc.
/kl.
/bag
/cu.m.
/cu.m.
/cu.m.
/pc.
/pc.
/bft.
/pc.
/pc.
/pc.
/pc.
/pc.
/kl.
/kl.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.

300x300x3.0mm Vinyl Tiles (Matico)


16x600x600 RH-90 Non-sagging Acoustic Board
16x600x600 Minaboard Fissured Acoustic Board
19x600x600 Marble Slab incl. Polishing
CDS Marble
ABC Grout
6"x6" Louver Blocks
Beige Pebbles # 10
Beige Pebbles # 5
Black Pebbles # 10
Black Pebbles # 5
Assorted Pebbles
Concrete Paving Blocks (Keyhole Pattern)
Vinyl Adhesive
Ga. # 16 GI Wires
Kd Tanguile Moulding
Suspension Grid System
1/2" x 1200 x 2400 Gypsum Board
5/8" x 1200 x 2400 Gypsum Board
1/2" x 1200 x 2400 Ficem Board
x 10' Carrying Channel
x 12' Furring Channel
x 10' Alum. Wall Angle
Gypsum Joint Tape
Ready Mix Joint Compound
Self Tapping Screw
4.5 x 1200 x 2400 Ficem Board
2mm x 100mm Flexible Vinyl Baseboard
3mm x 1/2" Brass Strip
Hanger rods
Chicken Wire Mesh
2"x12" Ceramic Tile Nosing
1/2"x3'x10' Joint Filler (Cork type)
3/4"x3'x10'
-do1"x3'x10'
-do2,200.00/pack (2.50 liters)
Perlite Concrete Grade (CG) (12 kgs./bag)
Air Entraining Agent (AEA)
Fibrin (2 lbs./ bag)
Light Aggregates (Dead Gravel)
8" x 8" Glass Block
300x300 Vigan Tiles
19x150 Wood Parquet
Flarefloor Rubber Tiles
3/4" Ord. Plywood
2"x8"x1/2" Ordinary Bricks

24.00
90.00
80.00
950.00
900.00
30.00
10.50
90.00
90.00
45.00
45.00
65.00
24.00
10.50
525.00
550.00
36.00
3.50
10.00
300.00
295.00
296.00
1,150.00
175.00
145.00
125.00
300.00
250.00
260.00
700.00
23.00
30.00
25.00
45.00
25.00
1,500.00
3,017.00
3,026.00
880.00
130.00
135.00
600.00
120.00
150.00
10.00
60.00
1,300.00
1,100.00
2.50

/pc.
/pc.
/pc.
/sq.m.
/sq.m.
/kl.
/pc.
/can
/can
/can
/can
/can
/kl.
/pc.
/gal.
/gal.
/kl.
/lft.
/lft.
/cu.m.
/pc
/pc
/pc
/pc
/pc
/pc
/roll
/gal.
/gross
/pc.
/lft.
/lft.
/pc.
/sq.m.
/pc.
/pc.
/pc.
/pc.
/liter
/bag
/gal.
/bag
/bag
/pc.
/pc.
/sq.ft.
/sq.m.
/pc.
/pc.

275.00 /bag

38pcs./sq.m.

Labor
25.00 /sq.ft.
80.00 /sq.m.

RENTALS

Dozer D8H w/ ripper


Dump trucks

Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump

Concrete Cutter
1-Bagger Mixer

Concrete Breaker

1,000.00
500.00
400.00
400.00
350.00
300.00
300.00
20.00
50.00
20.00
56.25
60.00
1,200.00
45.00
20.00
75.00
900.00
750.00
500.00

/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.

DAILY RATES

Timekeeper

Mixer Operator

HE Operator
Screeder Operator

220.00
200.00
150.00
175.00
175.00
185.00
145.00
175.00
160.00
185.00
185.00
175.00
160.00
175.00

/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day

A. GENERAL REQUIREMENTS
A.1 Mobilization/Demobilization
a. Mobilization
5 t/l @
b. Demobilization
5 t/l @

5,000.00

25,000.00

5,000.00

25,000.00

A.2 Bonds and Insurance


a. Performance Bond (20%)
TOTAL COST =
750,000,000.00 = A
Premium
=
A x 0.20 x 0.005
=
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

b. Surety Bond (Downpayment)


Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Municipality Tax
=

1,050,000.00
131,266.50
70.00
50.00
105,000.00
52,500.00
1,155.00
1,340,041.50

1,125,000.00
140,641.50
70.00
50.00
112,500.00
56,250.00
1,237.50
1,435,749.00

=
=
=

20%
A x 0.20 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011

=
=

c. Surety ,Warranty & Guarantee Bond (Retention) 30%


Premium
=
A x 0.30 x 0.005
=
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

d. Bid Bond 5%
Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=

750,000.00
93,766.50
70.00
50.00
75,000.00
37,500.00
825.00
957,211.50

=
=
=

A x 0.05 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=

262,500.00
32,829.00
70.00
50.00
26,250.00

Premium Tax
Municipality Tax

=
=

Premium x 0.05
Premium x 0.0011

e. Contractor's All Risk Insurance 100%


Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Municipality Tax
=

=
=
P

13,125.00
288.75
335,112.75

1,875,000.00
234,391.50
70.00
50.00
187,500.00
93,750.00
2,062.50
2,392,824.00

87,500.00
10,954.00
70.00
50.00
8,750.00
4,375.00
96.25
111,795.25

A x 0.0025
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011

=
=

A = 20,000,000.00
f. Comprehensive General Liability Insurance 100%
Premium
= For 3 m = 10,000.00
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=

=
=
=

A.3 Building and Occupancy Permits


a. Building Permit
54,730.62 sq.m. @

45.00 /sq.m.

2,462,877.90

b. Occupancy Permit
54,730.62 sq.m.

25.00 /sq.m.

1,368,265.50

c. Sidewalk & Road Permit


300.00 sq.m.

750.00 /sq.m.

225,000.00

150.00 sq.m. @

500.00 /cu.m.

75,000.00

d. Temfacil Permit

A.4 Temporary Facilities


a. Contractor's Field Office
b. CM Temporary Office
c. Bunkhouses
d. Kitchen
e. CR
f. Billboard
g. Safety Net
h. Portalet
A.5 Power and Water Consumptions

40.00 sq.m. @

3,500.00

400.00 sq.m. @
36.00 sq.m. @
18.00 sq.m. @

500.00
500.00
10,000.00

5.00 rental/mo.

7,500.00

=
=
=
=
=
=
=
=

140,000.00
250,000.00
200,000.00
18,000.00
180,000.00
120,000.00
37,500.00

Thi
insu
ma
nat

T
in
p
a

a.
b.
c.
c.

Power Consumptions
Water Consumptions
Deepwell Construction
Telephone Bill

A.6 Equipment Utilization


a. Tower Crane
b. Lifting Machine
c. Garbage Chute
d. Tamaraw

10,000.00
2,500.00

for
for

19.00 mos. =
19.00 mos. =

2,000.00

for

19.00 mos. =

180,000.00
54,000.00
30,000.00
108,000.00

for
for
for
for

16.00
8.00
8.00
4.00

mos.
mos.
mos.
mos.

190,000.00
47,500.00
100,000.00
38,000.00

=
=
=
=

2,880,000.00
432,000.00
240,000.00
432,000.00

B. SITEWORKS
Item 102-2
Grade Line Cut (Ord. Soil)
A. Equipment
1.00 - Bulldozer D80A-12, 180 HP
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1.00
5.00
2.00
3.00

B. Labor

C. Output

- Foreman
- Laborer
- Operator
- Driver
VAT, 10%
Sub-total

100.00 cu.m./hr.

D. Fuel & Oil


Bulldozer
Payloader
Dumptruck

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
DIRECT UNIT COST
Item Backfilling
104-3
& Compaction

COST

24.125 lit.
10.00 lit.
27.75 lit.

=
=
=

117.38 liters
11.74 liters

=
P

P
86.68 /cu.m.

A. Equipment
3 - Dump Truck
1 - Road Roller
1 - Payloader
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

65.00 cu.m./hr.

D. Fuel & Oil


Dump Truck
Road Roller
Payloader

27.75 lit.
14.00 lit.
2.28 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

99.53 liters
9.95 liters

T O TAL

COST

LABOR UNIT COST

65.00
107.60

*****
DIRECT UNIT COST =

107.60 /cu.m.

Item 102-3
Excavation (Adobe)
A. Equipment
1.00 - Backhoe
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1.00 - Foreman
5.00 - Laborer
2.00 - Operator

B. Labor

3.00 - Driver
VAT, 10%
Sub-total
C. Output

60.00 cu.m./hr.

D. Fuel & Oil


Backhoe
Payloader
Dumptruck

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL

COST

24.125 lit.
10.00 lit.
27.75 lit.

=
=
=

117.38 liters
11.74 liters

DIRECT UNIT COST =

P
139.88 /cu.m.

TRIMMING
A. Labor
1.00 - Foreman
5.00 - Laborer
VAT, 10%
B. Output

2.00 sq.m./hr.

DIRECT UNIT COST =

116.88 /sq.m.

Item Aggregate
200-1
Sub-Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

50.00 cu.m./hr.

D. Fuel & Oil


Road Grader
Road Roller
Water Truck

8.00 lit.
14.00 lit.
5.44 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

27.44 liters
2.74 liters

E. Materials, Aggregate Sub-Base Coarse with 20% shrinkage factor


60.00 cu.m. Agg.Sub-base Coarse
Sub-total
T O TAL

COST

DIRECT UNIT COST =

P
593.72 /cu.m.

Item Aggregate
201-1
Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total

1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total

B. Labor

C. Output

50.00 cu.m./hr.

D. Fuel & Oil


Road Grader
Road Roller
Water Truck

8.00 lit.
14.00 lit.
5.44 lit.

=
=
=

Fuel
=
Oil, 10% of Fuel =
Sub-total

27.44 liters
2.74 liters

E. Materials, Aggregate Sub-Base Coarse with 20% shrinkage factor

60.00 cu.m. Agg.Base Coarse


Sub-total
T O TAL

COST

DIRECT UNIT COST =

P
953.72 /cu.m.

Item Portland
311-2
Cement Concrete Pavement PCCP

0.15 mthick)

Assume Quantity
L
W
A
V

=
=
=
=

100.00
6.00
600.00
90.00

m.
m.
sq.m.
cu.m.

A. Materials:
a. Concrete Mix delivered @ jobsite
90.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12

6.00 in.

For 100.00m Preparation


No.of Center forms & key =
No.of Side forms
=
Total no.of bft.
=
For
100.00 m.preparation =
For 3 times usage
=
Sub-total
c.Steel bars
i.Dowels: 5/8"dia. x0.76m @ 0.75 moc
Wt/pc. = 0.76x1.57
=
No.of pcs. = 100.00/0.75 =
For width,every 100.00m (4 pcs.)
(100/100)x4x2
=
Total no.of dowels =
Wt
=
ii.Steel Pins : 1/2"dia. x 0.20m @ 0.75 moc
Wt.of/pc. = 0.20 x 0.888 =
No. of Pins =(100/0.75)x2 =
For 5 times usage=
Total Wt
=
Sub-total
d.Diamond Blade

10.00 bft.
3.33
10.00

444.33
333.33
777.67
777.67
259.22 bft.

1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.

0.18
266.67
53.33
9.47

kgs.
pcs.
pcs.
kgs.

Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=
No. of blades = 133.33/350 =
Sub-total

133.33
0.38 blades

e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total

0.0040 m
467.33 m
1.88 cu.m.
0.44 MT

f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total

266.67
88.89
2.22 kgs.

g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost

21.43 gals.

Output = 77.00 cu.m./day or 513.00 sq.m./day


No.of days = 3,000/513.00 6
=.00
days
B. Manpower:
1.00
2.00
2.00
4.00
5.00
7.00

- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost

350.00 /day
270.00
270.00
300.00
300.00
270.00

6.00
6.00
6.00
6.00
6.00
6.00

56.25 /day
60.00 /day
1,200.00 /day

4.00
4.00
1.00

C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost

T O TAL

COST

DIRECT UNIT COST =

P
523.02 /sq.m.

Item Portland
311-2
Cement Concrete Pavement PCCP

0.2 mthick)

Assume Quantity
L
W
A
V

=
=
=
=

100.00
6.00
600.00
120.00

m.
m.
sq.m.
cu.m.

A. Materials:
a. Concrete Mix delivered @ jobsite
120.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12

6.00 in.

For 100.00m Preparation


No.of Center forms & key =
No.of Side forms
=
Total no.of bft.
=
For
100.00 m.preparation =
For 3 times usage
=
Sub-total
c.Steel bars
i.Dowels: 5/8"dia. x0.76m @ 0.75 moc
Wt/pc. = 0.76x1.57
=
No.of pcs. = 100.00/0.75 =
For width,every 100.00m (4 pcs.)
(100/100)x4x2
=
Total no.of dowels =
Wt
=
ii.Steel Pins : 1/2"dia. x 0.20m @ 0.75 moc
Wt.of/pc. = 0.20 x 0.888 =
No. of Pins =(100/0.75)x2 =
For 5 times usage=
Total Wt
=
Sub-total
d.Diamond Blade
Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=

10.00 bft.
3.33
10.00

444.33
333.33
777.67
777.67
259.22 bft.

1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.

0.18
266.67
53.33
9.47

kgs.
pcs.
pcs.
kgs.

133.33

No. of blades = 133.33/350 =


Sub-total

0.38 blades

e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total

0.0040 m
467.33 m
1.88 cu.m.
0.44 MT

f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total

266.67
88.89
2.22 kgs.

g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost

21.43 gals.

Output = 77.00 cu.m./day or 513.00 sq.m./day


No.of days = 3,000/513.00 6
=.00
days
B. Manpower:
1.00
2.00
2.00
4.00
5.00
7.00

- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost

350.00 /day
270.00
270.00
300.00
300.00
270.00

6.00
6.00
6.00
6.00
6.00
6.00

56.25 /day
60.00 /day
1,200.00 /day

4.00
4.00
1.00

C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
DIRECT UNIT COST =

COST

=
P

P
656.27 /sq.m.

ITEMConcrete
502
Curbs & Gutter
1.Materials:
a.Forms : 100 bft.(Good for 60.00 m)
b.C.W.Nails:20 kgs.(Good for 60.00 m)
c.Concrete Volume = (0.15x0.15)+(0.00x0.00)=0.025 cu.m.
Cement = 0.09 x 9 =
Sand = 0.09 x 0.50 =
Gravel = 0.09 x 1.00 =
Sub-total

1.67 @
0.33

52.00
24.00

0.81
0.05
0.09

210.00
200.00
900.00

A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total

50.00

1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total

43.75
37.5
33.75

2.Manpower:

3.Fuel and Oil


Plate Compactor
Oil,10 % of fuel =
Sub-total
4.Output =

1.05 liters
0.11 liters

55.00
45.00

20.00 lm./hr.
Direct Cost =

19.62 /lm.

B.Placing and removal of Forms

1.Manpower:
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
2.Output =

43.750
37.500
33.750

11.00 lm./hr.
Direct Cost =

25.38 /lm.

C.Pouring and Finishing


1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total

45.00
60.00

2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total

43.75
37.50
33.75

3.Fuel and Oil


1-Bagger Mixer
Concrete Vibrator

3.00
1.05
4.05 liters
0.41 liters

Oil,10 % of fuel =
Sub-total
4.Output =

55.00
45.00

10.00 lm./hr.
Direct Cost =

DIRECT UNIT COST =

ITEMConcrete
601
Sidewalk
Assume Quantity = 100.00 sq.m.
Thickness =
0.10 m
1.Materials:
a.Forms : 4 bft./sq.m. x 100/3
Used 3 times
b.C.W.Nails:0.02 kgs./bft.x4x100 =
Cement = 10.00 x 9 =
Sand = 10.00 x 0.45 =
Gravel = 10.00 x 0.90 =
Sub-total

63.56 /lm.
P

463.33 /lm.

Volume =
133.33 @
8.00
90.00
4.50
9.00

10.00
52.00
24.00
210.00
200.00
900.00

A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total

50.00 /day

1.00

350.00 /day
300.00
270.00

1.00
1.00
1.00

2.Manpower:
1.00 Foreman
1.00 Operator
5.00 Laborers

VAT, 10%
Sub-total
3.Fuel and Oil
Vibrator Plate =
Oil,10 % of fuel =
Sub-total
4.Output =

1.05 liters
0.11 liters

55.00
45.00

20.00 lm./hr.

B.Placing and removal of Forms


1.Manpower:

Output =

60.00 sq.m./day
350.00 /day
300.00
270.00

1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
C.Pouring and Finishing
1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total

1.75
1.75
1.75

45.00 /hr.
60.00

2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total

350.00 /day
300.00
270.00

1.75
1.75
1.75

3.00
1.05
4.05 liters
0.41 liters

55.00
45.00

3.Fuel and Oil


1-Bagger Mixer
Concrete Vibrator
Oil,10 % of fuel =
Sub-total
DIRECT UNIT COST =

449.60 /sq.m.

C. MASONRY WORKS
a. 6" CHB (750 psi) Load Bearing
a.Materials
12.50 pcs. 6" CHB (Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand

@
@

21.50
210.00
200.00

3.00 kgs. Grade 33 Rebars


0.05 Ga.# 16 GI Wires

b. 4" CHB (750 psi) Load Bearing


a.Materials
12.50 pcs. 4"CHB (Load Bearing)
0.54 bags Cement
0.05 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

c. 6" CHB (400 psi) Non-Load Bearing


a.Materials
12.50 pcs. 6" CHB (Non-Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

d. 4" CHB (400 psi) Non-Load Bearing


a.Materials
12.50 pcs. 4"CHB (Non-Load Bearing)
0.54 bags Cement
0.05 cu.m. Sand
3.00 kgs. Grade 33 Rebars
0.05 Ga.# 16 GI Wires

e. 6"x6"x12" Louver Blocks


a.Materials
24.00
0.49
0.04
2.25
0.04

pcs. 6"x6"x12" Louver Blocks


bags Cement
cu.m. Sand
kgs. Grade 33 Rebars
Ga.# 16 GI Wires

19.50
210.00
200.00
36.30
36.00
M=

@
@

10.00
210.00
300.00
33.00
36.00
M=

@
@

8.00
210.00
300.00
33.00
36.00
M=

@
@

10.50
210.00
200.00
36.30
36.00
M=

@
@

f. Lightweight Concrete (fc' = 1,200 psi) Density = 80 to 100 pcf


a.Materials (Job Mixed)
8.00 bag Cement (Portland)
(8-18 bags/cm)
4.00 bag Perlite Concrete Grade (12 kgs./bag)
4.00 bag Light Aggregates (Dead Gravel)
0.68 cu.m. Sand (24 cu.ft.)
0.70 gal. Air Entraining Agent
1.00 bag Fibrin (2 lbs./bag)
b. Labor (Job Mixed Concrete)

36.30
36.00
M=

210.00
130.00
120.00
200.00
135.00
600.00
M=
L=

For One (1) Bagger Mixer (V = 0.125 cu.m.)


1.00 bag Portland Cement
1/2 bag Perlite Concrete Grade
3.00 cu.ft. Sand
1/2 pint Air Entraining Agent
1/8 bag Fibrin
g. Glass Block (8" x 8")
a. Materials
25.00 pcs. 8" x 8" Glass Block
12.50 kls. ABC Grout

150.00
60.00
M=

210.00
200.00
M=

210.00
200.00
M=

210.00
200.00
900.00
M=

210.00
200.00
900.00
M=

210.00
200.00
80.00
M=

FLOOR FINISHES
a. Patterned Cement Finish
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand

b. Plain Cement Floor Topping


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand

c. Plain Cement Floor Topping w/ Hardener


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
0.100 bag Floor Hardener
4 kls./sq.m.- 40 kls. /bag
d. Straight to Finish Floor Topping w/ Hardener
a.Materials
0.140 bag Cement(Portland)
0.011 cu.m. Sand
0.100 bag Floor Hardener
4 kls./sq.m.- 40 kls. /bag
e. Red Cement Topping
a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
0.250 kgs. Red Cement

f. Beige Peeble Washout Finish(By Area)

a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding

210.00
200.00
3.50

ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles

g. Beige Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.147 bag Cement(Portland)
0.011 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Beige Pebbles

h. Black Peeble Washout Finish(By Area)


a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Black Pebbles

i. Black Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.147 bag Cement(Portland)
0.011 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Black Pebbles

j. Beige Peeble Washout Finish(By Area) Deck w/ wire mesh


a.Materials
i.Scratch Coat
0.700 bag Cement(Portland)
0.054 cu.m. Sand
1.000 sq.m. Wire Mesh
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)

210.00
90.00
M=

210.00
200.00
210.00
90.00
M=

210.00
200.00
3.50
210.00
45.00
M=

210.00
200.00
210.00
45.00
M=

210.00
200.00
45.00
3.50
210.00

1.250 cans #10 Beige Pebbles

k. Plain Cement Finish w/ Peeble Washout Nosing


a.Materials
i.Scratch Coat
0.168 bag Cement(Portland)
0.013 cu.m. Sand
1.640 lft.kd Tang.moulding
ii.Final Coat
0.031 bag Cement(Portland)
0.063 cans #10 Ass. Pebbles

l. Peeble Washout Finish w/ 8"x8" Tile Pattern


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.625 bag Cement(Portland)
4.000 pcs.8"x8"Floor Tiles
0.100 kls. ABC Grout
1.250 cans #10 Ass. Pebbles

l. 12"x12" Vigan Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.219 bag Cement(Portland)
12.000 pcs.12"x12"Vigan Tiles
0.250 kls. Colored Cement
0.438 cans #10 Ass. Pebbles

m. 8" x 8" Vit. Floor Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.150 bag Cement(Portland)
9.000 pcs.8"x8"Vit. Floor Tiles
0.375 kls. ABC Grout
0.300 cans #10 Ass. Pebbles

90.00
M=

210.00
200.00
3.50
210.00
45.00
M=

210.00
200.00
210.00
14.00
60.00
45.00
M=

210.00
200.00
210.00
10.00
80.00
65.00
M=

210.00
200.00
210.00
14.00
60.00
45.00
M=

n. 25mm thk. Granite Slab


a.Materials
0.490
0.037
1.000
10.000

bag Cement (Portland)


cu.m. Sand
sq.m. Granite Slab
% Consumables
Materials
Labor

o. 300x300 Ceramic Tiles w/ Peeble Washout Border


a.Materials
i.Scratch Coat
0.560 bag Cement(Portland)
0.043 cu.m. Sand
ii.Final Coat
0.150 bag Cement(Portland)
9.000 pcs.12"x12"Ceramic Tiles
0.375 kls. ABC Grout
0.300 cans #10 Ass. Pebbles

210.00
200.00
4,500.00

210.00
200.00
210.00
35.00
60.00
45.00
M=

p. Vinyl Tiles (Tajima)


a. Materials
12.00 pcs. 12"x12"x3.0 mmthk. Vinyl Tiles
0.060 gal. Vinyl Adhesives

28.00
550.00

12.00 pcs. 12"x12"x3.0 mmthk. Vinyl Tiles


0.060 gal. Vinyl Adhesives

24.00
550.00

r. 200x200 Non skid Tiles


a.Materials
0.560 bag Cement(Portland)
0.043 cu.m. Sand
25.000 pcs.8"x8"Non skid Tiles

210.00
200.00
12.50
M=

s. Concrete Paving Block (Keyhole Pattern)


a.Materials
0.490 bag Cement(Portland)
0.037 cu.m. Sand
40.000 pcs. Keyhole Pattern Bricks

210.00
200.00
10.50
M=

210.00

q. Vinyl Tiles (Matico)


a. Materials

t. 150x150 Ceramic Unglazed Floor Tiles


a.Materials
0.490 bag Cement(Portland)

0.500 kls. ABC Grout


0.037 cu.m. Sand
45.000 pcs.6"x6"Floor Tiles

u. 101x101 Vitrified Floor Tiles (Piedra Tiles)


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
90.000 pcs.4-1/4"x4-1/4"Floor Tiles

v. 200x200 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
25.000 pcs.8"x8"Floor Tiles

w. 100x200 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
50.000 pcs.4"x8"Floor Tiles

x. 450x450 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
5.000 pcs.18"x18"Floor Tiles

y. 300x300 Vitrified Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
12.000 pcs.12"x12"Floor Tiles

z. 300x300 Cotto Homogeneous Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand

60.00
200.00
10.50
M=

210.00
60.00
200.00
6.00
M=

210.00
60.00
200.00
14.00
M=

210.00
60.00
200.00
10.50
M=

210.00
60.00
200.00
75.00
M=

210.00
60.00
200.00
28.00
M=

210.00
60.00
200.00

12.000 pcs.12"x12"Floor Tiles

aa. 300x300 Synthetic Granite Floor Tiles


a.Materials
0.490 bag Cement(Portland)
0.500 kls. ABC Grout
0.037 cu.m. Sand
12.000 pcs.12"x12"Floor Tiles

ab. 600x600mm x19mm thk. Marble @ Counters w = 0.60m


a. Materials
0.294 bag Cement (Portland)
0.022 cu.m. Sand
0.600 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor

150.00
M=

210.00
60.00
200.00
120.00
M=

210.00
200.00
900.00

ac. 600x600mm x19mm thk. Marble @ Counters (Splashboard) w = 0.35m


a. Materials
0.172 bag Cement (Portland)
@
0.013 cu.m. Sand
0.350 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ad. 600x600mm x19mm thk. Marble @ Counters (Splashboard) w = 0.20m
a. Materials
0.098 bag Cement (Portland)
@
0.007 cu.m. Sand
0.200 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ae. 600x600mm x19mm thk. Marble @ Counters (Fascia Board) w = 0.15m
a. Materials
0.074 bag Cement (Portland)
@
0.006 cu.m. Sand
0.150 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
af. 600x600mm x19mm thk. Marble Slabs
a. Materials
0.490 bag Cement (Portland)

210.00
200.00
900.00

210.00
200.00
900.00

210.00
200.00
900.00

210.00

0.037 cu.m. Sand


1.000 sq.m. 0.60x0.60 Marbles
10.000 % Consumables
Materials
Labor
ag. 600x600mm x19mm thk. Lavatory Sidings w = 0.30m
a. Materials
0.147 bag Cement (Portland)
0.011 cu.m. Sand
0.300 sq.m. 0.20x0.20 Marbles
10.000 % Consumables
Materials
Labor
ah. Plain Cement Floor Topping w/ Chicken Wire Mesh
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand
1.000 sq.m. Chicken Wiremesh

ai. 2"x12" Ceramic Tile Nosing


a. Materials
12.000 pcs. Ceramic Tile nosing
10.000 % Consumables

200.00
950.00

210.00
200.00
900.00

210.00
200.00
45.00
M=

25.00
M=

aj. Expansion Joint and Contraction Joints (1/2"thk.)


a. Materials
3.280 lft. x 1/2"x6" Non-extruding Joint Fiiler (Cork type)
0.081 liter Sealant

ak. Expansion Joint and Contraction Joints (3/4"thk.)


a. Materials
3.280 lft. x 3/4"x6" Non-extruding Joint Fiiler (Cork type)
0.121 liter Sealant

al. Expansion Joint and Contraction Joints (1"thk.)


a. Materials
3.280 lft. x 1"x6" Non-extruding Joint Fiiler (Cork type)
0.161 liter Sealant

WALL FINISHES
a. 300x300 Synthetic Granite
a.Materials

25.00
880.00
M=

50.28
880.00
M=

50.43
880.00
M=

0.450
0.250
0.027
12.000

bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs. 12"x12" Granite Tiles
Materials

b. 101x101 Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
90.000 pcs.4-1/4"x4-1/4"Wall Tiles

c. 100x200 Vit. Wall Tiles


a.Materials
0.450
0.250
0.027
50.000

bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs.4"x8"Wall Tiles

d. 200x200 Ceramic Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
25.000 pcs.8"x8"Wall Tiles

d. 300x300 Ceramic Vit. Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
12.000 pcs.12"x12"Wall Tiles

e. 450x450 Ceramic Glazed Wall Tiles


a.Materials
0.450 bag Cement(Portland)
0.250 kls. ABC Grout
0.027 cu.m. Sand
5.000 pcs.18"x18"Wall Tiles

210.00
60.00
200.00
120.00

210.00
60.00
200.00
2.50
M=

210.00
60.00
200.00
10.50
M=

210.00
60.00
200.00
14.00
M=

210.00
60.00
200.00
28.50
M=

210.00
60.00
200.00
75.00
M=

f. Ordinary Bricks 2"x8"x1/2" (on Exterior Wall)


a.Materials
97.00 pcs. 2"x8"x1/2" Ordinary Bricks

2.50

0.424 bag Cement(Portland)


0.032 cu.m. Sand

1. Exterior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.424 bag Cement(Portland)
0.032 cu.m. Sand

b. Plain Cement Plaster Finish (By Area)RC Walls


a.Materials
0.150 gal. Cement Gum
0.501 bag Cement(Portland)
0.038 cu.m. Sand

2. Interior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.350 bag Cement(Portland)
0.027 cu.m. Sand

b. Plain Cement Plaster Finish (By Area)RC Walls


a.Materials
0.150 gal. Cement Gum
0.420 bag Cement(Portland)
0.032 cu.m. Sand

c. Plain Cement Plaster Finish (By LM) w = 0.50m.


a.Materials
0.245 bag Cement(Portland)
0.019 cu.m. Sand

d. Plain Cement Plaster Finish (By LM) w = 0.30m.


a.Materials
0.147 bag Cement(Portland)
0.011 cu.m. Sand

e. Plain Cement Plaster Finish (By LM) w = 0.15m.


a.Materials
0.074 bag Cement(Portland)
0.006 cu.m. Sand

210.00
200.00
M=

205.00
240.00
M=

208.00
210.00
200.00
M=

210.00
200.00
M=

208.00
210.00
200.00
M=

210.00
200.00
M=

210.00
200.00
M=

210.00
200.00

M=
f. Plain Cement Plaster Finish (By LM) w = 0.60m.
a.Materials
0.294 bag Cement(Portland)
0.022 cu.m. Sand

g. Plain Cement Plaster Finish (By Area) on Louver Blocks


a.Materials
0.054 bag Cement(Portland)
0.004 cu.m. Sand

h. Beige Peeble Washout Finish(By Area)


a.Materials
i.Scratch Coat
0.350 bag Cement(Portland)
0.027 cu.m. Sand
3.000 lft.kd Tang.moulding
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles

i. Beige Peeble Washout Finish(By LM)


a.Materials
i.Scratch Coat
0.105 bag Cement(Portland)
0.008 cu.m. Sand
ii.Final Coat
0.188 bag Cement(Portland)
0.375 cans #10 Beige Pebbles

210.00
200.00
M=

210.00
200.00
M=

210.00
200.00
3.50
210.00
90.00
M=

210.00
200.00
210.00
90.00
M=

CEILING FINISHES
a. 1/4"thk.Marine Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)
w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@
0.375 pcs. 1/4"x4'x8'Marine Plywood
0.400 kls. Assorted Nails
0.050 gal. Solignum

b. 1/4"thk.Ordinary Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@

52.00
355.00
24.00
525.00
M=

52.00

0.375 pcs. 1/4"x4'x8'Ordinary Plywood


0.400 kls. Assorted Nails
0.050 gal. Solignum

200.00
24.00
525.00
M=

c. 1/2"thk.Gypsum Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 1/2"x4'x8'Gypsum Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

c. 5/8"thk.Gypsum Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 5/8"x4'x8'Gypsum Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

c. 1/2"thk. Ficem Board Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)


w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
10.000 bd.ft. Rough Tanguile
@
0.375 pcs. 1/2"x4'x8' Ficem Board
0.400 kls. Assorted Nails
0.050 gal. Solignum

d. Retouching of Exposed Slab


a.Materials
0.014 bag Cement(Portland)
0.001 cu.m. Sand

e.5/8" thk. RH-90 Non-sagging Acoustic Tiles on Baked Enamel T-runners


a. Materials
13.500 lft. 15/16" Baked enamel T-runners
@
11.500 sq.ft. 5/8" x 24"x24" RH - 90 Non-sagging

f.5/8" thk. Minaboard Fissured Acoustic Tiles on Baked Enamel T-runners


a. Materials
13.500 lft. 15/16" Baked enamel T-runners
@
11.500 sq.ft. 5/8" x 24"x24" Minaboard Fissured

52.00
295.00
24.00
525.00
M=

52.00
296.00
24.00
525.00
M=

52.00
1,150.00
21.50
175.00
M=

210.00
200.00
M=

10.00
22.50
M=

300.00
20.00
M=

g. Cemboard Ceiling on Furring Channel


a. Materials
0.375 pc. 3/16"x4'x8' Cemboard
0.120 pc. x 10' Carrying Channel
0.200 pc. Metal Furring Channel x 12'
0.150 pc. Alum. Wall Angle x 10'
0.040 gal. RM Joint Compound
0.100 gross Buglehead self tapping screw

h. Gypsum Board Ceiling on Furring Channel


a. Materials
0.375 pc. 1/2"x4'x8' Gypsum Board
0.120 pc. x 10' Carrying Channel
0.200 pc. Metal Furring Channel x 12'
0.150 pc. Alum. Wall Angle x 10'
0.013 roll Gypsum Joint Tape
0.040 gal. RM Joint Compound
0.100 gross Buglehead self tapping screw

700.00
175.00
145.00
125.00
250.00
260.00
M=

295.00
175.00
145.00
125.00
300.00
250.00
260.00
M=

2,890.00
36.80
250.00
M=

770.00
5.50
137.50
M=

2,890.00
36.80
250.00
M=

770.00
5.50
137.50
M=

CONCRETE WORKS
a. Lintel Beams (For 6" CHB)
a. Materials
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
b. Labor
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks

b. Lintel Beams (For 4" CHB)


a. Materials
0.0350 cu.m. Concrete
3.3000 kg. Rebars
0.8000 sq.m. Formworks
b. Labor
0.0350 cu.m. Concrete
3.3000 kg. Rebars
0.8000 sq.m. Formworks

c. Stiffener Columns (For 6" CHB)


a. Materials
0.0250 cu.m. Concrete

2,890.00

2.0000 kg. Rebars


0.3000 sq.m. Formworks

36.80
M=

b. Labor
0.0250 cu.m. Concrete
2.0000 kg. Rebars
0.3000 sq.m. Formworks

d. Stiffener Columns (For 4" CHB)


a. Materials
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks

770.00
5.50
137.50
M=

2,890.00
36.80
M=

770.00
5.50
137.50
M=

275.00
18.125

275.00
18.125

250.00
120.00
Equipment Cost
10% VAT

20.63

b. Labor
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks

Item SP- 3 Hauling Works


a. Rebars
1 ELF
10 Laborers

Production
Unit Cost

=
=

b. Forms
1 ELF
10 Laborers

20,000.00 kgs./day
P

Production
Unit Cost

=
=

Demolition Works
a. Equipment (Demolition)
1.00 Compressor
2.00 Jackhammer

12.00 hrs./day
12.00

0.30 /kg.

12.00 hrs./day
12.00
750.00 sq.m./day
7.88 /sq.m.

b. Manpower
20.00 Laborers

Labor Cost
10% VAT
Total Cost / hr.
Duration =
c. Equipment (Hauling & Disposal)
1.00 Loader
2.00 Dump Truck

Duration =

12 hrs. for 15 days

700.00
500.00
Equipment Cost
10% VAT
6 hrs. for 6 days
Total Cost =

Item SP- 4 Cleaning,Hauling & Disposal of Debris

1 Dumptruck
10 Laborers

8.00 hrs./day
8.00

450.00
18.125

10 times per month for 8 months


Item SP- 5 Dewatering Works
Pump Rental
Fuel
Operator

1.00 hr.

Unit Cost
Item SP - 6 G.I. Sheet Temporary Fence (H = 3.00m)
a. Materials
20.00 bft. Coco Lumber
15.00 lft. Ga. # 26 Pre-painted Corrugated GI Sheets
0.015 kegs CW Nails
0.10 kgs. Roof Nails

Item SP - 7 Protection of Adjacent Properties


a. Materials
30.00 lft. Corr. G.I.Sheets
2.00 pcs.62mm dia. GI Pipes
6.00 pcs. Pipe Clamp
0.25 pc.32mmdia. Plain Round Bars
1.00 pc.10mmdia.
-do2.00 pcs. Coil bolt w/ waler washer
b. Labor (Installation)

50.00
15.00
20.00
=

6.00
40.00
950.00
85.00
Unit Cost =

26.00
525.00
75.00
475.00
45.00
25
Unit Cost (M & L) =

Item SP - 8 Construction Safety Net


a. Materials
For 3.50 x 9 floors x 30.00 =
8.50
950.00
25.00
33.00
b. Labor (Installation)

945.00 sq.m.

lm. Ga. # 12 G.I. Wires


sq.m. Nylon Net (1/4" x 2.00 x 90.00m)
pcs. 10mm x 6.00m Plain Round Bars
pcs. 12mm x 6.00m
-do-

1.50
12.50
45.00
65.00

Unit Cost (M & L) =


Item SP - 9 100mm thk Wall w/ 50mm Rigid Insulation Welded Wire w/ 25mm thk. Plaster on Both Sides
a. Materials
4.00 lm. Carrying Channel
@
58.33
15.00 lm. Furring Channel
40.28
2.20 sq.m. Ga. # 22 Expanded Metal Lathe
140.00
2.50 lm. 16mm dia. Plain Round Bar
25.00
0.75 bag Cement
210.00
0.06 cu.m. Sand
200.00
1.10 sq.m. Rigid Insulation
140.00
Materials
Labor

Morales Shopping Mall


A. Vinyl Tiles

2 x 300 x 300 Vinyl Tiles


Vinyl Adhesive
Armstrong Imperial Series

12.00 pcs.
0.06 gal.

Installation
Polishing

12.00 tiles
12.00 tiles

Vinyl Cove Baseboard


Consumables

B. Plain Cement Floor Topping

3.28 ln.ft.
1.00 lot

23.00
525.00
Materials

3.50
2.40
Sub Total
VAT
Labor

26.50
3.08
Materials
Labor

P
P

Cement
Sand

II. Walls and Wall Finishes


A. 6" CHB Wall
6" CHB 350 psi
Cement
Sand
Grade 33 Rebars
GI Wires

B. 4" CHB Wall


4" CHB 350 psi
Cement
Sand
Grade 33 Rebars
GI Wires

0.70 bags
0.06 cu.m.

12.50
1.05
0.09
2.50
0.04

12.50
0.54
0.04
2.50
0.04

pcs.
bags
cu.m.
kgs.
kgs.

pcs.
bags
cu.m.
kgs.
kgs.

205.00
240.00
Materials
Labor

P
P

25.00
210.00
200.00
36.00
70.00
Materials
Labor

P
P

8.50
200.00
200.00
31.00
70.00
Materials
Labor

P
P

210.00
200.00
80.00
148.00
Materials
Labor

P
P

210.00
200.00
80.00
Materials
Labor

P
P

C. Exterior Plastering

Cement
Sand
ME 602 Mortar Enhancer
Sealopruf Integral Waterproofing

0.50
0.06
0.13
0.05

bags
cu.m.
liters
gal

D. Interior Plastering

Cement
Sand
ME 602 Mortar Enhancer

0.30 bags
0.03 cu.m.
0.08 liters

C.MATERIALS

50,000.00

4,179,910.00
0.5573%

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
45.
46.
47.

Premium Fuel
Diesel
Lubricating Oil
Gravel Fill
Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
CW Nails
Cement
Gravel
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)

This insurance is used to


insured construction
materials damaged by
natural calamity

This insurance is used to


insured critical adjacent
properties which might be
affected during construction.

4,131,143.40

945,500.00

Assume 1.50m per personnel/laborer


Assume 2.00m per unit

375,500.00

48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.

300x300x3.0mm Vinyl Tiles (Matico)


16x600x600 RH-90 Non-sagging Acoustic
16x600x600 Minaboard Fissured Acousti
19x600x600 Marble Slab incl. Polishing
CDS Marble
ABC Grout
6"x6" Louver Blocks
Beige Pebbles # 10
Beige Pebbles # 5
Black Pebbles # 10
Black Pebbles # 5
Assorted Pebbles
CW Nails
Concrete Paving Blocks (Keyhole Pattern
Solignum
Vinyl Adhesive
Ga. # 16 GI Wires
Kd Tanguile Moulding
Suspension Grid System
Boulders
1/2" x 1200 x 2400 Gypsum Board
5/8" x 1200 x 2400 Gypsum Board
1/2" x 1200 x 2400 Ficem Board
x 10' Carrying Channel
x 12' Furring Channel
x 10' Alum. Wall Angle
Gypsum Joint Tape
Ready Mix Joint Compound
Self Tapping Screw
4.5 x 1200 x 2400 Ficem Board
2mm x 100mm Flexible Vinyl Baseboard
3mm x 1/2" Brass Strip
Hanger rods
Chicken Wire Mesh
2"x12" Ceramic Tile Nosing
1/2"x3'x10' Joint Filler (Cork type)
3/4"x3'x10'
-do1"x3'x10'
-doSealant
Perlite Concrete Grade (CG) (12 kgs./bag
Air Entraining Agent (AEA)
Fibrin (2 lbs./ bag)
Light Aggregates (Dead Gravel)
8" x 8" Glass Block
300x300 Vigan Tiles
19x150 Wood Parquet
Flarefloor Rubber Tiles
3/4" Ord. Plywood
2"x8"x1/2" Ordinary Bricks

98.
99.
100.

3,984,000.00
A.EQUIPMENTS:

1,000.00 =
500.00 =
400.00 =
=
=

43.75
33.75
37.50
33.75

=
=
=
=
=

1,000.00
500.00
1,200.00
42.76
274.28
3,017.04 /hr.

43.75
168.75
75.00
101.25
38.88
427.63 /hr.

24.125
10.00
83.25
117.38 liters
40.00 =
45.00 =

8,667.85 /hr.

4,695.00
528.19
5,223.19 /hr.

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.

Dozer D8H w/ ripper


Payloader
Dump trucks
Grader
Roller
Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump
Screeder
Vibrator
Concrete Cutter
1-Bagger Mixer
Chainsaw
Portalift
Concrete Breaker
Backhoe
Trencher
B.MANPOWER:

1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.

Foreman
Leadman
Timekeeper
Carpenter
Mason
Steelman
Laborer
Floater
Mixer Operator
Painter
Welder
HE Operator
Driver
Screeder Operator

400.00 =
350.00 =
500.00 =
=
=

43.75
33.75
37.50
33.75

=
=
=
=
=

1,200.00
350.00
500.00
27.91
207.79
2,285.70 /hr.

43.75
101.25
75.00
33.75
25.38
279.13 /hr.

83.25
14.00
2.28
99.53 liters
40.00 =
45.00 =

3,981.20
447.89
4,429.09 /hr.

6,993.91 /hr.
/CU.M.
/CU.M.

750.00 =
500.00 =
400.00 =
=
=

43.75 =
33.75 =
37.50 =

750.00
500.00
1,200.00
42.76
249.28
2,742.04 /hr.

43.75
168.75
75.00

Granite Counter

33.75 =
=

101.25
38.88
427.63 /hr.

24.125
10.00
83.25
117.38 liters
40.00 =
45.00 =

4,695.00
528.19
5,223.19 /hr.

8,392.85 /hr.

43.75 =
33.75 =
=

43.75
168.75
21.25
233.75 /hr.

400.00 =
350.00 =
300.00 =
=
=

400.00
350.00
300.00
27.91
107.79
1,185.70 /hr.

43.75
33.75
37.50
33.75

=
=
=
=
=

43.75
101.25
75.00
33.75
25.38
279.13 /hr.

8.00
14.00
5.44
27.44 liters
40.00 =
45.00 =

1,097.60
123.48
1,221.08 /hr.

450.00 =

27,000.00
27,000.00 /hr.

29,685.91 /hr.

400.00 =
350.00 =
300.00 =
=
=

43.75
33.75
37.50
33.75

=
=
=
=
=

400.00
350.00
300.00
27.91
107.79
1,185.70 /hr.

43.75
101.25
75.00
33.75
25.38
279.13 /hr.

8.00
14.00
5.44
27.44 liters
40.00 =
45.00 =

1,097.60
123.48
1,221.08 /hr.

750.00 =

45,000.00
45,000.00 /hr.

47,685.91 /hr.

2,665.00

239,850.00
239,850.00

52.00 =

13,479.56
13,479.56

36.30 =

6,156.48

36.30 =

343.83
6,500.31

m.

days

day
day
day

10,400.00 =

3,961.90
3,961.90

13,500.00 =

5,976.45
5,976.45

24.00 =

53.33
53.33

40.00 =

857.14
857.14
P 270,678.70

451.13

2,100.00
3,240.00
3,240.00
7,200.00
9,000.00
11,340.00
3,612.00
39,732.00
39,732.00

66.22

450.00
240.00
2,400.00
309.00
3,399.00
3,399.00

5.67

=
=
=
=
=
=
=

=
=
=
=

313,809.70

2,665.00

m.

319,800.00
319,800.00

52.00 =

13,479.56
13,479.56

36.30 =

6,156.48

36.30 =

343.83
6,500.31

10,400.00 =

3,961.90
3,961.90

13,500.00 =

5,976.45
5,976.45

24.00 =

53.33
53.33

40.00 =

857.14
857.14
P 350,628.70

584.38

2,100.00
3,240.00
3,240.00
7,200.00
9,000.00
11,340.00
3,612.00
39,732.00
39,732.00

66.22

450.00
240.00
2,400.00
309.00
3,399.00
3,399.00

5.67

days

=
=
=
=
=
=
=

day
day
day

=
=
=
=

393,759.70

=
=

86.67
8.00

=
=
=
P

170.10
9.00
81.00
354.77

=
=
P

50.00
5.00
55.00

=
=
=
=

43.75
37.50
168.75
25.00
275.00

=
=
P

57.75
4.73
62.48

=
=
=
=
P

43.75
75.00
135.00
25.38
279.13

=
=
=
P

45.00
60.00
10.50
115.50

=
=
=
=
P

43.75
75.00
135.00
25.38
279.13

=
=
P

222.75
18.23
240.98

cu.m.
=

6,933.33

=
=
=
=
P

192.00
18,900.00
900.00
8,100.00
35,025.33

350.25

day

=
=
P

50.00
5.00
55.00

day

=
=
=

350.00
300.00
1,350.00

days
days
days

days
days
days

=
=
=

=
P

0.00
2,000.00

=
=
P

57.75
4.73
62.48

=
=
=
=
P

612.50
1,050.00
1,890.00
355.25
3,907.75

=
=
=
P

45.00
60.00
10.50
115.50

=
=
=
=
P

612.50
1,050.00
1,890.00
0.00
3,552.50

=
=
P

222.75
18.23
240.98

268.75
214.20
18.19

=
=
P

108.90
1.80
611.84 /sq.m.

=
=
=
=
=
P

243.75
113.40
9.63
108.90
1.80
477.48 /sq.m.

=
=
=
=
=
P

125.00
214.20
27.29
99.00
1.80
467.29 /sq.m.

=
=
=
=
=
P

100.00
113.40
14.45
99.00
1.80
328.65 /sq.m.

=
=
=
=
=
P

252.00
102.90
7.40
81.68
1.26
445.24 /sq.m.

=
=
=
=
=
=
P
P

1,680.00
520.00
480.00
136.05
94.50
600.00
3,510.55 /cu.m.
770.00 /cu.m.

=
=
P

3,750.00
750.00
4,500.00 /cu.m.

=
=
P

147.00
10.70
157.70 /sq.m.

=
=
P

117.60
8.56
126.16 /sq.m.

=
=
=
P

117.60
8.56
90.00
216.16 /sq.m.

=
=
=
P

29.40
2.14
90.00
121.54 /sq.m.

=
=
=
P

117.60
8.56
20.00
146.16 /sq.m.

=
=
=

102.90
7.49
10.50

=
=
P

131.25
112.50
364.64 /sq.m.

=
=

30.87
2.25

=
=
P

39.38
33.75
106.24 /lm.

=
=
=

102.90
7.49
10.50

=
=
P

131.25
56.25
308.39 /sq.m.

=
=

30.87
2.25

=
=
P

39.38
16.88
89.37 /lm.

=
=
=
=

147.00
10.70
45.00
10.50

131.25

=
P

112.50
456.95 /sq.m.

=
=
=

35.28
2.57
5.74

=
=
P

6.56
2.81
52.96 /lm.

=
=

117.60
8.56

=
=
=
=
P

131.25
56.00
6.00
56.25
375.66 /lm.

=
=

117.60
8.56

=
=
=
=
P

45.94
120.00
20.00
28.44
340.54 /lm.

=
=

117.60
8.56

=
=
=
=
P

31.50
126.00
22.50
13.50
319.66 /lm.

=
=
=
=
P
P

102.90
7.49
4,500.00
450.00
5,060.39 /lm.
220.00 /lm.

=
=

117.60
8.56

=
=
=
=
P

31.50
315.00
22.50
13.50
508.66 /lm.

=
=
P

336.00
33.00
369.00 /sq.m.

=
=
P

288.00
33.00
321.00 /sq.m.

=
=
=
P

117.60
8.56
312.50
438.66 /sq.m.

=
=
=
P

102.90
7.49
420.00
530.39 /sq.m.

102.90

=
=
=
P

30.00
7.49
472.50
612.89 /sq.m.

=
=
=
=
P

102.90
30.00
7.49
540.00
680.39 /sq.m.

=
=
=
=
P

102.90
30.00
7.49
350.00
490.39 /sq.m.

=
=
=
=
P

102.90
30.00
7.49
525.00
665.39 /sq.m.

=
=
=
=
P

102.90
30.00
7.49
375.00
515.39 /sq.m.

=
=
=
=
P

102.90
30.00
7.49
336.00
476.39 /sq.m.

=
=
=

102.90
30.00
7.49

=
P

1,800.00
1,940.39 /sq.m.

=
=
=
=
P

102.90
30.00
7.49
1,440.00
1,580.39 /sq.m.

=
=
=
=
P
P

61.74
4.49
540.00
54.00
660.23 /lm.
200.00 /lm.

=
=
=
=
P
P

36.02
2.62
315.00
31.50
385.14 /lm.
185.00 /lm.

=
=
=
=
P
P

20.58
1.50
180.00
18.00
220.08 /lm.
185.00 /lm.

=
=
=
=
P
P

15.44
1.12
135.00
13.50
165.06 /lm.
185.00 /lm.

102.90

=
=
=
P
P

7.49
950.00
95.00
1,155.39 /lm.
185.00 /lm.

=
=
=
=
P
P

30.87
2.25
270.00
27.00
330.12 /lm.
185.00 /lm.

=
=
=
P

147.00
10.70
45.00
202.70 /sq.m.

=
=
P

300.00
30.00
330.00 /sq.m.

=
=
P

82.00
70.94
152.94 /lm.

=
=
P

164.93
106.41
271.33 /lm.

=
=
P

165.42
141.87
307.29 /lm.

=
=
=
=
P

94.50
15.00
5.35
1,440.00
1,554.85 /lm.

=
=
=
=
P

94.50
15.00
5.35
225.00
339.85 /sq.m.

=
=
=
=
P

94.50
15.00
5.35
525.00
639.85 /sq.m.

=
=
=
=
P

94.50
15.00
5.35
350.00
464.85 /sq.m.

=
=
=
=
P

94.50
15.00
5.35
342.00
456.85 /sq.m.

=
=
=
=
P

94.50
15.00
5.35
375.00
489.85 /sq.m.

242.50

=
=
P

88.94
6.47
337.91 /sq.m.

=
=
P

86.82
7.77
94.59 /sq.m.

=
=
=
P

31.20
105.11
7.65
143.96 /sq.m.

=
=
P

73.50
5.35
78.85 /sq.m.

=
=
=
P

31.20
88.20
6.42
125.82 /sq.m.

=
=
P

51.45
3.75
55.20 /lm.

=
=
P

30.87
2.25
33.12 /lm.

=
=

15.44
1.12

16.56 /lm.

=
=
P

61.74
4.49
66.23 /lm.

=
=
P

11.34
0.80
12.14 /lm.

=
=
=

73.50
5.35
10.50

=
=
P

131.25
112.50
333.10 /sq.m.

=
=

22.05
1.61

=
=
P

39.38
33.75
96.78 /lm.

=
=
=
=
P

650.00
133.13
9.60
26.25
818.98 /sq.m.

650.00

=
=
=
P

75.00
9.60
26.25
760.85 /sq.m.

=
=
=
=
P

520.00
110.63
9.60
26.25
666.48 /sq.m.

=
=
=
=
P

520.00
111.00
9.60
26.25
666.85 /sq.m.

=
=
=
=
P

520.00
431.25
8.60
8.75
968.60 /sq.m.

=
=
P

2.94
0.21
3.15 /sq.m.

=
=
P

135.00
258.75
393.75 /sq.m.

=
=
P

4,050.00
230.00
4,280.00 /sq.m.

=
=
=
=
=
=
P

262.50
21.00
29.00
18.75
10.00
26.00
367.25 /sq.m.

119
119
119
119
119
119

45
14
24
18
5
12

=
=
=
=
=
=
=
P

110.63
21.00
29.00
18.75
3.75
10.00
26.00
219.13 /sq.m.

119
119
119
119
119
119
119

45
14
24
18
1
5
12

=
=
=
P

108.38
117.76
162.50
388.64 /l.m.

=
=
=
P

28.88
17.60
89.38
135.85 /l.m.

=
=
=
P

101.15
121.44
200.00
422.59 /l.m.

=
=
=
P

26.95
18.15
110.00
155.10 /l.m.

72.25

=
=
P

73.60
145.85 /l.m.

=
=
=
P

19.25
11.00
41.25
71.50 /l.m.

=
=
=
P

86.70
73.60
160.30 /l.m.

=
=
=
P

23.10
11.00
82.50
116.60 /l.m.

3,300.00
2,610.00
5,910.00

3,300.00
2,610.00
5,910.00

/hr.
/hr.

250.00
240.00
490.00
49.00
539.00 /hr.

/hr.

412.50

412.50
41.25
453.75
992.75 /hr.
180.00 hours
178,695.00
/hr.
/hr.

700.00
1,000.00
1,700.00
170.00
1,870.00 /hr.
36.00
67,320.00
246,015.00

3,600.00
1,740.00
5,340.00
427,200.00

/hr.
/hr.
/hr.

=
=
=

50.00
15.00
20.00
85.00 /hr./pump

=
=
=
=

120.00
600.00
14.25
8.50
742.75 /lm.

=
=
=
=
=
=
=
ost (M & L) =

780.00
1,050.00
450.00
118.75
45.00
50.00
997.50
3,491.25 /lm.

say

=
=
=
=
=

3,500.00 /lm.

12.75
11,875.00
1,125.00
2,145.00
7,578.88
22,736.63
24.06
25.00 /sq.m.

ost (M & L) =

=
=
=
=
=
=
=

233.33
604.17
308.00
62.50
157.50
12.00
154.00
1,531.50 /sq.m.
765.75 /sq.m.

276.00
31.50
307.50
42.00
28.80
70.80
7.08
77.88
86.92
3.08
90.00
22.00

143.50
13.20
156.70
104.00

312.50
220.50
18.00
90.00
2.80
643.80
110.00

106.25
108.00
8.00
77.50
2.80
302.55
104.00

105.00
11.00
10.00
7.40
133.40
139.00

63.00
6.60
6.00
75.60
115.50

UNIT COST
Premium Fuel
Lubricating Oil

Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade

Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)

55.00
40.00
45.00
900.00
150.00
450.00
750.00
2,665.00
52.00
36.30
40.00
13,500.00
10,400.00
24.00
210.00
900.00
430.00
200.00
355.00
375.00
55.00
28.00
21.50
19.50
10.00
8.00
80.00
900.00
10.50
6.00
35.00
28.00
10.50
14.00
75.00
150.00
4,500.00
12.50
120.00
10.50
14.00
2.50
28.50
75.00
4.00
25.00
6.00
28.00

/lit.
/lit.
/lit.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bft.
/kg.
/gal.
/MT
/pc.
/kl.
/bag
/cu.m.
/cu.m.
/cu.m.
/pc.
/pc.
/bft.
/pc.
/pc.
/pc.
/pc.
/pc.
/kl.
/kl.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.

300x300x3.0mm Vinyl Tiles (Matico)


16x600x600 RH-90 Non-sagging Acoustic Board
16x600x600 Minaboard Fissured Acoustic Board
19x600x600 Marble Slab incl. Polishing
CDS Marble
ABC Grout
6"x6" Louver Blocks
Beige Pebbles # 10
Beige Pebbles # 5
Black Pebbles # 10
Black Pebbles # 5
Assorted Pebbles
Concrete Paving Blocks (Keyhole Pattern)
Vinyl Adhesive
Ga. # 16 GI Wires
Kd Tanguile Moulding
Suspension Grid System
1/2" x 1200 x 2400 Gypsum Board
5/8" x 1200 x 2400 Gypsum Board
1/2" x 1200 x 2400 Ficem Board
x 10' Carrying Channel
x 12' Furring Channel
x 10' Alum. Wall Angle
Gypsum Joint Tape
Ready Mix Joint Compound
Self Tapping Screw
4.5 x 1200 x 2400 Ficem Board
2mm x 100mm Flexible Vinyl Baseboard
3mm x 1/2" Brass Strip
Hanger rods
Chicken Wire Mesh
2"x12" Ceramic Tile Nosing
1/2"x3'x10' Joint Filler (Cork type)
3/4"x3'x10'
-do1"x3'x10'
-do2,200.00/pack (2.50 liters)
Perlite Concrete Grade (CG) (12 kgs./bag)
Air Entraining Agent (AEA)
Fibrin (2 lbs./ bag)
Light Aggregates (Dead Gravel)
8" x 8" Glass Block
300x300 Vigan Tiles
19x150 Wood Parquet
Flarefloor Rubber Tiles
3/4" Ord. Plywood
2"x8"x1/2" Ordinary Bricks

24.00
90.00
80.00
950.00
900.00
60.00
10.50
90.00
90.00
45.00
45.00
65.00
24.00
10.50
525.00
550.00
36.00
3.50
10.00
300.00
295.00
296.00
1,150.00
175.00
145.00
125.00
300.00
250.00
260.00
700.00
23.00
30.00
25.00
45.00
25.00
1,500.00
3,017.00
3,026.00
880.00
130.00
135.00
600.00
120.00
150.00
10.00
60.00
1,300.00
1,100.00
2.50

/pc.
/pc.
/pc.
/sq.m.
/sq.m.
/kl.
/pc.
/can
/can
/can
/can
/can
/kl.
/pc.
/gal.
/gal.
/kl.
/lft.
/lft.
/cu.m.
/pc
/pc
/pc
/pc
/pc
/pc
/roll
/gal.
/gross
/pc.
/lft.
/lft.
/pc.
/sq.m.
/pc.
/pc.
/pc.
/pc.
/liter
/bag
/gal.
/bag
/bag
/pc.
/pc.
/sq.ft.
/sq.m.
/pc.
/pc.

275.00 /bag

38pcs./sq.m.

Labor
25.00 /sq.ft.
80.00 /sq.m.

RENTALS

Dozer D8H w/ ripper


Dump trucks

Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump

Concrete Cutter
1-Bagger Mixer

Concrete Breaker

1,000.00
500.00
400.00
400.00
350.00
300.00
300.00
20.00
50.00
20.00
56.25
60.00
1,200.00
45.00
20.00
75.00
900.00
750.00
500.00

/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.

DAILY RATES

Timekeeper

Mixer Operator

HE Operator
Screeder Operator

350.00
300.00
270.00
300.00
300.00
290.00
270.00
270.00
350.00
270.00
270.00
300.00
270.00
270.00

/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day

Granite Counter
Ovaline Hole
Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top
Material = actual + 25%

Type of Work

Labor Cost
1,100.00 / hole
150.00 / l.m.
420.00 / l.m.
420.00 / l.m.
450.00 / l.m.
85.00 / l.m.
420.00 / l.m.
1,600.00 / sq.m.

Unit

Excavation (Ordinary Soil)


cu.m.
Excavation (Adobe)
cu.m.
Trimming
sq.m
Backfill / Compaction
cu.m.
Sub-base Course
cu.m.
Base Course
cu.m.
Portland Cement Concrete Pavement 0.15m
sq.m
thk
Portland Cement Concrete Pavement 0.20m
sq.m
thk
Curve & Gutter
l.m
Concrete Sidewalk (100mm thk)
sq.m

Material

450.00
750.00
451.13
584.38
354.77
350.25

China

Labor
86.68
139.88
116.88
107.60
593.72
953.72
71.89
71.89
108.56
99.34

Granite Counter
Ovaline Hole
Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top
Material = actual + 25%

Labor Cost
/ hole
/ l.m.
/ l.m.
/ l.m.
/ l.m.
/ l.m.
/ l.m.

1,100.00
150.00
420.00
420.00
450.00
85.00
420.00

1,600.00 / sq.m.

China

COMPUTATION
Description

Qty.

Unit

Ovaline / Sink Hole


Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top

7.00
7.00
28.00
22.60
28.00
28.00
19.40

hole
hole
l.m.
l.m.
l.m.
l.m.
l.m.

Material = actual + 25%

14.55

Materials
unit cost
amount

1,600.00

Labor
unit cost

23,280.00

1,100.00
150.00
420.00
420.00
450.00
85.00
420.00

23,280.00
Total Amount
1200
3,938.66

COMPUTATION
Description
Ovaline / Sink Hole
Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top
Material = actual + 25%

Qty.
99.37
496.50
2,186.25
36.44

Unit

Materials
unit cost
amount

hole
hole
l.m.
l.m.
l.m.
l.m.
l.m.

3,000.00
450.00
34.00
55.00

1,600.00

Labor
unit cost

298,110.00
223,425.00
74,332.50
2,004.20
-

597,871.70
Total Amount

300.00
250.00
3.25
5.00
450.00
85.00
420.00

for Asphalt
Area x 0.05 x 2.33 = MT.
3.5 l.m.

Concrete Counter
concrete
formworks
rebars
g.i. wire

0.2625
3.5
16.716
0.2786

m
m
kgs
kgs

Qty.

Unit

2,700.00
250.00
46.00
50.00

700.00
185.00
3.75
5.00

3,400.00
435.00
49.75
55.00

COMPUTATION
Description
Ovaline / Sink Hole
Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top

2.00
-

hole
hole
l.m.
l.m.
l.m.
l.m.
l.m.

Materials
unit cost
amount

Labor
unit cost
-

1,100.00
150.00
420.00
420.00
450.00
85.00
420.00

Material = actual + 25%

0.30

2,500.00

750.00

750.00
Total Amount

487.50

316.88

conc.
reb
fw

plaster
conc.
reb
fw

0.135
27
2

391.50
810.00
700.00

101.25
101.25
400.00

0.9

1,901.50

602.50

316.92

100.42

2,112.78

669.44

352.13

111.57

65.25
135.00
116.67

16.88
16.88
66.67

316.92

100.42

120.00
208.80
96.00
280.00
704.80

96.00
54.00
12.00
160.00
322.00

0.80
0.07
3.20
0.80

Labor
amount
7,700.00
1,050.00
11,760.00
9,492.00
12,600.00
2,380.00
8,148.00
-

53,130.00
76,410.00

3,938.66
2,738.66
Labor
amount
29,811.00
124,125.00
7,105.31
182.20
-

161,223.51
759,095.21

795
954.84
752.04
202.80
4,893.50

18,523.83

94,933.83

892.50
1,522.50
831.62
15.32
3,261.94

708.75
875.00
768.94
13.93
2,366.62

183.75
647.50
62.69
1.39
895.33

88.64

676.18

255.81

4,027.30

Labor
amount
170.00
-

170.00
920.00

LIGHT & HEAVY EQUIPMENT RENTAL


Date (Updated): May 11,2010

Unit
Unit
I. Rentals
1. Heavy Equipment

a. Backhoe Sumitomo 1 (Excluded: optr. Salary)


i.
3/4 Bucket
b. Backhoe Kobelco 1 (Excluded: optr. Salary)
i.
1/2 Bucket
c. Bulldozer Komatsu 1 (Excluded: optr. Salary)
i.
D-155
d. Payloader 1 (Excluded: optr. Salary)
i.
RCM WA-450
e. Payloader 2 (Excluded: optr. Salary)
i.
TCM I-13
f. Miniloader 1 (Excluded: optr. Salary)
i.
Mitsubishi
g. Mobile Crane 1 (Excluded: optr. Salary)
i.
Kato
h. Forklift 1 (Excluded: optr. Salary)
i.
TCM 5 tonner
i. Skid Steer Loader (Excluded: optr. Salary)
i.
Bobcat S-160
j. Skid Steer Loader (Excluded: optr. Salary)
i.
Bobcat 743
k. Roller Compactor (Excluded: optr. Salary)
i.
Bomag
l. Roller Compactor (Excluded: optr. Salary)
i.
Walkbehind
m. Air Compressor
i.
Ingersorand
n. Air Compressor
i.
Atlas Copco
o. Generator Set
i.
Cummins 125 kva
p. Generator Set
i.
Airman 100 kva
k. Generator Set
i.
Elemax 75 kva
1. Light Equipment
a. Automatic Cutting Machine
b. Water Pump - Robin
c. Concrete Vibrator
d. Concrete Cutter
e. Power Trowel
f. Tamping Rammer
g. Jack Hammer
h. Chipping Hammer
i. Air Compressor Big
j. Air Compressor Small
k. Dumpy Level w/ Accessories
l. Jet Matic
m. Power Sprayer
n. Welding Machine 500amps

Supplier A
Rate/Hour

Supplier name

unit

PHP 1,900.00

FEMD

unit

PHP 1,700.00

FEMD

unit

PHP 1,800.00

FEMD

unit

PHP 1,600.00

FEMD

unit

PHP 1,300.00

FEMD

unit

PHP 800.00

FEMD

unit

PHP 2,500.00

FEMD

unit

PHP 1,800.00

FEMD

unit

PHP 700.00

FEMD

unit

PHP 700.00

FEMD

unit

PHP 600.00

FEMD

unit

PHP 800.00

FEMD

unit

PHP 3,000.00

FEMD

unit

PHP 3,000.00

FEMD

unit

PHP 300.00

FEMD

unit

PHP 300.00

FEMD

unit

PHP 300.00

FEMD

unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit

PHP 15,000.00
PHP 1,200.00
PHP 1,200.00
PHP 1,500.00
PHP 1,200.00
PHP 1,500.00
PHP 300.00
PHP 1,200.00
PHP 18,000.00
PHP 8,000.00
PHP 30,000.00
PHP 28,000.00
PHP 12,000.00
PHP 12,000.00

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

Supplier B
Rate/Hour

o.
p.
k.
l.
m.
n.
o.
p.
q.
r.
s.
t.

Welding Machine 300amps


Chain Block
Chain Saw
Jack Stand
Crocodile Jack
Cutting Outfit w/ Oxygen and Mgas
Rebar Bender
Rebar Cutter
Submersible Pump #3
Submersible Pump #4
Submersible Pump #5
Tower Crane Bucket
Pipe Cutter
Press Drill
Bench Grinder
Bagger Mixer
Cut-off Wheel Machine
Water Tank (drum)
Concrete Cutter
Hilti Heavy Duty Drill
Hand Drill Big
Hand Drill Small
Electrical Drill
Grinder Big
Grinder Small
Mixed for CHB
Moulding Motor
Lifting Belt
Stainless Cutter

unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit

PHP 6,000.00
PHP 3,000.00
PHP 8,000.00
PHP 1,500.00
PHP 15,000.00
PHP 1,000.00
PHP 1,100.00
PHP 1,100.00
PHP 6.50
PHP 7.40
PHP 9.20
PHP 400.00
PHP 10,000.00
PHP 4,000.00
PHP 4,000.00
PHP 1,200.00
PHP 10,000.00
PHP 1,000.00
PHP 600.00
PHP 600.00
PHP 3,000.00
PHP 2,500.00
PHP 2,500.00
PHP 3,000.00
PHP 1,500.00
PHP 1,600.00

Note

Per Day
Per Month

PHP 2,500.00
PHP 6,000.00

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

LABOR RATES
Unit Cost
Supplier B
Supplier name

Supplier C
Rate/Hour

Applied Rate

Supplier name
1,900.00
1,700.00
1,800.00
1,600.00
1,300.00
800.00
2,500.00
1,800.00
700.00
700.00
600.00
800.00
3,000.00
3,000.00
300.00
300.00
300.00
15,000.00
1,200.00
1,200.00
1,500.00
1,200.00
1,500.00
300.00
1,200.00
18,000.00
8,000.00
30,000.00
28,000.00
12,000.00
12,000.00

Item
I. Indirect Manpower
1. Accountant
2. Cadet Engineer
3. Carpenter
4. Cost Engineer
5. Driver
6. Electrician
7. Field Engineer
8. Foreman
9. Glass Installer
10. Guard
11. Heavy Equipment Operator
12. Laborer
13. Leadman
14. Mason
15. Mechanic
16. Messenger
17. Mixer Operator
18. Painter
19. Plumber
20. Project In-charge
21. Screeder Operator
22. Steelman
23. Surveying Aide
24. Surveyor
25. Tile Setter
26. Timekeeper
27. Utility
28. Utility
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32. General Manager
33. General Foreman
34. Safety Officer
35. Mason - Plasterer (int)
36. Mason - Plasterer (ext)
37. Mason - CHB Layer
38. Mason Finisher
39.
40.

1
Provincia
Minimum
375.00
250.00
280.00

400.00
250.00

6,000.00
3,000.00
8,000.00
1,500.00
15,000.00
1,000.00
1,100.00
1,100.00
6.50
7.40
9.20
400.00
10,000.00
4,000.00
4,000.00
1,200.00
10,000.00
1,000.00
600.00
600.00
3,000.00
2,500.00
2,500.00
3,000.00
1,500.00
1,600.00
2,500.00
6,000.00

1
Provincial Rate
Maximum
400.00
375.00
300.00

2
Manila Rate
Minimum
Maximum
450.00
400.00
310.00

500.00
475.00

400.00

450.00
280.00

350.00

400.00

500.00
270.00
350.00
350.00

600.00
300.00
400.00
380.00

310.00

310.00

340.00
330.00

350.00
350.00

330.00

350.00

350.00
835.00
400.00
330.00
340.00
360.00
300.00
320.00

350.00
1,000.00
450.00
350.00
350.00
380.00
310.00

Applied Rate

500
475
0
0
400
0
0
400
0
0
600
300
400
380
0
0
0
0
0
0
0
310
0
0
350
350
0
0
350
0
350
1000
450
350
350
380
310
0

Rate per Hour Location of Project:

62.5
59.375
0
0
50
0
0
50
0
0
75
37.5
50
47.5
0
0
0
0
0
0
0
38.75
0
0
43.75
43.75
0
0
43.75
0
43.75
125
56.25
43.75
43.75
47.5
38.75
0

LABOR RATES
Item
I. Indirect Manpower
1. Accountant
2. Cadet Engineer
3. Carpenter
4. Cost Engineer
5. Driver
6. Electrician
7. Field Engineer
8. Foreman
9. Glass Installer
10. Guard
11. Heavy Equipment Operator
12. Laborer
13. Leadman
14. Mason
15. Mechanic
16. Messenger
17. Mixer Operator
18. Painter
19. Plumber
20. Project In-charge
21. Screeder Operator
22. Steelman
23. Surveying Aide
24. Surveyor
25. Tile Setter
26. Timekeeper
27. Utility
28. Utility
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32. General Manager
33. General Foreman
34. Safety Officer
35. Mason - Plasterer (int)
36. Mason - Plasterer (ext)
37. Mason - CHB Layer
38. Mason Finisher

1
2
Provincial Rate
Manila Rate
Minimum Maximum Minimum Maximum
375.00
250.00
280.00

400.00
375.00
300.00

450.00
400.00
310.00

500.00
475.00
350.00
400.00

350.00

400.00

400.00
250.00

450.00
280.00

500.00
270.00
350.00
350.00

600.00
300.00
400.00
380.00

400.00

500.00

550.00

750.00

310.00

310.00

340.00
330.00

350.00
350.00

330.00

350.00

350.00
835.00
400.00
330.00
340.00
360.00
300.00
320.00

350.00
1,000.00
450.00
350.00
350.00
380.00
310.00

Applied Rate

500
475
350
0
400
0
0
400
0
0
600
300
400
380
0
0
0
0
0
750
0
310
0
0
350
350
0
0
350
0
350
1000
450
350
350
380
310
0

Rate per Hour Location of Project:

62.5
59.375
43.75
0
50
0
0
50
0
0
75
37.5
50
47.5
0
0
0
0
0
93.75
0
38.75
0
0
43.75
43.75
0
0
43.75
0
43.75
125
56.25
43.75
43.75
47.5
38.75
0

Premium Fuel
Diesel
Lubricating Oil
Gravel Fill
Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
CW Nails
Cement
Gravel
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles

42.00
38.00
45.00
440.00
150.00
250.00
270.00
2,557.00
42.00
31.00
40.00
13,500.00
10,400.00
24.00
198.00
440.00
300.00
400.00
355.00
375.00
51.00
17.50
21.50
19.50
10.00
8.00
80.00
900.00
10.50
6.00
35.00
28.00
10.50
14.00
75.00
150.00
4,500.00
12.50
120.00
10.50
14.00
2.50
28.50
75.00
4.00
25.00

/lit.
/lit.
/lit.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bft.
/kg.
/gal.
/MT
/pc.
/kl.
/bag
/cu.m.
/cu.m.
/cu.m.
/pc.
/pc.
/bft.
/pc.
/pc.
/pc.
/pc.
/pc.
/kl.
/kl.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.

100x100 Binangonan Rocks


300x300x3.0mm Vinyl Tiles (Tajima)
300x300x3.0mm Vinyl Tiles (Matico)
16x600x600 RH-90 Non-sagging Acoustic Board
16x600x600 Minaboard Fissured Acoustic Board
19x600x600 Marble Slab incl. Polishing
CDS Marble
ABC Grout
6"x6" Louver Blocks
Beige Pebbles # 10
Beige Pebbles # 5
Black Pebbles # 10
Black Pebbles # 5
Assorted Pebbles
CW Nails
Concrete Paving Blocks (Keyhole Pattern)
Solignum
Vinyl Adhesive
Ga. # 16 GI Wires
Kd Tanguile Moulding
Suspension Grid System
Boulders
1/2" x 1200 x 2400 Gypsum Board
5/8" x 1200 x 2400 Gypsum Board
1/2" x 1200 x 2400 Ficem Board
x 10' Carrying Channel
x 12' Furring Channel
x 10' Alum. Wall Angle
Gypsum Joint Tape
Ready Mix Joint Compound
Self Tapping Screw
4.5 x 1200 x 2400 Ficem Board
2mm x 100mm Flexible Vinyl Baseboard
3mm x 1/2" Brass Strip
Hanger rods
Chicken Wire Mesh
2"x12" Ceramic Tile Nosing
1/2"x3'x10' Joint Filler (Cork type)
3/4"x3'x10'
-do1"x3'x10'
-doSealant
Perlite Concrete Grade (CG) (12 kgs./bag)
Air Entraining Agent (AEA)
Fibrin (2 lbs./ bag)
Light Aggregates (Dead Gravel)
8" x 8" Glass Block
300x300 Vigan Tiles
19x150 Wood Parquet
Flarefloor Rubber Tiles
3/4" Ord. Plywood

6.00
28.00
24.00
90.00
80.00
950.00
900.00
60.00
10.50
90.00
90.00
45.00
45.00
65.00
24.00
10.50
525.00
550.00
36.00
3.50
10.00
300.00
295.00
296.00
1,150.00
175.00
145.00
125.00
300.00
250.00
260.00
700.00
23.00
30.00
25.00
45.00
25.00
1,500.00
3,017.00
3,026.00
880.00
130.00
135.00
600.00
120.00
150.00
10.00
60.00
1,300.00
1,100.00

/pc.
/pc.
/pc.
/pc.
/pc.
/sq.m.
/sq.m.
/kl.
/pc.
/can
/can
/can
/can
/can
/kl.
/pc.
/gal.
/gal.
/kl.
/lft.
/lft.
/cu.m.
/pc
/pc
/pc
/pc
/pc
/pc
/roll
/gal.
/gross
/pc.
/lft.
/lft.
/pc.
/sq.m.
/pc.
/pc.
/pc.
/pc.
/liter
/bag
/gal.
/bag
/bag
/pc.
/pc.
/sq.ft.
/sq.m.
/pc.

275/bag

38pcs./sq.m.

Labor
25/sq.ft
80/sq.m

2"x8"x1/2" Ordinary Bricks

EARTHWORKS / CIVIL WORKS


Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
Gravel Fill
Gravel
Black Sand
White Sand
Portland Cement
Asphalt Sealer
Diamond Blade
Grade 40 Rebars
Grade 60 Rebars
Curing Compound
CW Nails
3/4" Ord. Plywood
6 mils Polyethylene Sheet
FUEL & OIL
Premium Fuel
Diesel
Lubricating Oil

STRUCTURAL STEEL
50mm x 50mm x 6mm thk L-Bar (per pc)
31mm x 31mm x 4.5mm thk L-Bar (per pc)
4' x 8' x 4.5mm thk M.S. Plate (sheet)
4' x 8' x 12mm thk M.S. Plate (sheet)
4' x 8' x 16mm thk M.S. Plate (sheet)
4' x 8' x 20mm thk M.S. Plate (sheet)
50mm, Sch 40 Tubular Bar
16mm Plain Round Bar (6m)
12mm Plain Round Bar (6m)
50mm x 100mm x 2mm thk C-Purlin (per pc)
Dyna Bolt 12mm x 100mm (pc)
8" G.I. Pipe (6m Length)
Anchor Bolt 200mm x 300mm
1-1/2 Steel Pipe Sch. 40
4mm- 2"x4" Sch 40 Tubular
4mm- 1-1/2"x1-1/2" Tubular

2.50 /pc.

265.00
250.00
900.00
900.00
900.00
300.00
400.00
210.00
13,500.00
10,400.00
33.73
34.35
40.00
24.00
1,100.00
20.86

/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bag
/MT
/pc.
/kg.
/kg.
/gal.
/kl.
/pc.
/sq.m

42.00 /lit.
35.00 /lit.
45.00 /lit.

4' x 8' x 12mm thk Marine Plywood (sheet)


18mm thk Plyboard
600x1200 Acoustic Board
Tee Runner

Water-Seeping Geotextile(200g/sq.m)
Surveying Rod Socket

45-50 per/sq.m
4,800.00

Vanity Mirror (0.80x0.75m)


Vanity Mirror (0.60x0.75m)

3000 psi Concrete (3/4 agg.)

Ficemboard
Gypsum Board
Vinyl Tile (300x300)
300x300 Ceramic Non-skid Floor Tiles
300x300 Wall Tiles

PVC Door w/ Louver

Polyethelene sheet (6 mils)


G.I. Wire (Ga 16)

per sq.m.
per kilo

4000 psi Concrete


G-1 : Direct pouring
3/4 : Direct pouring
Pumpcrete
Steel:
W8 x 35
W8 x 40 (Wide Flange Section- 6m)
175 x 50 x 3.20mm thk. B.I. Tubular
4' x 8' x 4.50mm thk Checkered Plate
150 x 50 x 3.0mm thk B.I. Tubular
12 x 40
W 8 x 40
175 x 50 3.20 Tubular
3" x 3" x 1/4"
2" x 2" x 1/4"
1" x 1" x 3/16"
W 12 x 40
ST 12 x 60.5
ST 9 x 35
ST 2 x 3.55

per cu.m
per cu.m
per cu.m
per kgs
per piece
per piece
per piece(4,620)
kgs ( 4,800)
720 kgs / 2pcs.
1800 kgs / 5pcs
485.52 kgs / 7pcs
68,996.90 kgs
17601.88 kgs
64.41 kgs
35,640 kgs
106,955.64 kgs
61,882.92 kgs
171.90 kgs

Surveying Rod dia.40 Steel Pipe


Plastic Casing
Rammer Filling Clay
16mm dia Anchor Bolts
Mortar Rubber Masonry
Boulders (6-8 inches dia.)
M10 Cement Mortar
2- 1/2" x 2- 1/2 x 1/4" Angle Bar
2 x 2 x 1/4 Angle Bar
100mm x 50mm x 2mm thk C-Purlins
4' x 8' x 5mm thk M.S. Plate
4' x 8' x 6mm thk M.S. Plate
4' x 8' x 10mm thk M.S. Plate

GOOD LUMBER S4 kd
1" x 3" x 10'
1" x 3" x 12'
1" x 4" x 12'
2" x 2" x 10'
2" x 2" x 12'
2" x 2" x 12'
2" x 3" x 10'
2" x 3" x 12'
4" x 4" x 10'
4" x 4" x 12'

230 cu.m
piece
bag
cu.m
bag

3/4" thk Penolic Board


1" x 5" x 10'
1" x 5" x 12'

28-May-10

16-Jun-10

28-Jun-10

225.00

34.00

35.23
35.95
56.00

1,000.00
461.00
4,045.00
10,780.00
16,050.00
21,024.00
1,986.00
380.00
210.00
800.00
24.00
17,774.00
98.00
6,441.00
4,100.00
2,870.00

660.00
850.00
190.00
90.00

735.00
520.00

3,000.00

780.00
335.00
18.00
36.00
36.00

1,555.00

20.86
70.00

3,200.00
3,350.00
3,500.00
43.85
15,272.00
178.15 per kg
87.53
43.85
42.42
87.53
37.10
37.18
40.58
35.35
37.00
35.00

per
per
per
per
per
per

kg
kg
kg
kg
kg
kg

5,000.00
400.00 TL
50.00
900.00
2,500.00
900.00
1,450.00
1,140.00
862.00
4,375.00
5,250.00
8,740.00

130.00
156.00
224.00
160.00
192.00
192.00
260.00
312.00
720.00
864.00

52.00
52.00
54.00
48.00
48.00
48.00
52.00
52.00
60.00
60.00

bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft

1,400.00
266.65
320.00

1,250.00 pc
58.00 bd.ft
58.00 bd.ft

(Waltermart-Pampanga)
Date:

13-Jan-10

W 6X8 (Wide Flange Steel Section)


W 8X6 (Wide Flange Steel Section)
100Mm Stainless Steel Pipe Sch40
50Mm Thk M.S. Plate
20Mm Thk M.S. Plate
10Mm Thk M.S. Plate
8Mm Thk M.S. Plate
L 130Mm X 75Mm X 6Mm Thk
L 100Mm X 100Mm X 12Mm Thk
L 100Mm X 100Mm X 6Mm Thk
L 75Mm X 75Mm X 8Mm Thk
L 75Mm X 75Mm X 6Mm Thk
L 65Mm X 65Mm X 6Mm Thk
L 50Mm X 50Mm X 6Mm Thk
L 50Mm X 50Mm X 3Mm Thk
2" X 1/4" Thk Flat Bar
Lc 175Mm X 50Mm X 20Mm X 2Mm Thk Purlin
Lc 175Mm X 50Mm X 12.5Mm X 2Mm Thk Purlin
32Mm Anchor Bolt L=1300Mm
25Mm Anchor Bolt L=1000Mm
25Mm Anchor Bolt L=400Mm
20Mm Anchor Bolt L=300Mm
20Mm B.I. Round Bar Ladder Rung
16Mm Round Bar (Cross Bracings)
12Mm Round Bar (Sagrods)
Std Turn Buckle (16Mm)
12Mm Nut & Washer
12Mm Cap Screw
10Mm X 1" Bolts & Nuts
8 Mils Polyethylene Sheet
150Mm Thk Pre-Cast Wall(R.C.)
Grade 60 Reinforcing Bar
Grade 40 Reinforcing Bar

(DMIA-Clark)
Date:

11-Jan-10

Metal Decking
Remington Industrial Sales
150 X 150 X 10Mm Thk X 6M L-Bar
100 X 100 X 12Mm Thk X 6M L-Bar
75 X 75 X 12Mm Thk X 6M L-Bar
75 X 75 X 8Mm Thk X 6M L-Bar
75 X 75 X 6Mm Thk X 6M L-Bar
50 X 50 X 6Mm Thk X 6M L-Bar
W 27 X 281 (6M)
W 27 X 217 (6M)
W 27 X 161 (6M)
W 27 X 235 (6M)
W 27 X 161 (6M)
W 27 X 129 (6M)
W 27 X 114 (6M)
W 27 X 102 (6M)
W 24 X 117 (6M)
W 21 X 101 (6M)
W 21 X 57 (6M)
W 24 X 55 (6M)
W 16 X 50 (6M)
W 10 X 45 (6M)
W 8 X 21 (6M)
4' X 8' X 50Mm Thk M.S.Plate
6' X 20' X 16Mm Thk M.S. Plate
4' X 8' X 8Mm Thk M.S. Plate
75 X 175 X 18 X 6Mm Thk Lc-Purlins (6M)
20mm Plain Round Bar (6m)
16Mm Round Bar (6m)
20mm STD Turn Buckle
16mm STD Turn Buckle
Pipe 8" BI Sch.40 (6m)
Pipe 6" BI Sch.40 (6m)
Pipe 4" BI Sch.40 (6m)
Pipe 3" BI Sch.40 (6m)

(LLDA Complex, Quezon City)


Date:
Polyethelene Sheet (6 Mils)
G.I. Wire (Ga 16)
Grade 60 Reinforcing Bar
Grade 40 Reinforcing Bar
4000 Psi Concrete G-1 : Direct Pouring
4000 Psi Concrete 3/4 : Direct Pouring
4000 Psi Concrete Pumpcrete Design
W 8 X 35 (Wide Flange Section- 6M)
W 8 X 40 (Wide Flange Section- 6M)
175 X 50 X 3.20Mm Thk. B.I. Tubular
4' X 8' X 4.50Mm Thk Checkered Plate
150 X 50 X 3.0Mm Thk B.I. Tubular
W 12 X 40
W 8 X 40
175 X 50 X 3.20 Tubular

(Ormeco Dam, Linao-Cawayan, Orriental Mindoro)


Date:
1.4M Inside Diam X 6Mm X 1.2M L Steel Pipe
1.4M Inside Diam X 8Mm X 1.2M L Steel Pipe
1.4M Inside Diam X 10Mm X 1.2M L Steel Pipe
1.7M Inside Diam X 6Mm X 1.2M L Steel Pipe
Pvc Water Stop, T=6Mm, L=200Mm
H588X300X12X20 (H-Section Steel Beam)
100Mm X 12Mm Thk Flatbar
20A (Sgp)
M16 Bolt (Machine Bolt - 16Mm)(6"Length)

100 X 100 X 9Mm Thk L-Bar


100 X 100 X 8Mm Thk L-Bar
50 X 50 X 6Mm Thk L-Bar
50 X 50 X 5Mm Thk L-Bar
50 X 50 X 4Mm Thk L-Bar
40 X 40 X 6Mm Thk L-Bar
38 X 38 X 4Mm Thk L-Bar
8" X 8" X 36 Lb/Ft W-Section
20Mm Thk M.S. Plate
16Mm Thk M.S. Plate
12Mm Thk M.S. Plate
10Mm Thk M.S. Plate
6Mm Thk M.S. Plate
20Mm X 150/95 Hlc Sleeve Anchor (Hilti)
12Mm X 30Mm Flat Head Screw
J" Type Rubber Seal
63Mm G.I. Pipe
20Mm Stainless Steel Pipe
19Mm X 1.2Mm Thk Stainless Steel Pipe
White Polyethylene Sheet
Curing Compound
4000 Psi Concrete (G-1 Agg)
4000 Psi Concrete (3/4 Agg)
2500 Psi Concrete (G-1 Agg)
2500 Psi Concrete (3/4 Agg)
6Mm M.S. Bolt
8Mm M.S. Bolt
20Mm Anchor Bolt, L=350Mm
50 X 178Mm C-Purlin, Ga # 18
50 X 178Mm C-Purlin, Ga # 16
50 X 178Mm C-Purlin, Ga # 15
50Mm G.I. Pipe
Barbed Wire (50M/Roll)
Cyclone Wire (4" Mesh-2M Wide X 2M L)
100Mm Pvc Pipe
Stone Masonry (Rip Rap)
Security Gate Lever Lock (300Mm Length)
(Remington Industrial Sales)
3-1/2" X 3-1/2" X 1/4" L-Bar (6Mm Thk)
3" X 3" X 1/4" L-Bar (6Mm Thk)

2-1/2" X 2-1/2" X 1/4" L-Bar (6Mm Thk)


2" X 2" X 1/4" L-Bar (6Mm Thk)
1" X 1" X 3/16" L-Bar (4Mm Thk)
75Mm B.I. Pipe Sch40 Standard Seamless (6.00M)
1-1/4" X 1/4" Thk X 6M Flatbar (6Mm Thk)
12" X 8" X 40 Lbs/Ft X 6M W-Section
18" X 7-1/2" X 71 Lbs/Ft X 6M W-Section
24" X 12-3/4" X 131 Lbs/Ft X 6M W-Section
4' X 8' X 12Mm Thk M.S. Plate
1" X 1/4" X 6M Flatbar

(NBI Clearance Building, NBI Compound, Taft Ave., Manila)


Date:
Grade 60 Reinforcing Bar
Grade 40 Reinforcing Bar
4000 Psi Concrete (3/4 Agg) Pumpcrete Design
3000 Psi Concrete (3/4 Agg) Pumpcrete Design
28Mm A307 (L=1000Mm) Anchor Bolt
25Mm A307 (L=1000Mm) Anchor Bolt
3" B.I. Pipe Sch40
2.5" B.I. Pipe Sch40
2" B.I. Pipe Sch40
1.5" B.I. Pipe Sch40
1" B.I. Pipe Sch40
M28 X 100Mm Machine Bolt
M25 X 100Mm Machine Bolt
20Mm X 100Mm Stud Bolts
0.80Mm Thk; 80,000Psi Steel Decking Rib-Type
0.80Mm Thk; 80,000Psi Steel Decking Flat-Type
100 X 50 X 20 X 2Mm Thk Purlin
16Mm Plain Round Bar (Cross Bracing)

(Interphil Laboratory Warehouse, Canlubang Industrial Estate, Bo. Pittland, Cabuyao, Laguna)
Date:
Architectural Finishes

600 X 600Mm Homogeneous Tile, Superblack


600 X 600Mm Homogeneous Tile, White
300 X 300Mm Ceramic Unglazed Tile
300 X 300Mm Outdoor Tile
300 X 300Mm Outdoor Tile
300 X 300Mm Ceramic Wall Tile
300 X 300Mm Rusic Ceramic Tile
#10 Beige Pebble
Roofing
Rib-Type Long Span Pre-Painted 0.60Mm Thk Roofing
Insulation
Flashing
End Flashing
Ridge Roll
Gutter
Rib-Type Long Span Pre-Painted 0.60Mm Thk Wall Siding
7Ft Width X 7M Length Cyclone Wire
6Ft Width X 7M Length Cyclone Wire
Lean Concrete (1000 Psi)
15M Ps Pile (Prestressed)
Barrafilm (6Mils) / Polyethylene
Pej Filler W/ Sealant 12Mm Thk
Grade 40 Reinforcing Bar
3000 Psi Concrete (3/4 Agg) Pumpcrete Design
3-1/2" X 3-1/4" X 1/4" L-Bar
3" X 3" X 1/4" L-Bar
2-1/2" X 2-1/2" X 1/4" L-Bar
2" X 2" X 1/4" L-Bar
1" X 1" X 3/16" L-Bar
75Mm B.I. Pipe
4" Black Pipe
1-1/4" X 1/4" Thk Flatbar
12" X 10" X 3/10" (A36) Structural Tubing
12" X 10" X 1/4" (A36) Structural Tubing
W12 X 40
St 9 X 35
St 12 X 60.5
12Mm Thk M.S. Plate

20Mm A325 Anchor Bolt


12Mm X 40Mm Long Bolts W/ Std Nuts & Washers
2" X 4" X 0.9Mm Thk Tubular
1-1/2" X 1-1/2" Tubular
1" X 1" Tubular
1" X 1/4" Thk Flatbar
3/4" X 3/16" Thk Flatbar
2" X 3" X 0.9Mm Thk C-Purlins
10Mm Plain Round Bar (Sagrod)
Cyclone Wire(1.80M)
Barbed Wire (30Kg/Roll)
Steel Wheel Gate Roller

(Lasaltech Academy, Nueva Ecija)


Date:
2" X 4" Sch40 (4Mm Thk) Tubular
1-1/2" X 1-1/2" Sch40 (4Mm Thk) Tubular
2-1/2" X 2-1/2" X 1/4" L-Bar
2" X 2" X 1/4" L-Bar
100 x 50 X 20 X 2Mm Thk C-Purlin
4' x 8' x 10mm thk M.S. Plate
4' x 8' x 6mm thk M.S. Plate
4' x 8' x 5mm thk M.S. Plate

(Northrail, Valenzuela to Malolos, Bulacan)


Date:
Water Seeping Geotextile (200G/Sq.M)
Surveying Rod Socket
Surveying Rod 40mm Steel Pipe (5m) w/ Plastic Casing
Rammer Filling Clay (P400/TL)
16mm Anchor Bolt
M 7.50 Cement

Boulders 6"-8" Diam.


M10 Cement

(Super-8 Grocery, Baliuag, Bulacan)


Date:
4' X 8' X 16Mm Thk M.S. Plate
12Mm X 100Mm Long Dyna Bolt
Self Tapping Screw
Epoxy Primer
Red Lead Oxide Primer
20Mm X 300Mm Anchor Bolt
1-1/2" Steel Pipe Sch40
Vanity Mirror 0.80 X 0.75M
Vanity Mirror 0.60 X 0.75M
4' X 8' X 18Mm Thk Plyboard
Grade 40 Reinforcing Bar
3000 Psi Concrete (3/4 Agg)
4' X 8' Ficemboard
4' X 8' Gypsum Board
Vinyl Tile
300 X 300 Ceramic Non-Skid Floor Tile
300 X 300 Wall Tile
600 X 1200Mm Acoustic Board
Tee Runner
Pvc Door W/ Louver

(Proposed 10-Storey National Press Club Building)


Date:
C6 x 8.20 C-Channel
4' x 8' x 6mm thk Checkered Plate
4' x 8' x 0.80mm thk Checkered Plate
2" Stainless Steel (1.50mm thk x 20' long) outer diam

15-Jul-10

2" Stainless Steel (1.50mm thk x 20' long) inner diam


2" x " thk Flat Bar
50mm x 50mm x 3/16" L-Bar
1" x " thk Flat Bar
2" Sch40 GI Pipe

(Renovation : Stotsenberg Twist Restaurant)


Date:
2" x 4" Tubular Bar
2" x 6" Tubular Bar
Stone Bricks
300 x 300mm Embosed Ceramic Tile
1" x 4" Tubular Bar
" Hardiflex
Granite Counter
Stainless Sink (16" x 24")
Gas Burner (Standard)
Grill (1.30 x 0.60m)
Cabinet Hinges
Cabinet Hinges (pino)
Cabinet Door Handset
2" x 2" x 10' S-4 (Good Lumber)
1" x 1" Tubular Bar (1.20mm thk)
Sand
Gravel
Brickstone (4"x8")
Brickstone (8"x8")
" Ordinary Plywood
" Sch 40 G.I. Pipe
Corrugated G.I. Roofing Ga. 24, 12' long (Apo)
Corrugated G.I. Roofing Ga. 24, 12' long (Ordinary)
Corrugated G.I. Roofing Ga. 24, 10' long (Apo)
Corrugated G.I. Roofing Ga. 24, 10' long (Ordinary)
G.I. Gutter Ga. 24, 8' long
G.I. Flashing Ga. 24, 8' long
" thk Clear Glass

Metal Furring, 6m long

(Five-Bedroom Two-Storey Residential )


Date:
150mm x 50mm x 2mm thk Purlin (2" x 6")
100mm x 50mm x 1.5mm thk Purlin (2" x 4")
6mm thk Bronze Glass on Analok Finish Aluminum Frame Windows
W-01, 1.25m x 5.30m
W-02, 1.00m x 5.30m
W-03, 2.15m x 2.20m
W-04, 0.80m x 1.20m
W-05, 1.20m x 1.20m
W-06, 2.40m x 1.20m
W-07, 0.60m x 1.70m
W-08, 0.80m x 1.70m
W-09, 2.40m x 1.70m
W-10, 2.40m x 0.80m
W-11, 1.25m x 0.80m
W-12, 0.60m x 0.60m
W-13, 0.90m x 0.60m
W-14, 0.90m x 1.20m
W-15, 1.60m x 1.20m
W-16, 1.80m x 1.20m

(Obstacle Course - Stotsenberg)


Date:
Second Hand Tires

15-Jul-10

CWN 4"
CWN 3"
CWN 2"
Portland Cement (Northern Cement)
Portland Cement (Holcim Cement)
Wash Sand
Crushed Gravel 3/4"
Concrete Pail
4" x 4" x 10' Good Lumber
2" x 4" x 14' KD S4S
3" x 5" x 10' KD S4S
3" x 3" x 10' Good Lumber
Epoxy Primer Gray (ACP Concrete)
Epoxy Primer Gray (Rag J Hardware)
Baby Roller (Painting Works)

(Pamantasan ng Angeles / 2-Storey School Building)


Date:
4" x 4" x 3/8" thk Angle Bar
3" x 3" x 3/8" thk Angle Bar
3" x 3" x " thk Angle Bar
2" x 2" x " thk Angle Bar
2" x 2" x 3/16" thk Angle Bar
2" x 2" x " thk Angle Bar
1" x 1" x 3/16" thk Angle Bar
50mm x 150mm x 1.00mm thk C-Purlin
16mm Plain Round Bar
12mm Plain Round Bar
Polyethylene Sheets
G-1 Gravel
Washed Sand (White)
4,000psi Concrete (3/4agg) Pumpcrete Design
3,000psi Concrete (G-1) Direct Pouring
3,000psi Concrete (3/4agg) Direct Pouring
Grade 60 Rebar
Grade 40 Rebar

6-Sep-10

(Laoag Capitol Extension)


Date:

15-Oct-10

6" x 6" x 6mm Wire Mesh (6' x 6m)


(MWSS Perimeter Fence)
Date:

15-Oct-10

50mm G.I. Pipe Sch. 40


25mm G.I. Pipe Sch. 40
Ga #9 EWWF G.I. Interlink
Cyclone Wire (1.20m x 10m)
Galvanized Barbed Wire Ga.#14
8mm Plain Round Bar
12mm Square Bar
Ga#16 Plain G.I. Sheet
12mmx5mm thk Flat Bar
8" CHB Load Bearing
(MWSS Pumphouse & Guardhouse)
Date:

0.90x1.20m Sliding Type Clear Glass Window on Powder Coated Aluminum Frame & Casing
1.20x1.20m Fix-type Clear Glass Window on Powder Coated Aluminum Frame & Casing
0.60x0.60m Awning-type Clear Glass Window on Powder Coated Aluminum Framing & Casing
1.20x1.20m Fix-type Clear Glass Window on Powder Coated Aluminum Framing & Casing
1.20x1.20m Sliding Type Clear Glass Window
0.90x1.20m Sliding Type Clear Glass Window
0.80x2.10m Single Wooden Flush Swing Door (50mm thk)
0.70x2.10m Single Leaf PVC Swing Door w/ Bottom Louver
0.60x2.10m PVC Door
Rockwool Insulation (for soundproofing/wall insulation)
Ga#24 Pre-formed pre-painted G.I. Flashing
Ga#24 Pre-formed pre-painted G.I. Gutter
Ga#24 Pre-painted Rib-type Roofing Sheet
12mm thk. Hardi Senepa
25mm x 25mm S4S Lumber
10mm thk Reflective Insulation(Roof)

15-Oct-10

(Sea Place Restaurant & Mabini 101 Suites- Malate, Manila)


Date:
600x600x10mm Synthetic Unpolished Granite Tiles
600x600x10mm Synthetic Polished Granite Tiles
300x300x6mm Ceramic Tiles (Plain)
200x200mm Ceramic Floor Tiles
100x100mm Paver Tiles
4" Cornice
4" Baseboard
12mm Granite Slab
W24x55 (12m long)
W27x84 (12m long)
W16x40 (12m long)
W12x35 (12m long)
W12x30 (12m long)
W14x43
W18x43
W12x30
W27x129
W18x143
W27x84
W18x76
W16x31
W12x36
W8x10
W36x160
W30x108
W24x55
W12x58
W27x102
W14x132
W14x48
W14x120
W18x97
2"x2"x" Angle Bar
2"x2"x1/8" Angle Bar
2"x2"x" Angle Bar
50x50x6mm Angle Bar

23-Nov-10

50x50x3mm Angle Bar


8'x20'x50mm thk MS Plate
4'x8'x25mm thk MS Plate
4'x8'x25mm thk MS Plate
4'x8'x50mm thk MS Plate
4'x8'x15mm thk MS Plate
4'x8'x12.5mm thk MS Plate
28mmx800mm Anchor Bolt
16mm Machine Bolts w/ nuts (4" long)

(Laoag City Auditorium)


Date:

23-Nov-10

" thk Marine Plywood


2"x2"x10' S4S Good Lumber
1"x1" Crown Moulding (8' long)

()
Date:

23-Nov-10
Portland Cement Concrete 4000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 5000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 6000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 8000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 6000 psi 28da G-1 Slump-3"-4"
Note : Price of Pumpcharge is subject as per site inspection. Pumpcharge : Stationary-Php. 9,500.00 per
set-up, minimum of 50 cubic meter. Boom Type (18m-28m) - Php. 10,000.00 per set-up minimum of 50
cubic meter. Boom Type (36m) - Php. 11,000.00 per set-up of 50 cubic meter.
Additional : ***w/ added specification on the SPA Stationary-Php. 190.00 per cubic in excess of 50 cubic
meter. Boom Type (18m-28m)- Php. 200.00 per cubic in excess of 50 cubic meter. Boom Type (36m)Php. 220.00 per cubic in excess of 50 cubic meter.

(Angeles Hospital)
Date:

20-Sep-10

W12x30 (6.00m long)


W15x16 (6.00m long)
4'x8'x16mm thk MS Plate
4'x8'x8mm thk MS Plate
178x50x20x2mm thk Purlins

(Mabini 101 Suites)


Date:
36mm A490 Anchor Bolt (L-850mm)
28mmx1000mm Anchor Bolt (8325)
6"x8" Steel Channel
12"x20" Steel Channel
2"x4" Gauge #16 C-Purlins
10mm Plain Round Bar
16mm Plain Round Bar
16mm Sandard Turnbuckles

()
Date:
600x600 Homogenous Granite Tile
600x600 Homogenous Granite Tile
600x600 Non-skid Tile

()
Date:
2"x2"x3/16" thk Angle Bar
1"x1"x3/16" thk Angle Bar
2" G.I. Pipe Sch.40
2"x2"x3/16" thk Angle Bar
4'x8'x16mm thk M.S. Plate
2"x7" C-Purlins

29-Nov-10

()
Date:

10-Nov-10
Megakonztruk
12mm Expansion Bolt w/ plate washer
2x4x1.5mmx6m C-Purlin
50mmx75mmx1.5mmx6m C-Purlin
4'x8'x1/8"(3mm) M.S. Plate
50mmx100mmx1.5mmx6m Tubular Steel
50mmx150mmx1.5mmx6m Tubular Steel
38x38x3mmx6m Angle Bar
2"x2"x3/16" thk Angle Bar (2.8mm)
2"x2"x3/16" thk Angle Bar (3.5mm)
2"x2"x" Angle Bar
2"x"x6m Flat Bar
2"x3/8"x6m Flat Bar (7mm)

(Hanalei Heights, Laoag City)


Date:

10-Nov-10

Hardiflex Board
Tekscrew
2"x2"x3/16" Angle Bar
1"x1"x3/16" thk Angle Bar
2"x2"x" Angle Bar
2"x"x6m Flat Bar
12mm(Expansion) Bolt w/ nut
2"x4" C-Purlins / 50x100x12.5x1.5mm thk C-Purlins
4'x8'x1/8"(3mm) M.S. Plate
50x75x1.5mm thk Light Gage C-Purlins
50x100x1.5mm thk Light Gage Tubular Steel
50x150x1.5mm thk Light Gage Tubular Steel
13mmx300mm Anchor Bolt w/ standard lock nut & washer
38mmx38mmx3mm Angle Bar
10mm Machine Bolt (L=1")

Date:

10-Jan-11
Grade 60 Reinforcing Steel Bar
Grade 40 Reinforcing Steel Bar

6000 psi, 3/4 Agg., Pumpcrete Design


4000 psi, 3/4 Agg., Pumpcrete Design
3000 psi, 3/4 Agg., Pumpcrete Design
2800 psi, 3/4 Agg., Pumpcrete Design
Pumpcrete Charge: Minimum of 50m per setting
up to 4th Floor
Fifth Floor and up

(Fire Department Station)


Date:
Weserve
63mm x 63mm x 9.50mm Angle Bar
63mm x 63mm x 8.00mm Angle Bar
50mm x 50mm x 8.00mm Angle Bar
50mm x 50mm x 4.75mm Angle Bar
38mm x 38mm x 3.20mm Angle Bar
38mm x 38mm x 4.75mm Angle Bar
25mm x 25mm x 3.25mm Angle Bar
4' x 8' x 11.8mm thk M.S. Plate
4' x 8' x 4.75mm thk M.S. Plate
50mm x 175mm x 1.50mm thk Cee-Purlins
16mm Plain Round Bar
12mm Plain Round Bar
16mm Standard Turnbuckles

3-Jan-11

Rebars:
Grade 60
Grade 40
(SM-San Fernando)
Date:

3-Jan-11

Corrugated G.I. Sheet

(Gingoog Public Market - Gingoog, Misamis)


Date:
6" CHB Non-Load Bearing
4" CHB Non-Load Bearing

28-Jan-11

Concrete Paver Block (100x200mm)


Peeble Wash-out (Class A - Light Black)
PVC Door w/ Louvers
Latex Paint (White Latex)
Epoxy Primer (Gray)
50mm G.I. Pipe Sch. 40
50mm G.I. Pipe Sch. 40
16mm Square Bar (Standard Blk)

(Golden Town Construction Supply Co.)


Date:

18-Nov-10

Enamel Paint - Orange (for H-Frame)


Blind Rivets
Riveter
Drill Bit 1/8
Drill Bit 3/16
Grinding Disc #7

(CDO - Office & Warehouse Building, Valenzuela City, MM.)


Date:
3000psi G-1 Direct
5000psi 3/4 Direct
4000psi 3/4 Pumpcrete
7000psi 3/4 Pumpcrete
5000psi 3/4 Pumpcrete
Steel Deck 0.80mm thk Grade 550
Non Shrink Grout
Epoxy Primer (Gray)
Lacquer Thinner
Turco
Welding Rod 6013
Paint Brush
W16x26
W16x31
W10x30
W6x9
W12x16

9-Feb-11

4'x8'x20mm thk M.S. Plates


4'x8'x6mm thk M.S. Plates
28mm A325 Bolt x 600mm long w/ nut
12mm A325 Bolt x 350mm long w/ nut
LC - 150x50x50x1.50mm Light Gauge Purlins
12mm Plain Round Bar
10mm Plain Round Bar
Checkered Plate 2mm thk
50 x 50 x 6mm thk Angle Bar
150mm Sched. 40 G.I. Pipe
38mm Sched. 40 G.I. Pipe

(Proposed 1-Storey Aquafarm & Hydroponics Bldg.)


Date:
STRUCTURAL & MASONRY
Reinforcing Steel Bars - Grade 33
Tie Wires Ga#16
Concreting - 3000psi
Portland Cement (40kgs/bag)
Roofing & Roofing System
Roof Framing - Steelworks
3" x 3" x " L-Bar
2" x 2" x " L-Bar
150x50x20x1.5mm Purlin
16mm Plain Round Bar
12mm Plain Round Bar
16mm STD Turnbuckles
4'x8'x25mm thk M.S. Plate
4'x8'x6mm thk M.S. Plate
Roofing Accessories
Ga#26 Longspan Union Galvafoam Pre-painted G.I. Roofing
Ga#24 Pre-painted G.I. Gutter
Ga#24 Pre-paiinted G.I. Flashing
10mm thk Insulation

23-Mar-11

8,790.00
20,700.00
56,350.00
20,125.00
8,430.00
7,980.00
6,890.00
4,280.00
2,360.00
1,650.00
1,380.00
1,035.00
560.00
670.00
1,350.00
1,150.00
600.00
300.00
140.00
60.00
750.00
390.00
220.00
115.00
2.70
2.40

18,200.00
8,165.00
6,532.00
5,990.00
2,050.00
1,433.00
1,200.00
900.00
510.00
730.00
1,210.00
1,050.00
460.00
210.00
90.00
460.00
310.00
197.00
90.00
5.00
5.50
5.00

lgth
lgth
sht
sht
sht
sht
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
pc
pc
pc
pc
pc
lgth
lgth
pc
pc
pc
pc
sq.m
pc
kg
kg

CHB
Reinforcing Steel Bar
Structural Steel - Wide Flange
Structural Steel - Angle Bars
Steel Plates
Concrete
Roof Accessories & Metal Dec
Bolts, Screws, Ladder Rungs
Tubular Steel, Flat Bars & Squ
Steel Pipes
Other Steel Shapes
Granite, Ceramic, Vinyl Tiles &
Others

sht
6,480.00
5,990.00
3,120.00
1,863.00
1,442.00
925.00
141,000.00
123,480.00
70,785.00
95,095.00
70,785.00
62,425.00
37,309.00
33,382.00
38,291.00
33,054.50
18,654.50
18,000.00
15,227.00
13,704.50
6,395.50
41,423.00
6,160.00
6,160.00
1,677.00
460.00
300.00
140.00
90.00
14,439.00
10,973.00
6,323.00
4,083.00

42,590.00

lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
sht
sht
lgth
lgth
lgth
pc
pc
lgth
lgth
lgth
lgth

20.86
70.00
34.35
33.73
3,200.00
3,350.00
3,500.00
13,682.00
15,272.00
4,620.00
4,800.00

17,500.00
23,000.00
28,700.00
19,000.00

475.00
45.00

sq.m
kg
kg
kg
cu.m
cu.m
cu.m
lgth
lgth
lgth
sht
lgth
lgth
lgth
lgth

pc
pc
pc
pc
l.m.
lgth
lgth
pc
lgth

4,780.00
3,600.00
1,000.00
840.00
680.00
780.00
550.00
10,659.00
17,730.00
14,184.00
9,520.00
7,930.00
6,000.00
221.50

4,600.00
4,600.00
4,000.00
4,000.00
2.25
3.75
120.00
630.00
880.00
1,150.00
926.00
1,400.00
640.00
517.29
650.00

lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
sht
sht
sht
sht
pc
pc
pc
lgth
lgth
lgth
sq.m
gal
cu.m
cu.m
cu.m
cu.m
pc
pc
pc
lgth
lgth
lgth
lgth
roll
sht
lgth
cu.m

1,979.00
1,623.00

lgth
lgth

1,386.00
680.00

1,355.00
1,059.00
435.00
4,324.00
435.00
12,727.00
22,591.00
44,064.00
9,800.00
330.00

lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
lgth

3,450.00
3,150.00
535.00
410.00
1,793.00
1,458.00
952.00
684.00
410.00
165.00
115.00
40.00
596.85
760.00
800.00
353.00

kg
kg
cu.m
cu.m
pc
pc
lgth
lgth
lgth
lgth
lgth
pc
pc
pc
sq.m
sq.m
lgth
lgth

280.00
269.00
26.50
32.00
28.50
26.50
28.50
250.00

pc
pc
pc
pc
pc
pc
pc
sack

565.00

sq.m
sq.m
l.m
l.m
l.m
l.m
sq.m

840.00
570.00

sht
sht

1,530.00

l.m

1,593.00
1,340.00
985.00
256.00
4,680.00
665.00
450.00

10,080.00

lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht

253.60
112.20
690.00
345.00
192.00
223.00
82.00
330.00
108.00
1,200.00

pc
pc
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
roll
unit

4,100.00
2,870.00
1,450.00
1,140.00
862.00
8,740.00
5,250.00
4,375.00

lgth
lgth
lgth
lgth
lgth
sht
sht
sht

50.00
4,800.00
5,000.00
230.00
50.00
900.00

sq.m
unit
unit
cu.m
pc
bag

2,500.00
900.00

cu.m
bag

6,441.00
735.00
520.00
850.00
34.00
3,000.00
780.00
335.00
18.00
36.00
36.00
190.00
90.00
1,555.00

sht
pc
pc
gal
lit
pc
lgth
unit
unit
sht
kg
cu.m
sht
sht
pc
pc
pc
sht
lgth
unit

3,400.00
5,940.00
1,250.00

lgth
sht
sht
lgth

2,150.00
845.00
950.00
269.00
3,597.00

lgth
lgth
lgth
lgth
lgth

817.00
1,750.00
10.00
36.00

lgth
lgth
pc
pc

400.00
2,800.00
600.00
7,150.00

pc
m
pc
set

22.00
110.00
25.00
285.00
155.00
950.00
600.00 50pcs/sq.m
650.00 25pcs/sq.m
880.00
931.00
864.00
576.00
720.00
480.00
240.00
240.00
34.00

pc
per 8 ft.
set
lgth
m
m
m
m
sht
lgth
sht
sht
sht
sht
lgth
lgth
sq.ft

83.00

lgth

920.00
630.00

lgth
lgth

13,788.34
12,159.00
10,184.91
3,000.00
4,000.00
7,360.00
5,948.41
6,245.00
10,560.00
6,000.00
2,956.36
1,520.00
2,280.00
3,000.00
4,800.00
4,800.00

55.00

(Labor & Materials)


(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)
(Labor & Materials)

set
set
set
set
set
set
set
set
set
set
set
set
set
set
set
set

pc

49.00
50.00
47.00
220.00
213.00
800/elf truckload
(approx. 2.50cu.m)
2500/elf truckload
(approx. 2.50cu.m)
40.00
773.33
524.25
1,125.00
375.00
153.00
195.00
153.00

(manila)

kg
kg
kg
bag
bag

pc
lgth
lgth
lgth
lgth
lit
lit
pc

(pampanga)

5,100.00
1,620.00
1,360.00
1,033.00
1,016.00
595.00
525.00
360.00
(11.50m) 197.00
150.00
3,000/(18-19Cu.m)
3,700.00
2,950.00
3,200.00
33.54
32.85

lgth
lgth
lgth

1,434.00

998.00

600.00

460.00
330.00
295.00
(12.50m) 230.00

294.00
450.00
380.00
185.00

lgth
lgth
lgth
lgth
lgth
lgth
kg

cu.m
cu.m
cu.m
kg
kg

1,320.00

1,205.00
505.00
3,200.00
3,560.00
1,076.00
110.00
226.00
2,150.00
318.00
32.00

sht

2,230.00
1,053.00
7,200.00
1,350.00
92.00
260.00
1,520.00
88.00
21.50

4,581.20
4,212.00
2,685.15
4,212.00
5,379.40
4,581.20
2,800.00
2,800.00
2,600.00

2,170.80
1,475.11
757.95
1,317.00
66.00
3,036.00

per sheet (4'x8' plain sheet)


per pc (24"x8'x6mm thk)
per L.m. (6mm thk)
per lgth (1"x"x12')

1,500.00

650.00
650.00
25.52
15.00
15.00
21/ft
21/ft
2,200.00
42,000.00
62,700.00
30,500.00
26,700.00
22,900.00
40.00
40.00
42.00

4,500.00

pc
pc
pc
pc
pc
ft
ft
sq.m
pc
pc
pc
pc
pc
kg
kg
kg

Built-up
Built-up
41.00
46.00
44.00
42.00
40.00

kg
kg
kg
kg
kg

42.00
44.00
40.00
41.00
39.00
40.00
43.00
928.00
485.00
1,265.00
928.00

kg
kg
kg
kg
kg
kg
kg

Built-up
Built-up

485.00
113,770.00
23,910.00
22,450.00
58,320.00
13,475.00
9,660.00
480.00
39.00

sht
sht
sht
sht
sht
sht
pc
pc

335.00
45.00
52.00

sht
bd.ft
lgth

3,650.00
4,150.00
4,450.00
5,200.00
3,850.00

cu.m
cu.m
cu.m
cu.m
cu.m

12,000.00
5,818.00
14,180.00
6,719.00
1,062.00

895.00
600.00
3,100.00
8,400.00
550.00
135.00
355.00
90.00

240.00
280.00
310.00

687.00
510.00
1,896.00
925.00
16,050.00
1,200.00

pc
pc
sht
sht
pc

22.00
648.00
569.00
2,793.00
1,237.00
2,059.00
402.00
541.00
466.00
1,421.00
415.00
771.00

425.00
0.75
541.00
468.00
1,421.00
415.00
22.00
648.00
2,793.00
569.00
1,237.00
2,059.00
45.00
402.00
10.00

60.00
62.00

56.00
58.00

4,925.00
4,045.00
3,510.00
3,300.00

ReadyCon, Dasmarinas, Cavite


ReadyCon, Dasmarinas, Cavite
ReadyCon, Dasmarinas, Cavite
ReadyCon, Dasmarinas, Cavite

220.00 per cu.m


plus 15.00 per cu.m per floor

1,705.00
1,283.00
827.00
442.00
617.00
292.00

815.00
355.00
192.00
90.00

(+48%)
(+50%)

549.12/m

21.12/ft

6.2/pc
4.7/pc

Pick-up Price
Pick-up Price

ReadyCon, Dasmarinas, Cavite


ReadyCon, Dasmarinas, Cavite

18/pc
580/sack
1,100/set
404/gal (Davies)
597/gal (Davies)
1,293.00
1,014.00
633.00

Pick-up Price
1.20sq.m/sack
424.20/gal (Boysen)
626.85/gal (Boysen)
lgth
lgth
lgth

1,980/tin
220/box
260/pc
45/pc
55/pc
130/pc

3,250 /m (nonVAT)
4,150 /m (nonVAT)
4,050 /m (nonVAT)
5,000 /m (nonVAT)
4,300 /m (nonVAT)

3,600 /m (VAT)
4,500 /m (VAT)
4,550 /m (VAT)
5,300 /m (VAT)
4,700 /m (VAT)

680/bag (25kgs/bag) ZEMGROUT


540/gal
155/gal
490/gal
1,800/box
10,882.00
12,963.00
12,000.00
3,763.00
6,690.00

21,230.00
450.00
130.00
800.00
174.00
143.00
2,750.00
1,098.00
10,417.00
842.00

9,095.00

kg.
65.00 kg.
cu.m.
200.00 bag

1,530.00
713.00
815.00
375.00
192.00
105.00
27,590.00
6,090.00
310.00
335.00
335.00
2,995.00

pc
pc
pc
pc
pc
pc
sht.
sht.
l.m.
/8 ft length
/8 ft length
roll (1mWide x 50m Length)

Reinforcing Steel Bar


Structural Steel - Wide Flange Section
Structural Steel - Angle Bars

Roof Accessories & Metal Decking


Bolts, Screws, Ladder Rungs
Tubular Steel, Flat Bars & Square Bars
Other Steel Shapes
Granite, Ceramic, Vinyl Tiles & Bricks

DETAILED UNIT PRICE ESTIMATE

EARTHWORKS
1 SITE GRADING
A.

EQUIPMENT

1 Bull Dozer
1 Pay Loader
2 Dump Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~
~

1,800.00 /hr
1,600.00 /hr
1400 /hr

=
=
=
=
=
=

1,800.00
1,600.00
2,800.00
0,049.00
0,749.88
6,998.88

~
~
~
~
~

50.00
37.50
75.00
50.00

=
=
=
=
=
=

0,050.00
0,187.50
0,150.00
0,050.00
0,052.50
0,490.00

MANPOWER

1 Foreman
5 Laborer
2 Operator
1 Driver
Vat, 12%

/hr
/hr
/hr
/hr

Sub-total
C.

OUTPUT

D.

FUEL & OIL

80.00 sq.m/hr

1 Bull Dozer
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total

~
~
~
~
~
~

24.13
10.00
27.75
8.96
Php 35.00
Php 45.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19

TOTAL COST

11,029.07

DIRECT LABOR COST

PHP

137.86

2 EXCAVATION
A.

EQUIPMENT

1 Backhoe
1 Pay Loader
3 Dump Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~
~

1,900.00 /hr
1,500.00 /hr
1,400.00 /hr

=
=
=
=
=
=

1,900.00
1,500.00
4,200.00
0,059.36
0,919.12
8,578.48

~
~
~
~
~

50.00
37.50
75.00
47.50

=
=
=
=
=

0,050.00
0,187.50
0,150.00
0,142.50
0,063.60

MANPOWER

1 Foreman
5 Laborer
2 Operator
3 Driver
Vat, 12%

/hr
/hr
/hr
/hr

Sub-total
C.

OUTPUT

D.

FUEL & OIL

= 0,593.60
60.00 cu.m/hr

1 Backhoe
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total

~
~
~
~
~
~

24.13
10.00
27.75
8.96
Php 35.00
Php 45.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19

TOTAL COST

12,712.27

DIRECT LABOR COST

PHP

211.87

3 AGGREGATE SUB-BASE COURSE


A.

EQUIPMENT

1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~
~
~

1,500.00
800.00
600.00
400.00

/hr
/hr
/hr
/hr

=
=
=
=
=
=
=

1,500.00
0,800.00
0,600.00
0,400.00
0,043.40
0,401.21
3,744.61

~
~
~
~
~

50.00
37.50
75.00
-

/hr
/hr
/hr
/hr

=
=
=
=
=
=

0,050.00
0,112.50
0,225.00
0,000.00
0,046.50
0,434.00

=
=
=
=

0,010.00
0,008.00
0,014.00
0,005.44

MANPOWER

1 Foreman
3 Laborer
3 Operator
1 Driver
Vat, 12%
Sub-total
C.

OUTPUT

D.

FUEL & OIL

50.00 cu.m/hr

1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Oil, 10% of Fuel
37.44 Liter of Fuel
2.74 Liter of Oil
Sub-total
E.

~
~
~
~
~
~
~

10.00
8.00
14.00
5.44
2.74
Php 35.00
Php 45.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

PHP 250.00 /cu.m

= 1,310.40
= 0,123.48
= 1,433.88

MATERIAL (agg. w/ 20% SF)

### cu.m Course Aggregate


TOTAL COST

= 15,000.00
20,612.49

DIRECT MATERIAL COST


DIRECT LABOR COST
TOTAL DIRECT COST

PHP
PHP
PHP

300.00
112.25
412.25

4 AGGREGATE BASE COURSE


A.

EQUIPMENT

1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~
~
~

1,500.00
800.00
600.00
400.00

/hr
/hr
/hr
/hr

=
=
=
=
=
=
=

1,500.00
0,800.00
0,600.00
0,400.00
0,043.40
0,401.21
3,744.61

~
~
~
~
~

50.00
37.50
75.00
-

/hr
/hr
/hr
/hr

=
=
=
=
=
=

0,050.00
0,112.50
0,225.00
0,000.00
0,046.50
0,434.00

=
=
=
=

0,010.00
0,008.00
0,014.00
0,005.44

MANPOWER

1 Foreman
3 Laborer
3 Operator
1 Driver
Vat, 12%
Sub-total
C.

OUTPUT

D.

FUEL & OIL

50.00 cu.m/hr

1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Oil, 10% of Fuel
37.44 Liter of Fuel
3.74 Liter of Oil
Sub-total
E.

~
~
~
~
~
~
~

10.00
8.00
14.00
5.44
3.74
Php 35.00
Php 45.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

PHP 900.00 /cu.m

= 1,310.40
= 0,168.48
= 1,478.88

MATERIAL (agg. w/ 20% SF)

### cu.m Course Aggregate

= 54,000.00

TOTAL COST

59,657.49

DIRECT MATERIAL COST


DIRECT LABOR COST
TOTAL DIRECT COST

PHP
PHP
PHP

1,080.00
113.15
1,193.15

5 BACKFILLING & COMPACTION


A.

EQUIPMENT

1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck

~
~
~
~

1,500.00
800.00
600.00
400.00

/hr
/hr
/hr
/hr

=
=
=
=

1,500.00
0,800.00
0,600.00
0,400.00

Minor Tools, 10% of Manpower


Vat, 12%
Sub-total
B.

~
~

= 0,047.60
= 0,401.71
= 3,749.31

MANPOWER

1 Foreman
4 Laborer
3 Operator
1 Driver
Vat, 12%

~
~
~
~
~

50.00
37.50
75.00
-

/hr
/hr
/hr
/hr

Sub-total
C.

OUTPUT

D.

FUEL & OIL

=
=
=
=
=
=

0,050.00
0,150.00
0,225.00
0,000.00
0,051.00
0,476.00

=
=
=
=

0,010.00
0,008.00
0,014.00
0,005.44

50.00 cu.m/hr

1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Oil, 10% of Fuel
37.44 Liter of Fuel
3.74 Liter of Oil
Sub-total

~
~
~
~
~
~
~

10.00
8.00
14.00
5.44
3.74
Php 35.00
Php 45.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

= 1,310.40
= 0,168.48
= 1,478.88

TOTAL COST

5,704.19

DIRECT LABOR COST

PHP

114.08

5 BORROW FILL & COMPACTION


A.

EQUIPMENT

1 Pay Loader
1 Road Grader
1 Road Roller
2 Dump Truck
1 Water Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~
~
~
~

1,500.00 /hr
800.00 /hr
600.00 /hr
1400 /hr
400.00 /hr

=
=
=
=
=
=
=
=

1,500.00
0,800.00
0,600.00
2,800.00
0,400.00
0,047.60
0,737.71
6,885.31

~
~
~
~
~

50.00
37.50
75.00
-

=
=
=
=
=
=

0,050.00
0,150.00
0,225.00
0,000.00
0,051.00
0,476.00

MANPOWER

1 Foreman
4 Laborer
3 Operator
3 Driver
Vat, 12%

/hr
/hr
/hr
/hr

Sub-total
C.

OUTPUT

D.

FUEL & OIL

1 Pay Loader

50.00 cu.m/hr

10.00 Lit/hr

= 0,010.00

1 Road Grader
1 Road Roller
2 Dump Truck
1 Water Truck
Oil, 10% of Fuel
92.94 Liter of Fuel
9.29 Liter of Oil
Sub-total
E.

~
~
~
~
~
~
~

8.00
14.00
27.75
5.44
9.29
Php 35.00
Php 45.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

PHP 265.00 /cu.m

=
=
=
=

= 3,252.90
= 0,418.23
= 3,671.13

MATERIAL (Earthfill w/ 20% SF)

### cu.m Engineered Fill

= 15,900.00

TOTAL COST

26,932.44

DIRECT MATERIAL COST


DIRECT LABOR COST
TOTAL DIRECT COST

PHP
PHP
PHP

5 DEWATERING OF FOOTING (lot)


A.

318.00
220.65
538.65

No. of days(Foundation) =

EQUIPMENT

6 Water Pump
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

0,008.00
0,014.00
0,055.50
0,005.44

~
~
~

150.00 /hr

~
~

37.50 /hr

=
=
=
=

0,900.00
0,012.60
0,109.51
1,022.11

MANPOWER

3 Laborer
Vat, 12%
Sub-total
C.

OUTPUT (24 hours per day = 8/24)

D.

FUEL & OIL

6 Water Pump
Oil, 10% of Fuel
12.00 Liter of Fuel
1.20 Liter of Oil
Sub-total
TOTAL COST

DIRECT LABOR COST

= 0,112.50
= 0,013.50
= 0,126.00

0.33

~
~
~
~

2.00
1.20
Php 35.00
Php 45.00

Lit/hr
Lit/hr
/Lit
/Lit

= 0,012.00
= 0,420.00
= 0,054.00
= 0,474.00
1,622.11

PHP 38,969.66

/hr

/hr
/hr

/sq.m

/hr

/hr
/hr

/cu.m

/hr

/hr

/hr
/hr

/cu.m
/cu.m
/cu.m

/hr

/hr

/hr
/hr

/cu.m
/cu.m
/cu.m

/hr

/hr
/hr

/cu.m

/hr

/hr

/hr
/hr

/cu.m
/cu.m
/cu.m
1

/hr

/hr
/hr

CIVIL WORKS
1 CONCRETING -4000 PSI, 3/4 Aggregates, Pumpcrete Design
A.

EQUIPMENT

2 Transit Mixer
1 Pay Loader
1 Batching Plant
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~
~

1,800.00 /hr
1,600.00 /hr
1400 /hr

=
=
=
=
=
=

3,600.00
1,600.00
1,400.00
0,061.60
0,799.39
7,460.99

~
~
~
~
~

50.00
37.50
75.00
50.00

=
=
=
=
=
=

0,050.00
0,300.00
0,150.00
0,050.00
0,066.00
0,616.00

MANPOWER

1 Foreman
8 Laborer
2 Operator
1 Driver
Vat, 12%

/hr
/hr
/hr
/hr

Sub-total
C.

OUTPUT

D.

FUEL & OIL

18.00 cu.m/hr

1 Bull Dozer
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total
E.

~
~
~
~
~
~

24.13
10.00
27.75
8.96
Php 35.00
Php 45.00

~
~
~
~

210.00
900.00
400.00
40.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19

MATERIALS

13
234 bags Portland Cement
0.9 16.74 cu.m 3/4 Course Aggregate
0.6 10.08 cu.m Fine Sand
1 18.00 liter Admixture
Sub-total

/hr
/hr
/hr
/hr

=
=
=
=
=

TOTAL COST

49,140.00
15,066.00
4,032.00
0,720.00
68,958.00
80,575.18

DIRECT LABOR COST


DIRECT LABOR COST
DIRECT LABOR COST

PHP
PHP
PHP

4,476.40
645.40
5,121.80

1 CONCRETING -4000 PSI, 3/4 Aggregates, Pumpcrete Design


A.

EQUIPMENT

2 Transit Mixer

1,800.00 /hr

= 3,600.00

1 Pay Loader
1 Batching Plant
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,600.00 /hr
1400 /hr

=
=
=
=
=

1,600.00
1,400.00
0,061.60
0,799.39
7,460.99

~
~
~
~
~

50.00
37.50
75.00
50.00

=
=
=
=
=
=

0,050.00
0,300.00
0,150.00
0,050.00
0,066.00
0,616.00

MANPOWER

1 Foreman
8 Laborer
2 Operator
1 Driver
Vat, 12%

/hr
/hr
/hr
/hr

Sub-total
C.

OUTPUT

D.

FUEL & OIL

18.00 cu.m/hr

1 Bull Dozer
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total

~
~
~
~
~
~

24.13
10.00
27.75
8.96
Php 35.00
Php 45.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19

TOTAL COST

DIRECT LABOR COST

11,617.18

PHP

645.40

/hr

/hr

/hr
/hr

/cu.m
/sq.m
/sq.m

/hr

/hr
/hr

/sq.m

FORMWORKS
1 PANEL FORM - Installing of Penolic Board to Penolic Frame (Sub-con Works)
A.

EQUIPMENT

2 (by owner)
1 (by owner)
1 (by owner)

~
~
~
~

/hr
/hr
/hr

=
=
=
=
=

0,000.00
0,000.00
0,000.00
0,000.00
0,000.00

~
~
~

43.75 /hr
37.50 /hr

=
=
=
=

0,043.75
0,112.50
0,018.75
0,175.00 /hr

Sub-total
B.

MANPOWER

1 Carpenter
3 Laborer
Vat, 12%
Sub-total

Productivity =
C.

OUTPUT

D.

FUEL & OIL

4.50 sq.m/hr

1 (by owner)
1 (by owner)
2 (by owner)

~
~
~
~
~
~

0.00
0.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

Sub-total
TOTAL COST

50 pcs/day
0.72 sq.m
36 sq.m/day
4.5 sq.m/hr

= 0,000.00
= 0,000.00
= 0,000.00
= 0,000.00
= 0,000.00
= 0,000.00 /hr
175.00 /hr

DIRECT LABOR COST

### /sq.m

Laborer
Carpenter

Provincial Rate
Minimum
Maximum
250
280
280
300

Manila Rate
Applied Rate Rate per Hour
Minimum
Maximum
270
300
300
37.5
310
350
350
43.75

REINFORCING STEEL BAR


1 FOOTING
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total

500.00 kgs/hr

C.

OUTPUT

D.

MATERIALS

01.00 k Grade 60 RSB (Deformed)


01.00 k Ga. #16 G.I. Wire
Sub-total

~
~

24.13 Lit/hr
10.00 Lit/hr

TOTAL COST

DIRECT LABOR COST


1 FOOTING TIE BEAM, GRADE BEAM
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.

OUTPUT

D.

MATERIALS

01.00 k Grade 60 RSB (Deformed)

500.00 kgs/hr

24.13 Lit/hr

01.00 k Ga. #16 G.I. Wire


Sub-total

10.00 Lit/hr

TOTAL COST

DIRECT LABOR COST


1 SLAB ON GRADE / FILL
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total

500.00 kgs/hr

C.

OUTPUT

D.

MATERIALS

01.00 k Grade 60 RSB (Deformed)


01.00 k Ga. #16 G.I. Wire
Sub-total

~
~

24.13 Lit/hr
10.00 Lit/hr

TOTAL COST

DIRECT LABOR COST


1 COLUMNS (First Lift only, No Splice)
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.

OUTPUT

D.

MATERIALS

500.00 kgs/hr

01.00 k Grade 60 RSB (Deformed)


01.00 k Ga. #16 G.I. Wire
Sub-total

~
~

24.13 Lit/hr
10.00 Lit/hr

TOTAL COST

DIRECT LABOR COST


1 SUSPENDED SLABS
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total

500.00 kgs/hr

C.

OUTPUT

D.

MATERIALS

01.00 k Grade 60 RSB (Deformed)


01.00 k Ga. #16 G.I. Wire
Sub-total

~
~

24.13 Lit/hr
10.00 Lit/hr

TOTAL COST

DIRECT LABOR COST


1 SUSPENDED BEAMS
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.

OUTPUT

500.00 kgs/hr

D.

MATERIALS

01.00 k Grade 60 RSB (Deformed)


01.00 k Ga. #16 G.I. Wire
Sub-total

~
~

24.13 Lit/hr
10.00 Lit/hr

TOTAL COST

DIRECT LABOR COST


1 COLUMNS (w/ 2 or More Storey)
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total

500.00 kgs/hr

C.

OUTPUT

D.

MATERIALS

01.00 k Grade 60 RSB (Deformed)


01.00 k Ga. #16 G.I. Wire
Sub-total

~
~

24.13 Lit/hr
10.00 Lit/hr

TOTAL COST

DIRECT LABOR COST


1 SUSPENDED SLABS (4.00m and above ground level)
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.

OUTPUT

500.00 kgs/hr

D.

MATERIALS

01.00 k Grade 60 RSB (Deformed)


01.00 k Ga. #16 G.I. Wire
Sub-total

~
~

24.13 Lit/hr
10.00 Lit/hr

TOTAL COST

DIRECT LABOR COST


1 SUSPENDED BEAMS (4.00m and above ground level)
A.

EQUIPMENT

1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~

1,100.00 /hr
1,100.00 /hr

~
~
~
~

50.00 /hr
38.75 /hr
37.50 /hr

MANPOWER

1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.

OUTPUT

D.

MATERIALS

500.00 kgs/hr

01.00 k Grade 60 RSB (Deformed)


01.00 k Ga. #16 G.I. Wire
Sub-total
TOTAL COST

DIRECT LABOR COST

~
~

24.13 Lit/hr
10.00 Lit/hr

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13

= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

=
=
=
=
=

1,100.00
1,100.00
0,039.76
0,268.77
2,508.53

=
=
=
=
=

0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr

= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr

PHP

5.88 /sq.m

STEELWORKS
1 STEEL COLUMNS - W -Section
A.

EQUIPMENT

1 Tower Crane
1 Welding Machine
2 Chain Block
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.

~
~
~
~
~

1,800.00 /hr
1,600.00 /hr
1400 /hr

=
=
=
=
=
=

1,800.00
1,600.00
2,800.00
0,067.20
0,752.06
7,019.26

~
~
~
~
~

50.00
43.75
75.00
50.00

=
=
=
=
=
=

0,050.00
0,350.00
0,150.00
0,050.00
0,072.00
0,672.00

MANPOWER

1 Foreman
8 Welder
2 Operator
1 Driver
Vat, 12%

/hr
/hr
/hr
/hr

Sub-total
C.

OUTPUT

D.

FUEL & OIL

kgs/hr

1 Tower Crane
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total
TOTAL COST

DIRECT LABOR COST

~
~
~
~
~
~

24.13
10.00
27.75
8.96
Php 35.00
Php 45.00

Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit

= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19
11,231.45

#DIV/0!

/hr

/hr
/hr

/sq.m

Direct Cost Only


ITEM No.

SCOPE OF WORKS

UNITS

MATERIALS

EARTHWORKS
A.
B.

Site Grading
Excavation
b.1 Ordinary
b.1.1 Manual
b.1.2 Bulk
b.2 Adobe
b.2.1 Manual
b.2.2 Bulk
C.
Aggregate Sub-base Course
c.1 Manual
c.2 Bulk
D.
Aggregate Base Course
d.1 Manual
d.2 Bulk
E.
Backfilling & Compaction
F.
Borrow Fill & Compaction
G.
Dewatering (No. of work days =

sq.m

cu.m
cu.m
cu.m
cu.m
cu.m
cu.m

###

cu.m
cu.m
cu.m
cu.m
lot

300.00

1,080.00
180.00

LABOR SCALE
Small

LABOR SCALE
Medium

137.86

211.87

112.25

113.15
114.43
223.49
38,969.66

Large

TOTAL DIRECT COST


Small
Medium
Large

300.00
1,080.00
180.00
-

137.86
211.87
412.25
1,193.15
114.43
403.49
38,969.66
-

300.00
1,080.00
180.00
-

SPACING OF H-FRAME (SCAFFOLDINGS)


Width
1.20m
Height
1.70m
Vert. Distance b/w Locks
1.20m
Cross Brace Length
2.50m

DESCRIPTION
Scaffoldings
H-Frames
1.20 x 1.70m H-Frame (G.I.)
1.20 x 1.20m H-Frame (G.I.)
1.20 x 0.90m H-Frame (G.I.)
1.20 x 1.70m H-Frame (B.I.)
1.20 x 1.20m H-Frame (B.I.)
1.20 x 0.90m H-Frame (B.I.)
0.90 x 1.70m H-Frame (G.I.)
0.90 x 1.20m H-Frame (B.I.)
0.90 x 0.90m H-Frame (B.I.)
Other Accessories
2.50m Cross Brace
2.25m Cross Brace
2.00m Cross Brace
1.80m Cross Brace
1.70m Cross Brace
1.50m Cross Brace

0.90m
1.20m
0.70m
2.20m

WIDTH

1.20
1.20
1.20
1.20
1.20
1.20
0.90
0.90
0.90

HEIGHT

1.70
###
0.90
1.70
###
0.90
1.70
1.20
###

0.90m
0.70m
2.00m

1.80m

Lock Vertical
Distance

1.20
0.70
0.70
1.20
0.70
0.70
1.20
0.70
0.70

1.70m

1.55m

1.25m

SPACING w/ CROSS BRACE USED Be


2.50

2.20

2.00

1.80

2.19
2.40
2.40
2.19
2.40
2.40
2.19
2.40
2.40

1.84
2.09
2.09
1.84
2.09
2.09
1.84
2.09
2.09

1.60
1.87
1.87
1.60
1.87
1.87
1.60
1.87
1.87

1.34
1.66
1.66
1.34
1.66
1.66
1.34
1.66
1.66

SS BRACE USED Below(m)


1.70

1.55

1.25

1.20
1.55
1.55
1.20
1.55
1.55
1.20
1.55
1.55

0.98
1.38
1.38
0.98
1.38
1.38
0.98
1.38
1.38

0.35
1.04
1.04
0.35
1.04
1.04
0.35
1.04
1.04

1. Item No.

2. Description
3. Quantity
4. Unit
II-C-3-b-iv-*** 6" chb wall
100.00
sq.mts.
5. Sequence of Operation
1. Lay-out & hauling of materials 2. Inst of batterboards / fab of rebars & forms / mixing of concrete 3. Inst
of rebars / laying of chb 4. Cleaning
No.
Description
Quantity
Unit
Unit Cost
Amount
1
Cement - type I, 40kgs/bag
20.00
bags
130.00
2,600.00
2
6" chb - non load bearing
1,250.00
pcs.
8.50
10,625.00
M
3
Sand
20.00 cu.m.
240.00
4,800.00
A
4
Reinforcing bars - 10mm x 6.00m.
10.00
pcs.
320.00
3,200.00
T
5
Concrete nail - assorted size
1.00
kgs.
45.00
45.00
E
6
Common wire nail - assorted size
1.00
kgs.
30.00
30.00
R
7
Nylon cord 0.15mm x 100m
2.00
rolls
10.00
0.20
I
8
Batterboard - assorted lumber
20.00 bd.ft.
22.00
440.00
A
9
Hacksaw blade
1.00
pc.
70.00
70.00
L
10
Tie wire - G.I. gauge no.16
0.05
rolls
1,000.00
50.00
S
11
Water
40.00
gals.
20.00
800.00
12
Waste fator
8.00
%
20,060.20
1,604.82
13
6. Direct Material Cost
P 24,265.02
No.
Description
Number
Hours
Rate / Hour
Amount
1
Project In-charge
1.00
3.20
75.00
240.00
2
Field Engineer
1.00
3.20
43.75
140.00
3
Timekeeper
1.00
3.20
40.00
128.00
L
4
Warehouseman
1.00
3.20
43.75
140.00
A
5
Foreman
1.00
3.20
43.75
140.00
B
6
Leadman
1.00
16.00
40.00
640.00
O
7
Operator
1.00
16.00
37.50
600.00
R
8
Mason
5.00
16.00
37.50
3,000.00
9
Steelman
1.00
16.00
37.50
600.00
10
Laborer
8.00
16.00
31.25
4,000.00
11
Utility
1.00
3.20
31.25
100.00
7. Direct Labor Cost
P 9,728.00
No.
Description
Number
Hours
Rate / Hour
Amount
E
1
Bagger Mixer
1.00
16.00
50.00
800.00
Q
2
Power Sprayer
1.00
16.00
10.00
160.00
U
3
Hacksaw
1.00
16.00
2.00
32.00
I
4
###
P
5
###
M
6
###
E
7
###
N
8
###
T
9
###
8. Direct Equipment Cost
P 992.00
9. Total Direct Cost (5+6+7)
P 34,985.02
20. Work days to 10. Overhead Expenses (OE) = 7 % of ( 9 )
2,448.95
complete
1,123.02
11. Contingencies (C) = 3 % of ( 9 + 10 )
2 days
771.14
12. Miscellaneous Expenses (ME) = 2 % of ( 9 + 10 + 11 )
21. Calendar days 13. Contractor's Profit (CP) = 8 % of ( 9 + 10 + 11 + 12 )
3,146.25
to complete 14. Value Added Tax (VAT) = 1 / 1.10 x 0.10 % of ( 7 + 8 )
974.55
2 days
318.05
15. Expanded Witholding Tax (EWT) = 1 / 1.10 x 0.10 x 0.10 % of ( 9 )
22. Average out- 16. Total Indirect Cost (TIC) = 10 + 11 + 12 + 13 + 14 + 15
P 8,781.95
put per working17. Total Cost (TC) = 9 + 16
P 43,766.97
day
437.67
18. Derived Unit Cost (DUC) = 17 / 3
50.00 sq.mts. 19. Corrected Unit Cost (CUC)
P 437.67

CONCRETING MATERIALS PRICE LISTS (Classic Materials)


Date (Updated): May 11,2010
Material Unit Cost
Unit
I. Concrete Materials
1. Aggregates

a. Course Aggregates
i.
G-1
ii.
3/4 Gravel
iii.
3/4 Crushed Gravel
b. Course Aggregates
i.
Vibro Sand
ii.
Riverwashed Sand
c. Others (Boulders)
i.
ii.
iii.
2. Cement
a. Portland Cement
i.
ii.
iii.
b. Pozzolan Cement
i.
ii.
iii.
3. Reinforcing Steel Bar
a. Grade 60
b. Grade 40
c. Grade 33
4. G.I. Wire
a. Gauge # 18
b. Gauge # 16

Supplier A
Amount

cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m

bag
bag
bag
bag
bag
bag
kg
kg
kg
kg
kg

Supplier name

Supplier B
Amount

Supplier name

LABOR RATES

al Unit Cost
Supplier C
Amount

Supplier name

Item
I. Indirect Manpower
Applied Price
1. Accountant
2. Cadet Engineer
3. Carpenter
0
4. Cost Engineer
0
5. Driver
0
6. Electrician
7. Field Engineer
0
8. Foreman
0
9. Glass Installer
10. Guard
0
11. Heavy Equipment Operator
0
12. Laborer
0
13. Leadman
14. Mason
15. Mechanic
0
16. Messenger
0
17. Mixer Operator
0
18. Painter
19. Plumber
0
20. Project In-charge
0
21. Screeder Operator
0
22. Steelman
23. Surveying Aide
0
24. Surveyor
0
25. Tile Setter
0
26. Timekeeper
27. Utility
0
28. Utility
0
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32.
33.

1
Provincial Rate
Minimum
Maximum
PHP 400.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

2
Manila Rate
Minimum
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

PHP 700.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

Applied Rate

600
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Location of Project:

5
4
3
2
1

FORMWORKS MATERIALS PRICE LISTS (Panel Forms)


Date (Updated): May 11,2010

Unit Cos
Unit
I. Rentals
1. Metal Forms

a. Metal Panels
i.
750 x 1800mm
ii.
750 x 1200mm
iii.
750 x 900mm
iv.
650 x 1800mm
v.
650 x 1500mm
vi.
650 x 1200mm
vii. 600 x 1800mm
viii. 600 x 1500mm
ix.
600 x 1200mm
x.
600 x 900mm
xi.
600 x 600mm
xii. 550 x 1800mm
xiii. 550 x 1500mm
xiv. 550 x 1200mm
xv.
550 x 900mm
xvi. 500 x 1800mm
xvii 500 x 1500mm
xviii. 450 x 1800mm
xix. 450 x 1500mm
xx.
450 x 900mm
xxi 400 x 1800mm
xxii 400 x 1500mm
xxii 400 x 1200mm
xxiv. 400 x 900mm
xxv. 400 x 600mm
xxvi. 350 x 1800mm
xxvii. 350 x 1500mm
350 x 1200mm
300 x 1800mm
300 x 1500mm
300 x 900mm
300 x 600mm
250 x 1800mm
250 x 1500mm
250 x 900mm
200 x 1800mm
200 x 1200mm
150 x 1800mm
150 x 1500mm
150 x 1200mm
150 x 600mm
100 x 1500mm
1.80 Corner Section
1.50 Corner Section
1.20 Corner Section
0.90 Corner Section
0.60 Corner Section
1.80 Exterior Angle

Supplier A
Rate/Day

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 4.00
PHP 3.00
PHP 2.33
PHP 3.50
PHP 3.00
PHP 2.67
PHP 3.33
PHP 2.83
PHP 2.50
PHP 1.83
PHP 1.58
PHP 3.08
PHP 2.67
PHP 2.33
PHP 1.67
PHP 2.83
PHP 2.50
PHP 2.58
PHP 2.33
PHP 1.42
PHP 2.33
PHP 2.17
PHP 1.83
PHP 1.33
PHP 1.25
PHP 2.17
PHP 2.00
PHP 1.67
PHP 2.00
PHP 1.83
PHP 1.17
PHP 1.00
PHP 1.83
PHP 1.67
PHP 1.08
PHP 1.67
PHP 1.17
PHP 1.50
PHP 1.33
PHP 1.00
PHP 0.67
PHP 1.17
PHP 1.67
PHP 1.67
PHP 1.17
PHP 0.92
PHP 0.67
PHP 0.50

Supplier name
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

Supplier B
Rate/Day
13

1.50 Exterior Angle


1.20 Exterior Angle
0.90 Exterior Angle
0.60 Exterior Angle
0.30 Exterior Angle
1.80 Edge Section
1.50 Edge Section
1.20 Edge Section
0.90 Edge Section
1.50 Interior Corner
b. Metal Form Accessories
Panel Clips
J Bolt 1-1/2"
Waler Washer
Coil Bolt 300mm
Coil Bolt 200mm
c. Panel Frame
600 x 2000mm
600 x 1800mm
600 x 1500mm
600 x 1200mm
600 x 900mm
550 x 1800mm
550 x 1500mm
550 x 900mm
550 x 600mm
500 x 1800mm
500 x 1500mm
500 x 1200mm
500 x 900mm
450 x 1800mm
450 x 1500mm
450 x 1200mm
450 x 900mm
400 x 2400mm
400 x 1800mm
400 x 1500mm
400 x 1200mm
400 x 900mm
400 x 600mm
350 x 1800mm
350 x 1500mm
350 x 1200mm
350 x 900mm
350 x 600mm
300 x 2400mm
300 x 1800mm
300 x 1500mm
300 x 1200mm
300 x 900mm
300 x 600mm
250 x 2400mm
250 x 1800mm
250 x 1500mm
250 x 1200mm

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 0.42
PHP 0.33
PHP 0.25
PHP 0.17
PHP 0.12
PHP 0.30
PHP 0.30
PHP 0.25
PHP 0.20
PHP 1.42
PHP 0.05
PHP 0.03
PHP 0.02
PHP 0.03
PHP 0.03
PHP 3.50
PHP 3.33
PHP 0.90
PHP 2.50
PHP 0.54
PHP 3.08
PHP 0.83
PHP 1.67
PHP 1.50
PHP 2.83
PHP 2.50
PHP 2.17
PHP 1.50
PHP 2.58
PHP 2.33
PHP 2.00
PHP 1.42
PHP 3.10
PHP 2.33
PHP 2.17
PHP 1.83
PHP 1.83
PHP 1.25
PHP 2.17
PHP 2.00
PHP 1.67
PHP 1.25
PHP 1.17
PHP 2.33
PHP 2.00
PHP 1.83
PHP 1.50
PHP 1.17
PHP 1.00
PHP 2.17
PHP 1.83
PHP 1.67
PHP 1.33

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

c
o
r
r
e
c
t
e
d
u
n
i
t
c
o
s

250 x 900mm
200 x 1800mm
200 x 1500mm
200 x 1200mm
200 x 900mm
200 x 600mm
150 x 1800mm
150 x 1500mm
150 x 1200mm
150 x 900mm
100 x 1800mm
100 x 1500mm
100 x 1200mm
100 x 900mm
1.80 Outer Angle
1.50 Outer Angle
1.20 Outer Angle
0.90 Outer Angle
0.60 Outer Angle
1.80 Inside Corner
1.50 Inside Corner
0.90 Inside Corner
1.50 Filler Angle
1.20 Filler Angle
0.60 Filler Angle
1.80 Inside Corner for Slab
0.90 Inside Corner for Slab
0.60 Inside Corner for Slab
d. Gang Form
D-Beam x 3.30m (2.5mm thk)
D-Beam x 2.40m (2.5mm thk)
D-Beam x 1.40m (2.5mm thk)
D-Beam x 1.20m (2.5mm thk)
D-Beam x 0.60m (2.5mm thk)
Splice Plate
Cast Plate
Wing Nut 21mm
Wing Nut 17mm
Wing Nut 12mm
Tie Rod - 17mm x 300mm
e. Other Accessories
Wedge Pin
C-Purlins
2. Scaffoldings
a. H-Frames
i.
1.70 x 1.20m H-Frame (G.I.)
ii.
1.20 x 1.20m H-Frame (G.I.)
iii.
0.90 x 1.20m H-Frame (G.I.)
iv.
1.70 x 1.20m H-Frame (B.I.)
v.
1.20 x 1.20m H-Frame (B.I.)
vi.
0.90 x 1.20m H-Frame (B.I.)
vii. 1.70 x 0.90m H-Frame (G.I.)
viii. 1.20 x 0.90m H-Frame (B.I.)
ix.
0.90 x 0.90m H-Frame (B.I.)
b. Other Accessories

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 1.08
PHP 1.67
PHP 0.30
PHP 1.17
PHP 1.00
PHP 0.83
PHP 1.50
PHP 0.23
PHP 1.00
PHP 0.14
PHP 0.18
PHP 0.15
PHP 0.12
PHP 0.09
PHP 0.50
PHP 0.42
PHP 0.33
PHP 0.25
PHP 0.17
PHP 1.67
PHP 1.42
PHP 0.92
PHP 0.33
PHP 0.20
PHP 0.15
PHP 1.67
PHP 0.25

PHP 0.16
PHP 1.68

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 1.70
PHP 0.92
PHP 0.83
PHP 1.70
PHP 0.92
PHP 0.83
PHP 1.00
PHP 0.75
PHP 0.67

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

PHP 2.99
PHP 2.18
PHP 1.27
PHP 1.09
PHP 0.54
PHP 0.18
PHP 0.18
PHP 0.11
PHP 0.11
PHP 0.11
PHP 0.50

u
n
i
t
c
o
s
t

i.
2.50m Cross Brace
ii.
2.25m Cross Brace
iii.
2.00m Cross Brace
iv.
1.80m Cross Brace
v.
1.70m Cross Brace
vi.
1.50m Cross Brace
vii. Straight Props (outer pipe)
viii. Straight Props (inner pipe)
ix.
Fixed U-head 2"
x.
Fixed U-head 4"
xi.
Adjustable U-head 2"
xii. Adjustable U-head 3"
xii. Adjustable U-head 4"
xiv. Adjustable Base Jack
xv.
Joint Pin
c. Waller Pipe & Accessories
1" x 6.00m GI Pipe
i.
1" x 5.50m GI Pipe
ii.
1" x 5.00m GI Pipe
iii.
1" x 4.50m GI Pipe
iv.
1" x 4.00m GI Pipe
v.
1" x 3.00m GI Pipe
vi.
vii. 1" x 2.50m GI Pipe
viii. 1" x 2.40m GI Pipe
1" x 2.00m GI Pipe
ix.
1" x 1.85m GI Pipe
x.
1" x 1.60m GI Pipe
xi.
xii. 1" x 1.50m GI Pipe
xiii. 1" x 1.00m GI Pipe
xiv. 1" x 0.80m GI Pipe
1" x 0.70m GI Pipe
xv.
xvi. 1" x 0.50m GI Pipe
xvii 1" x 0.40m GI Pipe
xviii. Swivel Clamp
xix. Fixed Clamp
1" x 6.00m Double Pipe
xx.
xxi 1" x 5.00m Double Pipe
xxii 1" x 4.00m Double Pipe
xxii 1" x 3.00m Double Pipe
xxiv. 1" x 2.50m Double Pipe
xxv. 1" x 2.00m Double Pipe
xxvi. 1" x 1.50m Double Pipe
xxvii. 1" x 1.00m Double Pipe
d. Steel Headers
i.
2" x 4" BI Steel Headers x 3.00m
ii.
2" x 4" BI Steel Headers x 2.44m
iii.
2" x 4" BI Steel Headers x 2.00m
iv.
2" x 4" BI Steel Headers x 1.80m
v.
2" x 4" BI Steel Headers x 1.50m
vi.
2" x 4" BI Steel Headers x 1.20m
vii. 2" x 4" I-beam Steel Headers x 3.00m
viii. 2" x 4" I-beam Steel Headers x 1.50m
d. Hanging Steel Scaffolds
i.
Gondola
ii.
Gondola Bracket 0.40

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.67
PHP 0.67
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.07

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece

PHP 2.33
PHP 2.17
PHP 2.00
PHP 1.83
PHP 1.67
PHP 1.33
PHP 1.17
PHP 1.09
PHP 1.00
PHP 0.93
PHP 0.90
PHP 0.83
PHP 0.83
PHP 0.81
PHP 0.80
PHP 0.78
PHP 0.77
PHP 0.29
PHP 0.29
PHP 4.66
PHP 4.00
PHP 3.34
PHP 2.66
PHP 2.34
PHP 2.00
PHP 1.66
PHP 1.34

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

piece
piece
piece
piece
piece
piece
piece
piece

PHP 1.17
PHP 1.00
PHP 1.00
PHP 0.83
PHP 0.67
PHP 0.50
PHP 4.59
PHP 4.20

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

piece
piece

PHP 3.17
PHP 5.67

FEMD
FEMD

iii.
Gondola Bracket 0.55
iv.
Steel Platform (CP) 0.40 x 2.00m
v.
Steel Platform (EW) 0.40 x2.00m
vi.
Steel Ladder (Expanded Metal)
vii. Double C-Purlins Flatform x 3.00m
d. Others
i.
Caster Wheel (Swivel)

piece
piece
piece
piece
piece
piece
piece

PHP 4.79
PHP 1.67
PHP 5.79
PHP 21.58
PHP 2.94
PHP 1.95

FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD

LABOR RATES
Unit Cost
Supplier B
Supplier name

Supplier C
Rate/Day
14

Applied Rate

Supplier name
14.00
3.00
2.33
3.50
3.00
2.67
3.33
2.83
2.50
1.83
1.58
3.08
2.67
2.33
1.67
2.83
2.50
2.58
2.33
1.42
2.33
2.17
1.83
1.33
1.25
2.17
2.00
1.67
2.00
1.83
1.17
1.00
1.83
1.67
1.08
1.67
1.17
1.50
1.33
1.00
0.67
1.17
1.67
1.67
1.17
0.92
0.67
0.50

Item
I. Indirect Manpower
1. Accountant
2. Cadet Engineer
3. Carpenter
4. Cost Engineer
5. Driver
6. Electrician
7. Field Engineer
8. Foreman
9. Glass Installer
10. Guard
11. Heavy Equipment Operator
12. Laborer
13. Leadman
14. Mason
15. Mechanic
16. Messenger
17. Mixer Operator
18. Painter
19. Plumber
20. Project In-charge
21. Screeder Operator
22. Steelman
23. Surveying Aide
24. Surveyor
25. Tile Setter
26. Timekeeper
27. Utility
28. Utility
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32.
33.

1
Provincia
Minimum
PHP 400.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

0.42
0.33
0.25
0.17
0.12
0.30
0.30
0.25
0.20
1.42
0.05
0.03
0.02
0.03
0.03
3.50
3.33
0.90
2.50
0.54
3.08
0.83
1.67
1.50
2.83
2.50
2.17
1.50
2.58
2.33
2.00
1.42
3.10
2.33
2.17
1.83
1.83
1.25
2.17
2.00
1.67
1.25
1.17
2.33
2.00
1.83
1.50
1.17
1.00
2.17
1.83
1.67
1.33

1.08
1.67
0.30
1.17
1.00
0.83
1.50
0.23
1.00
0.14
0.18
0.15
0.12
0.09
0.50
0.42
0.33
0.25
0.17
1.67
1.42
0.92
0.33
0.20
0.15
1.67
0.25
2.99
2.18
1.27
1.09
0.54
0.18
0.18
0.11
0.11
0.11
0.50
0.16
1.68

1.70
0.92
0.83
1.70
0.92
0.83
1.00
0.75
0.67

0.33
0.33
0.33
0.33
0.33
0.33
0.67
0.67
0.50
0.50
0.50
0.50
0.50
0.50
0.07
2.33
2.17
2.00
1.83
1.67
1.33
1.17
1.09
1.00
0.93
0.90
0.83
0.83
0.81
0.80
0.78
0.77
0.29
0.29
4.66
4.00
3.34
2.66
2.34
2.00
1.66
1.34
1.17
1.00
1.00
0.83
0.67
0.50
4.59
4.20
3.17
5.67

4.79
1.67
5.79
21.58
2.94
1.95

1
Provincial Rate
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

2
Manila Rate
Minimum
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

PHP 700.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00

Applied Rate

600
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Location of Project:

5
4
3
2
1

ITEM
No.

DESCRIPTION

DATE OF CANVASS UNIT

Cement
Portland Cement
Colored Cement
M10 Cement Mortar
Portland Cement (Northern Cement)
Portland Cement (Holcim Cement)
M 7.50 Cement
M10 Cement
Reinforcing Steel Bars - Deformed Bars
Grade 60 Rebars
Grade 40 Rebars
Grade 30 Rebars
Ga. # 16 GI Wire
Concrete Aggregates / Boulders
G-1 Gravel
Agg.Sub-base Coarse
Agg.Base Coarse
Black Sand
White Sand
Light Aggregates (Dead Gravel)
Boulders
Mortar Rubber Masonry
Boulders (6-8 inches dia.)
Sand
Washed Sand (White)
Wash Sand
Crushed Gravel 3/4"
Stone Masonry (Rip Rap)
Boulders 6"-8" Diam.
Concrete
525 Ready Mixed Concrete

kgs
kgs
kgs

SUPPLIER 1
Name

4000 psi Concrete


G-1 : Direct pouring
3/4 : Direct pouring
Pumpcrete
3000 psi Concrete (3/4 agg.)
4000 Psi Concrete G-1 : Direct Pouring
4000 Psi Concrete 3/4 : Direct Pouring
4000 Psi Concrete Pumpcrete Design
4000 Psi Concrete (G-1 Agg)
4000 Psi Concrete (3/4 Agg)
2500 Psi Concrete (G-1 Agg)
2500 Psi Concrete (3/4 Agg)
4000 Psi Concrete (3/4 Agg) Pumpcrete Design
3000 Psi Concrete (3/4 Agg) Pumpcrete Design
Lean Concrete (1000 Psi)
3000 Psi Concrete (3/4 Agg) Pumpcrete Design
4,000psi Concrete (3/4agg) Pumpcrete Design
3,000psi Concrete (G-1) Direct Pouring
3,000psi Concrete (3/4agg) Direct Pouring
Portland Cement Concrete 4000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 5000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 6000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 8000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 6000 psi 28da G-1 Slump-3"-4"
3000 Psi Concrete (3/4 Agg)

Concrete Hollow Blocks (CHB)


Load Bearing
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
8" CHB Load Bearing
Non-Load Bearing
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"

Fuel & Oil


Premium Fuel
Diesel
Lubricating Oil
Fill Materials
Earthfill
Rammer Filling Clay

Plywood / Plyboard

1/4"thk. Narra Plywood


16x600x600 RH-90 Non-sagging Acoustic Board
16x600x600 Minaboard Fissured Acoustic Board
4.5 x 1200 x 2400 Ficem Board
18mm thk Plyboard
600x1200 Acoustic Board
4' x 8' x 12mm thk Marine Plywood (sheet)
Gypsum Board
3/4" thk Penolic Board
" thk Marine Plywood
" Ordinary Plywood
4' X 8' X 18Mm Thk Plyboard
4' X 8' Ficemboard
4' X 8' Gypsum Board
600 X 1200Mm Acoustic Board
" Hardiflex
Hardiflex Board

Common Working Nails (CWN)


CW Nails
CWN 4"
CWN 3"
CWN 2"

Lumber
Rough Tanguile
Kd Tanguile
Kd Tanguile Moulding
GOOD LUMBER S4 kd
1" x 3" x 10'
1" x 3" x 12'
1" x 4" x 12'
2" x 2" x 10'
2" x 2" x 12'
2" x 2" x 12'
2" x 3" x 10'
2" x 3" x 12'
4" x 4" x 10'
4" x 4" x 12'
1" x 5" x 10'
1" x 5" x 12'
4" x 4" x 10' Good Lumber
2" x 4" x 14' KD S4S
3" x 5" x 10' KD S4S
3" x 3" x 10' Good Lumber
2" x 2" x 10' S-4 (Good Lumber)
2"x2"x10' S4S Good Lumber

Admixtures
Curing Compound
Floor Hardener
Soil Poisoning / Termite Control
Solignum
Bolts & Screws
36mm A490 Anchor Bolt (L-850mm)
32Mm Anchor Bolt L=1300Mm
25Mm Anchor Bolt L=1000Mm
25Mm Anchor Bolt L=400Mm
20Mm Anchor Bolt L=300Mm
20Mm Anchor Bolt, L=350Mm
28Mm A307 (L=1000Mm) Anchor Bolt
28mmx1000mm Anchor Bolt (A325)
28mmx800mm Anchor Bolt
25Mm A307 (L=1000Mm) Anchor Bolt
20Mm A325 Anchor Bolt
16mm Anchor Bolt
13mmx300mm Anchor Bolt w/ standard lock nut & washer
Anchor Bolt 200mm x 300mm
20Mm X 150/95 Hlc Sleeve Anchor (Hilti)
20Mm B.I. Round Bar Ladder Rung
Self Tapping Screw
Hanger rods
Dyna Bolt 12mm x 100mm (pc)
12Mm Nut & Washer
M28 X 100Mm Machine Bolt
M25 X 100Mm Machine Bolt
M16 Bolt (Machine Bolt - 16Mm)(6"Length)
16mm Machine Bolts w/ nuts (4" long)
8Mm M.S. Bolt
6Mm M.S. Bolt
10mm Machine Bolt (L=1")
20Mm X 100Mm Stud Bolts
10Mm X 1" Bolts & Nuts
12Mm X 40Mm Long Bolts W/ Std Nuts & Washers
12Mm X 100Mm Long Dyna Bolt
12Mm Cap Screw
Self Tapping Screw
12Mm X 30Mm Flat Head Screw
Tekscrew
12mm Expansion Bolt w/ plate washer
Surveying Rod Socket
Purlins
178x50x20x2mm thk Purlins
Lc 175Mm X 50Mm X 20Mm X 2Mm Thk Purlin
Lc 175Mm X 50Mm X 12.5Mm X 2Mm Thk Purlin

150mm x 50mm x 2mm thk Purlin (2" x 6")


100 X 50 X 20 X 2Mm Thk Purlin
100mm x 50mm x 1.5mm thk Purlin (2" x 4")
100mm x 50mm x 2mm thk C-Purlins
50mm x 100mm x 2mm thk C-Purlin (per pc)
75 X 175 X 18 X 6Mm Thk Lc-Purlins (6M)
50 X 178Mm C-Purlin, Ga # 18
50 X 178Mm C-Purlin, Ga # 16
50 X 178Mm C-Purlin, Ga # 15
50mmx75mmx1.5mmx6m C-Purlin
2" X 3" X 0.9Mm Thk C-Purlins
50mm x 150mm x 1.00mm thk C-Purlin
2"x4" C-Purlins / 50x100x12.5x1.5mm thk C-Purlins
2"x4" Gauge #16 C-Purlins
2x4x1.5mmx6m C-Purlin
2"x7" C-Purlins
Roof Accessories
16Mm Round Bar (Cross Bracings)
12Mm Round Bar (Sagrods)
Std Turn Buckle (16Mm)
20mm Plain Round Bar (6m)
16Mm Round Bar (6m)
16Mm Plain Round Bar (Cross Bracing)
Rib-Type Long Span Pre-Painted 0.60Mm Thk Roofing
Insulation
Flashing
End Flashing
Ridge Roll
Gutter
Rib-Type Long Span Pre-Painted 0.60Mm Thk Wall Siding
10Mm Plain Round Bar (Sagrod)
Corrugated G.I. Roofing Ga. 24, 12' long (Apo)
Corrugated G.I. Roofing Ga. 24, 12' long (Ordinary)
Corrugated G.I. Roofing Ga. 24, 10' long (Apo)
Corrugated G.I. Roofing Ga. 24, 10' long (Ordinary)
G.I. Gutter Ga. 24, 8' long
G.I. Flashing Ga. 24, 8' long
16mm Plain Round Bar
12mm Plain Round Bar
8mm Plain Round Bar
Ga#16 Plain G.I. Sheet
20mm STD Turn Buckle
16mm STD Turn Buckle
16mm Plain Round Bar (6m)
12mm Plain Round Bar (6m)
10mm Plain Round Bar
16mm Plain Round Bar
16mm Sandard Turnbuckles

Damp Proofing / Concrete Curing


Curing Compound
8 Mils Polyethylene Sheet
6 mils Polyethylene Sheet
White Polyethylene Sheet
Barrafilm (6Mils)

Wire Mesh, Barbed Wire & Cyclone Wires


Chicken Wire Mesh
6" x 6" x 6mm Wire Mesh (6' x 6m)
Cyclone Wire (4" Mesh-2M Wide X 2M L)
Ga #9 EWWF G.I. Interlink
Cyclone Wire (1.20m x 10m)
Galvanized Barbed Wire Ga.#14
7Ft Width X 7M Length Cyclone Wire
6Ft Width X 7M Length Cyclone Wire
Cyclone Wire(1.80M)
Barbed Wire (30Kg/Roll)
Barbed Wire (50M/Roll)

Waterproofing / Water Stop


1/2"x3'x10' Joint Filler (Cork type)
Pej Filler W/ Sealant 12Mm Thk
Sealant
Pvc Water Stop, T=6Mm, L=200Mm
Water-Seeping Geotextile(200g/sq.m)
Water Seeping Geotextile (200G/Sq.M)

Tubular Bar
175 x 50 x 3.20mm thk. B.I. Tubular
150 x 50 x 3.0mm thk B.I. Tubular
150 X 50 X 3.0Mm Thk B.I. Tubular
175 X 50 X 3.20 Tubular
12" X 10" X 3/10" (A36) Structural Tubing
12" X 10" X 1/4" (A36) Structural Tubing
2" X 4" X 0.9Mm Thk Tubular
1-1/2" X 1-1/2" Tubular
1" X 1" Tubular
2" X 4" Sch40 (4Mm Thk) Tubular
1-1/2" X 1-1/2" Sch40 (4Mm Thk) Tubular
2" x 4" Tubular Bar
2" x 6" Tubular Bar
1" x 4" Tubular Bar
4mm- 2"x4" Sch 40 Tubular

4mm- 1-1/2"x1-1/2" Tubular


50mm, Sch 40 Tubular Bar
50mmx100mmx1.5mmx6m Tubular Steel
50mmx150mmx1.5mmx6m Tubular Steel
50x100x1.5mm thk Light Gage Tubular Steel
50x150x1.5mm thk Light Gage Tubular Steel
1" x 1" Tubular Bar (1.20mm thk)

Flat Bars
1-1/4" X 1/4" Thk X 6M Flatbar (6Mm Thk)
1" X 1/4" X 6M Flatbar
100Mm X 12Mm Thk Flatbar
1-1/4" X 1/4" Thk Flatbar
1" X 1/4" Thk Flatbar
3/4" X 3/16" Thk Flatbar
2" x " thk Flat Bar
1" x " thk Flat Bar
2" X 1/4" Thk Flat Bar
12mm Square Bar
12mmx5mm thk Flat Bar
2"x"x6m Flat Bar
2"x"x6m Flat Bar
2"x3/8"x6m Flat Bar (7mm)

Epoxy Primer
Epoxy Primer Gray (ACP Concrete)
Epoxy Primer Gray (Rag J Hardware)
Epoxy Primer
Red Lead Oxide Primer

Checkered Plates
4' x 8' x 4.50mm thk Checkered Plate
4' x 8' x 6mm thk Checkered Plate
4' x 8' x 0.80mm thk Checkered Plate

Metal Decking
Metal Decking
0.80Mm Thk; 80,000Psi Steel Decking Rib-Type
0.80Mm Thk; 80,000Psi Steel Decking Flat-Type

Structural Tees
ST 12 x 60.5
ST 9 x 35
ST 2 x 3.55

Asphalt Sealer
Diamond Blade

SUPPLIER 1
Unit Price Terms

Discount

Name

SUPPLIER 2
Unit Price Terms

Discount

Name

SUPPLIER 3
Unit Price

SUPPLIER 3
Terms

Discount

REMARKS

STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES

W SHAPES

tf

tw
k
bf

Y
Web
Item
No.

Designation

Area(A)

Depth(d)

tw

W 44 x
x
x
x

285
248
224
198

(mm)
54,064
46,968
42,452
37,419

(mm)
1,118.11
1,107.95
1,100.07
1,089.91

(mm)
26.01
21.97
19.99
18.01

W 40 x
x
x
x
x
x

328
298
268
244
221
192

62,193
56,516
50,839
46,258
41,806
36,452

1,016.00
1,008.13
1,000.00
992.12
982.22
970.28

23.11
21.08
19.05
18.03
18.03
18.03

W 40 x
x
x
x
x
x
x
x
x

655
593
531
480
436
397
362
324
297

123,871
112,258
100,645
90,322
82,580
74,839
68,387
61,484
56,387

1,107.95
1,091.95
1,075.44
1,061.74
1,050.04
1,040.13
1,029.97
1,020.06
1,011.94

50.04
45.47
40.89
37.08
34.04
30.99
28.45
25.40
23.62

Flange
tw
2
(mm)
13.01
10.99
10.00
9.01
11.56
10.54
9.53
9.02
9.02
9.02
25.02
22.74
20.45
18.54
17.02
15.50
14.23
12.70
11.81

bf

tf

(mm)
(mm)
300.00
45.01
300.00
40.01
300.00
35.97
300.00
30.99
454.91
452.88
450.85
449.83
449.83
449.83

43.94
40.01
35.94
32
27.05
21.08

428.50
423.93
419.35
415.54
412.50
409.45
406.91
403.99
401.96

89.92
82.04
73.91
67.06
60.96
55.88
51.05
45.97
41.91

x
x
x
x

277
249
215
199

52,452
47,290
40,839
37,677

1,008.13
1,000.09
990.09
982.22

21.08
19.05
16.51
16.51

10.54
9.53
8.26
8.26

402.08
400.05
400.05
400.05

40.01
36.07
30.99
27.05

W 40 x 183
x 167
x 149

34,645
31,677
28,258

990.09
980.19
970.28

16.51
16.51
16.00

8.26
8.26
8.00

299.97
299.97
299.97

30.99
26.04
21.08

W 36 x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

848
798
720
650
588
527
485
439
393
359
328
300
280
260
245
230

160,645
150,967
136,129
122,580
110,968
99,355
91,613
82,580
74,193
67,742
62,193
56,968
53,161
49,355
46,516
43,613

1,078.23
1,066.04
1,046.23
1,027.94
1,011.94
995.93
984.00
971.80
960.12
949.96
942.09
933.20
927.61
921.00
916.43
911.86

64.01
60.45
54.99
50.04
45.47
40.89
38.10
34.54
30.99
28.45
25.91
24.00
22.48
21.34
20.32
19.30

32.01
30.23
27.50
25.02
22.74
20.45
19.05
17.27
15.50
14.23
12.96
12.00
11.24
10.67
10.16
9.65

460.50 115.06
456.95 108.97
451.49
99.06
446.41
89.92
441.96
82.04
437.39
73.91
434.47
68.07
430.91
61.98
427.48
55.88
424.94
51.05
422.40
47.19
423.04
42.67
421.51
39.88
420.37
36.58
419.35
34.29
418.34
32.00

W 36 x
x
x
x
x
x
x
x
x

256
232
210
194
182
170
160
150
135

48,645
43,935
39,871
36,774
34,581
32,258
30,323
28,516
25,613

950.72
942.85
931.93
926.85
922.78
918.72
914.65
910.59
902.97

24.38
22.10
21.08
19.43
18.42
17.27
16.51
15.88
15.24

12.19
11.05
10.54
9.72
9.21
8.64
8.26
7.94
7.62

310.26
307.85
309.37
360.72
306.71
305.56
304.80
304.17
303.53

43.94
39.88
34.54
32.00
29.97
27.94
25.91
23.88
20.07

W 33 x
x
x
x
x
x
x
x
x
x
x
x

619
567
515
468
424
387
354
318
291
263
241
221

116,774
107,097
97,419
88,387
80,000
72,903
67,097
60,322
55,226
49,935
45,742
41,935

977.14
962.91
948.94
934.97
923.04
913.13
902.97
893.06
884.94
877.06
868.17
861.82

50.04
45.97
41.91
38.61
35.05
32.00
29.46
26.42
24.38
22.10
21.08
19.69

25.02
22.99
20.96
19.31
17.53
16.00
14.73
13.21
12.19
11.05
10.54
9.85

429.51
425.45
421.39
417.96
414.40
411.48
408.94
406.02
403.99
401.45
402.84
401.45

89.92
83.06
75.95
69.09
62.99
57.91
53.09
48.01
43.94
39.88
35.56
32.39

x 201

38,129

855.47

18.16

9.08

399.82

29.21

W 33 x
x
x
x
x

169
152
141
130
118

31,935
28,839
26,839
24,710
22,387

859.03
850.65
845.82
840.49
834.64

17.02
16.13
16.51
14.73
13.97

8.51
8.07
8.26
7.37
6.99

292.10
293.75
292.99
292.35
291.59

30.99
26.80
24.38
21.72
18.00

W 30 x
x
x
x
x
x
x
x
x
x
x
x
x

581
526
477
433
391
357
326
292
261
235
211
191
173

109,677
99,355
90,322
81,935
73,548
67,097
61,742
55,290
49,484
44,516
40,000
36,193
32,774

898.91
882.90
868.93
854.96
843.03
833.12
822.96
813.05
802.89
795.02
785.88
779.27
773.18

50.04
45.47
41.40
38.10
34.54
31.50
28.96
25.91
23.62
21.08
19.69
18.03
16.64

25.02
22.74
20.70
19.05
17.27
15.75
14.48
12.96
11.81
10.54
9.85
9.02
8.32

411.48
406.91
402.97
399.42
395.99
392.94
390.40
387.48
384.94
382.40
383.67
382.02
380.62

89.92
82.04
74.93
68.07
61.98
56.90
52.07
46.99
41.91
38.10
33.40
30.10
27.05

W 30 x
x
x
x
x
x
x

148
132
124
116
108
99
90

28,064
25,097
23,548
22,064
20,452
18,774
17,032

779.02
769.87
766.32
762.25
757.68
753.11
750.06

16.51
15.62
14.86
14.35
13.84
13.21
11.94

8.26
7.81
7.43
7.18
6.92
6.61
5.97

266.19
267.84
267.08
266.57
266.07
265.43
264.16

29.97
25.40
23.62
21.59
19.30
17.02
15.49

W 27 x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

539
494
448
407
368
336
307
281
258
235
217
194
178
161
146

101,935
93,548
84,516
76,774
69,677
63,677
58,193
53,290
48,829
44,581
41,161
36,774
33,742
30,581
27,677

826.01
812.04
798.07
784.10
771.91
762.00
752.10
743.97
736.09
727.96
722.12
712.99
712.99
700.79
695.45

50.04
45.97
41.91
38.61
35.05
32.00
29.46
26.92
24.89
23.11
21.08
19.05
19.05
16.76
15.37

25.02
22.99
20.96
19.31
17.53
16.00
14.73
13.46
12.45
11.56
10.54
9.53
9.53
8.38
7.69

387.48
383.42
379.48
375.92
372.49
369.44
366.90
364.49
362.46
360.43
358.52
356.49
356.49
356.11
354.71

89.92
83.06
75.95
69.09
62.99
57.91
53.09
49.02
44.96
40.89
38.10
34.04
30.23
27.43
24.77

W 27 x 129
x 114

24,387
21,613

701.80
693.17

15.49
14.48

7.75
7.24

254.25
255.78

27.94
23.62

x 102
x 94
x 84

19,355
17,871
16,000

688.09
683.77
678.43

13.08
12.45
11.68

6.54
6.23
5.84

254.38
253.75
253.90

21.08
18.92
16.26

492
450
408
370
335
306
279
250
229
207
192
176
162
146
131
117
104

92,903
85,161
76,774
69,677
63,484
57,935
52,903
47,419
43,355
39,161
36,323
33,355
30,774
27,742
24,839
22,194
19,742

753.11
738.89
724.92
710.95
699.01
689.10
678.94
669.04
660.91
653.03
646.94
641.10
635.00
628.40
621.79
616.20
611.12

50.04
45.97
41.91
38.61
35.05
32.00
29.46
26.42
24.38
22.10
20.57
19.05
17.92
16.51
15.37
13.97
12.70

358.52
354.46
350.52
346.96
343.41
340.49
337.95
334.90
332.99
330.45
328.93
327.41
329.06
327.66
326.52
325.12
323.85

89.92
83.06
75.95
69.09
62.99
57.91
53.09
48.01
43.94
39.88
37.08
34.04
30.99
27.69
24.38
21.59
19.05

W 24 x 103
x 94
x 84
x 76
x 68

19,548
17,871
15,935
14,452
12,968

623.06
617.47
612.14
607.57
602.74

13.97
13.08
11.94
11.18
10.54

25.02
22.99
20.96
19.31
17.53
16.00
14.73
13.21
12.19
11.05
10.29
9.53
8.96
8.26
7.69
6.99
6.35
6.99
6.54
5.97
5.59
5.27

228.60
230.25
229.11
228.35
227.71

24.89
22.23
19.56
17.27
14.86

62
55

11,742
10,452

603.00
598.68

10.92
10.03

5.46
5.02

178.82
177.93

14.99
12.83

402
364
333
300
275
248
223
201
132
166
147
132
122
111
101

76,129
69,032
63,161
56,903
52,129
46,968
42,193
38,193
34,581
31,484
27,871
25,032
23,161
21,097
19,226

660.91
646.94
635.00
623.06
612.90
603.00
593.09
584.96
577.09
570.99
560.32
554.48
550.67
546.35
542.54

43.94
40.39
37.08
33.53
30.99
27.94
25.40
23.11
21.08
19.05
18.29
16.51
15.24
13.97
12.70

21.97
20.20
18.54
16.77
15.50
13.97
12.70
11.56
10.54
9.53
9.15
8.26
7.62
6.99
6.35

340.49
336.93
333.50
329.95
327.41
324.49
321.95
319.41
317.50
315.47
317.75
315.98
314.71
313.44
312.17

79.50
72.39
66.55
60.45
55.63
50.55
45.47
41.40
37.59
34.54
29.21
26.29
24.38
22.23
20.32

93

17,613

549.15

14.73

7.37

213.87

23.62

W 24 x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

W 24 x
x
W 21 x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
W 21 x

x
x
x
x

83
73
68
62

15,677
13,871
12,903
11,806

544.32
539.50
536.70
533.22

13.08
11.56
10.92
10.16

6.54
5.78
5.46
5.08

212.22
210.69
210.06
209.30

21.21
18.80
17.40
15.62

W 21 x
x
x

57
50
44

10,774
9,484
8,387

534.92
529.08
524.76

10.29
9.65
8.89

166.50
165.86
165.10

16.51
13.59
11.43

311
283
258
234
211
192
175
158
143
130

59,032
53,677
48,968
44,387
40,064
36,387
33,097
29,871
27,161
24,645

566.93
554.99
545.08
534.92
525.02
516.89
509.02
500.89
495.05
488.95

38.61
35.56
32.51
29.46
26.92
24.38
22.61
20.57
18.54
17.02

304.93
302.01
298.96
295.91
293.50
290.96
288.93
287.02
284.99
283.46

69.60
63.50
58.42
53.59
48.51
44.45
40.39
36.58
33.53
30.48

W 18 x 119
x 106
x 97
x 86
x 76

22,645
20,064
18,387
16,323
14,387

481.38
475.74
472.19
467.11
462.53

16.64
14.99
13.59
12.19
10.80

5.14
4.83
4.45
19.31
17.78
16.26
14.73
13.46
12.19
11.31
10.29
9.27
8.51
8.32
7.50
6.80
6.10
5.40
6.29
5.72
5.27
4.96
4.51
4.57
4.00
3.81
7.43
6.68
5.78
5.02
5.46
4.83
4.38
3.88
3.75
3.50

286.13
284.48
283.08
281.69
280.29

26.92
23.88
22.10
19.56
17.27

193.93
192.79
191.90
191.26
190.37

20.57
19.05
17.65
16.00
14.48

153.92
152.78
152.40

15.37
13.34
10.80

264.80
263.27
261.49
259.97

25.02
22.23
19.30
16.89

180.85
179.58
178.69
177.67
177.42

18.16
16.00
14.35
12.83
10.92

140.34

11.18

W 18 x
x
x
x
x
x
x
x
x
x

W 18 x
x
x
x
x

71
65
60
55
50

13,419
12,323
11,355
10,452
9,484

469.14
466.09
463.30
459.99
456.95

12.57
11.43
10.54
9.91
9.02

W 18 x
x
x

46
40
35

8,710
7,613
6,645

458.72
454.66
449.58

9.14
8.00
7.62

W 16 x 100
x 89
x 77
x 67

18,968
16,903
14,580
12,710

431.04
425.45
419.61
414.78

14.86
13.35
11.56
10.03

W 16 x
x
x
x
x

57
50
45
40
36

10,839
9,484
8,581
7,613
6,834

417.32
413.00
409.70
406.65
402.84

10.92
9.65
8.76
7.75
7.49

W 16 x

31

5,884

403.35

6.99

26

4,955

398.53

6.35

W 14 x
x
x
x
x
x

730
665
605
550
500
455

138,709
126,451
114,838
104,516
94,839
86,451

569.47
549.66
531.37
514.10
497.84
483.11

77.98
71.88
65.91
60.45
55.63
51.18

W 14 x
x
x
x
x
x
x
x
x
x
x
x
x

426
398
370
342
311
283
257
233
211
193
176
159
145

80,645
75,484
70,322
65,161
58,968
53,742
48,774
44,193
40,000
36,645
33,419
30,129
27,548

474.22
464.57
455.17
445.52
434.85
425.20
416.05
407.42
399.29
393.19
386.59
380.49
375.41

47.63
44.96
42.04
39.12
35.81
32.77
29.85
27.18
24.89
22.61
21.08
18.92
17.27

W 14 x 132
x 120
x 109
x 99
x 90

25,032
22,774
20,645
18,774
17,097

372.36
367.79
363.73
359.66
356.11

16.38
14.99
13.34
12.32
11.18

W 14 x
x
x
x

82
74
68
61

15,548
14,064
12,903
11,548

363.47
359.92
356.62
352.81

12.95
11.43
10.54
9.53

W 14 x
x
x

53
48
43

10,065
9,097
8,129

353.57
350.27
346.96

9.40
8.64
7.75

W 14 x
x
x

38
34
30

7,226
6,452
5,710

358.14
355.09
351.54

7.87
7.24
6.86

W 14 x
x

26
22

4,961
4,187

353.31
349.00

6.48
5.84

W 12 x 336
x 305
x 279

63,742
57,806
52,839

427.23
414.53
402.59

45.09
41.28
38.86

3.18
38.99
35.94
32.96
30.23
27.82
25.59
23.82
22.48
21.02
19.56
17.91
16.39
14.93
13.59
12.45
11.31
10.54
9.46
8.64
8.19
7.50
6.67
6.16
5.59
6.48
5.72
5.27
4.77
4.70
4.32
3.88
3.94
3.62
3.43
3.24
2.92
22.55
20.64
19.43

139.70

8.76

454.41 124.71
448.31 114.81
442.37 105.66
436.88
97.03
432.05
88.90
427.61
81.53
424.05
421.39
418.47
415.54
412.24
409.19
406.27
403.61
401.32
399.03
422.91
395.35
393.70

77.09
72.26
67.56
62.74
57.40
52.58
48.01
43.69
39.62
36.58
33.27
30.23
27.69

374.02
372.62
370.97
369.95
368.81

26.16
23.88
21.84
19.81
18.03

257.30
255.78
254.89
253.87

21.72
19.94
18.29
16.38

204.72
203.96
203.07

16.76
15.11
13.46

171.96
171.32
170.94

13.08
11.56
9.78

127.64
127.00

10.67
8.51

339.98
336.17
333.76

75.06
68.71
62.74

x
x
x
x
x
x
x
x
x
x
x
x
x
x

252
230
210
190
170
152
136
120
106
96
87
79
72
65

47,806
43,677
39,871
36,000
32,258
28,839
25,742
22,774
20,129
18,194
16,516
14,968
13,613
12,323

391.41
382.27
373.63
365.25
356.36
348.23
340.61
333.25
327.41
322.83
318.26
314.45
311.15
307.85

35.43
32.64
29.97
26.92
24.38
22.10
20.07
18.03
15.49
13.97
13.08
11.94
10.92
9.91

W 12 x
x

58
53

10,968
10,065

309.63
306.32

9.14
8.76

W 12 x
x
x

50
45
40

9,484
8,516
7,613

309.63
306.32
303.28

9.40
8.51
7.49

W 12 x
x
x

35
30
26

6,645
5,671
4,935

317.50
313.44
310.39

7.62
6.60
5.84

W 12 x
x
x
x

22
19
16
14

4,181
3,594
3,039
2,684

312.67
308.86
304.55
302.51

6.60
5.97
5.59
5.08

W 10 x 112
x 100
x 88
x 77
x 68
x 60
x 54
x 49

21,226
18,968
16,710
14,581
12,903
11,355
10,194
9,290

288.54
281.94
275.34
269.24
264.16
259.59
256.29
253.49

19.18
17.27
15.37
13.46
11.94
10.67
9.40
8.64

W 10 x
x
x

45
39
33

8,581
7,419
6,265

256.54
251.97
247.14

8.89
8.00
7.37

W 10 x
x
x

30
26
22

5,703
4,910
4,187

265.94
262.38
258.32

7.62
6.60
6.10

17.72
16.32
14.99
13.46
12.19
11.05
10.04
9.02
7.75
6.99
6.54
5.97
5.46
4.96
4.57
4.38
4.70
4.26
3.75
3.81
3.30
2.92
3.30
2.99
2.80
2.54
9.59
8.64
7.69
6.73
5.97
5.34
4.70
4.32
4.45
4.00
3.69
3.81
3.30
3.05
-

330.33
327.53
324.87
321.82
319.28
316.99
314.96
312.93
310.39
308.86
307.98
306.83
305.82
304.80

57.15
52.58
48.26
44.07
39.62
35.56
31.75
28.07
25.15
22.86
20.57
18.67
17.02
15.37

254.25
253.87

16.26
14.61

205.23
204.34
203.33

16.26
14.61
13.08

166.62
165.61
164.85

13.21
11.18
9.65

102.36
101.73
101.35
100.84

10.80
8.89
6.73
5.72

264.54
262.64
260.73
258.83
257.30
256.03
254.76
254.00

31.75
28.45
25.15
22.10
19.56
17.27
15.62
14.22

203.71
202.82
202.18

15.75
13.46
11.05

147.57
146.56
146.05

12.95
11.18
9.14

W 10 x
x
x
x

19
17
15
12

3,626
3,219
2,845
2,284

260.10
256.79
253.75
250.70

6.35
6.10
5.84
4.83

W8 x
x
x
x
x
x

67
58
48
40
35
31

12,710
11,032
9,097
7,548
6,645
5,890

228.60
222.25
215.90
209.55
206.25
203.20

14.48
12.95
10.16
9.14
7.87
7.24

W8 x
x

28
24

5,323
4,568

204.72
201.42

7.24
6.22

W8 x
x

21
18

3,974
3,394

210.31
206.76

6.35
5.84

W8 x
x
x

15
13
10

2,865
2,477
1,910

205.99
202.95
200.41

6.22
5.84
4.32

W6 x
x
x

25
20
15

4,735
3,787
2,858

162.05
157.48
152.15

8.13
6.60
5.84

W 6 x 16
x 12
x
9

3,058
2,290
1,729

159.51
153.16
149.86

6.60
5.84
4.32

W5 x
x

19
16

3,574
3,019

130.81
127.25

6.86
6.10

W4 x

13

2,471

105.66

7.11

3.18
3.05
2.92
2.42
7.24
6.48
5.08
4.57
3.94
3.62
3.62
3.11
3.18
2.92
3.11
2.92
2.16
4.07
3.30
2.92
3.30
2.92
2.16
3.43
3.05
3.56

102.11
101.85
101.6
100.58

10.03
8.38
6.86
5.33

210.31
208.79
205.99
204.98
203.71
203.07

23.75
20.57
17.40
14.22
12.57
11.05

165.99
164.97

11.81
10.16

133.86
133.35

10.16
8.38

101.98
101.60
100.08

8.00
6.48
5.21

154.43
152.91
152.15

11.56
9.27
6.60

102.36
101.60
100.08

10.29
7.11
5.46

127.76
127.00

10.92
9.14

103.12

8.76

Distance
T

k1

ASEP
Nominal
Weight

(mm)
(mm)
(mm) (kg/m)
981.08
68.26
34.93 424
981.08
63.50
33.34 369
981.08
58.74
33.34 333
981.08
53.98
31.75 295
857.25
857.24
857.24
857.24
857.24
857.24

79.38
76.20
71.44
66.68
61.91
57.15

42.86
41.28
39.69
39.69
39.69
39.69

488
443
399
363
329
286

857.25
857.25
857.25
857.25
857.25
857.25
857.25
857.25
857.25

125.41
117.48
109.54
101.60
96.84
92.08
85.73
80.96
77.79

57.15
53.98
50.80
50.80
49.21
47.63
46.04
44.45
42.86

975
882
790
714
649
591
539
482
442

DATE OF CANVASS

UNIT

SUPPLIER 1
Name

Unit Price

857.25
857.25
857.25
857.25

76.20
96.84
66.68
61.91

41.28
39.69
39.69
39.69

412
371
320
296

857.25
857.25
857.25

66.68
61.91
57.15

39.69
39.69
38.10

272
249
222

790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58

144.46
138.11
128.59
119.06
111.13
103.19
96.84
90.49
84.14
79.38
76.20
71.44
68.26
65.09
63.50
60.33

57.15
71.44
52.39
50.80
47.63
44.45
44.45
41.28
41.28
39.69
38.10
38.10
38.10
38.10
36.51
36.51

1262
1188
1071
967
875
784
722
653
585
534
488
446
417
387
365
342

815.98
815.98
815.98
815.98
815.98
815.98
815.98
815.98
815.98

66.68
63.50
58.74
55.56
53.98
50.80
49.21
47.63
42.86

49.21
31.75
31.75
30.16
30.16
30.16
28.58
28.58
28.58

381
345
313
289
271
253
238
223
201

755.65 111.13
755.65 103.19
755.65
96.84
755.65
88.90
755.65
84.14
755.65
79.38
755.65
73.03
755.65
68.26
755.65
65.09
755.65
60.33
755.65
55.56
755.65
52.39

44.45
42.86
41.28
39.69
36.51
34.93
34.93
33.34
31.75
30.16
30.16
30.16

921
844
766
696
631
576
527
473
433
391
359
329

755.65

49.21

28.58

299

755.65
755.65
755.65
755.65
755.65

52.39
47.63
44.45
42.86
47.31

28.58
28.58
26.99
26.99
26.99

251
226
210
193
176

679.45 109.54
679.45 101.60
679.45
95.25
679.45
87.31
679.45
82.55
679.45
76.20
679.45
71.44
679.45
66.68
679.45
61.91
679.45
57.15
679.45
53.98
679.45
49.21
679.45
47.63

42.86
41.28
39.69
38.10
36.51
34.93
33.34
31.75
30.16
28.58
28.58
26.99
26.99

865
783
710
644
582
531
485
435
388
350
314
284
257

679.45
679.45
679.45
679.45
679.45
679.45
679.45

50.80
44.45
42.86
41.28
39.69
36.51
33.34

25.40
26.99
25.40
25.40
25.40
25.40
25.40

220
196
185
173
161
147
134

609.60 107.95
609.60 101.60
609.60
93.66
609.60
87.31
609.60
80.96
609.60
76.20
609.60
71.44
609.60
66.68
609.60
63.50
609.60
58.74
609.60
55.56
609.60
52.39
609.60
47.63
609.60
46.04
609.60
34.77

41.28
29.69
38.10
36.51
33.34
33.34
31.75
30.16
28.58
28.58
26.99
25.40
26.99
25.40
25.40

802
735
667
606
548
500
457
418
384
350
323
289
265
240
217

609.60
609.60

23.81
23.81

192
170

46.04
41.28

609.60
609.60
609.60

39.69
36.51
34.93

23.81
23.81
23.81

152
140
125

553.40 109.54
553.40 103.19
553.40
95.25
553.40
88.90
553.40
82.55
553.40
77.79
553.40
73.03
553.40
68.26
553.40
63.50
553.40
60.33
553.40
57.15
553.40
53.98
553.40
50.80
553.40
47.63
553.40
44.45
553.40
41.28
553.40
38.10

39.69
38.10
34.93
33.34
31.75
34.93
28.58
28.58
25.40
25.40
25.40
25.40
23.81
26.99
26.99
26.99
25.40

732
670
607
551
499
455
415
372
341
308
286
262
241
217
195
174
155

553.40
553.40
553.40
553.40
553.40

44.45
41.28
39.69
36.51
34.93

20.64
25.40
23.81
23.81
23.81

153
140
125
113
101

553.40
553.40

34.93
33.34

23.81
23.81

92
82

463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55

98.43
92.08
85.73
79.38
76.20
69.85
65.09
60.33
57.15
53.98
47.63
46.04
42.86
41.28
39.69

36.51
34.93
33.34
31.75
30.16
28.58
26.99
25.40
25.40
23.81
26.99
25.40
25.40
23.81
23.81

598
542
496
446
409
369
332
299
196
247
219
196
182
165
150

463.55

42.86

25.40

138

463.55
463.55
463.55
463.55

39.69
38.10
36.51
34.93

23.81
23.81
22.23
22.23

124
109
101
92

463.55
463.55
463.55

34.93
33.34
30.16

22.23
22.23
22.23

85
74
65

393.70
393.70
393.70
393.70
393.70
393.70
393.70
393.70
393.70
393.70

87.31
80.96
76.20
69.85
65.09
61.91
57.15
53.98
50.80
47.63

30.16
60.16
28.58
25.40
25.40
23.81
11.11
11.11
20.64
20.64

463
421
384
348
314
286
260
235
213
193

393.70
393.70
393.70
393.70
393.70

44.45
41.28
39.69
36.51
34.93

23.81
23.81
22.23
22.23
20.64

177
158
144
128
113

393.70
393.70
393.70
393.70
393.70

38.10
36.51
34.93
33.34
31.75

22.23
22.23
20.64
20.64
20.64

106
97
89
82
74

393.70
393.70
393.70

31.75
30.16
28.58

20.64
20.64
19.05

68
60
52

330.83
330.83
330.83
330.83

42.86
39.69
36.51
34.93

23.81
22.23
22.23
20.64

149
132
115
100

330.83
330.83
330.83
330.83
330.83

34.93
33.34
31.75
30.16
28.58

22.23
20.64
20.64
20.64
19.05

85
74
67
60
54

330.83

28.58

19.50

46

330.83

26.99

19.50

39

285.75
285.75
285.75
285.75
285.75
285.75

141.29
131.76
122.24
114.30
106.36
98.43

55.56
52.39
49.21
46.04
44.45
41.28

1086
990
900
818
744
677

285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75

93.66
88.90
84.14
79.38
74.61
69.85
65.09
60.33
57.15
53.98
50.80
47.63
44.45

36.69
38.10
36.51
34.93
33.34
31.75
30.16
30.16
28.58
26.99
26.99
25.40
25.40

634
592
551
509
463
421
382
347
314
287
262
237
216

285.75
285.75
285.75
285.75
285.75

42.86
41.28
39.69
36.51
34.93

23.81
23.81
22.23
22.23
22.23

196
179
162
147
134

279.40
279.40
279.40
279.40

41.28
39.69
38.10
36.51

25.40
23.81
23.81
23.81

122
110
101
91

279.40
279.40
279.40

36.51
34.93
33.34

23.81
22.23
22.23

79
71
64

304.80
304.80
304.80

26.99
25.40
23.81

15.88
15.88
15.88

57
51
45

304.80
304.80

23.81
22.23

14.29
14.29

39
33

241.30
241.30
241.30

93.66
87.31
80.96

38.10
36.51
34.93

500
454
415

241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30

74.61
69.85
66.68
61.91
57.15
53.98
49.21
46.04
42.86
41.28
38.10
36.51
34.93
33.34

33.34
31.75
31.75
30.16
28.58
26.99
25.40
25.40
23.81
22.23
22.23
22.23
22.23
20.64

375
342
313
283
253
226
202
179
158
143
129
118
107
97

241.30
241.30

34.93
31.75

20.64
20.64

86
79

241.30
241.30
241.30

34.93
31.75
31.75

20.64
20.64
19.05

74
67
60

266.70
266.70
266.70

25.40
23.81
22.23

14.29
12.70
12.70

52
45
39

266.70
266.70
266.70
266.70

22.23
20.64
19.05
17.46

12.70
12.70
12.70
12.70

33
28
24
21

193.68
193.68
193.68
193.68
193.68
193.68
193.68
193.68

47.63
44.45
41.28
38.10
34.93
33.34
31.75
30.16

23.81
22.23
20.64
20.64
19.05
19.05
17.46
17.46

167
149
131
115
101
89
80
73

193.68
193.68
193.68

31.75
28.58
26.99

17.46
17.46
17.46

67
58
49

219.08
219.08
219.08

23.81
22.23
19.05

12.70
12.70
12.70

45
39
33

219.08
219.08
219.08
219.08

20.64
19.05
17.46
15.88

12.70
12.70
11.11
11.11

28
25
22
18

155.58
155.58
155.58
155.58
155.58
155.58

36.51
33.34
30.16
26.99
25.40
23.81

17.46
17.46
15.88
15.88
14.29
14.29

100
86
71
60
52
46

155.58
155.58

23.81
22.23

14.29
14.29

42
36

168.28
168.28

20.64
19.05

12.70
11.11

31
27

168.28
168.28
168.28

19.05
17.46
15.88

12.70
11.11
11.11

22
19
15

120.65
120.65
120.65

20.64
19.05
15.88

11.11
11.11
9.53

37
30
22

120.65
120.65
120.65

19.05
15.88
14.29

11.11
9.53
9.53

24
18
13

88.90
88.90

20.64
19.05

11.11
11.11

28
24

69.85

1.00

11.11

19

SUPPLIER 1
Terms

SUPPLIER 2
Discount

Name Unit Price Terms

SUPPLIER 3
Discount

Name Unit Price

Terms

Discount

REMARKS

STRUCTURAL STEEL
PRICE LIST
ANGLES

Y
x

R1

R2

S.I. Designation
Item
No.

Designation
ANGLES-Equal Legs
L 200 x 200
x
x
x
x
x
x

Weight(asep)

Area

Depth

Width

(kg/m)

(mm)

(mm)

(mm)

12
14
16
18
22
25

36.82
42.69
48.50
54.25
65.55
73.87

4,691
5,439
6,179
6,911
8,351
9,410

200
200
200
200
200
200

200
200
200
200
200
200

L 150 x 150

x
x
x
x
x
x
x

8
10
12
14
16
18
22

18.55
22.98
27.35
31.65
35.89
40.06
48.23

2,363
2,927
3,483
4,031
4,571
5,103
6,143

150
150
150
150
150
150
150

150
150
150
150
150
150
150

L 125 x 125

x
x
x

8
10
12

15.34
18.98
22.56

1,954
2,418
2,874

125
125
125

125
125
125

x
x
x
x

14
16
18
22

26.08
29.53
32.92
39.52

3,322
3,762
4,194
5,034

125
125
125
125

125
125
125
125

L 100 x 100

x
x
x
x
x
x
x

6
8
10
12
14
16
18

9.26
12.18
15.04
17.83
20.56
23.23
25.84

1,179
1,551
1,915
2,271
2,619
2,959
3,291

100
100
100
100
100
100
100

100
100
100
100
100
100
100

L 90 x 90

x
x
x
x

6
8
10
12

8.30
10.90
13.45
15.93

1,057
1,389
1,713
2,029

90
90
90
90

90
90
90
90

L 75 x 75

x
x
x
x
x

5
6
8
10
12

5.78
6.87
9.00
11.07
13.08

736
875
1,147
1,411
1,667

75
75
75
75
75

75
75
75
75
75

L 65 x 65

x
x
x
x
x

5
6
8
10
12

4.97
5.91
7.73
9.49
11.18

634
753
985
1,209
1,425

65
65
65
65
65

65
65
65
65
65

L 50 x 50

x
x
x
x
x

3
5
6
8
10

2.33
3.77
4.47
5.82
7.11

296
480
569
741
905

50
50
50
50
50

50
50
50
50
50

L 40 x 40

x
x
x

3
5
6

1.84
2.97
3.52

235
379
448

40
40
40

40
40
40

L 30 x 30

x
x
x

3
5
6

1.36
2.18
2.56

174
278
327

30
30
30

30
30
30

L 25 x 25

1.12

142

25

25

L 20 x 20

0.88

112

20

20

ANGLES-Unequal Legs
L 150 x 90
x
8
x
10
x
12

14.69
18.18
21.60

1,871
2,315
2,751

150
150
150

90
90
90

L 125 x 75

x
x
x
x

6
8
10
12

9.24
12.16
15.02
17.81

1,177
1,549
1,913
2,269

125
125
125
125

75
75
75
75

L 100 x 75

x
x
x
x

6
8
10
12

8.04
10.57
13.04
15.44

1,025
1,347
1,661
1,967

100
100
100
100

75
75
75
75

L 90 x 75

x
x
x
x

6
8
10
12

7.55
9.92
12.23
14.47

962
1,264
1,558
1,835

90
90
90
90

75
75
75
75

L 75 x 50

x
x
x
x

5
6
8
10

4.75
5.65
7.39
9.07

605
719
941
1,155

75
75
75
75

50
50
50
50

L 65 x 50

x
x
x
x

5
6
8
10

4.35
5.16
6.75
8.28

554
658
860
1,054

65
65
65
65

50
50
50
50

L 50 x 50

x
x

5
6

3.35
3.97

427
506

50
50

50
50

Thickness
t
(mm)
12
14
16
18
22
25
8
10
12
14
16
18
22
8
10
12

DATE OF CANVASS

UNIT

SUPPLIER 1
Name

Unit Price

Terms

SUPPL
Discount

Name

14
16
18
22
6
8
10
12
14
16
18
6
8
10
12
5
6
8
10
12
5
6
8
10
12
3
5
6
8
10
3
5
6
3
5
6
3
3

8
10
12
6
8
10
12
6
8
10
12
6
8
10
12
5
6
8
10
5
6
8
10
5
6

SUPPLIER 2
Unit Price Terms

SUPPLIER 3
Discount

Name Unit Price

Terms

Discount

REMARKS

STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
ANGLES

Y
x

R1

R2

Y
Item
No.

z
k

AISC Designation

(mm)
Equal legs and Unequal legs
L 9 x
4
x
5/8
x 9/16
x
1/2
L 8 x

L 8 x

x 1 1/8
x
1
x
7/8
x
3/4
x
5/8
x 9/16
x
1/2
x
x
x
x
x
x

1
7/8
3/4
5/8
9/16
1/2

Weight(asep)
per
m.
(kg/m)

Area
A
(mm)

28.58
26.99
25.40

39.139
35.418
31.698

4,987
4,516
4,032

44.45
41.28
38.10
34.93
31.75
30.16
28.58

84.677
75.896
66.967
57.890
48.663
44.050
39.288

10,774
9,677
8,516
7,355
6,200
5,600
5,000

38.10
34.93
31.75
28.58
26.99
25.40

65.777
58.187
50.300
42.413
38.246
34.228

8,387
7,419
6,413
5,394
4,877
4,355

7/16

23.81

30.061

3,826

L 8 x

x
x
x
x

1
3/4
9/16
1/2

38.10
31.75
26.99
25.40

55.657
42.710
32.591
29.168

7,097
5,445
4,148
3,710

L 7 x

x
x
x
x

3/4
5/8
1/2
3/8

31.75
28.58
25.40
22.23

38.990
32.888
26.638
20.239

4,961
4,181
3,387
2,568

L 6 x

x
x
x
x
x
x
x
x
x

1
7/8
3/4
5/8
9/16
1/2
7/16
3/8
5/16

38.10
34.93
31.75
28.58
26.99
25.40
23.81
22.23
20.64

55.657
49.258
42.710
36.014
32.591
29.168
25.596
22.174
18.453

7,097
6,277
5,445
4,587
4,148
3,710
3,265
2,813
2,355

L 6 x

x
x
x
x
x
x
x
x

7/8
3/4
5/8
9/16
1/2
7/16
3/8
5/16

34.93
31.75
28.58
26.99
25.40
23.81
22.23
20.64

40.478
35.121
29.763
26.936
24.108
21.281
18.304
15.328

5,148
4,477
3,781
3,426
3,065
2,697
2,329
1,955

x
x
x

1/2
3/8
5/16

25.40
22.23
20.64

22.769
17.412
14.584

2,903
2,206
1,852

x
x
x
x
x
x
x

7/8
3/4
5/8
1/2
7/16
3/8
5/16

34.93
31.75
28.58
25.40
23.81
22.23
20.64

40.478
35.210
29.763
24.108
21.281
18.304
15.328

5,148
4,477
3,781
3,065
2,697
2,329
1,955

x
x
x
x
x

3/4
5/8
1/2
7/16
3/8

31.75
28.58
25.40
23.81
22.23

29.466
25.001
20.239
17.858
15.477

3,748
3,174
2,581
2,277
1,968

L 6 x 3 1/2

L 5 x

L 5 x 3 1/2

x
x

5/16
1/4

20.64
19.05

12.947
10.417

1,652
1,329

L 5 x

x
x
x
x
x
x

5/8
1/2
7/16
3/8
5/16
1/4

25.40
25.40
23.81
22.23
20.64
19.05

23.364
19.049
16.816
14.584
12.203
9.822

2,974
2,419
2,135
1,845
1,548
1,252

L 4 x

x
x
x
x
x
x
x

3/4
5/8
1/2
7/16
3/8
5/16
1/4

28.58
25.40
22.23
20.64
19.05
17.46
15.88

27.531
23.364
19.049
16.816
14.584
12.203
9.822

3,510
2,974
2,419
2,135
1,845
1,548
1,252

x
x
x
x
x

1/2
7/16
3/8
5/16
1/4

23.81
22.23
20.64
19.05
17.46

17.709
15.775
13.542
11.459
9.227

2,258
1,994
1,723
1,452
1,168

x
x
x
x
x

1/2
7/16
3/8
5/16
1/4

23.81
22.23
20.64
19.05
17.46

16.519
14.584
12.649
10.715
8.631

2,097
1,852
1,600
1,348
1,090

L 3 1/2 x 3 1/2 x
x
x
x
x

1/2
7/16
3/8
5/16
1/4

22.23
20.64
19.05
17.46
15.88

16.519
14.584
12.649
10.715
8.631

2,097
1,852
1,600
1,348
1,090

x
x
x
x
x

1/2
7/16
3/8
5/16
1/4

23.81
22.23
20.64
19.05
17.46

15.179
13.542
11.756
9.822
8.036

1,935
1,710
1,484
1,245
1,006

L 3 1/2 x 2 1/2 x
x
x
x
x

1/2
7/16
3/8
5/16
1/4

23.81
22.23
20.64
19.05
17.46

13.989
12.352
10.715
9.078
7.292

1,774
1,568
1,361
1,148
929

L 4 x 3 1/2

L 4 x

L 3 1/2 x 3

L 3 x

x
x
x
x
x
x

1/2
7/16
3/8
5/16
1/4
3/16

20.64
19.05
17.46
15.88
14.29
12.70

13.989
12.352
10.715
9.078
7.292
5.521

1,774
1,568
1,361
1,148
929
703

x
x
x
x
x
x

1/2
7/16
3/8
5/16
1/4
3/16

22.23
20.64
19.05
17.46
15.88
14.29

12.649
11.310
9.822
8.334
6.697
5.045

1,613
1,426
1,239
1,045
845
643

x
x
x
x
x
x

1/2
7/16
3/8
5/16
1/4
3/16

20.64
19.05
17.46
15.88
14.29
12.70

11.459
10.120
8.780
7.441
6.101
4.569

1,452
1,290
1,116
942
768
582

L 2 1/2 x 2 1/2 x
x
x
x
x

1/2
3/8
5/16
1/4
3/16

20.64
17.46
17.15
14.29
12.70

11.459
8.780
7.441
6.101
4.569

1,452
1,116
942
768
582

x
x
x
x

3/8
5/16
1/4
3/16

17.46
15.88
14.29
12.70

7.887
6.697
5.387
4.092

1,000
845
684
522

x
x
x
x
x

3/8
5/16
1/4
3/16
1/8

15.88
14.29
12.70
11.11
9.53

6.994
5.834
4.747
3.631
2.455

877
742
605
461
312

L 1 3/4 x 1 3/4 x
x

1/4
3/16

12.70
11.11

4.122
3.155

525
401

L 1 1/2 x 1 1/2 x
x

1/4
3/16

11.11
9.53

3.482
2.679

444
340

L 1 1/4 x 1 1/4 x
x

1/4
3/16

11.11
9.53

2.857
2.202

363
280

L 1 1/8 x 1 1/8 x

1/8

5.56

1.339

172

L 3 x 2 1/2

L 3 x

L 2 1/2 x 2

L 2 x

6.35

1.191

151

DATE OF CANVASS

UNIT

SUPPLIER 1
Name

Unit Price

Terms

SUPPLIER 2
Discount

Name Unit Price

SUPPLIER 2
Terms

SUPPLIER 3
Discount

Name Unit Price

Terms

Discount

REMARKS

STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES

PIPES

Wall
Weight Nominal Outside
Inside
Thicknes
Item Designation
W
Diameter Diameter Diameter
s
No.
d
(kg/m)
(mm)
(mm)
(mm)
(mm)

Elastic Properties
A
(mm)

PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS

12
10
8
6
5
4
3.5
3
2.5
2
1.5
1.25
1
0.75
0.5

73.65
60.51
42.65
28.23
21.77
16.03
13.59
11.31
8.62
5.43
4.07
3.38
2.52
1.70
1.26

304.8
254.0
203.2
152.4
127.0
101.6
88.9
76.2
63.5
50.8
38.1
31.8
25.4
19.1
12.7

323.8
273.1
219.1
168.3
141.3
114.3
101.6
88.9
73.0
60.3
48.3
42.2
33.4
26.7
21.3

304.8
254.5
202.7
154.1
128.2
102.3
90.1
77.9
62.7
52.5
40.9
35.1
26.6
20.9
15.8

9.50
9.30
8.20
7.10
6.55
6.00
5.75
5.50
5.15
3.90
3.70
3.55
3.40
2.90
2.75

9,380
7,707
5,433
3,596
2,773
2,041
1,731
1,441
1,098
691
518
431
320
217
160

PE
PE
PE
PE
PE
PE
PE
PE
PE
PE
PE
PE
PE

12
10
8
6
5
4
3.5
3
2.5
2
1.5
1.25
1

97.08
81.57
64.65
42.68
30.88
22.30
18.68
15.24
11.40
7.43
5.43
4.47
3.24

304.8
254.0
203.2
152.4
127.0
101.6
88.9
76.2
63.5
50.8
38.1
31.8
25.4

323.8
273.1
219.1
168.3
141.3
114.3
101.6
88.9
73.0
60.3
48.3
42.2
33.4

298.5
247.7
193.7
146.3
122.3
97.2
85.4
73.7
59.0
49.3
38.1
32.5
24.3

12.65
12.70
12.70
11.00
9.50
8.55
8.10
7.60
7.00
5.50
5.10
4.85
4.55

12,365
10,390
8,235
5,436
3,934
2,841
2,379
1,941
1,451
947
692
569
412

PE 0.75
PE 0.5
PD
PD
PD
PD
PD
PD
PD

8
6
5
4
3
2.5
2

2.22
1.61

19.1
12.7

26.7
21.3

18.8
13.9

3.95
3.70

282
205

108.03
79.23
57.44
41.00
27.70
20.37
13.42

203.2
152.4
127.0
101.6
76.2
63.5
50.8

219.1
168.3
141.3
114.3
88.9
73.0
60.3

174.6
124.4
103.2
80.1
58.4
45.0
38.2

22.25
21.95
19.05
17.10
15.25
14.00
11.05

13,760
10,092
7,316
5,222
3,529
2,595
1,710

Elastic Properties
I x 10
(mm )
4

S x 10
(mm)

Schedule
No.

(mm)

11,128.6
67,013.3
30,176.8
11,696.1
6,326.7
3,009.4
1,993.7
1,257.0
636.8
277.2
129.0
81.2
36.2
15.4
7.1

718.0 111.03
490.0 93.43
275.5 74.62
139.2 57.00
89.3 47.76
52.7 38.36
39.2 33.96
28.3 29.56
17.4 24.10
9.2 20.04
5.3 15.82
3.8 13.71
2.2 10.66
1.2
8.47
0.7
6.62

40
40
40
40
40
40
40
40
40
40
40
40
40
40
40

150,675.8
88,241.1
44,120.5
16,857.4
8,616.0
4,000.0
2,613.9
1,619.1
799.2
361.3
162.7
100.7
44.1

929.4 110.29
646.2 92.17
401.7 73.09
200.3 55.77
121.8 46.75
70.0 37.50
51.5 33.18
36.5 28.83
21.9 23.46
12.0 19.45
6.7 15.35
4.8 13.31
2.6 10.35

80
80
80
80
80
80
80
80
80
80
80
80
80

DATE OF CANVASS

UNIT

SUPPLIER 1
Name

18.7
8.3

1.4
0.8

8.19
6.35

67,429.5
27,596.1
13,985.4
6,368.3
2,493.2
1,194.6
545.3

815.5
328.2
198.2
111.3
56.1
32.7
18.1

70.05
52.36
43.80
34.91
26.58
21.43
17.82

80
80
-

SUPPLIER 1
Unit Price

Terms

SUPPLIER 2
Discount

Name Unit Price Terms

SUPPLIER 3
Discount

Name Unit Price

Terms

LIER 3
Discount

REMARKS

MILD STEEL PLATES

SIZE
FRACTION
1/16"

1/14"

1/8"

3/16"

1/4"

5/16"

3/8"

5/16"

3/8"
7/16"
1/2"

5/8"

THICKNESS
(mm)
1.40
1.50
1.60
1.80
1.90
2.00
2.60
2.80
3.00
3.18
3.20
4.00
4.30
4.50
4.76
5.00
5.50
5.60
5.80
6.00
6.35
7.00
7.30
7.50
7.94
8.00
9.00
9.53
7.00
7.30
7.50
7.94
8.00
9.00
9.53
10.00
11.00
11.11
12.00
12.70
14.00

(inch)
0.06
0.06
0.06
0.07
0.08
0.08
0.10
0.11
0.12
0.13
0.13
0.16
0.17
0.18
0.19
0.20
0.22
0.22
0.23
0.24
0.25
0.25
0.29
0.30
0.31
0.32
0.35
0.38
0.25
0.29
0.30
0.31
0.32
0.35
0.38
0.39
0.43
0.44
0.47
0.50
0.551

WIDTH x LENGTH
1.219m x 2.438m 1.219m x 6.096m 1.524m x 6.096m
4' x 8'
4' x 20'
5' x 20'
WEIGHT (Kg)
32.70
81.70
35.01
87.52
37.34
93.40
42.00
105.02
44.40
110.90
46.70
116.70
60.70
151.70
65.35
163.40
204.20
70.01
175.00
219.00
74.10
185.20
232.00
74.10
186.70
233.40
93.40
233.40
292.00
100.40
250.90
314.00
105.00
262.50
328.20
111.12
277.90
347.40
116.70
291.70
365.00
128.40
320.90
401.10
130.70
326.70
408.40
135.40
338.40
423.00
140.00
350.10
438.00
148.20
370.50
463.10
163.40
408.40
511.00
170.40
426.00
532.40
175.00
438.00
547.00
185.30
463.10
579.00
186.70
466.80
583.40
210.00
525.10
656.40
222.30
555.70
695.00
163.40
408.40
511.00
170.40
426.00
532.40
175.00
438.00
547.00
185.30
463.10
579.00
186.70
466.80
583.40
210.00
525.10
656.40
222.30
555.70
695.00
233.40
583.40
729.30
256.70
641.80
802.20
259.40
648.40
810.50
280.10
700.10
875.20
296.40
741.00
926.20
327.00
816.80
1021.00

5/8"

3/4"

7/8"

1"
1-1/8"
1-1/4"

1-3/8"
1-1/2"
1-5/8"
1-3/4"
2"
2-1/4"
2-1/2"
3"
4"

15.00
15.90
16.00
17.00
18.00
19.00
19.10
21.00
22.00
22.20
24.00
25.00
25.40
28.00
28.60
30.00
31.80
32.00
34.00
34.90
35.00
38.00
38.10
40.00
41.30
44.80
46.00
50.00
50.80
57.00
57.20
63.50
65.00
75.00
76.20
100.00
101.60

0.591
0.625
0.630
0.669
0.709
0.748
0.750
0.827
0.866
0.875
0.945
0.984
1.000
1.102
1.125
1.181
1.250
1.260
1.339
1.375
1.378
1.496
1.500
1.575
1.625
1.750
1.811
1.969
2.000
2.244
2.250
2.500
2.559
2.953
3.000
3.937
4.000

350.10
371.00
373.40
397.00
420.10
443.40
445.00
490.10
513.40
519.00
560.10
583.40
593.00
654.00
667.00
700.10
741.00
747.00
794.00
815.10
817.00
887.00
889.20
934.00
963.30
1037.4
1074.0
1167.0
1186.0
1330.3
1334.0
1482.0
1517.0
1750.3
1778.3
2334.0
2371.1

875.20
926.20
933.50
991.80
1050.20
1108.50
1111.50
1225.20
1284.00
1297.00
1400.30
1459.00
1482.00
1634.00
1667.20
1750.32
1853.00
1867.00
1984.00
2038.00
2042.00
2217.10
2223.00
2334.00
2408.20
2593.40
2684.00
2917.20
2964.00
3326.00
3334.40
3705.00
3792.40
4376.00
4446.00
5834.40
5928.00

1094.00
1158.00
1167.00
1240.00
1313.00
1386.00
1389.30
1532.00
1605.00
1621.00
1750.30
1823.30
1852.40
2042.00
2084.00
2188.00
2316.00
2334.00
2480.00
2547.10
2553.00
2771.30
2779.00
2917.20
3010.20
3242.00
3355.00
3647.00
3705.00
4157.00
4168.00
4631.10
4740.50
5470.00
5557.30
7293.00
7410.00

1.829m x 6.096m
6' x 20'

245.00
263.00
278.00
280.10
350.10
376.30
394.00
417.00
438.00
481.30
490.10
508.00
525.10
556.00
613.00
639.00
656.40
695.00
700.13
788.00
834.00
613.00
639.00
656.40
695.00
700.13
788.00
834.00
875.20
963.00
973.00
1,050.20
1,111.50
1225.20

UNIT WEIGHT
(Kg/ft)
1.02
1.09
1.17
1.32
1.39
1.46
1.89
2.04
2.19
2.32
2.33
2.91
3.14
3.28
3.47
3.65
4.01
4.08
4.23
4.38
4.63
5.11
5.32
5.47
5.79
5.83
6.56
6.95
5.11
5.32
5.47
5.79
5.83
6.56
6.95
7.30
8.02
8.10
8.76
9.26
10.207

(Kg/m)
10.99
11.78
12.56
14.13
14.92
15.70
20.41
21.98
23.55
24.92
25.12
31.40
33.76
35.33
37.39
39.25
43.18
43.96
45.53
47.10
49.85
54.95
57.30
58.90
62.31
62.80
70.65
74.77
54.95
57.30
58.90
62.31
62.80
70.65
74.77
78.50
86.35
87.24
94.20
99.70
109.902

DATE OF CANVASS

UNIT

SUPPLIER 1
Name

1313.00
1389.30
1400.30
1488.00
1575.30
1663.00
1667.20
1838.00
1925.40
1945.00
2100.40
2188.00
2223.00
2450.50
2501.00
2626.00
2779.00
2801.00
2976.00
3057.00
3063.10

10.948
11.578
11.670
12.393
13.134
13.856
13.893
15.320
16.042
16.209
17.505
18.228
18.524

117.752
124.621
125.602
133.452
141.302
149.152
149.545
164.852
172.703
174.469
188.403
196.253
199.393

SUPPLIER 1
Unit Price Terms

Discount

SUPPLIER 2
Name Unit Price Terms

Discount

SUPPLIER 3
Name Unit Price Terms

LIER 3
Discount

REMARKS

STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
Y

Weight
W
(kg/m)

Designation
HxBxt

Area
A
(mm)

LR SHAPES
LR 175 x 50 x
x
x
x
x
LR 100 x 50 x
x
x
LR 50 x 40 x
x
x
x
x
LR 50 x 20 x
x
LR 40 x 25 x
x
x
x
LR 40 x 20 x
x
LR 40 x 18 x

4.0
3.5
3.0
2.5
2.0
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
2.5
2.0
3.5
3.0
2.5
2.0
2.5
2.0
2.5

13.09
11.56
10.01
8.42
6.80
6.48
5.48
4.45
4.61
4.15
3.65
3.13
2.57
2.34
1.94
2.77
2.48
2.14
1.78
1.95
1.62
1.87

1667
1473
1275
1073
867
825
698
567
587
528
465
398
327
298
247
353
315
273
227
248
207
238.2

DATE OF CANVASS

UNIT

x
LR 40 x 16 x
LR 38 x 18 x
x
LR 32 x 25 x
x
x
x
LR 32 x 16 x
LR 28 x 18 x
x
LR 25 x 16 x

2.0
2.0
2.5
2.0
3.5
3.0
2.5
2.0
2.0
2.5
2.0
2.0

1.56
1.50
1.79
1.50
2.33
2.10
1.83
1.53
1.25
1.40
1.18
1.03

198.8
190.8
228.2
190.8
297.4
267.4
233.2
194.8
158.8
178.2
150.8
130.8

LR 100 x 100 x
x
x
x
x
LR 75 x 75 x
x
x
x
x
LR 50 x 50 x
x
x
x
x
LR 32 x 32 x
x
x
x
x
LR 28 x 28 x
x
x
x
x
LR 25 x 25 x
x
x
x
LR 24 x 24 x
x
x
x

4.0
3.5
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
3.5
3.0
2.5
2.0
3.5
3.0
2.5
2.0

11.52
10.19
8.83
7.44
6.02
8.38
7.44
6.48
5.48
4.45
5.24
4.70
4.12
3.52
2.88
2.98
2.72
2.43
2.10
1.75
2.48
2.28
2.05
1.79
1.50
1.95
1.77
1.56
1.31
1.84
1.67
1.48
1.25

1467
1298
1125
948
767
1067
948
825
698
567
667
598
525
448
367
379
346
309
268
223
315
290
261
228
191
248
225
198
167
234
213
188
159

LS SHAPES

STRUCTURAL TUBING (AISC SECTIONS)


SQUARE

Name

SUPPLIER 1
Unit Price Terms

Discount

Name

SUPPLIER 2
Unit Price Terms

SUPPLIER
Discount

Name

SUPPLIER 3
Unit Price
Terms

Discount

REMARKS

STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
Y

STRUCTURAL TUBING (AISC SECTIONS)

AISC SECTIONS

Weight
Wall
Thickness per m.
(mm)
(kg/m)

Area
A
(mm)

SQUARE
16 x 16

14 x 14

12 x 12

12 x 12

15.88
12.70
9.53
7.94
15.88
12.70
9.53
7.94
15.88
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76

189.55
153.73
116.85
98.03
164.23
133.46
101.66
85.36
138.91
113.20
86.46
72.71
58.68
44.41
113.59
103.40
92.95
71.28
60.05
48.56
36.80

24129
19613
14903
12516
20903
17032
12968
10903
17677
14452
11032
9290
7484
5658
14452
13161
11871
9097
7677
6187
4690

DATE OF CANVASS

UNIT

9x9

8x8

7x7

6x6

5x5

15.88
14.29
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76

100.93
92.01
82.83
63.68
53.72
43.50
33.01
88.28
80.61
72.70
56.09
47.38
38.42
29.21
69.21
62.58
48.48
41.06
33.36
25.42
57.83
52.44
40.89
34.73
28.30
21.62
42.31
33.29
28.39
23.25
17.81

12839
11742
10581
8129
6839
5542
4206
11226
10258
9290
7161
6039
4897
3723
8839
8000
6181
5232
4252
3239
7355
6710
5213
4426
3606
2755
5394
4245
3169
2961
2271

15.88
12.70
9.53
7.94
12.70
9.53
7.94
12.70
9.53
7.94
12.70
9.53
7.94
15.88
12.70
9.53

189.55
153.73
116.85
98.03
133.46
101.66
85.36
113.20
86.46
72.71
113.20
86.46
72.71
164.23
133.46
101.66

43484
19613
14903
12516
17032
12968
10903
14452
11032
9290
14452
11032
9290
20903
17032
12968

RECTANGULAR
20 x 12

20 x 8

20 x 4

18 x 6

16 x 12

16 x 8

16 x 4

14 x 10

14 x 6

14 x 4

12 x 8

12 x 6

12 x 4

12 x 2
10 x 8

7.94
12.70
9.53
7.94
12.70
9.53
7.94
15.88
12.70
9.53
7.94
12.70
9.53
7.94
6.35
12.70
9.53
7.94
6.35
15.88
14.29
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35

85.36
113.20
86.46
72.71
92.95
71.28
60.05
138.91
113.20
86.46
72.71
92.95
71.28
60.05
48.56
82.83
63.68
53.72
43.50
113.59
103.40
92.95
71.28
60.05
48.56
36.80
100.93
92.01
82.83
63.68
53.72
43.50
33.01
88.28
80.61
72.70
56.09
47.38
38.43
29.21
33.36
25.42
100.93
92.01
82.83
63.68
53.72
43.50

10903
14452
11032
9290
11871
9097
7677
17677
14452
11032
9290
11871
9097
7677
6187
10581
8129
6839
5542
14452
13161
11871
9097
7677
6187
4690
12839
11742
10581
8129
6839
5542
4206
11226
10258
9290
7161
6039
4897
3723
4252
3239
12839
11742
10581
8129
6839
5542

10 x 6

10 x 5

10 x 4

10 x 2

9x7

9x6

9x5

9x3

15.88
14.29
12.70
9.53
7.94
6.35
15.88
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76

88.28
80.61
72.70
56.09
47.38
38.42
81.94
74.91
67.64
52.28
44.23
35.89
27.31
69.21
62.58
48.48
41.06
33.36
25.42
40.89
34.73
28.30
21.62
88.28
80.61
72.70
56.09
47.38
38.42
29.21
81.94
74.91
67.64
52.28
44.23
35.89
27.31
69.21
62.58
48.48
41.06
33.36
25.42
52.44
40.89
34.73
28.30
21.62

11226
10258
9290
7161
6039
4897
10452
9548
8645
6645
5632
4574
3477
8839
8000
6181
5232
4252
3239
5213
4426
3606
2755
11226
10258
9290
7161
6039
4897
3723
10452
9548
8645
6645
5632
4574
3477
8839
8000
6181
5232
4252
3239
6710
5213
4426
3606
2755

8x6

8x4

8x3

8x2

7x5

7x4

7x3

7x2
6x5

6x4

6x3

14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
12.70
9.53
7.94
6.35
4.76
6.35
4.76
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
9.53

69.21
62.58
48.48
41.06
33.36
25.42
57.83
52.44
40.89
34.73
28.30
21.62
47.38
37.10
31.56
25.78
19.72
33.29
28.39
23.25
17.81
52.44
40.89
34.73
28.30
21.62
47.38
48.48
41.06
33.36
42.31
33.29
28.39
23.25
17.81
20.70
15.92
47.38
37.10
31.56
25.78
19.72
42.31
33.29
28.39
23.25
17.81
29.50

8839
8000
6181
5232
4252
3239
7355
6710
5213
4426
3606
2755
6039
4729
4019
3284
2510
4245
3619
2961
2271
6710
5213
4426
3606
2755
6039
6181
5232
4252
5394
4245
3619
2961
2271
2639
2026
6039
4729
4019
3284
2510
5394
4245
3619
2961
2271
3761

6x2

5x4

5x3

5x2

4x3

4x2

3.5 x 2.5
3x2

7.94
6.35
4.76
9.53
7.94
6.35
4.76
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
7.94
6.35
4.76
7.94
6.35
4.76
7.94
6.35
4.76
6.35
4.76
6.35
4.76

25.24
20.70
15.92
25.70
22.07
18.17
14.02
29.50
25.24
20.70
15.92
32.19
25.70
22.07
18.17
14.02
18.90
15.64
12.13
18.90
15.64
12.13
15.74
13.11
10.22
13.11
10.22
10.58
8.32

3213
2639
2026
3277
2813
2316
1787
3761
3213
2639
2026
4103
3277
2813
2316
1787
2406
1994
1542
2406
1994
1542
2006
1671
1303
1671
1303
1348
1058

Name

SUPPLIER 1
Unit Price Terms

Discount

Name

SUPPLIER 2
Unit Price Terms

SUPPLIER
Discount

Name

SUPPLIER 3
Unit Price
Terms

Discount

REMARKS

STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
CHANNELS - AMERICAN STANDARD

Designation
C15 x 50
x 40
x 33.9
C12 x 30
x 25
x 20.7
C10 x 30
x 25
x 20
x 15.3
C9 x 20
x 15
x 13.4
C8 x 18.75
x 13.75
x 11.50
C7 x 14.75
x 12.25
x 9.8
C6 x 13
x 10.5
x 8.2
C5 x 9
x 6.7
C4 x 7.25
x 5.4
C3 x 6
x 5
x 4.1

Area
Depth
Nominal
A
d
Weight per m
DATE OF CANVASS
(mm)
(mm)
(kg/m)
9484
381.0
74.41
7613
381.0
59.53
6426
381.0
50.45
5690
304.8
44.64
4742
304.8
37.20
3929
304.8
30.81
5690
254.0
44.64
4742
254.0
37.20
3794
254.0
29.76
2897
254.0
22.77
3794
228.6
29.76
2845
228.6
22.32
2542
228.6
19.94
3555
203.2
27.90
2606
203.2
20.46
2181
203.2
17.11
2794
177.8
21.95
2323
177.8
18.23
1852
177.8
14.58
2471
152.4
19.35
1994
152.4
15.63
1548
152.4
12.20
1703
127.0
13.39
1271
127.0
9.97
1374
101.6
10.79
1026
101.6
8.04
1135
76.2
8.93
948
76.2
7.44
781
76.2
6.10

UNIT

Name

SUPPLIER 1
Unit Price Terms

Discount

Name

SUPPLIER 2
Unit Price Terms

Discount

Name

SUPPLIER 3
Unit Price
Terms

Discount

REMARKS

Skim Coat
Application
1-1.20kg / m
Commercial:
20kgs/bag
25kgs/bag

Skimcoat
10% Waste factor

1.2
0.12

per mm thickness

370 white
30/kg gray

15
15

18
1.8
19.8

Delivery Charging:
Date : December 15, 2010
From MANILA to port below:
PORT
CAGAYAN DE ORO

VAN SIZE
20FT GP
40FT HC

PIER - DOOR
33,568.00
58,556.00

DOOR - DOOR
38,568.00
55,556.00

TERMS & CONDITION


1 Payments terms : CASH-ON-DELIVERY, Negotiable.
2 Sailing Schedule : Monday, Wednesday, Friday & Sundays.
3 Shippings lines : 2GO Aboitiz, MCC Transport.
4 Trucking rates for pick-up and delivery are within city limits only, outsides services will be charge on a case to case basis.
5 Rates above are "ALL-IN" and inclusive of vat.
6 Allowable declared value for 10ft is P250,000.00; 20ft is P500,000.00 & 40ft is P1,000,000.00. Excess will be charge P3.65 per thousand.
7 Rates above are applicable only for regular cargo, cargo which need special handling (lashing, stripping and stuffing, crating) etc. will be charge o
8 Maximum weight for 20ft is 21tons; 40ft is 30tons inclusive of van weight.

X-TRA MILE Cargo Logistics

Additional +18,000.00 Trucking Charge From CDO Pier to Gingoog Proper.


Weight of Van:
20FT
40FT

3 TONS
6 TONS

e to case basis.

be charge P3.65 per thousand.


nd stuffing, crating) etc. will be charge on a case to case basis.

Quotation :
Supplier: PACIFIC CONCRETE PRODUCTS, INC.
Date: January, 10, 2011
Project Location: Dasmarinas, Cavite
Owner Supplied Cement:
Compressive Strength

Aggregates

Design Criteria

2500 psi, 28d


3000psi, 28d
4000psi, 28d
6000psi, 28d

3/4"
3/4"
3/4"
3/4"

Pumpcrete
Pumpcrete
Pumpcrete
Pumpcrete

Note:
Minimum Pumpcrete charge of P12,000.00 per setup of 50 m or less.
Additional P240.00/m in excess of 50 m per setup
Additional P30.00/floor beyond 5th using 3 meter floor to floor height basis.
Additional P10.00 per pipe/m for the set up exceeding 25 pieces of pipes.
Terms of Payment :
Validity of Price :
Delivery Schedule :
Note :

07 days from date of delivery.


30 days from date of offer.
After confirmation of your office / site and after issuance of P.O.
Cement should be delivered to our batching plant 2 to 3 days prior to pouring schedule. We prefer REPUBLIC

Supplier : FILMIXCO
Locaion : San Fernando, Pampanga
Owner Supplied Cement =
2,500psi
3,000psi
3,500psi

1,250.00 per Cu.m.


2,800.00 per Cu.m.
3,000.00 per Cu.m.
3,200.00 per Cu.m.

PROPORTION S OF CONCRETE
Class of Concrete
Class AA
Class A
Class B
Class C
Class D

AGGREGATES

Cement; Sand; Probable Strength After


Gravel by Volume
28 days
1 : 1 : 3
1:2:4
1 : 2 : 5
1:2:4
1 : 3 : 7

4000 - 3500 psi


3000 - 2500 psi
2000 - 1500 psi
1000 - 500 psi
Less than 500 psi

Supplier : Coernerstone/Prime Rock Crushing Plant


Locaion : San Jose, Palakol, Floridablanca, Pampanga
Tel. 02 361 4159 ; Tel./Fax 02 455 7602
MATERIALS0
CRUSHED G-3/4
CRUSHED G-3/8
CRUSHED G-1
BASE COURSE
SUBBASE COURSE
S-1
VIBRO SAND (4mm)

FROM
380.00/cu.m.
400.00/cu.m.
350.00/cu.m.
300.00/cu.m.
200.00/cu.m.
160.00/cu.m.
140.00/cu.m.

Gov't. Fee =
Pass ways =
1 TRUCK =

NEW PRICES
430.00/cu.m.
400.00/cu.m.
380.00/cu.m.
300.00/cu.m.
200.00/cu.m.
160.00/cu.m.
140.00/cu.m.
390 per truck/load
160 per truck/load

14.00 m

Supplier : MARLBORO QUARRY


Location : Porac, Pampanga
LAHAR - 1,000.00 (Truck/Load)
Gov't. Fee =
Pass ways =

Dump Truck Sample


UAV 699 (Class 3)
G-3/4
L5.30 x W2.20 x H1.20m =

430.00
13.99 m

Toll Fee (NLEx)


San Fernando Exit to Bocaue Exit =
Valenzuela Exit Fom Valenzuela Vicinity =
Valenzuela Exit to San Simon Exit =

421.00
122.00
235.00
Gov't. Fee =
Donation Fee =

390 per truck/load


210 per truck/load

360.00 per truck/load


140.00 per truck/load

Cement Factor (bags/m) Price/cu.m


10.0
11.5
14.5
19.0

1,150.00
1,150.00
1,150.00
1,150.00

or to pouring schedule. We prefer REPUBLIC PORTLAND CEMENT.

QTY PER 1.00M VOLUME OF CONCRETE


CEMENT

SAND
10.46
7.85
6.49
5.49
4.82

GRAVEL
0.42
0.42
0.44
0.44
0.45

0.84
0.84
0.87
0.89
0.91

SPECIALTY WORKS:
Peeble Washout Finish (This consist of a mixture of pea-sized pebbles and cement.)
Estimating Guides:
Floor Area x
Floor Area x
Wall Area
x
Wall Area
x

0.95
0.213
0.67
0.125

No. of 16-liter cans of pebbles required


No. of bags cement required
No. of 16-liter cans of pebbles required
No. of bags cement required

PAINTINGS

FLATWALL ENAMEL

a topcoat that gives a flat or eggshell finish. It is recommended for use on new or previously painted interior walls, ceilings, mouldings, plaste
thinned with paint thinner.

You might also like