Three different near full-size caissons were tested to evaluate the effects of varying the diameter, Wall Thickness and length of suction piles. This was carried out through a testing program of large-scale instrumented caissons.
Three different near full-size caissons were tested to evaluate the effects of varying the diameter, Wall Thickness and length of suction piles. This was carried out through a testing program of large-scale instrumented caissons.
Three different near full-size caissons were tested to evaluate the effects of varying the diameter, Wall Thickness and length of suction piles. This was carried out through a testing program of large-scale instrumented caissons.
Subject: Large Scale Instrumented Offshore Suction Caisson Tests To Study Set-Up Around Suction Caissons
Fugro, under the sponsorship of ExxonMobil, has successful completed a two year program studying the set-up rate, and resulting axial increase in pullout capacity with time, of suction caissons. This was carried out through a testing program of large-scale instrumented caissons. Three different near full-size caissons were tested to evaluate the effects of varying the diameter, wall thickness and length of suction piles. The test caisson geometries and characteristics are as follows: The three different caissons were tested, so as to evaluate the effects of varying the diameter, wall thickness and length. The test caisson geometries and characteristics are as follows:
Caisson Diameter D (ft) Wall Thickness t (in.) Length L (ft) L/D Ratio D/t Ratio Small 1 5.5 3 / 8 22 4 176 Small 2 5.5 22 4 88 Large 11 44 4 176 The caissons were installed in a soft clay site in the Gulf of Mexico, chosen because of the availability of a previous Conoco pile test site and to get as close to a similar characteristic of that as soils in deep water. The caissons were outfitted with the necessary valves and fittings to allow water to escape during self- weight penetration and application of under pressure by suction during installation or overpressure for pump out load tests. Appropriate lifting lugs and outside top stiffener(s) has also been installed to provide the necessary lifting points during deployment and during pull-out and re-deployment.
44 Ft long, 11Ft diameter, Wall thickness Instrumented Suction Caisson. Fugro-McClelland Marine Geosciences, Inc. Structural Monitoring Department
Suction Caisson Research 2 of 8
22 Ft long, 5.5 Ft diameter, and 3 / 8 Wall thickness Instrumented Suction Caissons. ( valves at pore pressure points are used for filling only) The caissons were instrumented with differential and total pore pressure transducers, seafloor reference pressure transducers, differential pressure transducers, tilt sensors, plug level sensors, seafloor reference level sensors, temperature transducers, load cells, internal and external displacement and flow meters. All data was automatically acquired through redundant data loggers, powered by redundant power supplies.
Typical Sensor Overview for C3 Fugro-McClelland Marine Geosciences, Inc. Structural Monitoring Department
Suction Caisson Research 3 of 8
Overview of instruments Fugro-McClelland Marine Geosciences, Inc. Structural Monitoring Department
Suction Caisson Research 4 of 8
In addition, two 50 foot long pore-pressure sensing / CPT arrays were independently installed prior to installation of the 11-ft-diameter caisson (one installed where the center of the pile would be once installed and the other a short distance from where the outside pile wall would be). The array had a total of five total pore pressure transducers and one PCPT. To get an indication of far field pore pressure, the pore pressure transducers were allowed to dissipate to near 100% before the large caisson was installed. During the installation, load tests and extraction of the large caisson the pore pressures from the spear were recorded by a data logger attached to the top of the spear assembly.
Pore pressure array and CPT sensor. The testing program was designed to evaluate the magnitude of pore pressure increase at the pile wall (inside and outside) due to caisson installation and the rate of pore pressure dissipation with time for the three caissons. The two independent pore pressure sensing arrays recorded the pore pressure response both in the middle of the soil plug and within 18 inches outside the pile, for comparison to the response of sensors flush mounted to the interior and exterior pile wall. Also, the program measured the increase in pullout capacity with time (set -up) of the smaller caissons, by measuring pullout resistance by crane pull tests, as well a comparative pump out tests. Set -up load testing of the larger pile was accomplished by a combination of crane pull and pumping out. Tests were planned for various intervals from 1 hour to 90 days (or more) to develop the full setup curves in terms of evolution with time of pore pressure response and skin friction resistance.
Fugro-McClelland Marine Geosciences, Inc. Structural Monitoring Department
Suction Caisson Research 5 of 8
Deployment and Testing
Fugro-McClelland Marine Geosciences, Inc. Structural Monitoring Department
Suction Caisson Research 6 of 8
This program is currently being offered for participation to others at a cost of $300,000 per participant. Typically the data collected can be used for:
Accurately predict the increase in pile capacity with time (Set-up) Evolution of pore pressure dissipation with time (field permeability) Characterizing of Nc with reverse end bearing data. Data to evaluate Diameter / wall thickness Data to evaluate self-weight penetration and required installation suction Soil Plug behavior Soil zone of remolding Quantification of excess pore pressure field (internal and external) during installation Determination of effects on pore pressure field (internal and external) during load events Distribution of external soil strain in the shear zone during load events Data to establish the value of the NGI factor
Our initial findings from the program are that the data acquired during testing will revolutionize the current engineering philosophies in suction pile design.
Typical Data From Internal Spear Array Fugro-McClelland Marine Geosciences, Inc. Structural Monitoring Department
Suction Caisson Research 7 of 8
To put the costs into prospective consider if you had data to evaluate or minimize the following:
In project costs, schedule and execution flexibility With better knowledge of set-up time may resulting in:
Saving in mob-demob (depending on vessel). More optimized planning of installation sequence to allow for capacity development: e.g., install suction anchors/ mooring lines, demob (within field) to install something else (such as pipelines or flowlines) and to install FPSO, SPAR or surface wellhead platform etc. without demob (depending on vessel rate and weather operability). Greater savings potential for some programs. Reduced pile fabrication costs (designed and built for known setup and capacity)
Consider if you had data to evaluate and capitalize on the above!
Being able to quantify setup times provides these capabilities: Can assess risk and be able to respond in the event of installation schedule upset. Can more reliably design using actual setup data rather than using estimates from FEM or small-scale pile tests. Better position to get classification and certification authorities acceptance.
Fugro-McClelland Marine Geosciences, Inc. Structural Monitoring Department
Suction Caisson Research 8 of 8
The program data has increase the capability to efficiently design large diameter suction caissons in deepwater, particularly in those cases where setup is critical, such as with taut line systems. This program is currently being offered for participation to others at a cost of $300,000 per participant. We would like to find out if your company may be interested in licensing the data from this testing program. If you are interested in joining the study, and would like any further information please do not hesitate to contact either of the undersigned at the address below. We are preparing a presentation of the complete project. If you would like to attend our presentation on February 21 st , 2003 at our offices in Houston please do not hesitate to contact me at the address below. Very truly yours:
Paul R. Stevenson Regional Manager Fugro Structural Monitoring 6100 Hillcroft (77081) P.O. Box 740010 Houston, Texas 77274
Phone: + (1) 713-369-5600 Main Number Fax: + (1) 713-369-5570 Direct: + (1) 713-369-5594 USA Cell:+ (1) 832 434 9442 Email: pstevenson@fugro.com