Professional Documents
Culture Documents
II.
sq.m.
25.00
15.00
10.00
CARPENTRY WORKS
A. Formworks
1. Using Lumber (incl.stripping,formoil application & nail ext.)
a. Columns/Pedestal
i.Spiral
sq.m.
275.00
250.00
230.00
ii.Tied
sq.m.
250.00
240.00
225.00
b. Footing Tie Beams & Pile Caps
sq.m.
200.00
180.00
160.00
c. Floor Beams
sq.m.
240.00
220.00
200.00
d. Floor Slab
sq.m.
235.00
210.00
185.00
e. Floor Beams (Above 4.00m high)
sq.m.
250.00
240.00
230.00
f. Floor Slab (Above 4.00m high)
sq.m.
245.00
235.00
200.00
g. Roof Beams
sq.m.
255.00
240.00
230.00
h. Gutter w/ parapet
sq.m.
260.00
250.00
240.00
i. Roof Deck (if coverage is not the same as floorsq.m.
slabs below)
245.00
225.00
200.00
j. Shearwalls
sq.m.
250.00
235.00
210.00
k. Stair & Bleacher
sq.m.
275.00
270.00
260.00
l. Dentils
sq.m.
265.00
250.00
240.00
m. Parapet
sq.m.
250.00
240.00
210.00
n. Waffles
sq.m.
275.00
260.00
250.00
o. Stair on Fill
lm.
110.00
105.00
85.00
p. Lintel Beams & Stiff. Columns
sq.m.
210.00
205.00
200.00
q. Pavement
lm.
75.00
60.00
50.00
r. Slab on Fill
lm.
60.00
55.00
45.00
s. When forms used are scrap wood & lumber
plus 15.00 plus 15.00plus 15.00
2. Using Steel Forms
Installation
Small Sc. Big Scale
Stripping
165.00
160.00
155.00
160.00
155.00
185.00
180.00
165.00
180.00
160.00
160.00
80.00
80.00
75.00
80.00
80.00
85.00
85.00
80.00
85.00
80.00
80.00
a. Columns/Pedestal
i.Spiral
sq.m.
175.00
ii.Tied
sq.m.
180.00
b. Footing Tie Beams & Pile Caps
sq.m.
160.00
c. Floor Beams
sq.m.
175.00
d. Floor Slab
sq.m.
165.00
e. Floor Beams (Above 4.00m high)
sq.m.
200.00
f. Floor Slab (Above 4.00m high)
sq.m.
185.00
g. Roof Beams
sq.m.
180.00
h. Gutter w/ parapet
sq.m.
190.00
i. Roof Deck (if coverage is not the same as floorsq.m.
slabs below)
175.00
j. Shearwalls
sq.m.
165.00
3. Using Table Forms
sq.m.
220.00
i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers
1 of 616
sq.m.
sq.m.
sq.m.
sq.m.
17.50
20.00
25.00
30.00
10.00
15.00
17.50
20.00
7.50
10.00
15.00
17.50
v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers
sq.m.
sq.m.
sq.m.
sq.m.
35.00
40.00
45.00
50.00
25.00
30.00
35.00
40.00
20.00
25.00
30.00
35.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
12.50
17.50
22.50
25.00
30.00
35.00
40.00
45.00
20.00
10.00
15.00
20.00
22.50
25.00
30.00
35.00
40.00
15.00
7.50
10.00
15.00
17.50
20.00
25.00
30.00
35.00
10.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
17.50
20.00
25.00
30.00
35.00
40.00
45.00
50.00
15.00
17.50
20.00
25.00
30.00
35.00
40.00
45.00
10.00
15.00
17.50
20.00
25.00
30.00
35.00
40.00
b. Floor Slabs
i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers
v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers
ix. For Straight Props as Scaffoldings
c. Concrete Gutter Parapets (incl. Straight Props)
i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers
v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers
d. If H-Frame is to rest on soil
i. For Compacted Soil
ii. For Muddy/Loose Soil
e. Supporting Steel Deck
sq.m.
sq.m.
sq.m.
I.
2 of 616
40.00
50.00
60.00
45.00
50.00
35.00
45.00
45.00
40.00
45.00
40.00
45.00
35.00
40.00
30.00
35.00
sq.m.
sq.m.
sq.m.
set
set
set
105.00
110.00
175.00
330.00
385.00
275.00
85.00
105.00
110.00
275.00
360.00
220.00
70.00
80.00
85.00
250.00
330.00
200.00
set
set
set
500.00
650.00
450.00
450.00
600.00
400.00
400.00
450.00
350.00
lm.
lm.
a. On Double Walls
b. On Concrete Walls
D.
E.
F.
G.
H.
50.00
60.00
65.00
50.00
65.00
a. On Double Walls
b. On Concrete Walls
C.
Additional of P 5.00/sq.m.
Additional of P15.00/sq.m.
100.00
80.00
75.00
J.
K.
O.
P.
Q.
R.
S.
3 of 616
150.00
25.00
20.00
15.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
200.00
185.00
200.00
185.00
275.00
250.00
(By Negotiation)
160.00
150.00
185.00
175.00
175.00
175.00
200.00
135.00
160.00
lm.
lm.
lm.
30.00
35.00
15.00
25.00
30.00
12.50
20.00
25.00
10.00
sq.m.
sq.m.
sq.m.
sq.m.
210.00
190.00
245.00
110.00
200.00
185.00
235.00
105.00
185.00
160.00
210.00
85.00
sq.m.
sq.m.
110.00
100.00
100.00
85.00
85.00
75.00
set
set
lm.
set
165.00
185.00
30.00
20.00
160.00
175.00
25.00
15.00
140.00
140.00
22.50
12.50
Ceiling
III.
175.00
Baseboard
a. Kd. Tanguile
b. Narra
c. Vinyl
N.
bft.
185.00
sq.m.
sq.m.
210.00
lm.
115.00
lm.
135.00
by negotiation (30
lm.
25.00
lm.
45.00
set
set
set
set
set
set
lm.
pc.
pc.
pc.
200.00
185.00
110.00
100.00
125.00
110.00
% of materials)
20.00
15.00
40.00
35.00
200.00
175.00
125.00
500.00
125.00
125.00
75.00
6.50
17.50
17.50
A.
B.
C.
sq.m.
25.00
22.50
20.00
a. 8" CHB
b. 6" CHB
c. 4" CHB
sq.m.
sq.m.
sq.m.
185.00
165.00
155.00
175.00
155.00
150.00
165.00
135.00
125.00
sq.m.
sq.m.
175.00
165.00
165.00
160.00
160.00
155.00
sq.m.
sq.m.
200.00
185.00
175.00
165.00
160.00
155.00
sq.m.
sq.m.
155.00
185.00
150.00
175.00
145.00
165.00
sq.m.
175.00
(w/ scaffoldings)
165.00
160.00
a. 6" CHB
b. 4" CHB
D.
a. 6" CHB
b. 4" CHB
E.
200.00
35.00
sq.m.
sq.m.
220.00
45.00
sq.m.
sq.m.
270.00
55.00
sq.m.
sq.m.
285.00
65.00
sq.m.
sq.m.
sq.m.
sq.m.
lm.
lm.
lm.
lm.
lm.
sq.m.
sq.m.
lm.
sq.m.
200.00
210.00
100.00
125.00
200.00
145.00
165.00
160.00
150.00
100.00
330.00
300.00
85.00
185.00
190.00
85.00
110.00
185.00
135.00
160.00
150.00
110.00
65.00
260.00
165.00
175.00
80.00
100.00
165.00
110.00
125.00
110.00
75.00
35.00
225.00
sq.m.
250.00
240.00
225.00
sq.m.
325.00
300.00
285.00
a. By area
i.Flooring
ii.Walls
* w/scaffolding
4 of 616
sq.m.
sq.m.
* w/o scaffolding
b. by lm
G.
Sandblasting
Corduroy finish
Marble Finish / Granite Finish
a. 4"x8"Marble tiles
b. Marble @ Walls
c. Marble @ Floors
5 of 616
250.00
285.00
165.00
225.00
275.00
150.00
215.00
270.00
125.00
lm.
lm.
lft.
110.00
140.00
-
100.00
120.00
10.00
85.00
100.00
-
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
80.00
150.00
125.00
160.00
260.00
325.00
75.00
145.00
110.00
150.00
250.00
300.00
65.00
120.00
80.00
140.00
235.00
275.00
sq.m.
sq.m.
sq.m.
300.00
265.00
250.00
285.00
250.00
245.00
265.00
245.00
220.00
sq.m.
sq.m.
sq.m.
sq.m.
lm.
lm.
265.00
245.00
220.00
220.00
90.00
-
245.00
230.00
205.00
205.00
80.00
120.00
235.00
220.00
185.00
185.00
75.00
-
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
270.00
265.00
245.00
230.00
220.00
200.00
265.00
165.00
265.00
260.00
240.00
220.00
220.00
200.00
185.00
240.00
150.00
240.00
240.00
220.00
185.00
200.00
185.00
165.00
220.00
125.00
225.00
sq.m.
sq.m.
sq.m.
sq.m.
300.00
465.00
80.00
500.00
270.00
415.00
75.00
480.00
240.00
350.00
70.00
450.00
sq.m.
sq.m.
sq.m.
425.00
415.00
415.00
385.00
385.00
360.00
360.00
350.00
350.00
Brickworks
a. 1"x2"x8"Red bricks
b. 4"x8"Clay tiles
c. 12"x12"Red cement tiles
d. 8"x8"Clay tiles
e. 6"x6"x12"Louver blocks
f. 4"x12"x12"Decorative blocks
g. Mactan stone
h. Adobe blocks
i. Ashlar stone
j. Urra Tiles
* Ordinary Layout
* Extra-ordinary Layout (w/ many cuts)
L.
M.
N.
sq.m.
sq.m.
lm.
Tileworks
265.00
165.00
Topping
a. Straight to finish
b. Plain Cement finish
Stair Tread Topping
c. Red cement w/ V-cut
d. Deck Topping (including Cant,etc.)
e. Ramp Topping w/ Groove
J.
275.00
185.00
285.00
200.00
a. by area
i.Flooring
ii.Walls
b. by lm
H.
sq.m.
lm.
d. Granite @ Counters
lm.
e. Granite Splashboard
lm.
f. Granite Fascia Board
lm.
g. Opening for Lavatory
set
h. Rounding of Edges
lm.
i. Faucet Hole
set
j. Granite @ Walls including Anchors (Dry Anchors)
sq.m.
k. Granite @ Floors
sq.m.
l. Granolithic Flooring
sq.m.
O.
Rip-rapping
Synthetic Finish
a. by area
i. w/ scaffolding
ii. w/o scaffolding
b. by lm
R. Keyhole Pattern Bricks
S. 4"x8"Tiles w/ Pebble Washout Pattern
T. 200 x 200 Glass Blocks
U. Lime Stucco Finish
V. Skim Coating
L & M = 45.00/sq.m. (Gray)
L & M = 55.00/sq.m. (White)
W. Shotcreting
a. 6" thk.
b. 4" thk.
c. Exterior Walls
d. Opening
e. Grooves
IV.
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
6 of 616
###
550.00
550.00
###
385.00
###
###
385.00
385.00
350.00
-
sq.m.
sq.m.
lm.
lm.
cu.m.
40.00
80.00
70.00
70.00
510.00
35.00
65.00
50.00
60.00
480.00
30.00
55.00
40.00
50.00
415.00
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
400.00
375.00
245.00
275.00
400.00
480.00
80.00
-
365.00
330.00
220.00
235.00
350.00
415.00
70.00
45.00
55.00
320.00
290.00
200.00
200.00
330.00
350.00
55.00
-
Retouching
a. by area
i. Walls
ii.Exposed slab
b. by lm.(corners only)
c. Curbs & Gutter
P.
Q.
385.00
-
sq.m.
sq.m.
sq.m.
lm.
lm.
3.85
4.15
4.40
4.95
4.20
5.50
7.15
4.95
5.15
6.60
5.15
8.80
5.15
800.00
740.00
###
550.00
400.00
3.30
3.85
4.00
4.05
3.90
4.95
6.60
4.15
4.80
5.80
4.40
7.70
4.80
3.05
3.30
3.50
3.60
3.45
4.40
5.50
3.85
4.20
5.25
3.85
6.60
4.40
N.
O.
P.
Q.
R.
V.
A.
Backfilling
Levelling
Excavation of Ftg. Tie Beam & Wall Footings
Compaction
Basecoarse
Soil Poisoning
Polyethelene sheets
PVC Waterstop
Chipping
cu.m.
cu.m.
cu.m.
cu.m.
sq.m.
cu.m.
sq.m.
cu.m.
sq.m.
sq.m.
lm.
lm.
lm.
4.40
4.40
5.15
20.00
0.40
0.50
0.45
###
3.00
220.00
200.00
160.00
380.00
350.00
300.00
600.00
450.00
385.00
(By Administration)
160.00
145.00
120.00
50.00
40.00
35.00
415.00
365.00
350.00
50.00
40.00
35.00
185.00
145.00
110.00
20.00
15.00
12.50
15.00
12.50
10.00
25.00
15.00
12.50
20.00
40.00
17.50
35.00
15.00
30.00
175.00
600.00
385.00
650.00
650.00
150.00
550.00
350.00
600.00
600.00
120.00
475.00
275.00
550.00
550.00
135.00
420.00
650.00
150.00
350.00
600.00
120.00
325.00
550.00
250.00
650.00
500.00
200.00
600.00
450.00
165.00
550.00
420.00
120.00
150.00
100.00
75.00
Pouring/Concreting
7 of 616
4.80
4.80
###
27.50
Excavation
a. From 0.01-0.10
b. From 0.11-0.20
K.
kg.
kg.
kg.
kg.
5.50
5.50
5.15
38.50
LABOR WORKS
a. Ordinary Soil
* Bulk
* Manual
b. Adobe
c. Dewatering
B.
C.
D.
E.
F.
G.
H.
I.
J.
kg.
kg.
kg.
sq.m.
L.
M.
N.
O.
P.
Q.
VI.
A.
* Using Buggy
cu.m.
300.00
* Direct Pouring
* Volume < 200.00 cu.m.
cu.m.
* Volume = 200-300 ; 300-400 ; 400 & above
cu.m. cu.m.
100.00
iii. Job mix
cu.m.
600.00
g. Dentils (All levels)
i. Pumpcrete
cu.m.
200.00
ii. Job mix
cu.m.
750.00
h. Slab on Fill/Pavement
i. Job mix
cu.m.
385.00
ii. Ready mix
* Using Buggy
cu.m.
300.00
* Direct Pouring
cu.m.
135.00
iii. Pumpcrete
cu.m.
175.00
i. Curbs & Gutter
i. Ready mix
cu.m.
360.00
ii. Job mix
cu.m.
600.00
j. Lintel Beams, Stiff. Columns & counters
cu.m.
750.00
k. Stair
i. Pumpcrete
cu.m.
175.00
ii. Job mix
cu.m.
600.00
l. Cistern, Septic Tank, etc.
i. Pumpcrete
cu.m.
165.00
ii. Job mix
cu.m.
1,100.00
m. Floor Slabs only
i. Placing of Concrete
cu.m.
ii. Straight to Finish
sq.m.
pp
650.00
Cutting of Prestress Concrete Piles
sq.m.
175.00
Trimming of Mechanically Excavated Soil
lm.
75.00
Cutting of Concrete using Concrete Saw
pp
400.00
Cutting of Concrete Sheet Piles
pp
2,500.00
Cutting of Bored Piles
sq.m.
65.00
Steel Deck Installation
B.
C.
D.
E.
VII.
DEMOLITION / DISMANTLING
8 of 616
200.00
100.00
65.00
550.00
60.00
450.00
165.00
650.00
150.00
600.00
350.00
300.00
275.00
110.00
150.00
250.00
100.00
100.00
350.00
550.00
700.00
275.00
500.00
650.00
150.00
550.00
110.00
500.00
150.00
850.00
120.00
650.00
50.00
85.00
500.00
150.00
65.00
350.00
###
50.00
400.00
125.00
60.00
250.00
###
40.00
7.50
60.00
7.50
20.00
150.00
275.00
85.00
6.50
55.00
6.00
17.50
145.00
250.00
65.00
TINSMITHRY WORKS
A.
B.
250.00
Concrete
CHB Walls
lft.
sq.m.
lft.
lft.
pc.
pc.
sq.m.
10.00
65.00
8.50
25.00
175.00
300.00
100.00
cu.m.
sq.m.
2,750.00
###
###
###
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.
S.
T.
U.
V.
W.
X.
9 of 616
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
cu.m.
cu.m.
lm.
lot
lot
55.00
40.00
50.00
60.00
50.00
55.00
35.00
60.00
30.00
30.00
20.00
75.00
35.00
90.00
30.00
40.00
35.00
60.00
-
###
50.00
35.00
40.00
50.00
40.00
50.00
30.00
50.00
20.00
20.00
15.00
65.00
30.00
65.00
20.00
35.00
30.00
50.00
###
40.00
30.00
35.00
40.00
30.00
40.00
20.00
40.00
15.00
17.50
12.50
50.00
20.00
50.00
15.00
30.00
20.00
40.00
-
PRICE LIST
SIZE
(mm)
MASS
(kg/lm)
6.0
7.5
LENGTH ( M )
9.0
10.5
ASTM / GRADE 33
12.0
%age
10
0.616
73.92
92.4
110.88
129.36
147.84
12
0.888
106.56
133.2
159.84
186.48
213.12
16
1.578
189.36
236.7
284.04
331.38
378.72
20
2.466
295.92
369.9
443.88
517.86
591.84
25
3.853
462.36
577.95
693.54
809.13
924.72
ASTM / GRADE 40
%age
10
0.616
81.31
101.64
121.97
142.3
162.62
12
0.888
117.22
146.52
175.82
205.13
234.43
16
1.578
206.4
258
309.6
361.2
412.8
20
2.466
322.55
403.19
483.83
564.47
645.11
25
3.853
503.97
629.97
755.96
881.95
1007.94
28
4.834
632.29
790.36
948.43
1106.5
1264.57
32
6.313
833.32
1041.65
1249.97
1458.3
1666.83
36
7.990
1054.68
1318.35
1582.02
1845.69
2109.36
ASTM / GRADE 60
%age
10
0.616
83.9
104.87
125.85
146.82
167.8
12
0.888
120.95
151.18
181.42
211.65
241.89
16
1.578
213.03
266.29
319.55
372.8
426.06
20
2.466
332.91
416.14
499.37
582.59
665.82
25
3.853
520.16
650.19
780.23
910.27
1040.31
28
4.834
652.59
815.74
978.89
1142.03
1305.18
32
6.313
859.83
1074.79
1289.75
1504.7
1719.66
36
7.990
1088.24
1360.3
1632.36
1904.42
2176.48
40
9.865
1373.21
1716.51
2059.81
2403.11
2746.42
50
15.413
2191.73
2739.66
3287.59
3835.53
4383.46
%age
ASTM Grade 40
Base Price
1.61
%age
1.58
ASTM Grade 60
Base Price
Steel Asia, Pag-asa
%age
22
22.6
1.61
ASTM Grade 40
Base Price
%age
ASTM Grade 60
Base Price
21.9
1.58
22.6
Kg / Pc.
6.0
Unit Cost
mftg
kg. / m
1.5
3.696
20.00
30.00
5.328
20.00
30.00
9.468
20.00
30.00
14.796
20.00
30.00
23.118
20.00
30.00
3.696
22.00
28.60
5.328
22.00
28.60
119.75
33.00
1.3
9.468
21.80
28.34
14.796
21.80
28.34
23.118
21.80
28.34
29.004
21.80
28.34
37.878
22.00
28.60
47.94
22.00
28.60
3.696
22.70
29.06
5.328
22.70
29.06
9.468
22.50
28.80
14.796
22.50
28.80
23.118
22.50
28.80
29.004
22.50
28.80
37.878
22.70
29.06
47.94
22.70
29.06
59.19
23.20
29.70
92.478
23.70
30.34
1.28
35.42
35.708
296.72
31.34
106.92
35.259
35.708
Unit Cos
Unit
I. Rentals
1. Metal Forms
a. Metal Panels
i.
750 x 1800mm
ii.
750 x 1200mm
iii.
750 x 900mm
iv.
650 x 1800mm
v.
650 x 1500mm
vi.
650 x 1200mm
vii. 600 x 1800mm
viii. 600 x 1500mm
ix.
600 x 1200mm
x.
600 x 900mm
xi.
600 x 600mm
xii. 550 x 1800mm
xiii. 550 x 1500mm
xiv. 550 x 1200mm
xv.
550 x 900mm
xvi. 500 x 1800mm
xvii 500 x 1500mm
xviii. 450 x 1800mm
xix. 450 x 1500mm
xx.
450 x 900mm
xxi 400 x 1800mm
xxii 400 x 1500mm
xxii 400 x 1200mm
xxiv. 400 x 900mm
xxv. 400 x 600mm
xxvi. 350 x 1800mm
xxvii. 350 x 1500mm
350 x 1200mm
300 x 1800mm
300 x 1500mm
300 x 900mm
300 x 600mm
250 x 1800mm
250 x 1500mm
250 x 900mm
200 x 1800mm
200 x 1200mm
150 x 1800mm
150 x 1500mm
150 x 1200mm
150 x 600mm
100 x 1500mm
1.80 Corner Section
1.50 Corner Section
1.20 Corner Section
0.90 Corner Section
0.60 Corner Section
1.80 Exterior Angle
Supplier A
Rate/Day
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 4.00
PHP 3.00
PHP 2.33
PHP 3.50
PHP 3.00
PHP 2.67
PHP 3.33
PHP 2.83
PHP 2.50
PHP 1.83
PHP 1.58
PHP 3.08
PHP 2.67
PHP 2.33
PHP 1.67
PHP 2.83
PHP 2.50
PHP 2.58
PHP 2.33
PHP 1.42
PHP 2.33
PHP 2.17
PHP 1.83
PHP 1.33
PHP 1.25
PHP 2.17
PHP 2.00
PHP 1.67
PHP 2.00
PHP 1.83
PHP 1.17
PHP 1.00
PHP 1.83
PHP 1.67
PHP 1.08
PHP 1.67
PHP 1.17
PHP 1.50
PHP 1.33
PHP 1.00
PHP 0.67
PHP 1.17
PHP 1.67
PHP 1.67
PHP 1.17
PHP 0.92
PHP 0.67
PHP 0.50
Supplier name
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
Supplier B
Rate/Day
13
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 0.42
PHP 0.33
PHP 0.25
PHP 0.17
PHP 0.12
PHP 0.30
PHP 0.30
PHP 0.25
PHP 0.20
PHP 1.42
PHP 0.05
PHP 0.03
PHP 0.02
PHP 0.03
PHP 0.03
PHP 3.50
PHP 3.33
PHP 0.90
PHP 2.50
PHP 0.54
PHP 3.08
PHP 0.83
PHP 1.67
PHP 1.50
PHP 2.83
PHP 2.50
PHP 2.17
PHP 1.50
PHP 2.58
PHP 2.33
PHP 2.00
PHP 1.42
PHP 3.10
PHP 2.33
PHP 2.17
PHP 1.83
PHP 1.83
PHP 1.25
PHP 2.17
PHP 2.00
PHP 1.67
PHP 1.25
PHP 1.17
PHP 2.33
PHP 2.00
PHP 1.83
PHP 1.50
PHP 1.17
PHP 1.00
PHP 2.17
PHP 1.83
PHP 1.67
PHP 1.33
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
c
o
r
r
e
c
t
e
d
u
n
i
t
c
o
s
250 x 900mm
200 x 1800mm
200 x 1500mm
200 x 1200mm
200 x 900mm
200 x 600mm
150 x 1800mm
150 x 1500mm
150 x 1200mm
150 x 900mm
100 x 1800mm
100 x 1500mm
100 x 1200mm
100 x 900mm
1.80 Outer Angle
1.50 Outer Angle
1.20 Outer Angle
0.90 Outer Angle
0.60 Outer Angle
1.80 Inside Corner
1.50 Inside Corner
0.90 Inside Corner
1.50 Filler Angle
1.20 Filler Angle
0.60 Filler Angle
1.80 Inside Corner for Slab
0.90 Inside Corner for Slab
0.60 Inside Corner for Slab
d. Gang Form
D-Beam x 3.30m (2.5mm thk)
D-Beam x 2.40m (2.5mm thk)
D-Beam x 1.40m (2.5mm thk)
D-Beam x 1.20m (2.5mm thk)
D-Beam x 0.60m (2.5mm thk)
Splice Plate
Cast Plate
Wing Nut 21mm
Wing Nut 17mm
Wing Nut 12mm
Tie Rod - 17mm x 300mm
e. Other Accessories
Wedge Pin
C-Purlins
2. Scaffoldings
a. H-Frames
i.
1.70 x 1.20m H-Frame (G.I.)
ii.
1.20 x 1.20m H-Frame (G.I.)
iii.
0.90 x 1.20m H-Frame (G.I.)
iv.
1.70 x 1.20m H-Frame (B.I.)
v.
1.20 x 1.20m H-Frame (B.I.)
vi.
0.90 x 1.20m H-Frame (B.I.)
vii. 1.70 x 0.90m H-Frame (G.I.)
viii. 1.20 x 0.90m H-Frame (B.I.)
ix.
0.90 x 0.90m H-Frame (B.I.)
b. Other Accessories
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 1.08
PHP 1.67
PHP 0.30
PHP 1.17
PHP 1.00
PHP 0.83
PHP 1.50
PHP 0.23
PHP 1.00
PHP 0.14
PHP 0.18
PHP 0.15
PHP 0.12
PHP 0.09
PHP 0.50
PHP 0.42
PHP 0.33
PHP 0.25
PHP 0.17
PHP 1.67
PHP 1.42
PHP 0.92
PHP 0.33
PHP 0.20
PHP 0.15
PHP 1.67
PHP 0.25
PHP 0.16
PHP 1.68
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 1.70
PHP 0.92
PHP 0.83
PHP 1.70
PHP 0.92
PHP 0.83
PHP 1.00
PHP 0.75
PHP 0.67
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
PHP 2.99
PHP 2.18
PHP 1.27
PHP 1.09
PHP 0.54
PHP 0.18
PHP 0.18
PHP 0.11
PHP 0.11
PHP 0.11
PHP 0.50
u
n
i
t
c
o
s
t
i.
2.50m Cross Brace
ii.
2.25m Cross Brace
iii.
2.00m Cross Brace
iv.
1.80m Cross Brace
v.
1.70m Cross Brace
vi.
1.50m Cross Brace
vii. Straight Props (outer pipe)
viii. Straight Props (inner pipe)
ix.
Fixed U-head 2"
x.
Fixed U-head 4"
xi.
Adjustable U-head 2"
xii. Adjustable U-head 3"
xii. Adjustable U-head 4"
xiv. Adjustable Base Jack
xv.
Joint Pin
c. Waller Pipe & Accessories
1" x 6.00m GI Pipe
i.
1" x 5.50m GI Pipe
ii.
1" x 5.00m GI Pipe
iii.
1" x 4.50m GI Pipe
iv.
1" x 4.00m GI Pipe
v.
1" x 3.00m GI Pipe
vi.
vii. 1" x 2.50m GI Pipe
viii. 1" x 2.40m GI Pipe
1" x 2.00m GI Pipe
ix.
1" x 1.85m GI Pipe
x.
1" x 1.60m GI Pipe
xi.
xii. 1" x 1.50m GI Pipe
xiii. 1" x 1.00m GI Pipe
xiv. 1" x 0.80m GI Pipe
1" x 0.70m GI Pipe
xv.
xvi. 1" x 0.50m GI Pipe
xvii 1" x 0.40m GI Pipe
xviii. Swivel Clamp
xix. Fixed Clamp
1" x 6.00m Double Pipe
xx.
xxi 1" x 5.00m Double Pipe
xxii 1" x 4.00m Double Pipe
xxii 1" x 3.00m Double Pipe
xxiv. 1" x 2.50m Double Pipe
xxv. 1" x 2.00m Double Pipe
xxvi. 1" x 1.50m Double Pipe
xxvii. 1" x 1.00m Double Pipe
d. Steel Headers
i.
2" x 4" BI Steel Headers x 3.00m
ii.
2" x 4" BI Steel Headers x 2.44m
iii.
2" x 4" BI Steel Headers x 2.00m
iv.
2" x 4" BI Steel Headers x 1.80m
v.
2" x 4" BI Steel Headers x 1.50m
vi.
2" x 4" BI Steel Headers x 1.20m
vii. 2" x 4" I-beam Steel Headers x 3.00m
viii. 2" x 4" I-beam Steel Headers x 1.50m
d. Hanging Steel Scaffolds
i.
Gondola
ii.
Gondola Bracket 0.40
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.67
PHP 0.67
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.07
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 2.33
PHP 2.17
PHP 2.00
PHP 1.83
PHP 1.67
PHP 1.33
PHP 1.17
PHP 1.09
PHP 1.00
PHP 0.93
PHP 0.90
PHP 0.83
PHP 0.83
PHP 0.81
PHP 0.80
PHP 0.78
PHP 0.77
PHP 0.29
PHP 0.29
PHP 4.66
PHP 4.00
PHP 3.34
PHP 2.66
PHP 2.34
PHP 2.00
PHP 1.66
PHP 1.34
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
piece
piece
piece
piece
piece
piece
piece
piece
PHP 1.17
PHP 1.00
PHP 1.00
PHP 0.83
PHP 0.67
PHP 0.50
PHP 4.59
PHP 4.20
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
piece
piece
PHP 3.17
PHP 5.67
FEMD
FEMD
iii.
Gondola Bracket 0.55
iv.
Steel Platform (CP) 0.40 x 2.00m
v.
Steel Platform (EW) 0.40 x2.00m
vi.
Steel Ladder (Expanded Metal)
vii. Double C-Purlins Flatform x 3.00m
d. Others
i.
Caster Wheel (Swivel)
piece
piece
piece
piece
piece
piece
piece
PHP 4.79
PHP 1.67
PHP 5.79
PHP 21.58
PHP 2.94
PHP 1.95
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
LABOR RATES
Unit Cost
Supplier B
Supplier name
Supplier C
Rate/Day
14
Applied Rate
Supplier name
14.00
3.00
2.33
3.50
3.00
2.67
3.33
2.83
2.50
1.83
1.58
3.08
2.67
2.33
1.67
2.83
2.50
2.58
2.33
1.42
2.33
2.17
1.83
1.33
1.25
2.17
2.00
1.67
2.00
1.83
1.17
1.00
1.83
1.67
1.08
1.67
1.17
1.50
1.33
1.00
0.67
1.17
1.67
1.67
1.17
0.92
0.67
0.50
Item
I. Indirect Manpower
1. Accountant
2. Cadet Engineer
3. Carpenter
4. Cost Engineer
5. Driver
6. Electrician
7. Field Engineer
8. Foreman
9. Glass Installer
10. Guard
11. Heavy Equipment Operator
12. Laborer
13. Leadman
14. Mason
15. Mechanic
16. Messenger
17. Mixer Operator
18. Painter
19. Plumber
20. Project In-charge
21. Screeder Operator
22. Steelman
23. Surveying Aide
24. Surveyor
25. Tile Setter
26. Timekeeper
27. Utility
28. Utility
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32.
33.
1
Provincia
Minimum
PHP 400.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
0.42
0.33
0.25
0.17
0.12
0.30
0.30
0.25
0.20
1.42
0.05
0.03
0.02
0.03
0.03
3.50
3.33
0.90
2.50
0.54
3.08
0.83
1.67
1.50
2.83
2.50
2.17
1.50
2.58
2.33
2.00
1.42
3.10
2.33
2.17
1.83
1.83
1.25
2.17
2.00
1.67
1.25
1.17
2.33
2.00
1.83
1.50
1.17
1.00
2.17
1.83
1.67
1.33
1.08
1.67
0.30
1.17
1.00
0.83
1.50
0.23
1.00
0.14
0.18
0.15
0.12
0.09
0.50
0.42
0.33
0.25
0.17
1.67
1.42
0.92
0.33
0.20
0.15
1.67
0.25
2.99
2.18
1.27
1.09
0.54
0.18
0.18
0.11
0.11
0.11
0.50
0.16
1.68
1.70
0.92
0.83
1.70
0.92
0.83
1.00
0.75
0.67
0.33
0.33
0.33
0.33
0.33
0.33
0.67
0.67
0.50
0.50
0.50
0.50
0.50
0.50
0.07
2.33
2.17
2.00
1.83
1.67
1.33
1.17
1.09
1.00
0.93
0.90
0.83
0.83
0.81
0.80
0.78
0.77
0.29
0.29
4.66
4.00
3.34
2.66
2.34
2.00
1.66
1.34
1.17
1.00
1.00
0.83
0.67
0.50
4.59
4.20
3.17
5.67
4.79
1.67
5.79
21.58
2.94
1.95
1
Provincial Rate
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
2
Manila Rate
Minimum
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 700.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
Applied Rate
600
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Location of Project:
5
4
3
2
1
AS
OF
A P R I L
SCOPE OF WORKS
I.
II.
CARPENTRY WORKS
A. Formworks
1. Using Lumber (incl.stripping,formoil application & nail ext.)
a. Columns/Pedestal
i.Spiral
ii.Tied
b. Footing Tie Beams & Pile Caps
c. Floor Beams
d. Floor Slab
e. Floor Beams (Above 4.00m high)
f. Floor Slab (Above 4.00m high)
g. Roof Beams
h. Gutter w/ parapet
i. Roof Deck (if coverage is not the same as floor slabs below)
j. Shearwalls
k. Stair & Bleacher
l. Dentils
m. Parapet
n. Waffles
o. Stair on Fill
p. Lintel Beams & Stiff. Columns
q. Pavement
r. Slab on Fill
s. When forms used are scrap wood & lumber
2. Using Steel Forms
a. Columns/Pedestal
i.Spiral
ii.Tied
b. Footing Tie Beams & Pile Caps
c. Floor Beams
d. Floor Slab
2001
UNITS
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
lm.
sq.m.
lm.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
SMALL
SCALE
18.50
MEDIUM
SCALE
12.50
220.00
190.00
195.00
185.00
155.00
140.00
190.00
175.00
185.00
165.00
200.00
190.00
195.00
185.00
200.00
190.00
205.00
200.00
190.00
175.00
195.00
180.00
220.00
210.00
205.00
200.00
195.00
185.00
205.00
200.00
85.00
80.00
165.00
160.00
55.00
45.00
45.00
40.00
plus 15.00 plus 15.00
Installation
Small Sc. Big Scale
135.00
130.00
140.00
125.00
125.00
120.00
135.00
125.00
130.00
120.00
SCOPE OF WORKS
e. Floor Beams (Above 4.00m high)
f. Floor Slab (Above 4.00m high)
g. Roof Beams
h. Gutter w/ parapet
i. Roof Deck (if coverage is not the same as floor slabs below)
j. Shearwalls
3. H-Frames Installation/Dismantling only (Steel Scaffoldings)
a. Steel Scaffoldings
i. One Layer
ii. Two Layers
iii. Three Layers
iv. Four Layers
v. Five Layers
vi. Six Layers
vii. Seven Layers
viii. Eight Layers
b. If H-Frame is to rest on soil
i. For Compacted Soil
ii. For Muddy/Loose Soil
c. Supporting Steel Deck
4. Retouching, Grinding & Preparation (Ready to accept Paints)
a. Columns
b. Beams
c. Slabs
d. Walls
e. Parapets
B. Door Jambs Installation
a. On Double Walls
b. On Concrete Walls
C. Window Jambs Installation
a. On Double Walls
b. On Concrete Walls
D. Steel Window Installation
E. Flush Door Installation
F. Panel Door Installation
G. Bar Door Installation
H. Steel Door Installation
Single Leaf
Double Leaf
I. Steel Louver Installation
J. Wooden Roof Framing
a. Fabrication & Installation
K. Double Wall Partitions
a. 1/4"thk.Ply.on 2"x3"studs(V-cut & Open Joint)
b. Narra Ply.on 2"x3"studs(V-cut & Open Joint)
c. Narra Ply.on 2"x3"studs(Open Joint @ 0.30)
d. Other Kind of D/W Partition
UNITS
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
SMALL
SCALE
150.00
145.00
140.00
145.00
135.00
130.00
MEDIUM
SCALE
140.00
135.00
130.00
135.00
125.00
125.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
14.00
15.00
18.50
22.50
25.00
27.50
30.00
35.00
7.00
10.50
14.00
15.00
20.00
22.50
25.00
30.00
sq.m.
sq.m.
sq.m.
Additional of P 5.00/sq.m.
Additional of P15.00/sq.m.
70.00
50.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
37.50
45.00
50.00
37.50
50.00
27.50
37.50
47.50
35.00
40.00
lm.
lm.
27.50
32.50
22.50
30.00
sq.m.
sq.m.
sq.m.
set
set
set
80.00
85.00
135.00
220.00
290.00
175.00
65.00
80.00
75.00
200.00
275.00
150.00
set
set
sq.m.
350.00
485.00
140.00
350.00
450.00
125.00
bft.
12.50
12.50
sq.m.
sq.m.
sq.m.
145.00
140.00
145.00
140.00
190.00
175.00
(By Negotiation)
L.
M.
N.
O.
P.
Q.
R.
III.
SCOPE OF WORKS
e. 1/4"thk.Marine Plywood Panelling w/o groove
f. 1/4"thk.Narra Plywood Panelling w/ groove
Baseboard
a. Kd. Tanguile
b. Narra
c. Vinyl
Ceiling
a. 1/4" Plywood Ceiling (Ordinary)
i. w/ ceiling truss
ii. w/o ceiling truss
b. T&G, S-cut & V-cut
c. Installation of Accoustic board
d. Ceiling Board only
i. w/ V-cut
ii.Open joint
e. Covelights (Fabrication & Installation)
i.On Ordinary Ceiling
ii.On Wood Moulding(Fiberglass Ceiling)
iii.Alum.T-runner Installation
iiii. Diffuser Installation
f. Other Ceiling
i. Ord.Plywood ceiling @ Eaves
ii. Wood Slats w/ Insect Screen (W=0.30m)
Installation of wooden stair handrail (narra)
Cabinets & Shelves
Quarter C Moulding
2" x 3" Wood Mouldings
Others
Hardwares
Door Lockset
Door Closer
Flush & Head Bolts
Panic Exit Device
Push Plates
Door Stops
SMALL
SCALE
120.00
140.00
MEDIUM
SCALE
110.00
135.00
lm.
lm.
lm.
21.50
25.00
10.00
18.50
22.50
8.00
sq.m.
sq.m.
sq.m.
sq.m.
160.00
140.00
190.00
85.00
150.00
135.00
180.00
80.00
sq.m.
sq.m.
80.00
70.00
75.00
65.00
set
set
lm.
set
130.00
140.00
21.50
13.50
120.00
135.00
18.50
10.50
UNITS
sq.m.
sq.m.
sq.m.
160.00
150.00
lm.
90.00
85.00
lm.
100.00
95.00
by negotiation (30 % of materials)
lm.
16.50
14.50
lm.
32.50
28.50
set
set
set
set
set
set
150.00
125.00
65.00
350.00
65.00
65.00
sq.m.
18.50
16.50
sq.m.
sq.m.
sq.m.
140.00
130.00
120.00
135.00
120.00
115.00
sq.m.
sq.m.
135.00
130.00
130.00
125.00
sq.m.
sq.m.
145.00
140.00
135.00
130.00
F.
G.
H.
I.
SCOPE OF WORKS
a. by area (interior CHB walls)
b. by area (ext. CHB walls)needs scaffolding
c. by area (conc.walls & parapet)
i. Ordinary Concrete Walls (Interior Walls)
ii. Exterior Concrete & CHB Walls & Parapets (w/ scaffoldings)
1. Ground to Fourth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
2. Fourth to Seventh Floor
Up to 2-1/2" thk.
For every add'l. 1" thk.
3. Seventh to Tenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
4. Tenth to Fourteenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
5. Above Fourteenth Floor
Up to 2-1/2" thk.
For every add'l. 1-1/2" thk.
d. by area (irregular CHB walls)
e. Overhead
f. by lm.(vertical & horizontal)
g. by lm.(overhead)
h. Spiral columns
i. Beam plastering (sides)
j. Beam plastering (bottom)
k. Tool Joint Finish
l. Kustura Finish
m. Exterior Grooves
n. Plastering of Louver Blocks
Boracay Finish (incl.liston,& other acc.)
a. By area
i.Flooring
ii.Walls
* w/scaffolding
* w/o scaffolding
b. by lm
Pebble Washout Finish(incl.liston & other acc.)
a. by area
i.Flooring
ii.Walls
b. by lm
Stair Nosing Installation (incl. preparation)
a. Brass, Angular & Checkered Plate
b. Carborandum Strip
c. Vinyl Stair Nosing
Topping
a. Straight to finish
b. Plain Cement finish
UNITS
sq.m.
sq.m.
SMALL
SCALE
130.00
160.00
MEDIUM
SCALE
125.00
145.00
sq.m.
135.00
130.00
sq.m.
sq.m.
155.00
22.50
sq.m.
sq.m.
180.00
35.00
sq.m.
sq.m.
210.00
45.00
sq.m.
sq.m.
220.00
55.00
sq.m.
sq.m.
sq.m.
sq.m.
lm.
lm.
lm.
lm.
lm.
sq.m.
sq.m.
lm.
sq.m.
150.00
155.00
75.00
95.00
155.00
110.00
130.00
125.00
115.00
70.00
260.00
240.00
65.00
140.00
145.00
65.00
85.00
140.00
100.00
120.00
115.00
85.00
45.00
200.00
sq.m.
195.00
185.00
sq.m.
sq.m.
lm.
250.00
220.00
160.00
230.00
210.00
140.00
sq.m.
sq.m.
lm.
190.00
220.00
130.00
175.00
215.00
110.00
lm.
lm.
lft.
80.00
105.00
75.00
90.00
8.00
sq.m.
sq.m.
60.00
115.00
55.00
110.00
J.
K.
L.
M.
N.
O.
P.
Q.
SCOPE OF WORKS
Stair Tread Topping
c. Red cement w/ V-cut
d. Deck Topping (including Cant,etc.)
e. Ramp Topping w/ Groove
Tileworks
a. Glazed Tiles incl. rough plaster
i. 4-1/4"x4-1/4" Glazed Tiles
ii. 4"x8"
-doiii. Others
b. Vit.floor tiles incl. topping
i. 4-1/4"x4-1/4" Glazed Tiles
ii. 4"x8"
-doiii. Others
c. Mosaic floor tiles incl. topping
d. Tile fittings
Brickworks
a. 1"x2"x8"Red bricks
b. 4"x8"Clay tiles
c. 12"x12"Red cement tiles
d. 8"x8"Clay tiles
e. 6"x6"x12"Louver blocks
f. 4"x12"x12"Decorative blocks
g. Mactan stone
h. Adobe blocks
i. Ashlar stone
j. Urra Tiles
* Ordinary Layout
* Extra-ordinary Layout (w/ many cuts)
Sandblasting
Corduroy finish
Marble Finish / Granite Finish
a. 4"x8"Marble tiles
b. Marble @ Walls
c. Marble @ Floors
d. Marble @ Counters
e. Opening for Lavatory
f. Rounding of Edges
g. Faucet Hole
h. Granite @ Walls including Anchors (Dry Anchors)
i. Granite @ Floors
j. Granolithic Flooring
Retouching
a. by area
i. Walls
ii.Exposed slab
b. by lm.(corners only)
c. Curbs & Gutter
Rip-rapping
Synthetic Finish
a. by area
UNITS
lm.
sq.m.
sq.m.
sq.m.
SMALL
SCALE
95.00
120.00
200.00
255.00
MEDIUM
SCALE
80.00
115.00
190.00
235.00
sq.m.
sq.m.
sq.m.
230.00
205.00
195.00
220.00
200.00
185.00
sq.m.
sq.m.
sq.m.
sq.m.
lm.
205.00
185.00
165.00
165.00
65.00
190.00
180.00
160.00
160.00
60.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
210.00
205.00
190.00
180.00
170.00
150.00
205.00
125.00
205.00
200.00
185.00
165.00
170.00
150.00
140.00
185.00
115.00
185.00
sq.m.
sq.m.
sq.m.
sq.m.
230.00
360.00
60.00
385.00
210.00
320.00
55.00
375.00
sq.m.
sq.m.
sq.m.
lm.
set
lm.
set
sq.m.
sq.m.
sq.m.
330.00
320.00
320.00
300.00
525.00
215.00
180.00
300.00
300.00
280.00
260.00
450.00
180.00
150.00
2,000.00
280.00
280.00
sq.m.
sq.m.
lm.
lm.
cu.m.
30.00
60.00
50.00
50.00
400.00
25.00
50.00
40.00
45.00
375.00
SCOPE OF WORKS
i. w/ scaffolding
ii. w/o scaffolding
b. by lm
R. Keyhole Pattern Bricks
S. 4"x8"Tiles w/ Pebble Washout Pattern
T. 200 x 200 Glass Blocks
IV.
A.
B.
C.
D.
E.
F.
G.
H.
I.
J.
K.
L.
M.
N.
O.
P.
Q.
R.
V.
UNITS
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
SMALL
SCALE
310.00
290.00
185.00
210.00
310.00
375.00
MEDIUM
SCALE
285.00
250.00
165.00
180.00
275.00
325.00
A. Excavation
a. Ordinary Soil
* Bulk
* Manual
b. Adobe
c. Dewatering
B. Backfilling
a. Manual
b. by Equipment
C. Levelling
D. Excavation of Ftg. Tie Beam & Wall Footings
E. Compaction
F. Basecoarse
a. Manual
b. by Equipment
G. Soil Poisoning
H. Polyethelene sheets
cu.m.
cu.m.
cu.m.
175.00
140.00
295.00
265.00
480.00
350.00
(By Administration)
cu.m.
cu.m.
sq.m.
cu.m.
sq.m.
120.00
85.00
37.50
325.00
37.50
110.00
65.00
30.00
285.00
30.00
cu.m.
cu.m.
sq.m.
sq.m.
120.00
85.00
13.50
10.75
110.00
65.00
10.00
7.50
SCOPE OF WORKS
I. PVC Waterstop
J. Chipping
a. From 0.01-0.10
b. From 0.11-0.20
K. Pouring/Concreting
a. Floor beams, Slab & columns
i. Pumpcrete
ii. Jobmix
iii. Ready mix
b. Columns-(Job mix)
c. Wall footings (Job mix)
d. Shearwall / Retaining Walls
i. Pumpcrete
ii. Ready Mix
iii. Job mix
e. Roof beams, Gutter & Parapet
i. Pumpcrete
ii. Job mix
iii. Ready mix
f. Footings, Pedestals & Tie Beams
i. Pumpcrete
* Volume < 200.00 cu.m.
* Volume = 200-300 ; 300-400 ; 400 & above cu.m.
ii. Ready mix
* Using Buggy
* Direct Pouring
* Volume < 200.00 cu.m.
* Volume = 200-300 ; 300-400 ; 400 & above cu.m.
iii. Job mix
g. Dentils (All levels)
i. Pumpcrete
ii. Job mix
h. Slab on Fill/Pavement
i. Job mix
ii. Ready mix
* Using Buggy
* Direct Pouring
iii. Pumpcrete
i. Curbs & Gutter
i. Ready mix
ii. Job mix
j. Lintel Beams, Stiff. Columns & counters
k. Stair
i. Pumpcrete
ii. Job mix
l. Cistern, Septic Tank, etc.
i. Pumpcrete
ii. Job mix
L. Cutting of Prestress Concrete Piles
M. Trimming of Mechanically Excavated Soil
SMALL
SCALE
16.00
MEDIUM
SCALE
10.00
lm.
lm.
14.50
30.00
12.50
25.00
cu.m.
cu.m.
cu.m.
cu.m.
cu.m.
150.00
650.00
450.00
800.00
750.00
135.00
600.00
375.00
700.00
650.00
cu.m.
cu.m.
cu.m.
150.00
500.00
800.00
135.00
435.00
700.00
cu.m.
cu.m.
cu.m.
300.00
800.00
650.00
225.00
700.00
550.00
cu.m.
cu.m.
115.00
130.00
85.00
cu.m.
350.00
275.00
cu.m.
cu.m.
cu.m.
0.00
105.00
700.00
120.00
80.00
600.00
cu.m.
cu.m.
235.00
900.00
200.00
750.00
cu.m.
465.00
375.00
cu.m.
cu.m.
cu.m.
350.00
150.00
145.00
300.00
130.00
125.00
cu.m.
cu.m.
cu.m.
425.00
700.00
900.00
375.00
620.00
800.00
cu.m.
cu.m.
160.00
650.00
135.00
600.00
cu.m.
cu.m.
pp
185.00
1,350.00
500.00
150.00
1,000.00
350.00
UNITS
lm.
SCOPE OF WORKS
a. Manual
b. by Equipment
N. Cutting of Concrete using Concrete Saw
O. Cutting of Concrete Sheet Piles
P. Cutting of Bored Piles
UNITS
sq.m.
sq.m.
lm.
pp
pp
SMALL
SCALE
120.00
100.00
55.00
300.00
1,800.00
MEDIUM
SCALE
110.00
85.00
45.00
250.00
1,500.00
lft.
lft.
lft.
pc.
pc.
sq.m.
6.50
6.00
18.50
135.00
235.00
75.00
5.50
5.00
15.00
120.00
200.00
65.00
cu.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
cu.m.
cu.m.
lm.
lot
lot
1,750.00
40.00
30.00
35.00
45.00
35.00
40.00
25.00
45.00
20.00
20.00
15.00
60.00
25.00
65.00
20.00
30.00
25.00
45.00
1,000.00
35.00
25.00
30.00
35.00
30.00
35.00
20.00
35.00
15.00
15.00
10.00
45.00
20.00
50.00
15.00
25.00
20.00
35.00
1,200.00
350.00
40.00
Concrete
CHB Walls
Corr. G.I. Sheets
Asbestos Roofing
Steel Roof Framing
Wooden Roof Framing
Wooden Floor Framing
Steel Windows
Doors
Double Wall Partition
Ceiling
Gutter & Flashing
Chipping of Floor topping
Cabinets,counters & shelves
Chipping of tiles
Scraping of vinyl tiles
Wood parquet
Chipping of Synthetic Finish
Alum. Framed Glass
Blasting of Footings (by Dynamite)
Blasting of Walls (by Dynamite)
Cutting of Concrete
Electrical
Plumbing
NOTES :
All tools,equipments,scaffolding installation,accessories,hauling & other miscellaneous
shall be shouldered by the sub-contractors.
Hauling costs are included in above unit costs up to fourth floor if it will be done
starting to ground floor,however if works started from third or fourth floor,
SMALL
MEDIUM
SCOPE OF WORKS
UNITS
SCALE
SCALE
additional hauling cost will be given to the subcontractors.
For High Rise Building, Hauling shall be done by Tower Crane but with the help of Subcon labor.
Add 10% VAT to all labor unit costs only.
Add 5%-10% to all labor unit costs if work is outside Metro-Manila. (Optional)
Add 10% to all Materials supplied by the Sub-contractors.
All unit cost includes deliveries within Metro-Manila only.
(Painting) All lineal meters shall be computed once,(ex.Z-bar & sq.bar=total length=lm)
New unit costs are based on a minimum salary of P250.00/day
New unit costs are based if material is within the periphery of the building,if not
make an additional hauling costs to be computed by PE.
All items not included in above items of work shall be the responsibility of the Project
Engineer to compute and award to the contractors.
Formworks Unit Costs are based on A-Frames & Eco-forms to be used,when scaffold use is
lumber add an additional of P10.00 per sq.m. of beams,slabs,Shearwall or RC Walls.
All unit costs are based on the standard construction procedures,any actual works that
deviates on standard shall be the responsibility of the PE concerned.
Differentiating Small to Medium and Large Scale construction shall be the responsibility
of the Project Job Captain involved.
Bar Bender & Bar Cutter are not the obligation of the Company but if provided, repair & maintenance
shall be shouldered by subcon.
C O N S U MAB LE S :
^^^^^^^^^^ ^^^^^^^^^^^^^^ ^^^^^^^^^^^^^^^
BF
Nails =
-------------------- = No. of kegs.
40 X 45
Total bft. =
Vt x 192
-------------------- (For Ftb, Lintel beams & Stiff.columns)
2.40
Vt x 192
-------------------- (for all other structures)
1.60
Wt
G.I. Wires #16 =
--------------------------------------65x45
Total bft. =
SCOPE OF WORKS
UNITS
SMALL
SCALE
MEDIUM
SCALE
Wt
--------------------------------------60x45
Wt
--------------------------------------50x45
LARGE
SCALE
7.00
180.00
175.00
125.00
155.00
145.00
180.00
160.00
180.00
185.00
155.00
160.00
200.00
185.00
160.00
195.00
65.00
150.00
40.00
35.00
plus 15.00
Stripping
40.00
40.00
35.00
40.00
40.00
LARGE
SCALE
45.00
45.00
40.00
50.00
40.00
40.00
4.00
7.00
10.00
14.00
15.00
18.50
22.50
25.00
f P 5.00/sq.m.
P15.00/sq.m.
45.00
22.50
35.00
32.50
30.00
35.00
20.00
27.50
50.00
60.00
50.00
150.00
225.00
125.00
300.00
350.00
105.00
10.50
135.00
135.00
160.00
LARGE
SCALE
95.00
125.00
15.00
17.50
5.00
140.00
125.00
160.00
65.00
65.00
55.00
95.00
100.00
17.50
8.50
140.00
75.00
85.00
materials)
10.50
22.50
14.50
130.00
100.00
95.00
125.00
120.00
125.00
120.00
LARGE
SCALE
120.00
135.00
125.00
130.00
135.00
60.00
80.00
125.00
85.00
95.00
80.00
55.00
25.00
175.00
175.00
220.00
205.00
130.00
165.00
210.00
95.00
65.00
70.00
50.00
90.00
LARGE
SCALE
60.00
105.00
180.00
210.00
200.00
185.00
170.00
180.00
160.00
140.00
140.00
55.00
180.00
170.00
130.00
150.00
140.00
130.00
170.00
95.00
175.00
185.00
265.00
50.00
325.00
280.00
260.00
260.00
240.00
350.00
165.00
140.00
20.00
45.00
30.00
40.00
320.00
LARGE
SCALE
250.00
220.00
150.00
150.00
250.00
275.00
2.30
2.45
2.50
2.60
2.50
3.20
4.25
2.75
3.25
4.00
3.00
5.00
3.50
3.50
3.50
4.00
15.00
120.00
230.00
300.00
85.00
45.00
25.00
275.00
25.00
85.00
45.00
7.50
5.00
LARGE
SCALE
7.50
10.00
20.00
125.00
500.00
325.00
650.00
600.00
125.00
375.00
650.00
200.00
650.00
525.00
65.00
220.00
0.00
65.00
550.00
165.00
700.00
325.00
275.00
120.00
120.00
325.00
600.00
700.00
125.00
550.00
135.00
750.00
300.00
LARGE
SCALE
80.00
65.00
40.00
150.00
1,200.00
5.00
4.50
12.50
110.00
165.00
50.00
750.00
25.00
20.00
25.00
30.00
20.00
30.00
15.00
25.00
10.00
12.50
7.50
35.00
15.00
35.00
10.00
20.00
15.00
30.00
LARGE
SCALE
LARGE
SCALE
e Projects)
rojects)
R.C.Ramos Construction
SUB-CONTRACTORS LABOR UNIT COSTS
SCOPE OF WORKS
I.
II.
CARPENTRY WORKS
A. Formworks
1. Using Lumber (incl.stripping,formoil application & nail ext.)
a. Columns/Pedestal
i.Spiral
ii.Tied
b. Footing Tie Beams & Pile Caps
c. Floor Beams
d. Floor Slab
e. Floor Beams (Above 4.00m high)
f. Floor Slab (Above 4.00m high)
g. Roof Beams
h. Gutter w/ parapet
i. Roof Deck (if coverage is not the same as floor slabs below)
j. Shearwalls
k. Stair & Bleacher
l. Dentils
m. Parapet
n. Waffles
o. Stair on Fill
p. Lintel Beams & Stiff. Columns
q. Pavement
r. Slab on Fill
s. When forms used are scrap wood & lumber
2. Using Steel Forms
a. Columns/Pedestal
i.Spiral
ii.Tied
b. Footing Tie Beams & Pile Caps
c. Floor Beams
d. Floor Slab
e. Floor Beams (Above 4.00m high)
UNITS
sq.m.
7.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
lm.
sq.m.
lm.
lm.
180.00
175.00
125.00
155.00
145.00
180.00
160.00
180.00
185.00
155.00
160.00
200.00
185.00
160.00
195.00
65.00
150.00
40.00
35.00
plus 15.00
Stripping
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
40.00
40.00
35.00
40.00
40.00
45.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
45.00
40.00
50.00
40.00
40.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
4.00
7.00
10.00
14.00
15.00
18.50
22.50
25.00
sq.m.
sq.m.
sq.m.
45.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
22.50
35.00
32.50
30.00
35.00
lm.
lm.
20.00
27.50
sq.m.
sq.m.
sq.m.
set
set
set
50.00
60.00
50.00
150.00
225.00
125.00
set
set
sq.m.
300.00
350.00
105.00
bft.
10.50
sq.m.
sq.m.
sq.m.
135.00
135.00
160.00
sq.m.
95.00
sq.m.
125.00
lm.
lm.
lm.
15.00
17.50
5.00
sq.m.
sq.m.
sq.m.
sq.m.
140.00
125.00
160.00
65.00
sq.m.
sq.m.
65.00
55.00
set
set
lm.
set
95.00
100.00
17.50
8.50
sq.m.
140.00
lm.
75.00
lm.
85.00
by negotiation (30 % of materials)
lm.
10.50
lm.
22.50
set
set
set
set
set
set
sq.m.
14.50
sq.m.
sq.m.
sq.m.
130.00
100.00
95.00
sq.m.
sq.m.
125.00
120.00
sq.m.
sq.m.
125.00
120.00
sq.m.
120.00
F.
G.
H.
I.
sq.m.
135.00
sq.m.
125.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
lm.
lm.
lm.
lm.
lm.
sq.m.
sq.m.
lm.
sq.m.
130.00
135.00
60.00
80.00
125.00
85.00
95.00
80.00
55.00
25.00
175.00
sq.m.
175.00
sq.m.
sq.m.
lm.
220.00
205.00
130.00
sq.m.
sq.m.
lm.
165.00
210.00
95.00
lm.
lm.
lft.
65.00
70.00
sq.m.
sq.m.
lm.
50.00
90.00
60.00
J.
K.
L.
M.
N.
O.
P.
Q.
sq.m.
sq.m.
sq.m.
105.00
180.00
210.00
sq.m.
sq.m.
sq.m.
200.00
185.00
170.00
sq.m.
sq.m.
sq.m.
sq.m.
lm.
180.00
160.00
140.00
140.00
55.00
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
180.00
170.00
130.00
150.00
140.00
130.00
170.00
95.00
175.00
sq.m.
sq.m.
sq.m.
sq.m.
185.00
265.00
50.00
325.00
sq.m.
sq.m.
sq.m.
lm.
set
lm.
set
sq.m.
sq.m.
sq.m.
280.00
260.00
260.00
240.00
350.00
165.00
140.00
sq.m.
sq.m.
lm.
lm.
cu.m.
20.00
45.00
30.00
40.00
320.00
sq.m.
250.00
V.
LABOR WORKS
A. Excavation
a. Ordinary Soil
* Bulk
* Manual
b. Adobe
c. Dewatering
B. Backfilling
a. Manual
b. by Equipment
C. Levelling
D. Excavation of Ftg. Tie Beam & Wall Footings
E. Compaction
F. Basecoarse
a. Manual
b. by Equipment
G. Soil Poisoning
H. Polyethelene sheets
I. PVC Waterstop
J. Chipping
a. From 0.01-0.10
b. From 0.11-0.20
K. Concreting
i. Pumpcrete
ii. Job mix
sq.m.
lm.
sq.m.
sq.m.
sq.m.
220.00
150.00
150.00
250.00
275.00
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
kg.
sq.m.
2.30
2.45
2.50
2.60
2.50
3.20
4.25
2.75
3.25
4.00
3.00
5.00
3.50
3.50
3.50
15.00
cu.m.
cu.m.
cu.m.
120.00
230.00
300.00
cu.m.
cu.m.
sq.m.
cu.m.
sq.m.
85.00
45.00
25.00
275.00
25.00
cu.m.
cu.m.
sq.m.
sq.m.
lm.
85.00
45.00
7.50
5.00
7.50
lm.
lm.
10.00
20.00
cu.m.
cu.m.
80.00
700.00
pp
300.00
sq.m.
sq.m.
lm.
pp
pp
80.00
65.00
40.00
150.00
1,500.00
lft.
lft.
lft.
pc.
pc.
sq.m.
5.00
4.50
12.50
110.00
165.00
50.00
cu.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
set
sq.m.
sq.m.
lm.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
cu.m.
cu.m.
lm.
lot
lot
750.00
25.00
20.00
25.00
30.00
20.00
30.00
15.00
25.00
10.00
12.50
7.50
35.00
15.00
35.00
10.00
20.00
15.00
30.00
Concrete
CHB Walls
Corr. G.I. Sheets
Asbestos Roofing
Steel Roof Framing
Wooden Roof Framing
Wooden Floor Framing
Steel Windows
Doors
Double Wall Partition
Ceiling
Gutter & Flashing
Chipping of Floor topping
Cabinets,counters & shelves
Chipping of tiles
Scraping of vinyl tiles
Wood parquet
Chipping of Synthetic Finish
Alum. Framed Glass
Blasting of Footings (by Dynamite)
Blasting of Walls (by Dynamite)
Cutting of Concrete
Electrical
Plumbing
NOTES :
All tools,equipments,scaffolding installation,accessories,hauling & other miscellaneous
shall be shouldered by the sub-contractors.
Hauling costs are included in above unit costs up to fourth floor if it will be done
starting to ground floor,however if works started from third or fourth floor,
additional hauling cost will be given to the subcontractors.
For High Rise Building, Hauling shall be done by Tower Crane but with the help of Subcon labor.
Add 10% VAT to all labor unit costs only.
Add 5%-10% to all labor unit costs if work is outside Metro-Manila. (Optional)
Add 10% to all Materials supplied by the Sub-contractors.
All unit cost includes deliveries within Metro-Manila only.
(Painting) All lineal meters shall be computed once,(ex.Z-bar & sq.bar=total length=lm)
New unit costs are based on a minimum salary of P250.00/day
New unit costs are based if material is within the periphery of the building,if not
make an additional hauling costs to be computed by PE.
All items not included in above items of work shall be the responsibility of the Project
Engineer to compute and award to the contractors.
Formworks Unit Costs are based on A-Frames & Eco-forms to be used,when scaffold use is
lumber add an additional of P10.00 per sq.m. of beams,slabs,Shearwall or RC Walls.
All unit costs are based on the standard construction procedures,any actual works that
deviates on standard shall be the responsibility of the PE concerned.
Differentiating Small to Medium and Large Scale construction shall be the responsibility
of the Project Job Captain involved.
Bar Bender & Bar Cutter are not the obligation of the Company but if provided, repair & maintenance
shall be shouldered by subcon.
C O N S U MAB LE S :
^^^^^^^^^^ ^^^^^^^^^^^^^ ^^^^^^^^^^^^^^^
BF
Nails =
-------------------- = No. of kegs.
40 X 45
Total bft. =
Vt x 192
-------------------- (For Ftb, Lintel beams & Stiff.columns)
2.40
Vt x 192
-------------------- (for all other structures)
1.60
Wt
G.I. Wires #16 =
---------------------------------------
Total bft. =
65x45
Wt
--------------------------------------60x45
Wt
--------------------------------------50x45
n (30 % of materials)
maintenance
A. GENERAL REQUIREMENTS
A.1 Mobilization/Demobilization
a. Mobilization
5 t/l @
b. Demobilization
5 t/l @
5,000.00
25,000.00
5,000.00
25,000.00
1,050,000.00
131,266.50
70.00
50.00
105,000.00
52,500.00
1,155.00
1,340,041.50
1,125,000.00
140,641.50
70.00
50.00
112,500.00
56,250.00
1,237.50
1,435,749.00
=
=
=
20%
A x 0.20 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011
=
=
d. Bid Bond 5%
Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
750,000.00
93,766.50
70.00
50.00
75,000.00
37,500.00
825.00
957,211.50
=
=
=
A x 0.05 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
262,500.00
32,829.00
70.00
50.00
26,250.00
Premium Tax
Municipality Tax
=
=
Premium x 0.05
Premium x 0.0011
=
=
P
13,125.00
288.75
335,112.75
1,875,000.00
234,391.50
70.00
50.00
187,500.00
93,750.00
2,062.50
2,392,824.00
87,500.00
10,954.00
70.00
50.00
8,750.00
4,375.00
96.25
111,795.25
A x 0.0025
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011
=
=
A = 20,000,000.00
f. Comprehensive General Liability Insurance 100%
Premium
= For 3 m = 10,000.00
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=
=
=
=
45.00 /sq.m.
2,462,877.90
b. Occupancy Permit
54,730.62 sq.m.
25.00 /sq.m.
1,368,265.50
750.00 /sq.m.
225,000.00
150.00 sq.m. @
500.00 /cu.m.
75,000.00
d. Temfacil Permit
40.00 sq.m. @
3,500.00
400.00 sq.m. @
36.00 sq.m. @
18.00 sq.m. @
500.00
500.00
10,000.00
5.00 rental/mo.
7,500.00
=
=
=
=
=
=
=
=
140,000.00
250,000.00
200,000.00
18,000.00
180,000.00
120,000.00
37,500.00
Thi
insu
ma
nat
T
in
p
a
a.
b.
c.
c.
Power Consumptions
Water Consumptions
Deepwell Construction
Telephone Bill
10,000.00
2,500.00
for
for
19.00 mos. =
19.00 mos. =
2,000.00
for
19.00 mos. =
180,000.00
54,000.00
30,000.00
108,000.00
for
for
for
for
16.00
8.00
8.00
4.00
mos.
mos.
mos.
mos.
190,000.00
47,500.00
100,000.00
38,000.00
=
=
=
=
2,880,000.00
432,000.00
240,000.00
432,000.00
B. SITEWORKS
Item 102-2
Grade Line Cut (Ord. Soil)
A. Equipment
1.00 - Bulldozer D80A-12, 180 HP
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1.00
5.00
2.00
3.00
B. Labor
C. Output
- Foreman
- Laborer
- Operator
- Driver
VAT, 10%
Sub-total
100.00 cu.m./hr.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
DIRECT UNIT COST
Item Backfilling
104-3
& Compaction
COST
24.125 lit.
10.00 lit.
27.75 lit.
=
=
=
117.38 liters
11.74 liters
=
P
P
45.91 /cu.m.
A. Equipment
3 - Dump Truck
1 - Road Roller
1 - Payloader
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
65.00 cu.m./hr.
27.75 lit.
14.00 lit.
2.28 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
99.53 liters
9.95 liters
T O TAL
COST
65.00
55.04
*****
DIRECT UNIT COST =
55.04 /cu.m.
Item 102-3
Excavation (Adobe)
A. Equipment
1.00 - Backhoe
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1.00 - Foreman
5.00 - Laborer
2.00 - Operator
B. Labor
3.00 - Driver
VAT, 10%
Sub-total
C. Output
60.00 cu.m./hr.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
COST
24.125 lit.
10.00 lit.
27.75 lit.
=
=
=
117.38 liters
11.74 liters
P
71.93 /cu.m.
TRIMMING
A. Labor
1.00 - Foreman
5.00 - Laborer
VAT, 10%
B. Output
2.00 sq.m./hr.
64.97 /sq.m.
Item Aggregate
200-1
Sub-Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
50.00 cu.m./hr.
8.00 lit.
14.00 lit.
5.44 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
27.44 liters
2.74 liters
COST
P
332.97 /cu.m.
Item Aggregate
201-1
Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
50.00 cu.m./hr.
8.00 lit.
14.00 lit.
5.44 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
27.44 liters
2.74 liters
COST
P
356.97 /cu.m.
Item Portland
311-2
Cement Concrete Pavement PCCP
0.15 mthick)
Assume Quantity
L
W
A
V
=
=
=
=
100.00
6.00
600.00
90.00
m.
m.
sq.m.
cu.m.
A. Materials:
a. Concrete Mix delivered @ jobsite
90.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12
6.00 in.
10.00 bft.
3.33
10.00
444.33
333.33
777.67
777.67
259.22 bft.
1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.
0.18
266.67
53.33
9.47
kgs.
pcs.
pcs.
kgs.
Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=
No. of blades = 133.33/350 =
Sub-total
133.33
0.38 blades
e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total
0.0040 m
467.33 m
1.88 cu.m.
0.44 MT
f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total
266.67
88.89
2.22 kgs.
g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost
21.43 gals.
- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost
220.00 /day
175.00
175.00
175.00
175.00
145.00
6.00
6.00
6.00
6.00
6.00
6.00
56.25 /day
60.00 /day
1,200.00 /day
4.00
4.00
1.00
C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
COST
P
361.31 /sq.m.
Item Portland
311-2
Cement Concrete Pavement PCCP
0.2 mthick)
Assume Quantity
L
W
A
V
=
=
=
=
100.00
6.00
600.00
120.00
m.
m.
sq.m.
cu.m.
A. Materials:
a. Concrete Mix delivered @ jobsite
120.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12
6.00 in.
10.00 bft.
3.33
10.00
444.33
333.33
777.67
777.67
259.22 bft.
1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.
0.18
266.67
53.33
9.47
kgs.
pcs.
pcs.
kgs.
133.33
0.38 blades
e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total
0.0040 m
467.33 m
1.88 cu.m.
0.44 MT
f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total
266.67
88.89
2.22 kgs.
g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost
21.43 gals.
- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost
220.00 /day
175.00
175.00
175.00
175.00
145.00
6.00
6.00
6.00
6.00
6.00
6.00
56.25 /day
60.00 /day
1,200.00 /day
4.00
4.00
1.00
C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
DIRECT UNIT COST =
COST
=
P
P
456.31 /sq.m.
ITEMConcrete
502
Curbs & Gutter
1.Materials:
a.Forms : 100 bft.(Good for 60.00 m)
b.C.W.Nails:20 kgs.(Good for 60.00 m)
c.Concrete Volume = (0.15x0.15)+(0.00x0.00)=0.025 cu.m.
Cement = 0.09 x 9 =
Sand = 0.09 x 0.50 =
Gravel = 0.09 x 1.00 =
Sub-total
1.67 @
0.33
24.00
24.00
0.81
0.05
0.09
125.00
200.00
440.00
A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total
50.00
1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total
27.50
21.875
18.125
2.Manpower:
1.05 liters
0.11 liters
10.00
45.00
20.00 lm./hr.
Direct Cost =
11.21 /lm.
1.Manpower:
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
2.Output =
27.500
21.875
18.125
11.00 lm./hr.
Direct Cost =
14.38 /lm.
45.00
60.00
2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total
27.50
21.88
18.13
3.00
1.05
4.05 liters
0.41 liters
Oil,10 % of fuel =
Sub-total
4.Output =
10.00
45.00
10.00 lm./hr.
Direct Cost =
ITEMConcrete
601
Sidewalk
Assume Quantity = 100.00 sq.m.
Thickness =
0.10 m
1.Materials:
a.Forms : 4 bft./sq.m. x 100/3
Used 3 times
b.C.W.Nails:0.02 kgs./bft.x4x100 =
Cement = 10.00 x 9 =
Sand = 10.00 x 0.45 =
Gravel = 10.00 x 0.90 =
Sub-total
33.24 /lm.
P
256.67 /lm.
Volume =
133.33 @
8.00
90.00
4.50
9.00
10.00
24.00
24.00
125.00
200.00
440.00
A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total
50.00 /day
1.00
220.00 /day
175.00
145.00
1.00
1.00
1.00
2.Manpower:
1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total
3.Fuel and Oil
Vibrator Plate =
Oil,10 % of fuel =
Sub-total
4.Output =
1.05 liters
0.11 liters
10.00
45.00
20.00 lm./hr.
Output =
60.00 sq.m./day
220.00 /day
175.00
145.00
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
C.Pouring and Finishing
1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total
1.75
1.75
1.75
45.00 /hr.
60.00
2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total
220.00 /day
175.00
145.00
1.75
1.75
1.75
3.00
1.05
4.05 liters
0.41 liters
10.00
45.00
250.93 /sq.m.
C. MASONRY WORKS
a. 6" CHB (750 psi) Load Bearing
a.Materials
12.50 pcs. 6" CHB (Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand
@
@
10.50
125.00
200.00
10.30
125.00
200.00
12.00
36.00
M=
@
@
7.80
125.00
200.00
12.00
36.00
M=
@
@
7.50
125.00
200.00
12.00
36.00
M=
@
@
10.50
125.00
200.00
12.00
36.00
M=
@
@
12.00
36.00
M=
125.00
130.00
120.00
200.00
135.00
600.00
M=
L=
150.00
30.00
M=
125.00
200.00
M=
125.00
200.00
M=
125.00
200.00
900.00
M=
125.00
200.00
900.00
M=
125.00
200.00
80.00
M=
FLOOR FINISHES
a. Patterned Cement Finish
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand
a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding
125.00
200.00
3.50
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles
125.00
90.00
M=
125.00
200.00
125.00
90.00
M=
125.00
200.00
3.50
125.00
45.00
M=
125.00
200.00
125.00
45.00
M=
125.00
200.00
45.00
3.50
125.00
90.00
M=
125.00
200.00
3.50
125.00
45.00
M=
125.00
200.00
125.00
14.00
30.00
45.00
M=
125.00
200.00
125.00
10.00
80.00
65.00
M=
125.00
200.00
125.00
14.00
30.00
45.00
M=
125.00
200.00
4,500.00
125.00
200.00
125.00
35.00
30.00
45.00
M=
28.00
550.00
24.00
550.00
125.00
200.00
11.00
M=
125.00
200.00
10.50
M=
125.00
30.00
200.00
10.50
M=
125.00
30.00
200.00
6.00
M=
125.00
30.00
200.00
14.00
M=
125.00
30.00
200.00
10.50
M=
125.00
30.00
200.00
75.00
M=
125.00
30.00
200.00
28.00
M=
125.00
30.00
200.00
150.00
M=
125.00
30.00
200.00
120.00
M=
125.00
200.00
900.00
125.00
200.00
900.00
125.00
200.00
900.00
125.00
200.00
900.00
125.00
200.00
950.00
125.00
200.00
900.00
125.00
200.00
45.00
M=
25.00
M=
WALL FINISHES
a. 300x300 Synthetic Granite
a.Materials
25.00
880.00
M=
50.28
880.00
M=
50.43
880.00
M=
0.450
0.250
0.027
12.000
bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs. 12"x12" Granite Tiles
Materials
bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs.4"x8"Wall Tiles
125.00
30.00
200.00
120.00
125.00
30.00
200.00
2.50
M=
125.00
30.00
200.00
10.50
M=
125.00
30.00
200.00
14.00
M=
125.00
30.00
200.00
28.00
M=
125.00
30.00
200.00
75.00
M=
2.50
1. Exterior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.424 bag Cement(Portland)
0.032 cu.m. Sand
2. Interior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.350 bag Cement(Portland)
0.027 cu.m. Sand
125.00
200.00
M=
125.00
200.00
M=
208.00
125.00
200.00
M=
125.00
200.00
M=
208.00
125.00
200.00
M=
125.00
200.00
M=
125.00
200.00
M=
125.00
200.00
M=
f. Plain Cement Plaster Finish (By LM) w = 0.60m.
a.Materials
0.294 bag Cement(Portland)
0.022 cu.m. Sand
125.00
200.00
M=
125.00
200.00
M=
125.00
200.00
3.50
125.00
90.00
M=
125.00
200.00
125.00
90.00
M=
CEILING FINISHES
a. 1/4"thk.Marine Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)
w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@
0.375 pcs. 1/4"x4'x8'Marine Plywood
0.400 kls. Assorted Nails
0.050 gal. Solignum
24.00
355.00
24.00
525.00
M=
24.00
200.00
24.00
525.00
M=
24.00
295.00
24.00
525.00
M=
24.00
296.00
24.00
525.00
M=
24.00
1,150.00
10.50
175.00
M=
125.00
200.00
M=
10.00
22.50
M=
300.00
20.00
M=
700.00
175.00
145.00
125.00
250.00
260.00
M=
295.00
175.00
145.00
125.00
300.00
250.00
260.00
M=
1,665.00
12.50
M=
770.00
5.50
137.50
M=
1,665.00
12.50
M=
770.00
5.50
137.50
M=
CONCRETE WORKS
a. Lintel Beams (For 6" CHB)
a. Materials
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
b. Labor
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
1,665.00
12.50
M=
b. Labor
0.0250 cu.m. Concrete
2.0000 kg. Rebars
0.3000 sq.m. Formworks
770.00
5.50
137.50
M=
1,665.00
12.50
M=
770.00
5.50
137.50
M=
275.00
18.125
275.00
18.125
250.00
120.00
Equipment Cost
10% VAT
20.63
b. Labor
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks
Production
Unit Cost
=
=
b. Forms
1 ELF
10 Laborers
20,000.00 kgs./day
P
Production
Unit Cost
=
=
Demolition Works
a. Equipment (Demolition)
1.00 Compressor
2.00 Jackhammer
12.00 hrs./day
12.00
0.30 /kg.
12.00 hrs./day
12.00
750.00 sq.m./day
7.88 /sq.m.
b. Manpower
20.00 Laborers
Labor Cost
10% VAT
Total Cost / hr.
Duration =
c. Equipment (Hauling & Disposal)
1.00 Loader
2.00 Dump Truck
Duration =
700.00
500.00
Equipment Cost
10% VAT
6 hrs. for 6 days
Total Cost =
1 Dumptruck
10 Laborers
8.00 hrs./day
8.00
450.00
18.125
1.00 hr.
Unit Cost
Item SP - 6 G.I. Sheet Temporary Fence (H = 3.00m)
a. Materials
20.00 bft. Coco Lumber
15.00 lft. Ga. # 26 Pre-painted Corrugated GI Sheets
0.015 kegs CW Nails
0.10 kgs. Roof Nails
50.00
15.00
20.00
=
6.00
40.00
950.00
85.00
Unit Cost =
26.00
525.00
75.00
475.00
45.00
25
Unit Cost (M & L) =
945.00 sq.m.
1.50
12.50
45.00
65.00
12.00 pcs.
0.06 gal.
Installation
Polishing
12.00 tiles
12.00 tiles
3.28 ln.ft.
1.00 lot
23.00
525.00
Materials
3.50
2.40
Sub Total
VAT
Labor
26.50
3.08
Materials
Labor
P
P
Cement
Sand
0.70 bags
0.06 cu.m.
12.50
1.05
0.09
2.50
0.04
12.50
0.54
0.04
2.50
0.04
pcs.
bags
cu.m.
kgs.
kgs.
pcs.
bags
cu.m.
kgs.
kgs.
125.00
300.00
Materials
Labor
P
P
7.50
125.00
300.00
12.20
30.20
Materials
Labor
P
P
7.30
125.00
300.00
12.20
30.20
Materials
Labor
P
P
125.00
300.00
80.00
148.00
Materials
Labor
P
P
125.00
300.00
80.00
Materials
Labor
P
P
C. Exterior Plastering
Cement
Sand
ME 602 Mortar Enhancer
Sealopruf Integral Waterproofing
0.50
0.06
0.13
0.05
bags
cu.m.
liters
gal
D. Interior Plastering
Cement
Sand
ME 602 Mortar Enhancer
0.30 bags
0.03 cu.m.
0.08 liters
C.MATERIALS
50,000.00
4,179,910.00
0.5573%
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
45.
46.
47.
Premium Fuel
Diesel
Lubricating Oil
Gravel Fill
Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
CW Nails
Cement
Gravel
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)
4,131,143.40
945,500.00
375,500.00
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.
98.
99.
100.
3,984,000.00
A.EQUIPMENTS:
1,000.00 =
500.00 =
400.00 =
=
=
27.50
18.13
21.88
20.00
=
=
=
=
=
1,000.00
500.00
1,200.00
24.41
272.44
2,996.85 /hr.
27.50
90.63
43.75
60.00
22.19
244.06 /hr.
24.125
10.00
83.25
117.38 liters
7.00 =
45.00 =
4,590.72 /hr.
821.63
528.19
1,349.81 /hr.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Foreman
Leadman
Timekeeper
Carpenter
Mason
Steelman
Laborer
Floater
Mixer Operator
Painter
Welder
HE Operator
Driver
Screeder Operator
400.00 =
350.00 =
500.00 =
=
=
27.50
18.13
21.88
20.00
=
=
=
=
=
1,200.00
350.00
500.00
16.02
206.60
2,272.62 /hr.
27.50
54.38
43.75
20.00
14.56
160.19 /hr.
83.25
14.00
2.28
99.53 liters
7.00 =
45.00 =
696.71
447.89
1,144.60 /hr.
3,577.40 /hr.
/CU.M.
/CU.M.
750.00 =
500.00 =
400.00 =
=
=
750.00
500.00
1,200.00
24.41
247.44
2,721.85 /hr.
27.50 =
18.13 =
21.88 =
27.50
90.63
43.75
20.00 =
=
60.00
22.19
244.06 /hr.
24.125
10.00
83.25
117.38 liters
7.00 =
45.00 =
821.63
528.19
1,349.81 /hr.
4,315.72 /hr.
27.50 =
18.13 =
=
27.50
90.63
11.81
129.94 /hr.
400.00 =
350.00 =
300.00 =
=
=
400.00
350.00
300.00
16.02
106.60
1,172.62 /hr.
27.50
18.13
21.88
20.00
=
=
=
=
=
27.50
54.38
43.75
20.00
14.56
160.19 /hr.
8.00
14.00
5.44
27.44 liters
7.00 =
45.00 =
192.08
123.48
315.56 /hr.
250.00 =
15,000.00
15,000.00 /hr.
16,648.37 /hr.
400.00 =
350.00 =
300.00 =
=
=
27.50
18.13
21.88
20.00
=
=
=
=
=
400.00
350.00
300.00
16.02
106.60
1,172.62 /hr.
27.50
54.38
43.75
20.00
14.56
160.19 /hr.
8.00
14.00
5.44
27.44 liters
7.00 =
45.00 =
192.08
123.48
315.56 /hr.
270.00 =
16,200.00
16,200.00 /hr.
17,848.37 /hr.
1,900.00
171,000.00
171,000.00
24.00 =
6,221.33
6,221.33
12.00 =
2,035.20
12.00 =
113.66
2,148.86
m.
days
day
day
day
10,400.00 =
3,961.90
3,961.90
13,500.00 =
5,976.45
5,976.45
24.00 =
53.33
53.33
40.00 =
857.14
857.14
P 190,219.03
317.03
1,320.00
2,100.00
2,100.00
4,200.00
5,250.00
6,090.00
2,106.00
23,166.00
23,166.00
38.61
450.00
240.00
2,400.00
309.00
3,399.00
3,399.00
5.67
=
=
=
=
=
=
=
=
=
=
=
216,784.03
1,900.00
m.
228,000.00
228,000.00
24.00 =
6,221.33
6,221.33
12.00 =
2,035.20
12.00 =
113.66
2,148.86
10,400.00 =
3,961.90
3,961.90
13,500.00 =
5,976.45
5,976.45
24.00 =
53.33
53.33
40.00 =
857.14
857.14
P 247,219.03
412.03
1,320.00
2,100.00
2,100.00
4,200.00
5,250.00
6,090.00
2,106.00
23,166.00
23,166.00
38.61
450.00
240.00
2,400.00
309.00
3,399.00
3,399.00
5.67
days
=
=
=
=
=
=
=
day
day
day
=
=
=
=
273,784.03
=
=
40.00
8.00
=
=
=
P
101.25
9.00
39.60
197.85
=
=
P
50.00
5.00
55.00
=
=
=
=
27.50
21.88
90.63
14.00
154.00
=
=
P
10.50
4.73
15.23
=
=
=
=
P
27.50
43.75
72.50
14.38
158.13
=
=
=
P
45.00
60.00
10.50
115.50
=
=
=
=
P
27.50
43.75
72.50
14.38
158.13
=
=
P
40.50
18.23
58.73
cu.m.
=
3,200.00
=
=
=
=
P
192.00
11,250.00
900.00
3,960.00
19,502.00
195.02
day
=
=
P
50.00
5.00
55.00
day
=
=
=
220.00
175.00
725.00
days
days
days
days
days
days
=
=
=
=
P
0.00
1,120.00
=
=
P
10.50
4.73
15.23
=
=
=
=
P
385.00
612.50
1,015.00
201.25
2,213.75
=
=
=
P
45.00
60.00
10.50
115.50
=
=
=
=
P
385.00
612.50
1,015.00
0.00
2,012.50
=
=
P
40.50
18.23
58.73
131.25
127.50
18.19
=
=
P
36.00
1.80
314.74 /sq.m.
=
=
=
=
=
P
128.75
67.50
9.63
36.00
1.80
243.68 /sq.m.
=
=
=
=
=
P
97.50
127.50
18.19
36.00
1.80
280.99 /sq.m.
=
=
=
=
=
P
93.75
67.50
9.63
36.00
1.80
208.68 /sq.m.
=
=
=
=
=
P
252.00
61.25
7.40
27.00
1.26
348.91 /sq.m.
=
=
=
=
=
=
P
P
1,000.00
520.00
480.00
136.05
94.50
600.00
2,830.55 /cu.m.
770.00 /cu.m.
=
=
P
3,750.00
375.00
4,125.00 /cu.m.
=
=
P
87.50
10.70
98.20 /sq.m.
=
=
P
70.00
8.56
78.56 /sq.m.
=
=
=
P
70.00
8.56
90.00
168.56 /sq.m.
=
=
=
P
17.50
2.14
90.00
109.64 /sq.m.
=
=
=
P
70.00
8.56
20.00
98.56 /sq.m.
=
=
=
=
=
P
61.25
7.49
10.50
78.13
112.50
269.87 /sq.m.
=
=
18.38
2.25
=
=
P
23.44
33.75
77.81 /lm.
=
=
=
61.25
7.49
10.50
=
=
P
78.13
56.25
213.62 /sq.m.
=
=
18.38
2.25
=
=
P
23.44
16.88
60.93 /lm.
=
=
=
=
87.50
10.70
45.00
10.50
78.13
=
P
112.50
344.33 /sq.m.
=
=
=
21.00
2.57
5.74
=
=
P
3.91
2.81
36.03 /lm.
=
=
70.00
8.56
=
=
=
=
P
=
=
=
=
=
=
P
=
=
=
=
=
=
P
78.13
56.00
3.00
56.25
271.94 /lm.
70.00
8.56
27.34
120.00
20.00
28.44
274.34 /lm.
70.00
8.56
18.75
126.00
11.25
13.50
248.06 /lm.
=
=
=
=
P
P
=
=
61.25
7.49
4,500.00
450.00
5,018.74 /lm.
220.00 /lm.
70.00
8.56
=
=
=
=
P
18.75
315.00
11.25
13.50
437.06 /lm.
=
=
P
336.00
33.00
369.00 /sq.m.
=
=
P
288.00
33.00
321.00 /sq.m.
=
=
=
P
70.00
8.56
275.00
353.56 /sq.m.
=
=
=
P
61.25
7.49
420.00
488.74 /sq.m.
61.25
=
=
=
P
15.00
7.49
472.50
556.24 /sq.m.
=
=
=
=
P
61.25
15.00
7.49
540.00
623.74 /sq.m.
=
=
=
=
P
61.25
15.00
7.49
350.00
433.74 /sq.m.
=
=
=
=
P
61.25
15.00
7.49
525.00
608.74 /sq.m.
=
=
=
=
P
61.25
15.00
7.49
375.00
458.74 /sq.m.
=
=
=
=
P
61.25
15.00
7.49
336.00
419.74 /sq.m.
=
=
=
61.25
15.00
7.49
=
P
1,800.00
1,883.74 /sq.m.
=
=
=
=
P
61.25
15.00
7.49
1,440.00
1,523.74 /sq.m.
=
=
=
=
P
P
36.75
4.49
540.00
54.00
635.24 /lm.
200.00 /lm.
=
=
=
=
P
P
21.44
2.62
315.00
31.50
370.56 /lm.
185.00 /lm.
=
=
=
=
P
P
12.25
1.50
180.00
18.00
211.75 /lm.
185.00 /lm.
=
=
=
=
P
P
9.19
1.12
135.00
13.50
158.81 /lm.
185.00 /lm.
61.25
=
=
=
P
P
7.49
950.00
95.00
1,113.74 /lm.
185.00 /lm.
=
=
=
=
P
P
18.38
2.25
270.00
27.00
317.62 /lm.
185.00 /lm.
=
=
=
P
87.50
10.70
45.00
143.20 /sq.m.
=
=
P
300.00
30.00
330.00 /sq.m.
=
=
P
82.00
70.94
152.94 /lm.
=
=
P
164.93
106.41
271.33 /lm.
=
=
P
165.42
141.87
307.29 /lm.
=
=
=
=
P
56.25
7.50
5.35
1,440.00
1,509.10 /lm.
=
=
=
=
P
56.25
7.50
5.35
225.00
294.10 /sq.m.
=
=
=
=
P
56.25
7.50
5.35
525.00
594.10 /sq.m.
=
=
=
=
P
56.25
7.50
5.35
350.00
419.10 /sq.m.
=
=
=
=
P
56.25
7.50
5.35
336.00
405.10 /sq.m.
=
=
=
=
P
56.25
7.50
5.35
375.00
444.10 /sq.m.
242.50
=
=
P
52.94
6.47
301.91 /sq.m.
=
=
P
52.94
6.47
59.41 /sq.m.
=
=
=
P
31.20
62.56
7.65
101.41 /sq.m.
=
=
P
43.75
5.35
49.10 /sq.m.
=
=
=
P
31.20
52.50
6.42
90.12 /sq.m.
=
=
P
30.63
3.75
34.37 /lm.
=
=
P
18.38
2.25
20.62 /lm.
=
=
9.19
1.12
10.31 /lm.
=
=
P
36.75
4.49
41.24 /lm.
=
=
P
6.75
0.80
7.55 /lm.
=
=
=
=
=
P
43.75
5.35
10.50
78.13
112.50
250.23 /sq.m.
=
=
13.13
1.61
=
=
P
23.44
33.75
71.92 /lm.
=
=
=
=
P
300.00
133.13
9.60
26.25
468.98 /sq.m.
300.00
=
=
=
P
75.00
9.60
26.25
410.85 /sq.m.
=
=
=
=
P
240.00
110.63
9.60
26.25
386.48 /sq.m.
=
=
=
=
P
240.00
111.00
9.60
26.25
386.85 /sq.m.
=
=
=
=
P
240.00
431.25
4.20
8.75
684.20 /sq.m.
=
=
P
1.75
0.21
1.96 /sq.m.
=
=
P
135.00
258.75
393.75 /sq.m.
=
=
P
4,050.00
230.00
4,280.00 /sq.m.
=
=
=
=
=
=
P
262.50
21.00
29.00
18.75
10.00
26.00
367.25 /sq.m.
=
=
=
=
=
=
=
P
110.63
21.00
29.00
18.75
3.75
10.00
26.00
219.13 /sq.m.
=
=
=
P
62.44
40.00
102.44 /l.m.
=
=
=
P
28.88
17.60
89.38
135.85 /l.m.
=
=
=
P
58.28
41.25
99.53 /l.m.
=
=
=
P
26.95
18.15
110.00
155.10 /l.m.
41.63
=
=
P
25.00
66.63 /l.m.
=
=
=
P
19.25
11.00
41.25
71.50 /l.m.
=
=
=
P
49.95
25.00
74.95 /l.m.
=
=
=
P
23.10
11.00
82.50
116.60 /l.m.
3,300.00
2,610.00
5,910.00
3,300.00
2,610.00
5,910.00
/hr.
/hr.
250.00
240.00
490.00
49.00
539.00 /hr.
/hr.
412.50
412.50
41.25
453.75
992.75 /hr.
180.00 hours
178,695.00
/hr.
/hr.
700.00
1,000.00
1,700.00
170.00
1,870.00 /hr.
36.00
67,320.00
246,015.00
3,600.00
1,740.00
5,340.00
427,200.00
/hr.
/hr.
/hr.
=
=
=
50.00
15.00
20.00
85.00 /hr./pump
=
=
=
=
120.00
600.00
14.25
8.50
742.75 /lm.
=
=
=
=
=
=
=
ost (M & L) =
780.00
1,050.00
450.00
118.75
45.00
50.00
997.50
3,491.25 /lm.
say
=
=
=
=
=
3,500.00 /lm.
12.75
11,875.00
1,125.00
2,145.00
7,578.88
22,736.63
24.06
25.00 /sq.m.
ost (M & L) =
=
=
=
=
=
=
=
233.33
604.17
308.00
62.50
93.75
12.00
154.00
1,467.75 /sq.m.
733.88 /sq.m.
276.00
31.50
307.50
42.00
28.80
70.80
7.08
77.88
86.92
3.08
90.00
22.00
87.50
16.50
104.00
104.00
93.75
131.25
27.00
30.50
1.21
283.71
110.00
91.25
67.50
12.00
30.50
1.21
202.46
104.00
62.50
16.50
10.00
7.40
96.40
139.00
37.50
9.90
6.00
53.40
115.50
UNIT COST
Premium Fuel
Lubricating Oil
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)
10.00
7.00
45.00
440.00
150.00
250.00
270.00
1,900.00
24.00
12.00
40.00
13,500.00
10,400.00
24.00
125.00
440.00
300.00
200.00
355.00
375.00
38.00
17.50
10.50
10.30
7.80
7.50
80.00
900.00
10.50
6.00
35.00
28.00
10.50
14.00
75.00
150.00
4,500.00
11.00
120.00
10.50
14.00
2.50
28.00
75.00
4.00
25.00
6.00
28.00
/lit.
/lit.
/lit.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bft.
/kg.
/gal.
/MT
/pc.
/kl.
/bag
/cu.m.
/cu.m.
/cu.m.
/pc.
/pc.
/bft.
/pc.
/pc.
/pc.
/pc.
/pc.
/kl.
/kl.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
24.00
90.00
80.00
950.00
900.00
30.00
10.50
90.00
90.00
45.00
45.00
65.00
24.00
10.50
525.00
550.00
36.00
3.50
10.00
300.00
295.00
296.00
1,150.00
175.00
145.00
125.00
300.00
250.00
260.00
700.00
23.00
30.00
25.00
45.00
25.00
1,500.00
3,017.00
3,026.00
880.00
130.00
135.00
600.00
120.00
150.00
10.00
60.00
1,300.00
1,100.00
2.50
/pc.
/pc.
/pc.
/sq.m.
/sq.m.
/kl.
/pc.
/can
/can
/can
/can
/can
/kl.
/pc.
/gal.
/gal.
/kl.
/lft.
/lft.
/cu.m.
/pc
/pc
/pc
/pc
/pc
/pc
/roll
/gal.
/gross
/pc.
/lft.
/lft.
/pc.
/sq.m.
/pc.
/pc.
/pc.
/pc.
/liter
/bag
/gal.
/bag
/bag
/pc.
/pc.
/sq.ft.
/sq.m.
/pc.
/pc.
275.00 /bag
38pcs./sq.m.
Labor
25.00 /sq.ft.
80.00 /sq.m.
RENTALS
Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump
Concrete Cutter
1-Bagger Mixer
Concrete Breaker
1,000.00
500.00
400.00
400.00
350.00
300.00
300.00
20.00
50.00
20.00
56.25
60.00
1,200.00
45.00
20.00
75.00
900.00
750.00
500.00
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
DAILY RATES
Timekeeper
Mixer Operator
HE Operator
Screeder Operator
220.00
200.00
150.00
175.00
175.00
185.00
145.00
175.00
160.00
185.00
185.00
175.00
160.00
175.00
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
A. GENERAL REQUIREMENTS
A.1 Mobilization/Demobilization
a. Mobilization
5 t/l @
b. Demobilization
5 t/l @
5,000.00
25,000.00
5,000.00
25,000.00
1,050,000.00
131,266.50
70.00
50.00
105,000.00
52,500.00
1,155.00
1,340,041.50
1,125,000.00
140,641.50
70.00
50.00
112,500.00
56,250.00
1,237.50
1,435,749.00
=
=
=
20%
A x 0.20 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011
=
=
d. Bid Bond 5%
Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
750,000.00
93,766.50
70.00
50.00
75,000.00
37,500.00
825.00
957,211.50
=
=
=
A x 0.05 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
262,500.00
32,829.00
70.00
50.00
26,250.00
Premium Tax
Municipality Tax
=
=
Premium x 0.05
Premium x 0.0011
=
=
P
13,125.00
288.75
335,112.75
1,875,000.00
234,391.50
70.00
50.00
187,500.00
93,750.00
2,062.50
2,392,824.00
87,500.00
10,954.00
70.00
50.00
8,750.00
4,375.00
96.25
111,795.25
A x 0.0025
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011
=
=
A = 20,000,000.00
f. Comprehensive General Liability Insurance 100%
Premium
= For 3 m = 10,000.00
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=
=
=
=
45.00 /sq.m.
2,462,877.90
b. Occupancy Permit
54,730.62 sq.m.
25.00 /sq.m.
1,368,265.50
750.00 /sq.m.
225,000.00
150.00 sq.m. @
500.00 /cu.m.
75,000.00
d. Temfacil Permit
40.00 sq.m. @
3,500.00
400.00 sq.m. @
36.00 sq.m. @
18.00 sq.m. @
500.00
500.00
10,000.00
5.00 rental/mo.
7,500.00
=
=
=
=
=
=
=
=
140,000.00
250,000.00
200,000.00
18,000.00
180,000.00
120,000.00
37,500.00
Thi
insu
ma
nat
T
in
p
a
a.
b.
c.
c.
Power Consumptions
Water Consumptions
Deepwell Construction
Telephone Bill
10,000.00
2,500.00
for
for
19.00 mos. =
19.00 mos. =
2,000.00
for
19.00 mos. =
180,000.00
54,000.00
30,000.00
108,000.00
for
for
for
for
16.00
8.00
8.00
4.00
mos.
mos.
mos.
mos.
190,000.00
47,500.00
100,000.00
38,000.00
=
=
=
=
2,880,000.00
432,000.00
240,000.00
432,000.00
B. SITEWORKS
Item 102-2
Grade Line Cut (Ord. Soil)
A. Equipment
1.00 - Bulldozer D80A-12, 180 HP
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1.00
5.00
2.00
3.00
B. Labor
C. Output
- Foreman
- Laborer
- Operator
- Driver
VAT, 10%
Sub-total
100.00 cu.m./hr.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
DIRECT UNIT COST
Item Backfilling
104-3
& Compaction
COST
24.125 lit.
10.00 lit.
27.75 lit.
=
=
=
117.38 liters
11.74 liters
=
P
P
45.91 /cu.m.
A. Equipment
3 - Dump Truck
1 - Road Roller
1 - Payloader
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
65.00 cu.m./hr.
27.75 lit.
14.00 lit.
2.28 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
99.53 liters
9.95 liters
T O TAL
COST
65.00
55.04
*****
DIRECT UNIT COST =
55.04 /cu.m.
Item 102-3
Excavation (Adobe)
A. Equipment
1.00 - Backhoe
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1.00 - Foreman
5.00 - Laborer
2.00 - Operator
B. Labor
3.00 - Driver
VAT, 10%
Sub-total
C. Output
60.00 cu.m./hr.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
COST
24.125 lit.
10.00 lit.
27.75 lit.
=
=
=
117.38 liters
11.74 liters
P
71.93 /cu.m.
TRIMMING
A. Labor
1.00 - Foreman
5.00 - Laborer
VAT, 10%
B. Output
2.00 sq.m./hr.
64.97 /sq.m.
Item Aggregate
200-1
Sub-Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
50.00 cu.m./hr.
8.00 lit.
14.00 lit.
5.44 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
27.44 liters
2.74 liters
COST
P
332.97 /cu.m.
Item Aggregate
201-1
Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
50.00 cu.m./hr.
8.00 lit.
14.00 lit.
5.44 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
27.44 liters
2.74 liters
COST
P
356.97 /cu.m.
Item Portland
311-2
Cement Concrete Pavement PCCP
0.15 mthick)
Assume Quantity
L
W
A
V
=
=
=
=
100.00
6.00
600.00
90.00
m.
m.
sq.m.
cu.m.
A. Materials:
a. Concrete Mix delivered @ jobsite
90.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12
6.00 in.
10.00 bft.
3.33
10.00
444.33
333.33
777.67
777.67
259.22 bft.
1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.
0.18
266.67
53.33
9.47
kgs.
pcs.
pcs.
kgs.
Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=
No. of blades = 133.33/350 =
Sub-total
133.33
0.38 blades
e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total
0.0040 m
467.33 m
1.88 cu.m.
0.44 MT
f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total
266.67
88.89
2.22 kgs.
g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost
21.43 gals.
- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost
220.00 /day
175.00
175.00
175.00
175.00
145.00
6.00
6.00
6.00
6.00
6.00
6.00
56.25 /day
60.00 /day
1,200.00 /day
4.00
4.00
1.00
C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
COST
P
496.31 /sq.m.
Item Portland
311-2
Cement Concrete Pavement PCCP
0.2 mthick)
Assume Quantity
L
W
A
V
=
=
=
=
100.00
6.00
600.00
120.00
m.
m.
sq.m.
cu.m.
A. Materials:
a. Concrete Mix delivered @ jobsite
120.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12
6.00 in.
10.00 bft.
3.33
10.00
444.33
333.33
777.67
777.67
259.22 bft.
1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.
0.18
266.67
53.33
9.47
kgs.
pcs.
pcs.
kgs.
133.33
0.38 blades
e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total
0.0040 m
467.33 m
1.88 cu.m.
0.44 MT
f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total
266.67
88.89
2.22 kgs.
g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost
21.43 gals.
- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost
220.00 /day
175.00
175.00
175.00
175.00
145.00
6.00
6.00
6.00
6.00
6.00
6.00
56.25 /day
60.00 /day
1,200.00 /day
4.00
4.00
1.00
C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
DIRECT UNIT COST =
COST
=
P
P
636.31 /sq.m.
ITEMConcrete
502
Curbs & Gutter
1.Materials:
a.Forms : 100 bft.(Good for 60.00 m)
b.C.W.Nails:20 kgs.(Good for 60.00 m)
c.Concrete Volume = (0.15x0.15)+(0.00x0.00)=0.025 cu.m.
Cement = 0.09 x 9 =
Sand = 0.09 x 0.50 =
Gravel = 0.09 x 1.00 =
Sub-total
1.67 @
0.33
24.00
24.00
0.81
0.05
0.09
225.00
600.00
950.00
A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total
50.00
1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total
27.50
21.875
18.125
2.Manpower:
1.05 liters
0.11 liters
10.00
45.00
20.00 lm./hr.
Direct Cost =
11.21 /lm.
1.Manpower:
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
2.Output =
27.500
21.875
18.125
11.00 lm./hr.
Direct Cost =
14.38 /lm.
45.00
60.00
2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total
27.50
21.88
18.13
3.00
1.05
4.05 liters
0.41 liters
Oil,10 % of fuel =
Sub-total
4.Output =
10.00
45.00
10.00 lm./hr.
Direct Cost =
ITEMConcrete
601
Sidewalk
Assume Quantity = 100.00 sq.m.
Thickness =
0.10 m
1.Materials:
a.Forms : 4 bft./sq.m. x 100/3
Used 3 times
b.C.W.Nails:0.02 kgs./bft.x4x100 =
Cement = 10.00 x 9 =
Sand = 10.00 x 0.45 =
Gravel = 10.00 x 0.90 =
Sub-total
33.24 /lm.
P
401.57 /lm.
Volume =
133.33 @
8.00
90.00
4.50
9.00
10.00
24.00
24.00
225.00
600.00
950.00
A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total
50.00 /day
1.00
220.00 /day
175.00
145.00
1.00
1.00
1.00
2.Manpower:
1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total
3.Fuel and Oil
Vibrator Plate =
Oil,10 % of fuel =
Sub-total
4.Output =
1.05 liters
0.11 liters
10.00
45.00
20.00 lm./hr.
Output =
60.00 sq.m./day
220.00 /day
175.00
145.00
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
C.Pouring and Finishing
1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total
1.75
1.75
1.75
45.00 /hr.
60.00
2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total
220.00 /day
175.00
145.00
1.75
1.75
1.75
3.00
1.05
4.05 liters
0.41 liters
10.00
45.00
404.83 /sq.m.
C. MASONRY WORKS
a. 6" CHB (750 psi) Load Bearing
a.Materials
12.50 pcs. 6" CHB (Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand
@
@
10.50
225.00
600.00
10.30
225.00
600.00
12.00
36.00
M=
@
@
7.80
225.00
600.00
12.00
36.00
M=
@
@
7.50
225.00
600.00
12.00
36.00
M=
@
@
10.50
225.00
600.00
12.00
36.00
M=
@
@
12.00
36.00
M=
225.00
130.00
120.00
600.00
135.00
600.00
M=
L=
150.00
30.00
M=
225.00
600.00
M=
225.00
600.00
M=
225.00
600.00
900.00
M=
225.00
600.00
900.00
M=
225.00
600.00
80.00
M=
FLOOR FINISHES
a. Patterned Cement Finish
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand
a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding
225.00
600.00
3.50
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles
225.00
90.00
M=
225.00
600.00
225.00
90.00
M=
225.00
600.00
3.50
225.00
45.00
M=
225.00
600.00
225.00
45.00
M=
225.00
600.00
45.00
3.50
225.00
90.00
M=
225.00
600.00
3.50
225.00
45.00
M=
225.00
600.00
225.00
14.00
30.00
45.00
M=
225.00
600.00
225.00
10.00
80.00
65.00
M=
225.00
600.00
225.00
14.00
30.00
45.00
M=
225.00
600.00
4,500.00
225.00
600.00
225.00
35.00
30.00
45.00
M=
28.00
550.00
24.00
550.00
225.00
600.00
11.00
M=
225.00
600.00
10.50
M=
225.00
30.00
600.00
10.50
M=
225.00
30.00
600.00
6.00
M=
225.00
30.00
600.00
14.00
M=
225.00
30.00
600.00
10.50
M=
225.00
30.00
600.00
75.00
M=
225.00
30.00
600.00
28.00
M=
225.00
30.00
600.00
150.00
M=
225.00
30.00
600.00
120.00
M=
225.00
600.00
900.00
225.00
600.00
900.00
225.00
600.00
900.00
225.00
600.00
900.00
225.00
600.00
950.00
225.00
600.00
900.00
225.00
600.00
45.00
M=
25.00
M=
WALL FINISHES
a. 300x300 Synthetic Granite
a.Materials
25.00
880.00
M=
50.28
880.00
M=
50.43
880.00
M=
0.450
0.250
0.027
12.000
bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs. 12"x12" Granite Tiles
Materials
bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs.4"x8"Wall Tiles
225.00
30.00
600.00
120.00
225.00
30.00
600.00
2.50
M=
225.00
30.00
600.00
10.50
M=
225.00
30.00
600.00
14.00
M=
225.00
30.00
600.00
28.00
M=
225.00
30.00
600.00
75.00
M=
2.50
1. Exterior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.424 bag Cement(Portland)
0.032 cu.m. Sand
2. Interior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.350 bag Cement(Portland)
0.027 cu.m. Sand
225.00
600.00
M=
225.00
600.00
M=
208.00
225.00
600.00
M=
225.00
600.00
M=
208.00
225.00
600.00
M=
225.00
600.00
M=
225.00
600.00
M=
225.00
600.00
M=
f. Plain Cement Plaster Finish (By LM) w = 0.60m.
a.Materials
0.294 bag Cement(Portland)
0.022 cu.m. Sand
225.00
600.00
M=
225.00
600.00
M=
225.00
600.00
3.50
225.00
90.00
M=
225.00
600.00
225.00
90.00
M=
CEILING FINISHES
a. 1/4"thk.Marine Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)
w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@
0.375 pcs. 1/4"x4'x8'Marine Plywood
0.400 kls. Assorted Nails
0.050 gal. Solignum
24.00
355.00
24.00
525.00
M=
24.00
600.00
24.00
525.00
M=
24.00
295.00
24.00
525.00
M=
24.00
296.00
24.00
525.00
M=
24.00
1,150.00
10.50
175.00
M=
225.00
600.00
M=
10.00
22.50
M=
300.00
20.00
M=
700.00
175.00
145.00
125.00
250.00
260.00
M=
295.00
175.00
145.00
125.00
300.00
250.00
260.00
M=
3,275.00
12.50
M=
770.00
5.50
137.50
M=
3,275.00
12.50
M=
770.00
5.50
137.50
M=
CONCRETE WORKS
a. Lintel Beams (For 6" CHB)
a. Materials
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
b. Labor
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
3,275.00
12.50
M=
b. Labor
0.0250 cu.m. Concrete
2.0000 kg. Rebars
0.3000 sq.m. Formworks
770.00
5.50
137.50
M=
3,275.00
12.50
M=
770.00
5.50
137.50
M=
275.00
18.125
275.00
18.125
250.00
120.00
Equipment Cost
10% VAT
20.63
b. Labor
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks
Production
Unit Cost
=
=
b. Forms
1 ELF
10 Laborers
20,000.00 kgs./day
P
Production
Unit Cost
=
=
Demolition Works
a. Equipment (Demolition)
1.00 Compressor
2.00 Jackhammer
12.00 hrs./day
12.00
0.30 /kg.
12.00 hrs./day
12.00
750.00 sq.m./day
7.88 /sq.m.
b. Manpower
20.00 Laborers
Labor Cost
10% VAT
Total Cost / hr.
Duration =
c. Equipment (Hauling & Disposal)
1.00 Loader
2.00 Dump Truck
Duration =
700.00
500.00
Equipment Cost
10% VAT
6 hrs. for 6 days
Total Cost =
1 Dumptruck
10 Laborers
8.00 hrs./day
8.00
450.00
18.125
1.00 hr.
Unit Cost
Item SP - 6 G.I. Sheet Temporary Fence (H = 3.00m)
a. Materials
20.00 bft. Coco Lumber
15.00 lft. Ga. # 26 Pre-painted Corrugated GI Sheets
0.015 kegs CW Nails
0.10 kgs. Roof Nails
50.00
15.00
20.00
=
6.00
40.00
950.00
85.00
Unit Cost =
26.00
525.00
75.00
475.00
45.00
25
Unit Cost (M & L) =
945.00 sq.m.
1.50
12.50
45.00
65.00
12.00 pcs.
0.06 gal.
Installation
Polishing
12.00 tiles
12.00 tiles
3.28 ln.ft.
1.00 lot
23.00
525.00
Materials
3.50
2.40
Sub Total
VAT
Labor
26.50
3.08
Materials
Labor
P
P
Cement
Sand
0.70 bags
0.06 cu.m.
12.50
1.05
0.09
2.50
0.04
12.50
0.54
0.04
2.50
0.04
pcs.
bags
cu.m.
kgs.
kgs.
pcs.
bags
cu.m.
kgs.
kgs.
125.00
300.00
Materials
Labor
P
P
7.50
125.00
300.00
12.20
30.20
Materials
Labor
P
P
7.30
125.00
300.00
12.20
30.20
Materials
Labor
P
P
125.00
300.00
80.00
148.00
Materials
Labor
P
P
125.00
300.00
80.00
Materials
Labor
P
P
C. Exterior Plastering
Cement
Sand
ME 602 Mortar Enhancer
Sealopruf Integral Waterproofing
0.50
0.06
0.13
0.05
bags
cu.m.
liters
gal
D. Interior Plastering
Cement
Sand
ME 602 Mortar Enhancer
0.30 bags
0.03 cu.m.
0.08 liters
C.MATERIALS
50,000.00
4,179,910.00
0.5573%
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
45.
46.
47.
Premium Fuel
Diesel
Lubricating Oil
Gravel Fill
Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
CW Nails
Cement
Gravel
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)
4,131,143.40
945,500.00
375,500.00
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.
98.
99.
100.
3,984,000.00
A.EQUIPMENTS:
1,000.00 =
500.00 =
400.00 =
=
=
27.50
18.13
21.88
20.00
=
=
=
=
=
1,000.00
500.00
1,200.00
24.41
272.44
2,996.85 /hr.
27.50
90.63
43.75
60.00
22.19
244.06 /hr.
24.125
10.00
83.25
117.38 liters
7.00 =
45.00 =
4,590.72 /hr.
821.63
528.19
1,349.81 /hr.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Foreman
Leadman
Timekeeper
Carpenter
Mason
Steelman
Laborer
Floater
Mixer Operator
Painter
Welder
HE Operator
Driver
Screeder Operator
400.00 =
350.00 =
500.00 =
=
=
27.50
18.13
21.88
20.00
=
=
=
=
=
1,200.00
350.00
500.00
16.02
206.60
2,272.62 /hr.
27.50
54.38
43.75
20.00
14.56
160.19 /hr.
83.25
14.00
2.28
99.53 liters
7.00 =
45.00 =
696.71
447.89
1,144.60 /hr.
3,577.40 /hr.
/CU.M.
/CU.M.
750.00 =
500.00 =
400.00 =
=
=
750.00
500.00
1,200.00
24.41
247.44
2,721.85 /hr.
27.50 =
18.13 =
21.88 =
27.50
90.63
43.75
20.00 =
=
60.00
22.19
244.06 /hr.
24.125
10.00
83.25
117.38 liters
7.00 =
45.00 =
821.63
528.19
1,349.81 /hr.
4,315.72 /hr.
27.50 =
18.13 =
=
27.50
90.63
11.81
129.94 /hr.
400.00 =
350.00 =
300.00 =
=
=
400.00
350.00
300.00
16.02
106.60
1,172.62 /hr.
27.50
18.13
21.88
20.00
=
=
=
=
=
27.50
54.38
43.75
20.00
14.56
160.19 /hr.
8.00
14.00
5.44
27.44 liters
7.00 =
45.00 =
192.08
123.48
315.56 /hr.
250.00 =
15,000.00
15,000.00 /hr.
16,648.37 /hr.
400.00 =
350.00 =
300.00 =
=
=
27.50
18.13
21.88
20.00
=
=
=
=
=
400.00
350.00
300.00
16.02
106.60
1,172.62 /hr.
27.50
54.38
43.75
20.00
14.56
160.19 /hr.
8.00
14.00
5.44
27.44 liters
7.00 =
45.00 =
192.08
123.48
315.56 /hr.
270.00 =
16,200.00
16,200.00 /hr.
17,848.37 /hr.
2,800.00
252,000.00
252,000.00
24.00 =
6,221.33
6,221.33
12.00 =
2,035.20
12.00 =
113.66
2,148.86
m.
days
day
day
day
10,400.00 =
3,961.90
3,961.90
13,500.00 =
5,976.45
5,976.45
24.00 =
53.33
53.33
40.00 =
857.14
857.14
P 271,219.03
452.03
1,320.00
2,100.00
2,100.00
4,200.00
5,250.00
6,090.00
2,106.00
23,166.00
23,166.00
38.61
450.00
240.00
2,400.00
309.00
3,399.00
3,399.00
5.67
=
=
=
=
=
=
=
=
=
=
=
297,784.03
2,800.00
m.
336,000.00
336,000.00
24.00 =
6,221.33
6,221.33
12.00 =
2,035.20
12.00 =
113.66
2,148.86
10,400.00 =
3,961.90
3,961.90
13,500.00 =
5,976.45
5,976.45
24.00 =
53.33
53.33
40.00 =
857.14
857.14
P 355,219.03
592.03
1,320.00
2,100.00
2,100.00
4,200.00
5,250.00
6,090.00
2,106.00
23,166.00
23,166.00
38.61
450.00
240.00
2,400.00
309.00
3,399.00
3,399.00
5.67
days
=
=
=
=
=
=
=
day
day
day
=
=
=
=
381,784.03
=
=
40.00
8.00
=
=
=
P
182.25
27.00
85.50
342.75
=
=
P
50.00
5.00
55.00
=
=
=
=
27.50
21.88
90.63
14.00
154.00
=
=
P
10.50
4.73
15.23
=
=
=
=
P
27.50
43.75
72.50
14.38
158.13
=
=
=
P
45.00
60.00
10.50
115.50
=
=
=
=
P
27.50
43.75
72.50
14.38
158.13
=
=
P
40.50
18.23
58.73
cu.m.
=
3,200.00
=
=
=
=
P
192.00
20,250.00
2,700.00
8,550.00
34,892.00
348.92
day
=
=
P
50.00
5.00
55.00
day
=
=
=
220.00
175.00
725.00
days
days
days
days
days
days
=
=
=
=
P
0.00
1,120.00
=
=
P
10.50
4.73
15.23
=
=
=
=
P
385.00
612.50
1,015.00
201.25
2,213.75
=
=
=
P
45.00
60.00
10.50
115.50
=
=
=
=
P
385.00
612.50
1,015.00
0.00
2,012.50
=
=
P
40.50
18.23
58.73
131.25
229.50
54.57
=
=
P
36.00
1.80
453.12 /sq.m.
=
=
=
=
=
P
128.75
121.50
28.89
36.00
1.80
316.94 /sq.m.
=
=
=
=
=
P
97.50
229.50
54.57
36.00
1.80
419.37 /sq.m.
=
=
=
=
=
P
93.75
121.50
28.89
36.00
1.80
281.94 /sq.m.
=
=
=
=
=
P
252.00
110.25
22.20
27.00
1.26
412.71 /sq.m.
=
=
=
=
=
=
P
P
1,800.00
520.00
480.00
408.16
94.50
600.00
3,902.66 /cu.m.
770.00 /cu.m.
=
=
P
3,750.00
375.00
4,125.00 /cu.m.
=
=
P
157.50
32.10
189.60 /sq.m.
=
=
P
126.00
25.68
151.68 /sq.m.
=
=
=
P
126.00
25.68
90.00
241.68 /sq.m.
=
=
=
P
31.50
6.42
90.00
127.92 /sq.m.
=
=
=
P
126.00
25.68
20.00
171.68 /sq.m.
=
=
=
110.25
22.47
10.50
=
=
P
140.63
112.50
396.35 /sq.m.
=
=
33.08
6.74
=
=
P
42.19
33.75
115.75 /lm.
=
=
=
110.25
22.47
10.50
=
=
P
140.63
56.25
340.10 /sq.m.
=
=
33.08
6.74
=
=
P
42.19
16.88
98.88 /lm.
=
=
=
=
157.50
32.10
45.00
10.50
140.63
=
P
112.50
498.23 /sq.m.
=
=
=
37.80
7.70
5.74
=
=
P
7.03
2.81
61.09 /lm.
=
=
126.00
25.68
=
=
=
=
P
140.63
56.00
3.00
56.25
407.56 /lm.
=
=
126.00
25.68
=
=
=
=
P
49.22
120.00
20.00
28.44
369.34 /lm.
=
=
126.00
25.68
=
=
=
=
P
33.75
126.00
11.25
13.50
336.18 /lm.
=
=
=
=
P
P
110.25
22.47
4,500.00
450.00
5,082.72 /lm.
220.00 /lm.
=
=
126.00
25.68
=
=
=
=
P
33.75
315.00
11.25
13.50
525.18 /lm.
=
=
P
336.00
33.00
369.00 /sq.m.
=
=
P
288.00
33.00
321.00 /sq.m.
=
=
=
P
126.00
25.68
275.00
426.68 /sq.m.
=
=
=
P
110.25
22.47
420.00
552.72 /sq.m.
110.25
=
=
=
P
15.00
22.47
472.50
620.22 /sq.m.
=
=
=
=
P
110.25
15.00
22.47
540.00
687.72 /sq.m.
=
=
=
=
P
110.25
15.00
22.47
350.00
497.72 /sq.m.
=
=
=
=
P
110.25
15.00
22.47
525.00
672.72 /sq.m.
=
=
=
=
P
110.25
15.00
22.47
375.00
522.72 /sq.m.
=
=
=
=
P
110.25
15.00
22.47
336.00
483.72 /sq.m.
=
=
=
110.25
15.00
22.47
=
P
1,800.00
1,947.72 /sq.m.
=
=
=
=
P
110.25
15.00
22.47
1,440.00
1,587.72 /sq.m.
=
=
=
=
P
P
66.15
13.48
540.00
54.00
673.63 /lm.
200.00 /lm.
=
=
=
=
P
P
38.59
7.86
315.00
31.50
392.95 /lm.
185.00 /lm.
=
=
=
=
P
P
22.05
4.49
180.00
18.00
224.54 /lm.
185.00 /lm.
=
=
=
=
P
P
16.54
3.37
135.00
13.50
168.41 /lm.
185.00 /lm.
110.25
=
=
=
P
P
22.47
950.00
95.00
1,177.72 /lm.
185.00 /lm.
=
=
=
=
P
P
33.08
6.74
270.00
27.00
336.82 /lm.
185.00 /lm.
=
=
=
P
157.50
32.10
45.00
234.60 /sq.m.
=
=
P
300.00
30.00
330.00 /sq.m.
=
=
P
82.00
70.94
152.94 /lm.
=
=
P
164.93
106.41
271.33 /lm.
=
=
P
165.42
141.87
307.29 /lm.
=
=
=
=
P
101.25
7.50
16.05
1,440.00
1,564.80 /lm.
=
=
=
=
P
101.25
7.50
16.05
225.00
349.80 /sq.m.
=
=
=
=
P
101.25
7.50
16.05
525.00
649.80 /sq.m.
=
=
=
=
P
101.25
7.50
16.05
350.00
474.80 /sq.m.
=
=
=
=
P
101.25
7.50
16.05
336.00
460.80 /sq.m.
=
=
=
=
P
101.25
7.50
16.05
375.00
499.80 /sq.m.
242.50
=
=
P
95.29
19.42
357.21 /sq.m.
=
=
P
95.29
19.42
114.71 /sq.m.
=
=
=
P
31.20
112.61
22.95
166.76 /sq.m.
=
=
P
78.75
16.05
94.80 /sq.m.
=
=
=
P
31.20
94.50
19.26
144.96 /sq.m.
=
=
P
55.13
11.24
66.36 /lm.
=
=
P
33.08
6.74
39.82 /lm.
=
=
16.54
3.37
19.91 /lm.
=
=
P
66.15
13.48
79.63 /lm.
=
=
P
12.15
2.40
14.55 /lm.
=
=
=
78.75
16.05
10.50
=
=
P
=
=
140.63
112.50
358.43 /sq.m.
23.63
4.82
=
=
P
42.19
33.75
104.38 /lm.
=
=
=
=
P
300.00
133.13
9.60
26.25
468.98 /sq.m.
300.00
=
=
=
P
225.00
9.60
26.25
560.85 /sq.m.
=
=
=
=
P
240.00
110.63
9.60
26.25
386.48 /sq.m.
=
=
=
=
P
240.00
111.00
9.60
26.25
386.85 /sq.m.
=
=
=
=
P
240.00
431.25
4.20
8.75
684.20 /sq.m.
=
=
P
3.15
0.64
3.79 /sq.m.
=
=
P
135.00
258.75
393.75 /sq.m.
=
=
P
4,050.00
230.00
4,280.00 /sq.m.
=
=
=
=
=
=
P
262.50
21.00
29.00
18.75
10.00
26.00
367.25 /sq.m.
=
=
=
=
=
=
=
P
110.63
21.00
29.00
18.75
3.75
10.00
26.00
219.13 /sq.m.
=
=
=
P
122.81
40.00
162.81 /l.m.
=
=
=
P
28.88
17.60
89.38
135.85 /l.m.
=
=
=
P
114.63
41.25
155.88 /l.m.
=
=
=
P
26.95
18.15
110.00
155.10 /l.m.
81.88
=
=
P
25.00
106.88 /l.m.
=
=
=
P
19.25
11.00
41.25
71.50 /l.m.
=
=
=
P
98.25
25.00
123.25 /l.m.
=
=
=
P
23.10
11.00
82.50
116.60 /l.m.
3,300.00
2,610.00
5,910.00
3,300.00
2,610.00
5,910.00
/hr.
/hr.
250.00
240.00
490.00
49.00
539.00 /hr.
/hr.
412.50
412.50
41.25
453.75
992.75 /hr.
180.00 hours
178,695.00
/hr.
/hr.
700.00
1,000.00
1,700.00
170.00
1,870.00 /hr.
36.00
67,320.00
246,015.00
3,600.00
1,740.00
5,340.00
427,200.00
/hr.
/hr.
/hr.
=
=
=
50.00
15.00
20.00
85.00 /hr./pump
=
=
=
=
120.00
600.00
14.25
8.50
742.75 /lm.
=
=
=
=
=
=
=
ost (M & L) =
780.00
1,050.00
450.00
118.75
45.00
50.00
997.50
3,491.25 /lm.
say
=
=
=
=
=
3,500.00 /lm.
12.75
11,875.00
1,125.00
2,145.00
7,578.88
22,736.63
24.06
25.00 /sq.m.
ost (M & L) =
=
=
=
=
=
=
=
233.33
604.17
308.00
62.50
168.75
36.00
154.00
1,566.75 /sq.m.
783.38 /sq.m.
276.00
31.50
307.50
42.00
28.80
70.80
7.08
77.88
86.92
3.08
90.00
22.00
87.50
16.50
104.00
104.00
93.75
131.25
27.00
30.50
1.21
283.71
110.00
91.25
67.50
12.00
30.50
1.21
202.46
104.00
62.50
16.50
10.00
7.40
96.40
139.00
37.50
9.90
6.00
53.40
115.50
UNIT COST
Premium Fuel
Lubricating Oil
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)
10.00
7.00
45.00
440.00
150.00
250.00
270.00
2,800.00
24.00
12.00
40.00
13,500.00
10,400.00
24.00
225.00
950.00
500.00
600.00
355.00
375.00
38.00
17.50
10.50
10.30
7.80
7.50
80.00
900.00
10.50
6.00
35.00
28.00
10.50
14.00
75.00
150.00
4,500.00
11.00
120.00
10.50
14.00
2.50
28.00
75.00
4.00
25.00
6.00
28.00
/lit.
/lit.
/lit.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bft.
/kg.
/gal.
/MT
/pc.
/kl.
/bag
/cu.m.
/cu.m.
/cu.m.
/pc.
/pc.
/bft.
/pc.
/pc.
/pc.
/pc.
/pc.
/kl.
/kl.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
24.00
90.00
80.00
950.00
900.00
30.00
10.50
90.00
90.00
45.00
45.00
65.00
24.00
10.50
525.00
550.00
36.00
3.50
10.00
300.00
295.00
296.00
1,150.00
175.00
145.00
125.00
300.00
250.00
260.00
700.00
23.00
30.00
25.00
45.00
25.00
1,500.00
3,017.00
3,026.00
880.00
130.00
135.00
600.00
120.00
150.00
10.00
60.00
1,300.00
1,100.00
2.50
/pc.
/pc.
/pc.
/sq.m.
/sq.m.
/kl.
/pc.
/can
/can
/can
/can
/can
/kl.
/pc.
/gal.
/gal.
/kl.
/lft.
/lft.
/cu.m.
/pc
/pc
/pc
/pc
/pc
/pc
/roll
/gal.
/gross
/pc.
/lft.
/lft.
/pc.
/sq.m.
/pc.
/pc.
/pc.
/pc.
/liter
/bag
/gal.
/bag
/bag
/pc.
/pc.
/sq.ft.
/sq.m.
/pc.
/pc.
275.00 /bag
38pcs./sq.m.
Labor
25.00 /sq.ft.
80.00 /sq.m.
RENTALS
Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump
Concrete Cutter
1-Bagger Mixer
Concrete Breaker
1,000.00
500.00
400.00
400.00
350.00
300.00
300.00
20.00
50.00
20.00
56.25
60.00
1,200.00
45.00
20.00
75.00
900.00
750.00
500.00
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
DAILY RATES
Timekeeper
Mixer Operator
HE Operator
Screeder Operator
220.00
200.00
150.00
175.00
175.00
185.00
145.00
175.00
160.00
185.00
185.00
175.00
160.00
175.00
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
A. GENERAL REQUIREMENTS
A.1 Mobilization/Demobilization
a. Mobilization
5 t/l @
b. Demobilization
5 t/l @
5,000.00
25,000.00
5,000.00
25,000.00
1,050,000.00
131,266.50
70.00
50.00
105,000.00
52,500.00
1,155.00
1,340,041.50
1,125,000.00
140,641.50
70.00
50.00
112,500.00
56,250.00
1,237.50
1,435,749.00
=
=
=
20%
A x 0.20 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011
=
=
d. Bid Bond 5%
Premium
=
Documentary Stamp =
Notarial Fee
=
Service Fee
=
EVAT
=
750,000.00
93,766.50
70.00
50.00
75,000.00
37,500.00
825.00
957,211.50
=
=
=
A x 0.05 x 0.007
=
Premium x 0.125 + 16.50 =
=
=
=
262,500.00
32,829.00
70.00
50.00
26,250.00
Premium Tax
Municipality Tax
=
=
Premium x 0.05
Premium x 0.0011
=
=
P
13,125.00
288.75
335,112.75
1,875,000.00
234,391.50
70.00
50.00
187,500.00
93,750.00
2,062.50
2,392,824.00
87,500.00
10,954.00
70.00
50.00
8,750.00
4,375.00
96.25
111,795.25
A x 0.0025
=
Premium x 0.125 + 16.50 =
=
=
=
Premium x 0.05
Premium x 0.0011
=
=
A = 20,000,000.00
f. Comprehensive General Liability Insurance 100%
Premium
= For 3 m = 10,000.00
Documentary Stamp =
Premium x 0.125 + 16.50 =
Notarial Fee
=
Service Fee
=
EVAT
=
Premium Tax
=
Premium x 0.05
=
Municipality Tax
=
Premium x 0.0011
=
=
=
=
45.00 /sq.m.
2,462,877.90
b. Occupancy Permit
54,730.62 sq.m.
25.00 /sq.m.
1,368,265.50
750.00 /sq.m.
225,000.00
150.00 sq.m. @
500.00 /cu.m.
75,000.00
d. Temfacil Permit
40.00 sq.m. @
3,500.00
400.00 sq.m. @
36.00 sq.m. @
18.00 sq.m. @
500.00
500.00
10,000.00
5.00 rental/mo.
7,500.00
=
=
=
=
=
=
=
=
140,000.00
250,000.00
200,000.00
18,000.00
180,000.00
120,000.00
37,500.00
Thi
insu
ma
nat
T
in
p
a
a.
b.
c.
c.
Power Consumptions
Water Consumptions
Deepwell Construction
Telephone Bill
10,000.00
2,500.00
for
for
19.00 mos. =
19.00 mos. =
2,000.00
for
19.00 mos. =
180,000.00
54,000.00
30,000.00
108,000.00
for
for
for
for
16.00
8.00
8.00
4.00
mos.
mos.
mos.
mos.
190,000.00
47,500.00
100,000.00
38,000.00
=
=
=
=
2,880,000.00
432,000.00
240,000.00
432,000.00
B. SITEWORKS
Item 102-2
Grade Line Cut (Ord. Soil)
A. Equipment
1.00 - Bulldozer D80A-12, 180 HP
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1.00
5.00
2.00
3.00
B. Labor
C. Output
- Foreman
- Laborer
- Operator
- Driver
VAT, 10%
Sub-total
100.00 cu.m./hr.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
DIRECT UNIT COST
Item Backfilling
104-3
& Compaction
COST
24.125 lit.
10.00 lit.
27.75 lit.
=
=
=
117.38 liters
11.74 liters
=
P
P
86.68 /cu.m.
A. Equipment
3 - Dump Truck
1 - Road Roller
1 - Payloader
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
65.00 cu.m./hr.
27.75 lit.
14.00 lit.
2.28 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
99.53 liters
9.95 liters
T O TAL
COST
65.00
107.60
*****
DIRECT UNIT COST =
107.60 /cu.m.
Item 102-3
Excavation (Adobe)
A. Equipment
1.00 - Backhoe
1.00 - Payloader
3.00 - Dumptruck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1.00 - Foreman
5.00 - Laborer
2.00 - Operator
B. Labor
3.00 - Driver
VAT, 10%
Sub-total
C. Output
60.00 cu.m./hr.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
T O TAL
COST
24.125 lit.
10.00 lit.
27.75 lit.
=
=
=
117.38 liters
11.74 liters
P
139.88 /cu.m.
TRIMMING
A. Labor
1.00 - Foreman
5.00 - Laborer
VAT, 10%
B. Output
2.00 sq.m./hr.
116.88 /sq.m.
Item Aggregate
200-1
Sub-Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
50.00 cu.m./hr.
8.00 lit.
14.00 lit.
5.44 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
27.44 liters
2.74 liters
COST
P
593.72 /cu.m.
Item Aggregate
201-1
Base Coarse
A. Equipment
1 - Road Grader
1 - Road Roller
1 - Water Truck
Minor Tools, 10% of labor
VAT, 10%
Sub-total
1 - Foreman
3 - Laborer
2 - Operator
1 - Driver
VAT, 10%
Sub-total
B. Labor
C. Output
50.00 cu.m./hr.
8.00 lit.
14.00 lit.
5.44 lit.
=
=
=
Fuel
=
Oil, 10% of Fuel =
Sub-total
27.44 liters
2.74 liters
COST
P
953.72 /cu.m.
Item Portland
311-2
Cement Concrete Pavement PCCP
0.15 mthick)
Assume Quantity
L
W
A
V
=
=
=
=
100.00
6.00
600.00
90.00
m.
m.
sq.m.
cu.m.
A. Materials:
a. Concrete Mix delivered @ jobsite
90.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12
6.00 in.
10.00 bft.
3.33
10.00
444.33
333.33
777.67
777.67
259.22 bft.
1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.
0.18
266.67
53.33
9.47
kgs.
pcs.
pcs.
kgs.
Ave.rate of usage =
350.00 m/blade
For 4.50 m interval (1/4" width)
Total length to be sewed =(100/4.5)x10=
No. of blades = 133.33/350 =
Sub-total
133.33
0.38 blades
e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total
0.0040 m
467.33 m
1.88 cu.m.
0.44 MT
f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total
266.67
88.89
2.22 kgs.
g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost
21.43 gals.
- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost
350.00 /day
270.00
270.00
300.00
300.00
270.00
6.00
6.00
6.00
6.00
6.00
6.00
56.25 /day
60.00 /day
1,200.00 /day
4.00
4.00
1.00
C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
COST
P
523.02 /sq.m.
Item Portland
311-2
Cement Concrete Pavement PCCP
0.2 mthick)
Assume Quantity
L
W
A
V
=
=
=
=
100.00
6.00
600.00
120.00
m.
m.
sq.m.
cu.m.
A. Materials:
a. Concrete Mix delivered @ jobsite
120.00 cu.m. Agg. Portion for 525 psi Ready Mixed Concrete
Sub-total
b.Form Lumber
i.Center Form = (2"x6"x10')/12
ii.Key = (2"x2"x10')/12
iii.Side Form = (2"x6"x10')/12
6.00 in.
10.00 bft.
3.33
10.00
444.33
333.33
777.67
777.67
259.22 bft.
1.20 kgs.
133.33 pcs.
8.00 pcs.
141.33 pcs.
169.60 kgs.
0.18
266.67
53.33
9.47
kgs.
pcs.
pcs.
kgs.
133.33
0.38 blades
e.Asphalt Sealer
Width = 1/4" , Depth = 2-1/2"
Area = 0.00635 x 0.635 =
Total length to be filled w/ sealer=
(100/4.5)x6.00 + 334.00 =
Volume = 0.004 x 467.33 =
Q = 0.19 x 2.33 MT
=
Sub-total
0.0040 m
467.33 m
1.88 cu.m.
0.44 MT
f. C.W.Nails
2 pcs./pin
No.of pins = 100/0.75 x 2 =
For 3 times usage = 266.67/3 =
No.of kgs. = 88.89/40 =
Sub-total
266.67
88.89
2.22 kgs.
g.Curing Compound
Rate of application = 28.00 sq.m./gal.
No.of gals.=600.00/28.00 =
Sub-total
Total Material Cost
21.43 gals.
- Foreman
- Floaters
- Screeder Operator
- Masons
- Carpenters
- Laborers
VAT, 10%
Sub-total
Total Labor Cost
350.00 /day
270.00
270.00
300.00
300.00
270.00
6.00
6.00
6.00
6.00
6.00
6.00
56.25 /day
60.00 /day
1,200.00 /day
4.00
4.00
1.00
C. Equipment:
2.00 - Conc.Screeder
1.00 - Conc.Vibrator
2.00 - Conc.Cutter
VAT, 10%
Sub-total
Total Equipment Cost
T O TAL
DIRECT UNIT COST =
COST
=
P
P
656.27 /sq.m.
ITEMConcrete
502
Curbs & Gutter
1.Materials:
a.Forms : 100 bft.(Good for 60.00 m)
b.C.W.Nails:20 kgs.(Good for 60.00 m)
c.Concrete Volume = (0.15x0.15)+(0.00x0.00)=0.025 cu.m.
Cement = 0.09 x 9 =
Sand = 0.09 x 0.50 =
Gravel = 0.09 x 1.00 =
Sub-total
1.67 @
0.33
52.00
24.00
0.81
0.05
0.09
210.00
200.00
900.00
A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total
50.00
1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total
43.75
37.5
33.75
2.Manpower:
1.05 liters
0.11 liters
55.00
45.00
20.00 lm./hr.
Direct Cost =
19.62 /lm.
1.Manpower:
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
2.Output =
43.750
37.500
33.750
11.00 lm./hr.
Direct Cost =
25.38 /lm.
45.00
60.00
2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total
43.75
37.50
33.75
3.00
1.05
4.05 liters
0.41 liters
Oil,10 % of fuel =
Sub-total
4.Output =
55.00
45.00
10.00 lm./hr.
Direct Cost =
ITEMConcrete
601
Sidewalk
Assume Quantity = 100.00 sq.m.
Thickness =
0.10 m
1.Materials:
a.Forms : 4 bft./sq.m. x 100/3
Used 3 times
b.C.W.Nails:0.02 kgs./bft.x4x100 =
Cement = 10.00 x 9 =
Sand = 10.00 x 0.45 =
Gravel = 10.00 x 0.90 =
Sub-total
63.56 /lm.
P
463.33 /lm.
Volume =
133.33 @
8.00
90.00
4.50
9.00
10.00
52.00
24.00
210.00
200.00
900.00
A.Base Preparation
1.Equipment:
1.00 Plate Compactor
VAT, 10%
Sub-total
50.00 /day
1.00
350.00 /day
300.00
270.00
1.00
1.00
1.00
2.Manpower:
1.00 Foreman
1.00 Operator
5.00 Laborers
VAT, 10%
Sub-total
3.Fuel and Oil
Vibrator Plate =
Oil,10 % of fuel =
Sub-total
4.Output =
1.05 liters
0.11 liters
55.00
45.00
20.00 lm./hr.
Output =
60.00 sq.m./day
350.00 /day
300.00
270.00
1.00 Foreman
2.00 Carpenters
4.00 Laborers
VAT, 10%
Sub-total
C.Pouring and Finishing
1.Equipment:
1.00 1-Bagger Mixer
1.00 Concrete Vibrator
VAT, 10%
Sub-total
1.75
1.75
1.75
45.00 /hr.
60.00
2.Manpower:
1.00 Foreman
2.00 Masons
4.00 Laborers
VAT, 10%
Sub-total
350.00 /day
300.00
270.00
1.75
1.75
1.75
3.00
1.05
4.05 liters
0.41 liters
55.00
45.00
449.60 /sq.m.
C. MASONRY WORKS
a. 6" CHB (750 psi) Load Bearing
a.Materials
12.50 pcs. 6" CHB (Load Bearing)
1.02 bags Cement
0.09 cu.m. Sand
@
@
21.50
210.00
200.00
19.50
210.00
200.00
36.30
36.00
M=
@
@
10.00
210.00
300.00
33.00
36.00
M=
@
@
8.00
210.00
300.00
33.00
36.00
M=
@
@
10.50
210.00
200.00
36.30
36.00
M=
@
@
36.30
36.00
M=
210.00
130.00
120.00
200.00
135.00
600.00
M=
L=
150.00
60.00
M=
210.00
200.00
M=
210.00
200.00
M=
210.00
200.00
900.00
M=
210.00
200.00
900.00
M=
210.00
200.00
80.00
M=
FLOOR FINISHES
a. Patterned Cement Finish
a.Materials
0.700 bag Cement(Portland)
0.054 cu.m. Sand
a.Materials
i.Scratch Coat
0.490 bag Cement(Portland)
0.037 cu.m. Sand
3.000 lft.kd Tang.moulding
210.00
200.00
3.50
ii.Final Coat
0.625 bag Cement(Portland)
1.250 cans #10 Beige Pebbles
210.00
90.00
M=
210.00
200.00
210.00
90.00
M=
210.00
200.00
3.50
210.00
45.00
M=
210.00
200.00
210.00
45.00
M=
210.00
200.00
45.00
3.50
210.00
90.00
M=
210.00
200.00
3.50
210.00
45.00
M=
210.00
200.00
210.00
14.00
60.00
45.00
M=
210.00
200.00
210.00
10.00
80.00
65.00
M=
210.00
200.00
210.00
14.00
60.00
45.00
M=
210.00
200.00
4,500.00
210.00
200.00
210.00
35.00
60.00
45.00
M=
28.00
550.00
24.00
550.00
210.00
200.00
12.50
M=
210.00
200.00
10.50
M=
210.00
60.00
200.00
10.50
M=
210.00
60.00
200.00
6.00
M=
210.00
60.00
200.00
14.00
M=
210.00
60.00
200.00
10.50
M=
210.00
60.00
200.00
75.00
M=
210.00
60.00
200.00
28.00
M=
210.00
60.00
200.00
150.00
M=
210.00
60.00
200.00
120.00
M=
210.00
200.00
900.00
210.00
200.00
900.00
210.00
200.00
900.00
210.00
200.00
900.00
210.00
200.00
950.00
210.00
200.00
900.00
210.00
200.00
45.00
M=
25.00
M=
WALL FINISHES
a. 300x300 Synthetic Granite
a.Materials
25.00
880.00
M=
50.28
880.00
M=
50.43
880.00
M=
0.450
0.250
0.027
12.000
bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs. 12"x12" Granite Tiles
Materials
bag Cement(Portland)
kls. ABC Grout
cu.m. Sand
pcs.4"x8"Wall Tiles
210.00
60.00
200.00
120.00
210.00
60.00
200.00
2.50
M=
210.00
60.00
200.00
10.50
M=
210.00
60.00
200.00
14.00
M=
210.00
60.00
200.00
28.50
M=
210.00
60.00
200.00
75.00
M=
2.50
1. Exterior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.424 bag Cement(Portland)
0.032 cu.m. Sand
2. Interior Plastering
a. Plain Cement Plaster Finish (By Area)CHB Walls
a.Materials
0.350 bag Cement(Portland)
0.027 cu.m. Sand
210.00
200.00
M=
205.00
240.00
M=
208.00
210.00
200.00
M=
210.00
200.00
M=
208.00
210.00
200.00
M=
210.00
200.00
M=
210.00
200.00
M=
210.00
200.00
M=
f. Plain Cement Plaster Finish (By LM) w = 0.60m.
a.Materials
0.294 bag Cement(Portland)
0.022 cu.m. Sand
210.00
200.00
M=
210.00
200.00
M=
210.00
200.00
3.50
210.00
90.00
M=
210.00
200.00
210.00
90.00
M=
CEILING FINISHES
a. 1/4"thk.Marine Plywood Ceiling (2"x2"@ 0.40moc EW Ceiling Joists)
w/ Ceiling Truss 2"x4" Top Chord & Bottom Chord & 2"x3"Webs w/ a height of 2'
a. Materials
12.500 bd.ft. Rough Tanguile
@
0.375 pcs. 1/4"x4'x8'Marine Plywood
0.400 kls. Assorted Nails
0.050 gal. Solignum
52.00
355.00
24.00
525.00
M=
52.00
200.00
24.00
525.00
M=
52.00
295.00
24.00
525.00
M=
52.00
296.00
24.00
525.00
M=
52.00
1,150.00
21.50
175.00
M=
210.00
200.00
M=
10.00
22.50
M=
300.00
20.00
M=
700.00
175.00
145.00
125.00
250.00
260.00
M=
295.00
175.00
145.00
125.00
300.00
250.00
260.00
M=
2,890.00
36.80
250.00
M=
770.00
5.50
137.50
M=
2,890.00
36.80
250.00
M=
770.00
5.50
137.50
M=
CONCRETE WORKS
a. Lintel Beams (For 6" CHB)
a. Materials
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
b. Labor
0.0375 cu.m. Concrete
3.2000 kg. Rebars
0.6500 sq.m. Formworks
2,890.00
36.80
M=
b. Labor
0.0250 cu.m. Concrete
2.0000 kg. Rebars
0.3000 sq.m. Formworks
770.00
5.50
137.50
M=
2,890.00
36.80
M=
770.00
5.50
137.50
M=
275.00
18.125
275.00
18.125
250.00
120.00
Equipment Cost
10% VAT
20.63
b. Labor
0.0300 cu.m. Concrete
2.0000 kg. Rebars
0.6000 sq.m. Formworks
Production
Unit Cost
=
=
b. Forms
1 ELF
10 Laborers
20,000.00 kgs./day
P
Production
Unit Cost
=
=
Demolition Works
a. Equipment (Demolition)
1.00 Compressor
2.00 Jackhammer
12.00 hrs./day
12.00
0.30 /kg.
12.00 hrs./day
12.00
750.00 sq.m./day
7.88 /sq.m.
b. Manpower
20.00 Laborers
Labor Cost
10% VAT
Total Cost / hr.
Duration =
c. Equipment (Hauling & Disposal)
1.00 Loader
2.00 Dump Truck
Duration =
700.00
500.00
Equipment Cost
10% VAT
6 hrs. for 6 days
Total Cost =
1 Dumptruck
10 Laborers
8.00 hrs./day
8.00
450.00
18.125
1.00 hr.
Unit Cost
Item SP - 6 G.I. Sheet Temporary Fence (H = 3.00m)
a. Materials
20.00 bft. Coco Lumber
15.00 lft. Ga. # 26 Pre-painted Corrugated GI Sheets
0.015 kegs CW Nails
0.10 kgs. Roof Nails
50.00
15.00
20.00
=
6.00
40.00
950.00
85.00
Unit Cost =
26.00
525.00
75.00
475.00
45.00
25
Unit Cost (M & L) =
945.00 sq.m.
1.50
12.50
45.00
65.00
12.00 pcs.
0.06 gal.
Installation
Polishing
12.00 tiles
12.00 tiles
3.28 ln.ft.
1.00 lot
23.00
525.00
Materials
3.50
2.40
Sub Total
VAT
Labor
26.50
3.08
Materials
Labor
P
P
Cement
Sand
0.70 bags
0.06 cu.m.
12.50
1.05
0.09
2.50
0.04
12.50
0.54
0.04
2.50
0.04
pcs.
bags
cu.m.
kgs.
kgs.
pcs.
bags
cu.m.
kgs.
kgs.
205.00
240.00
Materials
Labor
P
P
25.00
210.00
200.00
36.00
70.00
Materials
Labor
P
P
8.50
200.00
200.00
31.00
70.00
Materials
Labor
P
P
210.00
200.00
80.00
148.00
Materials
Labor
P
P
210.00
200.00
80.00
Materials
Labor
P
P
C. Exterior Plastering
Cement
Sand
ME 602 Mortar Enhancer
Sealopruf Integral Waterproofing
0.50
0.06
0.13
0.05
bags
cu.m.
liters
gal
D. Interior Plastering
Cement
Sand
ME 602 Mortar Enhancer
0.30 bags
0.03 cu.m.
0.08 liters
C.MATERIALS
50,000.00
4,179,910.00
0.5573%
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
45.
46.
47.
Premium Fuel
Diesel
Lubricating Oil
Gravel Fill
Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
CW Nails
Cement
Gravel
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)
4,131,143.40
945,500.00
375,500.00
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
61.
62.
63.
64.
65.
66.
67.
68.
69.
70.
71.
72.
73.
74.
75.
76.
77.
78.
79.
80.
81.
82.
83.
84.
85.
86.
87.
88.
89.
90.
91.
92.
93.
94.
95.
96.
97.
98.
99.
100.
3,984,000.00
A.EQUIPMENTS:
1,000.00 =
500.00 =
400.00 =
=
=
43.75
33.75
37.50
33.75
=
=
=
=
=
1,000.00
500.00
1,200.00
42.76
274.28
3,017.04 /hr.
43.75
168.75
75.00
101.25
38.88
427.63 /hr.
24.125
10.00
83.25
117.38 liters
40.00 =
45.00 =
8,667.85 /hr.
4,695.00
528.19
5,223.19 /hr.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Foreman
Leadman
Timekeeper
Carpenter
Mason
Steelman
Laborer
Floater
Mixer Operator
Painter
Welder
HE Operator
Driver
Screeder Operator
400.00 =
350.00 =
500.00 =
=
=
43.75
33.75
37.50
33.75
=
=
=
=
=
1,200.00
350.00
500.00
27.91
207.79
2,285.70 /hr.
43.75
101.25
75.00
33.75
25.38
279.13 /hr.
83.25
14.00
2.28
99.53 liters
40.00 =
45.00 =
3,981.20
447.89
4,429.09 /hr.
6,993.91 /hr.
/CU.M.
/CU.M.
750.00 =
500.00 =
400.00 =
=
=
43.75 =
33.75 =
37.50 =
750.00
500.00
1,200.00
42.76
249.28
2,742.04 /hr.
43.75
168.75
75.00
Granite Counter
33.75 =
=
101.25
38.88
427.63 /hr.
24.125
10.00
83.25
117.38 liters
40.00 =
45.00 =
4,695.00
528.19
5,223.19 /hr.
8,392.85 /hr.
43.75 =
33.75 =
=
43.75
168.75
21.25
233.75 /hr.
400.00 =
350.00 =
300.00 =
=
=
400.00
350.00
300.00
27.91
107.79
1,185.70 /hr.
43.75
33.75
37.50
33.75
=
=
=
=
=
43.75
101.25
75.00
33.75
25.38
279.13 /hr.
8.00
14.00
5.44
27.44 liters
40.00 =
45.00 =
1,097.60
123.48
1,221.08 /hr.
450.00 =
27,000.00
27,000.00 /hr.
29,685.91 /hr.
400.00 =
350.00 =
300.00 =
=
=
43.75
33.75
37.50
33.75
=
=
=
=
=
400.00
350.00
300.00
27.91
107.79
1,185.70 /hr.
43.75
101.25
75.00
33.75
25.38
279.13 /hr.
8.00
14.00
5.44
27.44 liters
40.00 =
45.00 =
1,097.60
123.48
1,221.08 /hr.
750.00 =
45,000.00
45,000.00 /hr.
47,685.91 /hr.
2,665.00
239,850.00
239,850.00
52.00 =
13,479.56
13,479.56
36.30 =
6,156.48
36.30 =
343.83
6,500.31
m.
days
day
day
day
10,400.00 =
3,961.90
3,961.90
13,500.00 =
5,976.45
5,976.45
24.00 =
53.33
53.33
40.00 =
857.14
857.14
P 270,678.70
451.13
2,100.00
3,240.00
3,240.00
7,200.00
9,000.00
11,340.00
3,612.00
39,732.00
39,732.00
66.22
450.00
240.00
2,400.00
309.00
3,399.00
3,399.00
5.67
=
=
=
=
=
=
=
=
=
=
=
313,809.70
2,665.00
m.
319,800.00
319,800.00
52.00 =
13,479.56
13,479.56
36.30 =
6,156.48
36.30 =
343.83
6,500.31
10,400.00 =
3,961.90
3,961.90
13,500.00 =
5,976.45
5,976.45
24.00 =
53.33
53.33
40.00 =
857.14
857.14
P 350,628.70
584.38
2,100.00
3,240.00
3,240.00
7,200.00
9,000.00
11,340.00
3,612.00
39,732.00
39,732.00
66.22
450.00
240.00
2,400.00
309.00
3,399.00
3,399.00
5.67
days
=
=
=
=
=
=
=
day
day
day
=
=
=
=
393,759.70
=
=
86.67
8.00
=
=
=
P
170.10
9.00
81.00
354.77
=
=
P
50.00
5.00
55.00
=
=
=
=
43.75
37.50
168.75
25.00
275.00
=
=
P
57.75
4.73
62.48
=
=
=
=
P
43.75
75.00
135.00
25.38
279.13
=
=
=
P
45.00
60.00
10.50
115.50
=
=
=
=
P
43.75
75.00
135.00
25.38
279.13
=
=
P
222.75
18.23
240.98
cu.m.
=
6,933.33
=
=
=
=
P
192.00
18,900.00
900.00
8,100.00
35,025.33
350.25
day
=
=
P
50.00
5.00
55.00
day
=
=
=
350.00
300.00
1,350.00
days
days
days
days
days
days
=
=
=
=
P
0.00
2,000.00
=
=
P
57.75
4.73
62.48
=
=
=
=
P
612.50
1,050.00
1,890.00
355.25
3,907.75
=
=
=
P
45.00
60.00
10.50
115.50
=
=
=
=
P
612.50
1,050.00
1,890.00
0.00
3,552.50
=
=
P
222.75
18.23
240.98
268.75
214.20
18.19
=
=
P
108.90
1.80
611.84 /sq.m.
=
=
=
=
=
P
243.75
113.40
9.63
108.90
1.80
477.48 /sq.m.
=
=
=
=
=
P
125.00
214.20
27.29
99.00
1.80
467.29 /sq.m.
=
=
=
=
=
P
100.00
113.40
14.45
99.00
1.80
328.65 /sq.m.
=
=
=
=
=
P
252.00
102.90
7.40
81.68
1.26
445.24 /sq.m.
=
=
=
=
=
=
P
P
1,680.00
520.00
480.00
136.05
94.50
600.00
3,510.55 /cu.m.
770.00 /cu.m.
=
=
P
3,750.00
750.00
4,500.00 /cu.m.
=
=
P
147.00
10.70
157.70 /sq.m.
=
=
P
117.60
8.56
126.16 /sq.m.
=
=
=
P
117.60
8.56
90.00
216.16 /sq.m.
=
=
=
P
29.40
2.14
90.00
121.54 /sq.m.
=
=
=
P
117.60
8.56
20.00
146.16 /sq.m.
=
=
=
102.90
7.49
10.50
=
=
P
131.25
112.50
364.64 /sq.m.
=
=
30.87
2.25
=
=
P
39.38
33.75
106.24 /lm.
=
=
=
102.90
7.49
10.50
=
=
P
131.25
56.25
308.39 /sq.m.
=
=
30.87
2.25
=
=
P
39.38
16.88
89.37 /lm.
=
=
=
=
147.00
10.70
45.00
10.50
131.25
=
P
112.50
456.95 /sq.m.
=
=
=
35.28
2.57
5.74
=
=
P
6.56
2.81
52.96 /lm.
=
=
117.60
8.56
=
=
=
=
P
131.25
56.00
6.00
56.25
375.66 /lm.
=
=
117.60
8.56
=
=
=
=
P
45.94
120.00
20.00
28.44
340.54 /lm.
=
=
117.60
8.56
=
=
=
=
P
31.50
126.00
22.50
13.50
319.66 /lm.
=
=
=
=
P
P
102.90
7.49
4,500.00
450.00
5,060.39 /lm.
220.00 /lm.
=
=
117.60
8.56
=
=
=
=
P
31.50
315.00
22.50
13.50
508.66 /lm.
=
=
P
336.00
33.00
369.00 /sq.m.
=
=
P
288.00
33.00
321.00 /sq.m.
=
=
=
P
117.60
8.56
312.50
438.66 /sq.m.
=
=
=
P
102.90
7.49
420.00
530.39 /sq.m.
102.90
=
=
=
P
30.00
7.49
472.50
612.89 /sq.m.
=
=
=
=
P
102.90
30.00
7.49
540.00
680.39 /sq.m.
=
=
=
=
P
102.90
30.00
7.49
350.00
490.39 /sq.m.
=
=
=
=
P
102.90
30.00
7.49
525.00
665.39 /sq.m.
=
=
=
=
P
102.90
30.00
7.49
375.00
515.39 /sq.m.
=
=
=
=
P
102.90
30.00
7.49
336.00
476.39 /sq.m.
=
=
=
102.90
30.00
7.49
=
P
1,800.00
1,940.39 /sq.m.
=
=
=
=
P
102.90
30.00
7.49
1,440.00
1,580.39 /sq.m.
=
=
=
=
P
P
61.74
4.49
540.00
54.00
660.23 /lm.
200.00 /lm.
=
=
=
=
P
P
36.02
2.62
315.00
31.50
385.14 /lm.
185.00 /lm.
=
=
=
=
P
P
20.58
1.50
180.00
18.00
220.08 /lm.
185.00 /lm.
=
=
=
=
P
P
15.44
1.12
135.00
13.50
165.06 /lm.
185.00 /lm.
102.90
=
=
=
P
P
7.49
950.00
95.00
1,155.39 /lm.
185.00 /lm.
=
=
=
=
P
P
30.87
2.25
270.00
27.00
330.12 /lm.
185.00 /lm.
=
=
=
P
147.00
10.70
45.00
202.70 /sq.m.
=
=
P
300.00
30.00
330.00 /sq.m.
=
=
P
82.00
70.94
152.94 /lm.
=
=
P
164.93
106.41
271.33 /lm.
=
=
P
165.42
141.87
307.29 /lm.
=
=
=
=
P
94.50
15.00
5.35
1,440.00
1,554.85 /lm.
=
=
=
=
P
94.50
15.00
5.35
225.00
339.85 /sq.m.
=
=
=
=
P
94.50
15.00
5.35
525.00
639.85 /sq.m.
=
=
=
=
P
94.50
15.00
5.35
350.00
464.85 /sq.m.
=
=
=
=
P
94.50
15.00
5.35
342.00
456.85 /sq.m.
=
=
=
=
P
94.50
15.00
5.35
375.00
489.85 /sq.m.
242.50
=
=
P
88.94
6.47
337.91 /sq.m.
=
=
P
86.82
7.77
94.59 /sq.m.
=
=
=
P
31.20
105.11
7.65
143.96 /sq.m.
=
=
P
73.50
5.35
78.85 /sq.m.
=
=
=
P
31.20
88.20
6.42
125.82 /sq.m.
=
=
P
51.45
3.75
55.20 /lm.
=
=
P
30.87
2.25
33.12 /lm.
=
=
15.44
1.12
16.56 /lm.
=
=
P
61.74
4.49
66.23 /lm.
=
=
P
11.34
0.80
12.14 /lm.
=
=
=
73.50
5.35
10.50
=
=
P
131.25
112.50
333.10 /sq.m.
=
=
22.05
1.61
=
=
P
39.38
33.75
96.78 /lm.
=
=
=
=
P
650.00
133.13
9.60
26.25
818.98 /sq.m.
650.00
=
=
=
P
75.00
9.60
26.25
760.85 /sq.m.
=
=
=
=
P
520.00
110.63
9.60
26.25
666.48 /sq.m.
=
=
=
=
P
520.00
111.00
9.60
26.25
666.85 /sq.m.
=
=
=
=
P
520.00
431.25
8.60
8.75
968.60 /sq.m.
=
=
P
2.94
0.21
3.15 /sq.m.
=
=
P
135.00
258.75
393.75 /sq.m.
=
=
P
4,050.00
230.00
4,280.00 /sq.m.
=
=
=
=
=
=
P
262.50
21.00
29.00
18.75
10.00
26.00
367.25 /sq.m.
119
119
119
119
119
119
45
14
24
18
5
12
=
=
=
=
=
=
=
P
110.63
21.00
29.00
18.75
3.75
10.00
26.00
219.13 /sq.m.
119
119
119
119
119
119
119
45
14
24
18
1
5
12
=
=
=
P
108.38
117.76
162.50
388.64 /l.m.
=
=
=
P
28.88
17.60
89.38
135.85 /l.m.
=
=
=
P
101.15
121.44
200.00
422.59 /l.m.
=
=
=
P
26.95
18.15
110.00
155.10 /l.m.
72.25
=
=
P
73.60
145.85 /l.m.
=
=
=
P
19.25
11.00
41.25
71.50 /l.m.
=
=
=
P
86.70
73.60
160.30 /l.m.
=
=
=
P
23.10
11.00
82.50
116.60 /l.m.
3,300.00
2,610.00
5,910.00
3,300.00
2,610.00
5,910.00
/hr.
/hr.
250.00
240.00
490.00
49.00
539.00 /hr.
/hr.
412.50
412.50
41.25
453.75
992.75 /hr.
180.00 hours
178,695.00
/hr.
/hr.
700.00
1,000.00
1,700.00
170.00
1,870.00 /hr.
36.00
67,320.00
246,015.00
3,600.00
1,740.00
5,340.00
427,200.00
/hr.
/hr.
/hr.
=
=
=
50.00
15.00
20.00
85.00 /hr./pump
=
=
=
=
120.00
600.00
14.25
8.50
742.75 /lm.
=
=
=
=
=
=
=
ost (M & L) =
780.00
1,050.00
450.00
118.75
45.00
50.00
997.50
3,491.25 /lm.
say
=
=
=
=
=
3,500.00 /lm.
12.75
11,875.00
1,125.00
2,145.00
7,578.88
22,736.63
24.06
25.00 /sq.m.
ost (M & L) =
=
=
=
=
=
=
=
233.33
604.17
308.00
62.50
157.50
12.00
154.00
1,531.50 /sq.m.
765.75 /sq.m.
276.00
31.50
307.50
42.00
28.80
70.80
7.08
77.88
86.92
3.08
90.00
22.00
143.50
13.20
156.70
104.00
312.50
220.50
18.00
90.00
2.80
643.80
110.00
106.25
108.00
8.00
77.50
2.80
302.55
104.00
105.00
11.00
10.00
7.40
133.40
139.00
63.00
6.60
6.00
75.60
115.50
UNIT COST
Premium Fuel
Lubricating Oil
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
100x100 Binangonan Rocks
300x300x3.0mm Vinyl Tiles (Tajima)
55.00
40.00
45.00
900.00
150.00
450.00
750.00
2,665.00
52.00
36.30
40.00
13,500.00
10,400.00
24.00
210.00
900.00
430.00
200.00
355.00
375.00
55.00
28.00
21.50
19.50
10.00
8.00
80.00
900.00
10.50
6.00
35.00
28.00
10.50
14.00
75.00
150.00
4,500.00
12.50
120.00
10.50
14.00
2.50
28.50
75.00
4.00
25.00
6.00
28.00
/lit.
/lit.
/lit.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bft.
/kg.
/gal.
/MT
/pc.
/kl.
/bag
/cu.m.
/cu.m.
/cu.m.
/pc.
/pc.
/bft.
/pc.
/pc.
/pc.
/pc.
/pc.
/kl.
/kl.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
24.00
90.00
80.00
950.00
900.00
60.00
10.50
90.00
90.00
45.00
45.00
65.00
24.00
10.50
525.00
550.00
36.00
3.50
10.00
300.00
295.00
296.00
1,150.00
175.00
145.00
125.00
300.00
250.00
260.00
700.00
23.00
30.00
25.00
45.00
25.00
1,500.00
3,017.00
3,026.00
880.00
130.00
135.00
600.00
120.00
150.00
10.00
60.00
1,300.00
1,100.00
2.50
/pc.
/pc.
/pc.
/sq.m.
/sq.m.
/kl.
/pc.
/can
/can
/can
/can
/can
/kl.
/pc.
/gal.
/gal.
/kl.
/lft.
/lft.
/cu.m.
/pc
/pc
/pc
/pc
/pc
/pc
/roll
/gal.
/gross
/pc.
/lft.
/lft.
/pc.
/sq.m.
/pc.
/pc.
/pc.
/pc.
/liter
/bag
/gal.
/bag
/bag
/pc.
/pc.
/sq.ft.
/sq.m.
/pc.
/pc.
275.00 /bag
38pcs./sq.m.
Labor
25.00 /sq.ft.
80.00 /sq.m.
RENTALS
Water truck
Air Compressor
Jackhammer
Plate Compactor
Water Pump
Concrete Cutter
1-Bagger Mixer
Concrete Breaker
1,000.00
500.00
400.00
400.00
350.00
300.00
300.00
20.00
50.00
20.00
56.25
60.00
1,200.00
45.00
20.00
75.00
900.00
750.00
500.00
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
/hr.
DAILY RATES
Timekeeper
Mixer Operator
HE Operator
Screeder Operator
350.00
300.00
270.00
300.00
300.00
290.00
270.00
270.00
350.00
270.00
270.00
300.00
270.00
270.00
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
/day
Granite Counter
Ovaline Hole
Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top
Material = actual + 25%
Type of Work
Labor Cost
1,100.00 / hole
150.00 / l.m.
420.00 / l.m.
420.00 / l.m.
450.00 / l.m.
85.00 / l.m.
420.00 / l.m.
1,600.00 / sq.m.
Unit
Material
450.00
750.00
451.13
584.38
354.77
350.25
China
Labor
86.68
139.88
116.88
107.60
593.72
953.72
71.89
71.89
108.56
99.34
Granite Counter
Ovaline Hole
Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top
Material = actual + 25%
Labor Cost
/ hole
/ l.m.
/ l.m.
/ l.m.
/ l.m.
/ l.m.
/ l.m.
1,100.00
150.00
420.00
420.00
450.00
85.00
420.00
1,600.00 / sq.m.
China
COMPUTATION
Description
Qty.
Unit
7.00
7.00
28.00
22.60
28.00
28.00
19.40
hole
hole
l.m.
l.m.
l.m.
l.m.
l.m.
14.55
Materials
unit cost
amount
1,600.00
Labor
unit cost
23,280.00
1,100.00
150.00
420.00
420.00
450.00
85.00
420.00
23,280.00
Total Amount
1200
3,938.66
COMPUTATION
Description
Ovaline / Sink Hole
Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top
Material = actual + 25%
Qty.
99.37
496.50
2,186.25
36.44
Unit
Materials
unit cost
amount
hole
hole
l.m.
l.m.
l.m.
l.m.
l.m.
3,000.00
450.00
34.00
55.00
1,600.00
Labor
unit cost
298,110.00
223,425.00
74,332.50
2,004.20
-
597,871.70
Total Amount
300.00
250.00
3.25
5.00
450.00
85.00
420.00
for Asphalt
Area x 0.05 x 2.33 = MT.
3.5 l.m.
Concrete Counter
concrete
formworks
rebars
g.i. wire
0.2625
3.5
16.716
0.2786
m
m
kgs
kgs
Qty.
Unit
2,700.00
250.00
46.00
50.00
700.00
185.00
3.75
5.00
3,400.00
435.00
49.75
55.00
COMPUTATION
Description
Ovaline / Sink Hole
Faucet Hole
Splash Board
Appron
Edging
Cutting
Counter Top
2.00
-
hole
hole
l.m.
l.m.
l.m.
l.m.
l.m.
Materials
unit cost
amount
Labor
unit cost
-
1,100.00
150.00
420.00
420.00
450.00
85.00
420.00
0.30
2,500.00
750.00
750.00
Total Amount
487.50
316.88
conc.
reb
fw
plaster
conc.
reb
fw
0.135
27
2
391.50
810.00
700.00
101.25
101.25
400.00
0.9
1,901.50
602.50
316.92
100.42
2,112.78
669.44
352.13
111.57
65.25
135.00
116.67
16.88
16.88
66.67
316.92
100.42
120.00
208.80
96.00
280.00
704.80
96.00
54.00
12.00
160.00
322.00
0.80
0.07
3.20
0.80
Labor
amount
7,700.00
1,050.00
11,760.00
9,492.00
12,600.00
2,380.00
8,148.00
-
53,130.00
76,410.00
3,938.66
2,738.66
Labor
amount
29,811.00
124,125.00
7,105.31
182.20
-
161,223.51
759,095.21
795
954.84
752.04
202.80
4,893.50
18,523.83
94,933.83
892.50
1,522.50
831.62
15.32
3,261.94
708.75
875.00
768.94
13.93
2,366.62
183.75
647.50
62.69
1.39
895.33
88.64
676.18
255.81
4,027.30
Labor
amount
170.00
-
170.00
920.00
Unit
Unit
I. Rentals
1. Heavy Equipment
Supplier A
Rate/Hour
Supplier name
unit
PHP 1,900.00
FEMD
unit
PHP 1,700.00
FEMD
unit
PHP 1,800.00
FEMD
unit
PHP 1,600.00
FEMD
unit
PHP 1,300.00
FEMD
unit
PHP 800.00
FEMD
unit
PHP 2,500.00
FEMD
unit
PHP 1,800.00
FEMD
unit
PHP 700.00
FEMD
unit
PHP 700.00
FEMD
unit
PHP 600.00
FEMD
unit
PHP 800.00
FEMD
unit
PHP 3,000.00
FEMD
unit
PHP 3,000.00
FEMD
unit
PHP 300.00
FEMD
unit
PHP 300.00
FEMD
unit
PHP 300.00
FEMD
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
PHP 15,000.00
PHP 1,200.00
PHP 1,200.00
PHP 1,500.00
PHP 1,200.00
PHP 1,500.00
PHP 300.00
PHP 1,200.00
PHP 18,000.00
PHP 8,000.00
PHP 30,000.00
PHP 28,000.00
PHP 12,000.00
PHP 12,000.00
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
Supplier B
Rate/Hour
o.
p.
k.
l.
m.
n.
o.
p.
q.
r.
s.
t.
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
unit
PHP 6,000.00
PHP 3,000.00
PHP 8,000.00
PHP 1,500.00
PHP 15,000.00
PHP 1,000.00
PHP 1,100.00
PHP 1,100.00
PHP 6.50
PHP 7.40
PHP 9.20
PHP 400.00
PHP 10,000.00
PHP 4,000.00
PHP 4,000.00
PHP 1,200.00
PHP 10,000.00
PHP 1,000.00
PHP 600.00
PHP 600.00
PHP 3,000.00
PHP 2,500.00
PHP 2,500.00
PHP 3,000.00
PHP 1,500.00
PHP 1,600.00
Note
Per Day
Per Month
PHP 2,500.00
PHP 6,000.00
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
LABOR RATES
Unit Cost
Supplier B
Supplier name
Supplier C
Rate/Hour
Applied Rate
Supplier name
1,900.00
1,700.00
1,800.00
1,600.00
1,300.00
800.00
2,500.00
1,800.00
700.00
700.00
600.00
800.00
3,000.00
3,000.00
300.00
300.00
300.00
15,000.00
1,200.00
1,200.00
1,500.00
1,200.00
1,500.00
300.00
1,200.00
18,000.00
8,000.00
30,000.00
28,000.00
12,000.00
12,000.00
Item
I. Indirect Manpower
1. Accountant
2. Cadet Engineer
3. Carpenter
4. Cost Engineer
5. Driver
6. Electrician
7. Field Engineer
8. Foreman
9. Glass Installer
10. Guard
11. Heavy Equipment Operator
12. Laborer
13. Leadman
14. Mason
15. Mechanic
16. Messenger
17. Mixer Operator
18. Painter
19. Plumber
20. Project In-charge
21. Screeder Operator
22. Steelman
23. Surveying Aide
24. Surveyor
25. Tile Setter
26. Timekeeper
27. Utility
28. Utility
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32. General Manager
33. General Foreman
34. Safety Officer
35. Mason - Plasterer (int)
36. Mason - Plasterer (ext)
37. Mason - CHB Layer
38. Mason Finisher
39.
40.
1
Provincia
Minimum
375.00
250.00
280.00
400.00
250.00
6,000.00
3,000.00
8,000.00
1,500.00
15,000.00
1,000.00
1,100.00
1,100.00
6.50
7.40
9.20
400.00
10,000.00
4,000.00
4,000.00
1,200.00
10,000.00
1,000.00
600.00
600.00
3,000.00
2,500.00
2,500.00
3,000.00
1,500.00
1,600.00
2,500.00
6,000.00
1
Provincial Rate
Maximum
400.00
375.00
300.00
2
Manila Rate
Minimum
Maximum
450.00
400.00
310.00
500.00
475.00
400.00
450.00
280.00
350.00
400.00
500.00
270.00
350.00
350.00
600.00
300.00
400.00
380.00
310.00
310.00
340.00
330.00
350.00
350.00
330.00
350.00
350.00
835.00
400.00
330.00
340.00
360.00
300.00
320.00
350.00
1,000.00
450.00
350.00
350.00
380.00
310.00
Applied Rate
500
475
0
0
400
0
0
400
0
0
600
300
400
380
0
0
0
0
0
0
0
310
0
0
350
350
0
0
350
0
350
1000
450
350
350
380
310
0
62.5
59.375
0
0
50
0
0
50
0
0
75
37.5
50
47.5
0
0
0
0
0
0
0
38.75
0
0
43.75
43.75
0
0
43.75
0
43.75
125
56.25
43.75
43.75
47.5
38.75
0
LABOR RATES
Item
I. Indirect Manpower
1. Accountant
2. Cadet Engineer
3. Carpenter
4. Cost Engineer
5. Driver
6. Electrician
7. Field Engineer
8. Foreman
9. Glass Installer
10. Guard
11. Heavy Equipment Operator
12. Laborer
13. Leadman
14. Mason
15. Mechanic
16. Messenger
17. Mixer Operator
18. Painter
19. Plumber
20. Project In-charge
21. Screeder Operator
22. Steelman
23. Surveying Aide
24. Surveyor
25. Tile Setter
26. Timekeeper
27. Utility
28. Utility
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32. General Manager
33. General Foreman
34. Safety Officer
35. Mason - Plasterer (int)
36. Mason - Plasterer (ext)
37. Mason - CHB Layer
38. Mason Finisher
1
2
Provincial Rate
Manila Rate
Minimum Maximum Minimum Maximum
375.00
250.00
280.00
400.00
375.00
300.00
450.00
400.00
310.00
500.00
475.00
350.00
400.00
350.00
400.00
400.00
250.00
450.00
280.00
500.00
270.00
350.00
350.00
600.00
300.00
400.00
380.00
400.00
500.00
550.00
750.00
310.00
310.00
340.00
330.00
350.00
350.00
330.00
350.00
350.00
835.00
400.00
330.00
340.00
360.00
300.00
320.00
350.00
1,000.00
450.00
350.00
350.00
380.00
310.00
Applied Rate
500
475
350
0
400
0
0
400
0
0
600
300
400
380
0
0
0
0
0
750
0
310
0
0
350
350
0
0
350
0
350
1000
450
350
350
380
310
0
62.5
59.375
43.75
0
50
0
0
50
0
0
75
37.5
50
47.5
0
0
0
0
0
93.75
0
38.75
0
0
43.75
43.75
0
0
43.75
0
43.75
125
56.25
43.75
43.75
47.5
38.75
0
Premium Fuel
Diesel
Lubricating Oil
Gravel Fill
Earthfill
Agg.Sub-base Coarse
Agg.Base Coarse
525 Ready Mixed Concrete
Rough Tanguile
Grade 40 Rebars
Curing Compound
Asphalt Sealer
Diamond Blade
CW Nails
Cement
Gravel
Black Sand
White Sand
1/4"thk. Marine Plywood
1/4"thk. Narra Plywood
Kd Tanguile
CHB (Load Bearing) - 8"
CHB (Load Bearing) - 6"
CHB (Load Bearing) - 4"
CHB (Non-Load Bearing) - 6"
CHB (Non-Load Bearing) - 4"
Colored Cement
Floor Hardener
150x150 Ceramic Unglazed Floor Tiles
101x101
-do- (Piedra Tiles)
300x300
-do- (High Polish)
300x300 Ceramic Unglazed Floor Tiles
100x200
-do200x200
-do450x450
-do300x300 Cotto Homogenous Tiles
25mm thk. Granite Slab
200x200 Non-skid Floor Tiles (URRA)
12" x 12" Granite Tiles
100x200 Ceramic Glazed Wall Tiles
200x200
-do101x101
-do300x300
-do450x450
-doTile Fittings
200x200 Green Slate Tiles
42.00
38.00
45.00
440.00
150.00
250.00
270.00
2,557.00
42.00
31.00
40.00
13,500.00
10,400.00
24.00
198.00
440.00
300.00
400.00
355.00
375.00
51.00
17.50
21.50
19.50
10.00
8.00
80.00
900.00
10.50
6.00
35.00
28.00
10.50
14.00
75.00
150.00
4,500.00
12.50
120.00
10.50
14.00
2.50
28.50
75.00
4.00
25.00
/lit.
/lit.
/lit.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bft.
/kg.
/gal.
/MT
/pc.
/kl.
/bag
/cu.m.
/cu.m.
/cu.m.
/pc.
/pc.
/bft.
/pc.
/pc.
/pc.
/pc.
/pc.
/kl.
/kl.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
/pc.
6.00
28.00
24.00
90.00
80.00
950.00
900.00
60.00
10.50
90.00
90.00
45.00
45.00
65.00
24.00
10.50
525.00
550.00
36.00
3.50
10.00
300.00
295.00
296.00
1,150.00
175.00
145.00
125.00
300.00
250.00
260.00
700.00
23.00
30.00
25.00
45.00
25.00
1,500.00
3,017.00
3,026.00
880.00
130.00
135.00
600.00
120.00
150.00
10.00
60.00
1,300.00
1,100.00
/pc.
/pc.
/pc.
/pc.
/pc.
/sq.m.
/sq.m.
/kl.
/pc.
/can
/can
/can
/can
/can
/kl.
/pc.
/gal.
/gal.
/kl.
/lft.
/lft.
/cu.m.
/pc
/pc
/pc
/pc
/pc
/pc
/roll
/gal.
/gross
/pc.
/lft.
/lft.
/pc.
/sq.m.
/pc.
/pc.
/pc.
/pc.
/liter
/bag
/gal.
/bag
/bag
/pc.
/pc.
/sq.ft.
/sq.m.
/pc.
275/bag
38pcs./sq.m.
Labor
25/sq.ft
80/sq.m
STRUCTURAL STEEL
50mm x 50mm x 6mm thk L-Bar (per pc)
31mm x 31mm x 4.5mm thk L-Bar (per pc)
4' x 8' x 4.5mm thk M.S. Plate (sheet)
4' x 8' x 12mm thk M.S. Plate (sheet)
4' x 8' x 16mm thk M.S. Plate (sheet)
4' x 8' x 20mm thk M.S. Plate (sheet)
50mm, Sch 40 Tubular Bar
16mm Plain Round Bar (6m)
12mm Plain Round Bar (6m)
50mm x 100mm x 2mm thk C-Purlin (per pc)
Dyna Bolt 12mm x 100mm (pc)
8" G.I. Pipe (6m Length)
Anchor Bolt 200mm x 300mm
1-1/2 Steel Pipe Sch. 40
4mm- 2"x4" Sch 40 Tubular
4mm- 1-1/2"x1-1/2" Tubular
2.50 /pc.
265.00
250.00
900.00
900.00
900.00
300.00
400.00
210.00
13,500.00
10,400.00
33.73
34.35
40.00
24.00
1,100.00
20.86
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/cu.m.
/bag
/MT
/pc.
/kg.
/kg.
/gal.
/kl.
/pc.
/sq.m
42.00 /lit.
35.00 /lit.
45.00 /lit.
Water-Seeping Geotextile(200g/sq.m)
Surveying Rod Socket
45-50 per/sq.m
4,800.00
Ficemboard
Gypsum Board
Vinyl Tile (300x300)
300x300 Ceramic Non-skid Floor Tiles
300x300 Wall Tiles
per sq.m.
per kilo
per cu.m
per cu.m
per cu.m
per kgs
per piece
per piece
per piece(4,620)
kgs ( 4,800)
720 kgs / 2pcs.
1800 kgs / 5pcs
485.52 kgs / 7pcs
68,996.90 kgs
17601.88 kgs
64.41 kgs
35,640 kgs
106,955.64 kgs
61,882.92 kgs
171.90 kgs
GOOD LUMBER S4 kd
1" x 3" x 10'
1" x 3" x 12'
1" x 4" x 12'
2" x 2" x 10'
2" x 2" x 12'
2" x 2" x 12'
2" x 3" x 10'
2" x 3" x 12'
4" x 4" x 10'
4" x 4" x 12'
230 cu.m
piece
bag
cu.m
bag
28-May-10
16-Jun-10
28-Jun-10
225.00
34.00
35.23
35.95
56.00
1,000.00
461.00
4,045.00
10,780.00
16,050.00
21,024.00
1,986.00
380.00
210.00
800.00
24.00
17,774.00
98.00
6,441.00
4,100.00
2,870.00
660.00
850.00
190.00
90.00
735.00
520.00
3,000.00
780.00
335.00
18.00
36.00
36.00
1,555.00
20.86
70.00
3,200.00
3,350.00
3,500.00
43.85
15,272.00
178.15 per kg
87.53
43.85
42.42
87.53
37.10
37.18
40.58
35.35
37.00
35.00
per
per
per
per
per
per
kg
kg
kg
kg
kg
kg
5,000.00
400.00 TL
50.00
900.00
2,500.00
900.00
1,450.00
1,140.00
862.00
4,375.00
5,250.00
8,740.00
130.00
156.00
224.00
160.00
192.00
192.00
260.00
312.00
720.00
864.00
52.00
52.00
54.00
48.00
48.00
48.00
52.00
52.00
60.00
60.00
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
bd.ft
1,400.00
266.65
320.00
1,250.00 pc
58.00 bd.ft
58.00 bd.ft
(Waltermart-Pampanga)
Date:
13-Jan-10
(DMIA-Clark)
Date:
11-Jan-10
Metal Decking
Remington Industrial Sales
150 X 150 X 10Mm Thk X 6M L-Bar
100 X 100 X 12Mm Thk X 6M L-Bar
75 X 75 X 12Mm Thk X 6M L-Bar
75 X 75 X 8Mm Thk X 6M L-Bar
75 X 75 X 6Mm Thk X 6M L-Bar
50 X 50 X 6Mm Thk X 6M L-Bar
W 27 X 281 (6M)
W 27 X 217 (6M)
W 27 X 161 (6M)
W 27 X 235 (6M)
W 27 X 161 (6M)
W 27 X 129 (6M)
W 27 X 114 (6M)
W 27 X 102 (6M)
W 24 X 117 (6M)
W 21 X 101 (6M)
W 21 X 57 (6M)
W 24 X 55 (6M)
W 16 X 50 (6M)
W 10 X 45 (6M)
W 8 X 21 (6M)
4' X 8' X 50Mm Thk M.S.Plate
6' X 20' X 16Mm Thk M.S. Plate
4' X 8' X 8Mm Thk M.S. Plate
75 X 175 X 18 X 6Mm Thk Lc-Purlins (6M)
20mm Plain Round Bar (6m)
16Mm Round Bar (6m)
20mm STD Turn Buckle
16mm STD Turn Buckle
Pipe 8" BI Sch.40 (6m)
Pipe 6" BI Sch.40 (6m)
Pipe 4" BI Sch.40 (6m)
Pipe 3" BI Sch.40 (6m)
(Interphil Laboratory Warehouse, Canlubang Industrial Estate, Bo. Pittland, Cabuyao, Laguna)
Date:
Architectural Finishes
15-Jul-10
15-Jul-10
CWN 4"
CWN 3"
CWN 2"
Portland Cement (Northern Cement)
Portland Cement (Holcim Cement)
Wash Sand
Crushed Gravel 3/4"
Concrete Pail
4" x 4" x 10' Good Lumber
2" x 4" x 14' KD S4S
3" x 5" x 10' KD S4S
3" x 3" x 10' Good Lumber
Epoxy Primer Gray (ACP Concrete)
Epoxy Primer Gray (Rag J Hardware)
Baby Roller (Painting Works)
6-Sep-10
15-Oct-10
15-Oct-10
0.90x1.20m Sliding Type Clear Glass Window on Powder Coated Aluminum Frame & Casing
1.20x1.20m Fix-type Clear Glass Window on Powder Coated Aluminum Frame & Casing
0.60x0.60m Awning-type Clear Glass Window on Powder Coated Aluminum Framing & Casing
1.20x1.20m Fix-type Clear Glass Window on Powder Coated Aluminum Framing & Casing
1.20x1.20m Sliding Type Clear Glass Window
0.90x1.20m Sliding Type Clear Glass Window
0.80x2.10m Single Wooden Flush Swing Door (50mm thk)
0.70x2.10m Single Leaf PVC Swing Door w/ Bottom Louver
0.60x2.10m PVC Door
Rockwool Insulation (for soundproofing/wall insulation)
Ga#24 Pre-formed pre-painted G.I. Flashing
Ga#24 Pre-formed pre-painted G.I. Gutter
Ga#24 Pre-painted Rib-type Roofing Sheet
12mm thk. Hardi Senepa
25mm x 25mm S4S Lumber
10mm thk Reflective Insulation(Roof)
15-Oct-10
23-Nov-10
23-Nov-10
()
Date:
23-Nov-10
Portland Cement Concrete 4000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 5000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 6000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 8000 psi 28da 3/4" Slump-5"-6"
Portland Cement Concrete 6000 psi 28da G-1 Slump-3"-4"
Note : Price of Pumpcharge is subject as per site inspection. Pumpcharge : Stationary-Php. 9,500.00 per
set-up, minimum of 50 cubic meter. Boom Type (18m-28m) - Php. 10,000.00 per set-up minimum of 50
cubic meter. Boom Type (36m) - Php. 11,000.00 per set-up of 50 cubic meter.
Additional : ***w/ added specification on the SPA Stationary-Php. 190.00 per cubic in excess of 50 cubic
meter. Boom Type (18m-28m)- Php. 200.00 per cubic in excess of 50 cubic meter. Boom Type (36m)Php. 220.00 per cubic in excess of 50 cubic meter.
(Angeles Hospital)
Date:
20-Sep-10
()
Date:
600x600 Homogenous Granite Tile
600x600 Homogenous Granite Tile
600x600 Non-skid Tile
()
Date:
2"x2"x3/16" thk Angle Bar
1"x1"x3/16" thk Angle Bar
2" G.I. Pipe Sch.40
2"x2"x3/16" thk Angle Bar
4'x8'x16mm thk M.S. Plate
2"x7" C-Purlins
29-Nov-10
()
Date:
10-Nov-10
Megakonztruk
12mm Expansion Bolt w/ plate washer
2x4x1.5mmx6m C-Purlin
50mmx75mmx1.5mmx6m C-Purlin
4'x8'x1/8"(3mm) M.S. Plate
50mmx100mmx1.5mmx6m Tubular Steel
50mmx150mmx1.5mmx6m Tubular Steel
38x38x3mmx6m Angle Bar
2"x2"x3/16" thk Angle Bar (2.8mm)
2"x2"x3/16" thk Angle Bar (3.5mm)
2"x2"x" Angle Bar
2"x"x6m Flat Bar
2"x3/8"x6m Flat Bar (7mm)
10-Nov-10
Hardiflex Board
Tekscrew
2"x2"x3/16" Angle Bar
1"x1"x3/16" thk Angle Bar
2"x2"x" Angle Bar
2"x"x6m Flat Bar
12mm(Expansion) Bolt w/ nut
2"x4" C-Purlins / 50x100x12.5x1.5mm thk C-Purlins
4'x8'x1/8"(3mm) M.S. Plate
50x75x1.5mm thk Light Gage C-Purlins
50x100x1.5mm thk Light Gage Tubular Steel
50x150x1.5mm thk Light Gage Tubular Steel
13mmx300mm Anchor Bolt w/ standard lock nut & washer
38mmx38mmx3mm Angle Bar
10mm Machine Bolt (L=1")
Date:
10-Jan-11
Grade 60 Reinforcing Steel Bar
Grade 40 Reinforcing Steel Bar
3-Jan-11
Rebars:
Grade 60
Grade 40
(SM-San Fernando)
Date:
3-Jan-11
28-Jan-11
18-Nov-10
9-Feb-11
23-Mar-11
8,790.00
20,700.00
56,350.00
20,125.00
8,430.00
7,980.00
6,890.00
4,280.00
2,360.00
1,650.00
1,380.00
1,035.00
560.00
670.00
1,350.00
1,150.00
600.00
300.00
140.00
60.00
750.00
390.00
220.00
115.00
2.70
2.40
18,200.00
8,165.00
6,532.00
5,990.00
2,050.00
1,433.00
1,200.00
900.00
510.00
730.00
1,210.00
1,050.00
460.00
210.00
90.00
460.00
310.00
197.00
90.00
5.00
5.50
5.00
lgth
lgth
sht
sht
sht
sht
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
pc
pc
pc
pc
pc
lgth
lgth
pc
pc
pc
pc
sq.m
pc
kg
kg
CHB
Reinforcing Steel Bar
Structural Steel - Wide Flange
Structural Steel - Angle Bars
Steel Plates
Concrete
Roof Accessories & Metal Dec
Bolts, Screws, Ladder Rungs
Tubular Steel, Flat Bars & Squ
Steel Pipes
Other Steel Shapes
Granite, Ceramic, Vinyl Tiles &
Others
sht
6,480.00
5,990.00
3,120.00
1,863.00
1,442.00
925.00
141,000.00
123,480.00
70,785.00
95,095.00
70,785.00
62,425.00
37,309.00
33,382.00
38,291.00
33,054.50
18,654.50
18,000.00
15,227.00
13,704.50
6,395.50
41,423.00
6,160.00
6,160.00
1,677.00
460.00
300.00
140.00
90.00
14,439.00
10,973.00
6,323.00
4,083.00
42,590.00
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
sht
sht
lgth
lgth
lgth
pc
pc
lgth
lgth
lgth
lgth
20.86
70.00
34.35
33.73
3,200.00
3,350.00
3,500.00
13,682.00
15,272.00
4,620.00
4,800.00
17,500.00
23,000.00
28,700.00
19,000.00
475.00
45.00
sq.m
kg
kg
kg
cu.m
cu.m
cu.m
lgth
lgth
lgth
sht
lgth
lgth
lgth
lgth
pc
pc
pc
pc
l.m.
lgth
lgth
pc
lgth
4,780.00
3,600.00
1,000.00
840.00
680.00
780.00
550.00
10,659.00
17,730.00
14,184.00
9,520.00
7,930.00
6,000.00
221.50
4,600.00
4,600.00
4,000.00
4,000.00
2.25
3.75
120.00
630.00
880.00
1,150.00
926.00
1,400.00
640.00
517.29
650.00
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
sht
sht
sht
sht
pc
pc
pc
lgth
lgth
lgth
sq.m
gal
cu.m
cu.m
cu.m
cu.m
pc
pc
pc
lgth
lgth
lgth
lgth
roll
sht
lgth
cu.m
1,979.00
1,623.00
lgth
lgth
1,386.00
680.00
1,355.00
1,059.00
435.00
4,324.00
435.00
12,727.00
22,591.00
44,064.00
9,800.00
330.00
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
lgth
3,450.00
3,150.00
535.00
410.00
1,793.00
1,458.00
952.00
684.00
410.00
165.00
115.00
40.00
596.85
760.00
800.00
353.00
kg
kg
cu.m
cu.m
pc
pc
lgth
lgth
lgth
lgth
lgth
pc
pc
pc
sq.m
sq.m
lgth
lgth
280.00
269.00
26.50
32.00
28.50
26.50
28.50
250.00
pc
pc
pc
pc
pc
pc
pc
sack
565.00
sq.m
sq.m
l.m
l.m
l.m
l.m
sq.m
840.00
570.00
sht
sht
1,530.00
l.m
1,593.00
1,340.00
985.00
256.00
4,680.00
665.00
450.00
10,080.00
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
253.60
112.20
690.00
345.00
192.00
223.00
82.00
330.00
108.00
1,200.00
pc
pc
lgth
lgth
lgth
lgth
lgth
lgth
lgth
sht
roll
unit
4,100.00
2,870.00
1,450.00
1,140.00
862.00
8,740.00
5,250.00
4,375.00
lgth
lgth
lgth
lgth
lgth
sht
sht
sht
50.00
4,800.00
5,000.00
230.00
50.00
900.00
sq.m
unit
unit
cu.m
pc
bag
2,500.00
900.00
cu.m
bag
6,441.00
735.00
520.00
850.00
34.00
3,000.00
780.00
335.00
18.00
36.00
36.00
190.00
90.00
1,555.00
sht
pc
pc
gal
lit
pc
lgth
unit
unit
sht
kg
cu.m
sht
sht
pc
pc
pc
sht
lgth
unit
3,400.00
5,940.00
1,250.00
lgth
sht
sht
lgth
2,150.00
845.00
950.00
269.00
3,597.00
lgth
lgth
lgth
lgth
lgth
817.00
1,750.00
10.00
36.00
lgth
lgth
pc
pc
400.00
2,800.00
600.00
7,150.00
pc
m
pc
set
22.00
110.00
25.00
285.00
155.00
950.00
600.00 50pcs/sq.m
650.00 25pcs/sq.m
880.00
931.00
864.00
576.00
720.00
480.00
240.00
240.00
34.00
pc
per 8 ft.
set
lgth
m
m
m
m
sht
lgth
sht
sht
sht
sht
lgth
lgth
sq.ft
83.00
lgth
920.00
630.00
lgth
lgth
13,788.34
12,159.00
10,184.91
3,000.00
4,000.00
7,360.00
5,948.41
6,245.00
10,560.00
6,000.00
2,956.36
1,520.00
2,280.00
3,000.00
4,800.00
4,800.00
55.00
set
set
set
set
set
set
set
set
set
set
set
set
set
set
set
set
pc
49.00
50.00
47.00
220.00
213.00
800/elf truckload
(approx. 2.50cu.m)
2500/elf truckload
(approx. 2.50cu.m)
40.00
773.33
524.25
1,125.00
375.00
153.00
195.00
153.00
(manila)
kg
kg
kg
bag
bag
pc
lgth
lgth
lgth
lgth
lit
lit
pc
(pampanga)
5,100.00
1,620.00
1,360.00
1,033.00
1,016.00
595.00
525.00
360.00
(11.50m) 197.00
150.00
3,000/(18-19Cu.m)
3,700.00
2,950.00
3,200.00
33.54
32.85
lgth
lgth
lgth
1,434.00
998.00
600.00
460.00
330.00
295.00
(12.50m) 230.00
294.00
450.00
380.00
185.00
lgth
lgth
lgth
lgth
lgth
lgth
kg
cu.m
cu.m
cu.m
kg
kg
1,320.00
1,205.00
505.00
3,200.00
3,560.00
1,076.00
110.00
226.00
2,150.00
318.00
32.00
sht
2,230.00
1,053.00
7,200.00
1,350.00
92.00
260.00
1,520.00
88.00
21.50
4,581.20
4,212.00
2,685.15
4,212.00
5,379.40
4,581.20
2,800.00
2,800.00
2,600.00
2,170.80
1,475.11
757.95
1,317.00
66.00
3,036.00
1,500.00
650.00
650.00
25.52
15.00
15.00
21/ft
21/ft
2,200.00
42,000.00
62,700.00
30,500.00
26,700.00
22,900.00
40.00
40.00
42.00
4,500.00
pc
pc
pc
pc
pc
ft
ft
sq.m
pc
pc
pc
pc
pc
kg
kg
kg
Built-up
Built-up
41.00
46.00
44.00
42.00
40.00
kg
kg
kg
kg
kg
42.00
44.00
40.00
41.00
39.00
40.00
43.00
928.00
485.00
1,265.00
928.00
kg
kg
kg
kg
kg
kg
kg
Built-up
Built-up
485.00
113,770.00
23,910.00
22,450.00
58,320.00
13,475.00
9,660.00
480.00
39.00
sht
sht
sht
sht
sht
sht
pc
pc
335.00
45.00
52.00
sht
bd.ft
lgth
3,650.00
4,150.00
4,450.00
5,200.00
3,850.00
cu.m
cu.m
cu.m
cu.m
cu.m
12,000.00
5,818.00
14,180.00
6,719.00
1,062.00
895.00
600.00
3,100.00
8,400.00
550.00
135.00
355.00
90.00
240.00
280.00
310.00
687.00
510.00
1,896.00
925.00
16,050.00
1,200.00
pc
pc
sht
sht
pc
22.00
648.00
569.00
2,793.00
1,237.00
2,059.00
402.00
541.00
466.00
1,421.00
415.00
771.00
425.00
0.75
541.00
468.00
1,421.00
415.00
22.00
648.00
2,793.00
569.00
1,237.00
2,059.00
45.00
402.00
10.00
60.00
62.00
56.00
58.00
4,925.00
4,045.00
3,510.00
3,300.00
1,705.00
1,283.00
827.00
442.00
617.00
292.00
815.00
355.00
192.00
90.00
(+48%)
(+50%)
549.12/m
21.12/ft
6.2/pc
4.7/pc
Pick-up Price
Pick-up Price
18/pc
580/sack
1,100/set
404/gal (Davies)
597/gal (Davies)
1,293.00
1,014.00
633.00
Pick-up Price
1.20sq.m/sack
424.20/gal (Boysen)
626.85/gal (Boysen)
lgth
lgth
lgth
1,980/tin
220/box
260/pc
45/pc
55/pc
130/pc
3,250 /m (nonVAT)
4,150 /m (nonVAT)
4,050 /m (nonVAT)
5,000 /m (nonVAT)
4,300 /m (nonVAT)
3,600 /m (VAT)
4,500 /m (VAT)
4,550 /m (VAT)
5,300 /m (VAT)
4,700 /m (VAT)
21,230.00
450.00
130.00
800.00
174.00
143.00
2,750.00
1,098.00
10,417.00
842.00
9,095.00
kg.
65.00 kg.
cu.m.
200.00 bag
1,530.00
713.00
815.00
375.00
192.00
105.00
27,590.00
6,090.00
310.00
335.00
335.00
2,995.00
pc
pc
pc
pc
pc
pc
sht.
sht.
l.m.
/8 ft length
/8 ft length
roll (1mWide x 50m Length)
EARTHWORKS
1 SITE GRADING
A.
EQUIPMENT
1 Bull Dozer
1 Pay Loader
2 Dump Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
~
1,800.00 /hr
1,600.00 /hr
1400 /hr
=
=
=
=
=
=
1,800.00
1,600.00
2,800.00
0,049.00
0,749.88
6,998.88
~
~
~
~
~
50.00
37.50
75.00
50.00
=
=
=
=
=
=
0,050.00
0,187.50
0,150.00
0,050.00
0,052.50
0,490.00
MANPOWER
1 Foreman
5 Laborer
2 Operator
1 Driver
Vat, 12%
/hr
/hr
/hr
/hr
Sub-total
C.
OUTPUT
D.
80.00 sq.m/hr
1 Bull Dozer
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total
~
~
~
~
~
~
24.13
10.00
27.75
8.96
Php 35.00
Php 45.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19
TOTAL COST
11,029.07
PHP
137.86
2 EXCAVATION
A.
EQUIPMENT
1 Backhoe
1 Pay Loader
3 Dump Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
~
1,900.00 /hr
1,500.00 /hr
1,400.00 /hr
=
=
=
=
=
=
1,900.00
1,500.00
4,200.00
0,059.36
0,919.12
8,578.48
~
~
~
~
~
50.00
37.50
75.00
47.50
=
=
=
=
=
0,050.00
0,187.50
0,150.00
0,142.50
0,063.60
MANPOWER
1 Foreman
5 Laborer
2 Operator
3 Driver
Vat, 12%
/hr
/hr
/hr
/hr
Sub-total
C.
OUTPUT
D.
= 0,593.60
60.00 cu.m/hr
1 Backhoe
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total
~
~
~
~
~
~
24.13
10.00
27.75
8.96
Php 35.00
Php 45.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19
TOTAL COST
12,712.27
PHP
211.87
EQUIPMENT
1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
~
~
1,500.00
800.00
600.00
400.00
/hr
/hr
/hr
/hr
=
=
=
=
=
=
=
1,500.00
0,800.00
0,600.00
0,400.00
0,043.40
0,401.21
3,744.61
~
~
~
~
~
50.00
37.50
75.00
-
/hr
/hr
/hr
/hr
=
=
=
=
=
=
0,050.00
0,112.50
0,225.00
0,000.00
0,046.50
0,434.00
=
=
=
=
0,010.00
0,008.00
0,014.00
0,005.44
MANPOWER
1 Foreman
3 Laborer
3 Operator
1 Driver
Vat, 12%
Sub-total
C.
OUTPUT
D.
50.00 cu.m/hr
1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Oil, 10% of Fuel
37.44 Liter of Fuel
2.74 Liter of Oil
Sub-total
E.
~
~
~
~
~
~
~
10.00
8.00
14.00
5.44
2.74
Php 35.00
Php 45.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
= 1,310.40
= 0,123.48
= 1,433.88
= 15,000.00
20,612.49
PHP
PHP
PHP
300.00
112.25
412.25
EQUIPMENT
1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
~
~
1,500.00
800.00
600.00
400.00
/hr
/hr
/hr
/hr
=
=
=
=
=
=
=
1,500.00
0,800.00
0,600.00
0,400.00
0,043.40
0,401.21
3,744.61
~
~
~
~
~
50.00
37.50
75.00
-
/hr
/hr
/hr
/hr
=
=
=
=
=
=
0,050.00
0,112.50
0,225.00
0,000.00
0,046.50
0,434.00
=
=
=
=
0,010.00
0,008.00
0,014.00
0,005.44
MANPOWER
1 Foreman
3 Laborer
3 Operator
1 Driver
Vat, 12%
Sub-total
C.
OUTPUT
D.
50.00 cu.m/hr
1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Oil, 10% of Fuel
37.44 Liter of Fuel
3.74 Liter of Oil
Sub-total
E.
~
~
~
~
~
~
~
10.00
8.00
14.00
5.44
3.74
Php 35.00
Php 45.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
= 1,310.40
= 0,168.48
= 1,478.88
= 54,000.00
TOTAL COST
59,657.49
PHP
PHP
PHP
1,080.00
113.15
1,193.15
EQUIPMENT
1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
~
~
~
~
1,500.00
800.00
600.00
400.00
/hr
/hr
/hr
/hr
=
=
=
=
1,500.00
0,800.00
0,600.00
0,400.00
~
~
= 0,047.60
= 0,401.71
= 3,749.31
MANPOWER
1 Foreman
4 Laborer
3 Operator
1 Driver
Vat, 12%
~
~
~
~
~
50.00
37.50
75.00
-
/hr
/hr
/hr
/hr
Sub-total
C.
OUTPUT
D.
=
=
=
=
=
=
0,050.00
0,150.00
0,225.00
0,000.00
0,051.00
0,476.00
=
=
=
=
0,010.00
0,008.00
0,014.00
0,005.44
50.00 cu.m/hr
1 Pay Loader
1 Road Grader
1 Road Roller
1 Water Truck
Oil, 10% of Fuel
37.44 Liter of Fuel
3.74 Liter of Oil
Sub-total
~
~
~
~
~
~
~
10.00
8.00
14.00
5.44
3.74
Php 35.00
Php 45.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
= 1,310.40
= 0,168.48
= 1,478.88
TOTAL COST
5,704.19
PHP
114.08
EQUIPMENT
1 Pay Loader
1 Road Grader
1 Road Roller
2 Dump Truck
1 Water Truck
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
~
~
~
1,500.00 /hr
800.00 /hr
600.00 /hr
1400 /hr
400.00 /hr
=
=
=
=
=
=
=
=
1,500.00
0,800.00
0,600.00
2,800.00
0,400.00
0,047.60
0,737.71
6,885.31
~
~
~
~
~
50.00
37.50
75.00
-
=
=
=
=
=
=
0,050.00
0,150.00
0,225.00
0,000.00
0,051.00
0,476.00
MANPOWER
1 Foreman
4 Laborer
3 Operator
3 Driver
Vat, 12%
/hr
/hr
/hr
/hr
Sub-total
C.
OUTPUT
D.
1 Pay Loader
50.00 cu.m/hr
10.00 Lit/hr
= 0,010.00
1 Road Grader
1 Road Roller
2 Dump Truck
1 Water Truck
Oil, 10% of Fuel
92.94 Liter of Fuel
9.29 Liter of Oil
Sub-total
E.
~
~
~
~
~
~
~
8.00
14.00
27.75
5.44
9.29
Php 35.00
Php 45.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
=
=
=
=
= 3,252.90
= 0,418.23
= 3,671.13
= 15,900.00
TOTAL COST
26,932.44
PHP
PHP
PHP
318.00
220.65
538.65
No. of days(Foundation) =
EQUIPMENT
6 Water Pump
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
0,008.00
0,014.00
0,055.50
0,005.44
~
~
~
150.00 /hr
~
~
37.50 /hr
=
=
=
=
0,900.00
0,012.60
0,109.51
1,022.11
MANPOWER
3 Laborer
Vat, 12%
Sub-total
C.
D.
6 Water Pump
Oil, 10% of Fuel
12.00 Liter of Fuel
1.20 Liter of Oil
Sub-total
TOTAL COST
= 0,112.50
= 0,013.50
= 0,126.00
0.33
~
~
~
~
2.00
1.20
Php 35.00
Php 45.00
Lit/hr
Lit/hr
/Lit
/Lit
= 0,012.00
= 0,420.00
= 0,054.00
= 0,474.00
1,622.11
PHP 38,969.66
/hr
/hr
/hr
/sq.m
/hr
/hr
/hr
/cu.m
/hr
/hr
/hr
/hr
/cu.m
/cu.m
/cu.m
/hr
/hr
/hr
/hr
/cu.m
/cu.m
/cu.m
/hr
/hr
/hr
/cu.m
/hr
/hr
/hr
/hr
/cu.m
/cu.m
/cu.m
1
/hr
/hr
/hr
CIVIL WORKS
1 CONCRETING -4000 PSI, 3/4 Aggregates, Pumpcrete Design
A.
EQUIPMENT
2 Transit Mixer
1 Pay Loader
1 Batching Plant
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
~
1,800.00 /hr
1,600.00 /hr
1400 /hr
=
=
=
=
=
=
3,600.00
1,600.00
1,400.00
0,061.60
0,799.39
7,460.99
~
~
~
~
~
50.00
37.50
75.00
50.00
=
=
=
=
=
=
0,050.00
0,300.00
0,150.00
0,050.00
0,066.00
0,616.00
MANPOWER
1 Foreman
8 Laborer
2 Operator
1 Driver
Vat, 12%
/hr
/hr
/hr
/hr
Sub-total
C.
OUTPUT
D.
18.00 cu.m/hr
1 Bull Dozer
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total
E.
~
~
~
~
~
~
24.13
10.00
27.75
8.96
Php 35.00
Php 45.00
~
~
~
~
210.00
900.00
400.00
40.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19
MATERIALS
13
234 bags Portland Cement
0.9 16.74 cu.m 3/4 Course Aggregate
0.6 10.08 cu.m Fine Sand
1 18.00 liter Admixture
Sub-total
/hr
/hr
/hr
/hr
=
=
=
=
=
TOTAL COST
49,140.00
15,066.00
4,032.00
0,720.00
68,958.00
80,575.18
PHP
PHP
PHP
4,476.40
645.40
5,121.80
EQUIPMENT
2 Transit Mixer
1,800.00 /hr
= 3,600.00
1 Pay Loader
1 Batching Plant
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,600.00 /hr
1400 /hr
=
=
=
=
=
1,600.00
1,400.00
0,061.60
0,799.39
7,460.99
~
~
~
~
~
50.00
37.50
75.00
50.00
=
=
=
=
=
=
0,050.00
0,300.00
0,150.00
0,050.00
0,066.00
0,616.00
MANPOWER
1 Foreman
8 Laborer
2 Operator
1 Driver
Vat, 12%
/hr
/hr
/hr
/hr
Sub-total
C.
OUTPUT
D.
18.00 cu.m/hr
1 Bull Dozer
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total
~
~
~
~
~
~
24.13
10.00
27.75
8.96
Php 35.00
Php 45.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19
TOTAL COST
11,617.18
PHP
645.40
/hr
/hr
/hr
/hr
/cu.m
/sq.m
/sq.m
/hr
/hr
/hr
/sq.m
FORMWORKS
1 PANEL FORM - Installing of Penolic Board to Penolic Frame (Sub-con Works)
A.
EQUIPMENT
2 (by owner)
1 (by owner)
1 (by owner)
~
~
~
~
/hr
/hr
/hr
=
=
=
=
=
0,000.00
0,000.00
0,000.00
0,000.00
0,000.00
~
~
~
43.75 /hr
37.50 /hr
=
=
=
=
0,043.75
0,112.50
0,018.75
0,175.00 /hr
Sub-total
B.
MANPOWER
1 Carpenter
3 Laborer
Vat, 12%
Sub-total
Productivity =
C.
OUTPUT
D.
4.50 sq.m/hr
1 (by owner)
1 (by owner)
2 (by owner)
~
~
~
~
~
~
0.00
0.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
Sub-total
TOTAL COST
50 pcs/day
0.72 sq.m
36 sq.m/day
4.5 sq.m/hr
= 0,000.00
= 0,000.00
= 0,000.00
= 0,000.00
= 0,000.00
= 0,000.00 /hr
175.00 /hr
### /sq.m
Laborer
Carpenter
Provincial Rate
Minimum
Maximum
250
280
280
300
Manila Rate
Applied Rate Rate per Hour
Minimum
Maximum
270
300
300
37.5
310
350
350
43.75
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
500.00 kgs/hr
C.
OUTPUT
D.
MATERIALS
~
~
24.13 Lit/hr
10.00 Lit/hr
TOTAL COST
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.
OUTPUT
D.
MATERIALS
500.00 kgs/hr
24.13 Lit/hr
10.00 Lit/hr
TOTAL COST
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
500.00 kgs/hr
C.
OUTPUT
D.
MATERIALS
~
~
24.13 Lit/hr
10.00 Lit/hr
TOTAL COST
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.
OUTPUT
D.
MATERIALS
500.00 kgs/hr
~
~
24.13 Lit/hr
10.00 Lit/hr
TOTAL COST
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
500.00 kgs/hr
C.
OUTPUT
D.
MATERIALS
~
~
24.13 Lit/hr
10.00 Lit/hr
TOTAL COST
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.
OUTPUT
500.00 kgs/hr
D.
MATERIALS
~
~
24.13 Lit/hr
10.00 Lit/hr
TOTAL COST
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
500.00 kgs/hr
C.
OUTPUT
D.
MATERIALS
~
~
24.13 Lit/hr
10.00 Lit/hr
TOTAL COST
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.
OUTPUT
500.00 kgs/hr
D.
MATERIALS
~
~
24.13 Lit/hr
10.00 Lit/hr
TOTAL COST
EQUIPMENT
1 Bar Bender
1 Bar Cutter
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
1,100.00 /hr
1,100.00 /hr
~
~
~
~
50.00 /hr
38.75 /hr
37.50 /hr
MANPOWER
1 Foreman
4 Steelman
4 Laborer
Vat, 12%
Sub-total
C.
OUTPUT
D.
MATERIALS
500.00 kgs/hr
~
~
24.13 Lit/hr
10.00 Lit/hr
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
=
=
=
=
=
1,100.00
1,100.00
0,039.76
0,268.77
2,508.53
=
=
=
=
=
0,050.00
0,155.00
0,150.00
0,042.60
0,397.60 /hr
= 0,024.13
= 0,010.00
= 0,034.13 /hr
2,940.26 /hr
PHP
5.88 /sq.m
STEELWORKS
1 STEEL COLUMNS - W -Section
A.
EQUIPMENT
1 Tower Crane
1 Welding Machine
2 Chain Block
Minor Tools, 10% of Manpower
Vat, 12%
Sub-total
B.
~
~
~
~
~
1,800.00 /hr
1,600.00 /hr
1400 /hr
=
=
=
=
=
=
1,800.00
1,600.00
2,800.00
0,067.20
0,752.06
7,019.26
~
~
~
~
~
50.00
43.75
75.00
50.00
=
=
=
=
=
=
0,050.00
0,350.00
0,150.00
0,050.00
0,072.00
0,672.00
MANPOWER
1 Foreman
8 Welder
2 Operator
1 Driver
Vat, 12%
/hr
/hr
/hr
/hr
Sub-total
C.
OUTPUT
D.
kgs/hr
1 Tower Crane
1 Pay Loader
2 Dump Truck
Oil, 10% of Fuel
89.63 Liter of Fuel
8.96 Liter of Oil
Sub-total
TOTAL COST
~
~
~
~
~
~
24.13
10.00
27.75
8.96
Php 35.00
Php 45.00
Lit/hr
Lit/hr
Lit/hr
Lit/hr
/Lit
/Lit
= 0,024.13
= 0,010.00
= 0,055.50
= 3,136.88
= 0,403.31
= 3,540.19
11,231.45
#DIV/0!
/hr
/hr
/hr
/sq.m
SCOPE OF WORKS
UNITS
MATERIALS
EARTHWORKS
A.
B.
Site Grading
Excavation
b.1 Ordinary
b.1.1 Manual
b.1.2 Bulk
b.2 Adobe
b.2.1 Manual
b.2.2 Bulk
C.
Aggregate Sub-base Course
c.1 Manual
c.2 Bulk
D.
Aggregate Base Course
d.1 Manual
d.2 Bulk
E.
Backfilling & Compaction
F.
Borrow Fill & Compaction
G.
Dewatering (No. of work days =
sq.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
###
cu.m
cu.m
cu.m
cu.m
lot
300.00
1,080.00
180.00
LABOR SCALE
Small
LABOR SCALE
Medium
137.86
211.87
112.25
113.15
114.43
223.49
38,969.66
Large
300.00
1,080.00
180.00
-
137.86
211.87
412.25
1,193.15
114.43
403.49
38,969.66
-
300.00
1,080.00
180.00
-
DESCRIPTION
Scaffoldings
H-Frames
1.20 x 1.70m H-Frame (G.I.)
1.20 x 1.20m H-Frame (G.I.)
1.20 x 0.90m H-Frame (G.I.)
1.20 x 1.70m H-Frame (B.I.)
1.20 x 1.20m H-Frame (B.I.)
1.20 x 0.90m H-Frame (B.I.)
0.90 x 1.70m H-Frame (G.I.)
0.90 x 1.20m H-Frame (B.I.)
0.90 x 0.90m H-Frame (B.I.)
Other Accessories
2.50m Cross Brace
2.25m Cross Brace
2.00m Cross Brace
1.80m Cross Brace
1.70m Cross Brace
1.50m Cross Brace
0.90m
1.20m
0.70m
2.20m
WIDTH
1.20
1.20
1.20
1.20
1.20
1.20
0.90
0.90
0.90
HEIGHT
1.70
###
0.90
1.70
###
0.90
1.70
1.20
###
0.90m
0.70m
2.00m
1.80m
Lock Vertical
Distance
1.20
0.70
0.70
1.20
0.70
0.70
1.20
0.70
0.70
1.70m
1.55m
1.25m
2.20
2.00
1.80
2.19
2.40
2.40
2.19
2.40
2.40
2.19
2.40
2.40
1.84
2.09
2.09
1.84
2.09
2.09
1.84
2.09
2.09
1.60
1.87
1.87
1.60
1.87
1.87
1.60
1.87
1.87
1.34
1.66
1.66
1.34
1.66
1.66
1.34
1.66
1.66
1.55
1.25
1.20
1.55
1.55
1.20
1.55
1.55
1.20
1.55
1.55
0.98
1.38
1.38
0.98
1.38
1.38
0.98
1.38
1.38
0.35
1.04
1.04
0.35
1.04
1.04
0.35
1.04
1.04
1. Item No.
2. Description
3. Quantity
4. Unit
II-C-3-b-iv-*** 6" chb wall
100.00
sq.mts.
5. Sequence of Operation
1. Lay-out & hauling of materials 2. Inst of batterboards / fab of rebars & forms / mixing of concrete 3. Inst
of rebars / laying of chb 4. Cleaning
No.
Description
Quantity
Unit
Unit Cost
Amount
1
Cement - type I, 40kgs/bag
20.00
bags
130.00
2,600.00
2
6" chb - non load bearing
1,250.00
pcs.
8.50
10,625.00
M
3
Sand
20.00 cu.m.
240.00
4,800.00
A
4
Reinforcing bars - 10mm x 6.00m.
10.00
pcs.
320.00
3,200.00
T
5
Concrete nail - assorted size
1.00
kgs.
45.00
45.00
E
6
Common wire nail - assorted size
1.00
kgs.
30.00
30.00
R
7
Nylon cord 0.15mm x 100m
2.00
rolls
10.00
0.20
I
8
Batterboard - assorted lumber
20.00 bd.ft.
22.00
440.00
A
9
Hacksaw blade
1.00
pc.
70.00
70.00
L
10
Tie wire - G.I. gauge no.16
0.05
rolls
1,000.00
50.00
S
11
Water
40.00
gals.
20.00
800.00
12
Waste fator
8.00
%
20,060.20
1,604.82
13
6. Direct Material Cost
P 24,265.02
No.
Description
Number
Hours
Rate / Hour
Amount
1
Project In-charge
1.00
3.20
75.00
240.00
2
Field Engineer
1.00
3.20
43.75
140.00
3
Timekeeper
1.00
3.20
40.00
128.00
L
4
Warehouseman
1.00
3.20
43.75
140.00
A
5
Foreman
1.00
3.20
43.75
140.00
B
6
Leadman
1.00
16.00
40.00
640.00
O
7
Operator
1.00
16.00
37.50
600.00
R
8
Mason
5.00
16.00
37.50
3,000.00
9
Steelman
1.00
16.00
37.50
600.00
10
Laborer
8.00
16.00
31.25
4,000.00
11
Utility
1.00
3.20
31.25
100.00
7. Direct Labor Cost
P 9,728.00
No.
Description
Number
Hours
Rate / Hour
Amount
E
1
Bagger Mixer
1.00
16.00
50.00
800.00
Q
2
Power Sprayer
1.00
16.00
10.00
160.00
U
3
Hacksaw
1.00
16.00
2.00
32.00
I
4
###
P
5
###
M
6
###
E
7
###
N
8
###
T
9
###
8. Direct Equipment Cost
P 992.00
9. Total Direct Cost (5+6+7)
P 34,985.02
20. Work days to 10. Overhead Expenses (OE) = 7 % of ( 9 )
2,448.95
complete
1,123.02
11. Contingencies (C) = 3 % of ( 9 + 10 )
2 days
771.14
12. Miscellaneous Expenses (ME) = 2 % of ( 9 + 10 + 11 )
21. Calendar days 13. Contractor's Profit (CP) = 8 % of ( 9 + 10 + 11 + 12 )
3,146.25
to complete 14. Value Added Tax (VAT) = 1 / 1.10 x 0.10 % of ( 7 + 8 )
974.55
2 days
318.05
15. Expanded Witholding Tax (EWT) = 1 / 1.10 x 0.10 x 0.10 % of ( 9 )
22. Average out- 16. Total Indirect Cost (TIC) = 10 + 11 + 12 + 13 + 14 + 15
P 8,781.95
put per working17. Total Cost (TC) = 9 + 16
P 43,766.97
day
437.67
18. Derived Unit Cost (DUC) = 17 / 3
50.00 sq.mts. 19. Corrected Unit Cost (CUC)
P 437.67
a. Course Aggregates
i.
G-1
ii.
3/4 Gravel
iii.
3/4 Crushed Gravel
b. Course Aggregates
i.
Vibro Sand
ii.
Riverwashed Sand
c. Others (Boulders)
i.
ii.
iii.
2. Cement
a. Portland Cement
i.
ii.
iii.
b. Pozzolan Cement
i.
ii.
iii.
3. Reinforcing Steel Bar
a. Grade 60
b. Grade 40
c. Grade 33
4. G.I. Wire
a. Gauge # 18
b. Gauge # 16
Supplier A
Amount
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
cu.m
bag
bag
bag
bag
bag
bag
kg
kg
kg
kg
kg
Supplier name
Supplier B
Amount
Supplier name
LABOR RATES
al Unit Cost
Supplier C
Amount
Supplier name
Item
I. Indirect Manpower
Applied Price
1. Accountant
2. Cadet Engineer
3. Carpenter
0
4. Cost Engineer
0
5. Driver
0
6. Electrician
7. Field Engineer
0
8. Foreman
0
9. Glass Installer
10. Guard
0
11. Heavy Equipment Operator
0
12. Laborer
0
13. Leadman
14. Mason
15. Mechanic
0
16. Messenger
0
17. Mixer Operator
0
18. Painter
19. Plumber
0
20. Project In-charge
0
21. Screeder Operator
0
22. Steelman
23. Surveying Aide
0
24. Surveyor
0
25. Tile Setter
0
26. Timekeeper
27. Utility
0
28. Utility
0
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32.
33.
1
Provincial Rate
Minimum
Maximum
PHP 400.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
2
Manila Rate
Minimum
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 700.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
Applied Rate
600
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Location of Project:
5
4
3
2
1
Unit Cos
Unit
I. Rentals
1. Metal Forms
a. Metal Panels
i.
750 x 1800mm
ii.
750 x 1200mm
iii.
750 x 900mm
iv.
650 x 1800mm
v.
650 x 1500mm
vi.
650 x 1200mm
vii. 600 x 1800mm
viii. 600 x 1500mm
ix.
600 x 1200mm
x.
600 x 900mm
xi.
600 x 600mm
xii. 550 x 1800mm
xiii. 550 x 1500mm
xiv. 550 x 1200mm
xv.
550 x 900mm
xvi. 500 x 1800mm
xvii 500 x 1500mm
xviii. 450 x 1800mm
xix. 450 x 1500mm
xx.
450 x 900mm
xxi 400 x 1800mm
xxii 400 x 1500mm
xxii 400 x 1200mm
xxiv. 400 x 900mm
xxv. 400 x 600mm
xxvi. 350 x 1800mm
xxvii. 350 x 1500mm
350 x 1200mm
300 x 1800mm
300 x 1500mm
300 x 900mm
300 x 600mm
250 x 1800mm
250 x 1500mm
250 x 900mm
200 x 1800mm
200 x 1200mm
150 x 1800mm
150 x 1500mm
150 x 1200mm
150 x 600mm
100 x 1500mm
1.80 Corner Section
1.50 Corner Section
1.20 Corner Section
0.90 Corner Section
0.60 Corner Section
1.80 Exterior Angle
Supplier A
Rate/Day
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 4.00
PHP 3.00
PHP 2.33
PHP 3.50
PHP 3.00
PHP 2.67
PHP 3.33
PHP 2.83
PHP 2.50
PHP 1.83
PHP 1.58
PHP 3.08
PHP 2.67
PHP 2.33
PHP 1.67
PHP 2.83
PHP 2.50
PHP 2.58
PHP 2.33
PHP 1.42
PHP 2.33
PHP 2.17
PHP 1.83
PHP 1.33
PHP 1.25
PHP 2.17
PHP 2.00
PHP 1.67
PHP 2.00
PHP 1.83
PHP 1.17
PHP 1.00
PHP 1.83
PHP 1.67
PHP 1.08
PHP 1.67
PHP 1.17
PHP 1.50
PHP 1.33
PHP 1.00
PHP 0.67
PHP 1.17
PHP 1.67
PHP 1.67
PHP 1.17
PHP 0.92
PHP 0.67
PHP 0.50
Supplier name
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
Supplier B
Rate/Day
13
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 0.42
PHP 0.33
PHP 0.25
PHP 0.17
PHP 0.12
PHP 0.30
PHP 0.30
PHP 0.25
PHP 0.20
PHP 1.42
PHP 0.05
PHP 0.03
PHP 0.02
PHP 0.03
PHP 0.03
PHP 3.50
PHP 3.33
PHP 0.90
PHP 2.50
PHP 0.54
PHP 3.08
PHP 0.83
PHP 1.67
PHP 1.50
PHP 2.83
PHP 2.50
PHP 2.17
PHP 1.50
PHP 2.58
PHP 2.33
PHP 2.00
PHP 1.42
PHP 3.10
PHP 2.33
PHP 2.17
PHP 1.83
PHP 1.83
PHP 1.25
PHP 2.17
PHP 2.00
PHP 1.67
PHP 1.25
PHP 1.17
PHP 2.33
PHP 2.00
PHP 1.83
PHP 1.50
PHP 1.17
PHP 1.00
PHP 2.17
PHP 1.83
PHP 1.67
PHP 1.33
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
c
o
r
r
e
c
t
e
d
u
n
i
t
c
o
s
250 x 900mm
200 x 1800mm
200 x 1500mm
200 x 1200mm
200 x 900mm
200 x 600mm
150 x 1800mm
150 x 1500mm
150 x 1200mm
150 x 900mm
100 x 1800mm
100 x 1500mm
100 x 1200mm
100 x 900mm
1.80 Outer Angle
1.50 Outer Angle
1.20 Outer Angle
0.90 Outer Angle
0.60 Outer Angle
1.80 Inside Corner
1.50 Inside Corner
0.90 Inside Corner
1.50 Filler Angle
1.20 Filler Angle
0.60 Filler Angle
1.80 Inside Corner for Slab
0.90 Inside Corner for Slab
0.60 Inside Corner for Slab
d. Gang Form
D-Beam x 3.30m (2.5mm thk)
D-Beam x 2.40m (2.5mm thk)
D-Beam x 1.40m (2.5mm thk)
D-Beam x 1.20m (2.5mm thk)
D-Beam x 0.60m (2.5mm thk)
Splice Plate
Cast Plate
Wing Nut 21mm
Wing Nut 17mm
Wing Nut 12mm
Tie Rod - 17mm x 300mm
e. Other Accessories
Wedge Pin
C-Purlins
2. Scaffoldings
a. H-Frames
i.
1.70 x 1.20m H-Frame (G.I.)
ii.
1.20 x 1.20m H-Frame (G.I.)
iii.
0.90 x 1.20m H-Frame (G.I.)
iv.
1.70 x 1.20m H-Frame (B.I.)
v.
1.20 x 1.20m H-Frame (B.I.)
vi.
0.90 x 1.20m H-Frame (B.I.)
vii. 1.70 x 0.90m H-Frame (G.I.)
viii. 1.20 x 0.90m H-Frame (B.I.)
ix.
0.90 x 0.90m H-Frame (B.I.)
b. Other Accessories
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 1.08
PHP 1.67
PHP 0.30
PHP 1.17
PHP 1.00
PHP 0.83
PHP 1.50
PHP 0.23
PHP 1.00
PHP 0.14
PHP 0.18
PHP 0.15
PHP 0.12
PHP 0.09
PHP 0.50
PHP 0.42
PHP 0.33
PHP 0.25
PHP 0.17
PHP 1.67
PHP 1.42
PHP 0.92
PHP 0.33
PHP 0.20
PHP 0.15
PHP 1.67
PHP 0.25
PHP 0.16
PHP 1.68
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 1.70
PHP 0.92
PHP 0.83
PHP 1.70
PHP 0.92
PHP 0.83
PHP 1.00
PHP 0.75
PHP 0.67
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
PHP 2.99
PHP 2.18
PHP 1.27
PHP 1.09
PHP 0.54
PHP 0.18
PHP 0.18
PHP 0.11
PHP 0.11
PHP 0.11
PHP 0.50
u
n
i
t
c
o
s
t
i.
2.50m Cross Brace
ii.
2.25m Cross Brace
iii.
2.00m Cross Brace
iv.
1.80m Cross Brace
v.
1.70m Cross Brace
vi.
1.50m Cross Brace
vii. Straight Props (outer pipe)
viii. Straight Props (inner pipe)
ix.
Fixed U-head 2"
x.
Fixed U-head 4"
xi.
Adjustable U-head 2"
xii. Adjustable U-head 3"
xii. Adjustable U-head 4"
xiv. Adjustable Base Jack
xv.
Joint Pin
c. Waller Pipe & Accessories
1" x 6.00m GI Pipe
i.
1" x 5.50m GI Pipe
ii.
1" x 5.00m GI Pipe
iii.
1" x 4.50m GI Pipe
iv.
1" x 4.00m GI Pipe
v.
1" x 3.00m GI Pipe
vi.
vii. 1" x 2.50m GI Pipe
viii. 1" x 2.40m GI Pipe
1" x 2.00m GI Pipe
ix.
1" x 1.85m GI Pipe
x.
1" x 1.60m GI Pipe
xi.
xii. 1" x 1.50m GI Pipe
xiii. 1" x 1.00m GI Pipe
xiv. 1" x 0.80m GI Pipe
1" x 0.70m GI Pipe
xv.
xvi. 1" x 0.50m GI Pipe
xvii 1" x 0.40m GI Pipe
xviii. Swivel Clamp
xix. Fixed Clamp
1" x 6.00m Double Pipe
xx.
xxi 1" x 5.00m Double Pipe
xxii 1" x 4.00m Double Pipe
xxii 1" x 3.00m Double Pipe
xxiv. 1" x 2.50m Double Pipe
xxv. 1" x 2.00m Double Pipe
xxvi. 1" x 1.50m Double Pipe
xxvii. 1" x 1.00m Double Pipe
d. Steel Headers
i.
2" x 4" BI Steel Headers x 3.00m
ii.
2" x 4" BI Steel Headers x 2.44m
iii.
2" x 4" BI Steel Headers x 2.00m
iv.
2" x 4" BI Steel Headers x 1.80m
v.
2" x 4" BI Steel Headers x 1.50m
vi.
2" x 4" BI Steel Headers x 1.20m
vii. 2" x 4" I-beam Steel Headers x 3.00m
viii. 2" x 4" I-beam Steel Headers x 1.50m
d. Hanging Steel Scaffolds
i.
Gondola
ii.
Gondola Bracket 0.40
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.33
PHP 0.67
PHP 0.67
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.50
PHP 0.07
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
piece
PHP 2.33
PHP 2.17
PHP 2.00
PHP 1.83
PHP 1.67
PHP 1.33
PHP 1.17
PHP 1.09
PHP 1.00
PHP 0.93
PHP 0.90
PHP 0.83
PHP 0.83
PHP 0.81
PHP 0.80
PHP 0.78
PHP 0.77
PHP 0.29
PHP 0.29
PHP 4.66
PHP 4.00
PHP 3.34
PHP 2.66
PHP 2.34
PHP 2.00
PHP 1.66
PHP 1.34
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
piece
piece
piece
piece
piece
piece
piece
piece
PHP 1.17
PHP 1.00
PHP 1.00
PHP 0.83
PHP 0.67
PHP 0.50
PHP 4.59
PHP 4.20
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
piece
piece
PHP 3.17
PHP 5.67
FEMD
FEMD
iii.
Gondola Bracket 0.55
iv.
Steel Platform (CP) 0.40 x 2.00m
v.
Steel Platform (EW) 0.40 x2.00m
vi.
Steel Ladder (Expanded Metal)
vii. Double C-Purlins Flatform x 3.00m
d. Others
i.
Caster Wheel (Swivel)
piece
piece
piece
piece
piece
piece
piece
PHP 4.79
PHP 1.67
PHP 5.79
PHP 21.58
PHP 2.94
PHP 1.95
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
FEMD
LABOR RATES
Unit Cost
Supplier B
Supplier name
Supplier C
Rate/Day
14
Applied Rate
Supplier name
14.00
3.00
2.33
3.50
3.00
2.67
3.33
2.83
2.50
1.83
1.58
3.08
2.67
2.33
1.67
2.83
2.50
2.58
2.33
1.42
2.33
2.17
1.83
1.33
1.25
2.17
2.00
1.67
2.00
1.83
1.17
1.00
1.83
1.67
1.08
1.67
1.17
1.50
1.33
1.00
0.67
1.17
1.67
1.67
1.17
0.92
0.67
0.50
Item
I. Indirect Manpower
1. Accountant
2. Cadet Engineer
3. Carpenter
4. Cost Engineer
5. Driver
6. Electrician
7. Field Engineer
8. Foreman
9. Glass Installer
10. Guard
11. Heavy Equipment Operator
12. Laborer
13. Leadman
14. Mason
15. Mechanic
16. Messenger
17. Mixer Operator
18. Painter
19. Plumber
20. Project In-charge
21. Screeder Operator
22. Steelman
23. Surveying Aide
24. Surveyor
25. Tile Setter
26. Timekeeper
27. Utility
28. Utility
29. Warehouseman
30. Waterproofing Applicator
31. Welder
32.
33.
1
Provincia
Minimum
PHP 400.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
0.42
0.33
0.25
0.17
0.12
0.30
0.30
0.25
0.20
1.42
0.05
0.03
0.02
0.03
0.03
3.50
3.33
0.90
2.50
0.54
3.08
0.83
1.67
1.50
2.83
2.50
2.17
1.50
2.58
2.33
2.00
1.42
3.10
2.33
2.17
1.83
1.83
1.25
2.17
2.00
1.67
1.25
1.17
2.33
2.00
1.83
1.50
1.17
1.00
2.17
1.83
1.67
1.33
1.08
1.67
0.30
1.17
1.00
0.83
1.50
0.23
1.00
0.14
0.18
0.15
0.12
0.09
0.50
0.42
0.33
0.25
0.17
1.67
1.42
0.92
0.33
0.20
0.15
1.67
0.25
2.99
2.18
1.27
1.09
0.54
0.18
0.18
0.11
0.11
0.11
0.50
0.16
1.68
1.70
0.92
0.83
1.70
0.92
0.83
1.00
0.75
0.67
0.33
0.33
0.33
0.33
0.33
0.33
0.67
0.67
0.50
0.50
0.50
0.50
0.50
0.50
0.07
2.33
2.17
2.00
1.83
1.67
1.33
1.17
1.09
1.00
0.93
0.90
0.83
0.83
0.81
0.80
0.78
0.77
0.29
0.29
4.66
4.00
3.34
2.66
2.34
2.00
1.66
1.34
1.17
1.00
1.00
0.83
0.67
0.50
4.59
4.20
3.17
5.67
4.79
1.67
5.79
21.58
2.94
1.95
1
Provincial Rate
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
2
Manila Rate
Minimum
Maximum
PHP 600.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 700.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
PHP 0.00
Applied Rate
600
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Location of Project:
5
4
3
2
1
ITEM
No.
DESCRIPTION
Cement
Portland Cement
Colored Cement
M10 Cement Mortar
Portland Cement (Northern Cement)
Portland Cement (Holcim Cement)
M 7.50 Cement
M10 Cement
Reinforcing Steel Bars - Deformed Bars
Grade 60 Rebars
Grade 40 Rebars
Grade 30 Rebars
Ga. # 16 GI Wire
Concrete Aggregates / Boulders
G-1 Gravel
Agg.Sub-base Coarse
Agg.Base Coarse
Black Sand
White Sand
Light Aggregates (Dead Gravel)
Boulders
Mortar Rubber Masonry
Boulders (6-8 inches dia.)
Sand
Washed Sand (White)
Wash Sand
Crushed Gravel 3/4"
Stone Masonry (Rip Rap)
Boulders 6"-8" Diam.
Concrete
525 Ready Mixed Concrete
kgs
kgs
kgs
SUPPLIER 1
Name
Plywood / Plyboard
Lumber
Rough Tanguile
Kd Tanguile
Kd Tanguile Moulding
GOOD LUMBER S4 kd
1" x 3" x 10'
1" x 3" x 12'
1" x 4" x 12'
2" x 2" x 10'
2" x 2" x 12'
2" x 2" x 12'
2" x 3" x 10'
2" x 3" x 12'
4" x 4" x 10'
4" x 4" x 12'
1" x 5" x 10'
1" x 5" x 12'
4" x 4" x 10' Good Lumber
2" x 4" x 14' KD S4S
3" x 5" x 10' KD S4S
3" x 3" x 10' Good Lumber
2" x 2" x 10' S-4 (Good Lumber)
2"x2"x10' S4S Good Lumber
Admixtures
Curing Compound
Floor Hardener
Soil Poisoning / Termite Control
Solignum
Bolts & Screws
36mm A490 Anchor Bolt (L-850mm)
32Mm Anchor Bolt L=1300Mm
25Mm Anchor Bolt L=1000Mm
25Mm Anchor Bolt L=400Mm
20Mm Anchor Bolt L=300Mm
20Mm Anchor Bolt, L=350Mm
28Mm A307 (L=1000Mm) Anchor Bolt
28mmx1000mm Anchor Bolt (A325)
28mmx800mm Anchor Bolt
25Mm A307 (L=1000Mm) Anchor Bolt
20Mm A325 Anchor Bolt
16mm Anchor Bolt
13mmx300mm Anchor Bolt w/ standard lock nut & washer
Anchor Bolt 200mm x 300mm
20Mm X 150/95 Hlc Sleeve Anchor (Hilti)
20Mm B.I. Round Bar Ladder Rung
Self Tapping Screw
Hanger rods
Dyna Bolt 12mm x 100mm (pc)
12Mm Nut & Washer
M28 X 100Mm Machine Bolt
M25 X 100Mm Machine Bolt
M16 Bolt (Machine Bolt - 16Mm)(6"Length)
16mm Machine Bolts w/ nuts (4" long)
8Mm M.S. Bolt
6Mm M.S. Bolt
10mm Machine Bolt (L=1")
20Mm X 100Mm Stud Bolts
10Mm X 1" Bolts & Nuts
12Mm X 40Mm Long Bolts W/ Std Nuts & Washers
12Mm X 100Mm Long Dyna Bolt
12Mm Cap Screw
Self Tapping Screw
12Mm X 30Mm Flat Head Screw
Tekscrew
12mm Expansion Bolt w/ plate washer
Surveying Rod Socket
Purlins
178x50x20x2mm thk Purlins
Lc 175Mm X 50Mm X 20Mm X 2Mm Thk Purlin
Lc 175Mm X 50Mm X 12.5Mm X 2Mm Thk Purlin
Tubular Bar
175 x 50 x 3.20mm thk. B.I. Tubular
150 x 50 x 3.0mm thk B.I. Tubular
150 X 50 X 3.0Mm Thk B.I. Tubular
175 X 50 X 3.20 Tubular
12" X 10" X 3/10" (A36) Structural Tubing
12" X 10" X 1/4" (A36) Structural Tubing
2" X 4" X 0.9Mm Thk Tubular
1-1/2" X 1-1/2" Tubular
1" X 1" Tubular
2" X 4" Sch40 (4Mm Thk) Tubular
1-1/2" X 1-1/2" Sch40 (4Mm Thk) Tubular
2" x 4" Tubular Bar
2" x 6" Tubular Bar
1" x 4" Tubular Bar
4mm- 2"x4" Sch 40 Tubular
Flat Bars
1-1/4" X 1/4" Thk X 6M Flatbar (6Mm Thk)
1" X 1/4" X 6M Flatbar
100Mm X 12Mm Thk Flatbar
1-1/4" X 1/4" Thk Flatbar
1" X 1/4" Thk Flatbar
3/4" X 3/16" Thk Flatbar
2" x " thk Flat Bar
1" x " thk Flat Bar
2" X 1/4" Thk Flat Bar
12mm Square Bar
12mmx5mm thk Flat Bar
2"x"x6m Flat Bar
2"x"x6m Flat Bar
2"x3/8"x6m Flat Bar (7mm)
Epoxy Primer
Epoxy Primer Gray (ACP Concrete)
Epoxy Primer Gray (Rag J Hardware)
Epoxy Primer
Red Lead Oxide Primer
Checkered Plates
4' x 8' x 4.50mm thk Checkered Plate
4' x 8' x 6mm thk Checkered Plate
4' x 8' x 0.80mm thk Checkered Plate
Metal Decking
Metal Decking
0.80Mm Thk; 80,000Psi Steel Decking Rib-Type
0.80Mm Thk; 80,000Psi Steel Decking Flat-Type
Structural Tees
ST 12 x 60.5
ST 9 x 35
ST 2 x 3.55
Asphalt Sealer
Diamond Blade
SUPPLIER 1
Unit Price Terms
Discount
Name
SUPPLIER 2
Unit Price Terms
Discount
Name
SUPPLIER 3
Unit Price
SUPPLIER 3
Terms
Discount
REMARKS
STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
W SHAPES
tf
tw
k
bf
Y
Web
Item
No.
Designation
Area(A)
Depth(d)
tw
W 44 x
x
x
x
285
248
224
198
(mm)
54,064
46,968
42,452
37,419
(mm)
1,118.11
1,107.95
1,100.07
1,089.91
(mm)
26.01
21.97
19.99
18.01
W 40 x
x
x
x
x
x
328
298
268
244
221
192
62,193
56,516
50,839
46,258
41,806
36,452
1,016.00
1,008.13
1,000.00
992.12
982.22
970.28
23.11
21.08
19.05
18.03
18.03
18.03
W 40 x
x
x
x
x
x
x
x
x
655
593
531
480
436
397
362
324
297
123,871
112,258
100,645
90,322
82,580
74,839
68,387
61,484
56,387
1,107.95
1,091.95
1,075.44
1,061.74
1,050.04
1,040.13
1,029.97
1,020.06
1,011.94
50.04
45.47
40.89
37.08
34.04
30.99
28.45
25.40
23.62
Flange
tw
2
(mm)
13.01
10.99
10.00
9.01
11.56
10.54
9.53
9.02
9.02
9.02
25.02
22.74
20.45
18.54
17.02
15.50
14.23
12.70
11.81
bf
tf
(mm)
(mm)
300.00
45.01
300.00
40.01
300.00
35.97
300.00
30.99
454.91
452.88
450.85
449.83
449.83
449.83
43.94
40.01
35.94
32
27.05
21.08
428.50
423.93
419.35
415.54
412.50
409.45
406.91
403.99
401.96
89.92
82.04
73.91
67.06
60.96
55.88
51.05
45.97
41.91
x
x
x
x
277
249
215
199
52,452
47,290
40,839
37,677
1,008.13
1,000.09
990.09
982.22
21.08
19.05
16.51
16.51
10.54
9.53
8.26
8.26
402.08
400.05
400.05
400.05
40.01
36.07
30.99
27.05
W 40 x 183
x 167
x 149
34,645
31,677
28,258
990.09
980.19
970.28
16.51
16.51
16.00
8.26
8.26
8.00
299.97
299.97
299.97
30.99
26.04
21.08
W 36 x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
848
798
720
650
588
527
485
439
393
359
328
300
280
260
245
230
160,645
150,967
136,129
122,580
110,968
99,355
91,613
82,580
74,193
67,742
62,193
56,968
53,161
49,355
46,516
43,613
1,078.23
1,066.04
1,046.23
1,027.94
1,011.94
995.93
984.00
971.80
960.12
949.96
942.09
933.20
927.61
921.00
916.43
911.86
64.01
60.45
54.99
50.04
45.47
40.89
38.10
34.54
30.99
28.45
25.91
24.00
22.48
21.34
20.32
19.30
32.01
30.23
27.50
25.02
22.74
20.45
19.05
17.27
15.50
14.23
12.96
12.00
11.24
10.67
10.16
9.65
460.50 115.06
456.95 108.97
451.49
99.06
446.41
89.92
441.96
82.04
437.39
73.91
434.47
68.07
430.91
61.98
427.48
55.88
424.94
51.05
422.40
47.19
423.04
42.67
421.51
39.88
420.37
36.58
419.35
34.29
418.34
32.00
W 36 x
x
x
x
x
x
x
x
x
256
232
210
194
182
170
160
150
135
48,645
43,935
39,871
36,774
34,581
32,258
30,323
28,516
25,613
950.72
942.85
931.93
926.85
922.78
918.72
914.65
910.59
902.97
24.38
22.10
21.08
19.43
18.42
17.27
16.51
15.88
15.24
12.19
11.05
10.54
9.72
9.21
8.64
8.26
7.94
7.62
310.26
307.85
309.37
360.72
306.71
305.56
304.80
304.17
303.53
43.94
39.88
34.54
32.00
29.97
27.94
25.91
23.88
20.07
W 33 x
x
x
x
x
x
x
x
x
x
x
x
619
567
515
468
424
387
354
318
291
263
241
221
116,774
107,097
97,419
88,387
80,000
72,903
67,097
60,322
55,226
49,935
45,742
41,935
977.14
962.91
948.94
934.97
923.04
913.13
902.97
893.06
884.94
877.06
868.17
861.82
50.04
45.97
41.91
38.61
35.05
32.00
29.46
26.42
24.38
22.10
21.08
19.69
25.02
22.99
20.96
19.31
17.53
16.00
14.73
13.21
12.19
11.05
10.54
9.85
429.51
425.45
421.39
417.96
414.40
411.48
408.94
406.02
403.99
401.45
402.84
401.45
89.92
83.06
75.95
69.09
62.99
57.91
53.09
48.01
43.94
39.88
35.56
32.39
x 201
38,129
855.47
18.16
9.08
399.82
29.21
W 33 x
x
x
x
x
169
152
141
130
118
31,935
28,839
26,839
24,710
22,387
859.03
850.65
845.82
840.49
834.64
17.02
16.13
16.51
14.73
13.97
8.51
8.07
8.26
7.37
6.99
292.10
293.75
292.99
292.35
291.59
30.99
26.80
24.38
21.72
18.00
W 30 x
x
x
x
x
x
x
x
x
x
x
x
x
581
526
477
433
391
357
326
292
261
235
211
191
173
109,677
99,355
90,322
81,935
73,548
67,097
61,742
55,290
49,484
44,516
40,000
36,193
32,774
898.91
882.90
868.93
854.96
843.03
833.12
822.96
813.05
802.89
795.02
785.88
779.27
773.18
50.04
45.47
41.40
38.10
34.54
31.50
28.96
25.91
23.62
21.08
19.69
18.03
16.64
25.02
22.74
20.70
19.05
17.27
15.75
14.48
12.96
11.81
10.54
9.85
9.02
8.32
411.48
406.91
402.97
399.42
395.99
392.94
390.40
387.48
384.94
382.40
383.67
382.02
380.62
89.92
82.04
74.93
68.07
61.98
56.90
52.07
46.99
41.91
38.10
33.40
30.10
27.05
W 30 x
x
x
x
x
x
x
148
132
124
116
108
99
90
28,064
25,097
23,548
22,064
20,452
18,774
17,032
779.02
769.87
766.32
762.25
757.68
753.11
750.06
16.51
15.62
14.86
14.35
13.84
13.21
11.94
8.26
7.81
7.43
7.18
6.92
6.61
5.97
266.19
267.84
267.08
266.57
266.07
265.43
264.16
29.97
25.40
23.62
21.59
19.30
17.02
15.49
W 27 x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
539
494
448
407
368
336
307
281
258
235
217
194
178
161
146
101,935
93,548
84,516
76,774
69,677
63,677
58,193
53,290
48,829
44,581
41,161
36,774
33,742
30,581
27,677
826.01
812.04
798.07
784.10
771.91
762.00
752.10
743.97
736.09
727.96
722.12
712.99
712.99
700.79
695.45
50.04
45.97
41.91
38.61
35.05
32.00
29.46
26.92
24.89
23.11
21.08
19.05
19.05
16.76
15.37
25.02
22.99
20.96
19.31
17.53
16.00
14.73
13.46
12.45
11.56
10.54
9.53
9.53
8.38
7.69
387.48
383.42
379.48
375.92
372.49
369.44
366.90
364.49
362.46
360.43
358.52
356.49
356.49
356.11
354.71
89.92
83.06
75.95
69.09
62.99
57.91
53.09
49.02
44.96
40.89
38.10
34.04
30.23
27.43
24.77
W 27 x 129
x 114
24,387
21,613
701.80
693.17
15.49
14.48
7.75
7.24
254.25
255.78
27.94
23.62
x 102
x 94
x 84
19,355
17,871
16,000
688.09
683.77
678.43
13.08
12.45
11.68
6.54
6.23
5.84
254.38
253.75
253.90
21.08
18.92
16.26
492
450
408
370
335
306
279
250
229
207
192
176
162
146
131
117
104
92,903
85,161
76,774
69,677
63,484
57,935
52,903
47,419
43,355
39,161
36,323
33,355
30,774
27,742
24,839
22,194
19,742
753.11
738.89
724.92
710.95
699.01
689.10
678.94
669.04
660.91
653.03
646.94
641.10
635.00
628.40
621.79
616.20
611.12
50.04
45.97
41.91
38.61
35.05
32.00
29.46
26.42
24.38
22.10
20.57
19.05
17.92
16.51
15.37
13.97
12.70
358.52
354.46
350.52
346.96
343.41
340.49
337.95
334.90
332.99
330.45
328.93
327.41
329.06
327.66
326.52
325.12
323.85
89.92
83.06
75.95
69.09
62.99
57.91
53.09
48.01
43.94
39.88
37.08
34.04
30.99
27.69
24.38
21.59
19.05
W 24 x 103
x 94
x 84
x 76
x 68
19,548
17,871
15,935
14,452
12,968
623.06
617.47
612.14
607.57
602.74
13.97
13.08
11.94
11.18
10.54
25.02
22.99
20.96
19.31
17.53
16.00
14.73
13.21
12.19
11.05
10.29
9.53
8.96
8.26
7.69
6.99
6.35
6.99
6.54
5.97
5.59
5.27
228.60
230.25
229.11
228.35
227.71
24.89
22.23
19.56
17.27
14.86
62
55
11,742
10,452
603.00
598.68
10.92
10.03
5.46
5.02
178.82
177.93
14.99
12.83
402
364
333
300
275
248
223
201
132
166
147
132
122
111
101
76,129
69,032
63,161
56,903
52,129
46,968
42,193
38,193
34,581
31,484
27,871
25,032
23,161
21,097
19,226
660.91
646.94
635.00
623.06
612.90
603.00
593.09
584.96
577.09
570.99
560.32
554.48
550.67
546.35
542.54
43.94
40.39
37.08
33.53
30.99
27.94
25.40
23.11
21.08
19.05
18.29
16.51
15.24
13.97
12.70
21.97
20.20
18.54
16.77
15.50
13.97
12.70
11.56
10.54
9.53
9.15
8.26
7.62
6.99
6.35
340.49
336.93
333.50
329.95
327.41
324.49
321.95
319.41
317.50
315.47
317.75
315.98
314.71
313.44
312.17
79.50
72.39
66.55
60.45
55.63
50.55
45.47
41.40
37.59
34.54
29.21
26.29
24.38
22.23
20.32
93
17,613
549.15
14.73
7.37
213.87
23.62
W 24 x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
W 24 x
x
W 21 x
x
x
x
x
x
x
x
x
x
x
x
x
x
x
W 21 x
x
x
x
x
83
73
68
62
15,677
13,871
12,903
11,806
544.32
539.50
536.70
533.22
13.08
11.56
10.92
10.16
6.54
5.78
5.46
5.08
212.22
210.69
210.06
209.30
21.21
18.80
17.40
15.62
W 21 x
x
x
57
50
44
10,774
9,484
8,387
534.92
529.08
524.76
10.29
9.65
8.89
166.50
165.86
165.10
16.51
13.59
11.43
311
283
258
234
211
192
175
158
143
130
59,032
53,677
48,968
44,387
40,064
36,387
33,097
29,871
27,161
24,645
566.93
554.99
545.08
534.92
525.02
516.89
509.02
500.89
495.05
488.95
38.61
35.56
32.51
29.46
26.92
24.38
22.61
20.57
18.54
17.02
304.93
302.01
298.96
295.91
293.50
290.96
288.93
287.02
284.99
283.46
69.60
63.50
58.42
53.59
48.51
44.45
40.39
36.58
33.53
30.48
W 18 x 119
x 106
x 97
x 86
x 76
22,645
20,064
18,387
16,323
14,387
481.38
475.74
472.19
467.11
462.53
16.64
14.99
13.59
12.19
10.80
5.14
4.83
4.45
19.31
17.78
16.26
14.73
13.46
12.19
11.31
10.29
9.27
8.51
8.32
7.50
6.80
6.10
5.40
6.29
5.72
5.27
4.96
4.51
4.57
4.00
3.81
7.43
6.68
5.78
5.02
5.46
4.83
4.38
3.88
3.75
3.50
286.13
284.48
283.08
281.69
280.29
26.92
23.88
22.10
19.56
17.27
193.93
192.79
191.90
191.26
190.37
20.57
19.05
17.65
16.00
14.48
153.92
152.78
152.40
15.37
13.34
10.80
264.80
263.27
261.49
259.97
25.02
22.23
19.30
16.89
180.85
179.58
178.69
177.67
177.42
18.16
16.00
14.35
12.83
10.92
140.34
11.18
W 18 x
x
x
x
x
x
x
x
x
x
W 18 x
x
x
x
x
71
65
60
55
50
13,419
12,323
11,355
10,452
9,484
469.14
466.09
463.30
459.99
456.95
12.57
11.43
10.54
9.91
9.02
W 18 x
x
x
46
40
35
8,710
7,613
6,645
458.72
454.66
449.58
9.14
8.00
7.62
W 16 x 100
x 89
x 77
x 67
18,968
16,903
14,580
12,710
431.04
425.45
419.61
414.78
14.86
13.35
11.56
10.03
W 16 x
x
x
x
x
57
50
45
40
36
10,839
9,484
8,581
7,613
6,834
417.32
413.00
409.70
406.65
402.84
10.92
9.65
8.76
7.75
7.49
W 16 x
31
5,884
403.35
6.99
26
4,955
398.53
6.35
W 14 x
x
x
x
x
x
730
665
605
550
500
455
138,709
126,451
114,838
104,516
94,839
86,451
569.47
549.66
531.37
514.10
497.84
483.11
77.98
71.88
65.91
60.45
55.63
51.18
W 14 x
x
x
x
x
x
x
x
x
x
x
x
x
426
398
370
342
311
283
257
233
211
193
176
159
145
80,645
75,484
70,322
65,161
58,968
53,742
48,774
44,193
40,000
36,645
33,419
30,129
27,548
474.22
464.57
455.17
445.52
434.85
425.20
416.05
407.42
399.29
393.19
386.59
380.49
375.41
47.63
44.96
42.04
39.12
35.81
32.77
29.85
27.18
24.89
22.61
21.08
18.92
17.27
W 14 x 132
x 120
x 109
x 99
x 90
25,032
22,774
20,645
18,774
17,097
372.36
367.79
363.73
359.66
356.11
16.38
14.99
13.34
12.32
11.18
W 14 x
x
x
x
82
74
68
61
15,548
14,064
12,903
11,548
363.47
359.92
356.62
352.81
12.95
11.43
10.54
9.53
W 14 x
x
x
53
48
43
10,065
9,097
8,129
353.57
350.27
346.96
9.40
8.64
7.75
W 14 x
x
x
38
34
30
7,226
6,452
5,710
358.14
355.09
351.54
7.87
7.24
6.86
W 14 x
x
26
22
4,961
4,187
353.31
349.00
6.48
5.84
W 12 x 336
x 305
x 279
63,742
57,806
52,839
427.23
414.53
402.59
45.09
41.28
38.86
3.18
38.99
35.94
32.96
30.23
27.82
25.59
23.82
22.48
21.02
19.56
17.91
16.39
14.93
13.59
12.45
11.31
10.54
9.46
8.64
8.19
7.50
6.67
6.16
5.59
6.48
5.72
5.27
4.77
4.70
4.32
3.88
3.94
3.62
3.43
3.24
2.92
22.55
20.64
19.43
139.70
8.76
454.41 124.71
448.31 114.81
442.37 105.66
436.88
97.03
432.05
88.90
427.61
81.53
424.05
421.39
418.47
415.54
412.24
409.19
406.27
403.61
401.32
399.03
422.91
395.35
393.70
77.09
72.26
67.56
62.74
57.40
52.58
48.01
43.69
39.62
36.58
33.27
30.23
27.69
374.02
372.62
370.97
369.95
368.81
26.16
23.88
21.84
19.81
18.03
257.30
255.78
254.89
253.87
21.72
19.94
18.29
16.38
204.72
203.96
203.07
16.76
15.11
13.46
171.96
171.32
170.94
13.08
11.56
9.78
127.64
127.00
10.67
8.51
339.98
336.17
333.76
75.06
68.71
62.74
x
x
x
x
x
x
x
x
x
x
x
x
x
x
252
230
210
190
170
152
136
120
106
96
87
79
72
65
47,806
43,677
39,871
36,000
32,258
28,839
25,742
22,774
20,129
18,194
16,516
14,968
13,613
12,323
391.41
382.27
373.63
365.25
356.36
348.23
340.61
333.25
327.41
322.83
318.26
314.45
311.15
307.85
35.43
32.64
29.97
26.92
24.38
22.10
20.07
18.03
15.49
13.97
13.08
11.94
10.92
9.91
W 12 x
x
58
53
10,968
10,065
309.63
306.32
9.14
8.76
W 12 x
x
x
50
45
40
9,484
8,516
7,613
309.63
306.32
303.28
9.40
8.51
7.49
W 12 x
x
x
35
30
26
6,645
5,671
4,935
317.50
313.44
310.39
7.62
6.60
5.84
W 12 x
x
x
x
22
19
16
14
4,181
3,594
3,039
2,684
312.67
308.86
304.55
302.51
6.60
5.97
5.59
5.08
W 10 x 112
x 100
x 88
x 77
x 68
x 60
x 54
x 49
21,226
18,968
16,710
14,581
12,903
11,355
10,194
9,290
288.54
281.94
275.34
269.24
264.16
259.59
256.29
253.49
19.18
17.27
15.37
13.46
11.94
10.67
9.40
8.64
W 10 x
x
x
45
39
33
8,581
7,419
6,265
256.54
251.97
247.14
8.89
8.00
7.37
W 10 x
x
x
30
26
22
5,703
4,910
4,187
265.94
262.38
258.32
7.62
6.60
6.10
17.72
16.32
14.99
13.46
12.19
11.05
10.04
9.02
7.75
6.99
6.54
5.97
5.46
4.96
4.57
4.38
4.70
4.26
3.75
3.81
3.30
2.92
3.30
2.99
2.80
2.54
9.59
8.64
7.69
6.73
5.97
5.34
4.70
4.32
4.45
4.00
3.69
3.81
3.30
3.05
-
330.33
327.53
324.87
321.82
319.28
316.99
314.96
312.93
310.39
308.86
307.98
306.83
305.82
304.80
57.15
52.58
48.26
44.07
39.62
35.56
31.75
28.07
25.15
22.86
20.57
18.67
17.02
15.37
254.25
253.87
16.26
14.61
205.23
204.34
203.33
16.26
14.61
13.08
166.62
165.61
164.85
13.21
11.18
9.65
102.36
101.73
101.35
100.84
10.80
8.89
6.73
5.72
264.54
262.64
260.73
258.83
257.30
256.03
254.76
254.00
31.75
28.45
25.15
22.10
19.56
17.27
15.62
14.22
203.71
202.82
202.18
15.75
13.46
11.05
147.57
146.56
146.05
12.95
11.18
9.14
W 10 x
x
x
x
19
17
15
12
3,626
3,219
2,845
2,284
260.10
256.79
253.75
250.70
6.35
6.10
5.84
4.83
W8 x
x
x
x
x
x
67
58
48
40
35
31
12,710
11,032
9,097
7,548
6,645
5,890
228.60
222.25
215.90
209.55
206.25
203.20
14.48
12.95
10.16
9.14
7.87
7.24
W8 x
x
28
24
5,323
4,568
204.72
201.42
7.24
6.22
W8 x
x
21
18
3,974
3,394
210.31
206.76
6.35
5.84
W8 x
x
x
15
13
10
2,865
2,477
1,910
205.99
202.95
200.41
6.22
5.84
4.32
W6 x
x
x
25
20
15
4,735
3,787
2,858
162.05
157.48
152.15
8.13
6.60
5.84
W 6 x 16
x 12
x
9
3,058
2,290
1,729
159.51
153.16
149.86
6.60
5.84
4.32
W5 x
x
19
16
3,574
3,019
130.81
127.25
6.86
6.10
W4 x
13
2,471
105.66
7.11
3.18
3.05
2.92
2.42
7.24
6.48
5.08
4.57
3.94
3.62
3.62
3.11
3.18
2.92
3.11
2.92
2.16
4.07
3.30
2.92
3.30
2.92
2.16
3.43
3.05
3.56
102.11
101.85
101.6
100.58
10.03
8.38
6.86
5.33
210.31
208.79
205.99
204.98
203.71
203.07
23.75
20.57
17.40
14.22
12.57
11.05
165.99
164.97
11.81
10.16
133.86
133.35
10.16
8.38
101.98
101.60
100.08
8.00
6.48
5.21
154.43
152.91
152.15
11.56
9.27
6.60
102.36
101.60
100.08
10.29
7.11
5.46
127.76
127.00
10.92
9.14
103.12
8.76
Distance
T
k1
ASEP
Nominal
Weight
(mm)
(mm)
(mm) (kg/m)
981.08
68.26
34.93 424
981.08
63.50
33.34 369
981.08
58.74
33.34 333
981.08
53.98
31.75 295
857.25
857.24
857.24
857.24
857.24
857.24
79.38
76.20
71.44
66.68
61.91
57.15
42.86
41.28
39.69
39.69
39.69
39.69
488
443
399
363
329
286
857.25
857.25
857.25
857.25
857.25
857.25
857.25
857.25
857.25
125.41
117.48
109.54
101.60
96.84
92.08
85.73
80.96
77.79
57.15
53.98
50.80
50.80
49.21
47.63
46.04
44.45
42.86
975
882
790
714
649
591
539
482
442
DATE OF CANVASS
UNIT
SUPPLIER 1
Name
Unit Price
857.25
857.25
857.25
857.25
76.20
96.84
66.68
61.91
41.28
39.69
39.69
39.69
412
371
320
296
857.25
857.25
857.25
66.68
61.91
57.15
39.69
39.69
38.10
272
249
222
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
790.58
144.46
138.11
128.59
119.06
111.13
103.19
96.84
90.49
84.14
79.38
76.20
71.44
68.26
65.09
63.50
60.33
57.15
71.44
52.39
50.80
47.63
44.45
44.45
41.28
41.28
39.69
38.10
38.10
38.10
38.10
36.51
36.51
1262
1188
1071
967
875
784
722
653
585
534
488
446
417
387
365
342
815.98
815.98
815.98
815.98
815.98
815.98
815.98
815.98
815.98
66.68
63.50
58.74
55.56
53.98
50.80
49.21
47.63
42.86
49.21
31.75
31.75
30.16
30.16
30.16
28.58
28.58
28.58
381
345
313
289
271
253
238
223
201
755.65 111.13
755.65 103.19
755.65
96.84
755.65
88.90
755.65
84.14
755.65
79.38
755.65
73.03
755.65
68.26
755.65
65.09
755.65
60.33
755.65
55.56
755.65
52.39
44.45
42.86
41.28
39.69
36.51
34.93
34.93
33.34
31.75
30.16
30.16
30.16
921
844
766
696
631
576
527
473
433
391
359
329
755.65
49.21
28.58
299
755.65
755.65
755.65
755.65
755.65
52.39
47.63
44.45
42.86
47.31
28.58
28.58
26.99
26.99
26.99
251
226
210
193
176
679.45 109.54
679.45 101.60
679.45
95.25
679.45
87.31
679.45
82.55
679.45
76.20
679.45
71.44
679.45
66.68
679.45
61.91
679.45
57.15
679.45
53.98
679.45
49.21
679.45
47.63
42.86
41.28
39.69
38.10
36.51
34.93
33.34
31.75
30.16
28.58
28.58
26.99
26.99
865
783
710
644
582
531
485
435
388
350
314
284
257
679.45
679.45
679.45
679.45
679.45
679.45
679.45
50.80
44.45
42.86
41.28
39.69
36.51
33.34
25.40
26.99
25.40
25.40
25.40
25.40
25.40
220
196
185
173
161
147
134
609.60 107.95
609.60 101.60
609.60
93.66
609.60
87.31
609.60
80.96
609.60
76.20
609.60
71.44
609.60
66.68
609.60
63.50
609.60
58.74
609.60
55.56
609.60
52.39
609.60
47.63
609.60
46.04
609.60
34.77
41.28
29.69
38.10
36.51
33.34
33.34
31.75
30.16
28.58
28.58
26.99
25.40
26.99
25.40
25.40
802
735
667
606
548
500
457
418
384
350
323
289
265
240
217
609.60
609.60
23.81
23.81
192
170
46.04
41.28
609.60
609.60
609.60
39.69
36.51
34.93
23.81
23.81
23.81
152
140
125
553.40 109.54
553.40 103.19
553.40
95.25
553.40
88.90
553.40
82.55
553.40
77.79
553.40
73.03
553.40
68.26
553.40
63.50
553.40
60.33
553.40
57.15
553.40
53.98
553.40
50.80
553.40
47.63
553.40
44.45
553.40
41.28
553.40
38.10
39.69
38.10
34.93
33.34
31.75
34.93
28.58
28.58
25.40
25.40
25.40
25.40
23.81
26.99
26.99
26.99
25.40
732
670
607
551
499
455
415
372
341
308
286
262
241
217
195
174
155
553.40
553.40
553.40
553.40
553.40
44.45
41.28
39.69
36.51
34.93
20.64
25.40
23.81
23.81
23.81
153
140
125
113
101
553.40
553.40
34.93
33.34
23.81
23.81
92
82
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
463.55
98.43
92.08
85.73
79.38
76.20
69.85
65.09
60.33
57.15
53.98
47.63
46.04
42.86
41.28
39.69
36.51
34.93
33.34
31.75
30.16
28.58
26.99
25.40
25.40
23.81
26.99
25.40
25.40
23.81
23.81
598
542
496
446
409
369
332
299
196
247
219
196
182
165
150
463.55
42.86
25.40
138
463.55
463.55
463.55
463.55
39.69
38.10
36.51
34.93
23.81
23.81
22.23
22.23
124
109
101
92
463.55
463.55
463.55
34.93
33.34
30.16
22.23
22.23
22.23
85
74
65
393.70
393.70
393.70
393.70
393.70
393.70
393.70
393.70
393.70
393.70
87.31
80.96
76.20
69.85
65.09
61.91
57.15
53.98
50.80
47.63
30.16
60.16
28.58
25.40
25.40
23.81
11.11
11.11
20.64
20.64
463
421
384
348
314
286
260
235
213
193
393.70
393.70
393.70
393.70
393.70
44.45
41.28
39.69
36.51
34.93
23.81
23.81
22.23
22.23
20.64
177
158
144
128
113
393.70
393.70
393.70
393.70
393.70
38.10
36.51
34.93
33.34
31.75
22.23
22.23
20.64
20.64
20.64
106
97
89
82
74
393.70
393.70
393.70
31.75
30.16
28.58
20.64
20.64
19.05
68
60
52
330.83
330.83
330.83
330.83
42.86
39.69
36.51
34.93
23.81
22.23
22.23
20.64
149
132
115
100
330.83
330.83
330.83
330.83
330.83
34.93
33.34
31.75
30.16
28.58
22.23
20.64
20.64
20.64
19.05
85
74
67
60
54
330.83
28.58
19.50
46
330.83
26.99
19.50
39
285.75
285.75
285.75
285.75
285.75
285.75
141.29
131.76
122.24
114.30
106.36
98.43
55.56
52.39
49.21
46.04
44.45
41.28
1086
990
900
818
744
677
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
285.75
93.66
88.90
84.14
79.38
74.61
69.85
65.09
60.33
57.15
53.98
50.80
47.63
44.45
36.69
38.10
36.51
34.93
33.34
31.75
30.16
30.16
28.58
26.99
26.99
25.40
25.40
634
592
551
509
463
421
382
347
314
287
262
237
216
285.75
285.75
285.75
285.75
285.75
42.86
41.28
39.69
36.51
34.93
23.81
23.81
22.23
22.23
22.23
196
179
162
147
134
279.40
279.40
279.40
279.40
41.28
39.69
38.10
36.51
25.40
23.81
23.81
23.81
122
110
101
91
279.40
279.40
279.40
36.51
34.93
33.34
23.81
22.23
22.23
79
71
64
304.80
304.80
304.80
26.99
25.40
23.81
15.88
15.88
15.88
57
51
45
304.80
304.80
23.81
22.23
14.29
14.29
39
33
241.30
241.30
241.30
93.66
87.31
80.96
38.10
36.51
34.93
500
454
415
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
241.30
74.61
69.85
66.68
61.91
57.15
53.98
49.21
46.04
42.86
41.28
38.10
36.51
34.93
33.34
33.34
31.75
31.75
30.16
28.58
26.99
25.40
25.40
23.81
22.23
22.23
22.23
22.23
20.64
375
342
313
283
253
226
202
179
158
143
129
118
107
97
241.30
241.30
34.93
31.75
20.64
20.64
86
79
241.30
241.30
241.30
34.93
31.75
31.75
20.64
20.64
19.05
74
67
60
266.70
266.70
266.70
25.40
23.81
22.23
14.29
12.70
12.70
52
45
39
266.70
266.70
266.70
266.70
22.23
20.64
19.05
17.46
12.70
12.70
12.70
12.70
33
28
24
21
193.68
193.68
193.68
193.68
193.68
193.68
193.68
193.68
47.63
44.45
41.28
38.10
34.93
33.34
31.75
30.16
23.81
22.23
20.64
20.64
19.05
19.05
17.46
17.46
167
149
131
115
101
89
80
73
193.68
193.68
193.68
31.75
28.58
26.99
17.46
17.46
17.46
67
58
49
219.08
219.08
219.08
23.81
22.23
19.05
12.70
12.70
12.70
45
39
33
219.08
219.08
219.08
219.08
20.64
19.05
17.46
15.88
12.70
12.70
11.11
11.11
28
25
22
18
155.58
155.58
155.58
155.58
155.58
155.58
36.51
33.34
30.16
26.99
25.40
23.81
17.46
17.46
15.88
15.88
14.29
14.29
100
86
71
60
52
46
155.58
155.58
23.81
22.23
14.29
14.29
42
36
168.28
168.28
20.64
19.05
12.70
11.11
31
27
168.28
168.28
168.28
19.05
17.46
15.88
12.70
11.11
11.11
22
19
15
120.65
120.65
120.65
20.64
19.05
15.88
11.11
11.11
9.53
37
30
22
120.65
120.65
120.65
19.05
15.88
14.29
11.11
9.53
9.53
24
18
13
88.90
88.90
20.64
19.05
11.11
11.11
28
24
69.85
1.00
11.11
19
SUPPLIER 1
Terms
SUPPLIER 2
Discount
SUPPLIER 3
Discount
Terms
Discount
REMARKS
STRUCTURAL STEEL
PRICE LIST
ANGLES
Y
x
R1
R2
S.I. Designation
Item
No.
Designation
ANGLES-Equal Legs
L 200 x 200
x
x
x
x
x
x
Weight(asep)
Area
Depth
Width
(kg/m)
(mm)
(mm)
(mm)
12
14
16
18
22
25
36.82
42.69
48.50
54.25
65.55
73.87
4,691
5,439
6,179
6,911
8,351
9,410
200
200
200
200
200
200
200
200
200
200
200
200
L 150 x 150
x
x
x
x
x
x
x
8
10
12
14
16
18
22
18.55
22.98
27.35
31.65
35.89
40.06
48.23
2,363
2,927
3,483
4,031
4,571
5,103
6,143
150
150
150
150
150
150
150
150
150
150
150
150
150
150
L 125 x 125
x
x
x
8
10
12
15.34
18.98
22.56
1,954
2,418
2,874
125
125
125
125
125
125
x
x
x
x
14
16
18
22
26.08
29.53
32.92
39.52
3,322
3,762
4,194
5,034
125
125
125
125
125
125
125
125
L 100 x 100
x
x
x
x
x
x
x
6
8
10
12
14
16
18
9.26
12.18
15.04
17.83
20.56
23.23
25.84
1,179
1,551
1,915
2,271
2,619
2,959
3,291
100
100
100
100
100
100
100
100
100
100
100
100
100
100
L 90 x 90
x
x
x
x
6
8
10
12
8.30
10.90
13.45
15.93
1,057
1,389
1,713
2,029
90
90
90
90
90
90
90
90
L 75 x 75
x
x
x
x
x
5
6
8
10
12
5.78
6.87
9.00
11.07
13.08
736
875
1,147
1,411
1,667
75
75
75
75
75
75
75
75
75
75
L 65 x 65
x
x
x
x
x
5
6
8
10
12
4.97
5.91
7.73
9.49
11.18
634
753
985
1,209
1,425
65
65
65
65
65
65
65
65
65
65
L 50 x 50
x
x
x
x
x
3
5
6
8
10
2.33
3.77
4.47
5.82
7.11
296
480
569
741
905
50
50
50
50
50
50
50
50
50
50
L 40 x 40
x
x
x
3
5
6
1.84
2.97
3.52
235
379
448
40
40
40
40
40
40
L 30 x 30
x
x
x
3
5
6
1.36
2.18
2.56
174
278
327
30
30
30
30
30
30
L 25 x 25
1.12
142
25
25
L 20 x 20
0.88
112
20
20
ANGLES-Unequal Legs
L 150 x 90
x
8
x
10
x
12
14.69
18.18
21.60
1,871
2,315
2,751
150
150
150
90
90
90
L 125 x 75
x
x
x
x
6
8
10
12
9.24
12.16
15.02
17.81
1,177
1,549
1,913
2,269
125
125
125
125
75
75
75
75
L 100 x 75
x
x
x
x
6
8
10
12
8.04
10.57
13.04
15.44
1,025
1,347
1,661
1,967
100
100
100
100
75
75
75
75
L 90 x 75
x
x
x
x
6
8
10
12
7.55
9.92
12.23
14.47
962
1,264
1,558
1,835
90
90
90
90
75
75
75
75
L 75 x 50
x
x
x
x
5
6
8
10
4.75
5.65
7.39
9.07
605
719
941
1,155
75
75
75
75
50
50
50
50
L 65 x 50
x
x
x
x
5
6
8
10
4.35
5.16
6.75
8.28
554
658
860
1,054
65
65
65
65
50
50
50
50
L 50 x 50
x
x
5
6
3.35
3.97
427
506
50
50
50
50
Thickness
t
(mm)
12
14
16
18
22
25
8
10
12
14
16
18
22
8
10
12
DATE OF CANVASS
UNIT
SUPPLIER 1
Name
Unit Price
Terms
SUPPL
Discount
Name
14
16
18
22
6
8
10
12
14
16
18
6
8
10
12
5
6
8
10
12
5
6
8
10
12
3
5
6
8
10
3
5
6
3
5
6
3
3
8
10
12
6
8
10
12
6
8
10
12
6
8
10
12
5
6
8
10
5
6
8
10
5
6
SUPPLIER 2
Unit Price Terms
SUPPLIER 3
Discount
Terms
Discount
REMARKS
STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
ANGLES
Y
x
R1
R2
Y
Item
No.
z
k
AISC Designation
(mm)
Equal legs and Unequal legs
L 9 x
4
x
5/8
x 9/16
x
1/2
L 8 x
L 8 x
x 1 1/8
x
1
x
7/8
x
3/4
x
5/8
x 9/16
x
1/2
x
x
x
x
x
x
1
7/8
3/4
5/8
9/16
1/2
Weight(asep)
per
m.
(kg/m)
Area
A
(mm)
28.58
26.99
25.40
39.139
35.418
31.698
4,987
4,516
4,032
44.45
41.28
38.10
34.93
31.75
30.16
28.58
84.677
75.896
66.967
57.890
48.663
44.050
39.288
10,774
9,677
8,516
7,355
6,200
5,600
5,000
38.10
34.93
31.75
28.58
26.99
25.40
65.777
58.187
50.300
42.413
38.246
34.228
8,387
7,419
6,413
5,394
4,877
4,355
7/16
23.81
30.061
3,826
L 8 x
x
x
x
x
1
3/4
9/16
1/2
38.10
31.75
26.99
25.40
55.657
42.710
32.591
29.168
7,097
5,445
4,148
3,710
L 7 x
x
x
x
x
3/4
5/8
1/2
3/8
31.75
28.58
25.40
22.23
38.990
32.888
26.638
20.239
4,961
4,181
3,387
2,568
L 6 x
x
x
x
x
x
x
x
x
x
1
7/8
3/4
5/8
9/16
1/2
7/16
3/8
5/16
38.10
34.93
31.75
28.58
26.99
25.40
23.81
22.23
20.64
55.657
49.258
42.710
36.014
32.591
29.168
25.596
22.174
18.453
7,097
6,277
5,445
4,587
4,148
3,710
3,265
2,813
2,355
L 6 x
x
x
x
x
x
x
x
x
7/8
3/4
5/8
9/16
1/2
7/16
3/8
5/16
34.93
31.75
28.58
26.99
25.40
23.81
22.23
20.64
40.478
35.121
29.763
26.936
24.108
21.281
18.304
15.328
5,148
4,477
3,781
3,426
3,065
2,697
2,329
1,955
x
x
x
1/2
3/8
5/16
25.40
22.23
20.64
22.769
17.412
14.584
2,903
2,206
1,852
x
x
x
x
x
x
x
7/8
3/4
5/8
1/2
7/16
3/8
5/16
34.93
31.75
28.58
25.40
23.81
22.23
20.64
40.478
35.210
29.763
24.108
21.281
18.304
15.328
5,148
4,477
3,781
3,065
2,697
2,329
1,955
x
x
x
x
x
3/4
5/8
1/2
7/16
3/8
31.75
28.58
25.40
23.81
22.23
29.466
25.001
20.239
17.858
15.477
3,748
3,174
2,581
2,277
1,968
L 6 x 3 1/2
L 5 x
L 5 x 3 1/2
x
x
5/16
1/4
20.64
19.05
12.947
10.417
1,652
1,329
L 5 x
x
x
x
x
x
x
5/8
1/2
7/16
3/8
5/16
1/4
25.40
25.40
23.81
22.23
20.64
19.05
23.364
19.049
16.816
14.584
12.203
9.822
2,974
2,419
2,135
1,845
1,548
1,252
L 4 x
x
x
x
x
x
x
x
3/4
5/8
1/2
7/16
3/8
5/16
1/4
28.58
25.40
22.23
20.64
19.05
17.46
15.88
27.531
23.364
19.049
16.816
14.584
12.203
9.822
3,510
2,974
2,419
2,135
1,845
1,548
1,252
x
x
x
x
x
1/2
7/16
3/8
5/16
1/4
23.81
22.23
20.64
19.05
17.46
17.709
15.775
13.542
11.459
9.227
2,258
1,994
1,723
1,452
1,168
x
x
x
x
x
1/2
7/16
3/8
5/16
1/4
23.81
22.23
20.64
19.05
17.46
16.519
14.584
12.649
10.715
8.631
2,097
1,852
1,600
1,348
1,090
L 3 1/2 x 3 1/2 x
x
x
x
x
1/2
7/16
3/8
5/16
1/4
22.23
20.64
19.05
17.46
15.88
16.519
14.584
12.649
10.715
8.631
2,097
1,852
1,600
1,348
1,090
x
x
x
x
x
1/2
7/16
3/8
5/16
1/4
23.81
22.23
20.64
19.05
17.46
15.179
13.542
11.756
9.822
8.036
1,935
1,710
1,484
1,245
1,006
L 3 1/2 x 2 1/2 x
x
x
x
x
1/2
7/16
3/8
5/16
1/4
23.81
22.23
20.64
19.05
17.46
13.989
12.352
10.715
9.078
7.292
1,774
1,568
1,361
1,148
929
L 4 x 3 1/2
L 4 x
L 3 1/2 x 3
L 3 x
x
x
x
x
x
x
1/2
7/16
3/8
5/16
1/4
3/16
20.64
19.05
17.46
15.88
14.29
12.70
13.989
12.352
10.715
9.078
7.292
5.521
1,774
1,568
1,361
1,148
929
703
x
x
x
x
x
x
1/2
7/16
3/8
5/16
1/4
3/16
22.23
20.64
19.05
17.46
15.88
14.29
12.649
11.310
9.822
8.334
6.697
5.045
1,613
1,426
1,239
1,045
845
643
x
x
x
x
x
x
1/2
7/16
3/8
5/16
1/4
3/16
20.64
19.05
17.46
15.88
14.29
12.70
11.459
10.120
8.780
7.441
6.101
4.569
1,452
1,290
1,116
942
768
582
L 2 1/2 x 2 1/2 x
x
x
x
x
1/2
3/8
5/16
1/4
3/16
20.64
17.46
17.15
14.29
12.70
11.459
8.780
7.441
6.101
4.569
1,452
1,116
942
768
582
x
x
x
x
3/8
5/16
1/4
3/16
17.46
15.88
14.29
12.70
7.887
6.697
5.387
4.092
1,000
845
684
522
x
x
x
x
x
3/8
5/16
1/4
3/16
1/8
15.88
14.29
12.70
11.11
9.53
6.994
5.834
4.747
3.631
2.455
877
742
605
461
312
L 1 3/4 x 1 3/4 x
x
1/4
3/16
12.70
11.11
4.122
3.155
525
401
L 1 1/2 x 1 1/2 x
x
1/4
3/16
11.11
9.53
3.482
2.679
444
340
L 1 1/4 x 1 1/4 x
x
1/4
3/16
11.11
9.53
2.857
2.202
363
280
L 1 1/8 x 1 1/8 x
1/8
5.56
1.339
172
L 3 x 2 1/2
L 3 x
L 2 1/2 x 2
L 2 x
6.35
1.191
151
DATE OF CANVASS
UNIT
SUPPLIER 1
Name
Unit Price
Terms
SUPPLIER 2
Discount
SUPPLIER 2
Terms
SUPPLIER 3
Discount
Terms
Discount
REMARKS
STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
PIPES
Wall
Weight Nominal Outside
Inside
Thicknes
Item Designation
W
Diameter Diameter Diameter
s
No.
d
(kg/m)
(mm)
(mm)
(mm)
(mm)
Elastic Properties
A
(mm)
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
PS
12
10
8
6
5
4
3.5
3
2.5
2
1.5
1.25
1
0.75
0.5
73.65
60.51
42.65
28.23
21.77
16.03
13.59
11.31
8.62
5.43
4.07
3.38
2.52
1.70
1.26
304.8
254.0
203.2
152.4
127.0
101.6
88.9
76.2
63.5
50.8
38.1
31.8
25.4
19.1
12.7
323.8
273.1
219.1
168.3
141.3
114.3
101.6
88.9
73.0
60.3
48.3
42.2
33.4
26.7
21.3
304.8
254.5
202.7
154.1
128.2
102.3
90.1
77.9
62.7
52.5
40.9
35.1
26.6
20.9
15.8
9.50
9.30
8.20
7.10
6.55
6.00
5.75
5.50
5.15
3.90
3.70
3.55
3.40
2.90
2.75
9,380
7,707
5,433
3,596
2,773
2,041
1,731
1,441
1,098
691
518
431
320
217
160
PE
PE
PE
PE
PE
PE
PE
PE
PE
PE
PE
PE
PE
12
10
8
6
5
4
3.5
3
2.5
2
1.5
1.25
1
97.08
81.57
64.65
42.68
30.88
22.30
18.68
15.24
11.40
7.43
5.43
4.47
3.24
304.8
254.0
203.2
152.4
127.0
101.6
88.9
76.2
63.5
50.8
38.1
31.8
25.4
323.8
273.1
219.1
168.3
141.3
114.3
101.6
88.9
73.0
60.3
48.3
42.2
33.4
298.5
247.7
193.7
146.3
122.3
97.2
85.4
73.7
59.0
49.3
38.1
32.5
24.3
12.65
12.70
12.70
11.00
9.50
8.55
8.10
7.60
7.00
5.50
5.10
4.85
4.55
12,365
10,390
8,235
5,436
3,934
2,841
2,379
1,941
1,451
947
692
569
412
PE 0.75
PE 0.5
PD
PD
PD
PD
PD
PD
PD
8
6
5
4
3
2.5
2
2.22
1.61
19.1
12.7
26.7
21.3
18.8
13.9
3.95
3.70
282
205
108.03
79.23
57.44
41.00
27.70
20.37
13.42
203.2
152.4
127.0
101.6
76.2
63.5
50.8
219.1
168.3
141.3
114.3
88.9
73.0
60.3
174.6
124.4
103.2
80.1
58.4
45.0
38.2
22.25
21.95
19.05
17.10
15.25
14.00
11.05
13,760
10,092
7,316
5,222
3,529
2,595
1,710
Elastic Properties
I x 10
(mm )
4
S x 10
(mm)
Schedule
No.
(mm)
11,128.6
67,013.3
30,176.8
11,696.1
6,326.7
3,009.4
1,993.7
1,257.0
636.8
277.2
129.0
81.2
36.2
15.4
7.1
718.0 111.03
490.0 93.43
275.5 74.62
139.2 57.00
89.3 47.76
52.7 38.36
39.2 33.96
28.3 29.56
17.4 24.10
9.2 20.04
5.3 15.82
3.8 13.71
2.2 10.66
1.2
8.47
0.7
6.62
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
150,675.8
88,241.1
44,120.5
16,857.4
8,616.0
4,000.0
2,613.9
1,619.1
799.2
361.3
162.7
100.7
44.1
929.4 110.29
646.2 92.17
401.7 73.09
200.3 55.77
121.8 46.75
70.0 37.50
51.5 33.18
36.5 28.83
21.9 23.46
12.0 19.45
6.7 15.35
4.8 13.31
2.6 10.35
80
80
80
80
80
80
80
80
80
80
80
80
80
DATE OF CANVASS
UNIT
SUPPLIER 1
Name
18.7
8.3
1.4
0.8
8.19
6.35
67,429.5
27,596.1
13,985.4
6,368.3
2,493.2
1,194.6
545.3
815.5
328.2
198.2
111.3
56.1
32.7
18.1
70.05
52.36
43.80
34.91
26.58
21.43
17.82
80
80
-
SUPPLIER 1
Unit Price
Terms
SUPPLIER 2
Discount
SUPPLIER 3
Discount
Terms
LIER 3
Discount
REMARKS
SIZE
FRACTION
1/16"
1/14"
1/8"
3/16"
1/4"
5/16"
3/8"
5/16"
3/8"
7/16"
1/2"
5/8"
THICKNESS
(mm)
1.40
1.50
1.60
1.80
1.90
2.00
2.60
2.80
3.00
3.18
3.20
4.00
4.30
4.50
4.76
5.00
5.50
5.60
5.80
6.00
6.35
7.00
7.30
7.50
7.94
8.00
9.00
9.53
7.00
7.30
7.50
7.94
8.00
9.00
9.53
10.00
11.00
11.11
12.00
12.70
14.00
(inch)
0.06
0.06
0.06
0.07
0.08
0.08
0.10
0.11
0.12
0.13
0.13
0.16
0.17
0.18
0.19
0.20
0.22
0.22
0.23
0.24
0.25
0.25
0.29
0.30
0.31
0.32
0.35
0.38
0.25
0.29
0.30
0.31
0.32
0.35
0.38
0.39
0.43
0.44
0.47
0.50
0.551
WIDTH x LENGTH
1.219m x 2.438m 1.219m x 6.096m 1.524m x 6.096m
4' x 8'
4' x 20'
5' x 20'
WEIGHT (Kg)
32.70
81.70
35.01
87.52
37.34
93.40
42.00
105.02
44.40
110.90
46.70
116.70
60.70
151.70
65.35
163.40
204.20
70.01
175.00
219.00
74.10
185.20
232.00
74.10
186.70
233.40
93.40
233.40
292.00
100.40
250.90
314.00
105.00
262.50
328.20
111.12
277.90
347.40
116.70
291.70
365.00
128.40
320.90
401.10
130.70
326.70
408.40
135.40
338.40
423.00
140.00
350.10
438.00
148.20
370.50
463.10
163.40
408.40
511.00
170.40
426.00
532.40
175.00
438.00
547.00
185.30
463.10
579.00
186.70
466.80
583.40
210.00
525.10
656.40
222.30
555.70
695.00
163.40
408.40
511.00
170.40
426.00
532.40
175.00
438.00
547.00
185.30
463.10
579.00
186.70
466.80
583.40
210.00
525.10
656.40
222.30
555.70
695.00
233.40
583.40
729.30
256.70
641.80
802.20
259.40
648.40
810.50
280.10
700.10
875.20
296.40
741.00
926.20
327.00
816.80
1021.00
5/8"
3/4"
7/8"
1"
1-1/8"
1-1/4"
1-3/8"
1-1/2"
1-5/8"
1-3/4"
2"
2-1/4"
2-1/2"
3"
4"
15.00
15.90
16.00
17.00
18.00
19.00
19.10
21.00
22.00
22.20
24.00
25.00
25.40
28.00
28.60
30.00
31.80
32.00
34.00
34.90
35.00
38.00
38.10
40.00
41.30
44.80
46.00
50.00
50.80
57.00
57.20
63.50
65.00
75.00
76.20
100.00
101.60
0.591
0.625
0.630
0.669
0.709
0.748
0.750
0.827
0.866
0.875
0.945
0.984
1.000
1.102
1.125
1.181
1.250
1.260
1.339
1.375
1.378
1.496
1.500
1.575
1.625
1.750
1.811
1.969
2.000
2.244
2.250
2.500
2.559
2.953
3.000
3.937
4.000
350.10
371.00
373.40
397.00
420.10
443.40
445.00
490.10
513.40
519.00
560.10
583.40
593.00
654.00
667.00
700.10
741.00
747.00
794.00
815.10
817.00
887.00
889.20
934.00
963.30
1037.4
1074.0
1167.0
1186.0
1330.3
1334.0
1482.0
1517.0
1750.3
1778.3
2334.0
2371.1
875.20
926.20
933.50
991.80
1050.20
1108.50
1111.50
1225.20
1284.00
1297.00
1400.30
1459.00
1482.00
1634.00
1667.20
1750.32
1853.00
1867.00
1984.00
2038.00
2042.00
2217.10
2223.00
2334.00
2408.20
2593.40
2684.00
2917.20
2964.00
3326.00
3334.40
3705.00
3792.40
4376.00
4446.00
5834.40
5928.00
1094.00
1158.00
1167.00
1240.00
1313.00
1386.00
1389.30
1532.00
1605.00
1621.00
1750.30
1823.30
1852.40
2042.00
2084.00
2188.00
2316.00
2334.00
2480.00
2547.10
2553.00
2771.30
2779.00
2917.20
3010.20
3242.00
3355.00
3647.00
3705.00
4157.00
4168.00
4631.10
4740.50
5470.00
5557.30
7293.00
7410.00
1.829m x 6.096m
6' x 20'
245.00
263.00
278.00
280.10
350.10
376.30
394.00
417.00
438.00
481.30
490.10
508.00
525.10
556.00
613.00
639.00
656.40
695.00
700.13
788.00
834.00
613.00
639.00
656.40
695.00
700.13
788.00
834.00
875.20
963.00
973.00
1,050.20
1,111.50
1225.20
UNIT WEIGHT
(Kg/ft)
1.02
1.09
1.17
1.32
1.39
1.46
1.89
2.04
2.19
2.32
2.33
2.91
3.14
3.28
3.47
3.65
4.01
4.08
4.23
4.38
4.63
5.11
5.32
5.47
5.79
5.83
6.56
6.95
5.11
5.32
5.47
5.79
5.83
6.56
6.95
7.30
8.02
8.10
8.76
9.26
10.207
(Kg/m)
10.99
11.78
12.56
14.13
14.92
15.70
20.41
21.98
23.55
24.92
25.12
31.40
33.76
35.33
37.39
39.25
43.18
43.96
45.53
47.10
49.85
54.95
57.30
58.90
62.31
62.80
70.65
74.77
54.95
57.30
58.90
62.31
62.80
70.65
74.77
78.50
86.35
87.24
94.20
99.70
109.902
DATE OF CANVASS
UNIT
SUPPLIER 1
Name
1313.00
1389.30
1400.30
1488.00
1575.30
1663.00
1667.20
1838.00
1925.40
1945.00
2100.40
2188.00
2223.00
2450.50
2501.00
2626.00
2779.00
2801.00
2976.00
3057.00
3063.10
10.948
11.578
11.670
12.393
13.134
13.856
13.893
15.320
16.042
16.209
17.505
18.228
18.524
117.752
124.621
125.602
133.452
141.302
149.152
149.545
164.852
172.703
174.469
188.403
196.253
199.393
SUPPLIER 1
Unit Price Terms
Discount
SUPPLIER 2
Name Unit Price Terms
Discount
SUPPLIER 3
Name Unit Price Terms
LIER 3
Discount
REMARKS
STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
Y
Weight
W
(kg/m)
Designation
HxBxt
Area
A
(mm)
LR SHAPES
LR 175 x 50 x
x
x
x
x
LR 100 x 50 x
x
x
LR 50 x 40 x
x
x
x
x
LR 50 x 20 x
x
LR 40 x 25 x
x
x
x
LR 40 x 20 x
x
LR 40 x 18 x
4.0
3.5
3.0
2.5
2.0
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
2.5
2.0
3.5
3.0
2.5
2.0
2.5
2.0
2.5
13.09
11.56
10.01
8.42
6.80
6.48
5.48
4.45
4.61
4.15
3.65
3.13
2.57
2.34
1.94
2.77
2.48
2.14
1.78
1.95
1.62
1.87
1667
1473
1275
1073
867
825
698
567
587
528
465
398
327
298
247
353
315
273
227
248
207
238.2
DATE OF CANVASS
UNIT
x
LR 40 x 16 x
LR 38 x 18 x
x
LR 32 x 25 x
x
x
x
LR 32 x 16 x
LR 28 x 18 x
x
LR 25 x 16 x
2.0
2.0
2.5
2.0
3.5
3.0
2.5
2.0
2.0
2.5
2.0
2.0
1.56
1.50
1.79
1.50
2.33
2.10
1.83
1.53
1.25
1.40
1.18
1.03
198.8
190.8
228.2
190.8
297.4
267.4
233.2
194.8
158.8
178.2
150.8
130.8
LR 100 x 100 x
x
x
x
x
LR 75 x 75 x
x
x
x
x
LR 50 x 50 x
x
x
x
x
LR 32 x 32 x
x
x
x
x
LR 28 x 28 x
x
x
x
x
LR 25 x 25 x
x
x
x
LR 24 x 24 x
x
x
x
4.0
3.5
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
4.0
3.5
3.0
2.5
2.0
3.5
3.0
2.5
2.0
3.5
3.0
2.5
2.0
11.52
10.19
8.83
7.44
6.02
8.38
7.44
6.48
5.48
4.45
5.24
4.70
4.12
3.52
2.88
2.98
2.72
2.43
2.10
1.75
2.48
2.28
2.05
1.79
1.50
1.95
1.77
1.56
1.31
1.84
1.67
1.48
1.25
1467
1298
1125
948
767
1067
948
825
698
567
667
598
525
448
367
379
346
309
268
223
315
290
261
228
191
248
225
198
167
234
213
188
159
LS SHAPES
Name
SUPPLIER 1
Unit Price Terms
Discount
Name
SUPPLIER 2
Unit Price Terms
SUPPLIER
Discount
Name
SUPPLIER 3
Unit Price
Terms
Discount
REMARKS
STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
Y
AISC SECTIONS
Weight
Wall
Thickness per m.
(mm)
(kg/m)
Area
A
(mm)
SQUARE
16 x 16
14 x 14
12 x 12
12 x 12
15.88
12.70
9.53
7.94
15.88
12.70
9.53
7.94
15.88
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
189.55
153.73
116.85
98.03
164.23
133.46
101.66
85.36
138.91
113.20
86.46
72.71
58.68
44.41
113.59
103.40
92.95
71.28
60.05
48.56
36.80
24129
19613
14903
12516
20903
17032
12968
10903
17677
14452
11032
9290
7484
5658
14452
13161
11871
9097
7677
6187
4690
DATE OF CANVASS
UNIT
9x9
8x8
7x7
6x6
5x5
15.88
14.29
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
100.93
92.01
82.83
63.68
53.72
43.50
33.01
88.28
80.61
72.70
56.09
47.38
38.42
29.21
69.21
62.58
48.48
41.06
33.36
25.42
57.83
52.44
40.89
34.73
28.30
21.62
42.31
33.29
28.39
23.25
17.81
12839
11742
10581
8129
6839
5542
4206
11226
10258
9290
7161
6039
4897
3723
8839
8000
6181
5232
4252
3239
7355
6710
5213
4426
3606
2755
5394
4245
3169
2961
2271
15.88
12.70
9.53
7.94
12.70
9.53
7.94
12.70
9.53
7.94
12.70
9.53
7.94
15.88
12.70
9.53
189.55
153.73
116.85
98.03
133.46
101.66
85.36
113.20
86.46
72.71
113.20
86.46
72.71
164.23
133.46
101.66
43484
19613
14903
12516
17032
12968
10903
14452
11032
9290
14452
11032
9290
20903
17032
12968
RECTANGULAR
20 x 12
20 x 8
20 x 4
18 x 6
16 x 12
16 x 8
16 x 4
14 x 10
14 x 6
14 x 4
12 x 8
12 x 6
12 x 4
12 x 2
10 x 8
7.94
12.70
9.53
7.94
12.70
9.53
7.94
15.88
12.70
9.53
7.94
12.70
9.53
7.94
6.35
12.70
9.53
7.94
6.35
15.88
14.29
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
85.36
113.20
86.46
72.71
92.95
71.28
60.05
138.91
113.20
86.46
72.71
92.95
71.28
60.05
48.56
82.83
63.68
53.72
43.50
113.59
103.40
92.95
71.28
60.05
48.56
36.80
100.93
92.01
82.83
63.68
53.72
43.50
33.01
88.28
80.61
72.70
56.09
47.38
38.43
29.21
33.36
25.42
100.93
92.01
82.83
63.68
53.72
43.50
10903
14452
11032
9290
11871
9097
7677
17677
14452
11032
9290
11871
9097
7677
6187
10581
8129
6839
5542
14452
13161
11871
9097
7677
6187
4690
12839
11742
10581
8129
6839
5542
4206
11226
10258
9290
7161
6039
4897
3723
4252
3239
12839
11742
10581
8129
6839
5542
10 x 6
10 x 5
10 x 4
10 x 2
9x7
9x6
9x5
9x3
15.88
14.29
12.70
9.53
7.94
6.35
15.88
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
15.88
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
88.28
80.61
72.70
56.09
47.38
38.42
81.94
74.91
67.64
52.28
44.23
35.89
27.31
69.21
62.58
48.48
41.06
33.36
25.42
40.89
34.73
28.30
21.62
88.28
80.61
72.70
56.09
47.38
38.42
29.21
81.94
74.91
67.64
52.28
44.23
35.89
27.31
69.21
62.58
48.48
41.06
33.36
25.42
52.44
40.89
34.73
28.30
21.62
11226
10258
9290
7161
6039
4897
10452
9548
8645
6645
5632
4574
3477
8839
8000
6181
5232
4252
3239
5213
4426
3606
2755
11226
10258
9290
7161
6039
4897
3723
10452
9548
8645
6645
5632
4574
3477
8839
8000
6181
5232
4252
3239
6710
5213
4426
3606
2755
8x6
8x4
8x3
8x2
7x5
7x4
7x3
7x2
6x5
6x4
6x3
14.29
12.70
9.53
7.94
6.35
4.76
14.29
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
12.70
9.53
7.94
6.35
4.76
6.35
4.76
12.70
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
9.53
69.21
62.58
48.48
41.06
33.36
25.42
57.83
52.44
40.89
34.73
28.30
21.62
47.38
37.10
31.56
25.78
19.72
33.29
28.39
23.25
17.81
52.44
40.89
34.73
28.30
21.62
47.38
48.48
41.06
33.36
42.31
33.29
28.39
23.25
17.81
20.70
15.92
47.38
37.10
31.56
25.78
19.72
42.31
33.29
28.39
23.25
17.81
29.50
8839
8000
6181
5232
4252
3239
7355
6710
5213
4426
3606
2755
6039
4729
4019
3284
2510
4245
3619
2961
2271
6710
5213
4426
3606
2755
6039
6181
5232
4252
5394
4245
3619
2961
2271
2639
2026
6039
4729
4019
3284
2510
5394
4245
3619
2961
2271
3761
6x2
5x4
5x3
5x2
4x3
4x2
3.5 x 2.5
3x2
7.94
6.35
4.76
9.53
7.94
6.35
4.76
9.53
7.94
6.35
4.76
12.70
9.53
7.94
6.35
4.76
7.94
6.35
4.76
7.94
6.35
4.76
7.94
6.35
4.76
6.35
4.76
6.35
4.76
25.24
20.70
15.92
25.70
22.07
18.17
14.02
29.50
25.24
20.70
15.92
32.19
25.70
22.07
18.17
14.02
18.90
15.64
12.13
18.90
15.64
12.13
15.74
13.11
10.22
13.11
10.22
10.58
8.32
3213
2639
2026
3277
2813
2316
1787
3761
3213
2639
2026
4103
3277
2813
2316
1787
2406
1994
1542
2406
1994
1542
2006
1671
1303
1671
1303
1348
1058
Name
SUPPLIER 1
Unit Price Terms
Discount
Name
SUPPLIER 2
Unit Price Terms
SUPPLIER
Discount
Name
SUPPLIER 3
Unit Price
Terms
Discount
REMARKS
STRUCTURAL STEEL
TABLES OF DIMENSIONS AND PROPERTIES
CHANNELS - AMERICAN STANDARD
Designation
C15 x 50
x 40
x 33.9
C12 x 30
x 25
x 20.7
C10 x 30
x 25
x 20
x 15.3
C9 x 20
x 15
x 13.4
C8 x 18.75
x 13.75
x 11.50
C7 x 14.75
x 12.25
x 9.8
C6 x 13
x 10.5
x 8.2
C5 x 9
x 6.7
C4 x 7.25
x 5.4
C3 x 6
x 5
x 4.1
Area
Depth
Nominal
A
d
Weight per m
DATE OF CANVASS
(mm)
(mm)
(kg/m)
9484
381.0
74.41
7613
381.0
59.53
6426
381.0
50.45
5690
304.8
44.64
4742
304.8
37.20
3929
304.8
30.81
5690
254.0
44.64
4742
254.0
37.20
3794
254.0
29.76
2897
254.0
22.77
3794
228.6
29.76
2845
228.6
22.32
2542
228.6
19.94
3555
203.2
27.90
2606
203.2
20.46
2181
203.2
17.11
2794
177.8
21.95
2323
177.8
18.23
1852
177.8
14.58
2471
152.4
19.35
1994
152.4
15.63
1548
152.4
12.20
1703
127.0
13.39
1271
127.0
9.97
1374
101.6
10.79
1026
101.6
8.04
1135
76.2
8.93
948
76.2
7.44
781
76.2
6.10
UNIT
Name
SUPPLIER 1
Unit Price Terms
Discount
Name
SUPPLIER 2
Unit Price Terms
Discount
Name
SUPPLIER 3
Unit Price
Terms
Discount
REMARKS
Skim Coat
Application
1-1.20kg / m
Commercial:
20kgs/bag
25kgs/bag
Skimcoat
10% Waste factor
1.2
0.12
per mm thickness
370 white
30/kg gray
15
15
18
1.8
19.8
Delivery Charging:
Date : December 15, 2010
From MANILA to port below:
PORT
CAGAYAN DE ORO
VAN SIZE
20FT GP
40FT HC
PIER - DOOR
33,568.00
58,556.00
DOOR - DOOR
38,568.00
55,556.00
3 TONS
6 TONS
e to case basis.
Quotation :
Supplier: PACIFIC CONCRETE PRODUCTS, INC.
Date: January, 10, 2011
Project Location: Dasmarinas, Cavite
Owner Supplied Cement:
Compressive Strength
Aggregates
Design Criteria
3/4"
3/4"
3/4"
3/4"
Pumpcrete
Pumpcrete
Pumpcrete
Pumpcrete
Note:
Minimum Pumpcrete charge of P12,000.00 per setup of 50 m or less.
Additional P240.00/m in excess of 50 m per setup
Additional P30.00/floor beyond 5th using 3 meter floor to floor height basis.
Additional P10.00 per pipe/m for the set up exceeding 25 pieces of pipes.
Terms of Payment :
Validity of Price :
Delivery Schedule :
Note :
Supplier : FILMIXCO
Locaion : San Fernando, Pampanga
Owner Supplied Cement =
2,500psi
3,000psi
3,500psi
PROPORTION S OF CONCRETE
Class of Concrete
Class AA
Class A
Class B
Class C
Class D
AGGREGATES
FROM
380.00/cu.m.
400.00/cu.m.
350.00/cu.m.
300.00/cu.m.
200.00/cu.m.
160.00/cu.m.
140.00/cu.m.
Gov't. Fee =
Pass ways =
1 TRUCK =
NEW PRICES
430.00/cu.m.
400.00/cu.m.
380.00/cu.m.
300.00/cu.m.
200.00/cu.m.
160.00/cu.m.
140.00/cu.m.
390 per truck/load
160 per truck/load
14.00 m
430.00
13.99 m
421.00
122.00
235.00
Gov't. Fee =
Donation Fee =
1,150.00
1,150.00
1,150.00
1,150.00
SAND
10.46
7.85
6.49
5.49
4.82
GRAVEL
0.42
0.42
0.44
0.44
0.45
0.84
0.84
0.87
0.89
0.91
SPECIALTY WORKS:
Peeble Washout Finish (This consist of a mixture of pea-sized pebbles and cement.)
Estimating Guides:
Floor Area x
Floor Area x
Wall Area
x
Wall Area
x
0.95
0.213
0.67
0.125
PAINTINGS
FLATWALL ENAMEL
a topcoat that gives a flat or eggshell finish. It is recommended for use on new or previously painted interior walls, ceilings, mouldings, plaste
thinned with paint thinner.