Professional Documents
Culture Documents
Industry Association
Contents
Page
1
General
1.2
Scope of application
Installation Instructions
A 785
Storage
10
4.1
Laying operation
10
4.2
Pipe joints
11
4.2.1
Types of couplings
11
4.2.2
12
4.2.2.1
Push-on couplings
12
4.2.2.1.1
13
4.2.2.2
Flanged joints
14
4.2.2.3
Steel couplings
15
4.2.3
Making adapters
16
4.2.4
17
Sewerage Systems
Made of Centrifugally
Cast GRP Pipe
For Buried Sewers and Pipelines
4.3
19
Laying in slopes
33
4.4
Installing manholes
19
Water reservations
34
Pipe trench
22
8.1
Scope of application
34
5.1
Terms
22
8.2
Design guidelines
34
5.2
Trench geometry
22
8.3
35
5.3
Types of soil
24
8.4
36
5.4
27
36
5.4.1
General
27
10
40
5.4.2
Native soil
27
11
Leak tests
40
5.4.3
27
11.1
Hydrostatic test
41
5.4.3.1
27
11.2
Air test
41
5.4.3.2
28
11.3
42
5.4.4
30
12
43
Pipe zone
30
13
Retrofitting connections
(saddles)
44
6.1
General
30
14
46
6.2
31
15
Repairs
46
6.3
31
15.1
Assessing damage
46
6.4
Embedding pipes
31
6.5
32
15.2
46
15.3
Repair couplings
46
15.4
Repair laminate
47
1
15.5
47
16
Project questionnaire
48
17
51
General
To make sure that all the important parameters are taken into
consideration during installation, it is advisable to complete the
Project Questionnaire (see Section 16), which can also be used
as a specification, and send it to the client, contractor and pipe
manufacturer.
After the pipes have been installed, short-term deflection of 4%
max. is permissible in accordance with ATV A 127. Any
deflection over and above this limit in the first 24 hours
following installation cannot however be tolerated and would
result in the long-term deflection being exceeded.
Protect all pipe system parts against damage. Use wide plastic
slings or synthetic rope for loading, unloading and securing
parts during transit. Do not use hooks, metal cable, chains or
other sharp edged hoisting tackle. Avoid concentrated and
impact loads.
Pipes of different diameters can be transported more
economically by nesting smaller ones inside larger ones. The
nested pipes should however rest on the others and not hang
from steel straps.
The nested pipes should be extracted by fork-lift truck with the
metal forks protected and extended to suit the pipe length, thus
preventing the inner pipe surface from being damaged.
For transporting manholes and other custom-built assemblies,
similar instructions apply. Manholes can either be transported
horizontally or vertically, depending on their height. Loose
accessories (e.g. covers) are installed on site. It is easiest to
unload them with commercially available self-tensioning tackle
designed to prevent the pipe shaft from being damaged.
Storage
No. of
pipe lengths
200
250
300
400
500
600
700
800
900
1000
1100
1200
1400
8
7
6
5
4
3
3
2
2
2
2
2
1
Check all the pipe system parts for damage before lowering
them into the trench.
Depending on the weight and local conditions, most parts, especially pipes up to around DN 400 can be installed manually. If
used, suspension and hoisting tackle should not pose a threat
to the pipe wall. Hooks, chains, metal cable and any other
sharp-edged aids that could slip or cause impact and shock
should be avoided at all costs. It is therefore advisable to use
textile slings.
Every pipe and fitting should be installed to the specified line
and grade. Because the pipes are relatively long, check the level several times, ensuring that a continuous straight route of
the specified gradient is adhered to throughout.
10
4.2.2
4.2.2.1
Push-on couplings
Types of couplings
Type
FWC
FWC
Asymmetric
Diameters
DN
300 - 2600
150 - 1200
Permissible bending
DN
a max
500
3
600-900
2
1000-1400
1
1400
0,5
500
> 500
3
2
Before joining the pipes, check that all the parts are there and
correctly positioned in the trench. The pipes have to rest on the
bedding over their entire length, except at the bell holes under
the couplings. Point and line loads must be avoided. Clean the
mating surfaces thoroughly immediately prior to jointing,
especially the grooves in the rubber seal.
Now coat the spigots and the inner coupling surface with a
lubricant as recommended by the manufacturer to reduce the
required jointing force to a minimum. Ensure that no sand or
similar comes into contact with the coated surface.
The pipes have to be joined centrically in the direction of the
pipe axis. This can be done manually up to a diameter of
around DN 400 and above that with levers, grabs, winches,
jacks or bulldozer blades. It is extremely important for the force
to be applied under controlled conditions and the pipe parts to
be protected against damage during the entire jointing
operation.
DC
150 - 600
500
> 500
3
2
11
12
Maximum
deflection
Pipe length
Table 1:
4.2.2.2
DN
Max. perm.
deflection
[]
Deflection [mm]
per
pipe length
Resultant minimum
radius of curvature [m]
for pipe length
3m
6m
3m
6m
DN 500
157
314
57
115
500 DN 900
105
209
86
172
52
105
172
344
0,5
26
52
344
688
900 DN 1800
1800 DN
Flanged joints
GRP pipes can be joined both with GRP flanges and with other
industry standard flanges. The applicable standard for flange
dimensions is DIN 2501-1.
Joining pipes with flanges requires:
a.) Cleaning the flange surfaces and the housing for the sealing
ring, if necessary.
b.) Checking that the sealing ring is clean and is not damaged
in any way.
c.) Positioning the sealing ring on the sealing surface or in the
ring housing.
d.) Pressing the flanges together.
e.) Positioning the bolts and nuts. The jointing and sealing
materials have to be clean and intact. If GRP flanges are
used, washers have to be inserted.
13
14
4.2.2.3
4.2.3
Making adapters
First cut the adapters to length with a stone saw. Then bevel
both the pipe spigots to be joined and the adapter as detailed
in Table 2 and Fig. 5..
Table 2: Bevel dimensions
Diameter
DN
Dimension
A [mm]
Dimension
B [mm]
150
200 - 350
400 - 700
800 - 1500
1500 - 2600
20
30
30
40
50
3
5
6
10
12
Steel couplings
15
16
4.2.4
GRP-cast iron
GRP-concrete
GRP-stoneware
Fig. 6: Joints
17
18
After checking the connecting height, lay the subbase (e.g. 8/16
gravel/chips). Then, before finally installing the manhole, check
that it is located centrally between the connector and the pipe,
adjusting the subbase if necessary (see Fig. 8). The manhole
can be connected in the same way as the pipes, using
additional tools if required e.g. a winch.
Fix the media pipe in place with skids. To comply with the
stress rating, at least 2 skid rings per 6 m pipe are required. Due
to the varying rating for the individual skid models, more rings
may be used if necessary or under more difficult installation
conditions. Proof of suitability for the application should be
provided by the skid manufacturer. When joining, mount and
check the media pipe first and then the casing pipe.
DE
Winch
Chock
Connecting height
+ approx. 50 mm
19
3. Ensure that the joint between the manhole and pipe is free of
stress (use a bend)
4. Check that it is stable
5. Ensure that the maximum angular deflection between the
pipe and connector meets the requirements detailed in
4.2.2.1.1.
20
s connection length
DE outside diameter
DN connection
diameter
DNs manhole DN
DE
Pipe trench
5.1 Terms
The meaning of the terms pipe zone and backfill, and the
various parts of the pipe zone:
- Lower pipe bed
- Upper pipe bed
- Backfill
- Cover
are illustrated in Fig. 9 on the basis of DIN EN 1610 "Installation
of buried and sewers and pipelines.
DNS
DN
1000/1026
s
200
300
300
300
300
300
300
250
300
300
300
300
300
300
300
300
300
300
300
300
300
350
350
350
350
350
350
350
400
350
350
350
350
350
350
500
400
400
400
400
400
400
600
400
400
400
400
400
400
700
500
500
500
500
500
800
500
500
500
500
500
900
600
600
600
600
1000
600
600
600
600
1200
600
600
600
1400
600
600
2000/2047
s
Ground surface
Trench walls
Main backfill
Cover depth
Cover zone
c (at least 30 cm)
Trench depth
OD
Pipe bed
Trench bottom
21
22
DIN EN 1610, DIN 4124, DIN 18300, DIN 18303 and DIN 19630
apply to the design and digging of pipe trenches and pits, but
local conditions should also be taken into consideration. What
is important when calculating the trench width is that it is at
least wide enough to accommodate the machinery for
compaction.
Table 4:
Lined trench
Unlined trench
60
[mm]
> 60
225
da + 0,40
da + 0,50
da + 0,50
da + 0,40
da + 0,70
da + 0,70
da + 0,40
da + 0,85
da + 0,85
da + 0,40
> 1200
da + 1,00
da + 1,00
da + 0,40
1)
da + 0,40
23
Trench depth
[m]
<1
0,8
1,75 < 4
0,9
24
Group 1
Dense
soils,
gravel
Group 2
Dense
soils,
sand
Group 3
Cohesive
mixed
soils
Group 4
Cohesive
soils,
gravel
GE: closely
graded
gravel
GW: clean
gravel with
sand
GI: alternately
graded gravel/
sand mixtures
GU: gravel/silt
GT:
gravel/clay
mixture (5-15*)
16
23
40
SE: closely
graded
sand
SW: widely
graded
sand/gravel
mixtures
SI: alternately
graded sand/
gravel mixtures
SU: sand/silt
mixture (5-15*)
ST: sand/clay
mixture (5-15*)
1.2
11
20
GU:
gravel/silt
mixture
(15-40*)
GT: gravel/
clay
mixture
(15-40*)
SU: sand/silt
mixture (15-40*)
ST: sand/clay
mixture (15-40*)
0.8
13
UL: slightly
plastic silts
UM:
medium
plastic silts
TL: slightly
plastic clays
TA: highly
plastic clays
OU: silts
with organic
material
0.6
1.5
10
25
26
5.4
5.4.3.2
5.4.1
General
These are:
- Stabilized soils
- Lightweight concrete
- Lean concrete
- Unreinforced concrete
- Reinforced concrete
5.4.2
Native soil
5.4.3
Screen size
[mm]
Screen set
63
31.5
16.0
8.0
4.0
2.0
1.0
0.50
0.25
16
100
85 - 100
0 - 25
0-5
0-3
27
28
100
85 - 100
0 - 25
0-5
0-3
8/16
100
90 - 100
0 - 15
0-3
16/32
100
90 - 100
0 - 15
0-3
[mm]
[mm]
0/4
8.0
4.0
2.0
1.0
0.25
0.063
0/2
100
90 - 100
55 - 85
*)
0-5
0/1
100
90 - 100
0 - 25
0-5
29
for DN
11
20
< 900
1000
6
100
85 - 100
*)
0-5
Maximum grain
[mm]
Pipe zone
6.1 General
The embedment zone is of decisive importance to the load
bearing capacity of the pipeline. It therefore has to be laid with
due care, taking the following recommendations into
consideration.
Ensure that the pipes are lying uniformly on the bed. If any
corrections have to be made to the level, fill up or remove part
of the pipe bed. Do not attempt to compact the soil locally.
30
31
32
Water reservations
Laying in slopes
8.2 Design guidelines
33
34
b)
35
36
220
272
324
376
427
530
616
718
820
924
1026
1099
1229
1439
1499
1638
1842
2047
200
250
300
350
400
500
600
700
800
900
1000
1100
1200
1400
1500
1600
1800
2000
37
620
672
724
776
1127
1230
1318
1418
1520
1624
1726
1799
1929
2139
2199
1338
2842
3047
bed width
approx. or to
bg
[mm]
0.359
0.410
0.463
0.518
0.834
0.985
1.118
1.280
1.448
1.626
1.808
1.946
2.188
2.607
2.741
3.032
4.219
4.774
Material
requirement
with bed
[m3/m]
DN
Outside pipe
diameter
da
[mm]
Diameter
Material
requirement
with bed
[m3/m]
0.305
0.356
0.411
0.467
0.701
0.853
0.985
1.153
1.330
1.520
1.716
1.857
2.134
2.607
2.741
3.090
5.721
6.581
Material
displacement
with bed
[m3/m]
0.397
0.468
0.546
0.630
0.977
1.205
1.416
1.685
1.976
2.296
2.634
2.895
3.374
4.233
4.506
5.139
6.883
8.065
Material
requirement
for support
[m3/m]
0.074
0.084
0.094
0.105
0.158
0.185
0.211
0.241
0.273
0.308
0.345
0.378
0.424
0.513
0.550
0.608
0.796
0.914
U 1A cross section1
0.067
0.079
0.088
0.099
0.151
0.177
0.202
0.231
0.263
0.296
0.332
0.363
0.408
0.494
0.529
0.585
0.770
0.884
Material
requirement
for support
[m3/m]
0.343
0.415
0.493
0.578
0.844
1.073
1.283
1.558
1.789
2.191
2.543
2.806
3.320
4.234
4.506
5.198
8.387
9.871
6
7
8
9
10
12
14
16
18
20
22
24
27
29
30
32
36
40
Material
Average time
displacement per pipe length
with bed
(approx.)
[m3/m]
[min]
U 1A SECTION
V 1A 3:1 SECTION
38
39
kg
Weight
Suitability
light
- 25
25 - 60
light
- 600
- 100
- 100
medium 100 - 300
light
light
medium
o
+
+
+
+
heavy
medium
heavy
medium
+
+
+
o
o
24
2-4
3-4
3-5
3-5
4-6
- 15
20 - 40
20 - 30
- 20
20 - 30
20 - 30
+
+
o
o
+
+
20 - 40
40 - 50
20 - 40
30 - 50
30 - 50
20 - 50
24
2-4
3-4
3-4
3-5
4-6
+
+
+
+
o
+
Suitability
15 - 30
20 - 40
25 - 35
30 - 50
20 - 40
20 - 40
15 - 25
15 - 25
- 15
15 - 25
- 15
15 - 30
Layer
cm
2-4
2-4
3-4
3-4
3-5
5-6
5-6
3-5
4-6
4-6
24
3-4
No. of
passes
Layer
cm
- 10
10 - 30
20 - 30
10 - 30
20 - 30
20 30
30 - 40
-
Suitability
+
+
+
+
+
+
+
-
2-4
2-4
3-5
3-5
-
3-5
-
24
2-4
No. of
passes
V3
The above figures are averages only. Under adverse conditions (e.g. relatively high water content, trench lining) the densities may have to be reduced,
while they can be exceeded under especially favorable conditions. Exact figures can only be determined by testing.
Vibratory
roller
60 - 200
100 - 500
> 500
300 - 750
600 - 8000
medium 25 - 60
Frog
rammer
Vibratory
tamper
V2
Soil classes
Cohesive, mixed grade soils
G*, GT*, SU*, ST*
No. of
passes
Layer
cm
2. Medium and heavy duty compaction machines (above the pipe zone)
Vibratory
roller
Surface
vibrator
Frog
rammer
Vibratory
tamper
VI
Type of machine
Compactibility classes
Removing the trench lining from the pipe zone after backfilling
has been completed can have serious consequences for the
load bearing capacity and lead to alterations in the position and
level of the pipeline. The lining should therefore be removed
progressively as the pipe zone is backfilled. If this is not
possible, the following action should be taken:
- Select the building materials for the pipe zone with care
11 Leak tests
40
11.1
Hydrostatic test
Table 13: Test pressure, duration and pressure loss for air test
Carry out the test with pressure on the pipe crown of between
10 and 50 kPa. The pipeline should be prefilled with water for
1 hour before performing the actual test for 30 min. The pipe
passes the test if the water volume to be added during this time
is no greater than:
- 0.15 l/m2 1) for pipelines and sewers
- 0.20 l/m2 1) for pipelines and sewers with manholes
- 0.40 l/m2 1) for manholes
11.2
Air test
Test
po*)
p
procedure [kPa] [mbar]
DN
100
DN
200
DN
1000
10
(1)
2,5
(0.25)
10
14
19
24
LB
50
(5)
10
(1)
11
15
19
LC
100
(10)
15
(1.5)
11
14
LD
200
(20)
15
1.5
1.5
1.5
2.5
11.3
41
DN
800
LA
In the interests of safety the test with air has to be carried out
with due care, especially in the case of larger pipe diameters.
1)
42
150 1200
150 2600
150 2600
Diameter
DN
Application
150 2600
Masonry connector
with pipe ferrule and
sand coating, variable
wall thickness
150 2600
150 2600
43
Masonry connector
with pipe ferrule, sand
coating and thrust ring,
with greater resistance
to longitudinal displacement and groundwater
level, variable wall
thickness
Masonry connector
with pipe ferrule, sand
coating and wall collar
with greater resistance
to longitudinal displacement and pressurized
groundwater, variable
wall thickness
44
15 Repairs
4. Cut the pipe along the
marking with a saw
(carbide or stone disc,
not metal) or bore with a
core drill
15.1
Assessing damage
single component
or
two-component
adhesive
15.3
7. Apply the adhesive evenly
to the appropriate surfaces.
Close the single-component container immediately after use (e.g. with
string) to ensure that it
can be used again.
Adhesive
Saddle
Repair couplings
Pipe
46
15.4
Repair laminate
16 Project questionnaire
Sender Company
Company
Contact
Contact
Address
Adress
Fax
Date
Project
Diameter DN
Cover h=
made of GRP
to
Air traffic
Heavy-goods vehicles
Train, multiple-track
Native
Pipe zone
Cover
G4 clay, loam
Other soils
Threaded rod
Other
Non load-bearing
Groundwater None
Existent
Height above pipe bed h:
47
48
to
Gravel-sand
Custom design
Support angle for
60 (special case)
Stress analysis
90
Strain analysis
180
Deflection analysis
180
Conditions for
embedment
and backfill
Embedment
Backfill
B1
A1
B2
A2
B3
A3
B4
A4
Pipes quoted
Key data Nominal diameter
Inside diameter
Outside diameter
Wall thickness
DN
mm
mm
mm
License no.
Trench shape Backfill or embankment
Single trench
Multiple trench
Stepped trench
Quality mark
Plastic Pipe Quality Association
yes
no
Width of
trench bed bbed = max
Slope angle 45
60
at 90
Vertical planks
Other
49
50
DIN 19565-1
DIN 19565-5
DIN 4124
DIN 18300
DIN 18303
ATV-A 139
ATV-A 241
R 7.8.1/8
51
R 7.8.24
52
Published by:
Kunststoffrohrverband e.V.
Plastic Pipe Industry Association
Dyroffstrasse 2 D-53113 Bonn Tel: +49 228 91477-0
Fax: +49 228 211309 Website: www.krv.de
E-mail: kunststoffrohrverband@krv.de
53
54