You are on page 1of 12

: :

Lack of knowledge on the


hazards of storing, handling and
application.
Engineer,
Supervisor,
workers
4 4 16 2 1 2
Construction Manager,
Site Engineer
Incompetent supervision Supervisor,
Involved workers
3 4 12 1 1 1 Construction Manager,
Site Engineer
Untrained workers / store
personnel
Involved workers,
Store personnel.
3 4 12 2 1 2 Site Engineer,
Gen.Foreman,.Store
keeper
Keeping / Handling at work
locations.
Store personnel,
Involved workers
3 4 12 2 1 2 Gen.Foreman,Foreman
*ALARP - As Low As Reasonably Practicable
:
Date: 1/2/2014 : Date: :
Signature : : :
Likelihood / Severity /
1 Remote / Minor /
2 Unlikely / Major /
3 Likely / Severe /
4 Frequent / Fatality /
Gen.Foreman.Foreman 12 4 3
Involved
personnel /
Others in the
vicinity
Spillage - Environmental /
hygeinic aspects
Bring only required quantity to work site and keep them protected
from sunlight .Ensure no source of ignition at locations of
application. Ensure No Smoking Rule.
Keep people away from and upwind of spill / leak.
Keep containers closed always. Use drip-trays. Avoid spillage /
entry into drains, sewers and water courses. Avoid subsoil
penetration.
1
Description of work : Installation of GRP Pipes (concrete surround )in microtunnelling 1200mm dia.
Roads and Infrastructure in Bani Hajer North. Phase 1 & 2
06/CGC/HSE/ RA/29 REV. 0
Project Name :
Ref No:
Signature:
Assessed by: Aaron Aaloosi
Refer the MSDS of Epoxy Venyl Ester Resin and Polyster Resin
(attached herewith). Explain hazards to Supervisor, involved
workers. Take all precautions mentioned in MSDS .
Assign competent supervisor having experience in handling and
application of Venyl Ester Resin and Polyster Resin
Select and train concerned workers including store personnel on
the storage, handling and application of Venyl Ester Resin and
Polyster Resin as per the MSDS.
Store below 30C in closed containers.
Store in dark away from oxidizing materials.
Ensure no source of ignition at storage place. Ensure No
Smoking Rule. Prevent unauthorised access to storage.
Storage - Flammable,
Decomposition can lead to
release of irritating gases and
vapours.
RISK ASSESSMENT FORM -
Assessment location :
Locations of storm water manholes on site.
:
SR #
Activity
Hazard / Conditions that could
develop hazard
Who Might be
Harmed

Initial Risk

Safety precautions needed to control the Risk to ALARP *


RESIDUAL
RISK
Responsible Person
:

C
o
n
s
e
q
u
e
n
c
e
s



L
i
k
e
l
i
h
o
o
d

/

In-situ Joint Lamination in manhole systems (Benching and cover slabs)



L
i
k
e
l
i
h
o
o
d




R
i
s
k
R
a
t
i
n
g

C
o
n
s
e
q
u
e
n
c
e
s
Date : 1-2-2014




R
i
s
k
R
a
t
i
n
g
Spillage shall be soaked up with inert absorbant such as sand,
Gather into labelled containers and dispose thru' approved waste
disposal contractor.
"
Reviewed by : Mr. Radi Shunnar ( Operations Manager)
1 1
16 2 1 2 Store keeper
Storing,handling and
application of Epoxy
Venyl Ester Resin
(Crystic VE
671) and Polyster
Resin (Crystic 272
E)
1
Store personnel,
Involved workers
4 4
4
3
2
1
16
6
Likelihood
4 3 2 1
12
8
4
12
9
3
8
6
4
2
4
3
2
1
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 1 of 6
: :
:

Description of work : Installation of GRP Pipes (concrete surround )in microtunnelling 1200mm dia.
Roads and Infrastructure in Bani Hajer North. Phase 1 & 2
06/CGC/HSE/ RA/29 REV. 0
Project Name :
Ref No:
RISK ASSESSMENT FORM -
Assessment location :
Locations of storm water manholes on site.
:
SR #
Activity
Hazard / Conditions that could
develop hazard
Who Might be
Harmed

Initial Risk

Safety precautions needed to control the Risk to ALARP *


RESIDUAL
RISK
Responsible Person
:

C
o
n
s
e
q
u
e
n
c
e
s



L
i
k
e
l
i
h
o
o
d

/

In-situ Joint Lamination in manhole systems (Benching and cover slabs)



L
i
k
e
l
i
h
o
o
d




R
i
s
k
R
a
t
i
n
g

C
o
n
s
e
q
u
e
n
c
e
s
Date : 1-2-2014




R
i
s
k
R
a
t
i
n
g
"
Health hazard - Inhalation -
harmful to internal organs /
functions.
involved workers 3 4 12 1 1 1 Supervisor,Involved
workers
Unknown of First aid measures involved workers 3 4 12 1 1 1 Gen,Foreman,
First sider /Site Nurse
Handling/ applying
strand mats
Dust hazard 3 4 12 1 1 1 Gen.Foreman,Foreman
*ALARP - As Low As Reasonably Practicable
:
Date: 1/2/2014 : Date: :
Signature : : :
Likelihood / Severity /
1 Remote / Minor /
2 Unlikely / Major /
3 Likely / Severe /
4 Frequent / Fatality /
involved workers, 3 4 1 1 Supervisor,
Involved workers
Health hazard - Irritating to skin
and eyes
Storing,handling and
application of Epoxy
Venyl Ester Resin
(Crystic VE 671)
and Polyster Resin
Crystic 272 E
(Contd)
Take of contaminated cloth immediately. Report to First aider and
get medical attention if irritation persists..
Avoid inhalation of vapour / dust. Use heavy duty dust masks to
cover nose and mouth. Avoid drinking, eating while handling VE
Resin and Polyster resin. Advise involved workers to wash hands
and mouth before eating /drinking.
Ensure workers use PVC hand gloves,safety googles, Face
shield, Plastic apron, coverall, safety shoes, helmet. Avoid
contact with skin and eyes.
Explain the First aid measures explained in the MSDS to involved
workers thru' Tool Box Talk. . Keep MSDS in site clinic, store and
work place for referring First aid measures
12
Signature:
Mr. Radi Shunnar ( Operations Manager)
Assessed by: Aaron Aaloosi
VE Resins and Polyster Resins are supposed to be used only in
well ventilated areas as per the MSDS.
Arrange local exhaust ventilation system like exhaust blowers of
suitable evacuation capacity with large dia exhaust hoses
wherever the venilation is not sufficient.
Keep the upstream and down stream manholes open and provide
fresh air supply through them into working manhole.
Lack of ventilation where
applying VE Resin and Polyster
Resin
Reviewed by:
2
1
3 4 12 2 1 Gen.Foreman,Foreman Involved workers
Ensure workers use thick dust masks to cover nose and mouth
,safety googles,cover all,safetyhelmet,safety shoes.
4
3
2
1
16
6
Likelihood
Severity
4 3 2 1
12
8
4
12
9
3
8
6
4
2
4
3
2
1
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 2 of 6
: :
:

Description of work : Installation of GRP Pipes (concrete surround )in microtunnelling 1200mm dia.
Roads and Infrastructure in Bani Hajer North. Phase 1 & 2
06/CGC/HSE/ RA/29 REV. 0
Project Name :
Ref No:
RISK ASSESSMENT FORM -
Assessment location :
Locations of storm water manholes on site.
:
SR #
Activity
Hazard / Conditions that could
develop hazard
Who Might be
Harmed

Initial Risk

Safety precautions needed to control the Risk to ALARP *


RESIDUAL
RISK
Responsible Person
:

C
o
n
s
e
q
u
e
n
c
e
s



L
i
k
e
l
i
h
o
o
d

/

In-situ Joint Lamination in manhole systems (Benching and cover slabs)



L
i
k
e
l
i
h
o
o
d




R
i
s
k
R
a
t
i
n
g

C
o
n
s
e
q
u
e
n
c
e
s
Date : 1-2-2014




R
i
s
k
R
a
t
i
n
g
"
Access and egress Involved workers 3 4 12 2 1 2 Site Engineer,Supervisor
*ALARP - As Low As Reasonably Practicable
:
Date: 1/2/2014 : Date: :
Signature : : :
Likelihood / Severity /
1 Remote / Minor /
2 Unlikely / Major /
3 Likely / Severe /
4 Frequent / Fatality /
Signature:
Establish a system for communication / signalling between the
Through the established signal, the safe condition of the worker
inside manhole should be checked and ensured at frequent
intervals by the hole watch and supervisor
The worker can convey his status to hole watch thru' lifeline.
Mr. Radi Shunnar ( Operations Manager)
Construction Manager,
Site Engineer,
Gen.Foreman, Foreman
Safety Officer
Lack of Emergency rescue
arrangements
Involved workers 4 4 16 3 1 3
Construction Manager,
Site Engineer,
Gen.Foreman,Foreman
Ensure full time presence of competent Supervision.
Worker inside
manhole
4 4 16 3 1 3
Monitor the work through PTW system for works inside confined
space, ensure precautionary measures as per PTW.
Take gas test,ensure oxygen presence of 21.8 %, no hazardous
gases. Ensure no wastes,contaminations inside.
Worker going inside should wear safety harness which shall be
attached with the lifeline /pulling rope of rescue pulling
equipment. The life line shall be hold by hole-watch and use for
signalling between him and the worker inside manhole.
Assessed by: Aaron Aaloosi
Reviewed by:
Works inside deep
manholes
2 Lack of monitoring Works inside
confined space.
Conduct pre-task talk on hazards and precautions required.
Keep ready emergency rescue equipments such as tripod stand
with pulling equipments. Ensure Self-contained breathing
apparatus available.
Hole watch person trained on emergency rescue should keep
watch outside. Maintain personnel Entry- Exit log. Self-contained
breathing apparatus to be kept ready in place.
Provide safe and seccured access ladder.Ladder should
extended 1 mtr above the groud level.
4
3
2
1
16
6
Likelihood
4 3 2 1
12
8
4
12
9
3
8
6
4
2
4
3
2
1
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 3 of 6
: :
:

Description of work : Installation of GRP Pipes (concrete surround )in microtunnelling 1200mm dia.
Roads and Infrastructure in Bani Hajer North. Phase 1 & 2
06/CGC/HSE/ RA/29 REV. 0
Project Name :
Ref No:
RISK ASSESSMENT FORM -
Assessment location :
Locations of storm water manholes on site.
:
SR #
Activity
Hazard / Conditions that could
develop hazard
Who Might be
Harmed

Initial Risk

Safety precautions needed to control the Risk to ALARP *


RESIDUAL
RISK
Responsible Person
:

C
o
n
s
e
q
u
e
n
c
e
s



L
i
k
e
l
i
h
o
o
d

/

In-situ Joint Lamination in manhole systems (Benching and cover slabs)



L
i
k
e
l
i
h
o
o
d




R
i
s
k
R
a
t
i
n
g

C
o
n
s
e
q
u
e
n
c
e
s
Date : 1-2-2014




R
i
s
k
R
a
t
i
n
g
"
Assigning untrained workers to
work inside confined
space.(inside manhole)
Worker going
inside manhole.
4 4 16 3 1 3
Site Engineer,
Gen.Foreman,Foreman
3 4 12 3 1 3
Lack of lighting inside manhole-
Poor visibilty to do work , Injuries worker inside
manhole
3 4 12 2 1 2
Site Engineer,
Gen.Foreman,Foreman
*ALARP - As Low As Reasonably Practicable
:
Date: 1/2/2014 : Date: :
Signature : : :
Likelihood / Severity /
1 Remote / Minor /
2 Unlikely / Major /
3 Likely / Severe /
4 Frequent / Fatality /
Air-blowers and air-compressor should be kept on level surfaces
and safe distance away from the edges of manhole.
Ensure safe operating condition of air compressor and
blower.Ensure whip arrestor at air hose end connection
Air hose line inserted into bottom of manhole should be secured
well.It should not obstruct the manhole entrance.
Substandard mounting / unsafe
condition of air blower, air
compressor and air-hose
Lack of air flow / ventilation
inside the manhole
Provide enough light inside the manhole using intrinsically safe /
spark proof lighting at 24 volt.The lighting should be well fixed
inside manhole against undesired hanging / movement and
interference with worker.
Assessed by: Aaron Aaloosi (HSE Manager) Reviewed by : Mr. Radi Shunnar ( Operations Manager)
Signature:
12 2
Provide Air supply through the upstream / down stream manholes
using air blowers. Provide air supply into the bottom of working
manhole at normal pressure, if sufficient air circulation is not
available.
Keep Open the the nearest manholes at upstream and down
stream of the manhole in which work is to be done.
Air supply into manhole is to be provided at a minor/normal
pressure only, monitored thru' control valve referring pressure
guage by an assigned person.
Lamination Works
inside deep
manholes. (contd..)
Only workers trained for working inside confined spaces and on
using of self contained / air-supplied breathing apparatus shall to
work inside the manhole. Explain him the hazards and to give
signal to hole watch on suffering any abnormality.
Worker inside
manhole
3 1 2 Site Engineer,
Gen.Foreman,Foreman.
Site Engineer,
Gen.Foreman.Foreman.
4
4
3
2
1
16
6
Likelihood
4 3 2 1
12
8
4
12
9
3
8
6
4
2
4
3
2
1
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 4 of 6
: :
:

Description of work : Installation of GRP Pipes (concrete surround )in microtunnelling 1200mm dia.
Roads and Infrastructure in Bani Hajer North. Phase 1 & 2
06/CGC/HSE/ RA/29 REV. 0
Project Name :
Ref No:
RISK ASSESSMENT FORM -
Assessment location :
Locations of storm water manholes on site.
:
SR #
Activity
Hazard / Conditions that could
develop hazard
Who Might be
Harmed

Initial Risk

Safety precautions needed to control the Risk to ALARP *


RESIDUAL
RISK
Responsible Person
:

C
o
n
s
e
q
u
e
n
c
e
s



L
i
k
e
l
i
h
o
o
d

/

In-situ Joint Lamination in manhole systems (Benching and cover slabs)



L
i
k
e
l
i
h
o
o
d




R
i
s
k
R
a
t
i
n
g

C
o
n
s
e
q
u
e
n
c
e
s
Date : 1-2-2014




R
i
s
k
R
a
t
i
n
g
"
*ALARP - As Low As Reasonably Practicable
:
Date: : 1/2/2014 : Date: :
Signature : : :
Likelihood / Severity /
1 Remote / Minor /
2 Unlikely / Major /
3 Likely / Severe /
4 Frequent / Fatality /
Possibility of accumulation of
vapours of Epoxy Venyl Ester
Resin and Polyster Resin while
applying them on manhole
internal surfaces.
Worker inside
manhole
Assessed by: Aaron Aaloosi (HSE Manager)
Use exhaust blowers to evacuate the vapour that may
accumulate inside manhole while applying mortar and paint.
Take gas test frequently to ensure safe conditions inside.
Ensure rotation of workers to minimise duration of exposure.
If accumulation of epoxy vapour observed during work , the
worker should be called out immediately. Resume work only after
ensuring full evacuation of vapour and ensuring safe conditions
by taking gas test.
4 3 12 3
Reviewed by : Mr. Radi Shunnar ( Operations Manager)
Signature:
Using breathing apparatus to
work inside manhole.
Involved workers 4 4 3
Safe condition of the worker should be ensured frequently by
hole- watch through the signalling system (thru' lifeline)
established between the hole watch and the worker inside.
Rescue equipments ( Tripod stand with pulley / lifting equipment)
should be kept ready with the life line attached to it to lift / rescue
the person in case of emergency. Competent supervisor and
persons trained on rescue operation should be present on site
during the work.
Duration of work using self contained breathing apparatus should
be limited to 20% less than than the time prescribed for using the
air cylinder by the supplier. Ensure the worker is well- trained on
using breathing apparatus.
1 3 Site Engineer,
Gen.Foreman,Foreman..
1 3 Site Engineer,
Gen.Foreman,Foreman..
Lamination Works
inside deep
manholes. (contd..)
16 Work using breathing apparatus should be done only if it is a
must to complete the initiated task due to technical reasons.
4
3
2
1
16
6
Likelihood
4 3 2 1
12
8
4
12
9
3
8
6
4
2
4
3
2
1
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 5 of 6
: :
:

Description of work : Installation of GRP Pipes (concrete surround )in microtunnelling 1200mm dia.
Roads and Infrastructure in Bani Hajer North. Phase 1 & 2
06/CGC/HSE/ RA/29 REV. 0
Project Name :
Ref No:
RISK ASSESSMENT FORM -
Assessment location :
Locations of storm water manholes on site.
:
SR #
Activity
Hazard / Conditions that could
develop hazard
Who Might be
Harmed

Initial Risk

Safety precautions needed to control the Risk to ALARP *


RESIDUAL
RISK
Responsible Person
:

C
o
n
s
e
q
u
e
n
c
e
s



L
i
k
e
l
i
h
o
o
d

/

In-situ Joint Lamination in manhole systems (Benching and cover slabs)



L
i
k
e
l
i
h
o
o
d




R
i
s
k
R
a
t
i
n
g

C
o
n
s
e
q
u
e
n
c
e
s
Date : 1-2-2014




R
i
s
k
R
a
t
i
n
g
"

Working inside
manhole (contd..)
Continuos work inside by a
single worker - Fatigue,Heat
stress etc.
Workers who
work inside
manhole
3 4 12 2 1 2 Site Engineer,
Gen.Foreman,Foreman.
Generation of spark / fore inside
manhole
Involved workers 4 4 16 3 1 3
Site Engineer,
Gen.Foreman,Foreman.
Unsafe grinder machine
Involved workers 3 4 12 1 1 1 Gen.Foreman, Foreman
*ALARP - As Low As Reasonably Practicable
:
Date: 1/2/2014 : Date: :
Signature : : :
Likelihood / Severity /
1 Remote / Minor /
2 Unlikely / Major /
3 Likely / Severe /
4 Frequent / Fatality /
Evacuate dust from manhole by exhaust blower.
Grinding work shall be done thru' hotwork permit only. Take gas
test and ensure no flammable gases present inside the manhole.
Check whether grinding shall be replaced with abrading using
rough emery paper.
Site Engineer,
Gen.Foreman,Foreman.
Provide rotation between trained workers to work inside the
manhole;so that they get intervals for rest,coming out to open air
to cool down their body and to breathe fresh air . Ensure
washing water and drinking water at work place
3 4 12
Assessed by: Aaron Aaloosi (HSE Manager) Reviewed by : Mr. Radi Shunnar ( Operations Manager)
Ensure generator is mounted on level ground at safe distance
from manhole entrance,safe and secured cables, spark proof
switches. Use industrial connectors.
Power supply for
lighting inside
manhole and water
pump.
Involved workers 2
Ensure presence of electrician at work location to ensure
interrupted lighting inside manhole and electrical safety.
Substandard mounting of
Generator on site / it's Unsafe
condition - Interruption of lighting
inside manhole / power supply,
overturning of generator,
damages, Injuries.
Signature:
Ensure the grinder have safety guard, proper grinding wheels.
Ensure the worker use dust mask, safety googles, face cover,
helmet,disposable cover all, helmet and safety shoes.
Rotate workers to prevent continuos exposure to dust / stress
Cable to manhole should be fixed with clamp so that it will not
interfere with workers manhole entrance and inside.
1 2
Site Engineer,
Gen.Foreman,Foreman
1 1 1
4
3
Grinding works to
abrade the surfaces
for lamination
Involved workers 3 4 12 Dust emission, Heat stress
4
3
2
1
16
6
Likelihood
4 3 2 1
12
8
4
12
9
3
8
6
4
2
4
3
2
1
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 6 of 6
8
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 7 of 6
8
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 8 of 6
8
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 9 of 6
8
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 10 of 6
8
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 11 of 6
8
HSEF 4.3.1-01-01 Issue: 1 Rev: 2 Issue Date: 20 Mar 2012 Page 12 of 6

You might also like