1 Brick work in CM in Foundation and plinth 1.

25 Cum
2 Brick work in CM in Super Structure 1 Cum
3 Brick in CM in Arches 0.55 Cum
4 Brick in CM in Jack Arches 0.55 Cum
5 Half Brick wall in partition 5 Sqm
6 CRS Masonary in CM including dressing 1.8 Cum
7 RR Stone Masonary in CM 1 Cum
8 Ashlar Masonary inCM 0.4 Cum
9 Stone Arch Work 0.4 Cum
10 Cement concrete 1:2:4 5 Cum
11 Rbwork 1 Cum
12 RCC work 3 Cum
13 12mm Thick Plastering with CM 8 Sqm
14 Pointing with CM 10 Sqm
15 White washing or colour washing three coats 70 Sqm
16 White washing or colour washing three coats 200 Sqm
17 Painting or varnishing doors or windows one coat 25 Sqm
18 Coal tarring or solignum painting one coat 35 Sqm
19 Painting large surface one coat 35 Sqm
20 Distempering one coat 35 Sqm
21 2.5cm CC floor 7.5 Sqm
LABOUR OUT TURN WORK
S.No Item Description Quantity unit
22 Timber framing sal or teak wood 0.07 Cum
23 Timber framing Country wood 0.15 Cum
24 Door and window shutters panelled or glazed 0.15 Sqm
25 Door and window shutters battened 0.8 Sqm
26 Earth work in ecavation in ordinary soil 3 Cum
27 Earth work in ecavation in hard soil 2 Cum
28 excavation in rock 1 Cum
29
Number of Bricks laid by a mason in Brickwork upto a height
of 3m(10')
600 No's
30 Amount of work done by a mazdoor (helper) per day
Mix 3 Cum
Deliver brick to a distance of 15m 4000 No's
Deliver mortar 5.5 Cum
Scaffolding cost for Single Storey building 0.5 Rupees
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per Mason
per whitewasher
per whitewasher
per Painter
per Painter
per Painter
per Painter
per Painter
LABOUR OUT TURN WORK
Per Day
Per Carpenter
Per Carpenter
Per Carpenter
Per Carpenter
per 1 Beldar & 1 Mazdoor
per 1 Beldar & 1 Mazdoor
per 1 Beldar & 1 Mazdoor
per Mason
per Mazdoor
per Mazdoor
per Mazdoor
per Cum of Brick work
Beldars
1 Earthworks per 28.30 cum (1000cft) --
Earth works excavation in foundations, trenches etc., in
ordinary soil includingdisposal up to 30m and lift of 1.5m
28.30 Cum 5
Refilling excavated earth in foundations, plinth etc. including
consolidationin 15cms layers
28.30 Cum 3
Disposal of surplus earth within alead of 30m 28.30 Cum --
2 Cement concrete work per 2.83cum (100 cft) --
Laying Cement concrete 2.83 Cum 2
3 R.C.C work --
Laying Reinforced concrete 2.83 Cum 3
Centring and shuttering for Flat surface 9.60 Sqm 4
Renforcement work for RCC 100.00 Kgs 1
4 Stone work per 2.83 cum (100Cft) --
RR Masonary with blue stone in foundations 2.83 Cum 3
5 Brickwork per 2.83 cum --
Ist class brickwork in 1:4 CM insuper structure partition
walls, junctions ofroof, parapet walls and string course
2.83 Cum --
6 Flooring --
4cm thick CC flooringof 40Sqm 40.00 Sqm 4
7 Finishing --
Plastering with any mortar 12mm thick 40.00 Sqm --
White washing or colour washing (3coats) 60.00 Sqm --
Painting two coats such as chocolate, red, greyetc., on wood
or steel
10.00 Sqm --
S.No Item Description Quantity unit
MAZDOOR REQUIRED FOR DIFFERENT WORKS
Labour required
Mazdoors Bhisti
Mason/White
washer
Carpenters Fitter
-- -- -- -- --
4 -- -- -- --
2 0.5 -- -- --
1 -- -- -- --
-- -- -- -- --
3 0.75 0.25 -- --
-- -- -- -- --
3 1.5 0.5 -- --
-- -- -- 4 --
-- -- -- -- 1
-- -- -- -- --
2 0.5 3 -- --
-- -- -- -- --
4.5 0.5 2.25 -- --
-- -- -- -- --
3 1 -- -- --
-- -- -- -- --
3 1 3 -- --
1 -- 1 -- --
2 -- 3 -- --
MAZDOOR REQUIRED FOR DIFFERENT WORKS
Labour required
0.3 x 0.35 x 0.3 = 1.2 Cft =
S.No Item Description Qty Per unit
1 Bricks of 9"x 4 1/2" x 3" 1350 100 Cft
Dry mortar for Brickwork 30% 30 100 Cft
Stone for Rubble stone Masonary 125% 125 100 Cft
Dry mortar for Rubble stone Masonary 42% 42 100 Cft
Materials for Cementconcrete 1:2:4
Ballast or Grt 88% 88 100 Cft
Sand 44% 44 100 Cft
Cement 22% 22
MATERIALS FOR DIFFERENT ITEMS OF WORKS
1 bag of
cement
13.7795276
9.24
1984.32
1.2 1728
18.3333333
MATERIALS FOR DIFFERENT ITEMS OF WORKS