You are on page 1of 25

KI NGDOM DRI LLI NG SERVI CES LTD.

Platform rig design Platform rig design, ,


Daisy field development, ABC Oil Daisy field development, ABC Oil
Design Requirements
Lifting capacity of draw works.
Derrick load capacity
Substructure and setback load
BOP sizes and ratings
Drillstring capacities
Mud pump output and pressure / power ratings
Mud pit capacity
Solids treatment and mixing equipment.
Limitations:
The rig must be able to handle the heaviest casing string required during the field life with
a safety margin.
The derrick must be able to hole the entire drillstring required to drill to TD and still be able
to run the heaviest casing string.
Msc Drilling Engineering
2
Summar y
Lifting capacity of draw works : Calculations enclosed illustrate that a 3000Hp draw works working at
85% mechanical efficiency will provide sufficient lifting capacity to take an over pull of 150,000lbs on the
heaviest stuck casing or drillstring. In this case the heaviest string is the 9 5/8 casing. (see figures
enclosed.)
Derrick load capacity to accommodate a dynamic derrick load in excess of 825,750lbs
Substructure and setback load in excess of 1,000,000lbs
BOP sizes and ratings : 18 5000 BOPs, 3000psi annulars. Annular, Blind/shear ram, two sets of
pipe rams. (choke and kill lines located below shear rams.)
Drillstring capacities (critical design sections are 12 and 8 @ sections)
Drillstring summary for 12 section
Component Connection Length Cum length Air wt (lbs) Buoyed wt
(lbs)
Cum buoyed
wt (lbs)
Overpull
(pa-Cum Bw)
Drill collars 8 x 2 13/16
6 5/8 reg
120m 120m 59K 49K 49K -
HWDP
5 x 3
NC-50
200m 320m 35K 29K 78K -
Drill pipe 1 19.50 G
NC-50
6000ft
(1828m)
2148m 131K 109K 187K 166K
Drill pipe 2
19.50 S
NC-50
2795ft
(852m)
3000m 61K 51K 238K 217K
Drillst ring summary for 8 sect ion.
Component Connection Length Cum length Air wt (lbs) Buoyed wt
(lbs)
Cum buoyed
wt (lbs)
Overpull
(pa-Cum Bw)
Drill collars 6 x 2 13/16
4 IF
120m 120m 30K 25K 25K -
HWDP
5 x 3
NC-50
200m 320m 35K 29K 54K -
Drill pipe 1 19.50 G
NC-50
6000ft
(1828m)
2148m 131K 109K 163K 190K
Drill pipe 2
19.50 S
NC-50
7060ft
(2152m)
4300m 159K 132K 295K 160K
Note: BHA components can be reduced in horizontal section, see appendix 4
3
Summary (continued.)
Mud pump output and pressure / power ratings. Mud pumps rates to 4500psi, providing 3000hp
(i.e. sufficient to drill at 4350psi @ 950GPM at 12 section TD, at 85% mechanical efficiency and
95% volumetric efficiency.) See summaries in appendix 3.
Mud pit capacity : Minimum of 3000bls required. This however is unlikely to be accommodated on a
platform rig design due to loading conditions. (Note: In reality, Platform design may only allow approx.
2000bbls that add constraints to many operational aspects.)
Solids treatment and mixing equipment.
Shale shakers to handle circulation volumes 1100-1200GPM, with redundancy for one shakers to be
taken out of service using as fine as screens as possible maintaining high solids removal efficiency.
E.g. High capacity , fine screen shale shakers such as thule VSM 100s)
Built in scalping screen, quick change screen facility, easy to operate and maintin, repairable screens.
Efficient centrifuges to remove fine solids generated during drilling.
Shallow header tanks entry to shakers and proper flowline division to ensure flow can be equally
controlled and divided to each shakers as required.
Poor boy de-gasser to be fitted with minimum 8 vent line.
Vacuum de-gasser to be able to handle max. operating rate of charge pumps i.e. 1200GPM.
Gumbo box fitted to flowline.
Flowline access platform for fitting and maintaining flow shows, gas detectors etc.
2 weco flushing connections fitted at strategic points for flowline cleaning.
References:
Homco technical handbook.
Ds-1 ( Terrance Hill & associates.)
Drillstring desgin notes, Msc notes and Shell training notes.
Halliburton red-book.
KI NGDOM DRI LLI NG SERVI CES LTD.
Plat form rig design
Desi gn assumpt i ons
Well dat a.
The well data provided represents the TWFH-13 well that is currently under planning. This well is the
most demanding well to be drilled from the Daisy field platform. TWFH-13 Well data will hence be used
for the platform design criteria.
Pl at form dat a Dept hs (m) Comment s
Top reservoir 1900m TVD BDF Reservoir pressure
Air Gap 50m
Water depth @ Daisy Field 150m BDF to Seabed = 200m
16 slot platform
No shallow gas present
Pressure regime is normal 1950m TVD BDF Normal pore pressure assumed = 8.33ppg
Casi ng Scheme Dept hs (m) Comment s
30 conductor 300m TVD BDF
20 surface casing 800m TVD BDF
900m TVD BDF
Maximum anticipated angle 27degrees
13 3/8 intermediate csg. 1400m TVD BDF
1650M AHD BDF
Maximum anticipated angle 32degrees
Note: Required to isolate long Salt section.
9 5/8 intermediate casing 1900m TVD BDF
3000m AHD BDF
Tangent and build section to almost horizontal.
Shale stability required, >mud weight of 0.5ppg
per 30deg required for wellbore stability.
7 production liner 1950m TVD BDF
4300m AHD BDF
Set 150m inside 9 5/8 casing
Mud weight to represent minimum safe
overbalance to limit formation damage.
Pressure regime is normal Normal pore pressure assumed = 8.33ppg
Reservoir pressure Reservoir pressure assumed to be 1.5ppg
above normal i.e. 9.83ppg.
2
Desi gn Not es
26 section drilled with seawater and displaced to 1.2sg mud prior to running casing
17 section, mud weight to reflect 300psi working overbalance and 0.53ppg for 32 degrees hole
angle. (10.12pg)
9 5/8 section, mud weight to reflect 300psi working overbalance and 1.5ppg for hole angle (10.8ppg)
7 section mud weight to reflect 300psi working overbalance over reservoir pressure (10.73ppg)
Desi gn Fact ors
Tension design 1.33
Tension calculations assume that the drillstring is hanging vertically. For high angle wells this would be
accounted for in design as too conservative, hence a higher design factor has been used.
In reality in high angle wells, each section should be considered at an average hole angle.
Drag is also not accounted for in design calculations. In reality torque and drag simulations would have
to be conducted modeling field data friction factors known etc.
Collapse design factor: 1.15
Burst design factor: 1.15, 1.25 for 13 3/8 section due to requirement for salt section isolation.
BHA design factor: 1.1
Margin of overpull, 120,000lbs drillstring
Margin of overpull, 150,000lbs casing.
The operator would like to trip with a minimum speed of 90ft/min at highest loading conditions.
Draw works Wire rope safety factors, minimum of 2.0 for drilling / casing.
Maximum operating torque = 25,000ftlbs (safe working value for top drive system e.g. TDS-2.)
Solids Control : Enough shakers to have one redundant at required section flowrate.
System to be designed such that shakers and centrifuges provide required solids control efficiency.
KI NGDOM DRI LLI NG SERVI CES LTD.
Prel i mi nary desi gn cal cul at i ons.
1.) Pressures and mud weights.
Pore pressure Normal 8.33ppg
Max mud weight 17
section
32degrees angle
300psi safe overbalance
shale stability required.
8.33 + (300/1400*3.281)/0.052 + (0.5*(32/30)) = 10.12ppg
Max mud weight 12
section
32-90degrees max.
300psi safe overbalance
shale stability required
0.5ppg/30degrees
8.66 + (300/1900*3.281)/0.052 + (0.5*(90/30)) = 10.8ppg
Reservoir pressure 1.5ppg above normal 9.83ppg
Max mud weight 8
section
Max 90degrees
300psi safe overbalance
10.2 + (300/1950*3.281)/0.052 = 10.73ppg
Ref: see wellbore stratigraphy in appendix 1.
2.) Burst : No pressure tests to be conducted before cementing, burst loads not
considered.
3.) Max collapse pressures. (Design factor 1.15, & 1.25)
Note: Worst case (total evacuation) has been used in collapse for platform design i.e. heaviest casing
strings. In reality based on platform experience, lost circulation aspects etc, total evacuation not likely to
be used in design.
Collapse 17 section
For 13 3/8 casing
0.052 x 10.12ppg x (1400m x 3.281) x1.25 = 3021psi
1.25 design used due to isolating salt section.
Collapse 12 section
For 9 5/8 casing
0.052 x 10.8ppg x (1900m x 3.281) x1.15 = 4026psi
Collapse 8 section
For 7 liner
0.052 x 10.73ppg x (1950m x 3.281) x1.15 = 4105psi
4.) Design pressures.
Max anticipated surface
pressure
= TVD * ( Formation pressure gas gradient)
= (1950m * 3.281) * ( 9.83ppg 2ppg) * 0.052)) = 2272psi.
Maximum bottom hole
pressure
= TVD * ( Formation pressure)
= (1950m * 3.281) * ( 9.83ppg * 0.052)) = 3270psi.
Water Injection pressure = 300bar (4335psi).
Note: Surface equipment, BOP equipment, casing and drillstring component requirements would be
based upon likely maximum injection pressure into the reservoir of 4335psi. This may have to executed
2
during some operational stages in the life of a well via drilling equipment Bops etc. ( e.g. Injectivity test,
well stimulation etc.)
5000psi equipment would therefore be chosen and selected if it can fulfill other
requirements. I.e Drilling (Pumping /pressure) requirements.
Choke manifold. SWP of 5000psi valves before chokes. SWP of 3000psi valves downstream
of chokes. (one remote and one manual choke.)
Standpipe manifold. : SWP of 5000psi for all valves, lines and fitments.
BOPs : SWP : 3000psi annular, SWP : 5000psi rams, kill and choke line valves, HCR valve
fitted as first outlet v/v on choke line.
Rams : Solid ram block consisting of Pipe ram, Shear ram, and two pipe rams . Kill and choke
lines fitted below shear rams. Rams fitted with variables from 3 to 5 and 4 to 7.
IBOP eqpt. : All kellycocks, IBOPs , Grey valves etc rated to SWP of 5000psi.
KI NGDOM DRI LLI NG SERVI CES LTD.
Casi ng sel ect i on
Casing select ion
Casing was selected for burst and collapse criteria based on maximum anticipated
pressures given on the previous pages. Note: A premium gas tight connection would have
to be chosen for the 9 5/8 casing and 7 liner e.g. Vam
Size Grade Lbs/ft Yield
strength
(psi)
Burst
(psi)
Collapse
(psi)
Body strength
(Klbs)
13 3/8 P110 72 80,000 7400 2880 2596
13 3/8 N80 77* 80,000 6390 3170 1773
*Heavier casing may be required over salt section.
9 5/8 N80 47 80,000 6870 4750 1086
7 N80 29 80,000 8160 7020 676
Casing weight s
Based on casing weight above, the highest casing load would be running the 9 5/8
casing. Note: All tension calculations assume that the casing is hanging vertically and in
air. For high angle wells, this would be accounted as too conservative in design. A design
factor of 1.2 has been for hole angle and wellbore profile to be taken into account. In this
design, a value of 150,000lbs over-pull has also been used to account for casing being
stuck prior to landing at TD.
Size Grade Lbs/ft Length
(m)
Dry Weight
(klbs)
30 * X-56 310 300 305K
X-52 133 900 393K
13 3/8 P110 72 1300 307K
N80 77 350 88K
9 5/8 N80 47 3000 463K
7 N80
G&S
29
21.8
1450
2850
138K
203K
7 ** N80 29 4300 409K
* Assuming all ran at once.
** Contingency string if required to run to surface, e.g. if leak in 9 5/8 string.
KI NGDOM DRI LLI NG SERVI CES LTD.
Dri l l i ng Tubul ars sel ect i on
Drill collar and HWDP select ion
The critical BHA for design is in the 12 section. Here higher WOB will be required to
drill anticipated formations during tangent and build sections. Build section would incur
highest combine loads and worst case stress conditions.
It is envisaged that worst case conditions, i.e max WOB, likely buckling conditions would
exists at start of section (i.e 32degrees).
Drill collar and BHA requirement s.
Drill collar, BHA, and drillstring component lengths have been determined as follows:
Length of Drill collars + BHA components required to drill with max 45000lbs WOB in 12
@ section.
Based on the above 12 drill collars would be required in addition to other BHA
components, e.g. mud motor, MWD collar, stabilisers etc. that would make up the
additional length required.
The operator prefers however in the directional sections of the well, to run a DS1, BHA
type 3. I.e. utilising HWDP for available WOB. This is to minimise BHA handling time,
reduce stuck pipe likeliness, and run drill collars required for directional control and BHA
design.
) 142 (
465
32 83 . 0 151
1 . 1 000 , 45
m
ft
Cos
Cos Kb Wdc
Df Wob
=

3
( )
( )
[ ]
.) 21 ( 642
7 . 53
1
270 , 58 771 , 92
7 . 53
1
148 281 . 3 120
60 cos 83 . 0
1 . 1 35000
) (
1
cos
jts ft
m
hwdp W
Wdc Ldc
Kb
Df Wob
=
=

HWDP required.
Based on a drill collar and BHA component length of 120m, the following calculation determines the
amount of HWDP required for 35,000WOB (Upper limit of 12 PDC), at an angle of 60degrees (i.e.
where cos. = 0.5). Note: A t higher angles BHA has a diminishing effect for WOB requirements.
If buckling was the limiting factor appendix 4 illustrates that at 60degrees, drill-pipe could also be used
to apply WOB up to 53,000lbs before buckling would occur. (available weight from BHA components is
only 31,000lbs at 60degrees inclination.)
Init ial t ubular select ion
Size Grade Lbs/ft
*
Yield
strength
(psi)
Burst
(psi)
Collapse
(psi)
Body strength
(Klbs)
5 S 22.5 135,000 15,640 10,050 560,764
5 G 21.8 105.000 12,090 8,765 436,150
5HWDP -- 53.7 -- -- -- 691,185
HWDP dimensions: 5 OD x 3 ID
*Adjusted weights.
Burst, collapse and body strengths given for premium pipe.
4
Drillst ring design
ABC oil companies require that drill strings have at least a quality of API inspection " Premium " grade
for the drill string and depth of well required and that drill string are inspected to a minimum DS1 class 4
standard.
Note : For a specification of the various API inspection classifications see API standard 7 : Rotary
Drilling Equipment or the recently released DS-1 Drill stem Design and Inspection specification.
Normal operating conditions
During normal drilling operations, the drillstring is subjected to constantly changing individual and
combined tension, torsion, bending, and pressure loads. During any drillstring design it is important to
note in the design and operating stag. In reality worst case individual and combined conditions and
make compensation for any assumptions used or as the case may be for conditions that may change
or not be accounted and/or applied for.
It is generally accepted that the most damaging combined loads occur under the following conditions:
During extreme drilling operations; Directional , horizontal ,
extended reach.
Rotating the drillstring under tension and/or torsion e.g. back
reaming with a top drive,
Stuck pipe e.g. jarring, overpull, combined tension, compression
and/or torsion.
Fishing operations e.g. jarring, overpull, combined tension,
compression and/or torsion.
Main design considerations.
The main design considerations on the drillstring to be accounted for are :
Tensional pulling and pushing ( compression ) on the drillstring,
Combined tension / torsion while twisting the drillstring during rotation.
The torsion while making up or braking out the drillstring components,
The bending derived from wellbore geometry, doglegs in the wellbore, or through
misalignment of the crown block,
Pressures created by surface and subsurface pressure, or different drilling fluids
inside and outside the drillstring.
Slip crushing and stability forces.
Shock loading on applying tension, compression or combined loads to the
drillstring components.
5
Notes :
1.) Von Mises triaxial equation, fatigue and jar placement considerations are not considered in design
2.) Due to the complexities involved vibrational analysis is not considered and accounted for in this
brief.
3.) Corrosion and erosion are not loads, but they both reduce the strength of tubulars. Accounting for a
measure of wall thickness (e.g. 80%) to account for anticipated erosion and corrosion is considered
acceptable in this case. e.g. A long extended reach well where drillpipe wear may be severe.
The fundamental approach to drill string design is to calculate the loads individually to determine if the
strength of the drill string is exceeded by each individual load. Then combine all loads in the Von Mises
general stress and fatigue endurance equations to ascertain if general or fatigue failure will occur. (see
appendix2)
Tension Design Factors.
The first considerations to be made regarding designing a drillstring for tension applied is to select a
maximum working load that would never be exceeded during normal drilling operations.
In the case of drillpipe this working load is based on a stress of 85% of the yield strength of the pipe, as
recommended in strength and dimensions tables provided.
The second consideration in tension string design is to determine the maximumallowable static load.
This is the hook load when the drillstring ( including the drill collars, BHA components, etc. ) are hanging
free in the wellbore and are equal to the string weight in air multiplied by the buoyancy factor for the
weight of the drilling fluid in use.
Three general methods are used to determine the Maximumallowable static load, they are
Design factor.
Margin of overpull.
Safety factor for slip crushing.
6
TWFH-13 drillstring design requirements :
1.) calculate the lengths of various 5" 19.50 lbs/ft G105 and S135 drillstrings for drilling the hole.
2.) Using maximum lengths of all drillstrings , what is the maximum depth obtainable.
3.) Design the strings to account for slip crushing, safety factor for accelerating loads.
Margin of over pull allowed = 120,000 lbs.
Depth of along hole depths required = 12 section 9843ft (3000m.), 8 section 14,108ft
(4300m)
Use maximum lengths for G and S.
Drill collars = 8" x 2.813" x 120m, 200m HWDP, 5 x 3
6 x 2.813 x 120m in 8 @ hole.
Mud in use = 10.8ppg.
From API section B3 page 3
= 5" 19.50 lbs/ft G = 553,833 lbs, minimum yield strength., S = 712,070 lbs
a.) "G" pipe Maximum allowable static load ( for acceleration forces )
= Min Ys x 0.85 = 553,833 x 0.85 "G"= 353,953 lbs.
S.F 1.33
Similarly "S" = 455,082 lbs
b.) Margin of overpull, maximum allowable static load.
"G" = (min Ys x 0.85)/1.33 - M.O.P = (553,833 x 0.85)/1.33 - 120,000
"G"= 233,953 lbs
Similarly "S" = 335,082lbs.
c ) Slip crushing. ( Assume normally lubricated slips, coefficient of friction = 0.08 )
from table provided :
16 slips, friction factor = 0.08
K = 4.00 ( for 5" drillpipe. )
Safety factor Sh/St = 1.42.
Maximum allowable static load = Min Ys x 0.85
1.42
"G"= 553,833 x 0.85 = 331,520 lbs.
1.42
Similarly "S" = 331,518 lbs.
7
For "G" pipe the max. allowable static load = 203,953 lbs.
( From the M.O.P. calculations, i.e.lowest loadings)
Maximum allowable depth of "G" pipe. =
Max allowable static load - ( Wdc x Ldc) + (Whwdp x Lhwdp)
Wdp * Kb Wdp Wdp
BHA = (2.67 ( 8 - 2.813 ) x 120m + ( 2.67( 5 - 3 ) x 200m) x 3.281 x 0.83 = 86,992lbs
Buoyancy factor ( Kb ) = 0.83
= 233,953 - 86,992 = 8939ft
21.80 x 0.83 21.80
Maximum length "G" and "S"
= max all static load "S" - ( Wbha x Lbha ) + ( Wdp1 x Ldp1)
Wdp2 x Kb Wdp2
= 335,082 - ( 86,992 ) + ( 21.80 x 9839ft)
22.50 x 0.83 22.50
= 4544ft.
Maximum depth G and S
= 8939ft + 4544ft = 13,483ft
12 section 3000m (9843ft) & 8 section TD 4300m (14,108ft) a combination of G and S would
be required. Maximum depth we can drill to with G & S pipe.
=13,483t + 120m (drill collars) + 200m HWDP = 14,532ft (TD of well is 4300m (14,108ft.)
For additional safety 6000ft of G will be run with the remainder S. Summary sheets and
spreadsheet calculations have been based on these figures.
A design spreadsheet was run (courtesy of Mitchell engineering) to ensure all design criteria are
met. ( See Appendix 2.)
8
St iffness rat ios
Drill collars to HWDP ( section modulus figures taken from DS-1.)
Drill collars 8 x 2 13/16, HWDP 5 x 3
SR = Z below / Z above
= 54.382 / 10.682 = 5.09
Drill collars 6 x 2 13/16, HWDP 5 x 3
SR = Z below / Z above
= 20.181 / 10.682 = 1.89
HWDP to G drillpipe ( section modulus figures taken from DS-1.)
HWDP 5 x 3, G pipe 5 x 4.276
SR = Z below / Z above
= 10.682 / 5.708 = 1.87
Stiffness ratios are within acceptable ranges
Torsional check (* values from DS-1)
Connection O.D. (in) I.D. (in) *Make up
torque (ftlbs)
*Torsional
strength (ftlbs)
Max operating
torque (ftlbs)
G NC-50 6 5/8 3 27,080 45,130 25,000
S NC-50 6 5/8 3 31,020 51,700 25,000
Torsional checks are within max operating torque allowable.
9
Drillst ring summary for 12 sect ion.
Cum length Air wt (lbs) Buoyed wt
(lbs)
Cum buoyed
wt (lbs)
Overpull
(pa-Cum Bw)
Drill collars 8 x 2 13/16
6 5/8 reg
120m 120m 59K 49K 49K -
HWDP
5 x 3
NC-50
200m 320m 35K 29K 78K -
Drill pipe 1 19.50 G
NC-50
6000ft
(1828m)
2148m 131K 109K 187K 166K
Drill pipe 2
19.50 S
NC-50
2795ft
(852m)
3000m 61K 51K 238K 217K
Pa = maximum allowable load for drillpipe from design calculation
Drillst ring summary for 8 sect ion.
Cum length Air wt (lbs) Buoyed wt
(lbs)
Cum buoyed
wt (lbs)
Overpull
(pa-Cum Bw)
Drill collars
6 x 2 13/16
4 IF
120m 120m 30K 25K 25K -
HWDP 5 x 3
NC-50
200m 320m 35K 29K 54K -
Drill pipe 1
19.50 G
NC-50
6000ft
(1828m)
2148m 131K 109K 163K 190K
Drill pipe 2 19.50 S
NC-50
7060ft
(2152m)
4300m 159K 132K 295K 160K
Pa = maximum allowable static load
Note: In reality as inclinations increase, less BHA components are required and more drillpipe can be
used for WOB before buckling will occur. (see appendix 4)
To permit drillstring to slide, HWDP may have to be placed in the build section, drags and buckling
would have to be determined using a torque and drag simulator.
KI NGDOM DRI LLI NG SERVI CES LTD.
Derri ck l oadi ng
Derrick loading worst case
1.) Worst case would be running heaviest casing string (95/8 casing 463K), getting stuck
at section TD and applying maximum overpull i.e. 150,000lbs.
2.) Assuming all 5 drillpipe has been picked up to drill to TD
Block weight + top drive and hoisting equipment = 80,000lbs.
No account taken for other equipment and fixtures in derrick. E.g. Pipe handling
system.
Pipe in derrick
5 drillpipe required for well 1828m x 21.8 lbs/ft x 3.281 130,749lbs
2152m x 22.50 x 3.281 158,866lbs
120m BHA (Dcs + BHA) 120m x 99lbs/ft x 3.281 58,270lbs
21 joints of HWDP 200m x 53.7lbs/ft x 3.281 35,238lbs
1.) Pipe weight in derrick 383,123lbs set back load.
Casing stuck 3000m x 47lbs/ft x 3.281 463,000lbs
Over pull applied Design for 150,000lbs 150,000lbs
Block and travelling eqpt. weight 80,000lbs 80,000lvs
2.) Stuck casing load on derrick 693,000lbs.
1.) + 2.) Worst case derrick loading 1,0761,123lbs
Dynamic derrick loading for worst case
Dynamic derrick load (12 lines run blocks)
Hook line load (Hl) = Casing wt +overpull + blocks etc 693,000lbs
Fast line load (Fl) = Hl / (No of lines (n) x eff factor)
693,000 / ( 12 x 0.77)
75,000lbs
Deadline load (Dl) = Hl / No of lines (n)
693,000 / 12
57,750lbs
3.) Dynamic derrick load = Hl + Dl + Fl = 825,750lbs
4.) Derrick load static = ((n) + 2 / (n) ) * Hl 808,500lbs
KI NGDOM DRI LLI NG SERVI CES LTD.
Blockline select ion
1 3/8 Extra improved plough steel block line has a breaking strength of 192,000lbs.
Safety factor on maximum fast line load (75,000lbs) from previous page.
Sf = (192,000lbs / 75,000lbs)
Safety factor = 2.56
This is an acceptable factor for drilling and/or casing operations.
KI NGDOM DRI LLI NG SERVI CES LTD.
Draworks requi rement s
The operator would like to trip with a minimum speed of 90ft/min at the highest loading
conditions.
Fast line speed = (n) x speed required ft/min
= 12 lines x 90ft/min = 1080 ft/min.
For a 60 drum ( 1.25ft radius = (r) )
Velocity of the fast line (Vf) = 2 x x r x N
1080 = 2 x 3.14 x 1.25 x N
N = 138 revs /min.
Horse power of the drum (HP) = ( Fl x 2 x x r x N ) / (33,0000)
Where 33,000 = ftlbs / rev/min / per HP.
HP = (75,000lbs x 2 x 3.14 x 1.25ft x 138revs/min) / (33,000)
Horse power of drum = 2462 HP.
HP of draw works (assuming mechanical efficiency of 85%) = 2462 / 0.85
Horse power of draworks = 2896 Hp.
A 3000hp draw works would therefore be most suited for the Daisy platform.
KI NGDOM DRI LLI NG SERVI CES LTD.
Mud pump out put and pressure rat i ngs
Hydraulics calculations for the two critical hole cleaning sections i.e. the 17 and 12
sections is provided in appendix 3.
Based on a maximum section depth operating pressure of 4350psi and 950GPM in the
12 section.
The horsepower required for the mud pumps, assuming a 95% volumetric and 0.85%
efficiency factors =
HHP = (P x V) / (1714 x 0.85 x0.95)
= (4350psi x 950GPM) / (1714 x 0.85 x0.95)
= 2986HHP.
2 x 1600Hp pumps would be required e.g. National 12-P-160
Three pumps would be preferred to provide operational redundancy if one pump requires
repair.
KI NGDOM DRI LLI NG SERVI CES LTD.
Mud pi t capaci t y
Mud pit capacit y
Largest volumes required are in the 17 section and would be displacing hole to
mud at section TD.
17 hole volume = (900 x 0.3415bbls/ft) + (0.2975bbls/ft x 750m) x 3.281 = 1740
bbls
based on a rule of thumb that reserve = active requirements.
A pit volume capacity in excess of 3000bbls would be required.
Sol i ds removal equi pment .
Requirement s.
Shale shakers to handle circulation volumes 1100-1200GPM in 17 hole section.
With redundancy for one shakers to be taken out of service using as fine as screens
as possible to maintain high solids removal efficiency. E.g. High capacity , fine screen
shale shakers. ( Thule VSM 100s)
Built in scalping screen, quick change screen facility, easy to operate and maintain,
repairable screens.
Efficient centrifuges to remove fine solids generated during drilling.
As WBM being used shakers designed not to be underloaded so as to effect
maximum operating performance.
Shallow header tanks entry to shakers and proper flowline division to ensure flow can
be equally controlled and divided to each shakers as required.
Poor boy de-gasser to be fitted with minimum 8 vent line.
Vacuum de-gasser to be able to handle max. operating rate of charge pumps i.e.
1200GPM.
Gumbo box fitted to flowline.
Flowline access platform for fitting and maintaining flowshows, gas detectors etc.
2 weco flushing connections fitted at strategic points for flowline cleaning
2
Mud mi xi ng & t reat ment equi pment .
Large diameter piping, with as direct feed and discharge as possible with minimum
bends to reduce pressure losses ( 6 or 8 pipe.) with minimum fluid velocity of
10ft/sec.
Centrifugal mix pumps 6 x 8. Desirable to mix and treat mud in large quantities in
the shortest possible time.
Hoppers : 6 x 8 Centrifugal, 1400-1600GPM, @ 50 70psi.
Shearing device for mixing polymers, (ABC Oil policy to use WBM exclusively for
wells.)
KI NGDOM DRI LLI NG SERVI CES LTD.
Appendi x 3

You might also like