Professional Documents
Culture Documents
STORAGE UNIT
Vegard Aksnes
MARINTEK AS
Trondheim, Norway
Email: vegard.aksnes@marintek.sintef.no
Terje Nyb
Statoil ASA
Bergen, Norway
Email: tenyb@statoil.com
Halvor Lie
MARINTEK AS
Trondheim, Norway
Email: halvor.lie@marintek.sintef.no
ABSTRACT
The oating storage unit Navion Saga at the Volve eld in
the North Sea suffered from two mooring line breaks in steel wire
ropes in 2011. Investigations of the broken ropes indicated that a
possible failure mechanism could be high stresses near the wire
socket induced by large bending moments in leeward mooring
lines. The scope of the current study has been to make a numer-
ical model capable of capturing such behaviour of the steel wire
rope and to check if the minimum bending radius could be as low
as the ropes specied minimum bending radius.
The numerical model has revealed a possible failure mecha-
nism. The connecting link plate between the upper chain segment
and the upper wire segment lies initially on the seabed. When
lifted off the seabed, the link plate and the wire socket will fall
to the seabed at a higher speed than the upper wire segment. A
transverse wave in mooring line plane propagating towards fair-
lead is generated when the wire socket hits the seabed. The wave
leads to large curvature in the wire near the socket. Sensitivity
studies of the governing parameters have been performed to as-
sess the uncertainties of the numerical model. A modied system
is presented and it is shown that the phenomenon which is likely
to have caused failure in the original system will not occur for
the modied one.
BACKGROUND
The Volve eld is located in the North Sea, about 200 km
West of Stavanger in Norway. The layout of the eld is shown
in Fig. 1. The gas is exported through an export pipeline and
(clockwise
relative to North) were assumed, such that one of the broken lines
(line 4) was on the leeward side. A 100 year storm (100 years re-
turn period for wind and waves, combined with 10 years return
period for current) was used in the analysis, with three combi-
nations of signicant wave height (H
s
) and spectral peak period
(T
p
), see Table 2. The Torsethaugen spectrum [4] (double peaked
spectrum) was applied for the waves and the wind spectrum was
the one given in ISO 19901-1 [5]. The vessel response in these
three sea states were simulated for ballast and loaded drafts, and
4 Copyright 2013 by ASME
TABLE 2. ENVIRONMENTAL DATA USED IN THE SIMULA-
TIONS. SIGNIFICANT WAVE HEIGHT IS DENOTED BY H
s
, SPEC-
TRAL PEAK PERIOD BY T
p
, SURFACE CURRENT SPEED BY V
c
AND AVERAGE WIND SPEED BY V
w
.
H
s
[m] T
p
[s] V
c
[m/s] V
w
[m/s]
Environment 1 14.4 16.1 0.58 33.0
Environment 2 13.0 13.5 0.58 33.0
Environment 3 13.0 17.4 0.58 33.0
with and without constant thrust towards the weather direction.
Events with large differences in axial tension near the socket
of the upper wire segment of line 4 were identied from the
screening phase. These events were reanalysed with a detailed -
nite element model for a single mooring line (line 4). The vessel
response from the screening phase was imposed on the fairlead
node in the RIFLEX-model in order to drive the simulations.
RESULTS
The screening study showed that the response of the wire-
chain coupling was most violent with ballast draft, thrust towards
the weather and environment 1 (ref. Table 2). Some events from
this case were chosen based on visual inspection of the time se-
ries. Two of the events are indicated in Fig. 5, which shows time
histories of axial tension and vertical displacement for the upper
wire segment close to the socket.
Detailed analysis showed that these events induce a rela-
tively large curvature in the wire segment. The following para-
graphs describe the progress of such events and discuss the gov-
erning parameters, as well uncertainties in the numerical model.
Physical Phenomenon
The heavy coupling segments are lifted off the seabed at
events with high tension in leeward lines due to large forward
surge motion. The wire rope and the coupling segments fall to
the seabed with different speeds when the mooring line becomes
slack (surge motion in opposite direction). The free fall veloci-
ties (v) of wire, socket and connection plate can be calculated by
solving the following equation in v:
1
2
C
D
Dv
2
= (mA)g, (1)
where is the density of sea water, C
D
is dimensionless drag
coefcient, D is diameter, m is mass per unit length, A is cross-
sectional area and g is gravitational acceleration. This gives the
following free fall velocities:
- wire: 2.1 m/s,
- socket: 4.6 m/s,
- connection plate: 8.2 m/s.
Thus, the coupling segments are seen to fall at higher speed
than the wire. When the coupling segments hits the seabed, a
transverse wave/pulse (in the vertical mooring line plane) is
generated and propagates towards fairlead. See Figs. 6 and 7 for
illustrations of the phenomenon. The wave induces large curva-
ture in the upper wire segment and is damped out as the wire is
laid down on the seabed. The period of the wave is about 1 s.
Sensitivity Studies
A number of sensitivity studies have been performed in or-
der to nd the governing physical parameters as well as to check
if the failure mechanism persist within the range of uncertainty
for some of the parameters in the numerical model.
TABLE 3. RESULTS FROM SENSITIVITY STUDIES. CURVA-
TURE IS REPORTEDFROMTHE UPPERWIRE SEGMENT, CLOSE
TO THE SOCKET.
Curvature [m
1
]
Parameter Event 1 Event 2 Event 3
Drag coefcient
[-]:
1 0.28 0.24 0.28
2 0.27 0.22 0.24
3 0.22 0.18 0.22
Link plate rotation:
Rotation 0.27 0.22 0.24
No rotation 0.33 0.26 0.33
Bending stiffness [kNm
2
]:
2.1 0.29 0.27 0.29
5.0 0.21 0.17 0.20
9.9 0.16 0.12 0.15
b
= E
d
2
, (2)
where E is the modulus of elasticity of the wire rope, is the
curvature and d is the diameter of the wire rope. With E = 155
GPa, = 0.3 m
1
and d = 0.107 m, this gives a bending stress
2488 MPa.
By assuming that all wires in the rope move freely relative to
each other, an estimate for the lower limit for the bending stress
is
b
= E
s
d
w
2
cos
2
, (3)
where E
s
= 210 GPa is the elastic modulus of steel, d
w
= 5
mm is the diameter of each of wires in the outer layer of the wire
7 Copyright 2013 by ASME
FIGURE 8. STATIC CONFIGURATION OF THE MODIFIED MOORING SYSTEM FOR BALLAST DRAFT.
rope and = 18