2009 PCIC 2009 PCIC 40 40 2009 PCIC 2009 PCIC 40 40 Authors: Authors: Authors: Authors: Robert M. Spiewak Robert M. Spiewak Jerry Pittman Jerry Pittman Daniel Wilson Daniel Wilson Dashiell, LLC. Valero Energy Corporation Valero Port Arthur Refining Dashiell, LLC. Valero Energy Corporation Valero Port Arthur Refining Dominik Pieniazek Dominik Pieniazek Floyd Weisse Floyd Weisse VI E i i LLC VI E i i LLC D hi ll LLC D hi ll LLC VI Engineering, LLC. VI Engineering, LLC. Dashiell, LLC. Dashiell, LLC. 2009 Petroleum and Chemical Industry Committee Technical Conference 2009 Petroleum and Chemical Industry Committee Technical Conference Anaheim, California Anaheim, California September 14 September 14--16, 2009 16, 2009 Todays Presentation Todays Presentation Improving Substation Reliability and Availability Improving Substation Reliability and Availability Background Substation Documentation Automation, Data Retrieval, Historian and Automation, Data Retrieval, Historian and Alarm Annunciation Monitoring and Operation Monitoring and Operation Critical Auxiliaries Reliability, Numbers and Statistics Recommendations Conclusions Background Background Background Project Overview Project Overview Large expansion at an existing refinery Large expansion at an existing refinery Electrical Reliability Improvement Electrical Reliability Improvement Additional on Additional on--site generation site generation gg Multiple parties involved: Multiple parties involved: Two Owner/Operators Two Owner/Operators Two Owner/Operators Two Owner/Operators Three engineering companies Three engineering companies Two construction companies Two construction companies Two construction companies Two construction companies One third party testing company One third party testing company One Utility One Utility One Utility One Utility Background Background Refinery Electrical System Refinery Electrical System Background Background Electrical Events After Expansion Nov- 06 South Sub Ground on 13.8KV overhead line. Two new transformers installed with 400A resistor in existing 1000 A ground system. Both transformers ground relays set to trip on Pick Up. Sep- Refinery Balanced load to generation. Trip 80MW generator, refinery imports through Sep 07 Refinery Blackout, Post Hurricane Humberto Balanced load to generation. Trip 80MW generator, refinery imports through 230kV lines L1 & L2. Utility 230kV lines L554 & L591 in service. L554 faults on blown debris, no reclosing. Seconds later L591 faults on lightning strike, no reclosing. Refinery attempted to serve its load plus local community. Generation trips on overload and blacks out. N PP2 Li it d ti t PP2 I t d B il h t it hi f Nov- 07 PP2 Limited generation at PP2, Import mode. Boiler house operators switching for maintenance to replace pole in tie line 205 A/B. Over current relay picked up and tripped remaining tie line 402A/B. Training issues as refinery eliminates tie lines and TGs. Mar- PP6 & PP7 GTG 1 out for maintenance. Loss of a transformer along with GTG1, causes 08 g , overload on second transformer. DC batteries and chargers for equipment are in PP5. Lost a single battery charger, batteries discharged, Microprocessor relays lost power, When power restored, microprocessor relay initiated breaker failure tripping first transformer, second transformer tripped on overload overload. Background Background Electrical Events After Expansion (cont) Jul-08 PP7 Installed temporary battery charger at PS5. Tripped overnight, repowering DC system relays previously causing trips had been disabled, a line differential microprocessor relay initiated an unexplained trip on repowering causing an outage. outage. Jul-08 230kV private L1 Test " blue Button" trips line under a scheduled utility/refinery communication test. Logic at both ends in microprocessor relays did not match causing trip. Mar- 08 SG Sub TR1 & TR2 Microprocessor relay. Set to trip on pick up instead of TOC; M SG S b TR2 t i d i ti d t h i t i t t t Mar- 08 SG Sub TR2 tripped on energization due to harmonic restraint not set Apr-08 SG Sub Sync lights stay on all the time due to unproven wiring Jun- 08 69kV Ties Overcurrent set points in microprocessor relays set incorrectly Substation Documentation Substation Documentation Substation Documentation Requirements Last items considered on new projects Last items considered on new projects Must specify your requirements before Must specify your requirements before awarding project, Tool awarding project, Tool--Kit Kit Why Why Downsized staff Downsized staff Document control issues with advancing electronic Document control issues with advancing electronic formats formats St & t i l d i ti f d St & t i l d i ti f d Storage & retrieval during times of need Storage & retrieval during times of need Tracking recall or advisory bulletins Tracking recall or advisory bulletins FAT &SAT FAT &SAT FAT & SAT FAT & SAT Substation Documentation Substation Documentation Special Provisions Microprocessor relays have replaced Microprocessor relays have replaced h d i d l l i ith t l i di h d i d l l i ith t l i di hardwired relay logic without logic diagrams hardwired relay logic without logic diagrams Complex relay schemes difficult to test Complex relay schemes difficult to test D t t ( l tti ) D t t ( l tti ) Data storage (relay settings) Data storage (relay settings) Electrical Operating Procedures Electrical Operating Procedures FAT/SAT Test records is benchmark data FAT/SAT Test records is benchmark data BOM and O&M manuals BOM and O&M manuals Automation, Data Retrieval, St Hi t i Storage, Historian, and and AlarmAnnunciation Alarm Annunciation Automation, Data Retrieval, Alarm Annunciation What? Utilizing Installed IEDs Data Mining, trending, equipment status estimation SystemMinimumConfigurations Integration Best Practices Integration Best Practices Use data to Increase productivity and d t reduce cost Automation, Data Retrieval, Alarm Annunciation Typical IEDs existing within substations Protective relays and meters O li t h d lt On-line tap changers and voltage regulators Reclosers and digital fault recorders Reclosers and digital fault recorders Bushing monitoring devices Circuit breaker monitoring devices Circuit breaker monitoring devices Dissolved gas in oil monitors Partial discharge monitors Partial discharge monitors CCTV cameras Phone event messengers Phone event messengers Substation access system Automation, Data Retrieval, Alarm Annunciation Example of monitoring class III transformer Automation, Data Retrieval, Alarm Annunciation Mining of Data Data mining is the process of extracting patterns from data. As more data are available and gathered, g data mining is becoming an increasingly important tool to transform these data into p information. It is commonly used in a wide range of profiling y g p g practices, such as marketing, surveillance, fraud detection and scientific discovery, Time for industrial application. Automation, Data Retrieval, Alarm Annunciation Data mining Can effectively help determine: required maintenance intervals, replace interval-maintenance with risk-based maintenance approach, detect equipment deterioration at early stages, or estimate other system properties. Automation, Data Retrieval, Alarm Annunciation Data mining When such data is properly identified, the facility has adequate time to acquire replacement parts, schedule required maintenance, importantly avoid catastrophic failure. Automation, Data Retrieval, Alarm Annunciation Configuration and best practices Some of the best practices: Ensure system can integrate devices from various manufacturers Ensure system supports multiple technologies / protocols Utilize multifunction IEDs Choose best IED for assigned function Make system as flexible as possible Automation, Data Retrieval, Alarm Annunciation Configuration and best practices Integrated system shall provide: Increased system functionality Increased system reliability/availability (limit/eliminate outage time) Increased system safety Decrease a cost for automation Decrease a cost for protection Adequate tools at the fingertips of the engineer Monitoring and Operation Monitoring and Operation Remote monitoring For not-networked / not-connected apparatus obtaining data about the present state of the apparatus, IED, transformer or IED that monitors this transformer is: expensive, time consuming, could be risky. F i t lli t (IED t k d) d t For intelligent (IEDs are networked), data is stored in a database and repository and t i il bl remote access is available. Monitoring and Operation First most manifested benefit In not-networked system, to obtain configuration files, SER, or DFR fromIEDs, the engineer needed to travel to the site and obtain files fromthe devices In networked system, the engineer can y g access historical data froma historian, verify what is stored in the IED presently and how p y historical data compares with present data Monitoring and Operation Examples of usage IEDs, CTs, VTs problems detection, System recovery, switching unexpected loads and disturbances, Analysis of changes required to the system for changing operating conditions, F l h i i f d h i For example: changing consistency of gas and how it will influence starting and loading of the compressor etc., Automatic change of protection parameters, For example: different seasons, mode of operations t etc., Isolation from utility for special conditions. Monitoring and Operation Remote operation Remote control of: circuit breakers, switches, lockout relays (LOR) and other apparatus that at present requires an pp p q operator to control it locally, CCTV cameras, Access doors and gates. Monitoring and Operation FOREMOST safety benefit Performing switching operation remotely eliminates arc-flash hazard exposure to the operator / electrician by removing himfrom the danger zone. Note: safety procedures shall be established first before remote operation is allowed. Critical Auxiliaries Critical Auxiliaries Almost always forgotten Substation aspects considered as auxiliary in nature: Control Power Supply Time Synchronization Enabling SER and DFR recorders Critical Auxiliaries Control and auxiliary power supply Control Power Supply should be: Maintained Monitored Redundant Critical Auxiliaries Control and auxiliary power supply DC CONTROL POWER SUPPLY BLOCK DIAGRAM, NON- REDUNDANT WITH MONITORING AC SOURCE BATTERY CB TEST SOURCE DS1 DS2 MCB FCB DISTRIBUTION DISTRIBUTION PANEL Critical Auxiliaries Control and auxiliary power supply DC CONTROL POWER SUPPLY BLOCK DIAGRAM, AC CHARGING REDUNDANT, DC BUS NON-REDUNDANT WITH MONITORING WITH MONITORING Critical Auxiliaries Control and auxiliary power supply DC CONTROL POWER SUPPLY BLOCK DIAGRAM, 2 x 100% REDUNDANT WITH MONITORING Critical Auxiliaries SER and DFR SER and DFR default settings enable only basic functionality at best case Not utilized to collect operation and fault information The table in paper / Attachment C lists analog channels and digital element recommended for monitoring and data-collection applications Critical Auxiliaries Time synchronization Cannot depend on internal clock circuit timing drifts with usage time, temperature, environmental instability and other factors Th ti t dd i ifi t i f ti The time stamp adds significant information Not synchronized information creates havoc Time Synchronization could become a law Some utilities require Time Synchronization Some utilities require Time Synchronization measurements at the Inter-Tie point Reliability, Numbers, Statistics and Hidd F il Hidden Failures Reliability, Numbers,Hidden Failures What is reliability? Definition of reliability Definition of reliability IEEE Std 100 EE Standard Dictionary IEEE Std 100 EE Standard Dictionary The ability to perform a required function The ability to perform a required function under stated under stated diti diti f t t d i d f ti f t t d i d f ti conditions conditions for a stated period of time for a stated period of time IEEE Gold Book adds IEEE Gold Book adds Th tit ti li bilit l ti it li bilit The quantitative reliability evaluation permit reliability indexes to be computed from knowledge of the from knowledge of the reliability of the constituent components of the reliability of the constituent components of the system system IEEE C37.100 IEEE C37.100 Reliability: a measure of the degree of certainty that the relay, or relay system, will perform correctly will perform correctly Reliability, Numbers,Hidden Failures What is reliability? What are we looking for when we evaluate What are we looking for when we evaluate equipment / system reliability performance? equipment / system reliability performance? How system should perform, How system should perform, Highest reliability vs. CAPEX cost, Highest reliability vs. CAPEX cost, Equipment replacement, Equipment replacement, Are we considering all parameters? Are we considering all parameters? Wide gap between design and operation Wide gap between design and operation g p g p g p g p calculations calculations Reliability, Numbers,Hidden Failures How calculated? Reliability modeling principles and data we are using do not consider: Varying parameters environmental parameters Random, unpredictable chaotic disturbances Large set samples Other major reliability influences Parameters used in reliability analysis are Parameters used in reliability analysis are based on very small sampling set of data Reliability, Numbers,Hidden Failures Hidden Failure Hidden failures Hidden failures IN PROTECTION SYSTEM / UTILITY IN PROTECTION SYSTEM / UTILITY IN PROTECTION SYSTEM / UTILITY IN PROTECTION SYSTEM / UTILITY APPROACH APPROACH a permanent defect that will cause a relay system to a permanent defect that will cause a relay system to p y y p y y incorrectly and inappropriately remove incorrectly and inappropriately remove a circuit element a circuit element as a direct consequence of another switching event as a direct consequence of another switching event IN PROCESS INDUSTY SYSTEM IN PROCESS INDUSTY SYSTEM IN PROCESS INDUSTY SYSTEM IN PROCESS INDUSTY SYSTEM a permanent defect that will cause an EI&C system to a permanent defect that will cause an EI&C system to incorrectly and inappropriately remove a circuit element incorrectly and inappropriately remove a circuit element incorrectly and inappropriately remove a circuit element incorrectly and inappropriately remove a circuit element as a direct consequence of another usually abnormal as a direct consequence of another usually abnormal event in EI&C system and/or plant process event in EI&C system and/or plant process Reliability, Numbers,Hidden Failures Causes of Hidden Failure Examples Cause examples: Cause examples: Circuit fault Shortage of reactive power Randomoperation of DC power system Random operation of DC power system Inadequate testing / commissioning Operation of E&IC systemin seldomused state Operation of E&IC system in seldom used state Reliability, Numbers,Hidden Failures Hidden Failure Host Examples Hidden failure host Hidden failure host examples: Control schemes from previous projects Not performing FAT or SAT to minimize cost Removing monitoring equipment Removing monitoring equipment Selecting vendor/contractor based on capital cost Applying firmware without testing Not updating firmware Reliability, Numbers and Statistics How applies to reliability? RELIABILITY INDICES COMPARISON WITH AND WITHOUT HIDDEN FAILURES CONTINGENCES RELIABILITY INDEX NAME HIDDEN FAILURES NOT HIDDEN FAILURES INCLUDED CASE 1 CASE 2 NAME INCLUDED CASE 1 CASE 2 FAILURE PROB 1.1130E-03 1.1880E-03 1.6850E-03 INCREASE 107% 151% FAILURE FREQ [ /YR] 0.4425 0.4586 0.6034 INCREASE 104% 136% FAILURE DURATION [HRS/YEAR] 22.03 22.68 24.68 INCREASE 103% 112% Note: Hidden failure probabilities: Case 1 - 10e-3, Case 2 - 10e-2 Reliability, Numbers and Statistics Reliability Data in Gold Book is a generic Small sample set Sample set collected in minimal certain Sample set collected in minimal certain conditions Calculated indices Calculated indices do not represent reality Calculated indices Calculated indices do not represent reality Paper is focusing on improving VAILABILITY f th EI&C t t li bilit i di of the EI&C system, not reliability indices Summary Summary Formulate practices, standards, and data documentation applicable to your organization Include in RFQ requirements special needs that are not included in industry guides, y g specification, practices Evaluate howthe project should be Evaluate how the project should be executed Assure contractual cooperationwith utility Assure contractual cooperation with utility for post mortem analysis Summary Include provisions in POs allowing for third party to provide testing services without altering contractual responsibilities and obligations Incorporate procedures for updating and p p p g storing advisory bulletins and recall information for all apparatus and IEDs pp Apply automation for communication with IEDs and file management IEDs and file management Summary Implement procedures and software for analysis of the collected data Apply reliable engineering principles for AC ppy g g p p and/or DC control power sources design Test periodically power systemalarms and Test periodically power system alarms and monitoring Start collecting power systemdata apply Start collecting power system data apply time synchronization Conclusions Conclusions Reliability and availability of the EI&C system in process plants: Difficult to estimate Not considers project factors Sensitive to input parameters and environmental conditions Based on very small sample set of data Conclusions The reliability and availability of EI&C system can be improved by focusing on time-tested: Good engineering practices, Appropriate and correct documentation, Apparatus/equipment testing, commissioning and monitoring, Applications of available technologies to performed monitoring tasks with minimum human supervision, Perform tasks routinely to eliminate hidden failures in the system. Conclusions Data collected during monitoring of the EI&C system and equipment could Foresee approaching equipment failure, trigger an alarm i.e. safe time and money! Aid at verifying, adjusting, calibrating power system models for power studies Use data to your advantage!!! Use data to your advantage!!! Do not forget about Test Switches TEST SWITCH IS YOUR FRIEND !!! TEST SWITCH IS YOUR FRIEND !!! Questions? Thank you