Department of Public Works and Highways

Registry of Contractors for Civil Works Projects


Contract Profile for Eligibility Processing

Date: November 23, 2011

Form NR-002

Region/District Office: Region VI Iloilo 2
nd
ED, Balabag, Dumangas, Iloilo
Project/ Contract ID: 11GG0029 (Cluster Contract)

Project/ Contract Name: (A) Repair and Maintenance of Flood Control and Drainage
Systems, Structure and Facilities, Suage River Control
Project Location: Pototan, Iloilo

(B) Repair and Maintenance of Flood Control and
Drainage Facilities, Suage River Control
Project Location: Pototan, Iloilo

(C) Repair and Maintenance of Flood Control and Drainage
System, Structures and Facilities, Jalaur River Control
Project Location: Dingle, Iloilo

(D) Repair and Maintenance of Flood Control and Drainage
System, Structures and Facilities, Jalaur River Control
Project Location: Calinog, Iloilo

Contract Duration (CD): 45 CD
Approved Budget for the Contract (ABC): A. P 500,000.00
B. P 500,000.00
C. P 700,000.00
D. P 900,000.00
Name of Newspaper for this Advertisement: Manila Standard Today
Issuance of Bidding Documents: Nov. 23 Dec. 20, 2011
Cost of Bid Documents: P 1,000.00

Major Categories of
Works
Unit of
Measure
Dimension
Cost Estimate for
Each
Major Category of
Work
Similar Major Categories
of Work
MFC LM 8.00 P 500,000.00
FHN, FHG, FHR, FHD

MFC LM 8.00 P 500,000.00
FHN, FHG, FHR, FHD

MFC LM 8.50 P 700,000.00
FHN, FHG, FHR, FHD

MFC LM 18.00 P 900,000.00
FHN, FHG, FHR, FHD



Major Categories of Work
Code Category of Work Description
Dimension
Unit of
Measure
Code Category of Work Description
Dimension
Unit of
Measure
BCB Bridges-Construction-Bailey lm MBG Maintenance Buildings Stories
BCC Bridges-Construction-Concrete lm MFC Maintenance Flood Control Cm
BCS Bridges-Construction-Steel lm MRB Maintenance Roads and Bridges Km
BCP Bridges-Construction-With Bored Piles lm PHC Ports/Harbors-Causeway Lm
BIH Buildings-Industrial Plant-HIGH Rise stories PHW Ports/Harbors-Wharf Lm
BIL Buildings-Industrial Plant-LOW Rise stories RCA Roads-New Const.-Asphalt Km
BRB Bridges-Rehabilitation-Bailey lm RCG Roads-New Const.-Gravel Km
BRC Bridges-Rehabilitation-Concrete lm RCP Roads-New Const.-PCCP Km
BRR Bridges-Rehabilitation-Retrofitting lm RRA Roads-Rehabilitation-Asphalt Km
BRS Bridges-Rehabilitation-Steel lm RRG Roads-Rehabilitation-Gravel Km
BRP Bridges-Rehabilitation-With Bored Piles lm RRP Roads-Rehabilitation-PCCP Km
FHG Flood Control/Hydraulics/Dredging cm TEA Traffic Engg Signage Piece
FHD Flood Control/Hydraulics/Dams cm TEP Traffic Engg-Pavement Markings Lm
FHP Flood Control/Hydraulics/Pumping Stn. Unit TES Traffic Engg Signalization set
FHN Flood Control/Hydraulics/Drainage lm
FHR Flood Control/Hydraulics/River Control lm
FHW Flood Control/Hydraulics/Water Supply lm



Implementing Office Signature GERARDO G. PARRA, JR. Date: November 23, 2011