A numerical study on ground displacement and stress
during and after the installation of deep circular
diaphragm walls and soil excavation Yasushi Arai a, * , Osamu Kusakabe b , Osamu Murata c , Shinji Konishi d a Railway Technical Research Institute, Structure Technology Division, 2-8-38, Hikari-cho, Kokubunji-shi, 185-8540, Tokyo, Japan b Department of Civil & Environmental Engineering, Tokyo Institute of Technology, Japan c Marketing and Business Development Division, Railway Technical Research Institute, Japan d Railway Technology Promotion Division, Railway Technical Research Institute, Japan Received 31 May 2006; received in revised form 5 November 2007; accepted 5 November 2007 Available online 21 February 2008 Abstract Three-dimensional total stress elasto-plastic FEM analysis was conducted to examine ground movement and stress after the instal- lation of circular diaphragm walls and soil excavation within the walls. Combinations involving three dierent wall thicknesses and two dierent excavation sequences within the wall were adopted to inves- tigate dierences in the nal ground movement and the lateral stress in the ground after wall installation and excavation within the wall in multi-layered ground. The analysis results showed that the construction sequence signicantly aects ground displacement and lateral stress behind the wall, implying that the situation even before excavation within the wall is no longer axisymmetric. Reducing the wall thickness also reduced the vertical and circumferential section forces of the wall after excavation within it. 2007 Elsevier Ltd. All rights reserved. Keywords: Circular shaft; Excavation; Diaphragm wall; Installation eects; Three-dimensional FEM analysis 1. Introduction Any large-scale excavation requires retaining structures (such as diaphragm walls) to be installed before soil exca- vation is commenced. Although the inuence of excavation work on the surrounding ground and on existing structures has been commonly evaluated through numerical simula- tion, the main interest focuses on the inuence of the exca- vation process on these areas after retaining structures are installed in the soil. In other words, numerical simulation of the excavation process has generally been carried out under the assumption that the construction of retaining structures prior to excavation will not aect in situ stress conditions. The corresponding numerical technique is sometimes referred to as wished-in-place, where the wall is placed without any change to the in situ stress (e.g. De Moor and Stevenson [1]). This common assumption, how- ever, has been questioned in practice as the inuences of wall installation (referred to as installation eects) are thought to aect the subsequent behavior of the wall and the nal overall condition. The process of constructing diaphragm walls is rather complicated. The wall normally consists of a series of pan- els whose full construction sequence includes excavation under bentonite slurry followed by concreting and hardening. Gunn and Clayton [2] and Kutmen [3] stressed the importance of the eects of installing the retaining wall. Gunn et al. [4] performed two-dimensional FEM analysis, 0266-352X/$ - see front matter 2007 Elsevier Ltd. All rights reserved. doi:10.1016/j.compgeo.2007.11.001 * Corresponding author. Tel.: +81 42 573 7266; fax: +81 42 573 7248. E-mail address: araton@rtri.or.jp (Y. Arai). www.elsevier.com/locate/compgeo Available online at www.sciencedirect.com Computers and Geotechnics 35 (2008) 791807 modeling the full construction sequence of the diaphragm wall followed by concreting and subsequent hardening. De Moor [5] carried out two-dimensional FEM analysis series on a plan (horizontal) section through a series of wall panels for a given depth. Ng et al. [6] conducted pseudo three-dimensional FEM analysis on the eects of dia- phragm wall installation to examine load transfer mecha- nisms, horizontal arching and vertical load transfer. Ng and Yan [7] performed three-dimensional nite dierence analysis of a single-diaphragm wall panel construction of 15 m deep, 8 m long and 0.6 m wide, and later extended this to three-panel construction (Ng and Yan [8]). Gourve- nec and Powrie [9] published the results of three-dimen- sional FEM analysis of a straight diaphragm wall consisting of several wall panels and measuring 15 m deep, 2.57.5 m long and 1 m wide contained in sti clay. All the methods of analysis outlined above, however, model the wall installation stage but not the subsequent soil excavation stage. Furthermore, the notional prototype of a diaphragm wall in the previous analysis involved a long, straight wall of moderate depth installed in sti clay. In recent years, the construction of axisymmetric vertical shafts for shield tunnels and large-scale circular under- ground facilities as deep as 70-100 m has increased (Goto et al. [10], Ariizumi et al. [11]). Muramatsu and Abe [12] carried out eld measurements focusing on the peripheral ground deformation when a diaphragm wall was installed and when soil within the wall was excavated. Little attention has been paid to examining the eects that deep circular diaphragm wall construction has on ground conditions prior to the excavation process in prac- tical design. Analysis covering the complete process is required in order to examine the eects of the construction sequence on ground conditions and stress distribution in the wall, including the eects of installation. In this research, we performed three-dimensional total stress elasto-plastic FEM analysis to examine ground movement and stress in the ground after installation of circular diaphragm walls and soil excavation within the walls. We selected a notional prototype for this analysis to model a previous deep circular diaphragm wall con- struction for an underground river project in Tokyo, with 32 m diameter, 85.5 m wall length and 1.2 m wall thickness. The ground conditions selected are those typi- cally encountered in the Tokyo Bay area. Two factors considered are the thickness of the diaphragm wall and the type of soil excavation within the wall, and we dis- cussed the results to examine the eect due to construc- tion sequence. In the foregoing project, earth and water pressures, as well as stresses in the diaphragm wall are being monitored to verify and improve the current design calculations. The monitoring data has attracted the attention of those designing the future Central Linear Shinkansen and Out- Ring expressway projects, and this study will provide fur- ther insight into the properties of circular diaphragm wall construction. 2. Numerical modeling of diaphragm wall construction and soil excavation within the wall 2.1. Aims of this research Numerical modeling of the full construction sequence for diaphragm walls and subsequent soil excavation involves at least three numerical modeling phases. The rst phase is a modeling process to construct a single wall panel, including excavation under bentonite slurry, followed by concreting and hardening. The second phase involves installing the other wall panels and joining several single panels to form a complete diaphragm wall structure. The third phase is the main soil excavation in front of or within the wall. 2.2. Notional prototype The notional prototype for the wall adopted in this study involves a circular diaphragm wall constructed in typical ground conditions in the Tokyo Bay area, where a layer of soft, normally consolidated clay is underlaid by a sti sand layer on base mud rock. The dimensions and soil parameters used in the analysis were selected on the basis of previous experience and the current design practice for axisymmetric shafts in Japan. The notional reference prototype has a circular shaft with an internal diameter of 32 m, a wall thickness of 1.2 m and an embedded depth of 85.5 m. The depths of the clay and sand layers are 25.6 m and 40.8 m respectively, and the layer below the sand layer is base mud rock. The under- ground water level is assumed to be the surface ground level referred to in previous cases of construction. In this analysis, the circular wall was composed of twelve initial panels and twelve subsequent panels, and the circular wall was modeled as a polygonal shape with 48 sides. The initial panels consist of three gutters while the subsequent ones are comprised of a single gutter, mean- ing that the circular diaphragm wall consists of 48 gutters in total. Each gutter has a length of 2.09 m, a depth of 85.5 m and a typical thickness of 1.2 m. Japanese practice is to construct the subsequent panels (which join the initial panels to form a diaphragm wall) using an eective con- crete cutting method. This results in a joint so ecient at transferring circumferential forces that the circumferential stiness of the wall (both axial and bending) can be assumed to match the vertical stiness, referring to Japa- nese Standard Design Code [13]. Consequently, such an assumption has been made in the examples of analysis pre- sented in this paper, and the wall was modeled with isotro- pic stiness properties. 2.3. FEM analysis 2.3.1. Outline of FEM model Three-dimensional numerical simulations were carried out using a commercially available FEM analysis code 792 Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 named MARC. Fig. 1a shows the FEM mesh with a vol- ume of 200 m in depth and 400 m 400 m in area, and the circular shaft with an internal diameter of 32 m is located in the center of the analysis zone (see Fig. 1b and c). Such a large zone was selected to avoid any measurable eects from the boundary in the nal results. In this research, we use hexahedral elements for three-dimensional FEM. These elements have eight nodes and eight integra- tion points, and the Gaussian integration method was applied to them. The analyzed zone has 23,775 nodes and 21,075 elements in total. The displacement of nodes along the side boundaries is xed in the X-direction, while the dis- placement of those along the bottom boundary is xed in the Z-direction. The clay and sand were assumed to behave as an elasto-perfectly plastic body with the MohrCou- lomb failure criterion, obeying the associated ow rule. The base mud rock was assumed to be a linear elastic body. The ground is divided into 14 horizontal layers whose soil properties are listed in Table 1. These properties were selected to represent realistic values on the basis of previ- ous literature (Waseda University [14]). The way in which multiple wall panels are connected is also an important factor to consider. Large-scale circular diaphragm walls are typically formed by rst placing a number of initial panels with equal spacing, and then con- necting them with subsequent panels to ll the spaces (sche- matically illustrated in Fig. 2). Each initial panel is commonly composed of three gut- ters, and is constructed in four stages as shown in Fig. 3. The rst gutter (Gutter 1) is excavated and lled with slurry, the third gutter (Gutter 3) is formed in the same way, and the second gutter (Gutter 2) is then used to con- nect the three gutters. A reinforced steel cage is then inserted, and concrete slurry is poured into it. The subse- quent panel (consisting of a single gutter) is made in such a way that the gutter is excavated and lled with slurry, (a) An entire finite-element mesh (b) A half finite-element mesh (c) Detail finite-element mesh of the circular shaft 200m Z Y X 400m 400m 0. Layer 1 G.L.0.0 Layer 2 Layer 3 Layer 4 Layer 5 Layer 6 Layer 7 Layer 8 Layer 9 G.L. 52.7 Soil excavation layer 400m 200m Z Y X 85.5m 32m 200m Detailed in Fig.1(c) Fig. 1. Three-dimensional nite-element mesh. Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 793 and then a reinforced steel cage is inserted and concrete slurry is poured into it. 2.3.2. Modeling the wall panel construction In the numerical simulation, the construction sequence of the initial panel is modeled in the following stages: Stage 1 (Ben1): Soil elements in Gutter 1 are removed, and bentonite slurry with a pressure increasing linearly with depth is applied along the excavated area. The slurry has a unit weight of 11.0 kN/m 3 . Stage 2 (Ben13): Soil elements in Gutter 3 are removed, and the slurry pressure is applied along the excavated area. Stage 3 (Ben123): Soil elements in Gutter 2 are removed, and the slurry pressure is applied along the excavated area. Stage 4 (Con123): The slurry pressure is removed, and elastic elements are placed in the exca- vated area to model the solid concrete wall. The self-weight of a unit weighing 24.0 kN/m 3 with a Youngs modulus of 27 MN/m 2 and a Poisson ratio of 0.2 is then dened in the elastic elements. From Stage 3 (Ben123) to Stage 4 (Con123), the pres- sure along the excavated wall may vary with time. Lings, Table 1 Soil properties Soil type (index) Layer index Depth (G.L.- m) E (MN/m 2 ) Poisson ratio C (kN/m 2 ) / (deg) Clay (C) C1 0.05.1 4.9 0.48 19.6 0 C2 5.110.2 6.1 0.48 24.2 0 C3 10.215.3 7.2 0.48 28.8 0 C4 15.320.4 8.4 0.48 33.4 0 C5 20.425.6 9.5 0.48 38.0 0 Sand (s) S1 25.630.7 174.1 0.30 30.0 35 S2 30.735.8 190.4 0.30 30.0 35 S3 35.842.9 212.1 0.30 30.0 35 S4 42.952.7 240.8 0.30 30.0 35 S5 52.766.4 278.2 0.30 30.0 35 Base mud rock (B) B1 66.485.5 400.0 0.48 B2 85.5112.0 400.0 0.48 B3 112.0148.8 400.0 0.48 B4 148.8200.0 400.0 0.48 Initial panel Subsequent panel Thinner circle: Three construction areas 85.5m 32m I I I I I I Fig. 2. Dimensions of the deep circular diaphragm wall (not to scale). Gutter 1 Gutter 2 Gutter 3 Stage1 Stage2 Stage3 Stage4 Gutter 1 Bentonite (Ben1) Gutters 1, 3 Bentonite (Ben13) Gutters 1, 2, 3 Bentonite (Ben123) Gutters 1, 2, 3 Concrete (Con123) Fig. 3. Modeling construction sequence of the single initial panel (not to scale). 794 Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 Ng and Nash [15] adopted bi-linear distribution with depth, concrete slurry pressure at the upper part and bentonite slurry pressure at the lower part using the con- cept of critical height suggested in CIRIA report 108 (Clear 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 1 4 8 35 34 3 3 3 2 3 1 3 0 2 9 2 8 2 7 2 6 2 5 2 4 2 3 2 2 2 1 2 0 1 9 1 8 1 7 1 6 1 5 1 4 1 31 2 1 1 1 0 9 8 7 6 5 4 3 2 1 4 8 4 7 4 6 4 5 4 4 4 3 4 2 4 1 4 0 39 38 37 36 S-9 I - 1 1 S - 8 S - 7 S - 6 S - 5 S - 4 S - 3 S - 2 S - 1 S - 1 2 S - 1 1 S -1 0 I-10 I-9 I - 8 I - 7 I - 6 I - 5 I - 4 I - 3 I - 2 I - 1 I - 1 2 (Legends) I: Initial Panel, S: Subsequent Panel (Step F: Initial panels complete Step L: Diaphragm wall complete) Step A (Serial Step 4) Step B (Serial Step 5) Step C (Serial Step 6)
I II III Step D (Serial Step 10) Step E (Serial Step 11) Step F (Serial Step 12) Step G (Serial Step 16) Step H (Serial Step 17) Step I (Serial Step 18) Step J (Serial Step 22) Step K (Serial Step 23) Step L (Serial Step 24) Fig. 4. Installation of panels at selected steps of the diaphragm wall. Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 795 and Harrison [16]). In the present simulation, this method was not adopted as the concept of critical height is consid- ered applicable only up to a depth of 30 m. From experi- ence gained in Japan, the critical height may also change with the pouring rate of the concrete slurry, the slump value and the temperature when concreting is carried out (Arii [17], JSCE [18]). The construction sequence of the subsequent panels is modeled only in Stages 1 (Ben1) and 4 (Con123). In Stage 4, the boundaries between the concrete elements and the surrounding soil elements are assumed to be continuous. Fig. 4 shows the status of panel installation at selected steps for discussion of the FEM analysis. The diaphragm wall of this shaft is composed of 12 initial panels and 12 subsequent panels, meaning that 24 steps are required to complete the structure. In determining the installation sequence of each panel, the area of 360 was divided into the three areas of I, II and III as shown in Figs. 2 and 4. 0. (a) Type A (b) Type B 1 2 2 1 3 1 4 2 Fig. 5. Types of soil excavation within the diaphragm wall. 2 5 . 6 m C l a y ( C ) 4 0 . 8 m S a n d ( S ) 1 9 . 1 m B a s e
m u d
r o c k ( B ) 8 5 . 5 m 0.3m or 0.6m or 1.2m Initial panel Subsequent panel G u t t e r 3 G u t t e r 2 G u t t e r 1 Layer B1(G.L.-75.95m) Selected element Layer S3(G.L.-39.35m) Selected element Layer C3(G.L.-12.75m) Selected element 2 5 . 6 m C l a y ( C ) 4 0 . 8 m S a n d ( S ) 1 9 . 1 m B a s e
m u d
r o c k ( B ) 8 5 . 5 m 0.3m or 0.6m or 1.2m Initial panel Subsequent panel G u t t e r 3 G u t t e r 2 G u t t e r 1 Layer B1(G.L.-75.95m) Selected element Layer S3(G.L.-39.35m) Selected element Layer C3(G.L.-12.75m) Selected element Fig. 6. Geometry of the initial and subsequent panels and selected elements for lateral stress examination (not to scale). Table 2 Cases analyzed Diaphragm wall thickness (index) Soil excavation type (index) Case index 1.2 m (t12) Type A t12-A Type B t12-B 0.6 m (t06) Type A t06-A Type B t06-B 0.3 m (t03) Type A t03-A Type B t03-B 796 Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 In the rst phase, the initial panels were installed in a clock- wise direction maintaining an interval of 120 for each one. In the second phase, subsequent panels were installed in a similar way to avoid concentrating the installation eects Lateral stress : kN/m 2 0 10 20 30 40 50 60 70 80 90 0 250 500 750 1000 1250 1500 D e p t h
:
m (c) Behind Gutter 3 Cl ay Sand Base mud rock Lateral stress : kN/m 2 0 10 20 30 40 50 60 70 80 90 0 250 500 750 1000 1250 1500 D e p t h
:
m Ben1 Ben13 Ben123 Con123 Initial total horizontal stress Ben1 Ben13 Ben123 Con123 Initial total horizontal stress (a) Behind Gutter 2 Lateral stress : kN/m 2 0 10 20 30 40 50 60 70 80 90 0 250 500 750 1000 1250 1500 Ben1 Ben13 Ben123 Con123 Initial total horizontal stress (b) Behind Gutter 1 Clay Sand Base mud rock Clay Sand Base mud rock D e p t h
:
m Toe Toe Toe Fig. 7. Lateral total stress distribution with depth for various stages of initial panel construction: eect of position of gutters. Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 797 of each panel locally as in actual diaphragm wall construction. 2.3.3. Modeling soil excavation within the diaphragm wall Once the diaphragm wall is installed in the ground to an embedded depth of 85.5 m, soil excavation within the wall is carried out up to a depth of 52.7 m in nine layers as illus- trated in Fig. 1c. The numerical simulation of the excava- tion process is to remove the elements of each layer. The type of soil excavation may aect the nal condition of the surrounding soil, and two possible types were consid- ered. Type A involves excavating a quarter of each layer in a clockwise direction, while in Type B two opposite quarters of each layer are excavated at the same time, as illustrated in Fig. 5. 2.3.4. Cases analyzed Analysis was carried out for the two major possible con- trolling factors of wall thickness (1.2 m, 0.6 m, 0.3 m) and the type of excavation within the wall (Types A and B). These three dierent wall thicknesses and two dierent excavation types (totaling six cases) were examined, as summarized in Table 2. 3. Results and discussion 3.1. Lateral stress changes during initial panel construction One of the issues in terms of the eects of the installation process is its inuence on lateral stress distribution along the wall panel depth (as previously examined by Ng and Normalized distance from the edge of Gutter 2 by embedded depth 0.6 0.8 1.0 1.2 1.4 1.6 1.8 0.0 0.5 1.0 1.5 2.0 L a t e r a l
s t r e s s
r a t i o Layer C3-Ben123 Layer C3-Con123 Layer S3-Ben123 Layer S3-Con123 Layer B1-Con123 Layer B1-Ben123 Fig. 9. Lateral stress at Layers C3, S3 and B1 normalized by the initial total horizontal stress (lateral stress ratio) with distance from behind Gutter 2 towards the outside: eect of construction sequence. Earth pressure coefficient 0 10 20 30 40 50 60 70 80 90 100 0.4 0.6 0.8 D e p t h
:
m t03-Ben123 t03-Con123 t06-Ben123 t06-Con123 t12-Ben123 t12-Con123 Initial total horizontal stress Clay Sand Base mud rock 1 Toe Fig. 8. Eect of initial panel construction on lateral stress in terms of earth pressure coecient behind Gutter 2. 798 Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 Yan [8] and Gourvenec and Powrie [9]). The soil stresses and those of the diaphragm wall are the mean values of the stresses at each integration point in the selected ele- ments. Fig. 6 shows detailed element meshes around an ini- tial panel. Lateral stress was examined on three selected elements behind gutters at each ground layer (Layers C3, S3 and B1). Fig. 6 shows the geometry of the initial and subsequent panels in question, and Fig. 7 shows the total lateral stress distribution with depth at various stages of initial panel construction behind each gutter. The gure shows that along Gutter 2 the lateral stress at Layers C3 and B1 is less than the initial total horizontal stress, while the lateral stress at Layer S3 is greater than the initial total horizontal stress. Incidentally, before executing the analysis of the diaphragm wall installation, vertical stress r V corre- sponding to the force of gravity was set at each integration point of the nite element of the soil, and horizontal stress r h corresponding to the Poisson ratio was set at the same integration point. In this research, the horizontal stress was assumed to be the initial lateral stress, and this analyt- ical process was dened as the initial stress FEM analysis. When the stress distribution patterns along the three gutters are compared, it is clear that those along Gutters 1 and 3 are more or less identical, while the pattern along Horizontal displacement : mm 0 10 20 30 40 50 60 70 80 90 -30 -25 -20 -15 -10 -5 5 10 D e p t h
:
m Lv2-t03-Ben123 Lv2-t03-Con123 Lv2-t12-Ben123 Lv2-t12-Con123 Clay Sand Base mud rock (+) (-) Lv2 0 Toe Fig. 11. Change in horizontal displacement distribution with depth during installation of the rst initial panel: eect of wall thickness and construction sequence. Horizontal displacement : mm 0 10 20 30 40 50 60 70 80 90 -30 -25 -20 -15 -10 -5 5 10 D e p t h
:
m Lv1-t12-Ben123 Lv1-t12-Con123 Lv2-t12-Ben123 Lv2-t12-Con123 Lv3-t12-Ben123 Lv3-t12-Con123 Lv4-t12-Ben123 Lv4-t12-Con123 Clay Sand Base mud rock (+) (-) Lv4 Lv3 Lv2 Lv1 0 Toe Fig. 10. Change in horizontal displacement distribution with depth during installation of the rst initial panel: eect of construction sequence. Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 799 Gutter 2 (located in the middle) diers, particularly above the toe of the wall panel. This implies that stress redistribu- tion and concentration occurs behind Gutter 2 during the construction process from Ben13 to Ben123. Specically, lateral stress decreases slightly in the construction process from Ben1 to Con123 in the upper clay layer, and suddenly increases in the construction stage from Ben13 to Ben123 in the sand layer. Fig. 8 summarizes the eects of initial panel construction on lateral stress in terms of the earth pressure coecient (lateral total stress/vertical total stress) along Gutter 2. The reason for choosing Gutter 2 is that the major inuence of the initial panel construction process appears behind the middle gutter of the wall panel. Initial panel construction causes a decrease in lateral stress in the clay layer and an increase in the sand layer, and these trends become more marked when the panel wall is thicker, as seen in Fig. 8. It should be noted here that the lateral stress distribution in multi-layered ground is dierent from that in single-layer ground. It is also important to identify the zone that is aected by wall panel installation. Fig. 9 plots the lateral stress at Layers C3, S3 and B1 normalized by the initial total hori- zontal stress (i.e. the lateral stress ratio) with distance from the outer surface of Gutter 2. The lateral stress ratio varies with the soil layer; the change is less marked during con- creting (from Ben123 to Con123), as shown in Fig. 9. The lateral stress ratios at Layers C3 and B1 decrease from 1.0 to 0.65 and 0.80 respectively, and the ratio at Layer S3 increases from 1.0 to 1.7 towards the outer surface of Gut- ter 2 at the time of wall panel installation. These lateral stress ratios change rapidly with distance at about 0.2D (where D is the depth of the wall panel) from the outer 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 L a t e r a l
s t r e s s
r a t i o (t12) Behind Gutter 16 in Layer C3 Behind Gutter 17 in Layer C3 Behind Gutter 18 in Layer C3 Behind Gutter 19 in Layer C3 Behind Gutter 20 in Layer C3 In i A B C D E F G H I J K L Installation of panels at selected steps Fig. 13. Increase and decrease of lateral stress behind existing panel at Layer C3 during the whole process of panel construction. Normalized distance from the outer surface of gutter by embedded depth -10 -8 -6 -4 -2 0 2 4 0.0 0.2 0.4 0.6 0.8 1.0 1.2 V e r t i c a l
d i s p l a c e m e n t
:
m m Lh1-t03-Ben123 Lh1-t03-Con123 Lh1-t12-Ben123 Lh1-t12-Con123 Lh2-t03-Ben123 Lh2-t03-Con123 Lh2-t12-Ben123 Lh2-t12-Con123 (+) (-) Lh1 Lh2 (+) (-) (+) (-) Lh1 Lh2 (+) (-) Lh1 Lh2 (-) (-) (-) Fig. 12. Dierence in the vertical displacement prole on the ground surface along Lh1 and Lh2: eect of wall thickness and construction sequence. 800 Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 surface of Gutter 2 for Layers C3, B1 and S3. This is con- sistent with the previous results obtained by Ng and Yan [8] showing that the zone of rapid change is within 0.2D. The distance required to recover the initial stress condition in the present analysis is about 0.5D for Layers C3 and B1, and 0.2D for S3. These results are not always the same as those found by Ng and Yan [8], which show that the dis- tance is about 1.0D. This nding shows that the previous results of two-dimensional analysis may not be wholly applicable to circular diaphragm walls in multi-layered ground. 3.2. Horizontal and vertical displacement proles during initial panel installation There must be horizontal and vertical displacement in the ground associated with changes in stress near the panels. The selected positions of horizontal and vertical Horizontal displacement : mm 0 10 20 30 40 50 60 70 80 90 -35 -30 -25 -20 -15 -10 -5 0 10 D e p t h
:
m (t03) Lv19-Initial panels complete Lv19-Diaphragm wall complete Lv20-Initial panels complete Lv20-Diaphragm wall complete (t12) Lv19-Initial panels complete Lv19-Diaphragm wall complete Lv20-Initial panels complete Lv20-Diaphragm wall completet Clay Sand Base mud rock (+) (-) Lv20 Lv19 5 Toe Fig. 15. Horizontal displacement proles with depth along Lv19 and Lv20 during the construction of initial and subsequent panels: eect of wall thickness. I - 5 1 3 1 5 1 4 I - 4 1 6 S - 4 I - 6 2 4 2 3 2 2 2 1 2 0 S - 5 S - 6 I - 5 1 3 1 5 1 4 I - 4 1 6 S - 4 I - 6 2 4 S - 5 S - 6 2 0 I - 5 I - 4 1 6 S - 4 I - 6 2 4 2 0 S - 5 S - 6 Step A Step B Step D I - 5 I - 4 1 6 S - 4 I - 6 2 4 S - 5 S - 6 I - 5 I - 4 S - 4 I - 6 2 4 S - 5 S - 6 (Legends) I S : Newly installed panel : Already installed panel Step G Step J : Subsequent Panel : Initial Panel Fig. 14. Increase and decrease of lateral stress behind existing panel at Layer C3 during adjacent panel construction. Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 801 displacement for the initial panel are indicated as explan- atory notes on each related gure (see Figs. 1012). Lv1, Lv2, Lv3 and Lv4 are the lines for the horizontal dis- placement prole behind the panel, while Lh1 and Lh2 are for the vertical displacement proles. Figs. 10 and 11 show the change in horizontal displacement distribu- tion with depth during installation of the initial panel. Fig. 11 shows the eect of wall panel thickness on hori- zontal displacement distribution with depth, particularly in the clay layer. Corresponding to the lateral stress dis- tribution shown in Figs. 7 and 8, the soil in the clay layer moves inward, whereas that in the sand layer moves outward. The magnitude of horizontal displacement is signi- cantly greater along Lv2 and Lv3 and smaller along Lv1 and Lv4, regardless of the layers. Increased wall thickness requires wider excavation, causing larger horizontal dis- placement in the clay layer as seen in Fig. 11. A clear dierence in the vertical displacement prole on the ground surface along Lh1 and Lh2 is also seen in Fig. 12, implying that settlement may be observed behind the middle of the wall panel, and a slight heave may occur behind the outer surface of the wall panel. In particular, Fig. 12 indicates the eects of wall panel thickness on the vertical displacement distribution with distance. Normalized distance from the outer surface of panel by embedded depth -30 -25 -20 -15 -10 -5 0 0.0 0.5 1.0 1.5 2.0 H o r i z o n t a l
d i s p l a c e m e n t
:
m m (t12) Lh19-Initial panels complete Lh19-Diaphragm wall complete Lh20-Initial panels complete Lh20-Diaphragm wall complete (+) (-) Lh19 Lh20 Fig. 17. Horizontal displacement prole on the ground surface during the construction of initial and subsequent panels. Normalized distance from the outer surface of panel by embedded depth -10 -8 -6 -4 -2 0 2 4 6 0.0 0.5 1.0 1.5 2.0 V e r t i c a l
d i s p l a c e m e n t
:
m m (t03) Lh19-Initial panels complete Lh19-Diaphragm wall complete Lh20-Initial panels complete Lh20-Diaphragm wall complete (t12) Lh19-Initial panels complete Lh19-Diaphragm wall complete Lh20-Initial panels complete Lh20-Diaphragmwallcomplete (+) (-) Lh19 Lh20 + (-) (+) (-) Lh19 Lh20 (-) (-) ( ) (-) Fig. 16. Vertical displacement proles on the ground surface along Lh19 and Lh20 during the construction of initial and subsequent panels: eect of wall thickness. 802 Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 It is of practical importance to know the zone aected by the installation of the wall panel. In this analysis, the inuence of diaphragm wall construction ceases at a dis- tance approximately equal to one wall-panel depth (1.0D), which is consistent with the results of the centrifuge model tests reported by Powrie and Kantartzi [19]. The results obtained by Gourvenec and Powrie [9] indicated that avoiding the inuence of wall installation requires a distance of up to 40 m from the wall face. This corresponds to more than 2.0D, which is much less than the results obtained from two-dimensional plane strain nite element analysis. Table 3 Ratios of inward lateral stress to outward lateral stress Layer index t03-B t06-B t12-B Maximum Minimum Maximum Minimum Maximum Minimum C3 1.13 0.90 1.19 0.83 1.26 0.56 S3 1.03 0.98 1.01 0.95 1.00 0.93 Lateral stress : kN/m 2 0 10 20 30 40 50 60 70 80 90 -1500 -1250 -1000 -750 -500 -250 0 D e p t h
:
m t03 - Minimum t03 - Maximum t06 - Minimum t06 - Maximum t12 - Minimum t12 - Maximum Initial total horizontal stress (a) Inward Lateral stress : kN/m 2 0 10 20 30 40 50 60 70 80 90 0 250 500 750 1000 1250 1500 D e p t h
:
m t03 - Minimum t03 - Maximum t06 - Minimum t06 -Maximum t12 - Minimum t12 - Maximum Initial total horizontal stress (b) Outward Clay Sand Base mud rock Clay Sand Base mud rock Toe Toe Fig. 18. Maximum and minimum lateral stress distribution inward and outward from the wall with depth after completion of diaphragm wall: eect of wall thickness. Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 803 3.3. Lateral stress distribution and horizontal and vertical displacement proles during the installation of initial and subsequent panels Fig. 13 demonstrates how the lateral stress ratios behind Gutters 1620 uctuate in the upper clay layer (Layer C3) during the whole process of wall panel construction. The reason for this uctuation is considered to be the local for- mation of arching and stress transfer during the process of construction, as is schematically illustrated in Fig. 14. In the construction of initial panel No. 5, Gutter 17 is exca- vated rst, followed by Gutters 19 and 18. At Step A indi- cated in Fig. 14, the lateral stress ratio behind Gutter 18 decreases from 1 to 0.6, while the ratio behind Gutters 17 and 19 increases from 1 to 1.1. At this stage there is no inuence from lateral stress in neighboring areas (the lat- eral stress ratio is 1 at the location of Gutters 16 and 20). At Step B, initial panel No. 6 is constructed, resulting in an increase in the lateral stress ratio only behind Gutter 19, the nearest gutter. Similarly, at Step G, subsequent panel No. 5 is constructed, resulting in an increase of the lateral stress ratio only behind Gutter 20, the nearest gut- ter. In the nal step (Step L), the lateral stress ratio nally becomes 1.2 behind Gutter 17, 1.1 behind Gutters 19 and 20, 0.9 behind Gutter 16 and 0.6 behind Gutter 18. The displacement at initial panel No. 5 shown in Figs. 4 and 14 is to be examined. The locations of the line of inter- est in this consideration are indicated as explanatory notes on each related gure (see Figs. 1517). Fig. 15 shows hor- izontal displacement proles with depth along Lv19 and Lateral stress : k/m 2 0 10 20 30 40 50 60 70 80 90 0 250 500 750 1000 1250 1500 D e p t h
:
m t12-A-Maximum t12-B-Maximum t12-A-Minimum t12-B-Minimum Initial total horizontal stress before soil excavation Clay Sand Base mud rock Fig. 20. Maximum and minimum lateral stress acting on the outside wall face during the soil excavation stage: eect of soil excavation type. Lateral stress : kN/m 2 0 10 20 30 40 50 60 70 80 90 0 250 500 750 1000 1250 1500 D e p t h
:
m t03-B t06-B t12-B Initial total horizontal stress Clay Sand Base mud rock before soil excavation Toe Fig. 19. Lateral stress distribution behind the wall with depth at the center of initial panel No. 5 after soil excavation: eect of wall thickness. 804 Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 Lv20 during initial and subsequent panel construction for various wall thicknesses. The general trends at Lv20 on the outer surface of wall panel No. 5 are similar to those of Lv4 (see Fig. 10), and the trends at Lv19 in the middle are similar to those of Lv3 (see Fig. 10). The main dierences in the displacement prole are seen in the clay layer and in the increased hori- zontal displacement with thicker walls. Fig. 16 shows the vertical displacement prole with various wall thicknesses at the ground surface level. The prole is largely dependent on the relative location of the wall panel. Settlement is observed at Lh19, and heave is seen at Lh20. It is interest- ing to note that the magnitude of the dierential displace- ment between Lh19 and Lh20 remains the same for dierent wall thicknesses, suggesting that wider wall exca- vation leads to larger heave, compensating for the poten- tially large settlement. Muramatsu et al. [12] reported the results of eld mea- surements for displacement during circular shaft construc- tion. Although the ground and construction conditions were dierent from those used in this study, comparison of the order of magnitude may be useful for verication of the present study. The thickness of the soft ground was 8 m from the surface in the eld, while the present study assumed a thickness of 25 m from the surface. The predicted vertical displacement was 2.0 mm (see Fig. 16 at Lh20 (t12)) compared to the corresponding eld value of 3.0 mm. The prediction in this study for horizontal displacement at 5.5 m from the outer surface of the wall at the time of diaphragm wall installation was 15.0 mm (see Fig. 17 at Lh20), which is comparable to 5.0 mm of horizontal dis- placement at the corresponding location in the eld measurement. 3.4. Lateral stress distribution and horizontal displacement distribution after the completion of diaphragm walls The values of maximum and minimum lateral total stress distribution with depth inward and outward for the circular diaphragm wall are presented for various wall thicknesses in Fig. 18. The value of the initial total horizon- tal stress with depth is also plotted in the gure, and is found to be almost the average of the maximum and min- imum lateral stress levels both inward and outward. The Horizontal displacement : mm 0 10 20 30 40 50 60 70 80 90 -20 -15 -10 -5 5 D e p t h
:
m (t12-Diaphragm wall complete) x1 y1 x2 y2 (t12-B-Soil excavation complete) x1 y1 x2 y2 Clay Sand Base mud rock x2 x1 y1 y2 0 Toe Fig. 22. Change in horizontal displacement distribution with depth along x1, x2, y1 and y2 at the time when diaphragm wall construction stage and soil excavation stage were completed. Normalized internal displacement by shaft diameter 0 10 20 30 40 50 60 70 80 90 -0.0006 -0.0004 -0.0002 0.0000 D e p t h
:
m Lx-t03-B Lx-t06-B Lx-t12-B Ly-t03-B Ly-t06-B Ly-t12-B Clay Sand Base mud rock Ly Lx Toe Fig. 21. Internal displacement divided by shaft diameter with depth at Lx and Ly after soil excavation: eect of wall thickness. Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 805 inuence of the wall thickness is noticed in the clay layer. The thicker the wall is, the greater the dierence between the maximum and minimum lateral stress values. Table 3 summarizes the range of ratios of lateral stress on the internal wall face to the lateral stress on the outer wall face for various wall thicknesses at the clay and sand layer. It can be seen that the thinner the wall, the smaller the range of the ratio. 3.5. Lateral stress changes during and after the soil excavation stage No literature is available relating to the numerical study of installation eects, including the installation stage and the subsequent soil excavation stage. Fig. 19 shows the lat- eral stress distribution with depth for various wall thick- nesses behind the center of initial panel No. 5, indicating that the value of earth pressure diers considerably from that of the initial total horizontal stress, and that the eect of the wall thickness is as small as 20 kN/m 2 . The maxi- mum and minimum lateral stresses acting on the outer wall face during the soil excavation stage for a wall thickness of 1.2 m are plotted with depth for the two types of soil exca- vation in Fig. 20. It is noted that the type of soil excavation has no eect on the lateral stress distribution for either the maximum or minimum values. The initial total horizontal stress of each soil layer is also close to the maximum value for the soft clay layer, and gives approximately the mean value of the maximum and minimum values for sti-layer ground. The type of excavation is also predicted to have no eect on the internal horizontal displacement prole with depth. Fig. 21 shows the internal horizontal wall displacement divided by the shaft diameter with depth at the lines of Lx and Ly indicated as explanatory notes on the gure after soil excavation for various wall thicknesses. The magnitude of the maximum inward movement is in approximate inverse proportion to the wall thickness. Fig. 22 shows the changes in horizontal displacement distribution with depth at x1, x2, y1 and y2 indicated as explanatory notes on the gure at the times when the dia- phragm wall construction stage and soil excavation stage were completed. In these cases, during the construction stage the horizontal displacement gradually accumulates towards the inside of the wall in the clay layer and the base mud rock layer, whereas horizontal displacement in the sand layer occurs in the opposite direction. However, once the excavation stage starts, horizontal displacement only occurs toward the inside of the wall at all depths. The mag- nitude of the accumulated displacement in the clay layer is in the order of y2, x2, y1 and x1, clearly indicating that the magnitude of such displacement depends on the construc- tion sequence. The ratios of the displacement after dia- phragm wall completion to the accumulated displacement in clay are 0.15 at x1 and 0.1 at x2, x3 and x4. Corresponding to the wall deection, the vertical bend- ing moment changes with depth. Fig. 23 shows the vertical bending moment (M v ) distribution with depth for various wall thicknesses, and indicates that thinner walls have a smaller bending moment, although the overall pattern of the bending moment distribution remains similar. 4. Conclusions The processes of installing a circular diaphragm wall and excavating soil within the wall were analyzed as three-dimensional events. The main ndings on lateral stress in the ground and ground movements, examined by three-dimensional FEM analysis, are as follows: (1) Numerical evaluation using FEM analysis was suc- cessfully carried out to investigate the eects of M v : kNm/m 0 10 20 30 40 50 60 70 80 90 -50 50 100 150 D e p t h
:
m (t03) Gutter 5 Gutter 6 Gutter 7 (t12) Gutter 5 Gutter 6 Gutter 7 Clay Sand Base mud rock 0 Fig. 23. Vertical bending moment distribution with depth at initial panels No. 2: eect of wall thickness. 806 Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 installing circular diaphragm walls, including the detailed installation stage and the subsequent soil excavation stage. The realistic multi-layered ground used has a more complicated lateral stress distribu- tion. Results from single-layer ground may not have provided an overall picture of this complexity. (2) The results of the analysis showed that the situation even prior to excavation within the wall is no longer axisymmetric. This non-uniform characteristic with periodic uctuations was formed at an early stage of the initial panel construction. (3) The inuence of the type of soil excavation within the wall may be negligible. (4) The maximum value of lateral stress after excavation within the wall was greater than the initial total hor- izontal stress, and the minimum was smaller than the initial total horizontal stress. The mean of the maxi- mum and minimum values was found to be close to the initial total horizontal stress. (5) Reducing the wall thickness resulted in a decrease in the vertical section forces of the wall after excavation within it. Acknowledgements The authors are grateful to Dr. Shikai Du for his help with nite element analysis using MARC, and to Dr. Mo- toi Iwanami and Keiji Oishi for their help with the outline of the construction sequence for the circular shaft. References [1] De Moor EK, Stevenson MC. Evaluation of the performance of a multi-propped diaphragm wall during construction. In: Mair, Taylor, editors. Proc. int. symposium on geotechnical aspects of underground construction in soft ground. Balkema; 1996. p. 1116. [2] Gunn MJ, Clayton CRI. Installation eects and their importance in the design of earth-retaining structures. Geotechnique 1992;42(1):13741. [3] Kutmen G. The inuence of the construction process on bored piles and diaphragm walls: a numerical study, MPhil thesis, University of Surrey; 1986. [4] Gunn MJ, Satkunananthan A, Clayton CRI. Finite element modeling of installation eects. Retaining structures. London: Thomas Telford; 1993. p. 4655. [5] De Moor EK. An analysis of bored pile/diaphragm wall installation eects. Geotechnique 1994;44(2):3417. [6] Ng CWW, Lings ML, Simpson B, Nash DFT. An approximate analysis of the three-dimensional eects of diaphragm wall installa- tion. Geotechnique 1995;45(3):497507. [7] Ng CWW, Yan RWM. Stress transfer and deformation mechanisms around a diaphragm wall panel. J Geotech Geoenviron Eng ASCE 1998;124(7):63848. [8] Ng CWW, Yan RWM. Three-dimensional modeling of a diaphragm wall construction sequence. Geotechnique 1999;49(6):82534. [9] Gourvenec SM, Powrie W. Three-dimensional nite-element analysis of diaphragm wall installation. Geotechnique 1999;49(6):80123. [10] Goto S, Muramatsu M, Sueoka T, Saka F, Yabe H, Watanabe H, et al. Ground movement earth and water pressures due to shaft excavations. In: Fujita, Kusakabe, editors. Proc int symposium on underground construction in soft ground. Balkema; 1995. p. 1514. [11] Ariizumi K, Kumagai T, Kashiwagi A. Behaviour of large-scale cylindrical earth retaining wall. In: Kusakabe, Fujita, Miyazaki, editors. Proc int symposium on geotechnical aspects of underground construction in soft ground. Balkema; 2000. p. 4816. [12] Muramatsu M, Abe Y. Considerations in shaft excavation and peripheral ground deformation. In: Mair, Taylor, editors. Proc int symposium on geotechnical aspects of underground construction in soft ground. Balkema; 1996. p. 1738. [13] Japan Society of Civil Engineers Tunnel Committee, Standard Specications for Tunnel [Cut and Cover Tunnel Version], JSCE; 2006. p. 1179 [In Japanese]. [14] Advanced Research Institute for Science and Engineering, Waseda University, specic proposals for deep-level infrastructure for Central Tokyo 1995; October [In Japanese]. [15] Lings ML, Ng CWW, Nash DFT. The lateral pressure of wet concrete in diaphragm wall panels cast under bentonite. In: Proc institution of civil engineers, geotechnical engineering, no. 107, July; 1994. p. 16372. [16] Harrison TA, Clear CA. Concrete pressure on formwork, Construc- tion Industry Research and Information Association, Report 108, London; 1985. [17] Arii T. Experimental research of lateral pressure of concrete acting on the diaphragm wall. In: The 18th Japan national conference on soil mechanics and foundation engineering; 1983. p. 12256 [In Japanese]. [18] Japan Society of Civil Engineers Concrete Committee, Standard Specications for Concrete [Structures Materials and Construction Version]; 1998. p. 1113 [In Japanese]. [19] Powrie W, Kantartzi C. Ground response during diaphragm wall installation in clay: centrifuge model test. Geotechnique 1996;46(4): 72539. Y. Arai et al. / Computers and Geotechnics 35 (2008) 791807 807