DETAILED ESTIMATE FOR PROVIDING CRIKET

GROUND IN COLLEGE OF ENGINEERING

Sl. Description of Item Nos. L B D Qty

No.
1. Earth work open excavation for

cricket ground for a depth of 30cm

etc., complete
Cricket Ground 1x1 3.14/4x136x136x0.30 4355.81
Add for sundries - - - - 4.19
4360.00m3
2. Supplying and filling of sand gravel

mix of 1:1 ratio for a depth of 30cm

for cricket ground


Cricket Ground 1x1 3.14/4x1 4355.8

36x136x 1

0.30
Add for sundries - - - - 4.19
4360.00m3
3. Preparing the pitch - - - - L.S
4. Preparing the Boundry and pitch - - - - L.S.

lines

LEAD STATEMENT

Sl. Description Source Lead in Unit Cost of Lead Amount

No. Km materials Cost


1. Sand for mortar Palar 15km m3 110.00 81.50 191.50
2. Well Gravel Local 10km m3 86.00 57.50 143.50
Certified that the lead particulars furnished above are correct to the best of my

knowledge.

DATA

Sl. Qty Description Rate Per Amount

No.
1. Open earth work excavation for foundation

in hard stiff day, stiff black cotton, hard red

earth etc., complete – 10m3


1.00 m3 Earth work excavation as per SS 20B 24.00 m3 24.00

(19.25+28.75/2)=48.00/2 = 24.00)
0.33m3 Refilling the sides of foundation with exc. 10.10 m3 3.37
Earth
L.S. Add for sundries --L.S- -- 0.13
27.50
Rate for Rs. 27.50/m3
2. Supplying and filling in foundation &

Basement with filling sand etc., - 1m3


1.00m3 Cost of sand 191.50 m3 191.50
1.00m3 Refilling with sand 9.00 m3 9.00

(As per SSR item No. 84)


200.50
Rate for Rs. 200.50/m3
3. Supplying and Fixing with conveyed grewel

with lead of 3 km in layers 1cm thick etc.,


1.00m3 Cost of Gravel 143.50 m3 143.50
1.00m3 Filling with sand 10.10 m3 10.10

(As per SSR item No. 10)


L.S. Add for sundries --L.S- -- 0.40
154.00
Rate for Rs. 154.00/m3
Main Data
1m3 Sand 200.50 m3 200.50
1m3 Well gravel 154.00 m3 154.00
354.50
Rate for Rs. 177.25/m3
Name of work : Providing Cricket ground in Saraswathi Velu

College of Engineering in Sholinghur in

Vellore District.,

ABSTRACT

Sl. Qty Description Rate Per Amount

No.
1. Leveling the site by supply and filling the

low laying areas using the sand, Red Earth

4360m3 and red gravel mix at the ratio of 1:1:1 in 27.50 m3 119900

layers not more than 30cm thick including

watering, hand roller rolling etc., complete


2. 4360m3 Removing the top soil and gravel sand mix 177.25 m3 772810

in the ratio of 2:1 for a depth of cm laid in

layers not more than 30cm thick including

watering and hand roller rolling etc.,

complete
3. L.S. Preparing the pitch --L.S.- -- 33000
4. L.S. Preparing the boundry and pitch lines etc., --L.S.- -- 24290
Total Rs. 950000

(Rupees Nine Lakh and fifty thousand only)