Professional Documents
Culture Documents
Structural Engineering
Abstract
An experimental investigation on the relationship between corrosion of reinforcement and bond strength in pull-out test specimen has been
conducted to establish the allowable limit of rust of reinforcement in the construction field. The reinforcing bars used in this study were rusted
before embedded in pull-out test specimen. The first component of this experiment is to make reinforcing bar rust electrically based on
Faradays theory to be 2, 4, 6, 8 and 10% of reinforcing bar weight. For estimation of the amount of rust by weight, Clarkes solution and shot
blasting were adopted and compared. Parameters also include 24 and 45 MPa of concrete compressive strengths and diameter of reinforcing
bar (16, 19 and 25 mm). Pull-out tests were carried out according to KS F 2441 and ASTM C 234 to investigate the effect of the degree of rust
on bond strength. It is found from the test results that the test techniques for corrosion of bar used in this study is relatively effective and
correct. Results show that up to 2% of rust increases the bond strength regardless of concrete strength and diameter of reinforcing bar like the
existing data. It might result from the roughness due to rust. As expected, the bond strength increases as compressive strength of concrete
increases and the diameter of bar decreases.
Keywords: corrosion, artificial accelerated potentiometric corrosion, bond strength, slip, pullout test
1. Introduction
2. Experimental Program
35
Byung Duck Lee, Kook Han Kim, Hwan Gu Yu, and Tae Song Ahn
Table 1. Test Parameters for Corrosion Measurement and Bond
Strength
Parameters
2, 4, 6, 8, 10%
0, 2, 4, 6, 8, 10
Clakers solution
Shot blasting
24, 45
(1)
where,
w = mass loss in g, weight of corrosion products removed by
electrolyte solution during time(sec)
I = current, A
t = applying time of the current(A)
M = molecular weight of the metal, g/mol, in case of deformed
reinforcing bar, 55.85 g/mol
n = electron per molecule oxidized or reduced, in case of
deformed reinforcing bar, 2
F = Faraday constant, 96,500 C/mol or 96,500A . s/mol
(2) Constitution of current supplying circuit board and corrosion
cell
For artificial corrosion of the deformed bar from Faradays law of
electrolysis, the most important part might be the current supplying
circuit which can apply the constant electric current(A) for certain
period of time(t). The electric current of 30.2A was applied to each
deformed bar from the circuit used in this study.
The corrosion cell was made of acrylate board for the corrosion
reaction to be observed outside. The cell was divided into 18 subsells
to corrode 18 deformed reinforcing bars simultaneously. The size of
cell was 12764101 cm and that of each subcell was 2020100
cm. A waterproofing sealers was applied between subcells to prevent
the flow of electrolyte. Fig. 2 shows the corrosion set up in the cell.
The deformed bar used as an anode was immersed into electrolyte
by hanging specimen mount using a grip or connector. A coil-type
stainless steel was adopted as a cathode as shown in Fig. 2. The
anode was connected to positive terminal(+) of power source while
the cathode to the negative terminal(). In the electrolyzation reaction,
the cross-section of the cathode should be more than twice for the
cathode reaction not to limit the whole corrosion reaction.
Accordingly, the stainless steel used for each subcell was the plate of
305,0000.3 mm, which was then made into a coil. 5%-Nacl
solution was used as electrolyte which was prepared by first
dissolving Nacl 50 g in 900 ml of water and then making 1,000 ml
by adding more water.
Target strength
(MPa)
Gmax
(mm)
Slump
(cm)
W/C
(%)
S/A
(%)
Water
Cement
Fine aggregate
Coarse
aggregate
24
25
13.2
41
43
167
406
761
1095
45
25
16.3
36
43
167
463
741
1066
36
Size of
deformed
reinforcing bar
2%
4%
6%
8%
10%
D16
24.96
49.92
74.88
99.84
124.80
D19
36.00
72.00
108.00
144.00
180.00
D25
63.68
127.36
191.04
254.72
318.40
D16
28751
57502
D19
41468
D25
1 l
20 g
50 g
Temperature
room
Dip in time
up to 25 min
(2)
37
Byung Duck Lee, Kook Han Kim, Hwan Gu Yu, and Tae Song Ahn
Table 5. Dimension and Bond Length for Bond Strength Specimens
Description
D 16
151515
6.40
D 19
151515
7.64
D 25
151515
10.20
10
D 16
2.39/2.36
4.53/4.47
6.38/6.46
8.21/8.17 10.48/10.28
D 19
2.31/1.98
4.94/4.90
6.90/6.72
8.31/8.60 10.64/10.61
D 25
2.76/2.90
4.94/4.89
6.78/6.99
8.94/8.66 10.63/10.55
38
39
Byung Duck Lee, Kook Han Kim, Hwan Gu Yu, and Tae Song Ahn
2%
4%
6%
8%
10%
D 16
13.1/22.7
14.6/23.5
16.5/24.2
11.5/22.5
10.4/22.0
8.2/22.5
D 19
9.9/15.8
14.5/20.1
9.0/16.2
8.9/15.8
8.9/13.8
7.5/13.0
D 25
7.3/8.0
8.2/9.1
7.4/8.9
6.3/9.0
6.5/10.2
7.4/9.4
is not observed only for 8% and 10% corroded D-16 deformed bar.
However, in normal strength reinforced concrete, concrete failure
was not occurred for D-16 deformed bar with 6, 8 and 10% corrosion
40
4. Conclusions
(1) The amount of rust formed by artificial accelerated corroding
method was a little higher than theoretical one irrespective of
the nominal diameters of deformed bars and the rust removal
methods such as Clarkes Solution and Shot Blasting. It might
result from the additional source of corrosion other than D. C.
voltage was in artificial accelerated corroding method.
(2) The amount of rust produced by two different removal
methods (dipping in Clarkes Solution and Shot Blasting) was
almost same. The difference between the measured amount of
rust and the theoretical one became smaller with a decrease of
nominal diameters of bars and its decreased average ratio to
theoretical one was about be 13%.
(3) For the effects of nominal diameter on bond stress-slip
relationship, ultimate bond stress and slip extension rate
increased with a decrease of nominal diameters regardless of
concrete strength or the amount of rust.
(4) For the effects of concrete strength on bond stress-slip
relationship, ultimate bond stress of deformed bar with same
nominal diameter increased with increase of concrete strength
irrespective of the amount of rust of deformed bar.
(5) The effects of the amount of rust on bond stress-slip
relationship show a little difference for different nominal
diameters of deformed bars. For D-16 deformed bar embedded
in both high strength and normal strength, ultimate bond
stresses of 2% and 4% corroded deformed bar are greater than
that of 0% corroded deformed bar. For D-19 deformed bar,
ultimate bond stress of 2% corroded deformed bar is greater
than that of 0% corroded deformed bar irrespective of concrete
Vol. 8, No. 1 / January 2004
References
ACI Manual of Concrete Practice (1994). Materials and General Properties
of Concrete. ACI Manual of Concrete Practice, PART 1, pp. 222R 1-30.
Al-Sulaimani, G.J., Kaleemullah, M., Basunbul, I.A., and Rasheeduzzafa.
(1990). Influence of Corrosion and Cracking on Bond Behavior and
Strength of Reinforced Concrete Members. ACI Structural Journal,
Technical Paper, pp. 220-231.
ASTM G1-81 (1981). Preparing, Cleaning, and Evaluating Corrosion Test
Specimens. ASTM Standards, pp. 829-834.
ASTM C 234-91a (1991). Standard Test Method for Comparing Concretes
on the Basis of the Bond Developed with Reinforcing Steel. ASTM
Standards, pp. 153-157.
Malvar, L.J. (1995). Tensile and Bond Properties of GFRP Reinforcing
Bars. ACI Materials Journal, Technical Paper, Title No. 92-M30, pp.
276-284.
Soroushian, P., Choi, K.B., and Park, G.H. (1991). Bond of Deformed Bars
to Concrete: Effects of Confinement and Strength of Concrete. ACI
Materials Journal, Technical Paper, Title No. 88-M27, pp. 227-232.
41