SEDE

DAILY SITE REPORT


Daily Report No 362
Previous Current
Accumulative
Till today
1
1-1
Wooden fences for the site location L.S. Site location 97.00% 0.00% 97.00%
Install the wooden fences frames
100%(564 L.m from the total length
of the fences=564)
- Plywood panels 100%(564L.m from
the total length of the fences=564)
-Painting of the Fences
100%(564L.m from the total length of
the fences=564)
1-2
Prepare the site office L.S. Site location 95.00% 0.00% 95.00%
1-3
Reading water Ground Level in Three
Piezometers
Site location
Daily recorded (WATER GROUND
LEVEL=- 3.58)
2
2-1
supplying steel structure material Site location 85.00% 0.00% 85.00%
2-2
preparation of Pipe Support Site location 80.00% 10.00% 90.00%
2-3
Steel Fixing & Shuttering for Pipe
Support
Site location 30.00% 30.00% 30.00%
2-4
erection steel structure Site location 80.00% 0.00% 80.00%
2-5
grout Casting for Steel Column Site location 80.00% 20.00% 100.00%
2-6
concrete for pipe support Site location 80.00% 10.00% 90.00%
2-7
block work from axis 1-9 Site location 0.00% 10.00% 10.00%
3
3-1
Internal wall preparation for plaster Site location 95.00% 0.00% 95.00%
3-2
painting for basement walls ,columns &
beams
Site location 75.00% 0.00% 75.00%
3-3
plaster work Site location 95.00% 0.00% 95.00%
3-4
Paint for ground floor walls Site location 70.00% 10.00% 80.00%
3-5
Water proofing for Roof Site location 60.00% 10.00% 70.00%
3-6
shuttering for ground floor screed Site location 70.00% 20.00% 90.00%
3-7
screed for ground floor Site location 65.00% 25.00% 90.00%
3-8
thermal isolation for roof Site location 0.00% 20.00% 20.00%
3-9
anti-fungus paint for ground floor celling Site location 0.00% 50.00% 50.00%
4
4-1
finishing and grinding, repairing works for
internal walls
Site location 95.00% 0.00% 95.00%
4-2
finishing and grinding, repairing works for
external walls
Site location 85.00% 0.00% 85.00%
5
5-1
backfilling for foundation Site location 90.00% 0.00% 90.00%
5-2
Block work for internal walls Site location 95.00% 0.00% 95.00%
8:58:04 AM 26-06-14
REMARKS
Item
No.
Electrical & Control Building
WORK IN PROGRESS
Pump House:
General :
Location
Execution %
Description of works Unit
Contract
Qty.
Quantity
Accepted
Utility Building
Transformers Boxes
2 No's Distribution Transformers
( 26-06-2014 )
Abu Dhabi Transmission & Dispatch Company (TRANSCO)
WATER SUPPLY SYSTEM FOR FUJAIRAH DISTRBUTION NETWORK
DATE &TIME :
SOCIETE' EGYPTIENNE D' ENTREPRISES
CONSULTING
ENGI NEERS
Page 1 of 3
5-3
Block work for external walls Site location 15.00% 0.00% 15.00%
5-4
shuttering for cable trenches(Blinding) Site location 0.00% 15.00% 15.00%
5-5
blinding for cable trench Site location 0.00% 15.00% 15.00%
5-6
supplying steel structure materials Site location 0.00% 50.00% 50.00%
6
6-1
surface preparation for surge vessel
supports
Site location 100.00% 0.00% 100.00%
6-2
Install Surge Vessel tanks PG1 & PG2 Site location 100.00% 0.00% 100.00%
7
7-1
closing shutter of roof parapet Site location 0.00% 100.00% 100.00%
7-2
Curing for roof Site location OK
8
8-1
shoring for excavation sides retaining Site location 100.00% 0.00% 100.00%
8-2
Pouring Concrete for first stage of Walls
& Slab
Site location 100.00% 0.00% 100.00%
8-3
Curing Site location OK
8-4
surface preparation for first stage wall Site location 0.00% 50.00% 50.00%
9
9-3
Excavation Site location 0.00% 50.00% 50.00%
10
10-1
Excavation Site location 100.00% 0.00% 100.00%
10-2
Blinding Site location 100.00% 0.00% 100.00%
10-3
water proofing Site location 0.00% 100 10000.00%
10-4
screed for base Site location 0.00% 100.00% 100.00%
10-5
shuttering for foundation steel fixing Site location 0.00% 50.00% 50.00%
Prepared by: Checked By: Approved by: Reviewed
by :
Technical Engineer : Technical office Manger Project Manager: ILF Site Manager :
Ayman Saber
Peter Grogan
Engineer's Comments:
Surge Vessel PG1 & PG2
Oil Separator & Drain Storage
Water Quality Monitor
VP-05
Ahmed Al Shoura
Contractor's Highlights & Remarks:
VP-06
Page 2 of 3
362
1 Yes No
2 Yes No
3 Yes No
4 Yes No
5 Yes No
6 Yes No
7 Yes No
8 Yes No
9 Yes No
10 Yes No
11 Yes No
12 Yes No
1 Deputy General Manager 1 10 10 18 Site Engineer 1 10 10 40 Kitchen stuff 6 10 60
2 Project Manager 1 10 10 19 1 10 10 41 Labour 3 10 30
4 Technical Office Manger 1 10 10 20 QC / QA Engineer 1 10 10 42 Camp supervisor 2 10 20
5 QC / QA Manger 1 10 10 21 Foreman 4 10 40
6 Technical Eng. 3 10 30 22 Surveyors 1 10 10
7 Document Controller 1 10 10 23 Safety Officer 2 10 20
8 Head of Design Section 1 10 10 24 Carpenter 8 10 80
9 Design Eng. 16 10 160 25 Steel Fixer 8 10 80
10 Head of E/ ICT Eng. 1 10 10 26 Proofing Technician 1 10 10
11 E/ ICT site Engineer 1 10 10 27 Electrician 1 10 10
12 QS Engineer 1 10 10 28 Un-skilled Labours 34 10 340
13 Plant & Equipment Manager 1 10 10 29 skilled Labours 45 10 450
14 Planning Engineer 1 10 10 30 Operator 5 10 50
15 Secretary 1 10 10 31 Driver 11 10 110
16 Surveying Engineer 1 10 10 32 Security Guards 2 10 20
17 Site Office Boy 2 10 20 33 Mason 6 10 60
34 Dewatering Technician 1 10 10
35 block mason assistant 3 10 30
36 Block mason 5 10 50
37 steel structure foreman 1 10 10
38 2 10 20
39 Painter 2 10 20
40 3 10 30
34 10 340 148 10 1480 11 10 110
193
Number Number Number
1 Six Wheel 1 16 Pickup car ( 3 ton) 2 22 Water Tanker 1
2 Loader 1 17 Land cruiser 2 23 Salon Car 1
3 Water Pump 3 18 Crane 50 ton 1
4 J.C.B 1 19 excavator
5 Roller (1 Ton) 2 20 welding machine
6 Plate Compactor 1
7 Vibrator 4
8 Pickup car 2
9 Triller 1
10 Water tanker 2
11 Air Compressor 2
12 Generator130 KV. 2
13 Eagle Generator 5 KV. 1
14 Bus 5
15 sandblaster 1
Total 29 Total 5 Total 2
Prepared by: Checked by: Approved by: Reviewed by :
Technical Engineer : Technical office Manger: Project Manager:
ILF Site Manager :
Ahmed Al Shoura Ayman Saber
Peter Grogan
Steel fixing & Shuttering of Pump House Pipe supports
plaster work for E&C Building walls
Number
Man
Hr./day
Total
Man
Hr./day
Man Power (Site) Number
Man
Hr./day
Total Man
Hr./day
Construction Manger
shuttering & steel fixing for VP-06 foundation
steel structure technician
Equipment (Site )
Plaster mason
Sub Total (Camp and Office)
Equipment
SEDE SEDE SEDE
Total Total Total
Equipment (Camp) Equipment (Site )
Number
Man
Hr./day
Total
Man
Hr./day
Man Power (Office)
steel structure erection for utility building
shutter for utility building(cable trench)
concrete for W.Q.M parapet
blockwork for pump house
Man Power
SEDE SEDE SEDE
Man Power (Camp)
Roof slab of electrical building finishing works
excavation for VP-05
Paint for ground floor walls & Ceiling Electrical Building
Permits Required?
Prepare the site layout facility
Reading water Ground Level in Three Piezometers.
SEDE
WATER SUPPLY SYSTEM FOR FUJAIRAH DISTRBUTION NETWORK

I
t
e
m

N
o
Reporting Date ( 26-06-2014 )
Daily Equipment Report & Forecast No.-
Forecast for the next day ( 28-06-2014 )
CONSULTING
ENGI NEERS
Page 3 of 3