Bill of Materials Quantity:

Flooring:
Cement: 40 bags - P. cement @ 225.00/bag = Php 9,000.oo
Sand : 2.0 cu.m. @800.oo/cu.m. = 1,600.oo
Gravel : 4.0 cu.m. @ 900.oo/cu.m. = 3,600.oo
Rebar : 25lngths - 10mmx6.0m@130.oo/lgths = 3,250.oo
Tie wire 2 kls GA 16 @ 70.oo/kl = 140.oo

Walling : CHB
1,014pcs - 6x8x16 chb @18.oo/pc =Php 18,252.oo
701 pcs - 4x8x16 chb @ 12.oo/pc = 8,412.oo
156 bags - p.cement @225.oo/bag = 35,100.oo
15.00cu.m- sand @ 800.oo/cu.m. = 12,000.oo
40lgths - 10mm x6.0m def bars @130.oo/lght = 5,200.oo

Tileswork :

445 pcs - 300x300mm flr tiles @ 45.oo/pc =Php 20,025.oo
40bags - P.cement @ 225.oo/bag = 9,000.oo
3.0cu.m. - sand @ 800.oo/cu.m. = 2,400.oo

Paintings :

4 gals - concrete neutralizer @ 700.oo/gal = Php 2,800.oo
13 gals - flat latex white @ 850.oo/gal = 11,050.oo
18 gals - semi gloss @900.oo/gal = 16,200.oo
20 pcs - sanding paper @ 55.oo/pc = 1,100.oo
5 pcs - paint roller 7" @ 115.oo/pc = 575.oo
4 pcs - paint brush @ 70.oo/pc = 280.oo
40 bg - skimcoat @ 260.oo/bag = 10,400.oo

Roofings :

22pcs - 2x2x1/4 angle bar @ 480.oo/pcs = Php 10,560.oo
24pcs - 2x3 c-purlins @ 380.oo/pc = 9,120.oo
12lgths- 10mm def bars @ 130.oo/lgths = 1,560.oo
40kls - 6011 welding electrodes @ 70.oo/kl = 2,800.oo
4 gals - red oxide @ 450.oo/gal = 1,800.oo
4 pcs - paint brush 4" @ 70.oo/pc = 280.oo
22pcs -3x10' corr.g.i.sht GA24 @ 350.oo/pc = 7,700.oo
22pcs - 3x8' corr g.i.sht Ga24 @ 300.oo/pc = 6,600.oo
2 pcs - plain g.i.sht GA24 @ 300.oo/pc = 600.oo
240pcs - texcrew 1 1/2" @ 8.00/pc = 1,920.oo

Hardwares :

2 pc - solid panel door @ 8,000.oo = Php 16,000.oo
1 pc - pvc door @ 3,000.oo = 3,000.oo
1 lot - door accessories @ 1,000.oo = 1,000.oo

Electrical :

Lumpsum : = Php 20,000.oo

Plumbing :

Lumpsum : = Php 15,000.oo

TOTAL COST of MATERIALS =Php 236,890.oo

45% labor cost = 106,600.50
Total cost of project =Php 343,490.5o


under sa flooring:
concrete balusters - 16 units @ Php 480.oo/unit = Php 7,680.oo

under sa hardwares:

sliding windows with 10mm tempered glass on aluniminum analoc frame 1 lot = Php 70,000.oo
jalousy windows - 6 sets @ 2,500.oo/set = Php 15,000.oo