EXISTING PROVISIONS DRAFT CERC REGULATIONS Energy consumed for supply of power to housing colony and other facilities at the generating station & construction work not included 12/12/2013 2 Definition of Cut-off date EXISTING PROVISIONS DRAFT CERC REGULATIONS
Cut-off date 2 years from COD(3 years for COD in Q4). Same 12/12/2013 3 Useful life (years) EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Coal-25, Gas-25 Sub-station-25, Hydro- 35 Transmission- 35 Coal-25, Gas-25 Sub-station-35, Hydro- 35 Transmission- 35, Communication system-15 12/12/2013 4 Date of COD EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Demonstration of MCR Trial run at MCR for 72 hours shall commence after 7 days notice. Scheduling to commence after acceptance of test results or within 48 hours after trial run Certification by CEA A generating station or unit thereof after being put into commercial operation shall demonstrate the plant availability of not less than the NAPAF in the month following the date of declaration of commercial operation. If not able to demonstrate except for the reasons beyond the control of generating company, such generating company or the unit is said to be put into commercial service from the month of normative availability. 12/12/2013 5 Continuation of tariff based on projected capital cost EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Tariff based on projected capital cost In case, Projected Cap Cost > 105% of Actual Cap cost, refund to beneficiaries along with interest @1.20 times Bank Rate. For, Projected Cap Cost < 95% of Actual Cap cost,recovery from beneficiaries along with interest @0.8 times Bank Rate. 12/12/2013 6 Truing up exercise EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Truing up at the end of the period and allowed for one more time in between Same provision. Truing up on performance of controllable parameters such as heat rate, secondary fuel oil, Auxiliary energy consumption and uncontrollable parameters such as force majeure, change in law, primary fuel cost. Sharing of the financial gain due to controllable factors among Genco and beneficiary in the ratio of 3:1. Financial gain/loss due to uncontrollable factors to be passed on to beneficiaries. 12/12/2013 7 Capital Cost EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Prudence check of capital cost may be carried out taking into consideration the benchmark norms specified/to be specified by the Commission from time to time Same For variation of capital cost from benchmark norms, reasons to be specified by the company. 12/12/2013 8 Allowance of IDC/IEDC EXISTING PROVISIONS
DRAFT CERC REGULATIONS
IDC would consider phasing of funds upto SCOD. In case of additional IDC due to delay, the company would submit details with reasons.If delay is due to uncontrollable factors, IDC/IEDC may be allowed. 12/12/2013 9 Allowance of IEDC EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Any revenue earned during construction period would be adjusted against the IEDC. 12/12/2013 10 Controllable and Uncontrollable Factors EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Controllable: time/ cost overrun due to land acquisition, efficiency in implementation of project not involving any change in scope, delay due to contractor, supplier etc. Uncontrollable: force majeure events, change in law. Additional impact due to non- commissioning of generating station & transmission would be recovered through indemnification agreement. 12/12/2013 11 Initial Spares EXISTING PROVISIONS
DRAFT CERC REGULATIONS
% of original project cost: Coal- 2.5% Gas-4.0% Hydro-1.5% Transmission- 0.75% to 3.5% % of plant and machinery cost: Coal- 3.0% Gas- 3.0% Hydro- 4.0% Transmission- 1.0% to 4.5% 12/12/2013 12 Special Allowance EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Rs 5.0 lacs/ MW/ Yr in 2009- 10 with annual escalation of 5.72% Rs 7.5 lacs/ MW/ Yr in 2014-15 with annual escalation of 6.35% In case, Special Allowance is being availed in 2009-14, it is to be allowed by escalating the same for 2013-14 @ 6.35%. Details of Special Allowance to be kept and made available to commission as and when directed. 12/12/2013 13 Compensation allowance (for minor assets) EXISTING PROVISIONS
At UI rate At UI rate 12/12/2013 15 Tariff Structure EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Capacity charge includes secondary fuel oil consumption Secondary fuel oil consumption is part of the energy charge. 12/12/2013 16 Return on Equity (ROE) EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Thermal, Tx., ROR Hydro - 15.5% Storage type hydro - 16.5% Additional 0.5% linked to project completion as per specified timeline Thermal, Tx., ROR Hydro -15.5% Storage type hydro - 16.5% for Additional return of 0.5% for projects commissioned on or after 01.04.2014 within specified timelines (no change in timeline specified) 1% reduction in ROE if unit declared COD without RGMO / FGMO, data telemetry and communication system up to load despatch centre and protection system.
12/12/2013 17 Grossing up of tax rate EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Grossing up by tax rate Grossing up of ROE with tax rate shall not be available.Benefits of tax holiday for new project also NA. Tax on income corresponding to approved ROE to be recovered from the beneficiaries - If PBT is higher than IT on ROE approved, IT to be recovered = Total income tax paid ROE approved by Commission / PBT. If PBT is lower than tax on ROE, Actual income tax to be recovered from beneficiaries Annual adjustment of under / over recovery of IT Allocation of IT to beneficiaries in proportion to annual fixed charges 12/12/2013 18 Depreciation EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Depreciable value - 90% (excluding land) Depreciable life: Thermal - 25 years Hydro - 35 years Rate of Depreciation: As per the Companies Act for 12 years and balance depreciation spread over the remaining useful life. Depreciation disallowed on account of lower availability cannot be recovered at a later stage during the useful life CERC shall approve depreciation of proposed capex beyond 20 yrs from COD (Fag end) subject to prudence check. Other provisions same 12/12/2013 19 Norm for O&M expenses, escalation rate etc. EXISTING PROVISIONS
DRAFT CERC REGULATIONS
200/ 500/ 600 MW- 18.2/ 13.0/11.70 Lac/MW/ yr in 2009-10; Escalation- 5.72% 200/ 500/ 600 MW- 22.74/16.24/14.62 Lakhs /MW/ yr in 2013-14.
200/ 500/ 600 MW- 24.07/ 16.32/14.68 Lac/ MW/yr in 2014-15; Escalation- 6.35% Norms for gas station reduced from 18.49 in 2013-14 to 16.77 in 2014-15. Water charges shall be allowed separately. Not included in O&M norms. Impact of wage revision shall be allowed considering DPE guidelines and following % of O&M as employee cost .Coal - 40%, gas- 32% Hydro -46% and Tx -40% 12/12/2013 20 Station Heat rate EXISTING PROVISIONS
1.0 ml/ kWhr Pit head 0.5 ml/kwh Non pit head 1.0 ml/kwh 12/12/2013 22 Auxiliary Power Consumption EXISTING PROVISIONS
DRAFT CERC REGULATIONS
200 MW 8.5% 500 MW- 6%/ 8.5% for TDBFP and MDBFP. BTPS-9.5%, TTPS-10.5%, Tanda-12.0% Gas CC -3.0% OC-1.0% BTPS -8.5% Gas CC -2.5% REST NO CHANGE 12/12/2013 23 Normative Annual Availability EXISTING PROVISIONS
DRAFT CERC REGULATIONS
DC: 85% for full capacity charges recovery (except BTPS &TTPS : 82%) 85% 12/12/2013 24 Transit and Handling Loss EXISTING PROVISIONS
DRAFT CERC REGULATIONS
0.8% - Non pit head 0.2%- Pit head No change. In case of pit head stations transit loss of 0.8% applicable in case of rail fed coal Imported coal 0.2% 12/12/2013 25 Incentives- Linkage to Fixed Charge, Differential for Old/ New Plants EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Incentive linked to Fixed Charge on Availability
Flat rate of 50 p/kwh corresponding to scheduled energy in excess of ex bus energy corresponding to NAPLF. PLF for a given period means the total sent out energy corresponding to scheduled generation during the period, expressed as a percentage of sent out energy corresponding to installed capacity 12/12/2013 26 Use of part or full alternate coal EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Permitted in case of fuel shortage or optimization through blending Prior permission not a pre condition Wt avg. use of alternate fuel shall not exceed 30% of base price of fuel to be fixed by CERC in 2014- 15 to be escalated on month to month basis by rates notified for bidding purpose If it exceeds 30% of the above or 20% fuel price of previous month, which ever is lower prior consultation with beneficiaries shall be made 3 days in advance 12/12/2013 27 Late payment surcharge EXISTING PROVISIONS
DRAFT CERC REGULATIONS
1.25% per month beyond 60 days from date of billing 1.5% per month beyond 60 days from date of billing 12/12/2013 28 Method of computation of monthly capacity charge EXISTING PROVISIONS
DRAFT CERC REGULATIONS
Monthly Availability Method of computation of monthly capacity charge changed from monthly to cumulating every month successively. In case of shutdown due to R&M, recovery of part of AFC allowed which shall include O&M expenses and interest on loan only. 12/12/2013 29 THANK-YOU