You are on page 1of 47

MINISTRY OF CONSTRUCTION

PUBLIC WORKS
ANALYSIS OF RATES
FOR
BRIDGE WORKS
GOVERNMENT OFTHE REPUBLIC OF THE UNION OF MYANMAR
SECOND EDITION
JUNE 2013
CONTENTS
SH-NO
1 . O
2.0
3.0
4.0
5.0
6.0
NAME OF SUB-HEAD
BRIDGES
SUB-HEADS
Foundation Work
P.C Girder
Steel Truss
Steel Plate Girder
Suspension and Cablestayed Bridge
Survey
Miscellaneous Notes
-
PAGE NO
1
Standard Data for Working Out Rates Per Unit Quantity ofltems of Work.
Foreman
Carpenter (1 st Grade)
Carpenter (2nd Grade)
Worker
Sr
No.
1
2.
3.
Particulars of Materials and Labour
X IX. BRIDGES
Foundation Works
Labour For Driving (250 mm) Diameter Timber
Piles inordinary Soil(With 500 kg drop hammer
from pulley winch and local trestle and manually
operated). Penetration average 6 m.
Labour
Plants
Pile driving frame (1)No
Sundries
Labour For Driving (250 mm)Diameter Timber
Piles inordinary Soil (With pile driving machine).
Penetration average 6 m.
Labour
Operator
Foreman
Carpenter (I st Grade)
Carpenter (2nd Grade)
Worker
For Operation
H.S.D
Grease
Plants
Pile driving frame (1)No
Sundries
Labour for Pile Driving reinforced cement con-
crete pile (350 mm x 350 mm x 12000 mm) in
ordinary soil (with 12m dieselhammer).
Penetration average 12 m.
Labour
Foreman
Pile driving machine operator
Pile driving machine Asst
Crane operator
Worker
Unit
Man-Day
Man-Day
Man-Day
Man-Day
Hour
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
litre
kg
Hour
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Quantity
0.3
0.5
0.5
3
4
-
0.3
0.3
0.5
0.5
3
3
0.1
2.7
-
0.3
0.3
0.3
0.3
6
Remarks
- Cost of Timber piles
according to varying dia;
with all necessary fittings
is to be included in the
main estimate.
- Cost of Timber piles
according to varying dia;
with all necessary fittings
is to be included in the
main estimate.
A
2
StandardData for Working Out Rates Per Unit Quantity of Items of Work-contd.
Particulars of Materials and Labour
'001s Required
12m)rail line trollies for transport of precast
bile.
One crane for loading unloading erecting
and pitching of precast pile.
Pile driving machine (1) No
;or Operation
H.S.D for Pile Driving Machine
H.S.D for Crane
Engine Oil
Sundries
.abour for Pile Driving reinforced cement con-
rete pile (350 mm x 350 mm x 12000 mm) in
~rdinary soil ( Using drop hammer with winch
~perated by machine).Penetration Average 12m.
.abour
Foreman
Operator
Worker
dachine
Pile driving machine (1)No
:or Operation
Diesel Oil
Grease Oil
Sundries
Making of Stand Pipe 8 rnrn thk; 12mm thk;
(800 mm 0 to 1 650 mm 0 ) (For 1 Sqm)
Steel fixer
Worker
Driving Stand Pipe
Driving of Stand Pipe1 350mm 0,1650mm 0
with Vibro Hammer for 1200mm 0 ,
1500mm 0 Bored Pile. ( For 1 m )
Stand pipe
Steel fixer
Head Worker
Worker
Unit
Hour
Hour
Hour
Man-Da:
Man-Da:
Man-Dti
Remarks
Cost for R.C Piles to be
calculated according to
the reqd.Size and inclu-
ded in the main estimate.
Cost for R.C Piles to be
calculated according to
the reqd.Size and inclu-
ded in the main estimate.
3
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
(b)
7.
(a)
(b)
Particulars of Materials and Labour
Electric Helper
Operator /Machine Driver
Sundries
H.S.D
Driving of Stand Pipel950rnrn 0,2650mm 0
with Vibro Hammer for1 800mm 0,2500mm0
Bored Pile. ( For 1 m )
Stand Pipe
Steel Fixer
Head Worker
Worker
Electric Helper
Operator /Machine Driver
Sundries
H.S.D
Removing Stand Pipe
Removing of Stand Pipe 1350mm 0,1650mm0
with Vibro Hammer for 1200 mm 0 ,
1500mm 0 Bored Pile. ( For 1 m )
Stand Pipe
Steel Fixer
Head Worker
Worker
Electric Helper
Operator Machine Driver
Sundries
Removing of Stand Pipe 1950mm 0,
2650 mm0 with Vibro Hammer for 1800mm 0,
2500mm 0 Bored Pile. ( For 1 m )
Stand Pipe
Steel Fixer
Head Worker
Worker
Electric Helper
Operator /Machine Driver
Sundries
H.S.D
Unit
Man-Day
Man-Day
L.S
litre
No
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
litre
No
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
No
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
litre
Quantity
0.5
0.7
-
-
1
1
3.2
0.5
0.7
-
-
-
0.7
0.5
2
0.5
0.5
-
-
0.7
0.7
2.5
0.5
0.5
-
-
Remarks
4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd
Head Worker
Worker
Operator Machine Driver
Sundries
H.S.D
Sr
No.
8.
9.
10.
1 1.
Remarks Particulars of Materials and Labour
Fitting of Drilling Equipment to dig Bored Pile.
1200rnm 0 , 1500rnm 0 ,1800mm 0,
2500rnm 0. ( For 1 time )
Head Worker
Worker
Operator /Machine Driver
Sundries
H.S.D
Dismantling of Drilling Equipment.
( For 1 time )
Drilling of 800mm 0 mini Bored Pile.
(Ground, Ordinary Soil) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Water Pump Helper
Sundries
H.S.D
Machinary hair Charges
Drilling of 800 mm @mini Bored Pile.
(Ground , Weathered Soft Rock ) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Water Pump Helper
Sundries
H.S.D
Machinary hair Charges
-
Unit
Man-Day
Man-Day
Man-Day
L.S
litre
Man-Day
Man-Day
Man-Day
L.S
litre
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
litre
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L. S
litre
L.S
Quantity
2
7
0.8
-
-
2
7
0.8
-
-
0.7
0.5
2
0.3
0.3
-
-
-
1.3
1
4
0.7
0.7
-
-
-
5
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
12.
13.
14.
15.
Particulars of Materials and Labour
Drilling of 800 rnm 0 mini Bored Pile.
(Water, Ordinary Soil) ( For 1 m )
Head Worker
Foreman
Worker
Operator /Machine Driver
Water Pump Helper
Sundries
H.S.D
Drilling of 800mm 0 mini Bored Pile.
(Water , Weathered Soft Rock) ( For 1 m )
Head Worker
Foreman
Worker
Operator /Machine Driver
Water Pump Helper
Sundries
H.S.D
Drilling of 1200mm 0 Bored Pile
( Ordinary Soil ) ( For 1 m )
Head Worker
Foreman
Worker
Operator /Machine Driver
Water Pump Helper
Sundries
H.S.D
Drilling of 1500mm 0 Bored Pile
( Ordinary Soil ) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Water Pump Helper
Sundries
H.S.D
Unit
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L. S
litre
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
litre
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L. S
litre
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L. S
litre
Quantity
0.8
0.6
2.5
0.4
0.4
-
-
1.5
1.2
5
0.8
0.8
-
-
1
0.5
3
0.5
0.3
-
-
1.2
0.5
3.5
0.5
0.4
-
-
Remarks
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Quantity
1.4
0.8
4.3
0.7
0.5
-
-
1.5
0.8
4.5
0.8
0.5
-
-
1.5
0.8
4.8
0.8
0.5
-
-
1.3
0.5
3.5
0.5
0.4
-
-
Unit
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
litre
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
litre
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
litre
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
litre
Sr
No.
16.
17.
18.
19.
Remarks
Particulars of Materials and Labour
Drilling of 1500mm 0 R.C.D Bored Pile
( Ordinary Soil ) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Water Pump Helper
Sundries
H.S.D
Drilling of 1800mm 0 , Bored Pile
( Ordinary Soil ) ( For 1 m )
Head Worker
Foreman
Worker
Operator /Machine Driver
Water Pump Helper
Sundries
H.S.D
Drilling of 2500rnm 0 , Bored Pile
( Ordinary Soil ) ( For 1 m )
Head Worker
Foreman
Worker
Operator /Machine Driver
Water Pump Helper
Sundries
H.S.D
Drilling of 1200mm 0 Bored Pile.
( Weathered Soft Rock Layer Only, Based on Soil
Test Result ) ( For 1 m )
Head Worker
Foreman
Worker
Operator /Machine Driver
Water Pump Helper
Sundries
H.S.D
I
Standard Data for Working Out Rates Per Unit Quantiry of Items of Work-contd.
Particulars of Materials and Labour
lrilling of 1500mm 0 Bored Pile
: Weathered Soft Rock Layer Only) Based on Soil
rest Result ) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Water Pump Helper
Sundries
H.S.D
lrilling of 1500rnrn 0 R.C.D Bored Pile
Weathered soft rock Layer only Based on soil
Testresult) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Water Pump Helper
Sundries
H.S.D
lrilling of 1800mm 0 Bored Pile
: Weathered Soft Rock Layer Only Based on
Soil Test Result ) ( For 1 m )
Head Worker
Foreman
Worker
Operator /Machine Driver
Water Pump Helper
Sundries
H.S.D
Drilling of 2500mm 0 Bored Pile
( Weathered Soft Rock Layer Only based on
Soil Test Result ) ( For 1 m )
Head Worker
Foreman
Worker
Operator Machine Driver
Unit
Man-Da:
Man-Da:
Man-Da:
Man-Da:
Man-Da:
L.S
litre
Man-D?
Man-D?
Man-D?
Man-Da:
Remarks
8
Standard Data for Working Out Rates Per Unit Quantity of hems of Work-contd.
Worker
Sundries
H.S.D
Sr
No.
24.
25.
26.
27.
28.
Particulars of Materials and Labour
Water Pump Helper
Sundries
H.S.D
Mixing of Betonite Solution. (For 1 cum)
Worker
Sundries
H.S.D
After drilling Bored Pile and fitting tremie pipe to
pour concrete , Proving of Slime Wash with
Compressor, for cleaning to Bored hole.
(For 1 hole)
Hanging of Steel Cage for 800mm0,1000rnrn 0 ,
1200 mm 0 to Bored Hole with Crane.
(For 12m length )
Welding Rod
Steel Fixer
Worker
Sundries
Hanging of Steel Cage for 1500 mrn 0 ,
1800 mm 0, 2500 mm 0 to Bored Hole with
Crane. (For 12m length )
Welding Rod
Steel Fixer
Worker
Sundries
H.S.D
Pouring (1 : 1 ?4 :3) Cement concrete by Tremie
Method. (1 cum)
Head Worker
Worker
Operator /Machine Driver
Sundries
H.S.D
Unit
Man-Day
L.S
litre
Man-Day
L.S
litre
Man-Day
L.S
litre
kg
Man-Day
Man-Day
L.S
kg
Man-Day
Man-Day
L.S
litre
Man-Day
Man-Day
Man-Day
L.S
litre
Quantity
0.7
-
-
0.8
-
-
3
-
-
-
2
6
-
-
3
8
-
-
0.5
0.8
0.1
-
-
Remarks
9
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Particulars of Materials and Labour
oining, Dismantling, Cleaning, Painting of
:arth oil & Grease of Tremie Pipe to be ready.
For 1 m )
Steel Fixer
Helper
Sundries
3reaking of Bored Pile Head. ( 1 cum )
Head Worker
Sundries
Well Foundation
Iigging and sinking of 1200mrn0 spun pipe
o get specified depth including removing soil
md water pumping. (Ground, Ordinary soil)
For 1 m)
Worker
Carpenter
Head Worker
Operator
Steel Fixer
Sundries
Iigging and sinking of 1200mm0 spun pipe
o get specified depth including removing soil
md water pumping. (Ground, Sand) (For 1 m)
Worker
Carpenter
Head Worker
Operator
Steel Fixer
Sundries
Digging and sinking of 1200mm0 spun pipe
to get specified depth including removing soil
md water pumping. (Ground, Weathered soft
rock) (For 1 m)
Worker
Carpenter
Head Worker
Unit
vim-Daj
vim-Daj
Man-Da:
Man-Dq
Man-Dq
L. S
Man-Dq
Man-Da,
Man-Da
Remarks
10
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
34.
35.
36.
37.
Particulars of Materials and Labour
Operator
Steel Fixer
Sundries
Digging and sinking of 1200mrn0 spun pipe
to get specified depth including removing soil
and water pumping. (Water, Ordinary soil)
(For 1 m)
Worker
Carpenter
Head Worker
Operator
Steel Fixer
Sundries
Digging and sinking of 1200mm0 spun pipe
to get specified depth including removing soil
and water pumping. (Water, Sand) (For 1 m)
Worker
Carpenter
Head Worker
Operator
Steel Fixer
Sundries
Digging and sinking of 1200mm0 spun pipe
to get specified depth including removing soil
and water pumping. (Water, Weathered soft
rock) (For 1 m)
Worker
Carpenter
Head Worker
Operator
Steel Fixer
Sundries
Digging and sinking of 2750mm0 cassion well
to get specified depth including removing soil
and water pumping. (Ground , Ordinary soil)
(For 1 m)
Quantity
1.6
1.2
-
15.6
1.2
1.2
1
0.7
-
19.6
1.6
1.2
1.2
1
-
31.2
2.4
2.2
1.9
1.4
-
Unit
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L,S
Remarks
-1 -1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Quantity
2
63
0.5
10
3
6
6.5
9
10.5
3
-
2.5
78.8
0.6
12.5
3.8
7.5
8.1
11.3
13.1
3.8
-
4
126
1
20
6
12
13
18
Unit
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Sr
No.
38.
39.
Remarks
Particulars of Materials and Labour
Head Worker
Worker
Welder
Operator
Steel Fixer
Foreman
Diver
Helper
Rigger
Carpenter
Sundries
Digging and sinking of 2750mm0 cassion well
to get specified depth including removing soil
and water pumping. (Ground , Sand)
(For 1 m)
Head Worker
Worker
Welder
Operator
Steel Fixer
Foreman
Diver
Helper
Rigger
Carpenter
Sundries
Digging and sinking of 2750rnm0 cassion well
to get specified depth including removing soil
and water pumping. (Ground, Weathered soft
rock) (For 1 m)
Head Worker
Worker
Welder
Operator
Steel Fixer
Foreman
Diver
Helper
12
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Remarks
Sr
No.
40.
41.
42.
Particulars of Materials and Labour
Rigger
Carpenter
Sundries
Digging and sinking of 2750rnm0 cassion well
to get specified depth including removing soil
and water pumping. (Water , Ordinary soil)
(For 1 m)
Head Worker
Worker
Welder
Operator
Steel Fixer
Foreman
Diver
Helper
Rigger
Carpenter
Sundries
Digging and sinking of 2750rnrn0 cassion well
to get specified depth including removing soil
and water pumping. (Water, Sand) (For 1 m)
Head Worker
Worker
Welder
Operator
Steel Fixer
Foreman
Diver
Helper
Rigger
Carpenter
Sundries
Digging and sinking of 2750mm0 cassion well
to get specified depth including removing soil
and water pumping. (Water, Weathered soft
rock) (For 1 m)
Head Worker
Unit
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Quantity
21
6
-
2.4
75.6
0.6
12
3.6
7.2
7.8
10.8
12.6
3.6
-
3
94.6
0.7
15
4.6
9
9.7
13.6
15.7
4.6
-
4.8
13
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Mechanic
Worker
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
15
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
-
54.
I
Particulars of Materials and Labour
Stressing for Post tension HT Wire to get
complete strength . (1 Tendon)
Erector
Steel Fixer
Operator Machine Driver
Machine Helper
Electric Helper
Worker
Sundries
55. Plugging (1 : 1: 1)Cement Concrete into the
Concrete cavity of the end-block. (Girder 1 No)
Mason
Worker
Sundries
56.
1 58. 1 ~ i x i n ~ lowering bar, jacking beam, hanger jack
Grouting high strength cement motor with Gro-
uting machine to sheating pipe. (Girder 1 No)
Mechanic
Electric Helper
Operator Machine Driver
Worker
Sundries
57.
Erector
Worker
Sundries
Fixing cycle trolley, launching arm and accesso-
ries on the bailey girder. (with crane and man)
Including fixing break wedge and sway braces.
(1 pair)
Erector
Worker
Sundries
Remarks Unit
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L.S
Quantii
1
0.3
0.7
0.3
0.3
11
-
1
2
-
3
1
1
30
-
8
40
-
Man-Day 5
Man-Day 35
L.S -
16
Standard Data for Working Out Rates Per Unit Quantity ofItems of Work-contd.
Sr
No.
59.
60.
61.
62.
63.
64.
Particulars of Materials and Labour
Side shifting P.C Girder from casting position
to Launghing position distance l m . (1 time)
Erector
Worker
Sundries
Making Jack up P.C Girder, timber crib.
Tighting in hanging beam with steel cable,
removing crib, fixing to get right alignment
between two Launching Arm. (1 time)
Erector
Carpenter
Worker
Sundries
Pulling Steel cable from electric winch and
fixing them top of the launching Arm. (1 time)
Erector
Electric Helper
Worker
Launching P.C Girder by electric winch.
Launching (1 time)
Mechanic
Electric Helper
Erector
Worker
Making Jack Down Launched P.C Girder
bracing strut not to fall down. (1 time)
Erector
Carpenter
Worker
Sundries
After making jack down dismantling launching
equipment from P.C Girder,Pushing Launching
arm to the casting stagging. (1 time)
Erector
Machine operator driver
Worker
Unit
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Quantity
5
20
-
4
2
15
-
2
1
3
4
1
2
20
4
4
4
-
2
1
6
Remarks
-
Sr
Jo.
-
55.
i6.
i7.
58.
69
17
Slandard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Particulars of Materials and Labour
Levelling and carving on the Cross Beam for
fitting P.C Girder,carving 1200mm 0 x 254mm
grouting hole, fitting bearing plate. (1 sheet)
Mason
Erector
Worker
Sundries
Fixing pretension frame with anchor bolt on the
concrete pretension bench according to the
required design. (1 0 Nos)
Erector
Worker
Putting H.T wire coil (3MT)to the Dispencer
with crane using man,fixing bolt & nut.
(1 coil-3 ton)
Erector
Worker
Sundries
Pulling H.T wire to Dispencer for required
length,cutting then with griding machine.
(60 Nos)
Erector
Mechanic
Head Worker
Worker
Skill (Electric)
Sundries
Fixing repaired wires in pretension bench,
anchorage frame systematically.
(26m - 38 Nos)
Erector
Head Worker
Worker
Sundries
(18m - 38 Nos)
Erector
Unit
Aan-Daj
Aan-Daj
Am-Daj
L.S
Aan-Daj
Aan-Daj
Man-Da
Man-Da
Man-Da
L.S
Man-Da
Remarks
Standard Data for Working Out Rates Per Unit Quantig of Items of Work-contd.
Erector
Remarks Quantity
3
25
-
2
0.1
0.1
0.1
0.1
0.1
-
0.1
0.1
0.3
-
3
8
3
2
1
1
-
Unit
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L. S
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Sr
No.
70.
71.
72.
73.
74.
Particulars of Materials and Labour
Head Worker
Worker
Sandries
Fixing end plate each end of the P.C Girder
systematically whille arranging H.T wire.
(Girder 1 No)
Stressing for pretension H.t wire to get stressing
force3.45 MPa. ( wire 1 No)
Mechanic
Erector
Machine operator driver
Worker
Skill (electric)
Sundries
Stressing of 12mm 0 or 13 rnm 0 7 strand wire
(For 1 No)
Foreman
Steel Fixer
Worker
Sundries
After fixing and checking P.C wire and rein-
forcement due to design, stressing H.T wire to
get required design force and elongation.
(Wire 38 Nos)
Erector
Worker
Skill (electric)
Hard Worker
Operator (Jack operator)
Operator (Hydraulic pump)
Sundries
Fixing accessories on the P.C Girder as per
design.
(a)Making and fixing hook (2 points)
19
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd
Remarks Quantity
2
-
7
3
-
0.4
-
0.1
-
0.8
-
0.2
-
3
Unit
Man-Day
L. S
Man-Day
Man-Day
L.S
Man-Day
L.S
Man-Day
L.S
Man-Day
L.S
Man-Day
L.S
Man-Day
Sr
No,
75.
76.
77.
78.
79.
Particulars of Materials and Labour
Erector
Sundries
@)Making and fixing shoe plate (1 0 Points)
Welder
(c)fixing througt bolt & nut (1 0 Nos)
Erector
Sundries
Fixing of R.S.T Beam, H Beam, Angle,
M.S Flat & Channel for casting bed only.
(For 10 kg)
Head Worker
Sundries
Dismantling of R.S.T Beam, H Beam, Angle,
M.S Plate, M.S Flat & Channel for casting bed
only. (For 10 kg)
Head Worker
Sundries
Fixing of L.S.T Part, Bailey Part & C.H Parts
system. ( (For 10 kg)
Head Worker
Sundries
Dismantling of L.S.T Part , Bailey Part & C.H
Parts system. ( (For 10 kg)
Head Worker
Sundries
Steel Truss
Labour for Launching of R.S.JS. over bridge
sup ports (Using two pulleys and winch from
the other side) (5No x 13000rnrn x 610mrn x
190mm) at (43.l)kg per RFT.
(Total Weight = 9.3 MTons)
Labour
Bridge Foreman
20
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Total Kit one
One hammer
Coir rope (25mm 0 61m)
25000 Kg Jacks (2)No
Bridge Foreman
Worker
Sundries
2 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd
Quantity
-
-
-
-
-
-
-
-
-
-
-
-
20
150
1150
-
-
-
-
-
-
-
-
-
-
-
-
Unit
-
-
-
-
-
-
-
-
-
-
-
L.S
Man-Day
Man-Day
Man-Day
-
-
-
-
-
-
-
-
-
-
-
L.S
Sr
No.
83.
Remarks
Particulars of Materials and Labour
Tools Required
Total Kit one
One hammer
Coir rope (25mrn 0 61m)
4000 Kg Hand Winch (2)No
Bailey Roller (6)No
Jumper (1 0)No
Wire Rope (16mm 0 228m)
One local JIB
Double pulley (2)No
Single pulley (1)No
50000 kg Jacks (2)No
Sundries
(b) Labour for assembling and launching C.H.
bridge (6.5m Road way)bolts and nuts for all
steel works complete (48m) span double depth.
(Total Weight = 150 MTons) (By Crane)
Labour
Bridge Foreman
Skilled Worker
Unskilled Worker
Tools Required
Total Kit one
One hammer
Coir rope (25mm 0 61m)
4000 Kg Hand Winch (2)No
Bailey Roller (6)No
Jumper (1 0)No
Wire Rope (1 6mm 0 228m)
One local JIB
Double pulley (2)No
Single pulley (1)No
50000 kg Jacks (2)No
Sundries
Labour for assembling and German bridge
(3.35m Road way) on scaffolding and lowering
down on supports or launching (1 8m)span.
(Total Weight = 17.87 MTons)
22
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Bridge Foreman
Worker
Bridge Foreman
Skilled workers
Unskilled workers
Sr
No.
84.
85.
Particulars of Materials and Labour
Labour
Tools Required
Bailey Jacks = 2 No
Bailey rollers = 7 No
One spanner
One hammer
Sundries
Labour for assembling of R.P.T bridge on
scaffolding including rivetting and lowering
down on supports complete (30m).Span and
(5m) road way.
(Total Weight = 64.2 MTons)
Labour
Tools Required
4000 Kg hand winch
Wire rope (12rnm 0 457m)
Wire rope (1 6mm 0 457m)
Coir rope (25mm 0 152m)
Service bolts
Double pulley (2)No
Single pulley (1)No
One Bellow
Dollys (2)No
Rivetting guns (2)No
One compressor with (2)No. Hose pipe (1 52m)
Local JIB one No.
One hammer
75000 Kg Jacks (2)No
Sundries
Labour for assembling and launching of R.P.T
bridge after rivetting complete for all steel
works (3Om)span (5m) road way.
(Total Weight = 64.2 MTons)
Unit
Man-Day
Man-Day
-
-
-
-
L.S
Man-Day
Man-Day
Man-Day
-
-
-
-
-
-
-
-
-
-
-
-
-
-
L.S
Quantity
8
80
-
-
-
-
-
30
100
420
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
Remarks
23
Standard Datafor Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
86.
87.
Particulars of Materials and Labour
Labour
Bridge Foreman
Skilled workers
Unskilled workers
Tools Required
4000 Kg hand winch
Wire rope (1 2rnm 0 457m)
Wire rope (16rnm 0 457m)
Coir rope (25mm 0 152m)
Service bolts
Double pulley (2)No
Single pulley (1)No
One Bellow
Dollys (2)No
Rivetting guns (2)No
One compressor with (2)No. Hose pipe (500')
Local JIB one No.
Bailey rollers (6)No
Jumpers (1 0)No
75000 Kg Jacks (2)No
Sundries
Shifting Steel Truss and Bailey by Crane from
one place to another (Including hooking,
removing, handling with man) (10 MTons)
Foreman
Head Worker
Worker
Sundries
Sorting & arranging the steel truss systemati-
cally, Laying out them for preassambling works
systematically. (1 0 MTons)
Foreman
Head Worker
Worker
Sundries
Unit
Man-Day
Man-Day
Man-Day
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
L.S
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
L.S
Quantity
35
120
400
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
1
1
5
-
1
1
4
-
Remarks
Standard Data for Working Out Rates Per Unit Quantity ofltems of Work-contd.
Steel Fixer
Head Worker
Worker
Operator /Machine Driver
Electric Helper
Sundries
Remarks Quantity
2
1
2
0.5
0.5
-
4
2
4
1
1
-
1
4
1
0.5
4
0.5
0.8
0.5
3
0.5
Unit
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L. S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Sr
No.
88.
89.
90.
Particulars of Materials and Labour
Checking the steel truss according to the design
for preassembling works on the ground.
(1 000 kg)
(a) Erecting the preassembled steel truss from
pier to pier with erection crane according to
the design. (1000 kg)
Steel Fixer
Head Worker
Worker
Operator /Machine Driver
Electric Helper
Sundries
(b) Allowing 50% of the above expenditure
for dismentling.
(a) Installing Bolts & Nuts, Drift Pins & Tigh-
tenning according to the design while erecting
steel truss. (1000 Nos)
Steel Fixer
Worker
- Tightening them with & Electric Guns again
before transfering the target place. (1000 Nos)
Steel Fixer
Head Worker
Worker
Electric Helper
(b) Removing Bolt & Nuts (1 000 Nos)
Steel Fixer
Head Worker
Worker
Electric Helper
25
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
91.
92.
93.
94.
Particulars of Materials and Labour
Final Tightenning the ready installed Bolts &
Nuts according to theTightenning sequence
( including with checking them whether
standard or not ) (1 000 Nos)
Steel Fixer
Head Worker
Worker
Electric Helper
Sundries
Checking high tension Bolts & Nuts with check
Wrench whether standard or not. (1 000 Nos)
Steel fixer
Worker
Sundries
(a)Fixing the safety Net to the upper & lower
steel truss systematically. (1 00 m)
Carpenter
Head Worker
Worker
Sundries
(b) Removing Safety nets from Steel truss
Systemtically. (1 00 m)
Carpenter
Head Worker
Worker
Sundries
Fixing Sleeper on the top & bottom Chord of
the Steel truss. (200 mm x 200 rnm)
(a) Carving sleepers fixing on Top Chord.
(1 00 Nos)
Carpenter
Sundries
(b) Drilling holes on the sleepers for hooking.
(1 00 Nos)
Carpenter
Sundries
Unit
Man-Day
Man-Day
Man-Day
Man-Day
L. S
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
L.S
Man-Day
L.S
Man-Day
L.S
Quantity
2
1
6
1.5
-
1.5
5
-
4
6
50
-
2
3
25
-
4.5
-
2.4
-
Remarks
Standard Dafa for Working Out Rates Per Unit Quantity of Items of Work-contd.
r
Particulars of Materials and Labour Unit Quantity
Remarks
0.
(c) Shifting the sleepers within 30m with man
and arranging them Systemtically (not more
than one time. ) (100 Nos)
Carpenter Man-Day 4
Sundries L.S -
(d) Fixing the railway on the sleeper firmly on
the Top Chord of Installed steel truss.
- fixing with the required G.Bolt, U.Bolt along
the rail length for UIS & DIS. (10 m)
Steel Fixer Man-Day 2
Carpenter Man-Day 2
Head Worker Man-Day 1
Worker Man-Day 9
Operator /Machine Driver Man-Day 1
Electric Helper Man-Day 0.5
Sundries L.S -
(e) Fixing the railway on the the sleeper firmly
on the strainger of installed steel truss.
- fixing with the J.Bolt or Dog Spike for Up
Stream and Down Stream.
(10 m)
Steel Fixer Man-Day 1
Carpenter Man-Day 1
Head Worker Man-Day 1
Worker
Man-Day 4.5
Sundries L.S -
(f) Dismantling the railway (50 % of fixing)
95. Installing Erection Tower, Mast Crane & Multi-
purpose Crane on the Top Chord of the Steel
Truss. (1000 kg)
(a) With universal member
Steel Fixer Man-Day 5
Head Worker Man-Day 2
Worker Man-Day 13
Sundries L.S -
27
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Standard Data for Working Out Rates Per Unit Quantiv of Items of Work-contd.
Quantity
0.5
1
1
1
-
20
20
10
100
20
20
-
4
8
2
7
7
7
-
5
9
2
Unit
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Sr
No.
99.
100.
Remarks
Particulars of Materials and Labour
Steel Fixer
Worker
Operator /Machine Driver
Electric Helper
Sundries
Shifting Erection Tower on the Top Chord fiom
one span to another with winch, Pretension the
Steel Cables Final tension with 500 MT Jack
and Checking Erection Tower. (1 Time)
Foreman
Steel Fixer
Head Worker
Worker
Operator /Machine Driver
Electric Helper
Sundries
While erecting steel truss fiom one Pier to
another for the required level, fixing with 100 M
Ton jack, 3001350 MTon jack,500 MTon jack,
on the bearing of the piers.
- After that, making jack up & Jackdown
- Shifting horizontally & longitudinally
- Other components Work
(a) 100 MTon Jack
(1 0 Nos per 1 Time)
Foreman
Steel Fixer
Head Worker
Worker
Operator /Machine Driver
Electric Helper
Sundries
(b) 3001350 MTon Jack
(1 0 Nos per 1 Time)
Foreman
Steel Fixer
Head Worker
29
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
101.
102.
(a)
(b)
(c)
103.
Particulars of Materials and Labour
Worker
Operator /Machine Driver
Electric Helper
Sundries
(c) 500 MTon Jack
(1 0 Nos per 1 Time)
Foreman
Steel Fixer
Head Worker
Worker
Operator /Machine Driver
Electric Helper
Sundries
Fixing of Bearing. (1 000 kg)
Steel Fixer
Head Worker
Worker
Sundries
Cutting steel plate to get required size (With gas)
12mm thk: (for 2500 mm)
Welder
Oxygen gas
Propane gas
16 mm to 20 rnm thk: (for 2500 rnrn)
Welder
Oxygen gas
Propane gas
25 mm to 30 rnrn thk: (for 2500mm)
Welder
Oxygen gas
Propane gas
Welding work. (one ply:)
(for 2500mm)
welding rod (5kglpkt)
Welder
Unit
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
L.S
Man-Day
kg
kg
Man-Day
kg
kg
Man-Day
kg
kg
Pkt
Man-Day
Quantity
8
8
8
-
6
11
3
8.5
10
10
-
2
2
9
-
1
4.5
1.5
1.5
5
1.5
2
6
1.5
0.2
1
Remarks
Standard Data for Working Out Rates Per Unit Quanlily of Items of Work-contd.
Remarks
Including Loading,
Unloadtig and shifting
Quantio
2.5
3.3
-
2
1.5
-
2
2
-
0.8
-
1
-
1
1
1
0.1
-
- Moving main cable coin
to cutting place by cran
- Cleaning main cable
- Levelling ground and
setting turn table for
cutting main cable with
wheel cutter & chain
block to get specified
length.
- Transferring cutted mai
cable
Unit
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L. S
Man-Day
Man-Day
L.S
Man-Day
L. S
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
L.S
;r
Jo.
04.
05.
06.
07.
,08.
109.
Particulars of Materials and Labour
Steel Plate Girder
Preassembling of steel plate girder according
to design on the ground. (1000 kg)
Skilled Worker
Worker
Sundries
Fixing , Initial & final tightenning of bolt &
nuts and drip pins according to the design while
assembling steel plate girder .(I000 Nos)
Skilled Worker
Worker
Sundries
Installation of preassembled steel plate girder
by crane as per drawing from pier to pier.
(1 000 kg)
Skilled Worker
Worker
Sundries
Checking to final tightenned bolt nuts with
checking spanner whether standard or not.
(1 000 Nos)
Skilled Worker
Sundries
Placing bearing plate and fixing bolt & nut.
Skilled Worker
Sundries
Suspension and Cablestayed Bridge
Cutting and cleaning main cable (For 10 m)
Skilled Man
Head Worker
Worker
Machine Driver / Operator
Sundries
3 I
Standard Data for Working Out Rates Per Unit Quantity ofllems of Work-confd.
Sr
No.
11 0.
1 1 1.
112.
1 13.
114.
Particulars of Materials and Labour
Taking out and cleaning running cable from
Cable Drum and placing them on timber crib
(For 10 m)
Skilled Man
Head Worker
Worker
Sundries
Fixing running cable on Winch Drum at
Up stream and Down stream (For one winch)
Skilled Man
Head Worker
Sundries
Taking out and cleaning Pilot Cable from Cable
Drum and placing them on
timber Crib (For 10 m)
Skilled Man
Head Worker
Worker
Sundries
Fixing step by step steel wire rope Pilot Cable
on each side of Anchor on high Level.
(For lm)
Skilled Man
Head Worker
Worker
Sundries
Fixing Travelling Cage by safety belt on high
level of Tower with Pulley Travelly.
(For 1 Cage)
Skilled Man
Helper for Skilled Man
Head Worker
Electrician
Sundries
Unit
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
L. S
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Quantity
0.1
0.1
0.1
-
3
4.5
-
0.3
0.2
0.4
-
0.3
0.2
0.1
-
13.5
7.5
1.5
0.8
-
Remarks
- Including installation of
lock, Bull Dog Grip
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-confd.
Alignment (For one winch)
Skilled Man
Helper for Skilled Man
Sundries
3r
Particulars of Materials and Labour
qo.
15. Fixing 5 Mton winch According Tower Anchor
Fixing Supporting Frame Anchor Plate system-
tically according cable alignment behind
Anchorage. (For 1 Anchor Supporting Frame)
Skilled Man
Welder
Worker
Sundries
After installation main cable, dismantling
and cutting supporting Anchor Frame, extra
Anchor Plate ( For 1 Anchor Supporting
Unit
Frame.)
Quantit
Skilled Man
Welder
Worker
Sundries
Man-Day
Man-Day
L.S
3
4.5
-
Man-Day
Man-Day
Man-Day
L.S
3
1.5
6
-
Man-Day
Man-Day
Man-Day
Welder
Operator of welding M/C
Worker
Sundries
1
0.5
1.8
11 8. Fixing roller by welding on high level of Tower
with safety belt. (For 1 No)
Skilled Man
1 19. Making for Cable clamp systemmatically and
making hole for Bolt & Nut For Tower Tilting
work. (For Cable clamp 1 set)
Welder
Helper For Welder
Sundries
Man-Day
Man-Day
Man-Day
L.S
0.5
Man-Day
Man-Day
Man-Day
L.S
120. Fixing firmly Over lapping at least 5MTon Chain
0.3
1.3
1.8
-
I block, Steel Wire rope with Bull Dog Grip at
Remarks
- - ~
Including timber support
and wedging according
inline of Anchor slab
Including temporary
welding work
33
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Particulars of Materials and Labour
nall Anchor For Tower Tilting.(For small
achor (Dead men) 1 No)
Skilled Man
Sundries
king Over Lapping and chainging way of chain
)r 10 MTon Chain Block at 10 MTon pulley
tee1 Wire with Bull Dog Grip at Anchor Canopy
or Tower Tilting.
:or Anchor 1 Point)
Skilled Man
Worker
Sundries
urning back Tower According specific
besign For TowerTiting.
For One Tower (2)Nos)
Skilled Man
Worker
Sundries
'ransfering cable from stockyard to Anchorage
by men and placing one on another (8)shape
In timber crib. (For 10 m)
Skilled Man
Head Worker
Sundries
nstallation of Main Cable for Bridge (For1 Om)
Skilled Man
Head Worker
Electrician
Mechanic
Welder
Sundries
Unit
tan-Day
Ian-Day
L.S
tan-Day
Ian-Day
L.S
Remarks
Inserting Main Cable to
Anchor Plate
a Putting on place upon
temporary rope
. holding upon Main Cab1
at saddle at each Tower
with B.D Grip by safety
belt and layer with Filler
stand
. Transfering cable from
one Tower to another
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Head Worker
Electrician
Sundries
Head Worker
Worker
Sundries
Remarks
- Taking out cable from
Anchor Plate of Ancho-
rage
- Checking Cable of Back
stay between Tower and
Anchorage
- Numbering cable by
layer and layer
- Installation of Main
Cable on high level over
water by life jacket and
safety belt
- Joining heavy Cable
lamp to
Travelly by pulley and
chain block
- Specified cable marking
on main cable
- Doing difficulty on high
level of Main Cable
- Fixing Suspender Rod
on main cable with Hing
shaft and safety pin
- Transfering suspender
rod to working area
by Manpower
Quantity
14
3
4
-
0.3
0.1
-
0.4
-
7
2
0.5
-
Unit
Man-Day
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-Day
L.S
Man-Day
Man-Day
Man-Day
L.S
Sr
No.
125.
(a)
(b)
(c)
126.
(a)
Particulars of Materials and Labour
Installation of Cable Top Clamp.
(For Cable Clamp 1 set)
Skilled Man
Tightening Bolt & Nut for one time
(For 10 Nos of Bolt)
Skilled Man
Electrician
Sundries
Painting Enamel paint for cable Top Clamp on
high level (For 1 no of Top Clamp)
Skilled Man
Sundries
Installation Suspender Rod
(For Suspender Rod 1 No)
Skilled Man
35
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Skilled Man
Mechanic for Grout pump
Electrician
Head Worker
Sundries
Remarks Quantity
0.1
0.1
-
0.1
0.1
-
0.2
0.1
-
1
0.1
-
3.5
0.5
0.5
5
-
0.5
-
Unit
Man-Day
Man-Day
L. S
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-Day
Man-Day
Man-Day
Man-Day
L.S
Man-Day
L.S
Sr
No.
(b)
(c)
127.
128.
129.
130.
Particulars of Materials and Labour
Threading Suspender U bolt ,painting grease,
Checking Bolt & Nut washer and Specifing
U Bolt marking
Skilled Man
Head Worker
Sundries
Painting Enamel paint for Suspender rod by
safety belt on high level
Skilled Man
Head Worker
Sundries
Adjusting Back stayed (for 1 Om)
Skilled Man
Head Worker
Sundries
Stressing Main Cable and Specifing Elongation
within Anchor according specified tension.
(For 1 Om)
Skilled Man
Head Worker
Sundries
Grouting Cement motor for Cable Guide Tube
within Anchor after stressing Main cable.
(For 1 Om)
Releasing binding cable Working length position
of Main Cable For Enclosing Blockafter
stressing.
( For 1 No of cable )
Skilled Man
Sundries
36
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Skilled Man
Sundries
Sr
No.
13 1.
132.
133.
134.
135.
1 36.
137.
Particulars of Materials and Labour
Adjusting and cutting layer of cable to
install Anchor Plate For Stressing.
(For 1 No of cable)
Shifting bailey (or) Steel truss on ground for
PreAssembling work. (For 1000 Kg)
Skilled Man
Head Worker
Sundries
Preassembling work for bailey (or) steel truss.
(For 1000 Kg)
Skilled Man
Head Worker
Sundries
Shifting heavy bailey (or) Steel Truss from
Preassembled Yard to join cable car by Crane
(For 1000 Kg)
Skilled Man
Head Worker
Sundries
Fixing preassembled bailey (or)Steel Truss on
Suspender Rod of Main Cable.
(For 1000 Kg)
Skilled Man
Head Worker
Sundries
Fixing Safety Net (For 1 m)
Skilled Man
Sundries
Removing safety Net (For 1 m)
Skilled Man
Sundries
Unit
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L. S
Man-Day
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-Day
L.S
Man-Day
L.S
Quantity
0.1
-
1.5
1.5
-
5
0.5
-
0.8
1
-
7.5
10
-
0.5
-
0.2
-
Remarks
37
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
138.
139.
140.
14 1.
142.
143.
144.
Particulars of Materials and Labour
Laying systematically small Transon walk way
and Checking, Laying Decking Beam
(For 1 000 Kg)
Skilled Man
Sundries
Canying Decking Beam and small Transon
difficulty by man power on temporary walkway
at high level of main bridge. (For 1000 Kg)
Skilled Man
Sundries
Putting heavy Decking slab on main bridge
by crane (For 1000 Kg)
Skilled Man
Head Worker
Sundries
Adjusting bailey (or)Steel truss of main bridge
to get specified camber by wing temporary
cable and Cushion Block. (For Suspender
Hanger 1 Point)
Skilled Man
Sundries
Jacking Down bailey (or)Steel truss with right
alignment to get final R.L by using 30 MTon
Jack Cushion Block and M.S Plate.(For one Pier)
Skilled Man
Sundries
Fixing Bearing Bolt to Bearing Mat and Bailey
(or)Steel truss Pin to Bearing Mat & Bailey
(or)Steel truss. (For one Pier)
Skilled Man
Sundries
Pouring High Strength Concrete to get required
Bearing Level (For 1 Bearing)
Skilled Man
Unit
Man-Day
L.S
Man-Day
L.S
Man-Day
Man-Day
L.S
Man-Day
L. S
Man-Day
L.S
Man-Day
L. S
Man-Day
Quantity
9.5
-
2
-
0.8
1.3
-
3.5
-
13.5
-
12
-
5
Remarks
- Include adjusting bottom
surface of Bearing Mat
to get specified R.L.
- Including cushion.
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
39
Standard Datafor Working Out Rates Per Unit Quantity of Items of Work-contd.
Quantity
0.5
0.5
0.5
0.5
0.5
0.5
0.3
1
1
1
1
1
0.5
0.5
Unit
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Sr
No.
152.
153.
154.
155.
156.
157.
158.
Remarks
Particulars of Materials and Labour
Reading and specifying the centre of the Bored
pile when driving stand pipe from control point
by using theodolite.(l Time)
Surveyor
Helper
Surveying and specifying concrete top level to
pour bored concrete.(l Time)
Surveyor
Helper
Checking Bored Pile position after pouring
concrete. (1 Time)
Surveyor
Helper
Surveying and Checking Bored Pile after pouring
concrete to know stable or unstable. (1 Time)
Surveyor
Helper
Surveying and specifying Cap position of
Abutment or Pier.(l Time)
Surveyor
Surveying and Checking settlement of pier cap in
water. (1 Time)
Surveyor
Surveying and specifying Shaft position of Abutment
159.
160.
or Pier.(l Time)
Surveyor
Surveying and specifling Bearing position of
Abutment or Pier. (1 Time)
Surveyor
Specifling and Checking Level to fix M.S Rod in
Pile Cap, Shaft , Cross-beam. (1 Time)
Surveyor
Helper
Man-Day
Man-Day
Man-Day
Man-Day
Standard Data for Working Out Rates Per Unit Quantity ofltems of Work-contd.
Particulars of Materials and Labour
Levelling Cap (or) Shaft (or) Cross Beam in their
form works before pouring concrete. (1 Time)
Surveyor
Helper
Helper
162. Rechecking position of Pile (or)Cap (or) Shaft (or)
Cross Beam after concreting. (1 Time)
Surveyor
before pouring concrete for one pier. (1 Time)
Surveyor
Helper
163.
Surveying , Checking and specifying centre of
Abutment (or) pier systematically. (1 Time)
Surveyor
Helper
Surveying bearing hole depth to get right depth
Surveying and Checking bottom ground of Pier in
water. (1 Time)
Surveyor
Helper
Transfering and rechecking level Mark for specifiec
place from one bench Mark to another.(100 m)
Surveyor
I
Helper
Unit Quantity
4
Man-Day
Man-Day
I
0.3
1
Man-Day
Surveying Echo Sounding Pier in water and water
level daily. (1 Time)
Surveyor
0.5
Man-Day 0.5
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
0.5
0.5
0.3
0.5
0.3
0.3
Man-Day
Remarks
0.5
Fixing bearing for one pier of main bridge (or)
1
Approach bridge (Position or Grouting to fix bearing
hole position Bearing.) (1 Time)
Surveying Position
Surveyor
Helper
Man-Daj
Man-Daj
41
Standard Data for Working Out Rates Per Unit Quantity of Items of Work-contd.
Quantity
3
3
0.5
0.5
0.5
0.5
0.3
1
0.3
1
0.3
1
0.5
0.5
0.5
0.5
Unit
Man-Day
Man-Day
Sr
No.
(b)
169.
Remarks
Particulars of Materials and Labour
Rechecking position.
Surveyor
Helper
Fixing bearing for one pier of main bridge (or)
(a)
(b)
170.
171.
(a)
(b)
172.
173.
Approach bridge(Position or Grouting to fix bearing
hole position Bearing.) (1 Time)
Levelling
Surveyor
Helper
Rechecking level
Surveyor
Helper
Surveying and Rechecking 18m(or)2 1 m(or)24m(or)
27m(or)30m Girder for pouring concrete. (1 No)
Surveyor
Helper
Surveying for erection of main truss to get specified
level. (1 Time)
Surveyor
Helper
Surveying , Leveling and checking for erection of
main truss to get specified level. (1 Time)
Surveyor
Helper
Surveying and Checking Level for Laying Precast
slab and finished level. (1 Time)
Surveyor
Helper
Surveying and specifjing Center line for installation
of Road Curb and Hand Rail. (1 Time)
Surveyor
Helper
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Standard Data for Working Out Rates Per Unit Quantity ofItems of Work-contd.
Road Curb and Hand Rail. (1 Time)
Surveyor
Sr
No.
174.
Helper
Particulars of Materials and Labour
Surveying and specifLing level for installation of
Man-Day
Man-Day
Remarks Unit
0.5
0.5
175.
176.
177.
178.
(a)
@)
179.
(a)
Quantitj
0.5
0.5
0.3
1
0.3
1
0.5
0.5
0.5
0.5
0.5
0.5
Surveying and specifling level for laying AC.(l Time)
Surveyor
Helper
Surveying Overlay, Road Curb, Hand Rail and AC
to get right alignment. (1 Time)
Surveyor
Helper
Surveying Precast Slab, Overlay, Road Curb,
Hand Rail level. (1 Time)
Surveyor
Helper
Surveying position of anywork before starting work
(Excavation or Fixing Reinforcement and forrnwork
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
or Pouring concrete or embedded plate or Hand Rail
or Road Curb or P.C Girder or Collosion Barrier or
Decking slab or Girder Overlay or AC or Anchor
Box or Bored Pile or Stand Pipe or Keyline or Cap
Skirting or Road or Drain or Box Culvert or Steel
Truss or Pier Cap or shaft Cross-beam or Abutment
or Retaining Wall or Rail Road or Vertical devia -
tion.) (1 Time)
Surveyor
Helper
Man-Day
Man-Day
Rechecking position of anywork after working.(l Time)
Surveyor
Helper
Man-Day
Man-Day
Surveying alignment (Center Line)of anywork before
working. (1 Time)
Surveyor
Helper
Man-Day
Man-Day
43
Srandard Data for Working Out Rates Per Unit Quantity ofltems of Work-contd
Quantity
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.5
0.3
0.5
0.3
0.5
0.5
0.5
1.5
2
4
Unit
Sr
No.
Remarks
Particulars of Materials and Labour
(b)
180.
(a)
(b)
18 1.
182
(a)
(b)
(c)
183.
184.
Rechecking alignment (Center Line)of anywork after
working. (1 Time)
Surveyor
Helper
Surveying and levelling anywork before working.
(1 Time)
Surveyor
Helper
Man-Day
Man-Day
Man-Day
Man-Day
Rechecking level of anywork before working.(l Time)
Surveyor
Helper
Surveying and checking settlement (Main Bridge or
Approach Bridge or Highway or Railway.)(l Time)
Surveyor
Helper
Man-Day
Man-Day
Man-Day
Man-Day
Checking for theodolite level and E.D.M instrument
which are used for surveying in bridge construction.
Theodolite Calibration. (1 Time)
Surveyor
Helper
Level Calibration. (1 Time)
Surveyor
Helper
E.D.M Calibration. (1 Time)
Surveyor
Helper
Determination of Pier Position by E.D.M including
finding distance between piers etc; other relevant
or equivalent works.(l Time)
Surveyor
Helper
Level Net Survey Calculation & Drawing.(l Time)
Surveyor
Helper
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
44
Standard Datafor Working Out Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
185.
(a)
(b)
(c)
Particulars of Materials and Labour
Triangulation Net Survey
Basic Line Measurement (1 Time)
Surveyor
Helper
Calculation & Drawing.(l Time)
Surveyor
Helper
Check Base & Distance Measurement(1 Time)
Surveyor
Helper
Unit
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Man-Day
Quantity
3
4.5
2
4
0.5
0.5
Remarks
45
Standard Data for Working Oui Rates Per Unit Quantity of Items of Work-contd.
Sr
No.
1
2
Particulars of Materials and Labour
MISCELLANEOUS NOTES
For contractor's profit and overheads
(Taxes , safety charges , management & etc.)
For Bridge Machinery Work
(Use according to rate of analysis of Machanical
Department.)
Unit
L.S
L. S
Quantity
-
-
Remarks

You might also like