S.No.

Description of Activity
No. of Working
days Require
Start Date Finish date
Man power
Required
Equipment
required
1
Mobilization- of manpower, machinery, safety
induction and gate passes as per site requirements.
3 6/7/2014 9/7/2014
2
Material submittals for all the items required on
site.
2 10/7/2014 11/7/2014
3
Arranging of all the Irrigation materials as per the
approved material submittals as well as per the
approved shop drawings.
4 12/7/2014 16/7/2014
4 Getting the approval of material procured on site. 2 17/7/204 18/7/2014
5
Excavating the pits for palms and trees as per the
appoved shop drawings.
10 12/7/2014 22/7/2014
6
Making the trenches for Irrigation main line as per
the approved shop drawings.
4 20/7/2014 24/7/2014
7
Laying of Irrigation main lines as per the approved
shop drawings.
3 25/7/2014 27/7/2014
8
Getting the approval of Installed Irrigation Main
lines along with the hydrolic pressure test.
2 28/7/2014 29/7/2014
9
Backfilling with planting medium to all the tree
pits.
5 22/7/2014 27/7/2014
10
Installation of Lateral lines as per the approved
shop drawings
4 30/7/2014 2/8/2014
11
Installation of the solenoid valves as per the
approved irrigation shop drawings.
2 3/8/2014 4/8/2014
12
Making the connection of the main line to the
tapping point, i.e. for tank and irrigation pump set.
1 5/8/214 5/8/214
13 Flushing of all the irrigation lines. 1 6/8/2014 6/8/2014
14 Removal of existing trees and Palms. 10 5/8/2014 15/8/2014
15
Replanting of Trees and Palms as per approved
locations.
10 6/8/2014 16/8/2014
16
Fixing of the bubblers as per the planted Trees and
Palms.
1 17/8/2014 17/8/2014
17 Final Inspection, Snaging & Desnaging. 1 18/8/2014 18/8/2014
18 Final Handing over 2 19/8/2014 20/8/2014
Total 67
Sidra Agricultrue Company
Project Schedule Base Line
NOTE : As per project our schedule it will take only 40 working days to complete the whole works where as the total column shows 67 days but there will be some activities which will go parallel
along with the other activities.
Also please note that firdays and public holidays (like Eid Holidays) has not been considered, those will be treated as extra days.
Project Name : Removal of Trees and re-planting - Al Khubaib Station
Remarks
This activity will go parallel to the other
activities
This activity will go parallel to the other
activities
This activity will go parallel to the other
activities
This activity will go parallel to the other
activities
This activity will start immediately after the
approval of the main line.
This activity will be started when all the tree
pits are ready, and filled with planting soil
and irrigation water is available on site.
Removal and planting will go side by side
with only one day difference
Prepared and Presented by :
Anwaar ul Haq
Project Manger
Sidra Agricultrue Company
Project Schedule Base Line
NOTE : As per project our schedule it will take only 40 working days to complete the whole works where as the total column shows 67 days but there will be some activities which will go parallel
along with the other activities.
Also please note that firdays and public holidays (like Eid Holidays) has not been considered, those will be treated as extra days.