(1) Components: Anchor Shackle; Connecting-rod; Thimble; Dead-end Component; Structural


Reinforcing Rods; Grounding Wire Clamp

(2) Installation Method:

1. Assemble Anchor Shackle, Connecting-rod, 2. Fix the Anchor Shackle to the place of
thimble together as shown in the picture. hanging point.

H&C INTERNATIONAL HARDWARE CO.,LIMITED


TEL/FAX:86-591-83316700 EMAIL:sales@hcindustry.com
www.hcihardware.com
H&C INTERNATIONAL HARDWARE CO.,LIMITED

marks

3. Insert one leg of outer rods into the timble. 4. Make both of the two legs of outer rods
parallel to the cable,then make a winding mark
on the corresponding place of the cable
according to the installation mark outside the
rods.

5. Align the end color mark of the structural reinforcing 6. Align the center color mark of the structural
rods with winding mark made in step4,and leave the reinforcing rods of the second suit,even and uncrossed.
short end pointing to the tower and wind the structural
reinforcing rods for 2 circles from the installation mark.

7. Repeat the formor step ,wind the structural 8. For the convenience of installation, when winding
reinforcing rods of the 3rd and 4th to the cable for 2 the parts which are about 20 cm~30cm from the end of
circles ,even and uncrossed. preformed rods, you can separate them into smaller
wisps.

9. Finish winding the end of the preformed rods with 10. Starting from the color mark, wind one leg of the
your hands, making sure that they are winded evenly outer rod for 1~2 pitch.
and leveled.

H&C INTERNATIONAL HARDWARE CO.,LIMITED


TEL/FAX:86-591-83316700 EMAIL:sales@hcindustry.com
www.hcihardware.com
H&C INTERNATIONAL HARDWARE CO.,LIMITED

11.According to the former step ,wind another 12. For the convenience of installation, when winding
leg of the preformed rods for 2 to 3 circles in the the parts which are about 20 cm~30cm from the end of
same way and meanwhile wind the outer rods to preformed rods, you can separate them into smaller
the 20cm to 30cm of the preformed rods. wisps.

13. Connect the grounding wire plier type set and fix 14. Cover it with the grounding wire terminals and
the bolt. lock the nut.

15. The installation is over.

Instruction:
1.Choose the type of Suspension Set according to the specific situation such as the cable’s external
diameter , installation span and the turning angle of the line.
2.Both of structural reinforcing rods and the outer rods of the suspension set must avoid the extrusion or
strong crash to prevent them from deformation.
3.The suspension set is a set fitting and could not be changed casually, and the Tension Set could not be
installed or used repeatedly but could only be installed twice in the process of installation and once
installed ,it couldn’t be torn down and used again.
4.In the process of winding the preformed rods, operate it with hand but not tool in the purpose of not
damaging the fiber optic cable.
5.If have any problems, please contact us.