Professional Documents
Culture Documents
BOOK No.
TAB No.
COMMISSIONING MANUALS
E
DOCUMENT TITLE
17
DOCUMENT No.
REVISION
COMMISSIONING PROCEDURE:
11kV SWITCHGEAR
0
No. OF PAGES
APPENDICIES
9
PROJECT
LOCATION
Ministry Of Energy
CONTRACTOR
00
ISSUED BY
Baghdad, IRAQ
JOB Ref.
ISSUE DATE
1005
These instructions do not purport to cover all details or variations in equipment, nor to provide for every possible contingency to be met during testing or
commissioning. Should further Information be desired or should particular problems arise that are not covered sufficiently for the purchasers purpose, The matter
should be referred to OEM. This document contains proprietary information of SAKR, LEBANON and is furnished to its client solely to assist him in the testing and
commissioning of the equipment described herein. This Document shall not be reproduced in whole or in part nor shall its contents be disclosed to any third party
without the written approval of SAKR Power Group.
Note
The component level check sheets and test procedures referenced herein depict philosophies for minimum check out requirements. Other vendors or
subcontractors may have equivalent documentation that may be substituted for check sheets/forms with the concurrence of the site Commissioning Manager.
REV.
DESCRIPTION
APPROVED/ ISSUED
DOCUMENT TITLE
Procedure No.
PP1-MVSW-TP-001
COMMISSIONING PROCEDURE
11KV SWITCHGEAR
0
PROJECT
CLIENT
LOCATION
13
ISSUE DATE
Baghdad, IRAQ
15-07-2010
CONTENTS
1.0
SYSTEMS CONCERNED......................................................................................................................2
2.0
SCOPE......................................................................................................................................................2
3.0
REFERENCE DOCUMENTS................................................................................................................2
3.1
3.2
4.0
5.0
PREREQUISITES...................................................................................................................................3
6.0
7.0
TEST EQUIPMENT/TOOLS.................................................................................................................4
8.0
TEST EXECUTION................................................................................................................................4
8.1
8.2
8.2.1
8.2.2
8.2.3
8.3
8.4
8.5
8.6
9.0
INITIAL INSPECTION.........................................................................................................................4
SWITCHGEAR INSPECTION.............................................................................................................4
Inspection of the Power and Ground Bus........................................................................................4
Inspection of Control Wiring, Control & Protection Devices..........................................................5
Inspection of Cubicles......................................................................................................................5
PRE-COMMISSIONING CHECKS......................................................................................................6
OPERATIONAL TESTS........................................................................................................................7
FUNCTIONAL TESTS- (LOGIC TESTS).................................................................................................9
ENERGIZED TESTS...........................................................................................................................11
ACCEPTANCE......................................................................................................................................13
1.1
2.0
Scope
2.1
3.0
11kV switchgear.
The scope of the procedure is to perform inspection and tests to verify that the
equipment has been installed and will function according to design and
operation requirements.
Reference Documents
3.1
3.2
4.0
5.0
6.0
Prerequisites
5.1
5.2
5.3
5.4
5.5
Test team should verify that the equipment can be safely energized as a part of
the whole plant electrical system.
7.0
Test Equipment/Tools
c) Megger
d) Relay test equipment for secondary injection- ISA T/D series or equivalent
e) Unit relay primary injection- ISA KAM/ GE ODEN/Megger/ or equivalent.
f) Three phase adjustable transformer
8.0
Test Execution
8.1
INITIAL INSPECTION
1.1.1
1.1.2
Check the equipment against applicable Electrical and Schematic
Drawings to be sure that the proper equipment has been installed in the proper
location.
1.1.3
8.2
1.1.1
SWITCHGEAR INSPECTION
Inspection of the Power and Ground Bus.
a. Check power bus compartments for clearances, insulation, loose
debris, no exposed control wiring, damage, phasing.
b. Inspect all ground bus connections and ensure that the ground bus
is continuous throughout the switchgear and properly connected to
station ground.
c. After inspection, reinstall all power bus cover plates.
d. Complete PP1-MVSW-TF-001
1.1.4
1.1.1
Complete PP1-MVSW-TF-001
Inspection of Breakers
I. Check incoming/outgoing breakers as per manufacturers
instruction.
8.3
PRE-COMMISSIONING CHECKS
1.1.1
1.1.2
Perform Bus insulation resistance check (Megger) with all CBs
closed and power cables and voltage transformers disconnected. PP1-MVSWTF-002
1.1.3
Perform insulation resistance check of control and auxiliary circuits.
PP1-MVSW-TF-002
1.1.6
Check power supply for the cubicle (control, auxiliary). Record data
in PP1-MVSW-TF-002.
8.4
OPERATIONAL TESTS
1.1.1
The test set for this is a low voltage, high current test device
used to test the performance of electromechanical overloads and
solid state trip devices in low voltage air circuit breakers. The test
set is rated for operation at 20,000 amps continuous and 100,000
amps instantaneous.
The air circuit breaker is connected to the test set directly by
use of the primary disconnects and current is raised to the proper
levels to test all circuit breaker functions and characteristics that will
ultimately trip the circuit breaker. All characteristics (long time,
short time and instantaneous) are verified to fall within original
manufacturer's published curves.
The above tests will confirm the ability of the air circuit
breaker to sustain high current, hot spots on the contacts and verifies
that the overloads or solid state package operate properly within a
given range of times.
N.B. It is up to the commissioning engineer to decide whether to do
primary or secondary injection tests OR conduct both tests as required.
1.1.9
8.5
The functional tests are intended to test the control circuit of the Switchgear feeders
(Logic test). This will include testing of Start/Stop commands, feedback contacts,
local alarm and signalization in addition to any other interlocks. The tests shall be
based upon the wiring diagrams of the SWITCHGEAR. The test Engineer is expected
to test/simulate all the possible logic combinations and record the results. For the
signals to remote equipment (DCS, Local Control Panels LCP), the test will be
simulated/verified at the terminals of these signals.
8.6.1
Pre-Checks
a-
b-
Check the wiring and schematic diagrams and verify that the
wiring diagrams exactly mimics the schematic diagrams.
c-
d-
e-
f-
1.1.10
8.6.3
a-
Be
sure
to
have
the
CB/Switch
of
the
INCOMING/OUTGOING feeder compartment to be tested is
disconnected prior to test.
b-
c-
Trace the control circuit wiring from the circuit power source
through the switches to the output devices.
d-
e-
f-
Phase 2 Logic Tests (All the tests shall be done with the switchgear
denergized.)
a-
b-
c-
d-
e-
f-
g-
h-
For each contact in the control circuit, change the state of each
contact, monitor the controlled devices, and verify that the
controlled devices respond, energize and de-energize, per
design.
Complete PP1-MVSW-TF-003.
ENERGIZED TESTS
i. Initial Conditions:
a.
b.
c.
d.
IV. Check that bus couplers are open and locked off - close main
feeder breaker and energize main bus system and soak for 30
minutes. After that close bus couplers to energize all the PMCC.
Repeat soak test for each newly energized section. Check phase
rotation for each section.
V. Check that all instrumentation reads correctly.
VI. Check system voltage value.
VII. Record results on PP1-MVSW-TF-004.
VIII. Measure the secondary voltages of the voltage transformers and
calculate the equivalent primary voltages/ratio.
IX. Record results on PP1-MVSW-TF-004.
i.
8.6.1 ACCEPTANCE
8.7
8.8
8.9
Compare factory test to the PP1-MVSW design criteria to ensure all design
requirements are satisfied.