You are on page 1of 81

MUNICIPAL CORPORATION OF

GREATER MUMBAI
BRIDGE DEPARTMENT









VOLUME-I
UNIFIED SCHEDULE OF RATES FOR
BRIDGE WORKS
2013


FOREWORD
Ever since it's establishment in 1888 by the erstwhile British rulers in India, in the last
125 years of the history of its existence Mumbai Municipal Corporation has catered
to every aspect of the citizen of Mumbai that can be conceived of. Think of Engineer
Victor Tulloch, who through his unparalleled immense efforts conceived the water
supply scheme fetching running over from distance of more than 100 km by
constructing a dam across river Tansa, to feed the population of Mumbai, then only a
few thousands in number. The items have changed with technological advancement
and the works like Roller Compacted Concrete Dam at Middle Vaitarna or numerous
underground tunnels for water supply and sewerage disposal, for example, have
become hallmark of MCGM's dedication to the citizen of Mumbai. The challenges
have always been daunting, nevertheless, always met with.
Every civilization be it 5000 years old Harrappan civilization on the bank of
Sindhu River, or Mumbai on the west coast of the Indian Ocean, require
infrastructure like water supply and sewerage system, storm water drainage system,
road, bridges, etc. and hospitals, markets, recreation centers etc. The exponentially
growing population of Mumbai and the technological explosion in the field of
engineering has made every aspect of contracting of works highly challenging.
M.C.G.M. is one of the largest local self government in the Asian Continent.
In observance of historic traditions of strong civic activism, with the change in time
and living conditions to match with the urbanization, M.C.G.M. has mainly focused in
providing variety of engineering services viz, storm water drain, sewerage, water
supply projects, roads, bridges, solid waste management, environmental services.
Beside this, the Corporation is also providing dedicated services in the Health sector
by establishing numbers of Major and Peripheral hospitals.
To update and modernize the mechanism being used for working on projects
from the stage of conceptualization upto execution, the need was realized to revise
prevailing Schedule of Rates along with specifications which were in operations
with various departments and being prepared individually as per their need and
used to revised at different span of time, resulting into various anomalies. Therefore,
to overcome all these, it was essential to revise the schedule of rates, not only with
simple mechanized revision, major changes to keep up with the pace of urbanization,
civilization, construction techniques / mechanization and voluminous developments
by restructuring items in the schedule as per requirements. This exercise would

provide comfort with field requirements and designs and will assist in effective
checks on creation of extra items during execution.
A conscious decision has been taken to keep pace with the changing time
and preparation of Unified Schedule of Rates is the first step forward in this direction.
Since long time, there have been demands made by the stake holders like Municipal
Engineers and Contractors about non-uniformity, anomalies and discrepancies in
various schedules of rates for work contracts of various departments of MCGM.
Every department had its own expertise and way of functioning which got reflected in
its independent schedule of rates, which, however, had no linkage with the fair
market schedules of other departments and resulting into extra items and fair rates.
In place of earlier 9 Schedule of Rates, the Unified Schedule of Rates is an effort &
seeks to rectify the defects, discrepancies and non uniformities which will provide,
not to mention about the ease and accuracy of estimation to the Engineers.
In view of the enormous and voluminous nature of work, keeping time
frame in perspective and above all, to ensure professionalism, the work of
preparation of Unified Schedule of Rates was awarded to the eminent consultants
M/s.Tata Consulting Engineers Ltd. M/s.Tata Consulting Engineers Ltd were directed
to conduct a thorough factual market research for major materials from
stockists/manufacturers/dealers and to study schedules of rates of Govt bodies like
C.P.W.D. and P.W.D. The new Rate Analysis are based on Factual Market research
done by M/s.Tata Consulting Engineers Ltd.
The anomalies in rate are minimized after extensive market research and
collection of quotations from reputed large scaled stockists/dealers, and also after
comparison with rates of CPWD, PWD etc.
The SOR is linked with its comprehensive specifications of basic important
activities so as to have clarity in execution. These specifications follow a chronology
of general scope of the item, material required, processing of material, construction
operation, finishing and mode of measurement.
All the rates are now linked to their detailed specifications and wherever
required, with drawings. Though there are about 12500 items, every item is now
given a Unique Code No. which will eliminate the repetition.
It has been our endeavour to include all the necessary modern materials and
technologies in SOR, for example, the concept of green building, which will go a long

way to have control on creation of extra items and fair rates. A salient feature of this
USR is 'Starring of items' specified, categorically which can be used only at certain
works or locations.
Another salient features is 'Dynamic Rate System' which will be based on
study of data base of quantities and bidding prices of awarded contracts on the basis
of which necessary corrections can be applied to the Unified Schedule of Rates at
specified intervals. The MCGM will be now in position to revise the Unified Schedule
of Rates every year after incumbency period of M/s.Tata Consulting Engineers Ltd of
one year, to work with and correct the system as and when necessary.
I hope this 'Unified Schedule of Rates' will be a milestone in civic governance
by MCGM. This self-contained publication shall be of great help and guidance to the
officers engaged in the project work of MCGM.


A.M.C. (Project) Municipal Commissioner

A. GENERAL NOTES
1. The schedule of rates will be operative from 16-09-2013
2. The unified schedule of rates includes following department:
i. Buildings
ii. Water Supply Projects
iii. Hydraulic Engineering
iv. Sewerage Projects
v. Storm Water Drainage
vi. Roads
vii. Bridges
viii. Traffic and Signals
ix. Mechanical and Electrical
x. Garden Works
3. Volume-I contains USR, basic rate list and approved makes and Volume-II
contains specification along with drawings wherever necessary and mandatory
tests.
4. The specification of the items shall be as per latest Indian Standard Codes
unless otherwise specified.
5. The rates of the items in this schedule of rates are worked out assuming average
lead for Greater Mumbai area for all sorts of materials.
6. The rates are inclusive of transportation, duties, taxes and charges of all
Government, Municipal or any other statutory body, applicable from time to time
but exclusive of Works Contract Tax and Labour Cess levied by Government of
Maharashtra.
7. The rates also includes Overheads @ 5% and Contractors Profit @10% which is
inclusive of labour supervision charges, tools and plants.
8. Rates of common material and labour is attached in the Annexure-A in Volume-I.
9. The building Schedule of Rates 2013 includes the existing items of FMA, FMB
2009, SIC and Fair items, with deletion of obsolete items, merger of similar items

and value addition of new items in line with modern technology and trends in
accordance with latest rules, regulation, byelaws etc.
10. As per the Government policy the use fly ash is done for framing the items of
work in accordance with the latest provisions of IS Codes. Also green building
items have been introduced in new schedule to minimize the consumption of
energy during construction and occupancy of building and also maintaining
ecological balance.
11. From safety, health and environment point of view two legged steel tubular
scaffolding shall be used, without making any holes in the outer face of the
building or any structure. And no extra payment shall be made for works like
scaffolding, centering for any height unless otherwise specified.
12. All materials shall be as per approved list of MCGM or equivalent material having
quality standards as per relevant IS codes and shall be of first quality unless
otherwise specified.
13. Following basic rates are considered in the USR:
i. Cement : Rs. 6,000/ MT
ii. Mild Steel : Rs. 47,400/ MT
iii. HYSD Steel (Fe415) : Rs. 48,400/ MT
iv. T.M.T. (Fe500) : Rs. 49,400/ MT
v. Structural Steel : Rs. 53,400/ MT
14. Rates given in SOR are for estimation purpose.
15. Rates of items and specification for excavation, concrete, plaster and brickwork
shall be referred from common schedule unless and otherwise not mentioned in
concerned departments schedule.
16. Coding of items:
The Coding procedure for Basic master material is as follows:
Code will start with the common prefix of MA which stands for materials
Followed by Abbreviation code for each schedule of rate for eg H.E. for
Building works, SP for Sewerage, WSP for water supply and so on and so
forth.
The first item category in the list will be numbered as 1
The last part of the code will be a number starting with a to indicate the item
number in the master list.
The alpha numerics will be separated by (dash).

The code will look like: MA-GN-01

The Coding procedure for SOR is as follows:

Code will start from abbreviation for Department name HE or WSP or SP
The USR will be subdivided into chapters according to the item classification;
these chapters will be numbered as 1, 2, 3 ..
The items under the chapter will be numbered from 1
The sub items will be numbered as a, b, c .
The code will look like CS-CW-1-a-1

Abbreviations to be used for Department
Sr. No. Department Abbreviation
1 Building works/Common
Schedule
CS
2 Roads RW
3 Traffic and Signalling RT
4 Bridges BW
5 Water Supply Projects WSP
6 Hydraulic Engg. HE
7 Sewerage Projects SP
8 Storm Water Drains SWD
9 Mechanical and electrical ME
10 Garden Works GW

B. SALIENT FEATURES OF SOR FOR BUILDING WORKS
1) All the rates are for all heights and levels unless noted otherwise.
2) Chloropyrifos EC 20 has been considered for anti termite treatment.
3) Artificial sand (crushed sand) has been considered for flooring bedding and for
concrete work.
4) All the items are excluding fixtures otherwise not specified in respective item. In such
case, items of Hardware section shall be used for fixtures.
5) For plastering and mortar work, river sand has been considered.
6) For plastering work all the rates are for all heights and levels and architectural
decorative surface.
7) All external plaster items are including waterproofing compound except plastering
item for structures like compound wall, masonary pedestals, pillars, etc.
8) Items for ashlar masonry, dewatering, self compacting concrete, vacuum dewatered
concrete flooring and TMT steel bars have been introduced.
9) Rates of all the items in roofing work are inclusive of staging or scaffolding for any
height.
10) Non-asbestos cement sheet provided in place of asbestos cement sheet roofing.
11) Concreting of pile shall be done with RMC only.
12) Rates of piling are inclusive of Chiseling of intermediate local boulders. No separate
payment shall be made for the same
13) While estimating the quantity for Grouting of bentonite slurry in bored precast piles
shall be measured as per bore dia and pile dia. Exact quantity can be measured
while execution and shall be paid accordingly
14) Rates considered in concrete items are including pumping of concrete upto placing
point.
15) New items like Self compacting concrete, vacuum dewatered concrete flooring and
TMT steel bars have been introduced.
16) The dismantling and demolishing chapter covers only removing old items and repair
work covers both removing old items and refixing the new.
17) For heritage works the rate includes the statutory charges for heritage committee
and conservation architect and no extra payment will be made.
18) APP (Atactic poly-propylene) modified polymeric membrane water proofing will be
used only for trial basis on approval of City Engineer and/or Chief Engineer (P&D).
19) In plumbing waterless urinals, fly ash bricks, fly ash concrete for green building
concept have been introduced.

Star Rating:
In view of ambiguity related to choice of quality or grade of materials and subsequent
items of works to be used at Ward level projects, Centralised projects or Special projects
of and for smooth functioning during planning stage of a project, the new concept of Star
Rating has been introduced for building works depending on the life expectancy of
building, degree of occupancy of building and comfort to the end user. The buildings or
structures rated are as follows:
i. Two Star **- Ward offices and Central dept. Offices, schools, Small
Hospitals, Primary Health Center, Fire Station, Crematorium, Slaughter
Houses, Markets, Swimming Pools, Zoos, Chowkies, Libraries, Staff
quarters and residential colonies, Public Toilets and Water tanks.
ii. Three Star ***- Superspeciality Hospitals , Drama Theatres, MCGM
Mayors and Officers bungalow, Heritage Structures, Head Office and
Engineers Hub.
The items or work not marked as two star or three star are assumed to be
applicable for all the star buildings or structures mentioned above.

C. SALIENT FEATURES OF SOR FOR ROAD AND BRIDGE WORKS

1. The rate analysis includes some provisions such as shuttering / centering on a
percentage basis. This has been brought on a rational basis using available data.
2. Since the entire area covered by Greater Mumbai falls within the coastal belt, the
minimum grade of structural concrete as recommended by IRC / MORTH for severe
exposure has been adopted.
Items referred from common schedule or other schedule:
ROAD
CS-EW-15 & 16: Excavation in foundation for road works
CS-CW-1-c: Cement Concrete - Nominal Mix of 1:3:6 -M10
CS-CW-1-a: P/L M-20 grade concrete for RCC work (using cement @ 330
kg/cum) - All work upto plinth level
CS-CW-7 & 19: Providing and laying in position machine batched and machine
mixed design mix M-40 grade
CS-CW-30-a: Formwork
CS-PL-52: Cement Mortar 1:2 (1 Cement: 2 Coarse/ Fine Sand)
CS-PL-56: Cement Mortar 1:6 (1 Cement: 6 Coarse/ Fine Snad)
CS-CW-35-a: Reinforcement for R.C.C. work all complete. -Upto plinth level
Mild steel bars.
CS-SS-01: Providing, detailing, fabricating and fixing at desired location
using hot rolled sections and MS Plates of grade Fe 250 as
per specifications and approved fabrication drawings
S-PN-4-c: Oil paint/ synthetic enamel paint in two coats with one coat of
primer for Steelwork
BRIDGE:
CS-EW-1-10: Earthwork
CS-SS-01: Providing and Fabricating structural steel work in rolled
sections
CS-CW-1-b: PCC Grade M15 for Open Foundation by Mixer
CS-CW-1-a: PCC Grade M20 for Open Foundation by Mixer

CS-CW-2-a-1: RCC Grade M20 for Open Foundation by Batching Plant
(RMC)
CS-CW-16: Extra and over for providing richer RMC of M-25 grade cement
concrete instead of M20
CS-CW-17: Extra and over for providing richer RMC of M-30 grade cement
concrete instead of M20
CS-CW-18: Extra and over for providing richer RMC of M-35 grade cement
concrete instead of M20
CS-CW-19: Extra and over for providing richer RMC of M-40 grade cement
concrete instead of M20
CS-CW-20: Extra and over for providing richer RMC of M-45 grade cement
concrete instead of M20
CS-CW-21: Extra and over for providing richer RMC of M-50 grade cement
concrete instead of M20
CS-CW-35-b: Supplying, fitting and placing HYSD bar reinforcement
Items that are referred to other SORs
RW-2-01: Supplying blue trap stones of approved quality & providing the
same in rubble packing 25cm.
D. LIST OF UNITS USED
Sr.
No.
Units Abbreviation
Symbol
Remark
1 Length (Running Meter) Rmt
2 Weight (Metric Tonne) MT
3 Weight Kilogram Kg
4 Time Shift Shift Refers to a time duration of 8 Hrs
5 Time (Hour) Hr
6 Quantity (Numbers) Each/No.
Each refers to a single quantity per
entity
7 Quantity (Lump sum) LS
8 Volume Cum
9 Area (Square Meter) Sqm
10 Litre Ltr
11 Cubic Centimeter Cucm

E. LIST OF ABBREVIATIONS
AASHTO American Association of State Highway and Transportation Officials
ASTM American Society for Testing and Materials
BS British Standard published by the British Standards Institution
BOQ Bill of Quantities forming part of the contract
CBR California Bearing Ratio
IRC Indian Road Congress
IS Indian Standard published by the Bureau of Indian Standards
WC Water Cement Ratio
CRRI Central Road Research Institute
UCS Unconfined Compressive Strength
WBM Water Bound Macadam
SAM Stress Absorbing Membrane
SAMI Stress Absorbing Membrane Interlayer
MoRTH Ministry of Road Transport and Highways
PCC Plain cement concrete
RCC Reinforced cement concrete
PSC Prestressed concrete
HYSD High Yield Strength Deformed Bars
EJ Expansion joints
FBEC Fusion Bonded Epoxy Coating
RE Reinforced Earth
ESU Elastomeric slab unit

Schedule for Bridge Works
2013

INDEX

Chapter.
No.
Chapter
Code
Contents Item Range
Page
No.
1 BW-1 SUBSOIL INVESTIGATION BW-1-1 to BW-1-28 1-4
2 BW-2 FOUNDATION BW-2-1 to BW-2-115 4-24
3 BW-3 SUB-STRUCTURE BW-3-1 to BW-3-29 24-28
4 BW-4 SUPER-STRUCTURE BW-4-1 to BW-4-72 28-38
5 BW-5 MISCELLANEOUS ITEMS BW-5-1 to BW-5-7 38-45
6 BW-6
RIVER TRAINING AND
PROTECTION WORKS
BW-6-1 to BW-6-11 45-47
7 BW-7
REPAIR AND
REHABILITATION
BW-7-1 to BW-7-23 47-48


BASIC RATE LIST Appendix-A 49-57


LIST OF APPROVED
MAKE
Appendix-B

Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
SUBSOIL INVESTIGATION
A) WORKS TO BE CARRIED OUT IN HAND
Note: Contractors will have to submit proof of sufficient technical
competence of agency undertaking items below. The contractors will
not be entitled to additional reimbursement for employing alternative
agency, if Engineer-in-charge so desires.
BW-1-01
Providing and transporting necessary and adequate plant and
equipment to site with in a lead of 50 km for taking trial bores for subsoil
investigations including conducting an initial survey for establishing datum
RLS and locations at trial bores including installation of the drilling
equipment of the first bore location etc. complete as specified and
directed.
Each unit 25000.00
BW-1-02
Shifting and locating the drilling equipment from one location to
another within a lead of 500 m between successive locations including
surveying the spot for establishing bore hole location, fixing ground levels
with reference to datum RLs and observing groundwater level during
boring operation etc. complete as specified and directed.
Each
shift
1000.00
Taking trial bores upto 150 mm dia. for subsoil investigation through
overburden and soil of all sorts including providing of temporary casing
and cleaning the bottom of holes before conducting field tests or collecting
samples at various depths etc. complete as specified and directed.
BW-1-03-a a) Depth upto 6.0m below ground surface Rmt 1000.00
BW-1-03-b b) Depth beyond 6.0 m upto 20.0 m below ground surface Rmt 1200.00
Taking trial bores for subsoil investigation through rock using rotary
drilling equipment with NX size diamond core drilling bits to obtain
approximately 54 mm dia. rock cores including provision of wooden boxes
for storage of cores, indexing the core samples at site of work and
conveying the same to the head quarters of concerned office etc. complete
as specified and directed.
BW-1-04-a a)Depth upto 10.0 m below ground surface Rmt 950.00
BW-1-04-b b) Depth beyond 10.0 m upto 20.00 m below ground surface Rmt 1000.00
BW-1-04-c c) Beyond 20 mtr. Rmt 1100.00
Taking trial bores for subsoil investigation through rock using rotary
drilling equipment with NX size diamond core drilling bits and double tube
core barrel to obtain approximately 54 mm dia. rock cores including
provision of wooden boxes for storage of cores, indexing the core samples
at site of work and conveying the same to the headquarters of concerned
office etc. complete as specified and directed.
BW-1-05-a a)Depth upto 10.0 m below ground surface Rmt 1600.00
BW-1-05-b b) Depth beyond 10.0 m upto 20.00 m below ground surface Rmt 1900.00
BW-1-05-c c) Depth beyond 20mtr. Rmt 2000.00
BW-1-06
Conducting Standard penetration test as per specifications in soil at
various levels of bore holes and reporting the results in the approved
format etc. complete as specified and directed.
No. 200.00
Collecting disturbed samples of soil from bore holes as per
specifications and delivering the same to the testing laboratory anywhere
in Greater Mumbai as directed etc. complete as specified and directed.
DESCRIPTION OF ITEMS __ BRIDGE
1
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-1-07-a a) In M.S. Black tube 50 mm dia 150 mm. long including the cost of tube No. 300.00
BW-1-07-b b) In polythene bags by driving 100 mm size tube. No. 150.00
BW-1-08
Collecting undisturbed samples of soil as per specifications at any
depth in M.S. black tube 100 mm dia. 450 mm long, sealed at both ends
with paraffin wax and delivering the same to the testing laboratory
anywhere in Greater Mumbai etc. complete as specified and directed.
No. 450.00
B) WORKS TO BE CARRIED OUT IN WATER CREEK
Note: 1) The Contractors will have to submit proof of sufficient
technical competence of agency undertaking items below. The
Contractor will not be entitled to additional reimbursement for
employing agency, if Engineer-in-charge so desires.
2) The Contractor will have to make their own arrangements for
boats, barges, pontoons, floating platforms etc. for carrying out the
works covered under 1.009 to 1.016 below for which no extra,
payment what so ever will be made.
BW-1-09
Providing and transporting to site necessary and adequate plant and
equipment for taking trial bores for subsoil investigations including
conducting an initial survey for establishing datum RLS and locations of
trial bores including installation of the drilling equipment of the first bore
location etc. complete as specified and directed with reference to T.H.D.
Each
Unit
45000.00
BW-1-10
Shifting and locating the drilling equipment from one location to
another within a lead of 500 m between successive locations including
surveying the spot for establishing bore hole location, fixing ground levels
with reference to datum RLS and observing ground water level during
boring operation etc. complete as specified and directed.
Each
Unit
3500.00
Taking trial bores upto 150 mm dia. for subsoil investigation through
overburden and soil of all sorts including cleaning the bottom of holes
before taking field tests at various depths etc. complete as specified and
directed.
BW-1-11-a a) Depth upto 6.0 m below ground surface Rmt 1600.00
BW-1-11-b b) Depth beyond 6.0 m upto 20.0 m below ground surface Rmt 2100.00
Taking trial bores for subsoil investigation through rock using rotary
drilling equipment with NX size diamond core drilling bits to obtain
approximately 54 mm dia. rock cores including provision of wooden boxes
for storage of cores, indexing the core samples at site of work and
conveying the same to the head quarters of concerned office etc. -
complete as specified and directed.
BW-1-12-a a) Depth upto to 10.0 m below ground surface. Rmt 2500.00
BW-1-12-b b) Depth beyond 10.0 m upto 20.00 m below ground surface Rmt 2800.00
BW-1-12-c c) Depth beyond 20 m to 30 m Rmt 3000.00
Taking trial bores for sub soil investigation through rock using rotary
drilling equipment with NX size diamond core drillng bits and double tube
core barrel to obtain approximately 54 mm dia. rock cores including
provision of wooden boxes for storage of cores, indexing the core samples
at site of work and conveying the same to the headquarters of concerned
office etc. complete as specified and directed.
BW-1-13-a a) Depth upto 10.0 m below ground surface Rmt 1900.00
BW-1-13-b b) Depth beyond 10.0 m upto 20.00 m below ground surface Rmt 2400.00
2
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-1-14
Conducting Standard penetration test as per Specifications in soil at
various levels of bore holes and reporting the results in the approved
format etc. complete as specified and directed.
No. 300.00
Collecting disturbed samples of soil from bore holes as per
specifications and delivering the same to the testing laboratory anywhere
in Greater Mumbai as directed etc. complete as specified and directed.
BW-1-15-a a) In M.S. Black tube 50 mm dia 150 mm. long including the cost of tube No. 300.00
BW-1-15-b b) In polythene bags by driving 100 mm size tube. No. 150.00
BW-1-16
Collecting undisturbed samples of soil as per specifications at any
depth in M.S. black tube 100 mm dia. 450 mm long, sealed at both ends
with paraffin wax and delivering the same to the testing laboratory
anywhere in Greater Mumbai etc. complete as specified and directed.
No. 450.00
BW-1-17
Collecting soil samples and sub-soil water samples in glass or plastic
bottles I jars from trial bore holes and getting the same chemically
analyzed in an approved laboratory for determination of sulphate and
chloride contents and pH value etc. complete as specified and directed.
No. 100.00
BW-1-18
Carrying out Plate Load Test complete with necessary and adequate
Kentledge loads, equipments and instruments etc. as per specifications for
determination of bearing capacity of soil etc. complete as specified and
directed and submitting reports in duplicate.
No. 75000.00
(C) SUB-SURFACE EXPLORATIONS
BW-1-19
Preparing and submitting reports and drawings in triplicate for location
depth and details of underground pipe lines, cables and services as
existing according to standard technique as specified upto whatever depth
of excavation and including all equipment, material, and labour of technical
expertise as directed excluding excavation.
Each
Trench
15000.00
Taking trial pit in soil of all sorts excluding rock including shoring and
strutting as required, collecting disturbed & undisturbed samples at 1 m
intervals and trial depth, collecting water samples & transporting all soil &
water sample to lab., visual inspection for description of strata / recording
water table encountered, dewatering manually and refilling at end etc.
complete as specified and directed.
BW-1-20-a a) Upto 2 mt. depth Cum 2000.00
BW-1-20-b b) 2 m to 4 m depth Cum 3000.00
BW-1-20-c c) 4 m to 6 m depth Cum 5000.00
(D) LABORATORY TESTING
Carrying out tests as per specifications for determination of:
BW-1-21-a i) Natural moisture Content (NMC) of soil by Oven Drying method No. 150.00
ii) Atterberg limits
BW-1-21-b a) Liquid limit No. 150.00
BW-1-21-c b) Plastic limit No. 150.00
BW-1-21-d c) Shrinkage limit No. 150.00
iii) Grain size analysis including grain size distribution curves in
accordance with IS 2720 (part 4)
BW-1-21-e a) Sieve Analysis No. 200.00
BW-1-21-f b) Hydrometer Analysis No. 300.00
BW-1-21-g iv) In-situ density of soil samples No. 150.00
BW-1-21-h v) Specific gravity No. 150.00
3
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-1-21-i
vi) Unconfined compressive strength of rock samples, including
determination of percentage of water absorption and density.
No. 500.00
BW-1-22
Carrying out Vane Shear Test at various levels of bore holes as per
specifications laid down in IS:4434 and reporting results thereof as per
prescribed proforma etc. complete as specified and directed. (Including
mobilization of necessary and adequate equpment)
No. 12000.00
BW-1-23
Providing and transporting to site necessary and adequate plant and
equipment for performing DPT etc. complete as specified and directed.
Each
Unit
7000.00
BW-1-24
Shifting and locating plant and equipment from one location to another
location for performing DPT etc. complete as specified and directed.
Each
Shift
1000.00
Performing Dynamic cone penetration test in accordance with IS 4968
and reporting the results in the approved format etc. complete as specified
and directed.
BW-1-25-a
a) Conducting probing test by using lighter probing rod and light weight
hammer (18 kg)
No. 3000.00
BW-1-25-b b) Conducting probing test using a-drill and SPT hammer (65 kg) No. 3000.00
BW-1-26
Conducting Direct Shear Test in accordance with IS:2720 (part 13) and
reporting results thereof as per prescribed proforma etc complete as
specified and directed.
No. 500.00
BW-1-27
Conducting Consolidation test on undisturbed soil sample or soil sample
compacted to specified density in accordance with IS 2720 ( part-15
),reporting results including unit weights, specific gravity, e-log p curve,
virgin curve, PO, eo, Cc, Cv and mv for all pressure increments etc.
complete as specified and directed.
No. 900.00
BW-1-28
Conducting Unconfined compression test on undisturebed soil samples
or soil samples compacted to specified density in accordance with IS :
2720 (part 10) and reporting results thereof as per prescribed Proforma
etc. complete as specified and directed.
No. 350.00
FOUNDATION
A) EXCAVATION
BW-2-1
Excavation for foundation in any type of Marshy or creek land upto a
depth of 3.0 m by Manual means
Cum 427.00
BW-2-1-a Cost for dewatering , where required for Item No. BW -2-1 Cum 96.60
BW-2-1-b Cost for Shoring & strutting , where required for Item No. BW -2-1 Cum 48.30
It is assumed that Marshy Soil will be available upto 3 m depth only. For
deeper excavation below 3 m depth, refer Common Schedule Earth Work
Chapter
BW-2-2
Excavation for foundation in any type of Marshy or creek land upto a
depth of 3.0 m by Mechanical Means
Cum 177.00
BW-2-2-a Cost for dewatering , where required for Item No. BW -2.1.2 Cum 30.78
BW-2-2-b Cost for Shoring & strutting , where required for Item No. BW -2.1.2 Cum 15.39
It is assumed that Marshy Soil will be available upto 3 m depth only. For
deeper excavation below 3 m depth, refer Common Schedule Earth Work
Chapter
BW-2-3 Back Filling in Marshy Foundation Pits Cum 256.00
4
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-4
Excavation for foundation in earth, soil of all sorts excluding rock by
any method as required and / or directed including shoring and strutting as
necessary, removing down vegetation, bailing out water manually,
removing the excavated materials upto a safe distance as directed
including all lifts and leads, preparing the bed for foundation, backfilling
with approved materials, ramming, watering and disposing off the surplus
excavated material and cleaning the site etc. complete as specified and
directed (0 to 2m.)
Refer
Common
Schedule
Earth Work
Chapter
BW-2-5
Excavation for foundation in earth, soil of all sorts excluding rock by
any method as required and / or directed including shoring and strutting as
necessary, removing down vegetation, bailing out water manually,
removing the excavated materials upto a safe distance as directed
including all lifts and leads, preparing the bed for foundation, backfilling
with approved materials, ramming, watering and disposing off the surplus
excavated material and cleaning the site etc. complete as specified and
directed (above 2m upto 4m.)
Refer
Common
Schedule
Earth Work
Chapter
BW-2-6
Excavation for foundation in earth, soil of all sorts excluding rock by
any method as required and / or directed including shoring and strutting as
necessary, removing down vegetation, bailing out water manually,
removing the excavated materials upto a safe distance as directed
including all lifts and leads, preparing the bed for foundation, backfilling
with approved materials, ramming, watering and disposing off the surplus
excavated material and cleaning the site etc. complete as specified and
directed (above 4m upto 6m.)
Refer
Common
Schedule
Earth Work
Chapter
BW-2-7
E.O for Excavation for foundation in soft rock by any method as
required and / or directed including bailing out water manually, removing
the excavated materials upto a safe distance as directed including all lifts
and leads, preparing the bed for foundation, backfilling with approved
materials, watering and disposing off the surplus excavated materials and
cleaning the site etc. completed as specified and directed (any depth).
Refer
Common
Schedule
Earth Work
Chapter
BW-2-8
E.O for Excavation for foundation in hard rock by blasting including
bailing out water manually, removing the excavated materials upto a safe
distance as directed, stacking the serviceable materials neatly and
disposing off the unserviceable materials as directed including all leads
and lifts, preparing the bed for foundation backfilling with approved
materials and disposing off the surplus excavated materials and cleaning
the site etc. complete as specified and directed (any depth).
Refer
Common
Schedule
Earth Work
Chapter
BW-2-9
Excavation for foundation in hard rock by chiseling / wedging / line
drilling without blasting including bailing out water manually, removing
the excavated materials upto a safe distance as directed, stacking the
serviceable materials neatly and disposing off the unserviceable materials
as directed including all leads and lifts, preparing the bed for foundation,
backfilling with approved materials and disposing off the surplus excavated
materials and cleaning the site etc. complete as specified and directed
(any depth).
Refer
Common
Schedule
Earth Work
Chapter
BW-2-10
Filling Annular Space Around Footing in Rock (Lean cement concrete
1:3:6 nominal mix).
Cum 4696.00
BW-2-11
Sand Filling in Foundation Trenches as per Drawing & Technical
Specification
Cum 1766.00
5
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-12
Dewatering on Horse Power basis by using water pumps including
diversion of streams, providing earthen bunds, cofferdams etc. as may
necessary for foundation and other parts of structure including pumping
out water during and after excavation until work for foundation and sub-
structure above natural water is completed etc. completed as specified and
directed.
HP per
hr
Refer CS-
EW-10
MASONRY ITEMS
BW-2-13
Providing and laying Dry Rubble stone packing having thickness 230 mm
and above in foundation including hand packing in regular line and level,
filling interstices with small pieces of stone, thoroughly ramming and
consolidating including watering as necessary etc. complete as specified
and directed.
Cum 1219.00
BW-2-14
Providing Coursed rubble masonry 1st sort of trap stone in cement
mortar 1:5 in superstructure including scaffolding, racking out I striking out
joints, watering etc. complete as directed and specified.
Cum 3992.00
Providing random rubble stone masonry of trap stone in cement mortar 1:3
in foundation / sub structure as per drawing and specification striking joints
of non exposed faces and pointing the exposed faces with cement mortar
1:3 including scaffolding and watering including bailing out water manually
etc. complete.
BW-2-15-a Square Rubble Coursed rubble masonry( first sort ) Cum 4776.00
BW-2-15-b Random Rubble Masonry Cum 4611.00
(B) PLAIN AND R.C.C. FOR OPEN FOUNDATIONS
Notes: Applicable for all cement concrete items in the BRIDGE
Schedule.
1) All concrete shall be machine mixed and consolidated and I or
compacted by vibrators. The maximum siize of aggregate for plain
concrete works shall be limited to 40mm and that of reinforced
concrete shall be limited to 25mm unless otherwise specified in
particular items or in drawings.
2) Whenever contractor uses fly ash as part of the cement quantity,
the following formula shall be applied for deduction in the rate of the
item.
Amount in Rupees per Cubic metre of Concrete to be deducted from the
rate of item in the schedule of Rates/Tender :
Notes for R.M.C.
1) Any lead for R.M.C more than 20 km. is on contractors account.
2) R.M.C is required to be unloaded within one hour from plant to
site, hence more than 20kms. Is not desirable.
3) If lead is more than 20kms. The contractor has to establish his own
batching plant near site.
4) All Batch mixed plant is assumed to be RMC plant
1.155[N x a/100] (A - B)
Where N = The Number of bags per Cum. of concrete considered in the
mix.
a = Percentage of fly ash used in the concrete mix by the Contractor.
A : Market Rate of cement per bag (50 Kg) in Rupees In Mumbai or
Schedule Rate of Cement whichever is higher
B : Market Rate of fly Ash per 50Kg. in Rupees in Mumbai.
The factor 1.155 accounts for over head charges and sundries considered
in the Rate abstract of the item.
6
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
N' for various grade of concrete considered in the schedule of Rate.
M-45 = 10.8 bags/Cum. M-25= 8.2 bags I Cum.
M-40 = 10.8 bags/Cum. M-20 =7.20 bags / Cum.
M-35 = 10.2 bags/Cum. M-15= 6.40 bags I Cum.
M-30 = 9.2 bags/Cum. M-10 =5.50 bags / Cum.
BW-2-16
Providing and laying in position M-10 plain cement concrete to fill up loose
pockets of foundations bed for making required levels, annular filling
around abutments, piers, columns for foundation.
4775.00
BW-2-17
Providing and placing in position controlled cement concrete of M-15 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for PCC raft foundation slab with V notches Sloped
/ flat / strlp footings, pile caps tie beams to required lines / levels including
leveling, compacting by vibrators, curing including shuttering, centering as
necessary and required etc. complete as specified and as directed.
Cum 5218.00
BW-2-18
Providing and placing in position controlled cement concrete of M-20 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for PCC raft foundation slab with V notches Sloped
/ flat / strlp footings, pile caps tie beams to required lines / levels including
leveling, compacting by vibrators, curing including shuttering, centering as
necessary and required etc. complete as specified and as directed.
Cum 5609.00
Providing and placing in position controlled cement concrete of M-20 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for RCC raft foundation slab with V notches Sloped
/ flat / strlp footings, pile caps tie beams to required lines / levels including
leveling, compacting by vibrators, curing including shuttering, centering as
necessary and required etc. complete as specified and as directed but
excluding reinforcement.
BW-2-19-a a) Using concrete mixer Cum 5646.00
BW-2-19-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6019.00
Providing and placing in position controlled cement concrete of M-25 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for PCC raft foundation slab with V notches Sloped
/ flat / strlp footings, pile caps tie beams to required lines / levels including
leveling, compacting by vibrators, curing including shuttering, centering as
necessary and required etc. complete as specified and as directed.
BW-2-20-a a) Using concrete mixer Cum 5991.00
BW-2-20-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6210.00
Providing and placing in position controlled cement concrete of M-25 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for RCC raft foundation slab with V notches Sloped
/ flat / strlp footings, pile caps tie beams to required lines / levels including
leveling, compacting by vibrators, curing including shuttering, centering as
necessary and required etc. complete as specified and as directed but
excluding reinforcement.
BW-2-21-a a) Using concrete mixer Cum 6033.00
BW-2-21-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6210.00
Providing and placing in position controlled cement concrete of M-30 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for PCC raft foundation slab with V notches Sloped
/ flat / strlp footings, pile caps tie beams to required lines / levels including
leveling, compacting by vibrators, curing including shuttering, centering as
necessary and required etc. complete as specified and as directed.
7
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-22-a a) Using concrete mixer Cum 6020.00
BW-2-22-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6541.00
Providing and placing in position controlled cement concrete of M-30 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for RCC raft foundation slab with V notches
Sloped / flat / strlp footings, pile caps tie beams to required lines /
levels including leveling, compacting by vibrators, curing including
shuttering, centering as necessary and required etc. complete as specified
and as directed but excluding reinforcement.
BW-2-23-a a) Using concrete mixer Cum 6042.00
BW-2-23-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6606.00
Providing and placing in position controlled cement concrete of M-35 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for RCC raft foundation slab with V notches
Sloped / flat / strlp footings, pile caps tie beams to required lines /
levels including leveling, compacting by vibrators, curing including
shuttering, centering as necessary and required etc. complete as specified
and as directed but excluding reinforcement.
BW-2-24-a a) Using concrete mixer Cum 6122.00
BW-2-24-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6779.00
BW-2-25
Providing and placing in position controlled cement concrete of M-40 grade
for foundation work with minimum cement 400 kg./cum. and water cement
ratio not exceeding 0.4 for RCC raft foundation slab with V notches
Sloped / flat / strlp footings, pile caps tie beams to required lines /
levels including leveling, compacting by vibrators, curing including
shuttering, centering as necessary and required etc. complete as specified
and as directed but excluding reinforcement.
Cum 7017.00
(C) PILE FOUNDATIONS
Providing and installing in position controlled concrete of grade M-
30(Batching Plant,Transit Mixer and Concrete Pump ) with minimum
cement content as 400 kg/cum. and W.C. ratio not exceeding 0.40 for
RCC work in cast-in-situ bored piles each of load capacity as per design
and of specified diameter using maximum 20 mm size of aggregate
including boring through aIl strata except rock, including placing of
concrete by tremie arrangement through mild steel casing to the required
depth through all strata except rock, compaction as necessary with drawl
of mild steel casing including chipping / dressing of piles to required
levels, cleaning the reinforcement etc. complete as specified and directed
(Excluding reinforcement).
BW-2-26-a 1) 400 mm dia Rmt 1272.00
BW-2-26-b 2) 450 mm dia Rmt 1610.00
BW-2-26-c 3) 500 mm dia Rmt 1987.00
BW-2-26-d 5) 600 mm dia Rmt 2862.00
BW-2-26-e 8) 750 mm dia Rmt 4490.00
BW-2-26-f 11) 1000 mm dia Rmt 7982.00
BW-2-26-g 13) 1200 mm dia Rmt 11494.00
8
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and installing in position controlled concrete of grade M-35
(Batching Plant, Transit Mixer and Concrete Pump ) with minimum
cement content as 400 kg/cum. and W.C. ratio not exceeding 0.40 for
RCC work in cast-in-situ bored piles each of load capacity as per design
and of specified diameter using maximum 20 mm size of aggregate
including boring through aIl strata except rock, including placing of
concrete by tremie arrangement through mild steel casing to the required
depth through all strata except rock, compaction as necessary with drawl
of mild steel casing including chipping / dressing of piles to required
levels, cleaning the reinforcement, removal of excavated earth with all lifts
and lead upto 1000 m. etc. complete as specified and directed (Excluding
reinforcement).
BW-2-27-a 1) 400 mm dia Rmt 1245.00
BW-2-27-b 2) 450 mm dia Rmt 1575.00
BW-2-27-c 3) 500 mm dia Rmt 1945.00
BW-2-27-d 4) 550 mm dia Rmt 2353.00
BW-2-27-e 5) 600 mm dia Rmt 2801.00
BW-2-27-f 6) 650 mm dia Rmt 3287.00
BW-2-27-g 7) 700 mm dia Rmt 3812.00
BW-2-27-h 8) 750 mm dia Rmt 4376.00
BW-2-27-i 9) 800 mm dia Rmt 4979.00
BW-2-27-j 10) 900 mm dia Rmt 6302.00
BW-2-27-k 11) 1000 mm dia Rmt 7780.00
BW-2-27-l 12)1100mmdia Rmt 9414.00
BW-2-27-m 13) 1200 mm dia Rmt 11203.00
Extra over rates quoted in items BW-2-26 and BW-2-27 for chiseling
through soft / weathered rock / hard rock / large boulders / old foundations
/ masonry / concrete etc. using a chisel weighing not less than 750 kg.
BW-2-28-a 1) 400mmdia Rmt 786.00
BW-2-28-b 2) 450 mm dia Rmt 995.00
BW-2-28-c 3) 500 mm dia Rmt 1228.00
BW-2-28-d 4) 550 mm dia Rmt 1486.00
BW-2-28-e 5) 600 mm dia Rmt 1769.00
BW-2-28-f 6) 650 mm dia Rmt 2076.00
BW-2-28-g 7) 700 mm dia Rmt 2407.00
BW-2-28-h 8) 750 mm dia Rmt 2764.00
BW-2-28-i 9) 800 mm dia Rmt 3144.00
BW-2-28-j 10) 850 mm dia Rmt 3550.00
BW-2-28-k 11) 900 mm dia Rmt 3980.00
BW-2-28-l 12) 1000 mm dia Rmt 4913.00
BW-2-28-m 13) 1100 mm dia Rmt 5945.00
BW-2-28-n 14) 1200 mm dia Rmt 7075.00
BW-2-3-4
Empty boring through over burden including road crust upto the bottom of
pile cap for all diameters of piles.
Rmt 1806.00
Chipping and dressing of the RCC piles to remove surplus concrete
above cut off level without damaging the projecting reinforcement including
clearing reinforcement and removing the dismantled materials etc.
complete as specified and directed.
BW-2-29-a 1) 400 mm dia Rmt 110.00
BW-2-29-b 2) 450 mm dia Rmt 140.00
BW-2-29-c 3) 500 mm dia Rmt 173.00
BW-2-29-d 4) 550 mm dia Rmt 209.00
BW-2-29-e 5) 600 mm dia Rmt 248.00
BW-2-29-f 6) 650 mm dia Rmt 292.00
9
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-29-g 7) 700 mm dia Rmt 338.00
BW-2-29-h 8) 750 mm dia Rmt 388.00
BW-2-29-i 9) 800 mm dia Rmt 442.00
BW-2-29-j 10) 900 mm dia Rmt 499.00
BW-2-29-k 11) 1000 mm dia Rmt 559.00
BW-2-29-l 12) 1100 mm dia Rmt 690.00
BW-2-29-m 13) 1200 mm dia Rmt 835.00
Providing and installing in position controlled concrete of grade M-35
(Batching Plant, Transit Mixer and Concrete Pump ) with minimum cement
content as 400 kg/cum. and W.C. ratio not exceeding 0.40 for RCC work in
driven cast-in-situ vertical piles each of load capacity as per design and
of specified diameter using maximum 20 mm size of aggregate including
boring through aIl strata except rock, including placing of concrete by
tremie arrangement through mild steel casing to the required depth
through all strata except rock, compaction as necessary with drawl of mild
steel casing including chipping / dressing of piles to required levels,
cleaning the reinforcement etc. complete as specified and directed
(Excluding reinforcement).
BW-2-30-a a) 750 mm dia Rmt 4174.00
BW-2-30-b b) 1000 mm dia Rmt 6865.00
BW-2-30-c c) 1200 mm dia Rmt 9989.00
BW-2-31
Providing and placing in position M-35 RCC precast piles of 500 mm dia
in preformed bores made with hydraulic rig drilling / boring through all type
of strata including hard rock using portland cement with minimum cement
content as 400 kg. Per cum. and water cement ratio not exceeding 0.40
each with a load capacity as per design, transporting the precast pile from
casting yard to site of work, hoisting and holding the pile truly vertical with
the help of crane of required capacity, placing the pile in position including
grouting the annular space with cement grout (1 :2) (1 cement, 2 fine sand)
between the pile and the preformed bore including cutting off the surplus
length of pile and dressing neatly including providing M.S. black tube 30
mm dia through the centre of pile for grouting etc. complete including cost
of all boring work through all type of strata as specified and directed but
excluding the cost of reinforcement.
Rmt 2508.00
BW-2-32
Providing and placing in position M-35 RCC precast piles of 600 mm dia
in preformed bores made with hydraulic rig drilling / boring through all type
of strata including hard rock using portland cement with minimum cement
content as 400 kg. Per cum. and water cement ratio not exceeding 0.40
each with a load capacity as per design, transporting the precast pile from
casting yard to site of work, hoisting and holding the pile truly vertical with
the help of crane of required capacity, placing the pile in position including
grouting the annular space with cement grout (1 :2) (1 cement, 2 fine sand)
between the pile and the preformed bore including cutting off the surplus
length of pile and dressing neatly including providing M.S. black tube 30
mm dia through the centre of pile for grouting etc. complete including cost
of all boring work through all type of strata as specified and directed but
excluding the cost of reinforcement.
Rmt 2788.00
10
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-33
Providing and placing in position M-35 RCC precast piles of 450 mm dia
in preformed bores made with hydraulic rig drilling / boring through all type
of strata including hard rock using portland cement with minimum cement
content as 400 kg. Per cum. and water cement ratio not exceeding 0.40
each with a load capacity as per design, transporting the precast pile from
casting yard to site of work, hoisting and holding the pile truly vertical with
the help of crane of required capacity, placing the pile in position including
grouting the annular space with cement grout (1 :2) (1 cement, 2 fine sand)
between the pile and the preformed bore including cutting off the surplus
length of pile and dressing neatly including providing M.S. black tube 30
mm dia through the centre of pile for grouting etc. complete including cost
of all boring work through all type of strata as specified and directed but
excluding the cost of reinforcement.
Rmt 2255.00
BW-2-34
Providing and placing in position M-35 RCC precast piles of 750 mm dia
in preformed bores made with hydraulic rig drilling / boring through all type
of strata including hard rock using portland cement with minimum cement
content as 400 kg. Per cum. and water cement ratio not exceeding 0.40
each with a load capacity as per design, transporting the precast pile from
casting yard to site of work, hoisting and holding the pile truly vertical with
the help of crane of required capacity, placing the pile in position including
grouting the annular space with cement grout (1 :2) (1 cement, 2 fine sand)
between the pile and the preformed bore including cutting off the surplus
length of pile and dressing neatly including providing M.S. black tube 30
mm dia through the centre of pile for grouting etc. complete including cost
of all boring work through all type of strata as specified and directed but
excluding the cost of reinforcement.
4294.00
BW-2-35
Providing and placing in position M-35 RCC precast piles of 1000 mm
dia in preformed bores made with hydraulic rig drilling / boring through all
type of strata including hard rock using portland cement with minimum
cement content as 400 kg. Per cum. and water cement ratio not exceeding
0.40 each with a load capacity as per design, transporting the precast pile
from casting yard to site of work, hoisting and holding the pile truly vertical
with the help of crane of required capacity, placing the pile in position
including grouting the annular space with cement grout (1 :2) (1 cement, 2
fine sand) between the pile and the preformed bore including cutting off
the surplus length of pile and dressing neatly including providing M.S.
black tube 30 mm dia through the centre of pile for grouting etc. complete
including cost of all boring work through all type of strata as specified and
directed but excluding the cost of reinforcement.
6954.00
BW-2-36
Providing and installing in position permanent M.S. liners for piles of
specified diameter and fabricated from 6.0 to 8.0mm thick plates as per
detailed drawings and designs including cutting, bending to required
shape, welding, painting with Red Oxide paint etc. complete as specified
and directed.
MT 78465.00
BW-2-37
Levelling course for Pile cap - Providing and laying of PCC M15
levelling course 100mm thick below the pile cap.
Cum 4150.00
Providing and cutting bending, hooking, laying in position and tying Mild
steel / HYSD bars for reinforcement as per detailed drawings for
R.C.C.work.
BW-2-38-a a) HYSD bars MT 62100.00
BW-2-38-b b) Mild Steel bars MT 61199.00
11
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
(D) WEll FOUNDATIONS
Providing and constructing temporary island 16 m diameter for
construction of well foundation for 8m dia. Well.
BW-2-39-a Assuming depth of water 1.0 m and height of island to be 1.25m. Each 38565.00
BW-2-39-b Assuming depth of water 4.0 m and height of island 4.5 m. Each 228563.00
BW-2-40
Providing and constructing one span service road to reach island location
from one pier location to another pier location
Rmt 1928.00
BW-2-41
Providing, fabricating and setting out in requisite position Mild steel
weighing 40 kg per metre cutting edge for RCC wells including cutting,
bending to required shape as per detailed drawings and designs including
bolting, revetting or welding sections, dowels for anchoring the cutting
edge to well curb etc. complete as specifeid and directed.
MT 83902.00
Well curb
Providing and placing in position controlled cement concrete in M-25 grade
in well curbs with minimum cement content as 400 kg/cum. water cement
ratio not exceeding 0.40 and maximum size of coarse aggregate not
exceeding 20 mm including necessary formwork to give form finish
surface, compacting by vibrators, curing etc. complete as specified and
directed. (Excluding reinforcement).
BW-2-42-a a) Using concrete mixer Cum 6979.00
BW-2-42-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 7237.00
Providing and placing in position controlled cement concrete in M-30
grade in well curbs with minimum cement content as 400 kg/cum. water
cement ratio not exceeding 0.40 and maximum size of coarse aggregate
not exceeding 20 mm including necessary formwork to give form finish
surface, compacting by vibrators, curing etc. complete as specified and
directed. (Excluding reinforcement).
BW-2-43-a a) Using concrete mixer Cum 7006.00
BW-2-43-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 8995.00
Providing and placing in position controlled cement concrete in M-35
grade in well curbs with minimum cement content as 400 kg/cum. water
cement ratio not exceeding 0.40 and maximum size of coarse aggregate
not exceeding 20 mm including necessary formwork to give form finish
surface, compacting by vibrators, curing etc. complete as specified and
directed. (Excluding reinforcement).
BW-2-44-a a) Using concrete mixer Cum 7133.00
BW-2-44-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 7822.00
Well steining
BW-2-45
Providing and placing in position controlled cement concrete of M-15 grade
in PCC well steining as per detailed design and drawings with minimum
cement content of 400 kg/cum, water cement ratio not exceeding 0.40 and-
maximum size of aggregate not exceeding 20 mm including form work to
give form finish surface, compacting by vibrators, necessary bracings and
curing etc. complete as specified and directed.
Cum 5519.00
12
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-46
Providing and placing in position controlled cement concrete of M-20 grade
in PCC well steining as per detailed design and drawings with minimum
cement content of 400 kg/cum, water cement ratio not exceeding 0.40 and-
maximum size of aggregate not exceeding 20 mm including form work to
give form finish surface, compacting by vibrators, necessary bracings and
curing etc. complete as specified and directed.
Cum 5933.00
Providing and placing in position controlled cement concrete of M-20 grade
in RCC well steining as per detailed design and drawings with minimum
cement content of 400 kg/cum, water cement ratio not exceeding 0.40 and-
maximum size of aggregate not exceeding 20 mm including form work to
give form finish surface, compacting by vibrators, necessary bracings and
curing etc. complete as specified and directed. (Excluding
reinforcement)
BW-2-47-a a) Using concrete mixer Cum 5972.00
BW-2-47-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6367.00
Providing and placing in position controlled cement concrete of M-25
grade in PCC well steining as per detailed design and drawings with
minimum cement content of 400 kg/cum, water cement ratio not exceeding
0.40 and-maximum size of aggregate not exceeding 20 mm including form
work to give form finish surface, compacting by vibrators, necessary
bracings and curing etc. complete as specified and directed.
BW-2-48-a a) Using concrete mixer Cum 6353.00
BW-2-48-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6568.00
Providing and placing in position controlled cement concrete of M-25 grade
in RCC well steining as per detailed design and drawings with minimum
cement content of 400 kg/cum, water cement ratio not exceeding 0.40 and-
maximum size of aggregate not exceeding 20 mm including form work to
give form finish surface, compacting by vibrators, necessary bracings and
curing etc. complete as specified and directed. (Excluding
reinforcement)
BW-2-49-a a) Using concrete mixer Cum 6397.00
BW-2-49-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6634.00
Providing and placing in position controlled cement concrete of M-30 grade
in PCC well steining as per detailed design and drawings with minimum
cement content of 400 kg/cum, water cement ratio not exceeding 0.40 and-
maximum size of aggregate not exceeding 20 mm including form work to
give form finish surface, compacting by vibrators, necessary bracings and
curing etc. complete as specified and directed.
BW-2-50-a a) Using concrete mixer Cum 6398.00
BW-2-50-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6918.00
Providing and placing in position controlled cement concrete of M-30 grade
in RCC well steining as per detailed design and drawings with minimum
cement content of 400 kg/cum, water cement ratio not exceeding 0.40 and-
maximum size of aggregate not exceeding 20 mm including form work to
give form finish surface, compacting by vibrators, necessary bracings and
curing etc. complete as specified and directed. (Excluding
reinforcement)
BW-2-51-a a) Using concrete mixer Cum 6422.00
BW-2-51-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 6987.00
13
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and placing in position controlled cement concrete of M-35 grade
in RCC well steining as per detailed design and drawings with minimum
cement content of 400 kg/cum, water cement ratio not exceeding 0.40 and
maximum size of aggregate not exceeding 20 mm including form work to
give form finish surface, compacting by vibrators, necessary bracings and
curing etc. complete as specified and directed (Excluding
reinforcement).
BW-2-52-a a) Using concrete mixer Cum 6539.00
BW-2-52-b b) With Batching Plant, Transit Mixer and Concrete Pump Cum 7170.00
Providing and placing in position controlled cement concrete of M-40 grade
in RCC well steining as per detailed design and drawings with minimum
cement content of 400 kg/cum, water cement ratio not exceeding 0.40 and
maximum size of aggregate not exceeding 20 mm including form work to
give form finish surface, compacting by vibrators, necessary bracings and
curing etc. complete as specified and directed (Excluding
reinforcement).
BW-2-53 - With Batching Plant, Transit Mixer and Concrete Pump Cum 7494.00
Sinking of 6 m external diameter well ( other than pneumatic method
of sinking ) through all types of strata namely sandy soil, clayey soil
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil
BW-2-54-a Depth below bed level upto 3.0 M Rmt 3296.00
BW-2-54-b Beyond 3m upto 10m depth Rmt 4594.00
Beyond 10m upto 20m
BW-2-54-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 6067.00
Beyond 20m upto 30 m
BW-2-54-d
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 11378.00
BW-2-54-e
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour .
13654.00
Beyond 30m upto 40 m Rmt
BW-2-54-f
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
27033.00
BW-2-54-g
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour .
Rmt 32439.00
Clayey soil ( 6m dia. Well )
BW-2-55-a Depth below bed level upto 3.0 M Rmt 4623.00
BW-2-55-b Beyond 3m upto 10m depth Rmt 10132.00
Beyond 10 m upto 20 m
BW-2-55-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 13383.00
BW-2-55-d Add for dewatering @ 5% of cost, if required. Rmt 14052.00
Beyond 20m upto 30 m
BW-2-55-e
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 25104.00
BW-2-55-f Add 5% of cost for dewatering of the cost, if required Rmt 32949.00
14
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-55-g
Add 25% of cost for Kentledge including supports, loading arrangement
and Labour ).
Rmt 31380.00
Beyond 30m upto 40 m
BW-2-55-h
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 59644.00
BW-2-55-i Add 5% of cost for dewatering, if required Rmt 75151.00
BW-2-55-j
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour).
Rmt 71573.00
Soft rock (6m dia well )
BW-2-56 Depth of soft rock strata upto 3m Rmt 16577.00
Hard rock (6m dia well )
BW-2-57 Depth of soft rock strata upto 3m Rmt 16482.00
Sinking of 7 m external diameter well ( other than pneumatic method
of sinking ) through all types of strata namely sandy soil, clayey soil
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil
BW-2-58-a Depth below bed level upto 3.0 M Rmt 4831.00
BW-2-58-b Beyond 3m upto 10m depth Rmt 6367.00
Beyond 10m upto 20m
BW-2-58-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 8409.00
Beyond 20m upto 30 m
BW-2-58-d
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 15772.00
BW-2-58-e
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour) .
Rmt 18927.00
Beyond 30m upto 40 m
BW-2-58-f
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 37470.00
BW-2-58-g
Add 20% of cost for Kentledge including supports, loading arrangement,
and Labour etc.
Rmt 44964.00
Clayey soil ( 7m dia. Well )
BW-2-59-a Depth below bed level upto 3.0 M Rmt 6367.00
BW-2-59-b Beyond 3m upto 10m depth Rmt 9071.00
Beyond 10 m upto 20 m
BW-2-59-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 11980.00
BW-2-59-d Add for dewatering @ 5% of cost, if required. Rmt 12579.00
Beyond 20m upto 30 m
BW-2-59-e
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 22472.00
BW-2-59-f Add 5% of cost for dewatering on the cost, if required Rmt 29494.00
BW-2-59-g
Add 25% of cost for Kentledge including supports, loading arrangement
and Labour ).
Rmt 28089.00
Beyond 30m upto 40 m
15
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-59-h
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 53389.00
BW-2-59-i Add 5% of cost for dewatering, if required Rmt 67270.00
BW-2-59-j
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour).
64067.00
Soft rock ( 7m dia well )
BW-2-60 Depth of soft rock strata upto 3m Rmt 13392.00
Hard rock ( 7m dia well )
BW-2-61 Depth upto 3 m Rmt 19719.00
Sinking of 8 m external diameter well ( other than pneumatic method
of sinking ) through all types of strata namely sandy soil, clayey soil
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil
BW-2-62-a Depth below bed level upto 3.0 M Rmt 5893.00
BW-2-62-b Beyond 3m upto 10m depth Rmt 7216.00
Beyond 10m upto 20m
BW-2-62-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 9532.00
Beyond 20m upto 30 m
BW-2-62-d
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 17881.00
BW-2-62-e
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour .
Rmt 21457.00
Beyond 30m upto 40 m
BW-2-62-f
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 6285.00
BW-2-62-g
Add 20% of cost for Kentledge including supports, loading arrangement,
and Labour etc.
Rmt 7543.00
Clayey soil ( 8m dia. Well )
BW-2-63-a Depth upto 3.0 M Rmt 7801.00
BW-2-63-b Beyond 3m upto 10m depth Rmt 10550.00
Beyond 10 m upto 20 m
BW-2-63-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 13933.00
BW-2-63-d Add for dewatering @ 5% of cost, if required. Rmt 14630.00
Beyond 20m upto 30 m
BW-2-63-e
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 26133.00
BW-2-63-f Add 5% of cost for dewatering on the cost, if required Rmt 34299.00
BW-2-63-g
Add 25% of cost for Kentledge including supports, loading arrangement
and Labour ).
Rmt 32666.00
Beyond 30m upto 40 m
BW-2-63-h
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 62088.00
BW-2-63-i Add 5% of cost for dewatering, if required Rmt 78231.00
BW-2-63-j
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour).
Rmt 74505.00
Soft rock ( 8m dia well )
BW-2-64 Depth in soft rock strata upto 3m Rmt 14964.00
Hard rock ( 8m dia well )
BW-2-65 Depth in hard rock strata upto 3 m Rmt 20399.00
16
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Sinking of 9 m external diameter well ( other than pneumatic method
of sinking ) through all types of strata namely sandy soil, clayey soil
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil
BW-2-66-a Depth below bed level upto 3.0 M Rmt 6000.00
BW-2-66-b Beyond 3m upto 10m depth Rmt 7905.00
Beyond 10m upto 20m
BW-2-66-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 10440.00
Beyond 20m upto 30 m
BW-2-66-d
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 19582.00
BW-2-66-e
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour .
Rmt 23498.00
Beyond 30m upto 40 m
BW-2-66-f
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 46522.00
BW-2-66-g
Add 20% of cost for Kentledge including supports, loading arrangement,
and Labour etc.
Rmt 55827.00
Clayey soil ( 9m dia. Well )
BW-2-67-a Depth below bed level upto 3.0 M Rmt 8281.00
BW-2-67-b Beyond 3m upto 10m depth Rmt 11348.00
Beyond 10 m upto 20 m
BW-2-67-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 14987.00
BW-2-67-d Add for dewatering @ 5% of cost, if required. Rmt 15736.00
Beyond 20m upto 30 m
BW-2-67-e
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 28109.00
BW-2-67-f Add 5% of cost for dewatering on the cost, if required Rmt 36894.00
BW-2-67-g
Add 25% of cost for Kentledge including supports, loading arrangement
and Labour ).
Rmt 35137.00
Beyond 30m upto 40 m
BW-2-67-h
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 66781.00
BW-2-67-i Add 5% of cost for dewatering, if required Rmt 84145.00
BW-2-67-j
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour).
Rmt 80138.00
Soft rock ( 9m dia well )
BW-2-68 Depth upto 3m Rmt 18419.00
Hard rock ( 9m dia well )
BW-2-69 Depth of hard rock strata upto 3 m Rmt 23418.00
Sinking of 10 m external diameter well ( other than pneumatic method
of sinking ) through all types of strata namely sandy soil, clayey soil
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil
BW-2-70-a Depth below bed level upto 3.0 M Rmt 7055.00
BW-2-70-b Beyond 3m upto 10m depth Rmt 8397.00
Beyond 10m upto 20m
BW-2-70-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 11090.00
Beyond 20m upto 30 m
17
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-70-d
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 20802.00
BW-2-70-e
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour .
Rmt 24963.00
Beyond 30m upto 40 m
BW-2-70-f
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 49423.00
BW-2-70-g
Add 20% of cost for Kentledge including supports, loading arrangement,
and Labour etc.
Rmt 59308.00
Clayey soil (10m dia. Well )
BW-2-71-a Depth below bed level upto 3.0 M Rmt 9358.00
BW-2-71-b Beyond 3m upto 10m depth Rmt 11483.00
Beyond 10 m upto 20 m
BW-2-71-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 15166.00
BW-2-71-d Add for dewatering @ 5% of cost, if required. Rmt 15924.00
Beyond 20m upto 30 m
BW-2-71-e
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 28447.00
BW-2-71-f Add 5% of cost for dewatering on the cost, if required Rmt 37337.00
BW-2-71-g
Add 25% of cost for Kentledge including supports, loading arrangement
and Labour ).
Rmt 35559.00
Beyond 30m upto 40 m
BW-2-71-h
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 67586.00
BW-2-71-i Add 5% of cost for dewatering, if required Rmt 85159.00
BW-2-71-j
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour).
81104.00
Soft rock (10m dia well )
BW-2-72 Depth of soft rock strata upto 3m Rmt 18728.00
Hard rock (10m dia well )
BW-2-73 Depth of hard rock strata upto 3 m Rmt 25774.00
Sinking of 11 m external diameter well ( other than pneumatic method
of sinking ) through all types of strata namely sandy soil, clayey soil
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil
BW-2-74-a Depth from bed level upto 3.0 M Rmt 15860.00
BW-2-74-b Beyond 3m upto 10m depth Rmt 13687.00
Beyond 10m upto 20m
BW-2-74-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 18078.00
Beyond 20m upto 30 m
BW-2-74-d
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 33910.00
BW-2-74-e
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour .
Rmt 40692.00
Beyond 30m upto 40 m
BW-2-74-f
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 80568.00
BW-2-74-g
Add 20% of cost for Kentledge including supports, loading arrangement,
and Labour etc.
Rmt 96681.00
Clayey soil (11 m dia. Well )
BW-2-75-a Depth from bed level upto 3.0 M Rmt 15624.00
BW-2-75-b Beyond 3m upto 10m depth Rmt 23944.00
18
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Beyond 10 m upto 20 m
BW-2-75-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 31622.00
BW-2-75-d Add for dewatering @ 5% of cost, if required. Rmt 33203.00
Beyond 20m upto 30 m
BW-2-75-e
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 59314.00
BW-2-75-f Add 5% of cost for dewatering on the cost, if required Rmt 77850.00
BW-2-75-g
Add 25% of cost for Kentledge including supports, loading arrangement
and Labour ).
Rmt 74143.00
Beyond 30m upto 40 m
BW-2-75-h
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 140920.00
BW-2-75-i Add 5% of cost for dewatering, if required Rmt 177559.00
BW-2-75-j
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour).
Rmt 169104.00
Soft rock (11m dia well )
BW-2-76 Depth of soft rock strata upto 3m Rmt 41766.00
Hard rock (11m dia well )
BW-2-77 Depth of hard rock upto 3 m Rmt 56986.00
Sinking of 12 m external diameter well ( other than pneumatic method
of sinking ) through all types of strata namely sandy soil, clayey soil
and rock as shown against each case, complete as per drawing and
technical specifications. Depth of sinking is reckoned from bed level.
Sandy soil
BW-2-78-a I) Depth below bed level upto 3.0 M Rmt 33389.00
BW-2-78-b Beyond 3m upto 10m depth Rmt 38426.00
Beyond 10m upto 20m
BW-2-78-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 50748.00
Beyond 20m upto 30 m
BW-2-78-d
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 95189.00
BW-2-78-e
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour .
Rmt 114226.00
Beyond 30m upto 40 m
BW-2-78-f
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 226154.00
BW-2-78-g
Add 20% of cost for Kentledge including supports, loading arrangement,
and Labour etc.
Rmt 271384.00
Clayey soil (12 m dia. Well )
BW-2-79-a Depth below bed level upto 3.0 M Rmt 37933.00
BW-2-79-b Beyond 3m upto 10m depth Rmt 58219.00
Beyond 10 m upto 20 m
BW-2-79-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 76889.00
BW-2-79-d Add for dewatering @ 5% of cost, if required. Rmt 80733.00
Beyond 20m upto 30 m
BW-2-79-e
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 144223.00
BW-2-79-f Add 5% of cost for dewatering on the cost, if required Rmt 189292.00
BW-2-79-g
Add 25% of cost for Kentledge including supports, loading arrangement
and Labour ).
Rmt 180278.00
Beyond 30m upto 40 m
19
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-79-h
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 342652.00
BW-2-79-i Add 5% of cost for dewatering, if required Rmt 431742.00
BW-2-79-j
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour).
Rmt 411183.00
Soft rock (12m dia well )
BW-2-80 Depth of soft rock strata upto 3m Rmt 96500.00
Hard rock (12m dia well )
BW-2-81 Depth of hard rock strata upto 3 m Rmt 125737.00
Sinking of Twin D Type well ( other than pneumatic method of sinking
) through all types of strata namely sandy soil, clayey soil and rock
as shown against each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed level.
Sandy soil
BW-2-82-a Depth from bed level upto 3.0 M Rmt 7501.00
BW-2-82-b Beyond 3m upto 10m depth Rmt 8155.00
Beyond 10m upto 20m
BW-2-82-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 10770.00
Beyond 20m upto 30 m
BW-2-82-d
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 20200.00
BW-2-82-e
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour .
Rmt 24241.00
Beyond 30m upto 40 m
BW-2-82-f
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 47994.00
BW-2-82-g
Add 20% of cost for Kentledge including supports, loading arrangement,
and Labour etc.
Rmt 57593.00
Clayey soil (Twin D Type Well )
BW-2-83-a Depth below bed level upto 3.0 M Rmt 8998.00
BW-2-83-b Beyond 3m upto 10m depth Rmt 12702.00
Beyond 10 m upto 20 m
BW-2-83-c
Add 5% for every additional meter depth of sinking over the rate of sinking
for the previous meter
Rmt 16775.00
BW-2-83-d Add for dewatering @ 5% of cost, if required. Rmt 17614.00
Beyond 20m upto 30 m
BW-2-83-e
Add 7.5% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 31466.00
BW-2-83-f Add 5% of cost for dewatering on the cost, if required Rmt 41299.00
BW-2-83-g
Add 25% of cost for Kentledge including supports, loading arrangement
and Labour ).
Rmt 39332.00
Beyond 30m upto 40 m
BW-2-83-h
Add 10% for every additional meter depth of sinking over the rate of
sinking for the previous meter
Rmt 74759.00
BW-2-83-i Add 5% of cost for dewatering, if required Rmt 94196.00
BW-2-83-j
Add 20% of cost for Kentledge including supports, loading arrangement
and Labour).
Rmt 89710.00
Soft rock (Twin D Type well )
BW-2-84 Depth of soft rock strata upto 3m Rmt 20774.00
Hard rock (Twin D Type well )
BW-2-85 Depth of hard rock strata upto 3 m Rmt 27039.00
20
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-86
Pneumatic sinking of wells with equipment of approved design, drawing
and specifications worked by competent and trained personnel and
comprising of compression and decompression chambers, reducers, two
air locks separately for men and plant & materials, arrangement for supply
of fresh air to working chambers, check valves, exhaust valves, shafts
made from steel plates of riveted construction not less than 6 mm thick to
withstand an air pressure of 0.50 MPa, controlled blasting of hard rock
where required, staircases and 1 m wide landing plate forms with railing,
arrangement for compression and decompression, electric lighting of 50 V
maximum, proper rooms for rest and medical examinations and
compliance with safety precautions as per IS:4138, all as per
clause1207.6 of Specifications.
Cum 95739.00
BW-2-87 Sand filling in wells complete as per drawing and technical specifications Cum 1766.00
BW-2-88
Providing steel liner 10 mm thick for curbs and 6mm thick for steining of
wells including fabricating and setting out as per detailed drawing
MT 76648.00
Providing and placing in position controlled cement concrete in bottom
plug of well foundations in wells or through tremie arrangement including
compacting by vibrators and curing where necessary etc. complete as
specified and directed. (10% extra cement to be added when concreting is
done under water).
PCC Grade M20
BW-2-89-a Using Concrete Mixer Cum 6310.00
BW-2-89-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 6501.00
PCC Grade M25
BW-2-90-a Using Concrete Mixer Cum 6562.00
BW-2-90-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 6706.00
PCC Grade M30
BW-2-91-a Using Concrete Mixer Cum 6606.00
BW-2-91-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 6933.00
PCC Grade M35
BW-2-92-a Using Concrete Mixer Cum 6707.00
BW-2-92-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 7118.00
Providing and placing in position controlled cement concrete in
Intermediate plug of well foundations in wells or through tremie
arrangement including compacting by vibrators and curing where
necessary etc. complete as specified and directed
Grade M20 PCC
BW-2-93-a Using Concrete Mixer Cum 6035.00
BW-2-93-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 6193.00
Grade M25 PCC
BW-2-94-a Using Concrete Mixer Cum 6276.00
BW-2-94-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 6448.00
Grade M30 PCC
BW-2-95-a Using Concrete Mixer Cum 6317.00
BW-2-95-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 6733.00
Providing and placing in position controlled cement concrete in top plug
of well foundations including compacting by vibrators and curing etc.
complete as specified and directed.
Grade M15 PCC
BW-2-96 Using Concrete Mixer Cum 5017.00
Grade M20 PCC
BW-2-97 Using Concrete Mixer Cum 5394.00
21
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Grade M25 PCC
BW-2-98-a Using Concrete Mixer Cum 5775.00
BW-2-98-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 5971.00
Grade M30 PCC
BW-2-99-a Using Concrete Mixer Cum 5817.00
BW-2-99-b Using Batching Plant, Transit Mixer and Crane/concrete pump Cum 6289.00
Providing and placing in position controlled cement concrete in Well cap
RCC Grade M20
BW-2-100-a Using concrete Mixer Cum 5602.00
BW-2-100-b Using Batching Plant, Transit Mixer and Concrete Pump Cum 6019.00
RCC Grade M25
BW-2-101-a Using concrete Mixer Cum 6033.00
BW-2-101-b Using Batching Plant, Transit Mixer and Concrete Pump Cum 6195.00
Providing and placing in positon controlled cement concrete M-30 grade
for RCC well cap with minimum cement content as 400 kg/cum. water
cement ratio not exceeding 0.40 and maximum size of aggregate not
exceeding 20 mm including necessary formwork to give form finish
surface, compacting by vibrators and curing etc. complete as specified and
directed. (Excluding reinforcement)
RCC Grade M30
BW-2-102-a Using Concrete Mixer Cum 6042.00
BW-2-102-b Using Batching Plant, Transit Mixer and Concrete Pump Cum 6509.00
RCC Grade M35
BW-2-103-a Using Concrete Mixer Cum 6122.00
BW-2-103-b Using Batching Plant, Transit Mixer and Concrete Pump Cum 6714.00
RCC M40 Grade
BW-2-104 Using Batching Plant, Transit Mixer and Concrete Pump Cum 7017.00
BW-2-105
Providing and fixing steel anchor dowel bars in open foundations
including drilling holes 75 mm dia. in hard rock, providing and placing in
position 32 mm dia. dowel bars 1.8m in hard rock and 1.8m above hard
rock, effectively grouting the holes with cement mortar of 1:1 proportion etc
complete and specified as directed. (Grout shall be filled in the hole first
and bars inserted and pressed in the drilled hole).
No. 5556.00
BW-2-105
Providing and fixing steel anchor dowel bars at the base of well
foundations through bottom plug including drilling holes 75 mm dia in
hard rock, providing and placing in positon dowel bars of 32 mm dia 1.8 m
in hard rock and 1.8 m above hard rock, effectively grouting the holes with
cement mortar of 1: 1 proportion etc. complete as specified and directed.
(grout shall be filled in the hole first and bars inserted and pressed in
drilled hole.)
No. 9696.00
BW-2-106
Providing and laying colcrete for foundation of piers, abutments,
wingwalls, retaining walls, anchor blocks, thrust blocks etc. for encasing of
pipes in trenches etc. using cement sand colgrout of 1 :1.5 proportion by
weight and water cement ratio not exceeding 0.56 in required lines and
levels including watertight formwork, curing etc. complete as specified and
directed. (Excluding reinforcement)
No. 4149.00
BW-2-107
Supplying, fitting and placing un-coated HYSD bar reinforcement in
foundation complete as per drawing and technical specifications
MT 62100.00
BW-2-108
Supplying, fitting and placing un-coated Mild steel reinforcement complete
in foundation as per drawing and technical specification
MT 61199.00
(E) BASE SLAB
22
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-108
Providing and placing in position controlled cement concrete of M-30 grade
with minimum cement content of 400 kg/cum. and water cement ratio not
exceeding 0.40 in base slab for subways to required lines and levels
including surfaces to be roughen to receive the other finishes etc.
complete as specified and directed.
Cum 6202.00
BW-2-109
Providing and placing in position controlled cement concrete of M-35 grade
with minimum cement content of 400 kg/cum. and water cement ratio not
exceeding 0.40 in base slab for subways to required lines and levels
including surfaces to be roughen to receive the other finishes etc.
complete as specified and directed.
Cum 6547.00
BW-2-110
Providing and placing in position controlled cement concrete of M-45 grade
for foundation work with minimum cement 400 kg/cum and water cement
ratio not exceeding 0.4 for RCC raft foundation slab with V notches
sloped / flat / strip footings, pile caps, tie beams to required lines /
levels including levelling, compacting by vibrators, curing including
shuttering, centering as necessary and required etc. complete as specified
and as directed but excluding reinforcement.(Using Batching Plant, Transit
Mixer and Concrete Pump)
Cum 7197.00
BW-2-111
Providing and placing in position controlled cement concrete of M-50 grade
for foundation work with minimum cement 400 kg/cum and water cement
ratio not exceeding 0.4 for RCC raft foundation slab with V notches
sloped / flat / strip footings, pile caps, tie beams to required lines /
levels including levelling, compacting by vibrators, curing including
shuttering, centering as necessary and required etc. complete as specified
and as directed but excluding reinforcement.(Using Batching Plant, Transit
Mixer and Concrete Pump)
Cum 7756.00
Providing and installing in position controlled concrete of grade M-40 with
minimum cement content as 400 kg/cum. and W.C ratio not exceeding
0.40 for R.C.C work in cast-in-situ bored piles each of load capacity as
per design and of special diameter using maximum 20mm size of
aggregate including boring through all strata except rock, including placing
of concrete by tremie arrangement through mild steel casing to the
required depth through all strata except rock, compaction as necessary
with drawl of mild steel casing including chipping / dressing of piles to
required levels, cleaning the reinforcement etc. complete as specified and
directed (Excluding reinforcement) (Using Batching Plant, Transit Mixer
and Concrete Pump)
BW-2-112-a 1) 400mm dia Rmt 1282.00
BW-2-112-b 2) 450mm dia Rmt 1622.00
BW-2-112-c 3) 500mm dia Rmt 2003.00
BW-2-112-d 4) 550mm dia Rmt 2423.00
BW-2-112-e 5) 600mm dia Rmt 2884.00
BW-2-112-f 6) 650mm dia Rmt 3385.00
BW-2-112-g 7) 700mm dia Rmt 3926.00
BW-2-112-h 8) 750mm dia Rmt 4506.00
BW-2-112-i 9) 800mm dia Rmt 5127.00
BW-2-112-j 10) 900mm dia Rmt 6489.00
BW-2-112-k 11) 1000mm dia Rmt 8011.00
BW-2-112-l 12) 1100mm dia Rmt 9694.00
BW-2-112-m 13) 1200mm dia Rmt 11536.00
23
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-2-113
Providing and laying in position M-15 plain cement concrete to fill up loose
pockets of foundations bed for making required levels, annular filling
around abutments, piers, columns for foundation.
Cum 5218.00
Providing and installing in position controlled concrete of grade M-35 with
minimum cement content as 400 kg/cum. and W.C ratio not exceeding
0.40 for R.C.C work in cast-in-situ bored piles with hydraulic boring
machine including mobilization to the site of work. Each pile shall have
load capacity as per design and of specific diameter using maximum
20mm size of aggregate including boring through all strata including rock,
including placing of concrete by tremie arrangement through mild steel
casing to the required depth. Compaction as necessary with drawl of mild
steel casing including chipping / dressing of piles to required levels,
cleaning the reinforcement etc. complete as specified and directed
(Excluding reinforcement) (Using Batching Plant, Transit Mixer and
Concrete Pump)
BW-2-114-a 1) 400mm dia Rmt 2894.00
BW-2-114-b 2) 450mm dia Rmt 3129.00
BW-2-114-c 3) 500mm dia Rmt 3381.00
BW-2-114-d 4) 550mm dia Rmt 3678.00
BW-2-114-e 5) 600mm dia Rmt 3967.00
BW-2-114-f 6) 650mm dia Rmt 4256.00
BW-2-114-g 7) 700mm dia Rmt 5317.00
BW-2-114-h 8) 750mm dia Rmt 5711.00
BW-2-114-i 9) 800mm dia Rmt 6103.00
BW-2-114-j 10) 900mm dia Rmt 8390.00
BW-2-114-k 11) 1000mm dia Rmt 9430.00
BW-2-114-l 12) 1100mm dia Rmt 10470.00
BW-2-114-m 13) 1200mm dia Rmt 12217.00
Providing and installing in position controlled concrete of grade M-40 with
minimum cement content as 400 kg/cum. and W.C ratio not exceeding
0.40 for R.C.C work in cast-in-situ bored piles with hydraulic boring
machine including mobilization to the site of work. Each pile shall have
load capacity as per design and of specific diameter using maximum
20mm size of aggregate including boring through all strata including rock,
including placing of concrete by tremie arrangement through mild steel
casing to the required depth. Compaction as necessary with drawl of mild
steel casing including chipping / dressing of piles to required levels,
cleaning the reinforcement etc. complete as specified and directed
(Excluding reinforcement) (Using Batching Plant, Transit Mixer and
Concrete Pump)
BW-2-115-a 1) 400mm dia Rmt 2931.00
BW-2-115-b 2) 450mm dia Rmt 3176.00
BW-2-115-c 3) 500mm dia Rmt 3438.00
BW-2-115-d 4) 550mm dia Rmt 3748.00
BW-2-115-e 5) 600mm dia Rmt 4050.00
BW-2-115-f 6) 650mm dia Rmt 4351.00
BW-2-115-g 7) 700mm dia Rmt 5430.00
BW-2-115-h 8) 750mm dia Rmt 5841.00
BW-2-115-i 9) 800mm dia Rmt 6250.00
BW-2-115-j 10) 900mm dia Rmt 8576.00
BW-2-115-k 11) 1000mm dia Rmt 9661.00
BW-2-115-l 12) 1100mm dia Rmt 10747.00
BW-2-115-m 13) 1200mm dia Rmt 12550.00
24
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
SUB-STRUCTURE
BW-3-1
Brick masonry work in 1:3 in sub-structure complete excluding pointing
and plastering, as per drawing and technical specifications
Cum 5748.00
BW-3-2
Pointing with cement mortar (1:3 ) on brick work in substructure as per
Technical specifications
Sqm 713.00
BW-3-3
Plastering with cement mortar (1:3 ) on brick work in sub-structure as per
Technical specifications
Sqm 1581.00
Stone masonry work in cement mortar 1:3 for substructure complete as
per drawing and Technical Specifications
BW-3-4-a Random Rubble Masonry Cum 4696.00
BW-3-4-b Coursed rubble masonry (first sort ) Cum 4831.00
BW-3-4-c Ashlar masonry ( first sort ) Cum 6164.00
Plain/Reinforced cement concrete in sub-structure complete as per
drawing and technical specifications
BW-3-5 PCC Grade M15
Height upto 5m Cum 5519.00
Providing and laying cement concrete in abutment and piers, head walls
for culverts, using max aggregate size of 40mm minimum cement content
of 310Kg and max water cement ratio of 0.45 including shuttering and
scaffolding complete as specified and directed. the rate including providing
100 dia AC weep holes at 1.5m c/c vertical and horizontal above ground
level wherever required( The abutment and piers shall be cast for only
1.0m height at a time)
PCC Grade M20
BW-3-6 Height upto 5m Cum 5933.00
PCC Grade M25
Height upto 5m
BW-3-7-a Using concrete Mixer Cum 6353.00
BW-3-7-b With Batching Plant, Transit Mixer and Concrete Pump Cum 6568.00
Height 5m to 10m
BW-3-7-c Using concrete Mixer Cum 6584.00
BW-3-7-d With Batching Plant, Transit Mixer and Concrete Pump Cum 6807.00
Height above 10m
BW-3-7-e Using concrete Mixer Cum 6873.00
BW-3-7-f With Batching Plant, Transit Mixer and Concrete Pump Cum 7105.00
PCC Grade M30
Height upto 5m
BW-3-8-a Using concrete Mixer Cum 6398.00
BW-3-8-b With Batching Plant, Transit Mixer and Concrete Pump Cum 6918.00
Height 5m to 10m
BW-3-8-c Using concrete Mixer Cum 6631.00
BW-3-8-d With Batching Plant, Transit Mixer and Concrete Pump Cum 7170.00
Height above 10m
BW-3-8-e Using concrete Mixer Cum 6922.00
BW-3-8-f With Batching Plant, Transit Mixer and Concrete Pump Cum 7484.00
BW-3-9
Providing and placing in position not more than 1.5m height at one time
controlled cement concrete M-30 grade using minimum cement content as
400Kg/cum and max water cement ratio of 0.40 for RCC work in
abutmens, retaining walls with form finished surface as perdrg. in
required line and level including levelling, compacting by vibrators, curing
including formwork including providing and forming 100 dia AC weep holes
at 1.5m c/c vertically and horizontally in a staggered fashion above ground
level as necessary etc. complete as specified and directed.
Cum 6852.00
25
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-3-10
Providing and placing in position not more than 1.5m height at one time
controlled cement concrete M-35 grade using minimum cement content as
400Kg/cum and max water cement ratio of 0.40 for RCC work in
abutmens, retaining walls with form finished surface as per drawing in
required line and level including levelling, compacting by vibrators, curing
including formwork including providing and forming 100 dia AC weep holes
at 1.5m c/c vertically and horizontally in a staggered fashion above ground
level as necessary etc. complete as specified and directed.
Cum 7197.00
BW-3-11
Providing weep holes in Brick masonry/Plain/Reinforced concrete
abutment, wing wall/return wall with 100 mm dia AC pipe, extending
through the full width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical specifications
Each 278.00
Providing and Placing in position controlled cement concrete for sub-
structure work with minimum cement content of 400 kg/cum and water
cement ratio not exceeding 0.40 for columns pier shafts, abutments, walls
of subways retaining walls to required lines as necessary etc. complete as
directed.
RCC Grade M20
Height upto 5m
BW-3-12-a Using concrete Mixer Cum 5972.00
BW-3-12-b With Batching Plant, Transit Mixer and Concrete Pump Cum 6367.00
Height 5m to 10m
BW-3-12-c Using concrete Mixer Cum 6189.00
BW-3-12-d With Batching Plant, Transit Mixer and Concrete Pump Cum 6598.00
Height above 10m
BW-3-12-e Using concrete Mixer Cum 6461.00
BW-3-12-f With Batching Plant, Transit Mixer and Concrete Pump Cum 6888.00
RCC Grade M25
Height upto 5m
BW-3-13-a Using concrete Mixer Cum 6397.00
BW-3-13-b With Batching Plant, Transit Mixer and Concrete Pump Cum 6634.00
Height 5m to 10m
BW-3-13-c Using concrete Mixer Cum 6606.00
BW-3-13-d With Batching Plant, Transit Mixer and Concrete Pump Cum 6851.00
Height above 10m
BW-3-13-e Using concrete Mixer Cum 6921.00
BW-3-13-f With Batching Plant, Transit Mixer and Concrete Pump Cum 7176.00
RCC Grade M30
Height upto 5m
BW-3-14-a Using concrete Mixer Cum 6422.00
BW-3-14-b With Batching Plant, Transit Mixer and Concrete Pump Cum 6987.00
Height 5m to 10m
BW-3-14-c Using concrete Mixer Cum 6603.00
BW-3-14-d With Batching Plant, Transit Mixer and Concrete Pump Cum 7184.00
Height above 10m
BW-3-14-e Using concrete Mixer Cum 6860.00
BW-3-14-f With Batching Plant, Transit Mixer and Concrete Pump Cum 7464.00
RCC Grade M35
Height upto 5m
BW-3-15-a Using concrete Mixer Cum 6539.00
BW-3-15-b With Batching Plant, Transit Mixer and Concrete Pump Cum 7170.00
Height 5m to 10m
BW-3-15-c Using concrete Mixer Cum 6681.00
BW-3-15-d With Batching Plant, Transit Mixer and Concrete Pump Cum 7326.00
26
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Height above 10m
BW-3-15-e Using concrete Mixer Cum 6895.00
BW-3-15-f With Batching Plant, Transit Mixer and Concrete Pump Cum 7561.00
BW-3-16
Providing and placing in position controlled cement concrete M-30 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work in coping on retaining walls, bed blocks,
abutment / pier / column caps, dirtwalls, pedestals for bearing on
piers / abutments as per drawings and designs including projections,
moulding, champhers etc. of required shape and size including levelling,
compacting by vibrators, curing, finishing the exposed surfaces including
formwork, shuttering and centering as necessary and required etc.
complete as specified and directed but excluding reinforcement.
Cum 6678.00
BW-3-17
Providing and placing in position controlled cement concrete M-35 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work in coping on retaining walls, bed blocks,
abutment / pier / column caps, dirtwalls, pedestals for bearing on
piers / abutments as per drawings and designs including projections,
moulding, champhers etc. of required shape and size including levelling,
compacting by vibrators, curing, finishing the exposed surfaces including
formwork, shuttering and centering as necessary and required etc.
complete as specified and directed but excluding reinforcement.
Cum 6796.00
BW-3-18
Supplying, fitting and placing HYSD bar reinforcement in sub-structure
complete as per drawing and technical specifications
MT 62235.00
BW-3-19
Supplying, fitting and placing Mild steel reinforcement complete in sub-
structure as per drawing and technical specification
MT 60414.00
Back filling behind abutment, wing wall and return wall complete as per
drawing and Technical specification
BW-3-20-a Granular material Cum 826.00
BW-3-20-b Sandy material Cum 1930.00
BW-3-21
Providing and laying of Filter media with granular materials/stone crushed
aggregates satisfying the requirements laid down in clause 2504.2.2. of
MoRTH specifications to a thickness of not less than 600 mm with smaller
size towards the soil and bigger size towards the wall and provided over
the entire surface behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per drawing and
technical specification.
Cum 1109.00
BEARINGS
Note: The bearings shall be duly got tested and certified by an approved
agency to the satisfaction of the Engineer. Testing may be carried out
during the manufacturing and/or before their installation as may be
directed by the Engineer. All charges or expences incurred in this respect
shall be born by the contractor. the bearing shall be fixed perfectly in
horizontal position.
BW-3-22
Supplying, fitting and fixing in position true to line and level sliding plate
bearing with PTFE surface sliding on stainless steel complete including all
accessories as per drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH Specifications.
MT
capacity
378.00
27
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-3-23
Supplying, fitting and fixing in position true to line and level POT-PTFE
bearing consisting of a metal piston supported by a disc or unreinforced
elastomer confined within a metal cylinder, sealing rings, dust seals,
PTFE surface sliding against stainless steel mating surface, completre
assembly to be of cast steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I & II respectively and other
parts conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of
MoRTH Specifications complete asper drawing and approved technical
specifications.
MT
capacity
259.00
BW-3-24
Supplying, fitting and fixing in position true to line and level sliding plate
bearing with stainless steel plate sliding on stainless steel plate with mild
steel matrix complete including all accessories as per drawing and
Technical Specifications.
MT
capacity
365.00
BW-3-25
Supplying, fitting and fixing in position true to line and level elastomeric
bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of
MoRTH specifications complete including all accessories as per drawing
and Technical Specifications.
Cucm 1.00
BW-3-26
Providing and placing in position not more than 1.5m height at one time
controlled cement concrete M-40 grade using minimum cement content as
400Kg/cum and max water cement ratio of 0.40 for RCC work in
abutmens, retaining walls with form finished surface as per drawing in
required line and level including levelling, compacting by vibrators, curing
including formwork including providing and forming 100 dia AC weep holes
at 1.5m c/c vertically and horizontally in a staggered fashion above ground
level as necessary etc. complete as specified and directed.(Using Batching
Plant, Transit Mixer and Concrete Pump)
Cum 7834.00
BW-3-27
Providing and placing in position controlled cement concrete M-40 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work in coping on retaining walls, bed blocks,
abutment / pier / column caps, dirtwalls, pedestals for bearing on
piers / abutments as per drawings and designs including projections,
moulding, champhers etc. of required shape and size including levelling,
compacting by vibrators, curing, finishing the exposed surfaces including
formwork, shuttering and centering as necessary and required etc.
complete as specified and directed but excluding reinforcement.
Cum 7494.00
BW-3-28
Supplying, fitting and fixing in position true to line and level cast steel
rocker bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of
MoRTH specifications complete including all accessories as per drawing
and Technical Specifications.
MT 143.00
BW-3-29
Supplying, fitting and fixing in position true to line and level forged steel
roller bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of
MoRTH specifications complete including all accessories as per drawing
and Technical Specifications.
MT 143.00
SUPER-STRUCTURE
(I) RCC
Furnishing and Placing Reinforced/Prestressed cement concrete in super-
structure as per drawing and Technical Specification
28
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and placing in position controlled cement concrete, max water
cement ratio of 0.40 for RCC work of main beams, girders, cross
girders, diaphragm solid slab to required lines and levels including
levelling, compacting by vibrators, curing including formwork with
formfinish surface as necessary and required centering etc.complete as
specified and directed but excluding reinforcement.
RCC Grade M20
Using Concrete Mixer
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-1-a Height upto 5m Cum 6464.00
BW-4-1-b Height 5m to 10m Cum 6734.00
BW-4-1-c Height above 10m Cum 7003.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-2-a Height upto 5m Cum 6734.00
BW-4-2-b Height 5m to 10m Cum 7003.00
BW-4-2-c Height above 10m Cum 7272.00
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-3-a Height upto 5m Cum 6946.00
BW-4-3-b Height 5m to 10m Cum 7235.00
BW-4-3-c Height above 10m Cum 7524.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-4-a Height upto 5m Cum 7235.00
BW-4-4-b Height 5m to 10m Cum 7524.00
BW-4-4-c Height above 10m Cum 7814.00
RCC Grade M25
Using Concrete Mixer
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-5-a Height upto 5m Cum 6945.00
BW-4-5-b Height 5m to 10m Cum 7234.00
BW-4-5-c Height above 10m Cum 7523.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-6-a Height upto 5m Cum 7234.00
BW-4-6-b Height 5m to 10m Cum 7523.00
BW-4-6-c Height above 10m Cum 7813.00
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-7-a Height upto 5m Cum 7165.00
BW-4-7-b Height 5m to 10m Cum 7464.00
BW-4-7-c Height above 10m Cum 7762.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-8-a Height upto 5m Cum 7464.00
BW-4-8-b Height 5m to 10m Cum 7762.00
BW-4-8-c Height above 10m Cum 8061.00
Providing and placing in position controlled cement concrete of M-30 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work of main beams, girders, cross girders,
diaphragm solid slab to required lines and levels including levelling,
compacting by vibrators, curing including formwork with formfinish surface
as necessary and required centering etc.complete as specified and
directed but excluding reinforcement.(using concrete mixer).
RCC Grade M 30
Using Concrete Mixer
29
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-9-a Height upto 5m Cum 7005.00
BW-4-9-b Height 5m to 10m Cum 7297.00
BW-4-9-c Height above 10m Cum 7589.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-10-a Height upto 5m Cum 7297.00
BW-4-10-b Height 5m to 10m Cum 7589.00
BW-4-10-c Height above 10m Cum 7881.00
Providing and placing in position controlled cement concrete of M-35 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work of main beams, girders, cross girders,
diaphragm solid slab to required lines and levels including levelling,
compacting by vibrators, curing including formwork with formfinish surface
as necessary and required centering etc.complete as specified and
directed but excluding reinforcement.(using concrete mixer).
RCC/PSC Grade M35
Using concrete mixer.
For solid slab super-structure, 18-28% of (a+b+c)
BW-4-11-a Height upto 5m Cum 7013.00
BW-4-11-b Height 5m to 10m Cum 7311.00
BW-4-11-c Height above 10m Cum 7608.00
For T-beam & slab, 23-33% of (a+b+c)
BW-4-12-a Height upto 5m Cum 7311.00
BW-4-12-b Height 5m to 10m Cum 7608.00
BW-4-12-c Height above 10m Cum 7905.00
For box girder and balanced cantilever, 38-58% of cost of concrete.
BW-4-13-a Height upto 5m Cum 8202.00
BW-4-13-b Height 5m to 10m Cum 8797.00
BW-4-13-c Height above 10m Cum 9391.00
Providing and placing in position controlled cement concrete of M-40 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work of main beams, girders, cross girders,
diaphragm solid slab to required lines and levels including levelling,
compacting by vibrators, curing including formwork with formfinish surface
as necessary and required centering etc.complete as specified and
directed but excluding reinforcement.(using concrete mixer).
PSC Grade M-40
Using concrete mixer.
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-14-a Height upto 5m Cum 7590.00
BW-4-14-b Height 5m to 10m Cum 7906.00
BW-4-14-c Height above 10m Cum 8223.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-15-a Height upto 5m Cum 7906.00
BW-4-15-b Height 5m to 10m Cum 8223.00
BW-4-15-c Height above 10m Cum 8539.00
30
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and placing in position controlled cement concrete of M-30 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work of main beams, girders, cross girders,
diaphragm solid slab to required lines and levels including levelling,
compacting by vibrators, curing including formwork with formfinish surface
as necessary and required centering etc.complete as specified and
directed but excluding reinforcement.(using batch mixing plant).
RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-16-a Height upto 5m Cum 7547.00
BW-4-16-b Height 5m to 10m Cum 7862.00
BW-4-16-c Height above 10m Cum 8176.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-17-a Height upto 5m Cum 7862.00
BW-4-17-b Height 5m to 10m Cum 8176.00
BW-4-17-c Height above 10m Cum 8491.00
Providing and placing in position controlled cement concrete of M-35 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work of main beams, girders, cross girders,
diaphragm solid slab to required lines and levels including levelling,
compacting by vibrators, curing including formwork with formfinish surface
as necessary and required centering etc.complete as specified and
directed but excluding reinforcement.(using batch mixing plant).
RCC/PSC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 18-28% of (a+b+c)
BW-4-18-a Height upto 5m Cum 7691.00
BW-4-18-b Height 5m to 10m Cum 8017.00
BW-4-18-c Height above 10m Cum 8343.00
For T-beam & slab, 23-33% of (a+b+c)
BW-4-19-a Height upto 5m Cum 8017.00
BW-4-19-b Height 5m to 10m Cum 8343.00
BW-4-19-c Height above 10m Cum 8669.00
For box girder and balanced cantilever, 38-58% of cost of concrete.
BW-4-20-a Height upto 5m Cum 8995.00
BW-4-20-b Height 5m to 10m Cum 9647.00
BW-4-20-c Height above 10m Cum 10299.00
Providing and placing in position controlled cement concrete of M-40 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC work of main beams, girders, cross girders,
diaphragm solid slab to required lines and levels including levelling,
compacting by vibrators, curing including formwork with formfinish surface
as necessary and required centering etc.complete as specified and
directed but excluding reinforcement.(using batch mixing plant).
Grade M-40
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 18-28% of (a+b+c)
BW-4-21-a Height upto 5m Cum 8039.00
BW-4-21-b Height 5m to 10m Cum 8379.00
BW-4-21-c Height above 10m Cum 8720.00
31
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
For T-beam & slab, 23-33% of (a+b+c)
BW-4-22-a Height upto 5m Cum 8379.00
BW-4-22-b Height 5m to 10m Cum 8720.00
BW-4-22-c Height above 10m Cum 9061.00
For box girder and balanced cantilever, 38-58% of cost of concrete.
BW-4-23-a Height upto 5m Cum 9401.00
BW-4-23-b Height 5m to 10m Cum 10083.00
BW-4-23-c Height above 10m Cum 10764.00
BW-4-25
Providing and placing in position controlled cement concrete of M-30 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 in cast-in-situ RCC Kerbs in line and level and shape as per
drawings, finishing the exposed faces including levelling, compacting by
vibrators, curing including formwork, shuttering as necessary and required
centering etc.complete as specified and directed
Cum 6980.00
BW-4-26
Providing and placing in position controlled cement concrete of M-30 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 in RCC Approach Slab over / Beyond abutments as per drawings
and designs, including levelling, compacting by vibrators, curing including
formwork etc. complete as specified and directed but excluding
reinforcement.
Cum 6108.00
BW-4-27
Reinforced cement concrete approach slab including reinforcement and
formwork complete as per drawing and Technical specification
Cum 6241.00
BW-4-28
Providing and placing in position controlled cement concrete of M-35 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 in RCC Approach Slab over / Beyond abutments as per drawings
and designs, including levelling, compacting by vibrators, curing including
formwork etc. complete as specified and directed but excluding
reinforcement.
Cum 6241.00
Providing and placing in position controlled cement concrete of M-30 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for cast-in-situ portions after launching girders of RCC Deck Slab,
cross diaphragms to required lines and levels including levelling,
compacting by vibrators, curing including formwork, temporary supports as
necessary and required etc.complete as specified and directed but
excluding reinforcement.(using batch mixing plant).
M 30 Grade
Using Batching Plant, Transit Mixer and Concrete Pump.
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-29-a Height upto 5m Cum 7547.00
BW-4-29-b Height 5m to 10m Cum 7862.00
BW-4-29-c Height above 10m Cum 8176.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-30-a Height upto 5m Cum 7862.00
BW-4-30-b Height 5m to 10m Cum 8176.00
BW-4-30-c Height above 10m Cum 8491.00
32
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and placing in position controlled cement concrete of M-35 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for cast-in-situ portions after launching girders of RCC Deck Slab,
cross diaphragms to required lines and levels including levelling,
compacting by vibrators, curing including formwork, temporary supports as
necessary and required etc.complete as specified and directed but
excluding reinforcement.(Using Batching Plant, Transit Mixer and
Concrete Pump).
RCC/PSC Grade M35
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 18-28% of (a+b+c)
BW-4-31-a Height upto 5m Cum 7691.00
BW-4-31-b Height 5m to 10m Cum 8017.00
BW-4-31-c Height above 10m Cum 8343.00
For T-beam & slab, 23-33% of (a+b+c)
BW-4-32-a Height upto 5m Cum 8017.00
BW-4-32-b Height 5m to 10m Cum 8343.00
BW-4-32-c Height above 10m Cum 8669.00
For box girder and balanced cantilever, 38-58% of cost of concrete.
BW-4-33-a Height upto 5m Cum 8995.00
BW-4-33-b Height 5m to 10m Cum 9647.00
BW-4-33-c Height above 10m Cum 10299.00
Providing and placing in position controlled cement concrete of M-40 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for cast-in-situ portions after launching girders of RCC Deck Slab,
cross diaphragms to required lines and levels including levelling,
compacting by vibrators, curing including formwork, temporary supports as
necessary and required etc.complete as specified and directed but
excluding reinforcement.(using batch mixing plant).
PSC Grade M-40
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 18-28% of (a+b+c)
BW-4-34-a Height upto 5m Cum 8039.00
BW-4-34-b Height 5m to 10m Cum 8379.00
BW-4-34-c Height above 10m Cum 8720.00
For T-beam & slab, 23-33% of (a+b+c)
BW-4-35-a Height upto 5m Cum 8379.00
BW-4-35-b Height 5m to 10m Cum 8720.00
BW-4-35-c Height above 10m Cum 9061.00
For box girder and balanced cantilever, 38-58% of cost of concrete.
BW-4-36-a Height upto 5m Cum 9401.00
BW-4-36-b Height 5m to 10m Cum 10083.00
BW-4-36-c Height above 10m Cum 10764.00
(II) PRECAST & PRESTRESSED CONCRETE
33
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and placing in position controlled cement concrete of M-35 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC Precast Girders and Diaphragms with form finish
surface in any shape and size as per detailed drawings and designs
including formwork, temporary supports as necessary and required,
compacting by vibrators, levelling, curing and finishing etc.complete as
specified and directed but excluding reinforcement and placing in
position.(using concrete mixer).
RCC/PSC Grade M35
Using concrete mixer.
For solid slab super-structure, 18-28% of (a+b+c)
BW-4-37-a Height upto 5m Cum 7041.00
BW-4-37-b Height 5m to 10m Cum 7339.00
BW-4-37-c Height above 10m Cum 7637.00
For T-beam & slab, 23-33% of (a+b+c)
BW-4-38-a Height upto 5m Cum 7339.00
BW-4-38-b Height 5m to 10m Cum 7637.00
BW-4-38-c Height above 10m Cum 7936.00
For box girder and balanced cantilever, 38-58% of cost of concrete.
BW-4-39-a Height upto 5m Cum 8234.00
BW-4-39-b Height 5m to 10m Cum 8831.00
BW-4-39-c Height above 10m Cum 9427.00
Providing and placing in position controlled cement concrete of M-40 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC Precast Girders and Diaphragms with form finish
surface in any shape and size as per detailed drawings and designs
including formwork, temporary supports as necessary and required,
compacting by vibrators, levelling, curing and finishing etc.complete as
specified and directed but excluding reinforcement and placing in
position.(using concrete mixer).
PSC Grade M-40
Using concrete mixer.
For solid slab super-structure, 20-30% of (a+b+c)
BW-4-40-a Height upto 5m Cum 7691.00
BW-4-40-b Height 5m to 10m Cum 8012.00
BW-4-40-c Height above 10m Cum 8332.00
For T-beam & slab, 25-35% of (a+b+c)
BW-4-41-a Height upto 5m Cum 8012.00
BW-4-41-b Height 5m to 10m Cum 8332.00
BW-4-41-c Height above 10m Cum 8653.00
Providing and placing in position controlled cement concrete of M-40 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for Prestressed Concrete Girders as per detailed drawings and
designs having form finish surfaces including formwork on casting bed and
temporary supports as necessary and required, compacting by vibrators,
levelling, curing and finishing etc.complete as specified and directed
including launching the girders in position using plant and equipment and
providing erecting and removing the temporary staging as necessary and
required etc. complete as specified and directed excluding reinforcement
and placing in position.(using concrete mixer).
PSC Grade M-40
Using concrete mixer.
For T-beam & slab, 25-35% of (a+b+c)
34
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-4-42-a Height upto 5m Cum 8730.00
BW-4-42-b Height 5m to 10m Cum 9363.00
BW-4-42-c Height above 10m Cum 9995.00
Providing and placing in position controlled cement concrete of M-45 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for Prestressed Concrete Girders as per detailed drawings and
designs having form finish surfaces including formwork on casting bed and
temporary supports as necessary and required, compacting by vibrators,
levelling, curing and finishing etc.complete as specified and directed
including launching the girders in position using plant and equipment and
providing erecting and removing the temporary staging as necessary and
required etc. complete as specified and directed excluding reinforcement
and placing in position.(using concrete mixer).
PSC Grade M-45
For I-beam & slab including launching of precast girders by launching
truss upto 40 m span, 21-31% of cost of concrete.
BW-4-43-a Height upto 5m Cum 7979.00
BW-4-43-b Height 5m to 10m Cum 8309.00
BW-4-43-c Height above 10m Cum 8638.00
For cast-in-situ box girder, segmental construction and balanced
cantilever, 36-56% of cost of concrete.
BW-4-44-a Height upto 5m Cum 8968.00
BW-4-44-b Height 5m to 10m Cum 9627.00
BW-4-44-c Height above 10m Cum 10287.00
Providing and placing in position controlled cement concrete of M-40 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for Prestressed Concrete Girders as per detailed drawings and
designs having form finish surfaces including formwork on casting bed and
temporary supports as necessary and required, compacting by vibrators,
levelling, curing and finishing etc.complete as specified and directed
including launching the girders in position using plant and equipment and
providing erecting and removing the temporary staging as necessary and
required etc. complete as specified and directed excluding reinforcement
and placing in position.(Using Batching Plant, Transit Mixer and
Concrete Pump).
M-40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump
For solid slab super-structure, 18-28% of (a+b+c)
BW-4-45-a Height upto 5m Cum 8039.00
BW-4-45-b Height 5m to 10m Cum 8379.00
BW-4-45-c Height above 10m Cum 8720.00
For T-beam & slab, 23-33% of (a+b+c)
BW-4-46-a Height upto 5m Cum 8379.00
BW-4-46-b Height 5m to 10m Cum 8720.00
BW-4-46-c Height above 10m Cum 9061.00
For box girder and balanced cantilever, 38-58% of cost of concrete.
BW-4-47-a Height upto 5m Cum 9401.00
BW-4-47-b Height 5m to 10m Cum 10083.00
BW-4-47-c Height above 10m Cum 10764.00
35
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and placing in position controlled cement concrete of M-45 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for Prestressed Concrete Girders as per detailed drawings and
designs having form finish surfaces including formwork on casting bed and
temporary supports as necessary and required, compacting by vibrators,
levelling, curing and finishing etc.complete as specified and directed
including launching the girders in position using plant and equipment and
providing erecting and removing the temporary staging as necessary and
required etc. complete as specified and directed excluding reinforcement
and placing in position.(Using Batching Plant, Transit Mixer and
Concrete Pump).
PSC Grade M-45
For solid slab/voided slab super-structure, 16-26% of cost of
concrete (a+b+c)
BW-4-48-a Height upto 5m Cum 8105.00
BW-4-48-b Height 5m to 10m Cum 8455.00
BW-4-48-c Height above 10m Cum 8804.00
For I-beam & slab including launching of precast girders by launching
truss upto 40 m span, 21-31% of cost of concrete.
BW-4-49-a Height upto 5m Cum 8455.00
BW-4-49-b Height 5m to 10m Cum 8804.00
BW-4-49-c Height above 10m Cum 9153.00
For cast-in-situ box girder, segmental construction and balanced
cantilever, 36-56% of cost of concrete.
BW-4-50-a Height upto 5m Cum 9503.00
BW-4-50-b Height 5m to 10m Cum 10202.00
BW-4-50-c Height above 10m Cum 10900.00
(IV) ANTI-CRASH BARRIER - REINFORCEMENT,
PRESTRESSING
Reinforced Cement Concrete Crash Barrier
BW-4-51
Provision of an Reinforced cement concrete crash barrier at the edges of
the road, approaches to bridge structures and medians, constructed with
M-20 grade concrete with HYSD reinforcement conforming to IRC:21 and
dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-
moulded asphalt filler board, keyed to the structure on which it is built and
installed as per design given in the enclosure to MOST circular No.
RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the
approved drawing and at locations directed by the Engineer, all as
specified
Rmt 3446.00
Type - A, "W" : Metal Beam Crash Barrier
BW-4-52
Providing and erecting a "W" metal beam crash barrier comprising of 3 mm
thick corrugated sheet metal beam rail, 70 cm above road/ground level,
fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced 2 m
centre to centre, 1.8 m high, 1.1 m below ground/road level, all steel parts
and fitments to be galvanised by hot dip process, all fittings to conform to
IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a
spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per
clause 810
Rmt 2841.00
Type - B, "THRIE" : Metal Beam Crash Barrier
36
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-4-53
Providing and erecting a "Thrie" metal beam crash barrier comprising of 3
mm thick corrugated sheet metal beam rail, 85 cm above road/ground
level, fixed on ISMC series channel vertical post, 150 x 75 x 5 mm spaced
2 m centre to centre, 2 m high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip process, all fittings to
conform to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical
post with a space of channel section 150 x 75 x 5 mm, 546 mm long
complete as per clause 810
Rmt 3359.00
BW-4-54
Supplying, fitting and placing HYSD bar reinforcement in super-structure
complete as per drawing and technical specifications
MT 63413.00
BW-4-55
High tensile steel wires/strands including all accessories for stressing,
stressing operations and grouting complete as per drawing and Technical
Specifications
MT 193785.00
BW-4-56
Providing and placing in position controlled cement concrete of M-40 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 in RCC Approach Slab over / Beyond abutments as per drawings
and designs, including levelling, compacting by vibrators, curing including
formwork etc. complete as specified and directed but excluding
reinforcement.
Cum 6813.00
BW-4-57
Reinforced cement concrete approach slab including reinforcement and
formwork complete as per drawing and Technical specification
Cum 9879.00
BW-4-58
PCC M15 Grade leveling course below approach slab complete as per
drawing and Technical specification
Cum 5017.00
Providing and placing in position controlled cement concrete of M-45 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC Precast Girders and Diaphragms with form finish
surface in any shape and size as per detailed drawings and designs
including formwork, temporary supports as necessary and required,
compacting by vibrators, levelling, curing and finishing etc.complete as
specified and directed but excluding reinforcement and placing in
position.(using concrete mixer).
RCC Grade M-45
For solid slab/voided slab super-structure, 16-26% of cost of
concrete (a+b+c)
BW-4-59-a Height upto 5m Cum 7649.00
BW-4-59-b Height 5m to 10m Cum 7979.00
BW-4-59-c Height above 10m Cum 8309.00
For I-beam & slab including launching of precast girders by launching
truss upto 40 m span, 21-31% of cost of concrete.
BW-4-60-a Height upto 5m Cum 7979.00
BW-4-60-b Height 5m to 10m Cum 8309.00
BW-4-60-c Height above 10m Cum 8638.00
For cast-in-situ box girder, segmental construction and balanced
cantilever, 36-56% of cost of concrete.
BW-4-61-a Height upto 5m Cum 8968.00
BW-4-61-b Height 5m to 10m Cum 9627.00
BW-4-61-c Height above 10m Cum 10287.00
Providing and placing in position controlled cement concrete of M-50 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for RCC Precast Girders and Diaphragms with form finish
surface in any shape and size as per detailed drawings and designs
including formwork, temporary supports as necessary and required,
compacting by vibrators, levelling, curing and finishing etc.complete as
specified and directed but excluding reinforcement and placing in
position.(using concrete mixer).
37
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
RCC Grade M-50
For cast-in-situ box girder, segmental construction and balanced
cantilever, 35-55% of cost of concrete
BW-4-62-a Height upto 5m Cum 9160.00
BW-4-62-b Height 5m to 10m Cum 9838.00
BW-4-62-c Height above 10m Cum 10517.00
Providing and placing in position controlled cement concrete of M-50 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for Prestressed Concrete Girders as per detailed drawings and
designs having form finish surfaces including formwork on casting bed and
temporary supports as necessary and required, compacting by vibrators,
levelling, curing and finishing etc.complete as specified and directed
including launching the girders in position using plant and equipment and
providing erecting and removing the temporary staging as necessary and
required etc. complete as specified and directed excluding reinforcement
and placing in position.(using batch mixing plant).
PSC Grade M-50
For cast-in-situ box girder, segmental construction and balanced
cantilever, 35-55% of cost of concrete
BW-4-63-a Height upto 5m Cum 10166.00
BW-4-63-b Height 5m to 10m Cum 10919.00
BW-4-63-c Height above 10m Cum 11672.00
Providing and placing in position controlled cement concrete of M-45 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for cast-in-situ portions after launching girders of RCC Deck Slab,
cross diaphragms to required lines and levels including levelling,
compacting by vibrators, curing including formwork, temporary supports as
necessary and required etc.complete as specified and directed but
excluding reinforcement.(using batch mixing plant).
PSC Grade M-45
For solid slab/voided slab super-structure, 16-26% of cost of
concrete (a+b+c)
BW-4-64-a Height upto 5m Cum 8105.00
BW-4-64-b Height 5m to 10m Cum 8455.00
BW-4-64-c Height above 10m Cum 8804.00
For I-beam & slab including launching of precast girders by launching
truss upto 40 m span, 21-31% of cost of concrete.
BW-4-65-a Height upto 5m Cum 8455.00
BW-4-65-b Height 5m to 10m Cum 8804.00
BW-4-65-c Height above 10m Cum 9153.00
For cast-in-situ box girder, segmental construction and balanced
cantilever, 36-56% of cost of concrete.
BW-4-66-a Height upto 5m Cum 9503.00
BW-4-66-b Height 5m to 10m Cum 10202.00
BW-4-66-c Height above 10m Cum 10900.00
38
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and placing in position controlled cement concrete of M-50 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for cast-in-situ portions after launching girders of RCC Deck Slab,
cross diaphragms to required lines and levels including levelling,
compacting by vibrators, curing including formwork, temporary supports as
necessary and required etc.complete as specified and directed but
excluding reinforcement.(Using Batching Plant, Transit Mixer and
Concrete Pump).
PSC Grade M-50
For cast-in-situ box girder, segmental construction and balanced
cantilever, 35-55% of cost of concrete
BW-4-67-a Height upto 5m Cum 10166.00
BW-4-67-b Height 5m to 10m Cum 10919.00
BW-4-67-c Height above 10m Cum 11672.00
Providing and placing in position controlled cement concrete of M-55 grade
using minimum cement content as 400Kg/cum and max water cement ratio
of 0.40 for cast-in-situ portions after launching girders of RCC Deck Slab,
cross diaphragms to required lines and levels including levelling,
compacting by vibrators, curing including formwork, temporary supports as
necessary and required etc.complete as specified and directed but
excluding reinforcement.(Using Batching Plant, Transit Mixer and
Concrete Pump).
For cast-in-situ box girder, segmental construction and balanced
cantilever, 35-55% of cost of concrete
BW-4-68-a Height upto 5m Cum 10567.00
BW-4-68-b Height 5m to 10m Cum 11350.00
BW-4-68-c Height above 10m Cum 12133.00
BW-4-69
Providing and laying Cement concrete wearing coat M-30 grade including
reinforcement complete as per drawing and Technical Specifications
Cum 11440.00
BW-4-70
Precast - pretensioned Girders (Providing, precasting, transportation and
placing in position precast pretensioned concrete girders as per drawing
and technical specifications)
Cum 23650.00
BW-4-71 Providing and fixing Helical pipes in voided concrete slabs Rmt 622.00
BW-4-72
Painting on concrete surface (Providing and applying 2 coats of water
based cement paint to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and applying paint @ of 1
litre for 2 Sq.m. )
Rmt 55.00
MISCELLANEOUS ITEMS
(I) EXPANSION JOINT & DRAINAGE SPOUT
BW-5-1-a
Providing and fixing in position expansion joints with plain premoulded
bituminuous filler 25 mm thick including fixing 10 gauge moulded
galvanised iron sheet 38 cm wide etc.complete as specified and directed.
Rmt 970.00
BW-5-1-b
Providing and fixing expansion joint in carriageway with 1.4 mm thick
copper plate, 25 mm thick polysulphide sealant and polysterine as shown
in the drawing including fixing the copper plate to the deck slab with 5 mm
counter sunk bronze screws 75 mm long at 300 mm c/c in two stagered
layers etc. complete and as directed.
Rmt 3672.00
Filler joint
BW-5-1-c
Providing & fixing 2 mm thick corrugated copper plate in expansion joint
complete as per drawing & Technical Specification.
Rmt 2705.00
39
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-5-1-d
Providing & fixing 20 mm thick compressible fibre board in expansion joint
complete as per drawing & Technical Specification.
Rmt 173.00
BW-5-1-e
Providing and fixing in position 20 mm thick premoulded joint filler in
expansion joint for fixed ends of simply supported spans not exceeding 10
m to cater for a horizontal movement upto 20 mm, covered with sealant
complete as per drawing and technical specifications
Rmt 219.00
BW-5-1-f
Providing and filling joint sealing compound as per drawings and technical
specifications with coarse sand and 6% bitumen by weight
Rmt 25.00
providing and fixing elastomeric slab seal expansion joint with maximum
horizontal movement upto 50 mm complete as per approved drawings and
specificaitons to be installed by manufacturer / supplier ensuring
compliance to the manufacturer's instructions for installation etc. complete
and as directed.
BW-5-1-g
Elastomeric Slab Steel Expansion Joint (Providing and laying of an
elastomeric slab steel expansion joint, catering to right or skew (less than
20 deg., moderately curved with maximum horizontal movement upto 50
mm, complete as per approved drawings and standard specifications to
be installed by the manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for installation and
clause 2606 of MoRTH specifications for road & bridge works.)
Rmt 13336.00
BW-5-1-h
Providing and fixing in position expansion joints in footpath consisting of
Shalitex board, thermocol packing and polysulphide sealant as per
detailed drawings etc. complete as specified an directed.
Rmt 1067.00
providing and fixing strip seal type expansion joint catering to +40 mm size
expansion as per drawing and specifications including alloy extended edge
beams, fixing by welding etc. complete as specified and directed.(To be
installed by manufacturer / suplier ensuring compliances to manufacturer's
instructions)
BW-5-1-i
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion
joint catering to maximum horizontal movement upto 70 mm, complete as
per approved drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)
Rmt 12663.00
BW-5-1-j Drainage Spouts complete as per drawing and Technical specification Each 1869.00
BW-5-1-k
Burried Joint (Providing and laying a burried expansion joint, expansion
gap being 20 mm, covered with 12 mm thick, 200 mm wide galvanised
wieldable structural steel plate as per IS: 2062, placed symmetrical to
centre line of the joint, resting freely over the top surface of the deck
concrete, welding of 8 mm dia. 100 mm long galvanised nails spaced 300
mm c/c along the centre line of the plate, all as specified in clause 2604.)
Rmt 1444.00
BW-5-1-l
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide
for horizontal movement of 25 mm and vertical movement of 2 mm, depth
of joint varying from 75 mm to 100 mm, width varying from 500 mm to 750
mm (in traffic direction), covered with a closure plate of 200mm x 6mm of
wieldable structural steel conforming to IS: 2062, asphaltic plug to consist
of polymer modified bitumen binder, carefully selected single size
aggregate of 12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved drawings and specifications.)
Rmt 1071.00
40
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-5-1-m
Compression Seal Joint (Providing and laying of compression seal joint
consisting of steel armoured nosing at two edges of the joint gap suitably
anchored to the deck concrete and a preformed chloroprene elastomer or
closed cell foam joint sealer compressed and fixed into the joint gap with
special adhesive binder to cater for a horizontal movement upto 40 mm
and vertical movement of 3 mm.)
Rmt 3504.00
BW-5-1-n
Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box
steel expansion joint including anchorage catering to a horizontal
movement beyond 70 mm and upto 140mm, complete as per approved
drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)
Rmt 9222.00
BW-5-1-o
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box
seal expansion joint catering to a horizontal movement beyond 140mm
and upto 210mm, complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the manufacturer's
instructions for installation.)
Rmt 9234.00
(II) MASTIC ASPHALT
BW-5-2-a
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with paving grade bitumen
meeting the requirements given in table 500-29, prepared by using mastic
cooker and laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated fine grained
hard stone chipping of 9.5 mm nominal size at the rate of 0.005cum per 10
sqm and at an approximate spacing of 10 cm center to center in both
directions, pressed into surface when the temperature of surfaces not less
than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.)
Sqm 258.00
BW-5-2-b
Providing and laying bitumen mastic layer 25 mm thick over bridge deck
excluding tack coat etc. complete as specified and directed. (with bitumen
10/20 penetration not less than 10.5% and lime stone dust not, less than
40%)
Sqm 804.00
BW-5-2-c
Providing and laying bitumen mastic layer 20 mm thick over bridge deck
excluding tack coat etc. complete as specified and directed. (with bitumen
10/20 penetration not less than 10.5% and lime stone dust not, less than
40%)
Sqm 643.00
BW-5-2-d
Providing and laying bitumen mastic layer 40 mm thick over bridge deck
excluding tack coat etc. complete as specified and directed. (with bitumen
10/20 penetration not less than 10.5% and lime stone dust not, less than
40%)
Sqm 1272.00
(III) EPOXY PAINTING
BW-5-3-a
Providing and applying epoxy primer as a base coat to receive epoxy
paint.
Sqm 150.00
BW-5-3-b
Providing and applying epoxy base paint to RCC piers, columns, beams,
girders, diaphragms, slabs, parapets etc. including cleaning and preparing
the surface, applying putty consisting of epoxy base paint and steolite
powder, applying one coat of epoxy primer and one coat of epoxy paint to
render the concrete surfaces smooth by covering small irregularities
including scaffolding etc. complete as specified and directed, (1 coat
epoxy + primer)
Sqm 287.00
41
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-5-3-c
Providing and applying epoxy base paint to RCC piers, columns, beams,
girders, diaphragms, slabs, parapets etc. including cleaning the surfaces
thoroughly so as to remove deposited salts, oil, grease, tar, moisture etc.
from the surface, preparing the surface, applying putty consisting of epoxy
base paint and steolite powder, to render the concrete surfaces smooth by
covering small irregularities and applying one coat of epoxy paint including
scaffolding etc. complete as specified and directed.(2 coats epoxy +
primer)
Sqm 366.00
BW-5-3-d
Providind and appling epoxy seal coat to new or repaired surfaces of
RCC structural members, prepared by mixing araldite GY 250 and
hardener in 100:50 proportion by weight with stiff nylon bristle brush as per
manufacturer's specifications etc. complete as specified ands directed.
Sqm 185.00
BW-5-3-e
Providing and applyinf two coats of Hi-Build coal tar epoxy formulation
corroseal TE-321 with an interval of minimum 4 hours - 8 hours between
application of successive coats including preparing and cleaning the
surface thoroughly so as to remove deposited salts, grease, oil, dust, tar
etc. using coarse brush etc. complete as specified and directed.
Sqm 274.00
BW-5-3-f
Providing and applying protective paint consisting of two coats of coat
tar epoxy paint over one coat of primer of approved quality and make to
the external surfaces of concrete structures to be buried under the soil etc.
complete as specified and directed.
Sqm 300.00
(IV) OTHER ITEMS -PVC PIPES, M.S. SLEEVES, DISMANTLING
BW-5-4-a
Providing and fixing in position PVC pipe 150 mm dia. in any position
including all fittings and accessories, making joints / connections water
tight with solvent cement, scaffolding if necessary and making good the
damages if any etc. complete as specified and directed.
497.00
BW-5-4-b
Providing and fixing in position PVC pipe 100 mm dia. in any position
including all fittings and accessories, making joints / connections water
tight with solvent cement, scaffolding if necessary and making good the
damages if any etc. complete as specified and directed.
497.00
BW-5-4-c
Providing and fixing in position Mild steel sleeves of M.S pipe 200 mm dia
and 1.2 mtr length with base plate 300 x 300 x 3 mm thick for electric
poles etc. complete as specified and directed.
2323.00
BW-5-4-d
Dismantling existing R.C.C slabs, Beams, Parapets, Kerbs etc. with
outmost care without damaging the existing reinforcement including
cleaning the reinforcement and disposing off the dismantled material safely
without causing any disturbance to the traffic and public in general etc.
complete as specified and directed.
1590.00
(V) MISCELLANEOUS REPAIR ITEMS - REMOVING WEARING
COAT, STAGING, EPOXY MORTAR
BW-5-5-a
Removing the old heavy duty mastic asphalt wearing coat/asphaltic
wearing coat laid over the expansion joints by chiselling, picking or by any
other means as necessary and required so as to expose the joint
completely including disposing off the debris etc. complete as specified
and directed.
Sqm 89.00
BW-5-5-b
Providing and erecting scaffolding/ staging upto a height of 10m including
all cross bracings to make it strong and sturdy etc. complete as specified
as directed.
Sqm 157.00
42
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-5-5-c
Providing and applying epoxy mortar for repairs to cracked portions of
RCC columns, piers, beams, girders, diaphragms, slabs, parapets etc.
including chipping the loose cracked concrete, cleaning the surface and
removing the rust thoroughly and completely by means of wire brushes,
sand blasting and washing with water etc. rebuilding the section by first
applying one coat of epoxy primer coat of araldite / GY 257 and hardener
HY840 in 100:50 proportion by weight, applying epoxy mortar prepared by
mixing araldite, hardener and quartzite sand in 100:50:900 proportion by
weight in required shape and architectural finishes, if any, finishing the
surface smooth including applying a seal coat of araldite and hardener in
100:50 proportion by weight with stiff nylon bristle brush etc. complete as
specified as directed.
Kg 262.00
(VI) LOAD TEST
Conducting load test on the bridge as per the procedure and specifications
laid down by IRC and as directed including formulating and submitting the
required reports in triplicate after completion of the load test etc. complete
as specified and directed. (upto 140 M.T load)
BW-5-6-a a) First Test No. 350000.00
BW-5-6-b b) Subsequent Test No. 27400.00
Carrying out load test upto 1.50 times the design load on any vertical pile
selected by Engineer-in-charge as per the procedure and specifications
laid down by IS:2911 and maintaning complete record of observations
regarding load settlement etc. complete.
Upto 600mm dia
BW-5-6-c a) On first Pile No. 99220.00
BW-5-6-d b) Subsequent Pile No. 39045.60
Above 600mm to 750mm dia
BW-5-6-e a) On first Pile No. 148830.00
BW-5-6-f b) Subsequent Pile No. 58568.40
Above 800mm to 1000mm dia
BW-5-6-g a) On first Pile No. 248050.00
BW-5-6-h b) Subsequent Pile No. 97614.00
Above 1100mm to 1200mm dia
BW-5-6-i a) On first Pile No. 396880.00
BW-5-6-j b) Subsequent Pile No. 156182.40
Carrying out Dynamic load test at 2.50 times the design load on any
dia.of pile including all preparations for conducting test by precasting
required C.C hammer head and all machineries, labour etc. including
submitting report with graphs and interpretations complete ( excluding cost
of pile).
BW-5-6-k a) On first Pile No. 45000.00
BW-5-6-l b) Subsequent Pile No. 25000.00
Carrying out Dynamic load test at 1.50 times the design load on any
dia.of pile including all preparations for conducting test by precasting
required C.C hammer head and all machineries, labour etc. including
submitting report with graphs and interpretations complete ( excluding cost
of pile).
BW-5-6-m a) On first Pile No. 45000.00
BW-5-6-n b) Subsequent Pile No. 25000.00
BW-5-6-o
Carrying out Cyclic load test at 2.50 times the design load or as specified
on vertical test pile of 1000mm dia. as per the procedure laid down in
IS:2911 including maintaining and submitting complete records of load
settlement as specified and directed.
No. 800000.00
43
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-5-6-p
Carrying out Cyclic load test at 1.50 times the design load or as specified
on vertical test pile of 1000mm dia. as per the procedure laid down in
IS:2911 including maintaining and submitting complete records of load
settlement as specified and directed.
No. 750000.00
(VII) STRUCTURAL STEEL TRUSS, GALVANISING, GUNITING
Providing and Fabricating structural steel work in rolled sections like
angles, tees, channels, joists, etc. as per detail designs and drawings
including cutting, fabricating, hoisting, erecting and fixing in position
making rivetted / bolted / welded connections with connections with
connecting plates, braces, holdfasts and painting with two coats of enamel
paint of approved shade and make over one coat of primer (red oxide) etc.
complete as specified and directed.
Refer
Common
Schedule
Providing Galvanising to structural steel welded sections at 610gm / sqm
as per specifications including transportation to and fro site of work
including loading, unloading at site, factory etc. complete as specified and
directed.
Refer
Common
Schedule
Guniting to surfaces of RCC structural members such as walls,
columns, beams, slabs etc. with cement mortar 1:3 of average thickness of
40mm under pressure of 2.1 to 2.8 kg/cm2 including chipping the loose
concrete, cleaning rust by means of wire brush, providing and fixing BRC
fabric (welded mesh) of 75 x 75 mm size 10 gauge, necessary formwork,
floating and curing etc. complete as specified and directed.
Refer
Common
Schedule
(VIII) OTHER ITEMS
(Cleaning, Polymer painting, Integrity test, pier protection, CPCC,
Dressing Joints, Compression seal, Thermoplastic paint, stainless
steel railing, roof structure and roofing, cement paint, polymer
mortar)
BW-5-7-a
Cleaning the concrete surfaces of bridge with detergent and other
cleaning materials as necessary including removing all dust, grease, stains
etc. to render the surface clean including removing all traces of cleaning
materials with jet of clean water etc. complete as specified and directed.
Sqm 30.00
BW-5-7-b
Providing grease in grease box of bearing including removing the old
grease from the box, cleaning the box etc.as specified and directed.
Kg 271.00
BW-5-7-c
Providing and applying elastic, polymeric membrane forming system with
anti carbonation and breathing properties of approved make of water
based acrylic polimers with selected mineral fillers having properties of
ultra violet resistant, carbonation resistant breathable, water proofing
coating and applying one coat of primer and two top coats of approved
shade and colour including cleaning and preparing the surface as requred
including scaffolding and all labour etc. complete as directed.
Sqm 234.00
BW-5-7-d
Carrying out integrity test on piles of various diameters as per standard
procedure and submitting reports.
No. 500.00
BW-5-7-e
Providing and casting in C.C. M-25 for pier protection as per detailed
drawing complete as specified and directed.
Rmt 3563.00
BW-5-7-f
Providing and applying CPCC anticorrosive treatment as per the Indian
patent No. 481/DEL93. Dated 13/05/93 and Indian patent No. 258/DEL/92,
Dated 25/03/92 to Mild and HYSD bar reinforcement cut and bent to the
required length, shape and size including chemical, labours, transportation
of steel bars for treatment and bringing back the same for fixing in position
with all accessories and material required for giving the treatment etc.
complete as specified and directed.
MT 7525.03
44
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-5-7-g
Dressing of joints between the existing mastic panels with hot
rubberized sealing compound confirming to I.S. 1834-1984 after proper
cleaning with compressed air applying required primer and providing layer
of lime powder over hot sealing compound etc. completed as specified and
directed. (Sealing of 25 mm wide joints between
the mastic panels with average depth of 12 mm.)
Rmt 28.00
BW-5-7-h
Providing and laying of compression seal expansion joint consisting of
steel armoured nosing at two edges of the joint gap suitably anchored to
the deck concrete and a preformed chloroprene elastomer or closed cell
foam joint sealer compressed and fixed into the joint gap with special
adhesive binder to cater for a horizontal movement upto 40 mm and
vertical movement of 3 mm.
Rmt 8046.00
Providing and applying hot applied thermoplastic road marking material
with glass beads extremely high skid resistance 2.5 mm thick without
primer coat (Tack coat) on Asphalt road surface. All labour, materials, with
special aggregates as specified in B.S. part - l & ll 1989 and carrying out
the marking on any road in center line and other marking continious or
intermitten 10cm. or 15cm width also pedestrians crossing strips as well as
spraying further quantity of glass beads of type ll uniformly into a mono
layer on to the hot paint line in quick succession of the paint spraying
opration @ 250gms per sqm. area as directed and as per BS / MOST
specifications in white / yellow colour.
BW-5-7-i a) White colour Sqm 829.00
BW-5-7-j b) Yellow colour Sqm 829.00
BW-5-7-k
Providing, fitting and fixing mild steel railing complete as per drawing and
Technical Specification
Rmt 3015.00
BW-5-7-l
Providing and fixing stainless steel railing with stainless steel post of 5mm
thick S.S. post shaped as shown in the drawing and fixing 25mm dia S.S.
pipe in the precut holes in the post and 75mm dia s.s. pipe handrail fixed
at top with 3mm plate welded to s.s. post including handrail fixed at top
with 3mm plate welded to s.s. post including proper cutting welding
anchoring fixing of post to the treads of staircase, required machinery
labour etc. complete as specified and directed.
Rmt 2803.00
BW-5-7-m
Providing and fibricating in position support structure for roofing in s.s.
pipes of 75/100 mm and other diameters as per approved structural design
fixed to base slab with necessary base plates, cleats, fixtures, fasteners,
hardware etc. complete as specified and directed.
Rmt 1417.00
BW-5-7-n
Removing the existing rolled steel joist beams, stanchions etc. completely
and staking the material at ward office or at site as directed by Engineer.
MT 3342.00
BW-5-7-o
Removing existing advertising boards completely and stacking as directed
by Engineer.
Sqm 92.00
BW-5-7-p
Providing and fixing colour coated galvanised colour bond base having
tensile strength (Min. 550 Mpa) C.R. steel base metal with hot dip alloy
coating of AL-ZN-SI as per ASTM - A - 792 M- 02 / AS 1397 ALU Zinc
alloy crimp sheets with flashing for girth 0 to 600 mm with standard length
of 2440 mm and flashing for girth 601 to 1200 mm as directed by Engineer-
in-charge.
Sqm 1058.00
BW-5-7-q
Providing and fixing flashing for advertisement for girth 600 mm to 1200
mm with standard length as per detailed drawing and manufacturing
specification and as directed by Engineer-in-charge.
Rmt 746.00
45
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and applying approved quality water proof cement paint to
structure with one coat of primer and two coats of cement paint including
watering, brooming, curing complete as specified and directed.
Refer
Common
Schedule
Providing and laying polymer modified mortar in the proportion of 1:5:15
( 1 Polymer, 5 Cement, 15 Quartz sand) for replacement of spalled
concrete, plaster, repairing cracks in the structure etc. complete as
specified and directed.
Refer
Common
Schedule
a) 10 mm thick average
b) 25 mm thick average
BW-5-7-r
Providing & placing in position controlled concrete M-35 grade with
minimum cement content as 400 kg/cum and water cement ratio not
exceeding 0.40 for R.C.C Precast Box Drain in suitable handling units
with form finished surface in any shape & size as per detailed drawings
and designs including formwork, temporary supports if required,
compacting by vibrators, leveling, curing and finishing etc. complete as
specified and including precasting, transportation & erection in place
asdirected but excluding reinforcement (using RMC)
Cum 11501.00
BW-5-7-s
Providing & Laying inverted filter behind Abutment & RE wall with suitable
thickness.
Cum 787.00
BW-5-7-t
P & P erecting in place precast RE wall panels in M35 complete with
precast facia and GI/HDPE reinforcement. Panel shall be given approved
cement paint from outside & 2 coats of coal for epoxy from inside. Panel
shall be cast and stored away from the site as per manufacturers design
and as per MORTH specifications.
Sqm 3795.00
BW-5-7-u P & F Arc type Anticrash Barrier as per drawing Rmt 7482.00
BW-5-7-v
Drilling holes in existing foundation for anchoring 6mm to 32mm dia rods
pf RCC jacket with non shrink free flow grout. Cost to include drilling for
1m depth, grout etc. except reinforcement.
No. 1710.00
BW-5-7-w
Providing and placing 600 thk Diaphragm wall in M30 concrete with
reinforcement to enable excavation of new footing etc. cost to include
mobilisation equipment, drilling excluding reinforcement.
Sqm 10015.00
BW-5-7-x
Providing and placing in position Soil Anchors upto 6m length 15t
capacity by drilling through diaphragm wall etc. Cost to include drilling
grouting with cementitious material etc. complete excluding reinforcement.
No. 9186.00
BW-5-7-y
Providing Fusion Bonded Epoxy Coating (FBEC) to reinforcing steel bars
as per IS 13620: 1993 specifications for a coating thickness of 175
microns ( with permissible variation of 50 microns) including testing at
plant etc. complete as per specifications.
MT 13365.00
RIVER TRAINING AND PROTECTION WORKS
Providing and laying boulders apron on river bed for protection
against scour with stone boulders weighing not less than 40 kg each
complete as per drawing and Technical specification.
BW-6-1 Boulder laid dry without wire crates. Cum 1017.00
BW-6-2
Boulder apron laid in wire crates (Providing and laying of boulder apron
laid in wire crates made with 4mm dia GI wire conforming to IS: 280 &
IS:4826 in 100mm x 100mm mesh (weaved diagonally) including 10%
extra for laps and joints laid with stone boulders weighing not less than 40
kg each.)
Cum 1491.00
BW-6-3
Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of
apron with cement concrete blocks of size 0.5x0.5x0.5 m cast in-situ and
made with nominal mix of M-15 grade cement concrete with a minimum
cement content of 250 kg/cum as per IRC: 21-2000.)
Cum 5322.00
46
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
Providing and laying Pitching on slopes laid over prepared filter
media including boulder apron laid dry in front of toe of embankment
complete as per drawing and Technical specifications
BW-6-4 Stone/Boulder Cum 1017.00
BW-6-5
Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete
of Grade M15
Cum 5322.00
BW-6-6
Providing and laying Filter material underneath pitching in slopes
complete as per drawing and Technical specification
Cum 1301.00
BW-6-7
Geotextile Filter (Laying of a geotextile filter between pitching and
embankment slopes on which pitching is laid to prevent escape of the
embankment material through the voids of the stone pitching/cement
concrete blocks as well as to allow free movement of water without
creating any uplift head on the pitching.)
Sqm 3148.00
Toe protection (A toe wall for toe protection can either be in dry rubble
masonry in case of dry rubble pitching or pitching with stones in wire crates
or it can be in PCC M15 nominal mix if cement concrete block have been
used for pitching . Rates for toe wall can be adopted from respective
clauses depending upon approved design. The rate for excavation for
foundation, dry rubble masonry and PCC M15 have been analysed and
given in respective chapters.)
Providing and laying Flooring complete as per drawing and Technical
specifications laid over cement concrete bedding.
BW-6-8-a Rubble stone laid in cement mortar 1:3 Cum 5373.00
BW-6-8-b Cement Concrete blocks Grade M15 Cum 7009.00
BW-6-8-c Dry rubble Flooring Cum 1408.00
Curtain wall complete as per drawing and Technical specification
BW-6-9-a Stone masonry in cement mortar (1:3) Cum 5019.00
BW-6-8-b Cement concrete Grade M15 Cum 5218.00
BW-6-9
Flexible Apron :Construction of flexible apron 1 m thick comprising of
loose stone boulders weighing not less than 40 kg beyond curtain
wall.
Cum 1062.00
BW-6-10
Gabian Structure for Retaining Earth (Providing and construction of a
gabain structure for retaining earth with segments of wire crates of size 7
m x 3 m x 0.6 m each divided into 1.5 m compartments by cross netting,
made from 4 mm galvanised steel wire @ 32 kg per 10 sqm having
minimum tensile strength of 300 Mpa conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into mesh with double twist, mesh
size not exceeding 100 x 100 mm, filled with boulders with least
dimension of 200 mm, all loose ends to be tied with 4 mm galvanised
steel wire)
Cum 1530.00
BW-6-11
Gabian Structure for Erosion Control, River Training Works and Protection
works (Providing and constructing gabain structures for erosion control,
river training works and protection works with wire crates of size 2 m x 1 m
x 0.3 m each divided into 1m compartments by cross netting, made from 4
mm galvanised steel wire @ 32 kg per 10 sqm having minimum tensile
strength of 300 Mpa conforming to IS:280 and galvanizing coating
conforming to IS:4826, woven into mesh with double twist, mesh size not
exceeding 100 mm x 100 mm, filled with boulders with least dimension of
200 mm, all loose ends to be securely tied with 4 mm galvanised steel
wire.)
Cum 2489.00
REPAIR AND REHABILITATION
47
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-7-1
Removal of existing cement concrete wearing coat including its disposal
complete as per Technical specification without causing any detrimental
effect to any part of the bridge structure and removal of dismantled
material with all lifts and lead upto 1000m(Thickness 75 mm)
Sqm 88.00
BW-7-2
Removal of existing asphaltic wearing coat comprising of 50 mm thick
asphaltic concrete laid over 12 mm thick mastic asphalt including disposal
with all lift and lead upto 1000m.
Sqm 65.00
BW-7-3
Guniting concrete surface with cement mortar applied with compressor
after cleaning surface and spraying with epoxy complete as per Technical
specification
Sqm 1945.00
BW-7-4
Providing and inserting nipples with approved fixing compound after drilling
holes for grouting as per Technical specifications including subsequent
cutting/removal and sealing of the hole as necessary of nipples after
completion of grouting with Cement/Epoxy
Each 168.00
Sealing of cracks/porous concrete by injection process through
nipples/Grouting complete as per Technical specification.
BW-7-5-a Cement Grout Kg 148.00
BW-7-5-b Cement mortar (1:1) Grouting Kg 144.00
BW-7-6
Patching of damaged concrete surface with polymer concrete and curing
compounds, initiator and promoter, available in present formulations, to
be applied as per instructions of manufacturer and as approved by the
Engineer.
Sqm 9238.00
BW-7-7
Sealing of crack / porous concrete with Epoxy Grout by injection through
nipples complete as per clause 2803.1.
Kg 2246.00
BW-7-8
Applying epoxy mortar over leached, honey combed and spalled concrete
surface and exposed steel reinforcement complete as per Technical
specification
Sqm 327.00
BW-7-9
Removal of defective concrete, cleaning the surface thoroughly, applying
the shotcrete mixture mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates, water and quick setting
compound in the proportion as per clause 2807.1., sand and coarse
aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively,
water cement ratio ranging from 0.35 to 0.50, density of gunite not less
than 2000 kg/cum, strength not less than 25 Mpa and workmanship
conforming to clause 2807.6.
Sqm 337.00
BW-7-10
Applying pre-packed cement based polymer mortar of strength 45 Mpa at
28 days for replacement of spalled concrete
Sqm 615.00
BW-7-11 Eproxy bonding of new concrete to old concrete Sqm 515.00
BW-7-12
Providing external prestressing with high tensile steel wires/strands
including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing
and Technical specification
MT 461379.00
BW-7-13
Providing external prestressing with high tensile steel wires/strands
including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing
and Technical specification
MT 342261.00
BW-7-14
Providing external prestressing with high tensile steel wires/strands
including drilling for passage of prestessing steel, all accessories for
stressing and stressing operation and grouting complete as per drawing
and Technical specification
MT 303429.00
BW-7-15 Replacement of bearings complete as per Technical specification Each 49168.00
BW-7-16 Rectification of bearings as per Technical specifications Each 15962.00
BW-7-17 Replacement of Expansion Joints complete as per drawings Rmt 3990.00
BW-7-18 Replacement of damaged concrete railing. Rmt 206.00
BW-7-19 Replacement of crash barrier. Rmt 392.00
BW-7-20 Replacement of damaged mild steel railing Rmt 169.00
48
MUNICIPAL CORPORATION OF GREATER MUMBAI
Schedule for Bridge Works
2013
ITEM CODE ITEM DESCRIPTION UNIT RATE
BW-7-21
Repair of crash barrier (Repair of concrete crash barrier with cement
concrete of M-30 grade by cutting and trimming the damaged portion to a
regular shape, cleaning the area to be repaired thoroughly, applying
cement concrete after erection of proper form work.)
Rmt 263.00
BW-7-22
Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to
the original shape.)
Rmt 172.00
BW-7-23
Repair of steel Railing (Repair of steel railing to bring it to the original
shape)
Rmt 266.00
49
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-A
Schedule for Bridge Works 2013
Sl. No. Code Description of Labour Unit Rate
1 LB-02 Welder Day 425.00
2 LB-04 Mazdoor/Dresser/Sinker (Skilled) Day 450.00
3 LB-05 Bhisti Day 300.00
4 LB-06 Blacksmith (Ist class) Day 400.00
5 LB-07 Blacksmith (IInd class) Day 325.00
6 LB-08 Driller (Jumper) Day 400.00
7 LB-09 Carpenter 2nd class Day 375.00
8 LB-12 Mazdoor Day 300.00
9 LB-13 Operator (grouting) Day 350.00
10 LB-15 Diver Day 450.00
11 LB-17 Fitter Day 425.00
12 LB-20 Mali Day 350.00
13 LB-21 Mason (Ist class) Day 500.00
14 LB-22 Mason (IInd class) Day 400.00
15 LB-24 Mechanic Day 500.00
16 LB-25 Blaster (Stone cutter) Day 400.00
17 LB-28 Painter Ist class Day 450.00
18 LB-27 Painter semi skilled Day 325.00
19 LB-32 Beldar/Dresser (Semi Skilled)/Oil Man Day 350.00
20 LB-33 Mate / Supervisor Day 550.00
21 LB-40 Medical Officer Day 1,200.00
22 LB-41 Para medical personnel Day 600.00
Sl. No. Code Description of Machine Unit Rate
1 HC-02 Dewatering Pump of 5HP Day 770.00
2 HC-09 Hydraulic Excavator of 1 cum bucket Hr 1,375.00
3 HC-13 Tipper - 5 cum Hr 475.00
4 HC-15 Truck Trailor 30 tonne capacity Hr 1,210.00
5 HC-17 Front End loader 1 cum bucket capacity Hr 687.50
6 HC-22 Plate compactor Hr 50.00
7 HC-23 Welding machine Day 1,250.00
8 HC-27 Tractor Hr 185.63
9 HC-28 Air Compressor Hr 337.50
(B) Usage Rates of Plant and Machinery
(A) Labour
BASIC RATES LIST ADOPTED FOR FRAMING THE SCHEDULE
50
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-A
Schedule for Bridge Works 2013
BASIC RATES LIST ADOPTED FOR FRAMING THE SCHEDULE
10 HC-29
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Hr 350.00
11 HC-30
Compressor with guniting equipment along with
accessories
Hr 1,010.00
12 HC-31
Joint Cutting Machine with 2-3 blades (for rigid
pavement)
Hr 990.00
13 HC-32 Concrete Mixer - 0.4/0.28 cum Hr 110.00
14 HC-33 Concrete Mixer - 1 cum Day 1,920.00
15 HC-34 Transit Mixer 4.0/4.5 cum Hr 950.00
16 HC-34-1 Transit Mixer 4/4.5 cum t.km 4.05
17 HC-36 Concrete Pump of 45 & 30 cum capacity Hr 265.00
18 HC-36 Concrete Pump Day 2,120.00
19 HC-37 Water Tanker km 25.00
20 HC-38 Water Tanker Hr 95.00
21 HC-40 Generator 33 KVA Hr 380.00
22 HC-41 Generator 63 KVA Hr 550.00
23 HC-42 Generator 100 KVA Hr 770.00
24 HC-42 Generator 125 KVA Hr 770.00
25 HC-43 Generator 250 KVA Hr 1,200.00
26 HC-53 Bitumen Boiler oil fired Hr 200.00
27 HC-54 Concrete Paver Finisher with 40 HP Motor Hr 2,900.00
28 HC-57 Crane with grab 0.75 cum capacity Hr 750.00
29 HC-58 Cranes 3 tonnes Hr 370.00
30 HC-59 Crane 5 tonne capacity Hr 385.00
31 HC-60 Crane 10 tonne capacity Hr 400.00
32 HC-61 Crane 15 tonne capacity Hr 440.00
33 HC-62 Crane 20 tonne capacity Hr 550.00
34 HC-63 Cranes 35 tonne capacity Hr 800.00
35 HC-64 Crane 40 tonne capacity Hr 920.00
36 HC-65 Crane 80 tonne capacity Hr 1,100.00
37 HC-66 Pneumatic Sinking Plant Hr 4,300.00
38 HC-67 Prestressing Jack with Pump & access Hr 190.00
39 HC-68 Jackhammer Day 235.00
40 HC-69 Boat to carry atleast 20 persons Hr 1,320.00
41 HC-70 Epoxy Injection gun Hr 190.00
42 HC-71
Induction, deinduction and erection of plant and
equipment including all components and accessories
for pneumatic method of well sinking.
Hr 4,300.00
43 HC-72 Jack for Lifting 40 tonne lifting capacity. Day 9,900.00
51
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-A
Schedule for Bridge Works 2013
BASIC RATES LIST ADOPTED FOR FRAMING THE SCHEDULE
44 HC-73 Piling Rig with Bantonite Pump Hr 5,620.00
45 HC-74
Piling rig Including double acting pile driving hammer
(Hydraulic rig)
Hr 5,600.00
47 HC-75
Piling rig with tripod, winch chisel and other
accessories
Day 3,000.00
48 HC-76
Vibrating Pile driving hammer complete with power
unit and accessories.
Hr 5,600.00
49 HC-77 Vibrator (Needle type 40mm) Day 440.00
50 HC-80 Vibratory Roller 8 tonne Hr 1,500.00
51 HC-84 Pneumatic Road Roller Hr 1,275.00
52 HC-85 Smooth Wheeled Roller 8 tonne Hr 500.00
53 HC-88 Mastic cooker (hire charges) Day 1,320.00
54 HC-89 Mastic Cooker Hr 165.00
55 HC-92 Wet Mix Plant 60 TPH Hr 1,237.50
56 HC-94 Batching and Mixing Plant - 30 cum capacity Hr 2,100.00
57 HC-99 Mechanical Broom Hydraulic Hr 400.00
58 HC-106 Grouting pump with agitator Hr 22.00
59 HC-137 Truck Trailor 30 tonne capacity t.km 12.00
60 HC-150 Road marking machine Hr 225.00
61 HC-151 Pully and Winch Hr 40.00
Sl. No. Code Description Unit Rate
1 MA-GN-01 Cement MT 6000
2 MA-GN-04 Artificial crushed sand (Coarse sand at Site) Cum 1200
3 MA-GN-05 Plaster Sand (Fine sand at Site) Cum 3000
4 MA-GN-06
Stone Aggregate (Metal I) : 6-12 mm nominal size
(Aggregates 10 mm nominal size)
Cum 850
5 MA-GN-07
Stone Aggregate (Metal II) : 20-32 mm nominal size
(Aggregates 20 mm nominal size)
Cum 850
6 MA-GN-08
Stone Aggregate (Metal III) : 40 mm nominal size
(Aggregates 40 mm nominal size)
Cum 820
7 MA-GN-09 Rubble For Masonary Cum 650
8 MA-GN-10 Rubble For Soling Cum 600
9 MA-GN-11 Through and bond stone Each 13
10 MA-GN-14
Stone Boulder of size 150 mm and below at Cruser
Plant
Cum 420
11 MA-GN-15
Boulder with minimum size of 300 mm for Pitching
at Site
Cum 385.00
12 MA-GN-16 Gravel/Quarry spall at Site Cum 385
(C) Materials
52
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-A
Schedule for Bridge Works 2013
BASIC RATES LIST ADOPTED FOR FRAMING THE SCHEDULE
13 MA-GN-18 Moorum at Site Cum 400
14 MA-GN-19 Structural Steel MT 51400
15 MA-GN-20 Mild Steel bars MT 47400
16 MA-GN-21 Cold twisted bars (HYSD Bars) MT 48400
MA-GN-23 M.S. plates & Flats MT 53,400.00
17 MA-GN-27 Diesel Ltr 54.83
18 MA-GN-31 Binding wire Kg 60
19 MA-GN-32 Water KL 125
20 MA-GN-33 Brick Each 5.00
21 MA-BW-008
Granular Material or hard murrum for GSB works at
Site
Cum 400.00
22 MA-BW-009
Filter media/Filter Material as per Table 300-3
(MoRT&H Specification)
Cum 576.07
23 MA-BW-010 Polysulphide & polysterene LS 440.00
24 MA-BW-011 Bronze Screws No. 7.20
25 MA-BW-013 Bullies 150 mm to 100 mm Dia RM 47.00
26 MA-BW-014 Coir Strings Kg 24.00
27 MA-BW-017 Oil Ltr 165.00
28 MA-BW-018 Drilling holes 75 mm Dia Rmt 2,000.00
29 MA-BW-019 Shuttering simple (Formwork) Sqm 198.00
30 MA-BW-020 sliding Supplier Rates Day 88.00
31 MA-BW-021 fixed Supplier Rates Day 77.00
32 MA-BW-022 Cost of Neoprene Bearing qty 0.50
33 MA-BW-023 AC pipe 100 mm dia Rmt 169.29
34 MA-BW-024 Acrylic polymer bonding coat Ltr 1,265.00
35 MA-BW-025 Aluminium alloy/galvanised steel tonne 61,875.00
36 MA-BW-026 Bearing (Cost of parts) No. 1,375.00
37 MA-BW-027
Bearing (Cast steel rocker bearing assembly of 250
tonne )
No. 30,250.00
38 MA-BW-028
Bearing (Elastomeric bearing assembly consisting of
7 internal layers of elastomer bonded to 6 nos.
internal reinforcing steel laminates by the process of
vulcanisation,)
No. 10,560.00
39 MA-BW-029 Bearing (Forged steel roller bearing of 250 tonne) No. 30,250.00
40 MA-BW-030
Bearing (Pot type bearing assembly consisting of a
metal piston supported by a disc, PTFE pads
providing sliding surfaces against stainless steel
mating together with cast steel assemblies/fabricated
structural steel assemblies duly painted with all
No. 55,000.00
41 MA-BW-031
Bearing (PTFE sliding plate bearing assembly of 80
tonnes )
No. 25,492.50
42 MA-BW-032 Bearing (Supply of sliding plate bearing of 80 tonne) No. 24,750.00
43 MA-BW-033 Bentonite Kg 5.28
53
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-A
Schedule for Bridge Works 2013
BASIC RATES LIST ADOPTED FOR FRAMING THE SCHEDULE
44 MA-BW-035 Bitumen ( Cationic Emulsion ) MT 30,506.30
45 MA-RW-021 Bitumen (60-70 grade)/ VG-30 MT 36,380.00
46 MA-RW-094 Bitumen (80-100 grade )/ VG-10 MT 35,580.00
47 MA-BW-038 Bitumen (Cutback ) MT 53,870.31
48 MA-BW-039 Bitumen (emulsion) MT 30,506.30
49 MA-BW-040 Premoulded bitumen filler 25 mm thick Sqm 880.00
50 MA-BW-041 10 G moulded G.I. Sheet 38 cm wide Sqm 294.00
51 MA-BW-042 Bitumen (modified graded) MT 39,063.85
52 MA-RW-022 Bitumen 10/20 grade @ 10.5% weight of mix. Kg 39.74
53 MA-BW-045 C.I.shoes for the pile Kg 41.30
54 MA-BW-049 Coller for joints 300 mm dia No. 66.00
55 MA-BW-050 Compressible Fibre Board(20mm thick) Sqm 575.00
56 MA-BW-051 Copper Plate(12m long x 250mmwide) Kg 506.00
57 MA-BW-053
Corrugated sheet, 3 mm thick, "Thrie" beam section
railing
Kg 42.40
59 MA-BW-054
Earth Cost or compensation for earth taken from
private land
Cum 33.00
60 MA-BW-055
Elastomeric slab seal expansion joint assembly
manufactured by using chloroprene, elastomer for
elastomeric slab unit conforming to clause 915.1 of
IRC: 83 (part II),
Rmt 11,000.00
61 MA-BW-056
Electric Detonators @ 1 detonator for 1/2 gelatin
stick of 125 gms each
100 Nos. 2,200.00
62 MA-BW-057
Epoxy compound with accessories for preparing
epoxy mortar
Kg 1,650.00
63 MA-BW-058 Epoxy mortar Kg 66.00
64 MA-BW-059 Epoxy primer Kg 380.00
65 MA-BW-060 Epoxy resin-hardner mix for prime coat Kg 495.00
66 MA-BW-061 Galvanised MS flat clamp No. 49.50
67 MA-BW-062
Galvanised steel wire crates of mesh size 100 mm x
100 mm woven with 4mm dia. GI wire in rolls of
required size.
Sqm 137.50
68 MA-BW-063
Galvanised structural steel plate 200 mm wide, 6
mm thick, 24 m long
Kg 57.75
69 MA-BW-064 Gelatin 80% Kg 110.00
70 MA-BW-065 GI bolt 10 mm Dia No. 22.00
71 MA-BW-067 HDPE pipes 75mm dia Rmt 96.00
72 MA-BW-068 HDPE pipes 90mm dia Rmt 138.00
73 MA-BW-069 Helical pipes 600mm diameter Rmt 343.75
74 MA-BW-070 HTS strand MT 69,106.69
75 MA-BW-071 LDO for steam curing Ltr 59.40
76 MA-BW-072 M.S. Clamps No. 36.30
54
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-A
Schedule for Bridge Works 2013
BASIC RATES LIST ADOPTED FOR FRAMING THE SCHEDULE
77 MA-BW-073 M.S. Clamps Kg 3.85
78 MA-BW-074 M.S.shoes @ 35 Kg per pile of 15 m Kg 69.11
79 MA-BW-076
Modular strip/box seal expansion joint including
anchorage catering to a horizontal movement
beyond 70 mm and upto 140mm assembly
comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative
Rmt 7,976.65
80 MA-BW-077
Modular strip/box seal expansion joint catering to a
horizontal movement beyond 140mm and upto
210mm box/box seal joint assembly containing 3
modules/cells and comprising of edge beams, two
central beams, chloroprene seal, anchorage
elements, support and control system, all steel
sections protected against corrosion and installed by
the manufacturer or his authorised representative
Rmt 7,976.65
81 MA-BW-078 Nipples 12mm No. 41.25
82 MA-BW-079 Nuts and bolts Kg 47.30
83 MA-BW-080 Paint Ltr 123.75
84 MA-BW-081 Pavement Marking Paint Ltr 319.00
85 MA-BW-082
Pre moulded Joint filler,25 mm thick for expansion
joint.
Sqm 605.00
86 MA-BW-083 Pre-coated stone chips of 13.2 mm nominal size Cum 550.00
87 MA-BW-084
Preformed continuous chloroprene elastomer or
closed cell foam sealing element with high tear
strength, vulcanised in a single operation for the full
length of a joint to ensure water tightness.
Rmt 756.25
88 MA-BW-085 Pre-moulded asphalt filler board Sqm 1,039.50
89 MA-BW-086
Pre-packed cement based polymer concrete of
strength 45 Mpa at 28 days
Kg 253.00
90 MA-BW-087 Quick setting compound Kg 41.00
91 MA-BW-089 Sand bags (Cost of sand and Empty cement bag) No. 5.50
92 MA-BW-090 Sheathing duct Rmt 165.00
93 MA-BW-092
Steel helmet and cushion block on top of pile head
during driving.
Kg 69.00
94 MA-BW-093 Strip seal expansion join Rmt 10,450.00
95 MA-BW-095
Super plastisizer admixture IS marked as per 9103-
1999
Kg 165.00
96 MA-BW-096
Synthetic Geogrids as per clause 3102.8 and
approved design and specifications.
Sqm 2,475.00
97 MA-BW-098 Tie rods 20mm diameter No. 89.00
98 MA-BW-099
Tube anchorage set complete with bearing plate,
permanent wedges etc
No. 15,400.00
99 MA-BLD-HW-5 Unstaked lime MT 3,250.00
55
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-A
Schedule for Bridge Works 2013
BASIC RATES LIST ADOPTED FOR FRAMING THE SCHEDULE
100 MA-BW-102 Water based cement paint Ltr 49.50
101 MA-BW-103 Wire mesh 50mm x 50mm size of 3mm wire Kg 68.75
102 MA-BW-104 Wooden ballies 2" Dia for bracing Each 115.50
103 MA-BW-105 Wooden ballies 8" Dia and 9 m long Each 253.00
104 MA-BW-106 Wooden packing Cum 13,750.00
105 MA-BW-107 Polysulphide sealent Each 330.00
106 MA-BW-108 Shalitex board 25 mm thick Sqm 660.00
107 MA-BW-109 Thermocole Each 33.00
108 MA-BW-110 Supplying expanssion joint as per specifications Rmt 5,280.00
109 MA-BW-111 Anticorrosive LS 22.00
110 MA-BW-112 G.I. Pipe 100 mm dia. Rmt 700.00
111 MA-BW-113 Limestone dust Kg 6.60
112 MA-BW-114 Brush No. 10.00
113 MA-BW-115 Thiner Ltr 110.00
114 MA-BW-116 P.V.C. pipe 150 mm dia. Rmt 250.00
116 MA-BW-118 Primer (1 Litre for 4 sq.m) Ltr 330.00
117 MA-BW-119 Silica flour / Quarts Sand Kg 11.00
118 MA-BW-120 Primer as base coat Ltr 330.00
119 MA-BW-122 M.S. grating with trough no 110.00
120 MA-BW-123 Coal tar epoxy (2 coats) Ltr 275.00
121 MA-BW-124
Stone crusher dust finer than 3mm with not more
than 10% passing 0.075 sieve
Cum 1,500.00
122 MA-BW-125
Coarse graded Granular sub-base Material 4.75
mm to 2.36 mm
Cum 1,100.00
123 MA-BW-134 MS pipe 200 mm dia Rmt 1,600.00
124 MA-BW-135 Base plate 300 x 300 x 3 mm thick Kg 31,350.00
125 MA-BW-136 Soap Powder Kg 50.00
126 MA-BLD-SS-21 Grease Kg 120.00
127 MA-BLD-SS-22 Cotton Waste Kg 90.00
128 MA-BW-137 Anticarbonation Paint Ltr 200.00
129 MA-BLD-PN-11 Oil paint/ synthetic enamel paint Ltr 215.00
130 MA-BW-138
CPCC anticorrosive treatment as per the Indian
platent No. 481/DEL93.
MT 6,543.50
131 MA-BW-139 Chloroprene seal (Expansion joint) Rmt 3,335.00
132 MA-BW-140 Theromoplastic paint Ltr 200.00
133 MA-BW-141 Glass beads Kg 275.00
134 MA-BW-142 Stainless steel pipe 25mm Rmt 300.00
135 MA-BW-143 Top rail pipe 75mm Rmt 475.00
56
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-A
Schedule for Bridge Works 2013
BASIC RATES LIST ADOPTED FOR FRAMING THE SCHEDULE
136 MA-BW-144 Stainless steel post 5mm thick including fabrication Rmt 1,300.00
137 MA-BW-145 Crimp Sqm 650.00
138 MA-BW-146 RE wall Sqm 3,300.00
139 MA-BW-147 Structural Steel frame for flashing Sqm 425.00
140 MA-BW-148 Arc type Wave, Border Flat, Base Plate Kg 75.00
141 MA-BW-149 MS pipe 75mm dia. Kg 80.00
142 MA-BW-150 Anchor Fastener 12 Nos. 140.00
143 MA-BW-151 Inclined position 1200 x 0.6 m for soil anchors No. 800.00
144 MA-BW-152 Anchor plates tightening nuts etc. No. 1,600.00
145 MA-BW-153
Fusion Bonded Epoxy Coating (FBEC) for 8 mm to
32 mm dia
MT 10,100.00
146 MA-BW-154 P.V.C coated G.I wires Kg 250.00
57
MUNICIPAL CORPORATION OF GREATER MUMBAI
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 1

APPROVED MAKES LIST
Sr.
No.
Category Sub Category Brand Name
1 Cement
OPC 43/53 Grade(ISI
marked)
Ambuja Cement, L & T, ACC,
Birla,VIKRAM,J.K.,Ultratech,Ambuja,
Grasim, JK, Binani, India cement
2 Cement PSC (ISI marked) Commando Cement Ltd.
3 Cement White Cement Ultra tech, ACC, Birla ,J.K,
4 Cement Chemical Admixtures
Kerakoll, MC Bauchemie, BASF, MYK
Schomburg, Pidilite, Sunanda Chemicals,
Sika, FOSROC, Choksey Chemicals
5 Cement Expansion joint board Supreme Industries or equivalent
6 Steel Rebars Vizag Nigam Ltd., SAIL
7 Steel Structural Steel
Vizag,TISCON, SAIL, Metro structure,
RINL,AGRASEN ISPAT,JSW, CORUS
8 Steel HYSD Bars Metro HSDS bars
9 Steel TMT Bars Thermex TMT
10 Steel
M.S. Pipe, Tubes, Bar,
Flats,Angle, Tee
Sections
SAIL ,TISCO
11 Brick Work AAC blocks
BILT Industries Pvt. Ltd, Aerocon, Siporex
India limited, Xtralite
12
Wood & PVC
Work
PVC continuous fillet for
periphery Packing of
Glazings / Cur. Wall
Roop / Anand / Forex Plastic
13
Wood & PVC
Work
PVC sheet Forbo, Armstrong
14
Wood & PVC
Work
Wooden Flush Doors Kutty, Anand, Anchor, Duro, Kent
15
Wood & PVC
Work
Flush Door Duraboard,Kit ply, MerinoPly
16
Wood & PVC
Work
Flush Door Shutter Green, Century
17
Wood & PVC
Work
Waterproof Ply Green Ply, Garnet, Century
18
Wood & PVC
Work
Commercial ply. Garnet,Century, Donear, Green Ply
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 2
Sr.
No.
Category Sub Category Brand Name
19
Wood & PVC
Work
Veneer Duro, Green, Donear, Century
20
Wood & PVC
Work
Laminate Greenlam, Century, Merino
21
Wood & PVC
Work
Pre-laminated particle
board-Exterior grade
Novopan/ Merino / Anchorlam/ Bhutan
Board
22
Wood & PVC
Work
Gypsum board. Saint Gobain, Lafarge
23
Wood & PVC
Work
Cement Bonded Board BISON by NCL
24
Wood & PVC
Work
Shower partitions Dorma, Grohe, Hindware
26
Wood & PVC
Work
Mineral Fiber Ceiling Lloyd, Nittobo,Armstrong.
27
Wood & PVC
Work
Calcium silicate false
ceiling
Hilux, Promat
28
Wood & PVC
Work
Wax Polish Mansion
29
Wood & PVC
Work
Block Board / Ply
Phenol bonded boards of Merino/ Duro/
Samrat/ Kit Ply
30
Wood & PVC
Work
Cement Board Smart Board, JAMES Hardie
31
Wood & PVC
Work
PVB/ Laminate Film Dupont
32
Wood & PVC
Work
Door Hardware
Ingersolrand, Geze, Dorma,
Guardian,Dorset, Magnum, Union, Kitch
33
Wood & PVC
Work
Door Lock & Handle
Ingersolrand, Geze, Dorma Guardian, D-
Line
34
Wood & PVC
Work
Door closer Ingersolrand, Geze, Dorma , Guardian
35
Wood & PVC
Work
Door Locks (Concealed
/ Surface mounted)
Ingersolrand / Dorma,Haffle,Dorset
36
Wood & PVC
Work
Locks Dorset, Sobeet, Godrej
37
Wood & PVC
Work
Door Seal Wool pile
Weather Strip
Enviro Seal, Anand Raddiplex
38
Wood & PVC
Work
Door Handle
(Concealed / Surface
Ingersolrand , Geze, Dorma, Alu Alpha
39
Wood & PVC
Work
Metalic Steel Fire Door
Naviar,Shakti Met,Promat , Godrej
,Adhunik,Basic Arch Products, Radiant,
Signum
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 3
Sr.
No.
Category Sub Category Brand Name
40
Wood & PVC
Work
Fire smoke Seal Hilti, CFS, SPWB Joints Spray
41
Wood & PVC
Work
Fire Rated Hardware Ingersolrand, Gaze, Dorma
42
Wood & PVC
Work
Non Metalic Fire Door Naviar / Promat, Signum
43
Wood & PVC
Work
Metallic Door Shakti Met / Promat, Signum
44
Wood & PVC
Work
Metallic Window Shakti Met
45
Wood & PVC
Work
Stainless Steel Screws
for fabrication and fixing
of windows
Kundan/ Puja/ Atul
46
Wood & PVC
Work
Two or Four Point
locking Openable
Window Handle
Gize, Alu Alpha
47
Wood & PVC
Work
Butt Hinges openable
Window shutters
Haffle, Alu Alpha
48
Wood & PVC
Work
Mild Steel Butt Hinges/
Piano Hinges
Jolly, Garg,AMIT, ASI Supreme
49
Wood & PVC
Work
Nuts Bolts /Screws Kundan/ Puja/ Atul
50
Wood & PVC
Work
Concealed Tower Bolt Ingersolrand, Alu Alpha
51
Wood & PVC
Work
Patch Fitting Ingersolrand, Dorma, Geze
52
Wood & PVC
Work
Double Side Tab,
Decoretive Tab
3M
53
Wood & PVC
Work
UPVC Joinery
Fenesta, Veka, Euro plast, Aluplast, Amon
Ra
54
Wood & PVC
Work
Acoustic Insulation
U.P. Twiga Ltd, Lloyd, Saint Gobain,
Ecophone
55
Wood & PVC
Work
Glass
Saint Gobain, AIS ,Asahi, Pilkington, Modi,
Guardian Glass
56
Wood & PVC
Work
Clear Float Glass AIS Glass/ Saint Gobain/ Modiguard
57
Wood & PVC
Work
Source for tempering
Refl. Glass /Clear
GSC Toughened / Gold Plus/ Gurind/ Art
n Glass/ Impact Safety
58
Wood & PVC
Work
Glass (Toughened) Saint Gobain/ Modi Float/ Asahi Float
59
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 4
Sr.
No.
Category Sub Category Brand Name
60 Flooring work Vitrified Ceramic Tiles
Diamontile , Marbo Granit,
Granamite,Boss,NITCO, Asian, RAK, Euro,
Somany, Bell Ceramic, Kajaria
61 Flooring work
Precast mosaic & P.C.
Tiles
NITCO/ MODERN
62 Flooring work Industrial Tile Endura
63 Flooring work Glazed Ceramic Tiles
Orient, Kajaria, Nitco, Somany,Bell,
Johnson, Asian, RAK, Euro,
64 Flooring work Timber flooring Par-Ky, Ego flooring, Beutex
65 Flooring work False Floor Hewetson, Unifloor, Unitile
66 Flooring work Perquet Floor Nemo / Prima/ Pergo
67 Flooring work Floor Springs Ingersolrand /Dorma/ GEZE
68 Flooring work Rubber Tile Flooring
Ecoflex Surfaces Pvt. Ltd., Rudi Sports
Surfaces, The Floorsmiths
69 Flooring work Granamex Tiles
Vyara Tiles Pvt. Ltd.. Super Decorative
Floorings Pvt. Ltd., Sai Enterprises
70 Flooring work
Interlocking Concrete
Blocks
Vyara Tiles Pvt. Ltd.. Super Decorative
Floorings Pvt. Ltd., Sai
Enterprises,Hindustan Tiles, Nimco
Prefab,R.K. Tiles.
72 Finishing Works Gypsum Plaster St. Gobain, Permaboard, Vinayak gypsum
73 Finishing Works White washing lime Dehradun (Source)
74 Finishing Works
Paint/primer/oil bound
distemper Acrylic paint
Asian Paints, ICI,
Nerolac,Dulux,Spectrum,Unitile
,Berger,Aero paints,Jotun
75 Finishing Works
Water proof cement
paint
Snowcem India Ltd ,Asian Paints,
Berger,Nitco Cem
76 Finishing Works Fire Retardant paint Jotun, Hilti, Akzonobel
77 Finishing Works Mirror Modi Guard, Saint Gobain
78 Finishing Works
Anti Corrosive
Bitumastic Paint
Asian/Burger/J&N
79 Finishing Works Epoxy Paint Asian / Berger / J&N
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 5
Sr.
No.
Category Sub Category Brand Name
80 Finishing Works Epoxy Coating BASF
81 Finishing Works Silicon Coating BASF & Dowcorning
82 Sanitary ware Parry ware , Hindware , Cera
83 Sanitary ware
Vitreous China
Sanitaryware
CERA,ROCA,HINDWARE
84 Sanitary ware
Concealed Flushing
Cisterns
CERA,ROCA,HINDWARE
85 Sanitary ware European water closet Parry ware , Hindware , Cera
86 Sanitary ware
Sensor Operated
Flushing System
CERA,ROCA,PARRYWARE
87 Sanitary ware
Seat covers (Heavy
Duty)
Parry ware , Hindware , Cera
88 Sanitary ware
Flat Back Urinal (Sensor
Operated
CERA,ROCA,PARRYWARE
89 Sanitary ware Urinal Parry ware , Hindware , Cera
90 Sanitary ware Wash basin
HINDWARE,PARRYWARE,JHONSON
TOPAZ
91 Sanitary ware
SEMI-RECESSED
BASIN
HINDWARE,DURAVIT,RAKNOVA
92 Sanitary ware Bath Tub KOHLER,PARRYWARE,HINDWARE
93 Sanitary ware Bath Tub Mixer KOHLER,JAQUAR,HINDWARE
94 Sanitary ware Telephonic Shower PARRYWARE,JAQUAR,HINDWARE
95 Sanitary ware
C.P fittings & Bathroom
accessories
Jaquar , Parry ware , Hindware,ROCA,Cera
96 Sanitary ware Geayser Racold, venus wave,AO smith jaquar
97 Sanitary ware Health Faucet
JAQUAR,KOHLER,SCHELL,PARRYWARE
,ESS
98 Sanitary ware Soap Dispensar JAQUAR,ROCA,CERA
99 Sanitary ware Flow Regulator Devices ARCO
100 Sanitary ware Stainless Steel Sink
Nirali , Franke , Parry ware ,
Cera,JAYNA,AMC,NEELKANTH
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 6
Sr.
No.
Category Sub Category Brand Name
101 Sanitary ware C.P Bottle Trap
JAQUAR,ROCA,KOHLER,PARRYWARE,E
SS
102 Sanitary ware
Sink mixer with regular
swinging spout
JAQUAR,ESS,GROHE
103 Sanitary ware Basin mixer Jaquar,Hindware,ESS
104 Sanitary ware Waste coupling Jaquar,Hindware,PARRYWARE
105 Sanitary ware C.P. Grating GMGR , Chilly , Viking
106 Sanitary ware
CP / SS Grating for
Floor Trap & Floor Drain
NEER,ACO,VIJAY
107 Sanitary ware
Stainless Steel (304)
Square Frame Grating
Noway,Chilly,Camry
108 Sanitary ware Strainer RB , Intervalve , Zoloto , VB
109 Sanitary ware
C.I Strainer more than
65mm dia.
LEADER,KARTAR,SANT
110 Sanitary ware
Cast Brass Clean Out
Plugs
GMGR,Neer, Viking
111 Sanitary ware Concealed stop cock Jaquar , Hindware , ESS
112 Sanitary ware Shower arm,rose Jaquar , Hindware , ESS
113 Sanitary ware
Bath spout with wall
flange
Jaquar , Parry ware , Hindware
114 Sanitary ware
4way diverter concealed
fitting, withbuilt in
nonreturn valves and
diverter handle
Jaquar , Parry ware , ESS
115 Sanitary ware Double coat hook JAQUAR,HINDWARE
116 Sanitary ware Towel Rack (600mm) JAQUAR,HINDWARE,PARRYWARE
117 Sanitary ware Towel Ring JAQUAR,ESS,PARRYWARE
118 Sanitary ware Toilet Paper Holder JAQUAR,HINDWARE,ESS
119 Sanitary ware Grab Bar JAQUAR,HINDWARE
120 Sanitary ware Urinal Push Cock Jaquar , Parry ware
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 7
Sr.
No.
Category Sub Category Brand Name
121 Sanitary ware ANGLE COCK JAQUAR,HINDWARE,PARRYWARE
122 Sanitary ware Piller COCK
JAQUAR,ESS,AMERICAN STANDARD-
CELLA
123 Sanitary ware Soap Dish JAQUAR,HIDWARE,PARRYWARE
124 Sanitary ware Two way Bib cock JAQUAR,ESS,PARRYWARE
125 Sanitary ware C.P Angle Valve JAQUAR,ROCA,KOHLER
126 Sanitary ware Ball Valve
RB , Intervalve , Zoloto ,
VB,ARCO,SANT,KARTAR
127 Sanitary ware GM Peet Valve RB , Intervalve , Zoloto , VB
128 Sanitary ware GM Wheel Valve RB , Intervalve , Zoloto , VB
129 Sanitary ware
Pressure Reducing
Valves
Hawa , Kirloskar , Sant , VB, zoloto, RB
130 Sanitary ware Butterfly valves
RB , Intervalve , Zoloto , VB, KSB,
KARTAR, SKS, Delval, Audco, Intervalve
131 Sanitary ware Float valve (C.I) LEADER,SARKAR
132 Sanitary ware Gate valve Zoloto,neta,leader
133 Sanitary ware G.M. Non return valve RB , Intervalve , Zoloto , VB
134 Sanitary ware C.I. Non return valve RB , Intervalve , Zoloto , VB
135 Sanitary ware Flap Type Check Valve hawa , Intervalve , Audco
136 Sanitary ware Solenoid Valve Rotex , Asco , Switzer , Intervalve
137 Sanitary ware Automatic Air vent Hawa , RB, Zoloto
138 Sanitary ware
Stoneware pipes/Gully
traps
Rajora , Equivalent
139 Sanitary ware
SWR Pipe & Fittings
type B ( for internal
drainage)
supreme, finolex, prince
140 Sanitary ware
SWR Pipe & Fittings
type A ( for Rain water
upto 160mm dia)
supreme, finolex, prince
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 8
Sr.
No.
Category Sub Category Brand Name
141 Sanitary ware UPVC pipes/fittings Supreme , Finolex , Prince,JAIN PIPES
142 Sanitary ware UPVC ASTM pipes SUPREME,SURYA ROSHNI,FINOLEX
143 Sanitary ware
CPVC Pipes and
Fittings
Astral, Ajay, Ashirwad flow guard
pipes,supreme,Prince
144 Sanitary ware Copper Pipes Rajco, Maxflow
145 Sanitary ware G.I. Pipes / M.S. Pipe Tata , Jindal , Zenith,SURYA ROSHNI
146 Sanitary ware
G.I. fittings (malleable
cast iron)
Unik , R Brand , Zoloto M , Unco,KS
147 Sanitary ware C.I. fittings NEEL,KARTAR,SARKAR
148 Sanitary ware C.I pipe & Fittings NECO,SKF
149 Sanitary ware
Sand Cast Iron Pipes &
fittings
NECO,RIF,HEPCO
150 Sanitary ware
HDPE pipes For Internal
Drainage
SUPREME,JAIN PIPES,EONN PLAST
151 Sanitary ware RCC NP2 Class Pipe
Indian Hume pipe, AA Srinivasa pipe
industries
152 Sanitary ware PVC KHURRA SUPREME,prince,FINOLEX
153 Sanitary ware Pressure Guage
H. Guru / Forbes Marshall /
Waaree,wika,fiberg
154 Sanitary ware RCC Grating Pratibha / Alcock
155 Sanitary ware Electronic Flow Meter Rockwin / Aquamate
156 Sanitary ware Water Level Controller Technica / Waaree
157 Sanitary ware Water Level Indicator Technica / Waaree
158 Sanitary ware Grating K.K.Manhole Jain spun pipe / Pragati
159 Sanitary ware
C.I manhole cover &
framing
neco, bengal iron corporation
160 Sanitary ware Water Meter Kay Cee / Kent / Desmesh
161 Sanitary ware R.C.C Pipe Jain Spun Pipe / Pragati /Daya Spun Pipe
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 9
Sr.
No.
Category Sub Category Brand Name
162 Sanitary ware Pipe Supports Hangers Intello Tech / GMGR / Chilly
163 Sanitary ware Insulation Thermaflex / Armaflex / Kiflex
164 Sanitary ware Solar System TATA BP/Racold/Jain solar/Sudarshan
165 Sanitary ware
Storage Type Hot Water
Heater
Venus / Bajaj / Racold
166 Sanitary ware
Pre-Fabricated
Structural supports and
clamps
CHILLY,EASYFLEX,CAMRY
167 Sanitary ware pumps Grundfos,ITT,DP
Aluminum Work
168 Aluminum Work
Aluminium Systems/
Anodized aluminum
fittings for
doors/windows
Indal,Hindalco,Bhoruka,Midi,Royal
Touch,Alufit(Sapa),Kawneer,Schueco,Reyn
aers ,Crown, ALANS,
Classic/,Bharat,Argent
169 Aluminum Work
Aluminium Cleat
arrangement for
Glazings / Cur. Wall
size
Samples to be got approved by Engineer-
in charge.
170 Aluminum Work Aluminium Sections Hindalco/ Jindal/ Mahavir/ lndal
171 Aluminum Work E.P.D.M. Gaskets Anand/ Roop/Bohra/Hanu
172 Water Proofing
Water proofing
compound
CICO, Pidilite, Laticrete
173 Water Proofing
Membrane
Waterproofing system
BASF, STP limited, Texsa, W R Grace
174 Water Proofing
Chemical Waterproofing
system
BASF, MC-Bauchemie, Sika, Sunanda
Specialty Coatings, Perma Construction Aid
Pvt. Ltd.
175 Water Proofing Water stops Hydrotite, BASF, Hydroswell
176
Landscaping &
Irrigation
Garden Benches
Saflow Products Pvt. Ltd., Kanha Import
Export Pvt. Ltd., Shardha Metalic
177
Landscaping &
Irrigation
Granite Benches
Jayantilal & Co., Jayant Minerals Pvt. Ltd.,
Ambaji Stones Dcor Pvt. Ltd.
178
Landscaping &
Irrigation
Versicell Mat
ZTC International Landscape Solutions Pvt.
Ltd., Hesda Solutions, Matrix Solutions
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 10
Sr.
No.
Category Sub Category Brand Name
179
Landscaping &
Irrigation
PVC Perforated Pipes
Rex Polyextrusion Ltd., Akash Enterprises,
Zenplas Pipes Pvt. Ltd.
180
Landscaping &
Irrigation
Play equipments Koochie, Playworld Systems
181
Ready Mix
Concrete
Ready Mix Concrete ACC, RMC, Ultra tech
182 Miscellaneous Structural Sealant Wacker, Dow Corning, GE
183 Miscellaneous Polysulphide sealant Pidilite, Chemetall-Rai
184 Miscellaneous
Bitumen Impregnated
Board
Shalitex
185 Miscellaneous
Polyethylene back up
rod
Supreme Ind. Ltd.
186 Miscellaneous Epoxy Fosroc/ STP/ CICO/ Ardex
187 Miscellaneous
False Ceiling
Members(Perimeter,
ceiling section,
intermediates, angles
etc.)
Gyp. Steel of India Gypsum Ltd
188 Miscellaneous Welding rod ADVANI
189 Miscellaneous
MS black
enameled/galvanized
ERW conduits
AKG, BEC, Steelkraft
190 Miscellaneous Toilet Cubical Merino
191 Miscellaneous Metal Deck Sheet TATA/SAIL
192 Miscellaneous Shear Stud/Connector KOCO
193 Miscellaneous
Clamp,Rebar,Chemcial
fastner
Hilti,Fischer,Wurth
194 Miscellaneous Anchor Fasteners / bolts Hilti, Fischer, Halfen
195 Miscellaneous Masking Tapes 3M, Sun Control/ Wonder Polymer
196 Miscellaneous Dash Fasteners SS grade, Hilti/
197 Miscellaneous
Stainless Steel Bolts,
Washers and Nuts
Kundan/ Puja/ Atul
Appendix-B

APPENDIX-B
MUNICIPAL CORPORATION OF GREATER MUMBAI

Page 11
Sr.
No.
Category Sub Category Brand Name
198 Miscellaneous
Stainless Steel
Pressure Plate Screws
Kundan/ Puja/ Atul
199 Miscellaneous
Stainless Steel Friction
Stay
Hetish, Haffle, Securistyle
200 Miscellaneous
Weather Silicon make
and grade
Dow Corning/ Momentive (GE)
201 Miscellaneous Structural Silicon Dow Corning/ Momentive (GE)
202 Miscellaneous Backer Road Supreme Industries Ltd
203 Miscellaneous GRC Jali Terrafirma, Ecovision & Mahesh GRC
204 Miscellaneous Tensile fabric System Ferrari, Mehler, MakMax
205 Miscellaneous Stainless Steel Jindal/ SAIL/ Golden
206 Miscellaneous Polycarbonate Sheet
Danpalon,Alcox, Polygal,V. A. Corporation,
Joy Fab, Yadav Engineering
207 Miscellaneous Post tensioning system VSL, Utracon, BBR
208 Miscellaneous PT strands DP Wires, Tata, Usha Martin
209 Miscellaneous Adhesives & Grouts Bal, Laticrete, KeraKoll, Pidilite