Professional Documents
Culture Documents
FEBRUARY 2014
ENVIRONMENTAL
IMPACT
ASSESSMENT
REPORT
Description
Page No.
1.
INTRODUCTION ...............................................................................................
1.1.
General ................................................................................................................. 9
1.2.
1.2.1.
1.3.
1.4.
Accessibility ...................................................................................................... 10
1.4.1.
1.4.2.
1.5.
1.6.
1.7.
1.8.
1.8.1.
1.8.2.
Limitations ......................................................................................................... 18
1.9.
1.9.1.
1.9.2.
1.9.3.
2.
2.1.
2.2.
2.2.1.
Dam .................................................................................................................... 25
2.2.2.
2.2.3.
Cofferdams ........................................................................................................ 25
2.2.4.
Reservoir ........................................................................................................... 25
2.2.5.
Spillways ............................................................................................................ 26
Page|i
2.2.6.
2.2.7.
Powerhouse ....................................................................................................... 27
2.2.8.
2.2.9.
2.2.10.
2.3.
2.3.1.
General ............................................................................................................... 28
2.3.2.
2.3.3.
2.3.4.
2.4.
2.4.1.
3.
3.1.
General ............................................................................................................... 32
3.2.
3.2.1.
3.2.2.
3.2.3.
3.2.4.
3.3.
3.4.
3.4.1.
3.4.2.
3.4.3.
3.4.4.
3.4.5.
3.4.6.
3.4.7.
3.4.8.
Page|ii
3.4.9.
3.4.10.
3.4.11.
3.4.12.
Regulations of Mines and Oil Fields and Mineral Development Act, 1948 .. 42
3.4.13.
3.4.14.
3.4.15.
3.4.16.
3.4.17.
3.4.18.
3.4.19.
3.4.20.
3.4.21.
3.5.
3.5.1.
3.5.2.
3.5.3.
3.5.4.
3.5.5.
3.5.6.
3.5.7.
3.6.
3.7.
3.7.1.
3.7.2.
3.7.3.
3.7.4.
3.7.5.
3.7.6.
Page|iii
3.8.
3.9.
4.
4.1.
4.1.1.
Physiography .................................................................................................... 56
4.1.2.
Climate ............................................................................................................... 56
4.1.3.
Precipitation ...................................................................................................... 57
4.1.4.
Temperature ...................................................................................................... 59
4.1.5.
Geology .............................................................................................................. 66
4.1.6.
Seismology ........................................................................................................ 67
4.1.7.
4.1.8.
4.1.9.
Soils ................................................................................................................... 68
4.1.10.
4.1.11.
Agriculture ......................................................................................................... 69
4.1.12.
Livestock ........................................................................................................... 70
4.1.13.
4.1.14.
4.1.15.
4.2.
4.2.1.
Flora ................................................................................................................... 74
4.2.1.1.
4.2.1.2.
4.2.2.
Fauna ................................................................................................................. 79
4.2.2.1.
Birds ................................................................................................................... 80
4.2.2.2.
Insects ................................................................................................................ 81
4.2.2.3.
4.2.3.
4.3.
4.3.1.
Population ......................................................................................................... 81
Page|iv
4.3.2.
4.3.3.
5.
5.1.
General ............................................................................................................... 83
5.2.
5.2.1.
Sensitivity .......................................................................................................... 84
5.2.2.
Magnitude .......................................................................................................... 84
5.3.
5.3.1.
5.3.2.
5.3.3.
5.3.4.
5.3.5.
5.3.6.
5.3.7.
5.3.8.
5.3.9.
5.3.10.
5.3.11.
5.3.12.
5.3.13.
5.3.14.
5.3.15.
5.3.16.
5.3.17.
5.3.18.
5.3.19.
5.3.20.
5.3.21.
Page|v
5.3.22.
5.3.23.
5.3.24.
5.3.25.
5.3.26.
5.3.27.
5.3.28.
5.4.
5.4.1.
5.4.2.
5.4.3.
5.4.4.
5.4.5.
5.4.6.
5.4.7.
5.4.8.
5.4.9.
5.4.10.
5.4.11.
5.4.12.
5.4.13.
5.4.14.
5.4.15.
5.4.16.
5.4.17.
5.4.18.
5.4.19.
5.4.20.
5.4.21.
6.
Page|vi
6.1.
6.2.
6.3.
6.4.
6.4.1.
6.4.2.
6.4.3.
6.5.
6.6.
7.
7.1.
7.2.
7.3.
7.4.
7.5.
7.5.1.
7.5.2.
7.6.
7.6.1.
7.6.2.
7.6.3.
7.6.4.
7.7.
8.
8.1.
8.2.
8.3.
8.4.
8.5.
Page|vii
8.6.
8.7.
8.7.1.
8.8.
8.9.
8.10.
8.11.
9.
9.1.
9.2.
9.3.
9.4.
9.4.1.
9.4.2.
9.4.3.
9.4.4.
9.4.5.
9.5.
10.
10.1.
10.2.
10.3.
10.4.
10.4.1.
Area for Auxiliary Services and other Project Requirements ..................... 145
10.4.2.
10.4.3.
10.5.
10.5.1.
10.5.2.
10.5.3.
Page|viii
10.6.
10.6.1.
10.6.2.
10.7.
10.7.1.
10.7.2.
10.8.
11.
11.1.
12.
12.1.
12.2.
12.2.1.
12.2.2.
12.2.3.
12.3.
12.4.
12.5.
13.
Page|ix
LIST OF TABLES
Sr. No.
Description
Page No.
Table 1:
Table 2:
Table 3:
Table 4:
Table 5:
Table 6:
Table 7:
Table 8:
Table 9:
Table 10:
Table 11:
Table 12:
Table 13:
Table 14:
Table 15:
Table 16:
Table 17:
Table 18:
Table 19:
Table 20:
Table 21:
Table 22:
Table 23:
Table 24:
Table 25:
Mass of CO2 Released per GWh of Energy Generated for Various Types of
Thermal Generation ........................................................................................ 135
Table 26:
Page|x
LIST OF FIGURES
Sr. No.
Description
Page No.
Figure 1:
Figure 2:
Figure 3:
Agricultural Fields.......................................................................................... 69
Figure 4:
Figure 5:
Figure 6:
Page|xi
ABBREVIATIONS
A
AAR
AAUs
AC
ACSR
ADB
AF
ASR
ASTM
ATL
B/C
BCR
CCGT
CDM
CEF
CERs
CFRD
CFC
Ch
CIDA
CITES
CM
CNG
COP
CPM
CPP
CPT
Cusec
CVC
CW
DBE
DC
DNA
DEM
Deg
d/s
DSL
EARI
EB
EHV
EIA
EIRR
El
E&M
EMS
EMP
EPA
ESDD
EU
EU ETS
FDI
FIRR
Amperes
Alkali aggregate reaction
Assigned Amount Units
Alternating current
Aluminum core steel reinforced
Asian Development Bank
Acre-feet
Alkali silica reaction
American Society of Testing Materials
Associated Technologies (Pvt) Limited
Benefit/cost
Benefit cost ratio
Combined cycle gas turbine
Clean Development Mechanism
Carbon Emission Factor
Certified Emission Reductions
Concrete faced rock fill dam
Chlorofluoro Carbon
Chainage (distance measured along a construction work)
Canadian International Development Agency
Convention on International Trade in Endangered Species of Wild Fauna and
Flora
Combined Margin
Combined Margin
Conference of the Parties
Critical path method
Capacity cost
Cone Penetration Test
Cubic foot per second
Conventionally vibrated concrete
Cooling water
Design basis earthquake
Direct current
Designated National Authority
Digital elevation model
Degree
Downstream
Detailed scan line survey
Economic accounting rate of interest
Executive Board EHS Extra high strength
Extra high voltage
Environmental impact assessment
Economic internal rate of return
Elevation above mean sea level
Electrical and mechanical
Environmental Management System
Environmental management plan
Environmental Protection Agency of Pakistan
Equivalent salt deposit density
European Union
European Union Emission Trading Scheme
Federal Development Investment
Financial internal rate of return
Page|1
FRC
FSL
FSD
Ft
FWO
G
GCB
GDP
GERCC
GEVR
GHG
GIB
GIL
GIS
GLOF
GOP
Gpa
GPS
GSI
GTZ
GWh
GWh/a
GWP
Ha
HEPO
Hr
HRT
HV
HVAC
HVAC
HVDC
Hz
ICIMOD
ID
IDC
IET
IDC
IET
IEE
IFC
InSAR
IP
IPB
IRR
ISRIP
ISO
IUCN
JI
KKH
KHP
K
Kg
kg/m3
kJ
Km
km
km/h
KP
KPK
Kt
kV
KVF
kW
kWh
L
Lb
lb/ft3
LAA
LCDP
LLO
LRMC
LV
M
M
m/s
m2
m3
m3/s
Max
Mbtu
MCE
Min
MIV
MKT
MLO
MOL
MONENCO
MMP
MMT
Mpa
MP
MSA
Mt
MUV
MV
MVA
MW
MWh
NEPRA
NEQS
NESC
NGO
NHA
No
NPCC
NPV
NTDC
NWFP
OCGT
Kilometre
Square kilometers
Kilometres per hour
Kyoto Protocol
Khyber Pakhtun Khwah
Knots (nautical miles per hour)
Kilovolt
Kandiah Valley Fault
Kilowatt
Kilowatt hour
Litre
Pound
Pounds per cubic foot
Land Acquisition Act
Least cost development plan
Low level outlet
Long run marginal cost
Low voltage
Million
Metre
Metres per second
Square metres
Cubic metres
Cubic metres per second (cumecs)
Maximum
Million British thermal units
Maximum credible earthquake
Minimum
Main inlet valve
Main Karakoram Thrust
Mid-level outlet
Minimum operating level
Montreal Engineering Company
Mitigation Management Plan
Main Mantle Thrust
Megapascal
Monitoring Plan
Maximum size of aggregate
Million tonnes (megatonnes)
Manufacturing unit value (World Bank)
Medium voltage
Megavolt ampere
Megawatt
Megawatt hours
National Electric Power Regulatory Authority
National Environmental Quality Standards
National Electric Safety Code
Non-governmental organization
National Highways Authority
Number
National Power Control Centre
Net present value
National Transmission and Dispatch Company
North-West Frontier Province
Open cycle gas turbine
Page|3
ODA
OD
OD
OP
OM
O&M
PARC
PAP
PC
PDD
PEPA
PEPO
PEPC
PEPCO
PESMU
PF
PFA
PGRC
PKR
PLC
PM
PMD
POE
POT
PPE
PPIB
ppm
PSS
PTDC
PWD
Q
RAP
RCC
RCNLIP
RMC
RMR
ROW
RQD
SC
SCOM S
SCADA
SCF
SCPA
SCR
SFRS
SHYDO
SIL
SOP
SPT
SRSP
SRTM
SSR
SVC
SW&DO
SWHP
T
T/km
TBM
TCR
TCSC
TDS
T/L
TOR
TVI
UCS
UK
UPS
u/s
UHVDC
UNCED
UNFCC
UPFC
US
USBR
USD
USGS
Var
Vs
VERs
VSC
VT
WAPDA
WB
WCD
WHO
WPPO
WWF
Yr
Tonnes
Tonnes per square kilometre
Tunnel boring machine
Total core recovery
Thyristor controlled series compensation
Total dissolved solids
Transmission line
Terms of Reference
Television interference
Unconfined compressive strength
United Kingdom of Great Britain and Northern Ireland
Uninterruptible power supply
Upstream
Ultra-high voltage direct current
United Nations Conference on Environment and Development
United Nations Framework Convention on Climate Change
Unified power flow controller
United States cent
United States Bureau of Reclamation
United States Dollar
United States Geological Survey
Volt Ampere Reactive
Versus
Voluntary Emission Reductions
Voltage source converter
Voltage transformer
Pakistan Water and Power Development Authority
World Bank
World Commission on Dams
World Health Organization
WAPDA Power Privatization Organization
World Wildlife Fund
Year
Page|5
EXECUTIVE SUMMARY
Kaigah Hydropower Project is a proposed on River Kandiah as a run of river hydropower
project located in Kandiah valley, District Kohistan in the province of KPK. This project will
have an installed capacity of 545 MW. This project forms part of WAPDAs strategic vision
program to the year 2025. The aim of Vision 2025 is to improve hydropower generation
capacity in the country to meet the ever growing electricity demands and expansion of
economic activities. An accelerated power production especially hydroelectric generation
is under focus through medium term power generation projects. Private sector is being
encouraged to make investment to develop and produce hydropower wherever such
potential exist in the country.
Kaigah Hydropower Project scheme was taken over by Private Power Infrastructure Board
(PPIB) to be offered as an Investment Power Project (IPP) to the private sector on Public
Private Partnership basis.
Access to the Project site is through Dasu town which is located about 340 kilometers
from Islamabad. The main accessibility to Dasu town from down country is through the
Karakoram Highway. Kaigah power house site is located near Thauti village about 8
kilometers upstream from confluence of Kandiah and Indus Rivers. Dam site is accessible
from Dasu town by a jeepable road. Karrang village is located on Kandiah Kalam Road
about 26 kilometers from Kandiah Bridge and connected to the latter through a jeepable
road which has been badly damaged by flashy floods of 2010.
The major Project feature consists of the construction of an asphalt faced rockfill dam on
River Kandiah about 200 meters downstream of the Karrang Village. This will be a 90
meters high Dam from the river bed and will create a reservoir extending up to 3-4 km
upstream of the Dam Site at the level of 1500 masl. The reservoir is planned to be
contained within the narrow river canyon which will submerge neither substantial natural
vegetation nor any productive land significantly. But it will affect the population in Karrang,
Birti and Dong villages in the Project area,
The power intake structure will be constructed on the left bank of the river immediately
upstream of the Dam Site. This power intake structure will be largely submerged and
located at the left bank of the proposed reservoir and divert river water into headrace
tunnel. From the 17.2 Km long headrace tunnel the water is dropped through an
underground vertical shaft, connected to a horizontal tunnel entering into a cavern
powerhouse accommodating all the electricity generating equipment. After passing
through the turbines, the water will be discharged back to the Kandiah River through 4.2
Km long tailrace tunnel located at the left bank of the River Kandiah.
According to Pakistan Environment Protection Act (1997) hydroelectric projects with a
generation capacity of over 50 MW and power transmission lines with a capacity more
than 11 kV fall into Schedule-II, i.e. projects requiring EIA. Similarly, in accordance with
the guidelines of the World Bank, the Asian Development Bank and the Japan Bank for
International Cooperation Environmental guidelines, the Kaigah Hydropower Project (with
a planned generating capacity of over 545 MW and 500 kV power transmission lines)
Page|6
would fall within the category A projects having significant impacts on the environment
and requiring a full scale EIA.
The EIA seeks to identify the environmental, ecological and socio-cultural changes arising
from the development of the project. These may have a positive or negative outcome and
include:
Direct and indirect effects on the socio-economic and cultural system as well as on
environmental components such as soil, water and air.
Page|7
Baseline conditions in the project area were identified for physical, biological and socioeconomic parameters, both quantitative and qualitative, based on collected data, field
visits and desk studies.
Impacts of the proposed Project on the baseline conditions are identified and mitigation
measures have been proposed accordingly in addition to the environmental management
and monitoring plan.
The potential benefit to the project of carbon credits under CDM is currently difficult to
estimate and our estimate ranges from zero to around USD 60 million per year. Until the
post Kyoto international agreements are in place, it is very difficult to know how the
projects like Kaigah HPP will be treated under CDM.
About 900 people will be displaced because of the proposed Project and land acquisition
and resettlement of PAP constitutes the major chunk of the environmental management
cost of the Project which is estimated to be around USD 15 Million.
Following can be safely concluded as the result of this EIA report:
The study of the environmental and social setting of the Kaigah Hydropower
Project, and the implications of the proposed interventions, i.e. construction of a
dam, excavation of tunnels, creation of the reservoir, and construction of
underground powerhouse and so on, do not indicate any significant negative
impact of such nature or magnitude that would suggest the project is
environmentally unfriendly.
The study has identified some potential impacts, which are not of serious nature
and can be ameliorated or mitigated within normally acceptable levels through
practicable control and management measures.
The overall findings of the EIA studies show that the Kaigah Hydropower Project is
environmentally and socially viable subject to the development and implementation
of a full Environmental Management Plan.
Page|8
1.
INTRODUCTION
1.1.
General
The identification of Hydropower Potential was started during 1980s when Canadian
International Development Agency (CIDA) provided financial assistance and engaged a
Canadian engineering consulting firm, Montreal Engineering Company Limited
(MONENCO), to undertake the preparation of an inventory of potential hydropower
generation sites, and their ranking on the three Rivers.
MONENCO conducted a study in the upper reaches of River Indus, Jhelum above
Mangla, and in Swat and Chitral Basins, identifying twenty-five (25) promising potential
sites for hydropower generation including their ranking.
Later on, during eighties and nineties, identification and ranking studies for hydropower
schemes on the Rivers and tributaries of Azad Jammu and Kashmir (AJK) and Khyber
Pakhtun Khwah (KPK) and Northern Areas were also carried out by WAPDA and Sarhad
Hydel Development Organization (SHYDO) (now PHYDO) in collaboration with the
German Agency for Technical Co-Operation (GTZ). A number of sites for development of
small and medium size hydropower projects, including Kaigah Hydropower Project in the
Kohistan Valley, with power potential of 545 MW were identified.
The main objective of the Project is to provide cheap hydro-electric power to the national
grid system and to lessen the prevailing high cost of power supply mainly through the
thermal powerhouses as base load stations. The proposed Project will eventually become
a part of low cost power generation system.
The scope of the consultancy services for the Kaigah Hydropower Project involves
preparation of a Bankable Feasibility Study Report in sufficient details.
1.2.
Objective of Study
The objective of the present study is to prepare a comprehensive EIA study report
encompassing the probable impacts of the selected Project layout and the appropriate
measures to mitigate them effectively.
1.2.1.
Scope of Work
The scope of services as stated has been briefly stated below:
i.
ii. Collection of data through primary sources like field surveys, inventories including site
investigations through structured questionnaires for the following:
Stakeholders consultation
Biological environment data including terrestrial ecology, flora and fauna, forests and
fruit trees, mammals, birds, insects, amphibians, reptiles and fisheries
1.3.
Project Location
The proposed Kaigah Hydropower Project was identified along Kandiah River with dam
near Karrang village and powerhouse site is on left bank of Kandiah River neat Thauti
village (Annexure- A1). Kandiah River has its confluence with the Indus River near
Kandiah Bridge, about 20 kilometers upstream of Dasu town.
The dam site identified near Karrang village has reservoir spread over 4 km in upstream
valley. The dam axis was proposed downstream of confluence of Bangroan Khwar on the
right bank and of Dadli Khwar on the left bank where the Kandiah valley becomes narrow
and the valley slopes become steep and form the entrance of a ravine.
The river bed elevation at dam site has been observed as 1420 m a.s.l and reservoir level
was proposed as 1500 m.a.s.l. The headrace tunnel crosses the mountains on the left
river bank and follows a nearly straight line to the powerhouse cavern, which is situated on
the left bank of Kandiah River near Thauti village.
1.4.
Accessibility
Dasu town is located about 340 kilometers from Islamabad. The main accessibility to Dasu
town from down country is through the Karakoram Highway. Kaigah power house site is
located near Thauti village about 8 kilometers upstream from confluence of Kandiah and
Indus Rivers. Dam site is accessible from Dasu town by a jeepable road. Karrang village is
located on Kandiah Kalam Road about 28 kilometers from Kandiah Bridge and connected
Page|10
to the latter through a jeepable road which has been badly damaged by flashy floods of
2010.
A jeepable road exists in Kandiah valley on its right bank between KKH upto a few
kilometers upstream of Karrang village. The scheme is recommended to be constructed
before upstream identified project Karrang is developed, therefore the improvement of
existing roads and construction of new access roads between KKH and Karrang are
necessary. The access road must be designed truckable for heavy loads.
The construction of an Indus bridge is necessary to connect the next access road system
in Kandiah valley with the KKH on the left bank of Indus. It is estimated that around 25 Km
of upgraded truckable road is essentially needed, alongwith number of bridges in order to
provide accessibility to various locations of the Project. Post flood 2010 conditions
necessitate to rebuild the damaged portion of road within Kandiah valley.
The terrain is characterized by steep embankments in narrow valleys. The roads and mule
paths are subject to landslides, rockfall and avalanches. Therefore, a good quality of
design and construction of the roads is essential.
It has to be mentioned, that the design of the roads is to be carried out to prevent
blockage of the road by rockfall, landslides or avalanches as far as possible considering a
justifiable expenditure, but it cannot be excluded totally.
1.4.1.
Air Route
PIA operates daily flights from Islamabad to Gilgit. Landing in Gilgit depends upon the
weather conditions at Gilgit valley. Sometimes, the passengers are stranded at the two
terminal stations for several days, waiting for weather to clear for flights.
1.4.2.
Communication Services
Dasu Town has postal services, telephone and a receiving TV booster.
The
communication system is not as good as desired. However, it is possible to communicate
with Peshawar and other cities. Also, mobile phones service is available. Mobile telephone
service is available at Dasu town and near adjoining area but no other communication
service is available at two sites.
1.5.
Page|11
The road linking to the Project Site from bridge over Indus River, which was constructed
by FWO, has been totally washed away and therefore, jeepable road access to the Project
Site remains possible for hardly 6 to 7 months per year. The entire locality at Project Site
including Thauti village, Chappar, Cool and Aleel villages have been badly damaged.
During recent floods, the Chappar nullah having significant flow has deposited a fan of
boulders/gravel in sufficient height at confluence of Kandiah River where huge landslides
have also occurred at right bank.
Landslides and other types of slope movements along with the Kandiah River particularly
at right bank have occurred which has destroyed almost the whole right bank area of the
valley.
It has been observed that the left bank of the Kandiah River is more stable and rocks are
in good condition. Now the Powerhouse site has been proposed on the left bank near
Thauti Nullah as shown in Annexure- A.2. Additional site investigations have been
conducted to demonstrate the actual geological conditions of the proposed Powerhouse
site to evaluate both the merits and demerits of the location.
1.6.
Page|12
1.7.
Help ensure the environmental and social soundness and sustainability of projects
Support integration of environmental and social aspects of projects into the decision
making process
Promote
environmentally
sustainable
development
by
supporting
the
protection, conservation, maintenance, and rehabilitation of natural habitats and their
functions
Design and implement projects in a way that fosters full respect for indigenous
peoples dignity, human rights, and cultural uniqueness and so that they: (a) receive
culturally compatible social and economic benefits; and (b) do not suffer adverse
effects during the development process
Assure quality, health and safety in the design and construction of new dams and the
rehabilitation of existing dams, and in carrying out activities that may be affected by an
existing dam
Project Categorization
According to Pakistan Environment Protection Agency regulations for review of IEE and
EIA, hydroelectric projects with a generation capacity of over 50 MW and power
transmission lines with a capacity more than 11 kV fall into Schedule-II, i.e. projects
requiring EIA. Similarly, in accordance with the guidelines of the World Bank, the Asian
Development Bank and the Japan Bank for International Cooperation Environmental
guidelines, the Kaigah Hydropower Project (with a planned generating capacity of 545
MW) would fall within the category A projects having significant impacts on the
environment and requiring a full scale EIA.
Page|13
The Projects in Schedule A are generally major projects and have the potential to affect a
large number of people. They also include projects in environmentally sensitive areas. The
impact of such projects may be irreversible and could lead to significant changes in land
use and the social, physical and biological environment.
Agriculture and Livestock
Petroleum Refineries
Petrochemical complexes
Man-made fibers and resin projects greater than10 crore (100 million) rupees in
value
Large scale food processing such as sugar mills, refineries, breweries, distilleries,
soft drinks, milk and dairy products greater than 10 crore rupees in value
Large scale industrial plants such as: synthetic resins, plastics and manmade fibers,
paper and paperboard containers and boxes, plastic products, textiles except
apparel, printing and publishing, paints and dyes, oils and fats greater than1 crore
rupees in value
Cement plants
Major mineral development including; mining and processing of coal, gold, copper,
Page|14
Transport
Major Airports
Federal or Provincial Highways or major roads greater than 5 crore rupees in value.
Maintenance (rebuilding or reconstruction of existing roads is exempted from the
requirement of an EIA).
Dams and reservoirs with a maximum storage volume greater than 50 million cubic
meters or a surface area greater than 8 square kilometers
Major urban water supply infrastructure, including major head works and treatment
plants.
Waste Disposal
Waste disposal and/or storage of hazardous or toxic wastes (including landfill sites,
incineration of hospital toxic waste)
Waste disposal facilities for domestic or industrial wastes, where more than 10,000
cubic meters of waste will handled annually
SCHEDULE B
LIST OF PROJECTS REQUIRING AN IEE
These projects include those where the range of environmental issues is comparatively
Page|15
narrow and the issues can be understood and managed through less extensive analysis.
These are projects not generally located in environmentally sensitive areas or smaller
proposals in sensitive areas.
Agricultural and Livestock
Energy
Man-made fibers and resin projects less than 10 crore (100 million) rupees in value
Food processing such as sugar mills, refineries, breweries, distilleries, soft drinks,
milk and dairy products less than than10 crore rupees in value
Commercial extraction of sand, gravel, limestone, clay and other minerals not
included in Schedule A.
Transport
Ports and Harbours Development for ships less than 500 gross tons
Dams and Reservoirs with a storage volume less than 50 million cubic meters or a
Page|16
Waste Disposal
Waste disposal facility for domestic or industrial wastes, where less than 10,000
cubic meters of waste will handled annually
Urban development projects, including large rural hotels, schools and universities
Public facilities which have significant off-site impacts (i.e. hospital wastes)
Housing Estates
SCHEDULE C
LIST OF PROJECTS NOT REQUIRING IEE OR EIA
Essentially Schedule C" combines everything not in Schedules A and B. As is the case
for A and B projects, Schedule C projects are also subject to review if they are situated
in an environmentally sensitive or critical area. No attempt is made here to detail these
projects, however some illustrative examples are provided below:
on-farm dams;
Source: Government of Pakistan, Pakistan Environmental Protection Agency, Policy and procedure
for the filing, review and approval of environmental assessments
1.8.
1.8.1.
The Scope
The scope of the proposed study for the preparation of bankable feasibility study includes
this EIA which only covers the dam site, downstream area, reservoir and powerhouse
areas. The EIA for the transmission line will be prepared separately. Displacement of
about 900 persons belonging to Karrang, Birti and Thuati village will be involved due to the
execution of the project in addition to acquisition of land for project execution. A
Page|17
Resettlement Action Plan (RAP) will also be prepared to provide sufficient compensation
and assistance to Project Affected Persons (PAP) for their loss of economic assets and
livelihood. The RAP will be prepared as a separate document containing all details for
compensation that would assist PAP to improve or at least restore their living standard,
income earning or production capacity to the pre-project level.
Main activities carried out for the preparation of the EIA report are as follows:
1.8.2.
Limitations
The baseline information documented in the present report reflects the prevailing physical,
biological and socio-economic conditions of the project area. The project is at feasibility
stage and the detailed design and tender documents preparation stages will follow. If the
project is implemented after two years of completion of the design stage then certain
variables such as development of infrastructure, population growth, increase or decrease
in the forest, land use, cropping patterns and economic conditions could be changed
significantly.
1.9.
1.9.1.
Page|18
1.9.2.
1.9.3.
Page|19
Geographic boundaries of the project area were identified and existing villages and
settlements were listed
Developed the tools for data collection i.e. questionnaires for household sample
survey, village profile, women sample survey, community participation and water
use.
Sampling Design
A stratified proportionate random sampling technique was applied to select
adequate and representative samples to generalize survey findings at the project
level. The stratification variables were taken into consideration for enhancing the
representation level for adopting appropriate sampling design.
Page|20
f) Sampling Unit
The primary sampling unit for the socio-economic survey was the head (male or
female) of the household falling within the four sample villages of proposed Kaigah
Project area.
g) Basic Unit of Study
The basic unit of study and analysis for the purpose of socio-economic investigation of
four villages of project influence was a household falling within any possible influence
of the proposed Kaigah Hydropower Project, i.e. Karrang, Birti, Dong and Thauti.
h) Questionnaires
In order to test the validity and reliability of the proposed questionnaires, interviewing
guides were pre-tested in the area and then the questionnaires were reviewed to
assess whether questions needed to be clarified, changed or re-sequenced and then a
final editing of questionnaires was conducted prior to their subsequent application in
the real sample areas.
The questionnaires used for the social survey and women survey are included in
Annexure C1& C3 respectively.
i)
Field Investigators
Field investigators were given a one week course on the job orientation and training on
the objectives of the studies, operational definitions for the concepts and variables,
which are included in the questionnaires as well as role playing exercises to enhance
their interviewing in skills at the field level. The role playing exercises provided the field
investigators with the ability and confidence to establish a rapport with the respondents
as well as other interviewing skills in order to minimize the non- sampling error,
wrongly asked or interpreted or recorded answers. The services of a local qualified
female were hired for the data collection on the subjects of gender and development.
j)
socio-economic status of the family and household was obtained from the
respondents.
m) Village Profile
A comprehensive village profile was prepared to document the socio-economic and
demographic data of each sample village in project area.
n) Gender Survey
The consultants developed a separate questionnaire covering various aspects and
issues of women in the area. The services of a qualified local female were hired for
this survey. In total, 31 women were interviewed. Respondent women were selected
by applying the same technique as used for socio- economic survey.
o) Data Editing
The filled-in questionnaires and interviewing guides were edited by the same field
investigators, who were involved in the data collection. This was done immediately
after completing the field investigations.
p) Data Analysis
Data sets were processed after the completion of the field survey and editing of socioeconomic information. Analysis of this diversified data and preparation of conclusions
in the minimum possibletime was achieved using statistical techniques of data
analysis.
Page|22
2.
PROJECT DESCRIPTION
2.1.
Salient Features
125
m3/s
68.0
m3/s
2113
m3/s
Reservoir length
3500
Reservoir area
74300
m2
1500
m.a.s.l
1480
m.a.s.l
40.39
MCM
19.65
MCM
Dam height
100
m.a.s.l
1510
m.a.s.l
400
m.a.s.l
Reservoir
Dam Structure
Spillways
No. of Bays
Number of gates
Ungated
Gate Type
N/A
Width of gate
Height of gate
Discharge capacity
2150
m3/s
No. of outlets
Nos.
Gate type
Radial
3x6
Discharge capacity
407.5
m3/s
Page|23
Power Waterways
Power Intake
Type
Deep Frontal
No. of gates
5.3 x 6.7
Deck elevation
1511.0
m.a.s.l
1464.0
m.a.s.l
Diameter
7.7
Length
17058
Diameter
10.5
Height
260
527.5
523.9
480
125
m3/s
545
MW
Turbine Type
Pelton vertical
No. of units
972.65
Generator
2112.0
Cavern
105.5x27.1x47.9
m.
Transmission line
500
KV
Size of tunnel
3383.4
Surge Tank
Power Generation
m.a.s.l
GWh
Tailrace Tunnel
Page|24
2.2.
Project Components
The main components of the project include the construction of a dam and a powerhouse.
The dam includes a asphalt faced rock-fill dam (AFRD), spillways, diversion tunnels,
headrace tunnels and tailrace tunnels. The powerhouse includes caverns for the
generating units, transformers and a gate gallery and switchyard.
2.2.1.
Dam
The selected dam axis is located 400 m downstream of confluence of two Bangroan
Khwar with Kandiah River. The dam structures includes: a 100 m high (including
foundations) Asphalt Face Rockfill Dam (AFRD) with overflow spillway, flushing low level
outlets and intake structures for headrace tunnel. The water way leads from the left bank
of the dam site to a powerhouse cavern placed on the left bank of the Kandiah River near
Thauti Nullah.
The Kaigah dam site is located some 28 km upstream of the Kaigah confluence with the
Indus River and 0.40 km downstream of Karrang village. The valley at the dam axis is
about 300 to 400 m wide with moderate to steep slopes (40~60) having slope height in
access of 500 m. An upstream looking of the Dam site is shown in Photo-log attached as
Annexure-B
2.2.2.
Diversion Tunnels
During the construction of the dam the river Kaigah is by-passed in a diversion tunnel
through the right bank of the dam site. The tunnel has a length of about 730 m, a gradient
of some 4 % and a horseshoe shape in cross section.
2.2.3.
Cofferdams
Two cofferdams, one upstream of the main dam and other downstream of the main dam,
will be constructed to divert the river through the diversion tunnels water prior to and
during the construction of the main dam.
2.2.4.
Reservoir
The calculation of the reservoir areas and volumes are based on the topographical survey
in scale 1:1,000. The storage volume elevation curve was computed by using the frustum
formula. The reservoir area curve for the head pond of Kaigah dam site is shown in the
figure below.
Page|25
The total storage volume at full supply level (FSL) 1500 m a.s.l. is given to 40.39 mi. m3.
At minimum operating level (MOL) 1480 m a.s.l. The storage volume accounts about
19.65 mi. m3 and the dead storage of the Kaigah reservoir is 20.74 million m3.
2.2.5.
Spillways
For the spilling of floods a side overfall with inclined chute is intended. Floods with an
amount of more than 2113.0 m/s flow are spilled. Three bays each of 10 m width and 12
m high are proposed. The uncontrolled ogee-shaped side overfall, which leads into a
steeply inclined chute with a plunge pool, is situated on the right side of the dam and is
able to spill the design flood at a water elevation in the reservoir of 1500 m a.s.l. The
overfall edge is set at elevation 1510 m a.s.l.
2.2.6.
Headrace Tunnel
The headrace tunnel would be a low pressure tunnel proposed on the left bank of Kandiah
River. From intake to surge tank area, there will be 5 adits on the way where the tunnel
cross nallahs underneath.
Page|26
2.2.7.
Length:
17.058 km
Inner diameter:
7.7 m
Lining:
Concrete
125 m1/3/s
3.1 m/s
Powerhouse
The suggested powerhouse is planned in the left bank of the Kandian Valley near Thauti
village. The power house location has been chosen on the basis of geological data, so
that the cavern can be founded on solid rock and away from potential landslide zones to
the south. In addition, it has been tried to keep the excavation volume minimal. The
proposed powerhouse area is shown in the figure below.
2.2.8.
Tailrace Tunnel
Restitution of the turbined water to the Kandiah River will be through the tailwater tunnel.
General technical data:
Length:
3.39 km
Size of tunnel:
8m
Slope:
0.1 %
Height difference:
0.5 m
Lining:
Concrete
60 m1/3/s
The downstream manifold collects the free surface flow from the 3 Pelton turbines and
merges into the tailrace tunnel, which conveys it to Kandiah River. At design discharge the
flow velocity in the tailrace tunnel will be about 3.6 m/s
2.2.9.
Access Roads
The dam site is accessible by a jeepable road which can be used in low flow season only
and the powerhouse is accessible from the same route, which is connected to the KKH by
a suspension bridge over Indus River (Japan Bridge). However, the whole road
Page|27
Contractor camps
Batching plant
Workshops
Spoil disposal
Quarries
Borrow pits
Turbine factory
2.3.
2.3.1.
General
The main purpose of the Analysis of Alternatives is to compare feasible alternatives to the
proposed project and its components (site, technology, design and operation etc.)
including a without project scenario. The potential environmental impacts of each
alternative and the feasibility of mitigation of any impacts along with their suitability under
local conditions are also compared.
2.3.2.
No Project Option
Electricity has become a basic need of human beings and is one of the most important
ingredients of economic development. There exists a strong correlation between energy
utilization and rate of economic expansion of any country. In Pakistan per capita energy
consumption is very low.
Pakistan is endowed with a large hydro potential of more than 40,000 MW but
unfortunately only approximately 7,000 MW has been exploited so far. Despite the large
hydropower potential, Pakistans grid is predominantly hydrocarbon intensive (64%
thermal, 33% hydro and 3% nuclear). Due to an acute power shortage in the country (up
to 3,500 MW in some months of the year) the Government of Pakistan is forced to turn to
thermal generation to mitigate the significant power shortage. Thermal power generation
Page|28
is more expensive, being dependent on the imported oil, and is less environmental friendly
due to high emission rate of GHGs. The power shortfall situation is being tackled through
load management by shedding and supplying the power to various areas and sectors
alternatively. The economy of the country is at stake as number of industrial/commercial
units are either closed or are run far less than the optimum period of time.
Hydropower generation is very attractive for sustainable development of the country as it
reduces the need for imports and can abate substantial amount of GHG emission by
substituting for largely gas and oil based power generation. The no project option would
therefore require the installation of more thermal units which will further aggravate the
economy and will become a major source of environmental degradation.
2.3.3.
2.3.4.
Page|29
2.4.
2.4.1.
a) Volume 1
Main Report
b) Volume 2
c) Volume 3
d) Volume 4
e) Volume 5
f)
Volume 6
g) Volume 7
h) Volume 8
i)
Volume 9
j)
Volume 10
k) Volume 11
l)
Volume 12
m) Volume 13
n) Volume 14
Project Drawings
Introduction
Page|30
Page|31
3.
3.1.
General
The legislation of Pakistan contains many laws in the form of Acts, and ordinances which
have direct or indirect relevance and implications in the layout, design, construction and
operation of the Kaigah Hydropower Project.The main national and international
instruments of environmental legislation, which have bearing on the project, are discussed
in this chapter. The prevailing operational manuals and guidelines of the World Bank,
the Asian Development Bank and other donors and financial institutions are also
considered. Pakistan is signatory to various international conventions for pollution control
and biodiversity, which are also mentioned.
3.2.
3.2.1.
Page|32
Revised Standards
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
Parameter
Temperature/ Temperature increase*
pH value
5-days Biochemical Oxygen Demand
(BOD) at 20oC. (1)
Chemical Oxygen Demand (COD)
(1)
Total Suspended Solids
Total Dissolved Solids
Grease and Oil
Phenolic Compounds (as phenol)
Chloride (as CI)
Fluoride (as F)
Cyanide (as QN) total
An-lonic Detergents (as MBAS) (2)
Sulphate (SO4)
Sulphide (S)
Ammonia (NH3)
Pesticides, Herbicides, Fungicides
and Insecticides (3)
Cadmium (4)
Chromium (trivalent & hexavalent)
(4)
Copper (4)
Lead (4)
Mercury (4)
Selenium (4)
Nickel (4)
Silver (4)
Total Toxic Metals
Zinc
Arsenic (4)
Barium (4)
Iron
Manganese
Boron (4)
Chlorine
Existing
Standards
Into Sewage
Treatment
Into Sea
40o C
6 - 10
80
Into
Inland
Waters
3o C
6-9
80
3o C
6-9
250
3o C
69
80**
150
150
400
150
150
3500
10
0.1
1000
20
2
20
600
1.0
40
0.15
200
3500
10
0.1
1000
10
1
20
600
1
40
0.15
400
3500
10
0.3
1000
10
1
20
1000
1
40
0.15
200
3500
10
0.3
SC
10
1
20
SC
1
40
0.15
0.1
1.0
0.1
1
0.1
1
0.1
1
1.0
0.5
0.01
0.5
1.0
1.0
2.0
5.0
1.0
1.5
2.0
1.5
6.0
1.0
1
0.5
0.01
0.5
1
1
2
5
1
1.5
8
1.5
6
1
1
0.5
0.01
0.5
1
1
2
5
1
1.5
8
1.5
6
1
1
0.5
0.01
0.5
1
1
2
5
1
1.5
8
1.5
6
1
Page|33
1. Summing minimum dilution 1:10 on discharge, lower ratio would attract progressively stringent
standards to be determined by the Federal Environmental Protection Agency. By 1:10 dilution
means for example, that for each one cubic meter of treated effluent the recipient water body
should have 10 cubic meter of water for dilution of this effluent.
2. Modified Benzene Alkyl Sulphate; assuming surfactant as bio-degradable.
3. Pesticides. Herbicides, fungicides, and insecticides.
4. Subject to total toxic metals discharge.
5. Applicable only when and where sewage treatment is operational and BOD5=80 mg/l is
achieved by the sewer treatment system.
6. Provided discharge is not at shore and not within 10 miles of mangrove or other important
estuaries.
SC Discharge concentration at or below Sea concentration.
*
The effluent should not result in temperature increase of more than 3C at the edge of the
zone where initial mixing and dilution take place. In case zone is not defined, use 100 meters from
the point of discharge.
Note: Dilution of gaseous emissions and liquid effluents to bring them to the NEQS limiting value
is not permissible through excess air mixing/blowing into the gaseous emissions or through fresh
water mixing with the effluent before discharge into environment.
**
Sr.
No.
Parameter
Source of Emission
Smoke (1)
3
4
5
6
7
Hydrogen
Chloride (3)
Chlorine (3)
Hydrogen fluoride (3)
Hydrogen Sulphide (3)
Sulphur Oxides
Existing
Standards
40% or 2
(Ringleman
n scale)
300
500
200
500
Revised
Standards
40%
300
500
200
500
Any.
400
400
Any.
150
150
Any.
150
150
Any.
10
10
400
5000
1700
Page|34
Carbon monoxide
(3)
Any.
800
Lead (3)
Any.
50
10
Mercury (3)
Any.
11
Cadmium (3)
Any.
20
12
Arsenic (3)
Any.
20
13
Cooper (3)
Any.
50
14
Antimony (3)
Any.
20
15
Zinc (3)
16
1.
2.
800
50
10
10
20
20
50
20
Any
200
200
Nitric acid manufacturing Unit
3000
400
Gas fired.
400
Oxides of Nitrogens
Oil fired
600
400
Coal fired
1200
Based on the assumption that the size of the particulates is 10 micron or more.
In respect of emissions of sulphur dioxide and nitrogen oxides, the power plants
operating on oil or coal as fuel shall, in addition to national Environmental Quality
Standards (NEQS) specified above, comply with the following standard.
Annual
Average
(g/m3)
Max. In 24 Hour
Interval
(g/m3)
Criterion I
Criterion II
< 50
< 200
500
Max. Allowable
Ground Level
Increment To
Ambient (One year
average, g/m3)
50
Low
50
200
500
50
High
100
400
100
10
> 100
> 400
100
10
Quality (SO2
Basic)
Unpolluted
Moderately
Polluted*
Very Polluted**
* For intermediate values between 50 and 100 g/m3) liner interpolations should be used
** No project with sulphur dioxide emissions will be recommended
Page|35
3.2.2.
3.2.3.
3.2.4.
On federal land
Military projects
3.3.
protecting watersheds
conserving biodiversity
3.4.
Environmental Legislation
3.4.1.
Section 12-2b (Review of IEE and EIA): The Federal Agency shall review the
Environmental Impact Assessment report and accord its approval subject to such
conditions as it may deem fit to impose, or require that the Environmental Impact
Page|37
3.4.2.
Section 15 (Regulation of Motor Vehicles): Subject to provision of this clause of the Act
and the rules and regulations made thereunder, no person shall operate a motor
vehicle from which air pollutants or noise are being emitted in an amount,
concentration or level which is in excess of the NEQS, or where the applicable
standards established under clause (g) of subsection (1) of Section-6 of the Act.
Section 18 (Offences by Bodies Corporate): Where any contravention of this Act has
been committed by a body corporate, and it is proved that such offence has been
committed with the consent or connivance or, is attributed to any negligence on the
part of, any director, partner, manager, secretary or other officer of the body corporate,
such director, partner, manager, secretary or other officer of the body corporate, shall
be deemed guilty of such contravention along with the body corporate and shall be
punished accordingly.
Page|38
The projects listed in Schedule-II are generally major projects and have the potential to
affect a large number of people in addition to significant adverse environmental impacts.
The impacts of projects included in Schedule-II may be irreversible and could lead to
significant changes in land use and the social, physical and biological environment. Dams
and reservoirs with a maximum storage volume greater than 50 Mm3 or a surface area
greater than 8 km fall under Schedule-II of the IEE-EIA Regulations, 2000.
3.4.3.
The standards apply to liquid effluents from the construction sites, dam area, powerhouse
site and residential areas and to wastewater discharges from workers and other
construction camps, and to project vehicles, especially heavy construction vehicles.
The prevailing NEQS for liquid effluents discharged to inland surface waters and gaseous
emission from industrial sources are provided in Annexure D1. These standards will be
applicable to the gaseous emissions and liquid effluents discharged to the environment
from the project.
3.4.4.
Damage sustained by the person interested by taking of any standing crops or trees
Damage sustained by the person at the time of Collector's taking possession of land
Page|39
Damage sustained by the person at the time of acquisition of land injuriously affecting
his other property, movable or immovable.
For the Kaigah Hydropower Project compensation for acquisition of land for project
operations and hearing of complaints will be carried out primarily in the light of this Act,
supported by other measures (to be decided in the particular circumstances to suit the
requirements). However, in case a need arises, this Act will be used for this purpose,
supported by other measures as warranted, to fulfil requirements of the World Bank
Guidelines. In the project area mostly land ownership belongs to the community, people
living in valleys have ownership rights on the local rangelands.The community has
unwritten traditional laws for possession, distribution and transfer of assets or the income
of the assets to the original inhabitants of these valleys.
3.4.5.
3.4.6.
3.4.7.
In case any antiquities have been found or reported in any project area it will be the
responsibility of the proponent to report to the department of Archaeology,
Government of Pakistan.
3.4.8.
3.4.9.
Labour Laws
Labour laws in Pakistan are governed by several legislative tools. However, the principal
labour rights are provided by the constitution of Pakistan.The following articles enforce key
labour rights:
Article 11 of the constitution prohibits all forms of slavery, forced labour and child
labour
Article 17 provides for a fundamental right to exercise the freedom of association and
the right to form union
Article 18 prescribes the right of its citizen to enter upon any lawful profession or
occupation and to conduct any lawful trade or business
Article 25 lays down the right to equality before the law and prohibition of
discrimination on the grounds of sex alone
Article 37 (e) makes provisions for securing just and human conditions of work,
ensuring that children and women are not employed in vacations unsuited to their age
or sex, and for maternity benefits for women employment.
In addition to constitutional rights, Act and Ordinances have been enforced for limiting
working hours, minimum working age, and conditions of employment.
Page|41
3.4.12. Regulations of Mines and Oil Fields and Mineral Development Act, 1948
This Act provides regulatory procedures for the quarrying and mining of construction
material on public as well as private lands.
Page|42
3.5.
3.5.1.
3.5.2.
The need to incorporate suitable mitigation measures into every stage of project
implementation
The terms of reference for the reports are to be prepared by the project proponents
themselves. The reports must contain baseline data on the project area, a detailed
assessment thereof, and mitigation measures.
Page|43
3.5.3.
3.5.4.
3.5.5.
3.5.6.
3.5.7.
KPK Province
As the dam site and all of the reservoir area falls into the province of Khyber Pakhtun
Khwah (KPK). At the Provincial level, the KPK holds all the required administrative powers
regarding land acquisition, resettlement and rehabilitation of displaced people of any
development project. For the Kaigah Hydropower Project various government
departments at Federal, Provincial and District level will interact and collaborate for
implementation of the project. One of the prerequisites which will require immediate action
relates to the handling of environmental issues. The construction of the Kaigah
Hydropower Project will require that all land and immovable assets located upstream of
the dam axis and lying below reservoir level will need to be acquired. The project area is
mainly covered within the administrative jurisdiction of District Administration of District
Kohistan, in the Khyber Pakhtun Khwah(KPK) province.
Page|44
The Land Acquisition Act of 1894 with its amendments will need to be applied for
acquisition of the land. Other land based assets will be acquired according to the rules and
regulations applicable for acquiring such assets.
The Government of the Khyber Pakhtun Khwah functions under the provisions of the
Constitution of Pakistan (1973). The Province has a Provincial Assembly with 124 elected
members, constituent of 99 Regular seats, 22 seats reserved for Women and 3 seats for
Non-Muslims. The Provincial Assembly elects the Chief Minister of the Province who
forms a Cabinet of Ministers to look after various Departments. The Chief Minister is the
Chief Executive of the Province. The Federal Government appoints a Governor for the
Province.
The bureaucratic machinery of the Province is headed by a Chief Secretary who
coordinates and supervises functions of various Departments headed by Departmental
Secretaries. In the KPK the person in charge of the Planning & Development Department
is the Additional Chief Secretary who reports to the Chief Secretary. All the Secretaries of
different Departments are assisted by Additional Secretaries, Deputy Secretaries, Section
Officers and other staff. The Departments may have attached Departments and
autonomous or semi-autonomous bodies to look after various functions.
Since 2001, a system of elected District Governments has been introduced in the KPK.
The Province is divided into 24 districts. The Districts are headed by a Zilla Nazim (District
Nazim) assisted by a District Coordination Officer (DCO), who is in charge of the District
bureaucracy. In a District the functions are devolved further to the Tehsil, Town and Union
Council Governments as a part of the local Government system. Each District has an
elected Zilla Council, elected Tehsil, Town and Union Councils who look after various
activities at their respective levels. At District level a District Police Officer looks after the
Law and Order and he reports to the Zilla Nazim. Each District has a Public Safety
Commission which addresses public complaints against the Police. There is a Provincial
Police Officer who is in charge of the police system at the provincial level.
3.6.
Land Use
LEGISLATION
Page|45
Noise
Toxic or Hazardous
Air Quality
Substances
Solid Waste and
Effluents
Marine and
Fisheries
Forest Conservation
Mineral
Development
Cultural
Environment
Livestock
Resettlement
3.7.
3.7.1.
International Treaties.
Annex-A (Definitions): This Annex defines some terms that are frequently used in
Environmental Assessment (EA) reports
Operational Policy (OP) 4.04 (Natural Habitats): This OP explains the Banks
precautionary approach to natural resource management to ensure opportunities for
environmentally sustainable development, and supports the protection, maintenance,
and rehabilitation of natural habitats and their functions. Since there are no habitats of
wildlife in natural or semi-natural state within or near the project area, this OP will not
apply
Operational Policy (OP) 4.10 (Indigenous Peoples): This OP describes the Banks
policy of ensuring that any development project must fully respect the dignity, human
rights, economies, and cultures of Indigenous Peoples.There are no distinct,
vulnerable, social and cultural groups in the project area which could qualify as
indigenous according to this Policy, so no Social Assessment, or preparation of an
Indigenous Peoples Plan is required
Operational Policy (OP) 4.12 (Involuntary Resettlement): This document provides the
Banks guidelines relating to involuntary resettlement of population dislocated by the
Project.The Bank recommends that involuntary resettlement should be avoided.
Where resettlement is unavoidable, it should be handled as a sustainable development
project. The affected persons should be engaged in meaningful consultation,
properly compensated and resettled.The document also identifies the need for a
Resettlement Plan, an abbreviated Resettlement Plan or otherwise.
Page|48
3.7.2.
Environmental Assessment Sourcebook, Volume I: Policies, Procedures, and CrossSectoral Issues (World Bank, 1991)
3.7.3.
3.7.4.
Equator Principles apply globally to development projects in all industry sectors with a
capital cost of USD 10 M or more; most apply to projects in non-OECD or OECD countries
not designated as high-income.
The Equator Principles, developed in close consultation with IFC, are a series of ten
principles relating to the environmental and social assessment and management of
development projects under consideration for finance. They require commercial banks to
categorize the risk of a project in accordance with the environmental and social screening
criteria of the IFC which determine the type of environmental assessment required. Both
Category A and B projects require a Social and Environmental Assessment to determine
the social and environmental impacts and risks of a proposed project in its area of
influence. The Equator Principles established a list of issues to be addressed as part of
the EIA and require consideration of IFC Safeguard Policies for projects located in low to
middle income countries. Host country laws and regulations must be applied, in addition
to the guidelines established in the World Bank Pollution Prevention and Abatement
Handbook, and IFC environmental, health and safety guidelines.
As part of the environmental and social assessment process, a project is required to
consult in a structured and culturally appropriate way with project affected groups,
including indigenous peoples and local NGOs, or projects with significant adverse
impacts on affected communities, the consultation process must ensure free, prior and
informed consultation for the entire project process. The concerns of communities need to
be adequately incorporated into the project. Appropriate procedures to receive and
address concerns or grievances must be established.
Action Plans are required which draw on the conclusions of the assessment describe and
prioritize measures for managing impacts and risks. An independent expert review is
required for Category A projects and as appropriate for Category B projects.The Equator
Principles incorporate covenants to comply with relevant legislation, comply with the
Action Plans, provide regular reporting, and decommission facilities according to an
agreed upon plan. Independent environmental or social advisors may be appointed for
monitoring and reporting.
The Equator Principles require the Social and Environmental Action report to address:
Major hazards
Socio-economic impacts
Involuntary resettlement
Cumulative impacts of existing projects, the proposed project, and anticipated future
projects
Pollution prevention and waste minimization, pollution controls (liquid effluents and air
emissions) and solid and chemical waste management.
The Equator Principles are based on the environmental and social standards of the IFC
and reflect inBank Safeguard Policies and Operative Procedures.
3.7.5.
Indigenous peoples
Cultural heritage.
Page|51
3.7.6.
3.8.
Before a decision is taken to build a new dam, outstanding social and environmental
issues from existing dams should be addressed, and the benefits from existing
projects should be maximized
All stakeholders should have the opportunity for informed participation in decisionmaking processes related to large dams through stakeholder forums. Public
acceptance of all key decisions should be demonstrated. Decisions affecting
indigenous peoples should be taken with their free, prior and informed consent
The project should provide entitlements to affected people to improve their livelihoods
and ensure that they receive the priority share of project benefits (beyond
compensation for their losses).
Affected people include communities living
downstream of dams and those affected by dam-related infrastructure such as
transmission lines and irrigation canals
Affected people should be able to negotiate mutually agreed and legally enforceable
agreements to ensure the implementation of mitigation, resettlement and development
entitlements
The project should provide for the release of environmental flows to help maintain
downstream ecosystems.
Convention concerning the Protection of World Culture and Natural Heritage (World
Heritage Convention), 1972
Vienna Convention for the Protection of the Ozone Layer, Montreal, 1987
Treaty /
Convention
The Convention on
Biological Diversity
Brief Description
Pakistan signed this convention in 1992. The objective of this
convention is the conservation of biological diversity, the
sustainable use of its components and the fair and equitable
sharing of the benefits arising out of the utilization of genetic
resources, including those by appropriate access to genetic
resources and by appropriate transfer of relevant technologies,
taking into account all rights over those resources and to
technologies and by appropriate funding.
The Convention on
Wetlands of
International
Importance, Ramsar
1971
Convention on
International Trade
of Endangered
Species of Wild
Fauna and Flora
(CITES) 1973
3.9.
been formed, and have been engaged in advocacy and, in some cases, research. The
most prominent national environmental NGOs, such as the Sustainable Development
Policy Institute (SDPI) and Shirkatgah, are members of the Pakistan National Committee
of IUCN. The International Fund for Agricultural Development (IFAD) has also been active
for some time.
As mentioned earlier, environmental NGOs have been particularly active in advocacy and
promoting sustainable development approaches. Much of the governments environmental
and conservation policy has been formulated in consultation with leading NGOs, who have
also been involved in drafting new legislation on conservation.
Page|55
4.
BASELINE CONDITIONS
This section provides baseline data (physical, biological and socio-economic parameters)
related to the project area. Information provided is both quantitative and qualitative and is
based on secondary and primary data collected, site field visits and desk studies.
A baseline consists of the existing environmental and socio-economic and cultural status
of the project area. The baseline information and indigenous knowledge is required for
scoping potential environmental issues associated with the implementation of the project.
On the basis of baseline information, the project interventions are assessed and mitigation
measures are proposed. The baseline information also helps to indicate the specific
issues to be monitored during project execution as well as during operational phase.
The anticipated environmentally impacted area would consist of following:
Catchment are as of major perennial streams and nallah sentering the Kandiah river
upstream and downstream from the damsite (from the upstream end of the reservoir
and down stream to the confluence of the TWL with the Kandiah river).
4.1.
Physical Environment
4.1.1.
Physiography
The project area is located in Kohistan District of Pakistan in province of KPK.
Geologically, the project site is located in the Kohistan Island Arc which lies between
Indian crustal plate to the south and the Asian plate to the north. These mountain ranges
belong to the Karakoram-Himalayan region in which the project is located, comprising the
Karakoram Range, the Kailas range, and the Hinduraj range. The area generally consists
of rugged and precipitous terrain classified as alpine scrub zone and is characterized by
substantial snowfall at higher altitudes (near dam axis) in winter.
The dam site is not a site of settlement as it has developed in relatively steep alluvial and
debris flow fan deposits
4.1.2.
Climate
The climate of the catchment is characterized by cold snowy winter and relatively pleasant
summer. The high areas of the catchment are permanently clad with snow and glaciers.
The climate data in Kandiah valley is very scarce. One station in Indus valley with limited
climatologically record is located at Chilas. The nearest station to project area with long
term climatic data record is located at Besham.
The project area is generally affected by two large-scale meteorological phenomena: The
influence of the westerlies mainly during the winter period causing a precipitation
maximum in March and monsoon effects, leading to a second precipitation maximum in
Page|56
July/August. Mean annual precipitation at the stations south of the project area range from
1100 mm to 1600 mm. As the monsoon influence is declining northwards, summer
precipitation on the leeward side of the Karakorum and Himalaya foothills is less
pronounced. In the upper Indus valley, north of the project area, no monsoon rainfalls
occur and summer is extremely dry (mean annual precipitation 300-400 mm)
The two types of precipitation climate are illustrated by the long-term average of monthly
precipitation observed at Shinkiari and Naran. Both stations are located close to the
project area with a distance of less than 100 km between them. Besham Qila west of
Palas shows influences of both climate types.
Air temperature and snow conditions very much depend on the elevation of the considered
sub area. In the lowest parts of the catchments mean monthly temperatures vary between
approximately 5C in February and 25C in June, with daily maxima up to 40C. In the
highest parts above 5000 m average temperature is always below zero.
Due to the high elevation most of the catchment is snow covered from December to May.
Snowmelt is also the governing factor for runoff, which reaches a maximum in May and
June. Runoff peaks due to monsoon rainfalls typically occur in July and August.
Table 7: Long Term Climatic Stations in the Region
Station
4.1.3.
Period
of
Record
Elevation
(m.a.s.l)
Latitude
345530
352810
725255
723540
Longitude
Mean Annual
Rainfall(mm)
Besham
1971-2003
Kalam
1966-2003
610
2744
Shahpur
1964-2004
2012
345500
724000
73
113
Chilas
1954-2006
1070
345415
733840
19
Astore
1954-2004
2363
345415
733840
51
Bunji
1954-2004
1340
345415
733840
14
105
Precipitation
Kandiah River descends from the mountains peak at 4917.9 masl and 4999 masl. The
average gradient of Kandiah River in the project area is about 1.8%. The elevation at its
confluence with Indus River is 826 masl.
Along the river, the valley supports clustered and scattered population centers on both the
banks.
There are a number of tributaries that joins the main stream to form Kandiah River. These
streams include: Sami Khwar (584 km2), Maidain Khwar (419 km2), Bangroan Khwar (284
km2), Soyal Khwar (98 km2) and Seri dara (327 km2). Kandiah River is joined by a few
tributaries from either bank.
Page|57
The catchment area of the nullah at its confluence with Indus River is about 2408 km2 and
up to dam site, it is 1800 km2. The catchment area of Kandiah River is illustrated in Figure
above.
Mean Annual rain fall varies from 666mm in 2001 to 1503mm in 1992. The average of
mean annual rain fallis 1000mm over a period from 1970 to 2004. The monthly rain fall
varies from 39.6mm in November to 327.5mm in July.
From November to May, during the winter period the precipitation is mainly brought by the
western disturbances. The precipitation during this part of the year is approximately 690
mm. During summer period, i.e., from June to October, the precipitation in the catchment
is induced by the monsoon rainfall and averages to about 844 mm.
Page|58
4.1.4.
Temperature
One meteorological station with long record of temperature is located at Besham at a
distance of about 100 km from the project area.The data has been collected from the
SWHP WAPDA for the period 1971 to 2003 in order to get the maximum and minimum
temperatures on monthly and yearly basis.
Page|59
22.2
23.3
30
27.8
28.0
35
33.3
36.7
37.2
39.4
40.0
33.3
40
Temperature ( C)
42.0
20.6
25
20
15
10
5
0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
The elevation at Besham is about 530 m.a.s.l and upto Dam site in Kandiah valley, the
elevation is 1500 m.a.s.l. The Kandiah valley near Karrang village would have cooler
temperature than Besham by 6 to 8 C. Mean maximum and minimum temperatures are
graphically indicated in Figure - 3.2. The minimum monthly temperature at Besham varies
from 5 C in January to 22.5 C in July and maximum monthly temperature varies from 2042 degrees from winter-summer.
35.1
28.4
30.9
25.7
Mean Minimum
19.8
20.7
25
15
13.8
14.5
20
12.0
Temperature ( C)
30
Mean Maximum
38.7
37.1
40
35
39.5
45
10
5
0
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
For Chilas town, climate data was collected from of Pakistan Meteorological Services for
the period from 1953 to 2004.
The variation in temperature pattern is similar to Besham except that Chilas is cooler place
than that of Besham due to higher elevation. Chilas is at El. 1050 m.a.s.l which is closer to
project area elevation. January is the coldest month at the project site, when the
Page|60
Also, the brief of satellite data obtained from interpolation using the software Meteonorm
7 is presented below and details are attached as Annexure- D2:
Page|61
Page|62
Page|63
However, the interpolated results of this software are best illustrated when compared with
the reference measurements obtained from a nearby meteorological station. Also, the data
obtained from NASA is tabulated as follows:
Page|64
Climate data
location
Latitude
35.5
Longitude
72.9
Elevation
3005
-13.48
20.87
25.71
day
179
Air
temperature
Relative
humidity
Daily solar
radiation horizontal
Atmospheri
c pressure
Wind
speed
Earth
temperature
Heating
degreedays
Cooling
degreedays
kWh/m2/d
kPa
m/s
C-d
C-d
January
-9.1
76.1%
2.58
70.8
5.3
-9.8
835
February
-7.4
78.2%
3.13
70.7
5.2
-7.8
721
March
-2.6
75.4%
4.05
70.8
5.4
-2.5
643
April
2.6
65.7%
5.13
71.0
5.9
3.2
471
May
7.8
53.0%
6.23
71.0
5.4
9.9
325
16
June
13.6
41.9%
7.08
70.8
4.7
17.1
143
102
July
16.3
42.6%
6.96
70.8
4.5
20.6
70
180
August
15.5
45.9%
6.23
70.9
4.6
19.3
86
161
September
11.7
44.2%
5.56
71.1
5.4
14.6
191
60
October
5.5
49.0%
4.41
71.2
6.6
7.0
380
November
-0.2
56.5%
3.27
71.2
6.2
0.1
535
December
-6.0
69.8%
2.44
71.0
5.3
-6.6
732
Annual
4.0
58.2%
4.76
71.0
5.4
5.4
5132
520
Month
Page|65
4.1.5.
Geology
The project site is located in the Kohistan Island Arc. The area lies between Indian crustal
plate to the south and the Asian plate to the north. These mountain ranges belong to the
Karakoram-Himalayan region in which the project is located, comprising the Karakoram
Range, the Kailas range, and the Hinduraj range.
The Kohistan sequence is believed to be the remnants of an island arc formed during the
collision of the Indian and Eurasian plates from Cretaceous time through Palaeogene. This
process resulted in the accumulation of a 40-km-thick sequence of mafic, ultramafic,
intermediate calc-alkaline layered plutonic and volcanic rocks, and some metasedimentary and sedimentary rocks. This sequence is considered as the only complete
vertical section of an intra-oceanic island arc presently exposed anywhere in the world.
Figure 4.1 shows the Kohistan Island Arc bounded by the Main Karakoram Thrust (MKT)
in the north and west (Northern Suture) and by the Main Mantle Thrust (MMT) to the south
and east (Southern Suture). The regional geology of the Karakoram-Himalayan region in
northern Pakistan is divided into three different tectonic units:
These three tectonic provinces have distinctly different lithologies and tectonic settings
and are separated by two major branches of the Indus suture (Tahir kheli, et al. 1979;
Treloar, et al. 1996; Khan, et al. 2000). Both branches are marked by the occurrence of a
melange that includes ultramafic rocks and the southern branch also incorporates a
wedge of garnet granulites considered to have re-crystallized at a depth of more than 40
km.
Regional Geological Map is presented in Figure-1.
Page|66
4.1.6.
Seismology
The region (Karakoram-Hindukush and Himalaya), as a whole, has already been under
study for seismic and neotectonic studies for various projects (e.g. Dasu Hydropower
Project, Basha Hydropower Project, Bunji Hydropower Project, etc) and many national and
international researchers. In view of these studies, a lot of literature is already available
that provides the basis for the understanding of the regional tectonic setting and as
guideline for further neotectonic studies and seismic risk analysis.
For the neotectonic studies of Kaigah Hydropower Project, a good basis is provided by the
Geological Map produced by Searle and Asif (1995) and Geological Map of the Jijal- Dasu
Region, Indus Kohistan, NW Pakistan produced by Gerold Zeilinger (2001) which indicate
the various lithological units and faults of the area identified on the basis of geological
mapping conducted along the Karakoram Highway (KKH) and up several tributary valleys,
further supported by satellite image interpretation.
4.1.7.
The reservoir will saturate the base of several talus slopes and could increase the risks of
landslides and sedimentation. Some of the talus will require removal, at least above
reservoir level.
4.1.8.
Land Use
A few human settlements exist on alluvial fans and terraces on either side of the Kandiah
River and its tributaries where water is available for human consumption and agriculture.
The mountains on both sides of the river have steep slopes and many streams and
nallahs join the river in this length. The alluvial fans contain clay silt layer with an
undulated topography over hard bedrock.The available flat land is used for residential
purposes as well as for agriculture and grazing for cattle, goats and sheep etc.
4.1.9.
Soils
Soils provide moisture, nutrients and a foothold to plants. The soils of the project area are
the most unstable and subject to active water erosion. The intensity, however, depends
upon the vegetation cover and the slope gradient. The mountains on both sides of the
river have steep slopes and hold very little vegetation. Alluvial fan deposits are created as
a result of glaciated materials carried by stream flows or where these streams create
space due to meandering within the valley.
The fertile lands in the project area are located in the fans and the terraces close to
streams and nallahs. All the farmlands and orchards are irrigated by streams as rainfall in
the area is very meagre.
Page|68
4.1.11. Agriculture
The project area is mountainous with steep slopes, rainfall is low. Irrigation and
agricultural is practiced on very limited scale. The landholding is very small (average 2
acres) and 85% of the farmers obtain only a single crop in a year. Cultivation is done using
the traditional techniques of farming with ploughs pulled by bullocks.
However, the ownership of the land is based on tribal family distributions only. As a whole,
more than 1000 kanal is possessed by Shahbaz Khels of Birti and similarly about 1500
kanal is owned by the tribe of Mula Khel in Karrang.
In the winter season almost all farmers grow maize on a major part of their land. However
some farmers have recently started wheat cultivation (Figure-3). Fodder is also cultivated
to feed the domestic animals. Other crops include tomatoes, peas, beans, cabbage and
capsicum on very limited scale.
Page|69
4.1.12. Livestock
Livestock is one of the major contributors to the local economy of the project area and
comprises native cattle, goats, buffalos, sheep, poultry and donkeys. People of the area
are practice vertical seasonal livestock movement (transhumance) for centuries. The
livestock owners move to higher altitude at the beginning of summer where pastures are
available for their livestock and return to their houses at the start of winter.The main
reasons for moving is limited land and fodder resources in the valley as grazing land and
fuel wood on slopes is limited and does not meet their requirement. Local livestock
products are used for home consumption and also for income generation.
As sufficient flood data was not available for Kandiah River, therefore long term data of
Kalam has been used to estimate floods of different return periods at Kandiah River,
Annual peak discharges of Kalam hydrological station were obtained and Gumble, Log
pear-III and long normal distribution frequency analysis were applied.
Page|71
The floods obtained in different return periods at Kalam were used to achieve floods at
Kandiah. The results are presented below:
Table 8: Floods at Kandiah River in Different Return Periods
Return Period
(Years)
Floods(m3/s)
407.5
Log PearsonTypeIII
358
Log
Normal
377
554.2
457
465
10
655.1
537
529
25
752.6
656
598
50
879.2
759
648
100
974.2
874
696
200
1073.3
1004
743
1000
1288.6
1432
851
Gumbels
The ambient air quality was monitored at these locations continuously for a period of
24 hours at each sampling point. The monitoring was conducted from May 21 to May
28, 2013. During the monitoring of ambient air quality, priority pollutants i.e. carbon
monoxide, nitrogen dioxide, sulphur dioxide and particulate matter were monitored.
Page|72
The weather data collected comprises of Temperature, Humidity, Wind direction and
wind velocity. The results obtained are given in Table-9. It is evident from the table that
concentration of all ambient air quality parameters are within the limit of NEQS.
During the site visits, it was also observed that ambient air in the area is clean at
present as no heavy industry or other source of air pollution exists in the project area.
Smoke is generated through domestic activities, particularly cooking and heating as
wood is a main source of fuel but the smoke emissions are not high as the project area
is not densely populated. However, sometimes there are increased concentrations of
dust and smoke in the project area due to high speed winds. The vehicular movement
data collected through the traffic count survey at three locations in the project area
during February-March 2013 is given in Table-10. This Table shows that presently the
number of vehicles moving in the project area is not high enough to cause a threat to
the air quality.
Table 9: Ambient Air Quality of the Area
Sampling
Points
Nitrogen
dioxide NO2
(mg/m3)
Sulphur
dioxide(SO2)
ug/m
24
24
NEQS
NEQS
hravg
hravg
Thauti
Village
Karrang
Village
Carbon
monoxide
(CO)mg/m
Particulate
matter
(PM10)ug/m
24
hravg
NEQS
24
hravg
NEQS
19
80
20.5
120
1.22
92
250
17.5
80
18
120
1.08
81
250
The potential air quality issues within the project area are associated with the natural
emission of dust. The reservoir area is tectonically active, landslides happens
occasionally and the road becomes blocked. The entire project area is barren and
mountainous and covered with very thin vegetation. Moreover, the catastrophic floods
of 2010 and the earthquake of 2005 have contributed to the destabilization of slopes,
which are subject to frequent landslides resulting in dust emissions.
Table 10: Traffic Countin the Project Area (Average of 24 Hours)
Dates
25-Feb-13
26-Feb-13
27-Feb-13
Loader/
Passenger
Heavy
Tractor
Jeeps
Trucks
Car
Loaders
Trolleys
Pick up
16
1
8
0
0
0
12
0
4
0
0
0
11
0
7
0
0
0
Total
25
16
18
28-Feb-13
16
1-Mar-13
17
24
2-Mar-13
Average/day
15
13
1
0.67
4
6
0
0
0
0
0
0
20
19.67
Percentage
66.09
3.41
30.50
100
Page|73
b) Noise
The sound level was monitored at same locations where the ambient air quality was
monitored with the help of portable Digital sound meter. The monitoring results are
given in Table-11. The noise levels at different locations were found in range of 43.774.2 dB, which is within the range of NEQS.
Presently there is no industry and any other source of noise pollution in the project
area and only source of noise is associated with vehicular traffic. Traffic vehicles plying
in the area are also very low. Noise level exceeding 85 dB is harmful to the human
health. Excessive noise level damages the eardrum and very high levels damage
human lungs. Continuous exposure to excessive noise causes depression and can
damage the nervous system.
Table 11: Noise Level observed in the Project Area
Sampling Point
NEQS (dB)
Thauti Village
37.7 39.2
85
Karrang Village
34.5 37.6
85
c) Greenhouse Gases
Greenhouse gases are those gases (CO2, CH4, O3, CFCs and NO) which contribute to
global warming. The main sources of these gases are industries and vehicles using
fossil fuel as fuel. At present there is no industry in the project area that emits
greenhouse gas (GHG) and vehicles intensity is also very low. The main sources of
carbon and nitrogen oxide emissions are the automobiles being operated in the project
area. The traffic count data (Table 4-3) shows very less number of vehicles running in
the area and thus GHG emissions from these vehicles may not be in a quantity to have
a significant contribution to global warming. Similarly, there is no large volume of
stagnant water body in the project area which could trap significant amounts of organic
matter that could cause emissions of methane or other greenhouse gases.
4.2.
Biological Environment
4.2.1.
Flora
Most of the project area consists of bare rocky mountain and vegetation cover is very
limited and is confined only to settlement areas, agricultural fields, along stream banks,
road sides, and on mountain tops in patches. The mountain and hill slopes bear sparse
vegetation only at joints where soil and moisture are available. The common project flora
is classified into different ecological zones as shown in Table-12. The vegetation of the
area has also been grouped as trees, shrubs, herbs, grasses and fruit trees, whereas,
some common species are shown as pictures in Figure-6.
Page|74
Local Name
Scientific Name
Vegetation in settlements
Kikar
Beyu
Salix babylonica
Beyu
Salix tetrasperma
Kikar
Ailanthus altissima
Gunair
Elaeagnusm angustifolia
Kau
Olea ferruginea
Khakie
Juglans regia
Phagwara
Ficus palmata
Wheat
Triticum sp.
Maize
Zeamayz
Barley
Triticum aestivum
Potato
Solanum tuberosum
Tomato
Lycopersicon esculentum
Tori
Luffa cylindrica
Kikar
Ailanthus altissima
Elaeagnusm angustifolia
Kau
Olea ferruginea
Phagwara
Ficus palmate
Zoon
Artemisia sieversiana
Ispundar
Peganum harmala
Kabair
Capparis spinosa
Kau
Olea ferruginea
Hookaro
Tamarix aphylla
Kabair
Capparis spinosa
Ispundar
Peganum harmala
Page|75
Page|76
Page|77
Page|78
4.2.2.
Fauna
Wildlife in the Project area include the marcopolo sheep, ibex, musk deer, wolf, fox, monal
pheasant, snow partridge, chukor, eagles, vultures and falcons. No national park, reserved
area or protected area is located in the project vicinity.
The project area is not very rich in natural fauna because of hilly, bare, dry and hard
climatic conditions but some very special type of wildlife is found on the tops of the hills.
Wildlife and other fauna generally consists of mammals, reptiles, amphibians, insects,
butterflies, vectors, livestock and poultry, freshwater fish, birds and fowls.
Page|79
Biodiversity of is also at lower side except for insects as compared to the surrounding
regions because of the above said reasons.
4.2.2.1. Birds
Birds are not common in the project area due to the specific terrain
characteristics, scattered population and limited agricultural activities. A list of birds
generally found in the area is given in Table 4-6. The project area falls within the Indus
Flyway which is used by a variety of migrating birds, especially duck travelling from
Siberia to Pakistan and India. On their return in spring to Europe, these birds also follow
the Indus north before turning to the west and heading north over Afghanistan to avoid the
high Himalayan mountains. The main migration times are around December when the
southwards migration commences and in April when the flocks again return to the north.
Main migratory birds reported in the project area are Buteorutinus (pintail) Garrulous sp.
(common teal) Nucefragacaryocatactes (coot) Corvusmacrorhynchos (gray heron) and
Troglodytes trogloglodytes (sand piper)
Common bird species are tabulated as follows:
Page|80
4.2.2.2. Insects
The Kohistan district is rich in biodiversity of insects including butterflies found in the
project area, particularly during the humid months of July and August. In addition,
caterpillars, bugs, beetles, black bees, weevils, mosquitoes, ants, green aphids, codling
moths, leaf miners, mitts, fruit flies, woody aphids, stray grass hoppers, leaf hoppers,
mealy and woolly bugs, peach leaf curling aphids, scale insects, walnut weevils, blister
mites, and dusky veined aphides are all found in the Kohistan region including the Project
site in Kandiah valley.
There are no endangered, threatened or vulnerable species of fauna present in the Project
area.
4.2.3.
Aquatic Ecology
The aquatic ecology of the Kandaih River and its tributaries (Birti, Thauti and Karrang)
within the project area has been studied to assess the prevailing aquatic ecology.The
survey has shown that the diversity and composition of aquatic life vary throughout the
system. The prominent aquatic life includes fish, phyto-planktons (spirogyra) and zooplanktons (Paramecium), benthic insects, larvae of mayfly, caddis flies, mosquito larvae,
stone fly and water mite.
The fish species collected included Schizothorax, plagiostomus, Schizopygeesocinus,
Racomalabiata (all of these belonging to Family Cyprinidae), Glyptosternumreticulatum
(Family Sisoridae), and Triplophysa spp. (Family Noemacheilidae).The first three are
commercial species, whereas the remaining two are not. No exotic fish like trout, Chinese
carps etc. were caught.
4.3.
4.3.1.
Population
The Kaigah Hydropower Project is located in Kohistan district of Khyber Pakhtunkhwa
province. There are four villages (Karrang, Birti, Thauti and Dong) in the project area
which are expected to be affected directly or indirectly by the implementation of the
project. The actual population of these settlements alongwith houses are tabulated as
follows (Table-13):
Page|81
No. of Houses
112
58
25
18
Population
520
257
101
58
Karrang, Birti and Dong villages will be directly affected by proposed dam and reservoir of
Kaigah Hydropower Project. The location of proposed powerhouse and ancillary structures
will affect Thauti village.
Complete list of villages and respective population in Kandiah valley is attached as
Annexure- E.
All villages in the project area have a mixture of pacca and kacha houses. Average area of
the housing unit is 15 Marla to 1 Kanal. The area reported included both covered and
uncovered areas. It is pertinent to note that information on housing area may not be
precise as the revenue records were not available to verify the responses.
4.3.2.
Health Facilities
The health facilities are not adequate in the project area. There are Basic Health Units
(BHU) in Karrang, Joshoi and Thauti but due to shortage of qualified staff and medicine
these are not working effectively. The people of Kandiah valley have to travel to Dasu and
Besham for serious illnesses. The civil hospital at Dasu is unable to function properly due
to insufficient power supply, X-ray machine and clinical laboratory.
Lack of adequate medical facilities is the main cause of illness, mortality and infertility. The
common diseases reported from the project area are diarrhea, dysentery, and skin
problems. The main reasons for such diseases are poverty, poor diet and unhygienic living
conditions
4.3.3.
Educational Infrastructure
There are about 20 schools in Kandiah valley out of which 5 schools are middle level, only
one high school and 14 are providing education upto primary level. Also there are 9
religious institutions i.e. Madrassah which are somehow contributing to the educational
requirements of the local children.
There is no school available for girls education at all and above-mentioned boys schools
are also highly under-staffed and lack the basic infrastructure like propoer buildings and
furniture.
A very few number of students move to other towns and cities to acquire college education
or higher as thers is no such facility available in Kandiah valley.
Page|82
5.
5.1.
General
Determining the significance of impacts identified is one of the main purposes of an EIA
and it enables the identification of necessary mitigation and a determination of
environmental and social costs associated with the Project. Environmental and social
impacts of any project are identified taking into account all phases of the project cycle,
including planning, construction, operation and decommissioning. The environmental
issues and impacts of a project depend upon the nature of the project activities, and the
types and extent of interventions involved. It is not easy to predict the future and assign a
relative value or overall significance to an impact, since every impact has a different and
multi-dimensional nature, and also because it involves personal and subjective judgment
for many attributes. An environmental or social impact can be either beneficial or adverse
and is assessed by comparing the quality of the existing environment with the predicted
quality of the environment once the project is in place.
This EIA identifies the impacts likely to arise as a result of construction and operational
activities and assesses the likely magnitude of the impact in order to provide some
indication as to which impacts are likely to be most significant. A full determination of the
significance of the identified impacts, based on an assessment of the magnitude in relation
to the sensitivity of the receiving environment has been formed part of the EIA. The impact
assessment has been based on that environmental checklist developed in the light of the
guidelines of World Bank (WB) and the Asian Development Bank (ADB) as given in
following Table-14.
Table 14: Environmental Checklist
Component
Water
Land
Climate
Atmosphere
Social
Environmental Issues
Water availability
Water quality
Erosion sedimentation
Floods river bed morphology
Land submergence
Geology and seismology
Land severance due to Reservoir
Climate change
Micro-climate
Dust
Noise
Air quality
Population
Demography
Land ownership
Social cohesion
Social attitude
Gender and age
Page|83
Economic
Human use
Cultural
Fauna
Flora
5.2.
Income
Employment
Land value
Resettlements
Livestock
Fisheries
Cultivation
Transport and communication
Recreation
Lifestyle
Historical and archaeological
Sites
Aesthetics
Wildlife
Fish
Bird
Reptiles
Forests and trees
Other terrestrial Vegetation
Aquatic vegetation
5.2.1.
Sensitivity
Sensitivity is generally site specific and criteria are developed from baseline information
gathered. The sensitivity of a receptor is determined based on review of the population
(proximity/numbers/vulnerability), presence of biological features of the site or the
surrounding area, soil, agricultural suitability, geology and geomorphology, existing air
quality, presence of any architectural and historic heritage, landscape etc. Sensitivity,
relates to the value, importance and tolerance of an environmental resource or receptor
and should take into account where possible stakeholders views and public acceptability.
Sensitivity can be categorized as high, medium, low, and negligible to the assessment of
receptor sensitivity.
5.2.2.
Magnitude
The assessment of magnitude is undertaken in two steps. Firstly the key issues
associated with the project are categorized as being either adverse or beneficial.
Secondly, beneficial and adverse impacts are then further subdivided into major,
moderate, minor or negligible based on consideration of the parameters listed below:
Page|84
reversibility
likelihood, and
In order to make the report as meaningful and useful as possible, an attempt has been
made to describe each impact in the following terms: positive impacts refer to beneficial
effects and negative impacts refer to harmful effects on e.g. natural resources, human
beings and economy. In addition, it is the aim of the EIA to categorize the magnitude of
impacts identified according to the categories outlined in Table 5-2
5.3.
5.3.1.
Impacts on Topography
The project area consists mainly of hilly terrain with steep slopes having some patches
and strips of flat land being used for settlements and agriculture. Some residents have
converted the gentle slopes into terraces, where crops are grown and orchards are raised.
The interventions of the proposed Kaigah Hydropower Project are not likely to impact the
topography of the area on a large scale except for those areas which will be submerged in
the reservoir and where the physical activities of excavation, digging and movement of
heavy machinery will take place. Similarly, areas where excavated material from tunnels
will be disposed, dumped or stored will be negatively affected. This impact can be
considered as a negative impact with moderate magnitude.
Mitigation
The impact on land to be submerged in the reservoir is unavoidable and irreversible and
cannot be mitigated, but mitigation for the nuisance expected to be created by excavated
material is given in detail under Section 5.3.6.
5.3.2.
Impact of Seismicity
The project area lies near the edges of the Indian and Eurasian tectonic plates. Therefore
it is considered part of an active seismic zone having high seismic potential. In past the
epicenters of a large number of earthquakes were located in this region. In October 2005
an earthquake of very high intensity (7.8 Richter scale) hit the area and disturbed the area
to a significant extent. No change (+/-) in the impact of seismology risk of the area is
expected during the project construction phase as none of the project activities is
expected to be of such a powerful extent to influence the tectonic risk. However, the high
seismic potential of the region can disrupt the project construction activities at any time
during construction phase of the project.
Mitigation
All structures to be built must be designed giving maximum allowance to seismic factors.
A very careful analysis of the situation will be required during the design stage of the
project by specialist consultants.
5.3.3.
Impact on Geology
Almost all project interventions involve extensive excavation of natural rocks, cutting of
formations, moving and dumping of spoil. During tunnels excavation and some other
operations, extensive blasting of the formation will be required. All these activities will
disturb the existing stable geological formations and consequently physical features of the
local geological formations of the project area will be damaged at some places, which is a
negative impact of minor magnitude.
Mitigation
All these activities are an integral part of the project interventions and cannot be avoided.
Blasting should be minimized where possible (near the surface) and, if unavoidable, low
Page|86
power explosive should be used and a greater number of blasts with low power material
may be preferred instead of high intensity single blasting.
In case of implementing TBM procedures for excavation of tunnels, special care must be
taken in order to assess the gravity of the impacts generated or foreseen.
5.3.4.
Impacts on Landslides
Landslides are common in the project area due to the high steepness, common seismic
activities and unstable geological formations on both sides of the river. Due to the project
activities, especially blasting of rocks in some areas, the formation will become loose and
the risk of landslides will increase in the immediate vicinity of the construction sites, which
may be considered as a minor negative impact of the project.
Mitigation
Minimize blasting of formations and, if unavoidable, then use low intensity explosive if
possible.
5.3.5.
5.3.6.
Page|87
construction of the project. The nuisance created by excavated material will be a major
negative impact of the project.
Mitigation
To reduce the negative impacts of excavated material: firstly, the emphasis should be to
reduce the volume of material requiring disposal and, secondly, to dispose it in
environmentally friendly way. The following measures are proposed in this respect:
5.3.7.
As far as disposal on the dam site are aisconcerned, some of the spoil can beused for
construction of upper and lower coffer dams and other project related structures. To
reduce the volume of spoil requiring disposal, one option could be to increase the
width of the cofferdams
To make the dam site easily accessible form ovement of heavy machinery and for
large number of vehicles (per hour/per day), it will be necessary to improve, upgrade
and widen the existing road from Kandiah Bridge to the dam site (28km). Some of the
spoil can beused for widening of this road.
The spoil can be dumped at various places along the river between the dam and
powerhouse sites. There are many places along this length along the river where spoil
can be dumped without narrowing the river section. A special purpose survey to
identify the exact points can be conducted during the design stage of the project.
Part of the excavated material on the powerhouse site can be used for making
aggregate required for project construction and for the development of infrastructure
such as roads and filling of natural depressions
At the powerhouse site, within the colony area, the material can be dumped as a manmade hill(s) at any suitable place(s) to be identified during construction phase,
levelled and covered with a mixture of sand easily available from the river for
improving the vegetation in the area. Initially, native bushes and grasses can be
planted and, with the passage of time, some natural vegetation will grow and cover the
whole spoil dumps, which will increase the greenery and enhance the aesthetic
scenery of the project colony area.
Impacts on Infrastructure
The maximum reservoir level of the reservoir has been fixed at El 1500 masl and details of
the infrastructure to be affected require moving or need compensation due to the
implementation of the project is shown in Annexure F1 & F2. Most of the damage is
centred on the village of Karrang and part of the village Birti in addition to Dong which also
falls within the reservoir limit in addition to Thauti village which is located near to proposed
powerhouse site. The remaining part of the Karrang and Birti village which will not be
directly submerged into the reservoir, is located very near to the periphery of the reservoir
and on a highly unstable formation, and will require relocation from the present place. The
displacement of these villages will be the major negative impact of the project.
Page|88
Mitigation
Damage to infrastructure will be compensated at market rate. The PAP of the village of
Karrang, Birti, Dong and Thauti will be given the option to obtain full compensation at
market rates for all sorts of damage or to get the land plus construction cost to build the
house at any proper place near the project area. The potential sites for relocating PAP
have been identified and are shown on AnnexureF5. The PAP will be offered a special
package(s) in the light of prevailing government policy. The detail of the compensation
package(s) will be provided in the Resettlement Action Plan (RAP) to be prepared
separately at design stage of the project.
5.3.8.
Impacts on Climate
The interventions planned during the construction of the Kaigah Hydropower Project are
given in Chapter 2. No impact on climate of the whole project area is expected, either
positive or negative, during the construction phase. Project construction involves large
scale activities including the movement of different types of light and heavy traffic, working
of heavy machinery, blasting of rocks, operation of batching and mixing plants and the
presence of large numbers of people in the area. Due to all these activities, it is expected
that the microclimate of the project area (surrounding the dam site and powerhouse site)
will deteriorate significantly.
Mitigation
The deterioration in the local climate during the construction phase will be of a temporary
nature and will disappear with the completion of the project. However, some measures to
minimize the impacts on air quality mentioned under Section 5.3.14 will also be helpful to
mitigate the impacts on micro climate of the area.
5.3.9.
Impacts on Hydrology
During the construction stage, there will be only minor changes in the hydrology of the
river except in the area between upper and lower cofferdams. The flow from upper side of
cofferdam will be diverted to downstream of the lower cofferdam through diversion tunnels
and thereafter flow in the river will flow in the historic pattern. The adverse impact may be
considered as of negligible magnitude.
Mitigation
No mitigation is required as impact is unavoidable and very minor in nature.
Page|89
Mitigation
No mitigation is required as impact is unavoidable and very minor in nature.
pollution. The impact on air quality is considered as short duration negative impact of
moderate magnitude.
Mitigation
All sources of air quality deterioration will be for short duration, temporary in nature and
associated with project construction activities, which will end with the completion of the
project. The contractors and sub-contractors must be held responsible through special
clauses in the tender documents to strictly follow the following measures:
Use of new and good condition old vehicles which emitless quantity of smoke
Avoid blasting to the maximum level but where necessary make the moderate intensity
blasting instead of heavy intensity and blasting must be during day time.
The clearance of the reservoir from all types of vegetation is necessary to reduce the
emission of large quantities of methane (CH4) which is a greenhouse gas. Clearance
of the reservoir area from all types of vegetation before filling with water will be
required. Methane gas is produced due to the decomposition of organic matter in the
water in anaerobic conditions. Almost all existing trees and other vegetation within the
reservoir limit (below El 1500 masl) will be required to be felled before filling of the
reservoir at the end of construction phase. It is estimated that approximately 300 trees
will have to be felled. Some shrubs, bushes and grasses in addition to trees identified
will also be submerged by the reservoir. No endangered, threatened or vulnerable flora
species exist in the reservoir area. The medicinal plants grow at higher elevations.
There is scanty growth of bushes on both the left and right banks of the river in the
Page|91
project area. The felling of a large number of trees is a major negative impact of the
project.
Mitigation
Cutting of trees falling within the reservoir limit is unavoidable and the following measures
are proposed to reduce the negative impact of tree felling:
For mitigating the impact of trees felling from the reservoir area, the project proponent
will be responsible for planting twice the number of native species of plants in the area
along the periphery of the reservoir, on flat lands where available, along the river and
streams from the dam site to powerhouse site. Plants will be removed before filling of
reservoir but replanting of new plants can be started from the time of the beginning of
the construction period so that new plants can be come almost the same size at the
time of cutting of trees.
Page|92
There will be significant impacts on insects during construction phase, as large number of
insects in the construction areas will be killed due to the project activities. It is assumed
that some insects would move to similar habitats in the neighborhood. In the temporary
labour camps, the numbers of insects would grow due to the availability of water, sewage
water and solid waste disposal areas.
During construction works, it is possible that amphibians and reptiles would escape and
find new habitats. On the other hand, growth of reptiles in and around labour camps is
expected to increase due to the availability of water (fresh water and sewage) and nutrition
(insects and garbage). In particular those amphibians and reptiles will be adversely
affected who are more sensitive to noise, vibration, and light during night. Reptiles along
roads and near settlements are killed frequently even under present traffic conditions.
This may be expected to increase due to increased traffic during the construction period.
Overall, the construction activities will generate impacts of negative nature on all types of
fauna but of moderate magnitude.
Mitigation
Almost all impacts will be of a temporary nature, which will end with completion of the
project. Dumping of construction materials should be avoided in areas where mammals,
amphibians, reptiles and birds settle. Contractors will have to select suitable dumping
areas by considering only those locations which have less chances of faunal habitation.
Annexure- F5. A Resettlement Action Plan to safeguard the rights of PAP and to ensure
their complete and comprehensive rehabilitation and to restore their livelihoods and living
standard will be prepared at the design stage of the project.
Page|94
Mitigation
The proposed Project Environmental and Social Management Unit (PESMU) will be
required to take care of occupational health and safety requirements of the project.
PESMU can employ a part time qualified occupational safety officer during the
construction phase.The contractors will need to carry out risk assessments and then
develop site and project specific Health and Safety Management Plans to prevent
accidents, injuries and work-related diseases.
The main measures include carrying health screening of workers, identifying potential
hazards to workers, particularly those that are life-threatening, providing preventive and
protective measures for hazardous conditions or substances; training and equipping
workers with information and personal protective equipment (PPE) with the aim of
preventing accidents, injuries or diseases and of minimizing hazards, documenting
and reporting occupational accidents, diseases and incidents and to develop emergency
prevention, preparedness and response arrangements.
It is recognized that poor labour management practices, for instance frequent and long
overtime and lack of legally required minimum wages, combined with a lack of adequate
occupational health and safety focus can lead to accidents. Providing satisfactory and safe
working conditions will promote the ability of the labour force to achieve tasks without
undue delays and discontentment, which can have financial ramification.
74 km further on the north. The portion of existing path from Kandiah Bridge to dam site
will be submerged in Dasu reservoir requiring its construction on the higher level.
Moreover, the road from Kandiah Bridge to dam site will have to be constructed in order to
materialize the project.
Mitigation
The upgrading of the KKH is already under consideration by the government. It is hoped
that the upgraded KKH will be available by the time the project is started. It includes the
connection of Kandiah valley with KKH on the right bank of River Indus. Road within the
Kandiah valley (28 km) will be constructed to implement the project.
Care must be exercised for the safe transport of raw materials and the transport and
disposal of waste. The contractors should not be allowed to use products that fall under
hazard classified by the WHO as pesticides. Project vehicles and equipment will be
maintained properly and project related traffic will be required, as a minimum, to travel at
not more than the speed limit.
communities may try to benefit from the employment opportunities, the increase in
localized population density is likely to increase interaction among the migrant and
sedentary population which may create some psychological disturbances, for instance
feelings of insecurity about sustaining each the cultural identity of each group.
Mitigation
The impacts described above will occur during the construction period and are reversible
once the project is complete. Efforts will be made by the PESMU to inform and consult the
leaders and elders of the community about the project, especially regarding mobility and
access through the construction areas. Their access and mobility requirements will be
accommodated by providing rights of way and access through the construction zone in
such a way that women and girls feel comfortable. Efforts will be made to ensure, and
where necessary improve, water availability in the dry season for shepherds, human and
livestock consumption.
Impact
Negative
No
Intensity
Major
Moderate
Moderate
Moderate
Minor
Moderate
Minor
Moderate
Moderate
Minor
Minor
Major
Minor
Minor
Moderate
Minor
Page|97
Communication
Heritage and archaeology
Tourism
Women and indigenous people
5.4.
Moderate
5.4.1.
Impact of Seismicity
The project area lies near the edges of the Indian and Eurasian tectonic plates and is
considered as part of a seismically active zone. In the past, the epicenters of a large
number of earthquakes were located in this region. In October 2005 an earthquake of very
high intensity (7.8 Richter scale) hit the area and disturbed the area to a significant extent.
The construction of very large structures such as the dam and reservoir may enhance
seismic activity in the area which can adversely affect the dam structure, headrace
tunnels, main access tunnel, diversion tunnels and other structures as well as public and
private property besides the loss of human life.
Mitigation
As the project is situated in an active seismic zone, continuous monitoring of the
behaviour of faults will be required during the operation stage and contingency plans to
deal with such a situation must be part of the project management. Instruments to monitor
seismic activity must be installed at the time of construction.
5.4.2.
Impacts on Geology
During operation of the project the seepage from the reservoir will significantly impact the
geology of the area. The seepage water will saturate the formation below and along the
reservoir and soluble minerals from the rocks will dissolve in the water. Some solution
channels may develop in the formation making the formation more pervious.
Mitigation
It is difficult to check or reduce the seepage from the reservoir, but seepage rates will
reduce with the passage of time when most of the pores and openings in the bed and
along the surface of the reservoir will be blocked with silt. A continuous monitoring system
will be required during operation of the project to monitor the changes in groundwater level
and chemistry of ground water.
5.4.3.
Impacts on Landslides
It is expected that landslides will increase substantially along the reservoir due to seepage
of water in the beginning when the reservoir is first filled with water. The seepage of water
Page|98
will make the formation loose and unstable and the chances of sliding due to rainfall,
abnormally high and low temperatures and due to seismic activities will increase. The
phenomenon will become less common with the passage of time as formations more
prone to sliding will wear out. The major impact of these landslides will be a reduction in
the storage capacity of the reservoir. However, as compared to the total volume of the
reservoir, reduction in storage will be very nominal and also part of this sliding matter will
pass from the reservoir during annual flushing. This impact may be considered as a minor
negative impact.
Another significant impact of the project due to landslides will be the risk of sliding of the
formation on which the village of Karrang is located. This impact will be a major negative
impact of the project.
Mitigation
As no mitigation is possible to check either the seepage or any resulting landslide,
Karrang village will be relocated to any suitable place before completion of the
construction phase. Some potential sites have been identified and are shown on
Annexure- F5, where sufficient space is available for resettlement of PAP who will be
given the choice to get cash compensation for the assets lost and to move to any other
place of their own choice. More details on rehabilitation aspect will be provided in the RAP
to be prepared separately as standalone document at the design stage.The impact of
sliding will reduce with the passage of time, as after a few years of project operation most
of the rocks along the periphery of the reservoir will become stable.
5.4.4.
5.4.5.
Page|99
dumped without narrowing the river section. A special purpose survey to identify the exact
points is proposed to be conducted during design stage of the project.
5.4.6.
Impacts on Infrastructure
There is no such infrastructure like bridges or cable crossings which will be eliminated by
the reservoir or any other project component. Besides, the road on top of the dam at crest
level can be declared as a thoroughfare for people of the area which will be a more
reliable crossing point for them to cross the river. So, in general, it can be taken as a
positive impact.
5.4.7.
Impacts on Climate
The Kaigah Hydropower Project will create a 3.5 km long reservoir with surface area of
74300 m2 when full at El 500 masl.This large water body will be a major hydrological
change that is likely to impact the climate of the area.The moisture contents in the
atmosphere, especially during summer, will increase substantially. The present climate of
the project area is dry and temperate and induced evaporation will increase relative
humidity and decrease the mean maximum and minimum temperature of the area.
Dew formation will take place during the night when temperatures will drop and
atmosphere will become super-saturated with high humidity. There is a possibility of fog
formation in the winter months along the periphery of the lake.This change in climate will
have a major positive impact in the project area as, because of the higher humidity, there
will be less evaporation from the bare land and transpiration from the vegetative cover of
the area resulting in increase of vegetation and greenery. The area relatively closer to the
reservoir is expected to have drastic positive impacts because of more moisture in the
plant root zone as well as in the air.
5.4.8.
Impacts on Hydrology
The hydrology of the river Kandiah starting from upper limit of reservoir to the end of the
tailrace channel near Thauti village is expected to change significantly during operation of
the project. A water body in the form of the reservoir will emerge in the area and the water
flow pattern will change as significant volumes of water will be diverted towards headrace
tunnels to generate power. The worst affected area will be the river bed from dam site to
Thauti village. The flow in this part of the river will reduce drastically below historic flows.
However, as there is minimum human population on this section of the river getting any
sort of benefit, no negative impacts on human population are anticipated due to changes
in the hydrology. However, changes in river flow patterns from the dam site to Thauti
village will have impacts on the aquatic life of the river, although presently there is very
little vegetation on the banks and in the bed of the river.The reduction in river flow will
adversely affect the aquatic life specially fish which will be negative impact of the project.
Mitigation
To conserve the aquatic life (flora and fauna) of the river downstream of the dam to Thauti
village, minimum flow of 2 m3/s has been estimated as the environmental flow. It will be
Page|100
obligatory for project operating agency to release 2 m3/s in the river throughout the year as
environmental flow.
5.4.9.
Page|101
By damming the river, the river velocity is reduced which also reduce the transport
capacity of the flow, as a result deposition will take place all over the reservoir area. The
capacity at over sections of the reservoir is reduced.
The sediment concentration during the year will reduce below the dam as some part of the
sediments will settle in the reservoir bed but at the time of flushing of the reservoir a large
quantity of sediments will be released in the river bed in a very short time. It is expected
that abrupt release of sediments in large quantity will change the morphology of the river
below the dam. However, as sediments will be released with very high velocity of water
and the river in this section has a high natural gradient, it is expected that sediment will
move far away from the dam.
Complete flushing of the reservoir from sediments deposition is not possible, which will
reduce the storage capacity of reservoir considered to be negative impact of the
sedimentation on reservoir.The sediments released in large quantity during flushing will
create some alluvial fans in the riverbed, which will serve as habitat of flora and fauna and
will become source of food for fish and other aquatic life.This will be a minor positive
impact of the project.
Mitigation
The silt clearance mechanism will be provided through sluices and flushing of the silt from
the reservoir must be completed at reasonable intervals.
Mitigation
The mitigation of this impact is difficult as there is no way to check or reduce the seepage
from reservoir, although seepage rates are likely to reduce with the passage of time when
most of the pores and opening in the bed and along the reservoir will be blocked with silt.
To monitor the changes in groundwater level and chemistry, a continuous monitoring
system will be required along the periphery of the reservoir.
there are no exotic cold water fish species currently found in the Kandiah valley of
Kohistan but there is a strong possibility to induce and increase their controlled
productivity in the reservoir of Kaigah HPP.
Although the project is a run-of-river type, it is expected that due to the induced low
gradient and resultant low water velocity in the reservoir (because of the impounding of
the reservoir) some species of fish can be cultured. It is a valid assumption that due to the
creation of this water body, reduced velocity and turbulence and availability of spawning
grounds in reservoir would generally favour enhancement of fish stocks. That would have
a positive impact on fish production and fishery.
In addition, trash racks or fish screens might have to be established in order to
control entry particularly into the intakes (power tunnels, turbines, sluices, spillways).
Fishing by the staff of the contractors will be prohibited through appropriate provisions in
the tender documents.The PESMU will have to control any form of poaching.This will
include performing regular unannounced inspections and checks at suitable locations
within the project area. Some enhancement of prescribed penalties will have also to be
enforced.
Enhancement Measures
During design stage of the project a special study may be conducted to find the
fisheries potential of the project
Dumping of spoil material in the Kandiah River and adjacent nallahs to be avoided
Sewage water treatment discharged from all labour camps and toilet facilities must be
treated before disposal into the river
Tanks of fuel,oil and other liquids to be placed quite distant from any water body
Oil changes for engines and other machinery to be only allowed in workshops
All vehicle and machinery to be maintained properly in order to avoid any leakages
Page|104
Category
Positive
Negative
Seismicity
Geology
Landslides
Land use
No
Dismantling material
Physical infrastructure
Climate
Hydrology
Kaigah river
Page|105
Surface water
Sedimentation
Flood
Ground water
Air quality
Power
Employment opportunities
Social services
Women
Page|106
6.
6.1.
6.2.
6.3.
Page|107
The contractors must be made aware through contract documents of the importance of the
environmental and social components of the project.They should be prepared to cooperate with the executing agency, project management, supervising consultants and
local population for the mitigation of impacts. Furthermore, the contractor must be legally
bound through the contract to implement the Environmental Management Plan in full and
be ready to engage trained environmental management staff to monitor the
implementation and effectiveness of the mitigation measures as the project proceeds.
6.4.
Institutional Requirements
It will be the responsibility of Project Proponent to implement and monitor the mitigation
measures proposed in this chapter.The following institutional arrangements will be
necessary to implement the MMP and to deal with other environment related issues.
6.4.1.
Project Sponsor
Representative
Status
Project director
Chairman
Head of PESMU
Secretary
Government
Member
Consultant
Resident Engineer
Member
Main Contractor
Designated Engineer
Member
EPA
Member
Local Government
Member
NGO
Member
6.4.2.
Page|108
Ensuring that all contractors follow the PEPA regulations and other requirements
stipulated in the construction contracts concerning dust suppression, solid waste
disposal, municipal waste water disposal, air pollution, noise and vibration, biodiversity
and safety, transport,storage and use of flammable and explosive materials
Liaison with the neighboring communities for their concerns about the construction
activities
Ensuring proper disposal of all the construction spoil (excavated material and
construction materials)
No
Remarks
Environmental Expert
Social/resettlement
Expert
Administrative and
supporting staff
6.4.3.
Page|109
Representative
Director or Executive Engineer
Head of Land acquisition
Status
Chairman
Coordination
Head of PESMU
Secretary
Contractor
Resident Engineer
Member
Line agencies
Member
Member
Member
Member
Local Government
Member
NGO
Member
Member
Community
The implementation of the project will imply the assessment of damages, calculation and
payment of compensations, and attention to day-to-day complaints of the community
members as and when they are affected by project operations. Developers should
consider withholding 10% of the interim payments of the contractors until it is satisfied that
the Contractor has fulfilled the environmental and social obligations provided in the
contract.
The cost of properties likely to be damaged, removed or relocated will be assessed by
PESMU. An inventory of the properties will be maintained in the compensation registers.
Where needed, the relevant Revenue Record will also be consulted to verify land
ownerships. All the payments will be made in the presence of local representatives,
through crossed cheques. PAP will be informed of their rights, and of the procedures for
addressing complaints whether verbally or in writing during consultation, survey, and at
the time of compensation.
The project management should adopt a policy of preventing grievances rather than going
through a redressal process.This can be achieved through careful development of the
compensation procedure and its implementation, by ensuring full participation and
consultation with the PAP, and by maintaining effective communication and coordination
between the community, project management, contractors and local government.
6.5.
be implemented during this phase. The management of the proposed mitigation measures
will cater following categories:
6.6.
Resolve conflicts with community through the Project Conflict Resolution Committee
Excavated Material
Page|111
COMPONENT
RECOMMENDED MITIGATION
MEASURE
IMPLEMENTATION
RESPONSIBILITY
PM, ,PC, C,
PESMU
Geology
PM, PC
Landslides
PC, C
Climate
C, PESMU
Page|112
Sedimentation
PC, C, PESMU
Incidental damage to crops, trees and vegetation Replanting of almost double the number
during project works. Loss of trees within the
of trees of native species along the
dam site, reservoir area and powerhouse sites
periphery of the reservoir where relatively
flat land is available. Assess value of lost
trees and arrange payment of
Felling of trees from the reservoir
compensation
C, PESU, PGRC
C, PESMU
Resources
C, PESMU
Page|114
Indigenous people
C, PESMU
Women
C, PESMU
Page|115
RECOMMENDED MITIGATION
MEASURE
IMPLEMENTATION
RESPONSIBILITY
Seismicity
Geology
Landslides
PC, PESMU
Page|116
Surface Water
Sedimentation
PM, PESMU
Page|117
Page|118
PC, PESMU
7.
7.1.
General
Parameters to be monitored
Frequency of measurements
Provisions are proposed to ensure that all construction phase monitoring is integrated into
the standard operating procedures of construction, to ensure that all monitoring outcomes
can be responded to promptly. In addition to recording information to track performance
and establishing relevant operational controls, mechanisms will be employed, such as
inspections and audits, where relevant, to verify compliance and progress toward the
requirements of the EMP. The extent of monitoring will be commensurate with the risks
and impacts of the project and compliance with the project requirements and include
procedures for documentation, reporting and feedback of the outcomes of corrective and
preventive actions.
In general, the objectives of the monitoring will be to:
Record the inputs provided by various participants in the environmental and social
management process (i.e. client, consultants, contractors, etc.)
Record the number of persons affected, and the values and assessments of their
damage
Check whether the prescribed guidelines and plans are being followed
Ensure that the required mitigation measures and activities are being accomplished in
time
Page|119
7.2.
Ensuring that the PESMU is in place, staffed and equipped well before start of
constructionwork
Conducting additional base line environmental and social studies for gaps identified
from any source after issue of the EIA
Selection of sites on the river which could be affected by project activities e.g. labour
camps, spoil material dumps
Observation of the ambient air quality at and around sites which could be affected by
vehicles if not already done
Checking the contractors tender submissions, particularly to ensure that all necessary
environmental requirements have been included
Checking that guidelines on topics such as health, safety and environment, route
plans, and waste disposal plans are available for the contractors
Checking that different contingency plans are available before start of the construction
works.
The main responsibility for design stage monitoring will rest with the Project Consultant
and the PESMU. They should have regular meetings with the local community groups, to
discuss and obtain their views on the activities of the project, and use this communication
as a channel of monitoring. The consultant could also collect required necessary
information through direct measurements, consultation and informal interviews with
affected households.
7.3.
Page|120
record the environmental performance of the project and to guide any remedial action to
address unexpected impacts.
7.4.
7.5.
7.5.1.
Internal Monitoring
It is important that the senior management within both the Kaigah Hydropower Project and
donor(s) receive periodic assessments of the effectiveness of the environmental
management programme, based on systematic data collection and analysis. The scope
and frequency of such reporting will depend upon the nature and scope of the activities
identified and undertaken in accordance with environmental management programme and
other applicable project requirements.
Results of the internal monitoring carried out by the different participants will be reported in
their periodic reports for information on indicators for implementation of the measures, as
well as the achievements and results.This information will be collected directly from the
field and reported monthly to the project management to assess the progress and results
of implementation of the mitigation and management measures and to provide any
necessary feedback and actions.The monthly reports will be summarized in the quarterly
reports and will be sent to donors and other concerned quarters to be determined by the
project management.
7.5.2.
External Monitoring
The objectives of external monitoring will be: firstly, to verify that environmental
and social mitigation measures are implemented as presented in the EIA and other
environmental reports; and secondly, to ensure that compensation is paid promptly to PAP
and organizations, and interruptions to their incomes and lifestyles are restored at least to
previous levels.
Indicators for external monitoring, in addition to those required during internal monitoring,
will include:
Impact assessment through formal and informal surveys with the PAP
Assess the efficacy of the mitigation measures, especially the resettlement frame-work
and grievance resolution mechanism, and draw lessons for future resettlement policy
formulation and planning
7.6.
Institutional Requirements
7.6.1.
Institutional Responsibilities
Project developers have the overall responsibility for preparation, implementation,
monitoring and financing of environmental and social safeguards.This is a large task,
which will demand execution of many kinds of office and field activities, at several levels to
address project requirements at the various stages of the project i.e. planning,
construction and operation.
7.6.2.
Institutional Arrangements
The Mitigation Management and Environmental Management Plans reported in Chapters
6 and 7 respectively, include a set of mitigation, monitoring and institutional measures to
be taken during implementation and operation of the project, to eliminate adverse
environmental and social impacts, offset them, or reduce them to acceptable limits.The
staff allocated to monitoring the MMP and EMP must have the capability to handle the
complexities and size of the Kaigah Hydropower Project.They must have been trained to
accomplish the jobs related to resettlement and monitoring in addition to academic
qualifications.
This can be achieved through a series of short awareness raising and training sessions on
the related topics, at regular intervals especially during the construction phase and
throughout the project life to cover all stages.The contents of the courses should be
designed for the needs of each target group.
Some of the training workshops could be conducted twice in each year, for the first two
years and yearly thereafter to share the monitoring data on the implementation of the
EMP, to share lessons learned in the implementation and to decide on remedial actions, if
unexpected environmental impacts occur. Most of the courses and workshops could be of
one or two days.
7.6.3.
Page|122
7.7.
Environmental Audit
It is proposed to arrange environmental audits of the project: one in middle of the
construction phase and secondly at the end of construction activities.The objective of the
environmental audit is to have an evaluation of the execution of the environmental
obligations of the project authority proposed in EIA. Environmental auditing is generally
done by an unbiased independent organization or a person having full command on the
subject. The terms of reference for environmental audits will be designed by the project
consultant with the collaboration of donors. The findings of the environmental audits will be
circulated to project management, environmental authorities and donors and other
interested parties.
Page|123
MONITORING TASKS
TIMING
LOCATIONS
INDICATORS
RESPONSIBILITY
Land
topography,
land use,
disposal of
excavated
material
Disposal of spoil
material in violation of
MMP
Monitoring of
excavated material
disposal sites
Weekly
PC, C, PESMU
Landslides
Instability of geological
formations identified
during feasibility stage
Inspection of sensitive
points prone to
landslides identified
during feasibility
Quarterly
Appearance of
cracks,
indications of
sliding and
movement of
formation
PC, PESMU
stage
Sedimentation
Sedimentation in river
water
Monitoring of
concentration of
sediments in river
water
Quarterly
Downstream of dam
Sediments
site at any suitable
concentration in
point (quarterly
ppm or mg/l
collection of water
samples from the same
site)
PESMU
Surface water
Deterioration of river
Monitoring of changes
Quarterly
Downstream of dam
Sample collection
Page|124
Nature and
quality
water quality
in dissolved soluble
salts and presence of
E. coli bacteria
concentration of
individual salts.
Total
concentration
by PESMU and
analysis from a
reliable laboratory
of salts and
presence of E.
coli bacteria with
respect to NEQS
Air quality
Check conditions of
vehicle running in the
project
Qualitative
through
visual
observations
at weekly
intervals
Quantitative
at yearly
basis
Visual
observations of
emissions, dust
and noise, etc.;
number of
complaints.
Visual
observations.
No of violations
during sleep
hours;
complaints.
Check compliance by
drivers and operators
Visual
observations of
faulty vehicles
Page|125
PESMU
For quantitative
survey by hiring
services of a
suitable laboratory
Damage
compensation
Compensation to
PAP
Inventory and
valuation of assets and
infrastructure damaged
% of damages
paid as compared
to total damages
PC, PESMU,
PGRC
Land
acquisition
3 years
To be selected in
before
consultation of PAP
completion
of the project
Selection,
arrangement of
payment and
possession of
land
PC, PESMU,
PGRC
Agriculture
and planting
Throughout
the
construction
period
Health and
safety
Monthly
Working places,
labour camps,
residential areas and
offices etc.
No. of cases
reported per
month
PESMU
Women
Check compliance
with agreed procedure;
number of complaints
if any
During all
construction
activities
No. of complaints
observed or
recorded
C, PESMU
Employment
Scope of job
opportunities for local
communities on project
sites
Compliance with
agreed procedure for
hiring of local labour
Monthly
No. of
opportunities
available
C, PESMU
Page|126
PC, PESMU
MONITORING TASKS
TIMING
LOCATIONS
INDICATORS
RESPONSIBILITY
Land
topography,
land use,
disposal of
excavated
material
Disposal of spoil
material in violation of
MMP
Monitoring of
excavated material
disposal sites
Monthly
Location of spoil
dumps
PC, C, PESMU
Landslides
Instability of geological
formations identified
during feasibility stage
Inspection of sensitive
points prone to
landslides identified
during feasibility
Monthly in
first year and
quarterly
thereafter
Periphery of reservoir
Symptoms of
land sliding
PC, PESMU
stage
Sedimentation
Sedimentation in river
water
Monitoring of
Monthly
concentration of
sediments in and out of
reservoir
At start of the
Sediments
reservoir and
concentration in
downstream of dam
ppm or mg/l
site at any suitable
point (monthly
collection of water
samples from the same
site)
PESMU
Surface water
Deterioration of river
Monitoring of changes
in dissolved soluble
Downstream of dam
site at any suitable
Sample collection
by PESMU and
Quarterly
Page|127
Nature and
concentration of
quality
water quality
point (collection of
water samples from
the same site)
E. coli bacteria
individual salts.
Total
concentration
analysis from a
reliable laboratory
of salts and
presence of E.
coli bacteria with
respect to
NEQS
Air quality
Check conditions of
vehicle running in the
project
Qualitative
through
visual
observations
at weekly
intervals
Quantitative
at yearly
basis
Visual
observations of
emissions, dust
and noise, etc.;
number of
complaints.
Visual
observations.
No of violations
during sleep
hours;
complaints.
Check compliance by
drivers and operators
Visual
observations of
faulty vehicles
Page|128
PESMU
For quantitative
survey by hiring
services of a
suitable laboratory
Compensation
Balance (leftover)
compensation of
damages to PAP
Health and
safety
Occupational health
and safety of workers
To monitor
occupational health
hazard
Monthly
Working places,
labour camps,
residential areas and
offices etc.
No. of cases
reported per
month
Women
Check compliance
with agreed procedure;
number of complaints
if any
During all
construction
activities
Indigenous
people,
cultural
heritage and
archaeology
Continuous
No. of cases
reported
PAP
Page|129
PC, PESMU
PESMU
PESMU
8.
POTENTIAL ADDITIONAL
MECHANISM
8.1.
Introduction
REVENUE
UNDER
CLEAN
DEVELOPMENT
The United Nations Framework Convention on Climate Change (UNFCCC) was one of the
key outcomes of the United Nations Conference on Environment and Development
(UNCED) in Rio de Janeiro in 1992. The stated objective of the UNFCCC was to stabilize
greenhouse gas (GHG) concentrations in the atmosphere at a level that would prevent
dangerous human interference with the global climate.The convention divided countries of
the world into two groups: Annex-1, the industrialized countries (38 in number) which have
historically contributed the most to anthropogenic climate change, and non-Annex-1
countries which include primarily the developing countries. The principal of equity and
common but differential responsibilities contained in the convention requires Annex -1
countries to take the lead in reducing their GHG emissions.
8.2.
Kyoto Protocol
The Kyoto Protocol was adopted in Kyoto, Japan in 1997 at the third conference of the
parties (COP) to the UNFCCC. At this historic meeting the COP negotiated a set of
binding quantitative targets for Annex-1 countries to reduce their GHG emissions (the
protocol did not become legally binding until February 2005).These targets are to be
achieved separately by each Annex-1 country as a percentage reduction below 1990
emission levels. During the first five-year commitment period from 2008 to 2012, the total
reduction adds up to 5%. A target beyond 2012 has not yet been agreed.
The Kyoto Protocol legally binds all Annex-1 countries to limit their national emissions to
the specified target level. Based on the principle that the effect of GHG on the global
environment is the same regardless of where emission occurs geographically, the Kyoto
Protocol establishes three Flexibility Mechanisms to help the Annex-1 countries to
reduce the costs of meeting their emissions targets by allowing them to realize emission
reductions at lower costs in other countries. These three mechanisms are:
Joint Implementation JI
JI and CDM are project based mechanisms which involve developing and implementing
projects that reduce GHG emissions, thereby generating carbon credits known as
Emission Reduction Units (ERUs) or Certified Emission Reductions (CERs) that can be
sold in the carbon market. JI allows the generation of ERUs from projects within Annex-1
countries, whereas CDM allows the generation of CERs from projects within non Annex-1
countries. IET allows trading of Assigned Amount Units (AAUs) directly between Annex 1
countries to meet their respective emission reduction targets.
Page|130
8.3.
8.4.
GHG
GWP
1
21
310
15011,700
6,5009,200
23,900
Land use, Land use Change and Forestry (forestation and re-forestation)
Waste Management (e.g. landfill, solid waste management, recycling, animal and
livestock waste)
Page|131
vehicles,
mass
transit
systems,
cleaner
CDM projects provide opportunities for accessing "additional" financing for local
sustainable development priorities in the country and as such have the potential of
"catalyzing" large Foreign Direct Investment (FDI) flows because:
CDM projects are being used as instruments for "appropriate" and "environmentally
friendly" technology transfer
CDM projects help in addressing local environmental issues -(air/water pollution, solid
waste management,enhancement management, etc.)
CDM projects are effective instruments for environmentally friendly alternative energy
production
CDM projects help by creating jobs and building local capacities, and contributing to
other sustainable development aspects of the national economy
In order for a project to generate Certified Emission Reductions (CERs) it must undergo a
rigorous process of documentation and approval by a variety of local and international
stakeholders.The key stages in the CDM project cycle are:
The process is being continuously updated by the CDM Executive Board (EB) and various
conditions and limitations are being incorporated in the process.Once the project is
registered with UNFCCC- EB the CERs may be issued at any time following verification
and other formalities.
8.5.
It must provide real, measurable and long term benefits related to mitigation of climate
change using a baseline and monitoring methodology approved by the UNFCCC
It must deliver reductions in emissions that are additional to the emission reductions
that would occur in the absence of the project activity
It must not result in significant environmental negative impacts and must have
undertaken public consultation
Page|132
It must not result in the diversion of official development assistance (ODA) from a
developed country to developing country.
result in new reservoirs, where the power density of the power plant is greater than 4
W/m.
The power density is calculated as power generation capacity divided by reservoir surface
area when full. The power density of Kaigah HPP is 7.375 W/m2. Because the reservoir is
so deep it easily exceeds the 4 W/m threshold for CDM eligibility.
The Kaigah HPP has many positive points which can help justify its inclusion in the CDM.
When the project is compared to other dam projects, the number of people to be displaced
is quite small (a few hundred) and because the project is of the run of river type situated in
a narrow valley the reservoir area is very small. Furthermore, the expected input of
organic matter that acts as a source of methane production is negligible (catchments
almost bare) with no stagnant water, again necessary for methane production. The project
will have 545 MW of power generating capacity which will replace the power to be
generated with the burning of fossil fuels mainly imported from other countries. The project
will also contribute to the sustainable development of the country with economic and social
benefits to the area.Technology transfer from developed countries during construction and
operation are additional benefits.
Therefore, considering the aims of the CDM and the salient features of the Kaigah HPP
and potential environmental and social impacts associated with the project, it can be
concluded that the project fulfils almost all basic requirements needed to qualify for
consideration under the CDM (mentioned above).
8.6.
Carbon Credits
Carbon credits or CERs generated by any project under the CDM depend upon the net
capacity of that project to provide GHG emission reductions after becoming operational. A
specific project boundary around each CDM project needs to be determined, within which
the project impacts in term of GHG emission reductions will be assessed. During the
project crediting period, all GHG emissions within that project boundary are monitored and
compared with baseline emissions. The baseline will include all direct emissions expected
from the generation of the same quantity of energy through the power plants of the
Pakistan electricity grid.The project emissions will include those caused by reservoir
emissions because of degradation of biomass and emissions caused by clearing of
vegetation, although these are expected to be small for the reasons given above.
8.7.
Page|134
8.7.1.
Electricity generated that would have otherwise been generated by the operation of
grid- connected power plant.
CEF
Coal
25.8
Lignite
27.6
CCGT-NG
15.3
Diesel
20.0
Source: IPCC
Table 25: Mass of CO2 Released per GWh of Energy Generated for Various Types of
Thermal Generation
Fossil Fuel Type Generation Technology
620
450
By applying the above emission factors to the most recent three years of data available for
the Pakistan grid, the grid Operating Margin (OM) can be calculated.This is the actual
emissions produced per GWh of electricity generated over the three years.The Build
Margin (BM) is then calculated, which is the average emissions produced per GWh of the
most recently installed plants only.It indicates how the emissions are increasing or
decreasing over time. The baseline of the project is calculated as a combination of these
two margins, known as the Combined Margin (CM).
The total CO2 emission reduction due to any project or activity can be calculated by the
formula:
ERproject =CMEEG
Page|135
Where:
8.8.
ERproject
CM
EEG
8.9.
Page|136
It was agreed to have a new round of negotiations until 2015 to create a new Protocol to
extend the Kyoto Protocol and limit CO2 emissions over the world starting in 2020. In other
words, by 2015, delegates will negotiate an agreed outcome with legal force so within
four years, there is supposed to be something like a treaty covering developed and
developing countries that limits carbon emissions. This treaty or treaty-like document is
supposed to take effect in 2020. For the first time, officials of the nations that are the
biggest carbon emitters (China, the United States and India) have agreed to negotiate
legally binding restrictions since all 191 nations have agreed to be bound by the same rule
(The Kyoto Protocol covers only 40 nations).
What was at stake in Durban was the legal basis of the CDM. Technically without the KP
there is no legal basis. A kind of substitute legal basis was provided by some of the Annex
1 countries such as the EU states who have their own regional emissions reductions
targets agreed under the auspices of the EU. Before Durban began, it was believed that
even if the KP was not extended, countries would have found a way to continue with the
system. The CDM is after all one of the few successful mitigation programmes that is
international in nature and involves both developed and developing countries. Developed
countries can transfer their emissions reductions and developing countries can get higher
investments in clean energy. A notable achievement of the CDM is transfer of technology
to developing countries. To date, 44% of approved projects have used new technology.
According to many NGOs that is not good enough and it should have been more like 70 or
80%, but I think that even 44% is a significant number.
Other benefits for developing countries include increased energy production, jobs and
economic activity. The CDM has acquired its own viability because different countries
such as Australia and China, and states in the US such as California are thinking of
introducing their own carbon trading systems. The CDM Executive Board has made
impressive progress in streamlining and simplifying the modalities and procedures of the
CDM initially agreed upon in Marrakesh in 2001.
Before the Durban meeting, the carbon market had shown considerable strain because of
the uncertainty about the future of the KP and there was a noticeable reduction in the
number of projects and the price of the CERs, which had once gone up to 13 Euros and
then came down to less than 5 Euros. The price has still not picked up. But now at least
there is no uncertainty about the future of the CDM.
There are as of today 3,800 registered projects located in 72 countries and in addition
3,600 projects are in the pipeline, undergoing various stages of verification and validation
by the CDM secretariat located in Bonn.
In 2010 the transactions involving carbon trading emissions amounted to 20 billion US
dollars. The main thing about the CDM is that it is meant to help the Annex 1 countries (a
total of 36 countries) to buy credits in order to meet their KP commitments in case they are
unable to reduce their emissions through efforts at home. They can buy credits generated
by projects in non-Annex 1 countries.
Page|137
The CDMs future in South Asia is assured. It was a very uneven situation in the past as
India was number two globally in hosting CDM projects and other countries in the region
were absent. But in the last three years, the other Asian countries are picking up.
Pakistan, which four years ago had only one CDM project at the Pak Arab Fertilizer plant,
now has 9 or 10 registered projects, which is a significant jump. Bangladesh also has a
couple now, as does Sri Lanka. South Asias share has increased and other Asian
countries are also gearing up.
8.10.
Anticipated Revenue
In view of the above discussion, it is not possible to estimate the anticipated revenue until
any firm mechanism replacing Kyoto Protocol is agreed.
8.11.
Conclusions
The potential benefit to the project of carbon credits is currently difficult to estimate and
our estimate ranges from zero to around USD 60 million. Whilst this additional income
would be welcome it is unlikely to make or break the project.
Until the post Kyoto international agreements are in place it is very difficult to know how
hydro projects such as Kaigah will be treated. Furthermore, justifying the additionality of
Kaigah in accordance with the CDM rules would be very difficult. We therefore suggest
that at the present time, the carbon benefits are not included in the project economic and
financial analysis.
Page|138
9.
9.1.
General
Like most other development projects, the Kaigah Hydropower Project will also affect the
human population due to the involuntary displacement from their native place to another
place. Both the Government of Pakistan and international donors (WB, ADB etc.) place
emphasis on involving parties who could be affected by any development project for
determining the social and environmental impacts associated with the project interventions
and for proposing mitigation measures for identified impacts. Accordingly, an attempt has
been made to consult government departments, the general public, line agencies, NGOs
and affected persons in the project area to obtain their views. This chapter describes the
mechanism adopted and activities undertaken for their involvement in the process and
information collected and conclusions drawn during the public consultation process.
Consultation with affected people and other stakeholders has become standard practice in
environmental assessment of development projects. The concept of public consultation is
that the project proponent should share relevant information about the project intervention
and its potential environmental impacts with all stakeholders. Consultation is a two-way
process by which the knowledge and views of affected persons, NGOs, the private sector
and other interested parties is taken into account in decision making. Nevertheless, it is
becoming increasingly clear that the knowledge of affected communities and local NGOs
can contribute to the quality of environmental assessments, as well as providing a better
understanding of the social impacts. Information dissemination during public consultation
by the project proponent or his representative is fundamental to meaningful consultation.
9.2.
9.3.
9.4.
9.4.1.
9.4.2.
To inform about the objectives and salient features of the project especially those
features which would affect the area.
To obtain ideas for any possible improvement in project layout and design
To provide an opportunity to the people to ask any questions about the project
To enquire about any other schemes or plans of other departments in the area.
Page|140
9.4.3.
9.4.4.
9.4.5.
Women Survey
A women survey (as a focussed survey) was also conducted in the project area. 31
households were also selected for this survey and one woman (the eldest or most well
informed) from each household was selected for interview using a pre-designed
questionnaire (Annexure-C3) through a female enumerator. The results of the survey are
provided in Table 26.
9.5.
Visits to Government
offices, line agencies
and NGOs
Summary of Feedback
Scoping sessions in
affected villages
Page|143
10.
10.1.
Introduction
This chapter discusses the broad framework for land acquisition, resettlement issues and
compensation procedure required for the project. At this stage most estimates are at a
preliminary level according to the requirements of feasibility study, which will be refined
and updated at design stage. A separate document covering the Resettlement Action Plan
will be prepared for dealing with the subject of land acquisition for project needs and
issues related with resettlement and compensation to affected persons.
10.2.
Project Affectees
Any person department or organization (private or public), whose land, asset, or source of
income is likely to be affected by the interventions and operations of the project, is
considered to be a Project Affectee. In the Kaigah Hydropower Project, the Project
Affectees include mainly the owners or occupants of the following type of land and
structures built thereon:
Owners and all residents of 112 households belonging to Karrang village and 18
household of Dong village
Owners of infrastructure, properties, agricultural land in Birti village below the reservoir
level at El 1500 masl
Land near the dam and powerhouse sites (Thauti) required for construction of
residential colonies, offices and other auxiliary services
Land falling within the reservoir area (the whole area to be submerged at maximum
reservoir level of El 1500 masl).
Land to be used as access routes to reach the construction sites and work places
Land required for storage of construction material (aggregate, sand, cement etc.)
Land required for workers camps, parking of vehicles and other machinery.
Comprehensive information about the number of Project Affectees and the extent of their
losses will be identified at the design stage and an exact inventory of assets to be lost will
be prepared and their value at market price will be determined.
10.3.
guidelines, the borrower should prepare a resettlement plan that covers the rights of the
PAP, especially those below the poverty line, the landless, the elderly, women and
children, indigenous peoples, ethnic minorities, or other displaced persons who may not
be protected through national land compensation legislation.
10.4.
Land Acquisition
10.5.
Page|145
10.6.
In view of the factors mentioned above, the Ministry of Environment has proposed an
amendment to the Land Acquisition Act, in the form of a National Resettlement
Policy and a Resettlement Ordinance. These instruments have been drafted to broaden
provisions of the Land Acquisition Act and its current practices, so as to widen the scope
of eligibility for compensation, and reduce its present weaknesses (e.g. definitions of
malpractices, cut-off dates, political influence, etc.). Both these documents are awaiting
the approval of the government.
10.7.
Page|147
Page|148
maximum benefits. They will be provided with all possible assistance for acquiring
skills, and will be given preference in employment in project related jobs.
i) Indigenous Groups
No indigenous people have been identified in the project area, and hence preparation
of an Indigenous Peoples Plan is not required.
Those who do not have formal right to land but have a claim to such land or assets
Those who do not have any recognisable legal right to land they are occupying.
Persons under (a) and (b) are provided compensation for the land they lose, and other
assistance in accordance as prescribed and agreed. Persons under (c) are provided
resettlement assistance in lieu of compensation for land they are occupying, if they occupy
the project prior to a cut-off date established by the borrower and acceptable to the Bank.
Persons who encroach on the area after the cut-off date are not entitled to any
compensation or assistance. The cut-off date normally is the date when the survey or
census of the affected population was undertaken, and when they were informed of the
project. All persons under (a), (b) and (c) categories are to be provided with compensation
for loss of assets other than land.
10.8.
Cut-off Date
According to the World Bank, a compensation policy requires the cut-off date for a project
to be fixed and announced. For the Kaigah Hydropower Project, this date may be taken as
sufficient before start of actual physical works in the project area. According to the WB,
people who settle in the affected areas after this cut-off date should not be eligible for
compensation.
Page|149
11.
11.1.
Introduction
The management of environment impacts during construction and operation phases, the
undertaking of the necessary mitigation measures (Chapter 6) and the monitoring of the
environmental management of the project (Chapter 7) carries a cost implication.The major
project cost implication for the Kaigah Hydropower Project is during construction with
lower costs in the post-construction phase.
Some costs will be additional expenditure (e.g. compensation costs to be paid to affected
persons). On the other hand, some of the mitigation measures do not imply any additional
expenditure (e.g. safety precautions). Some of the investment or cost will be required from
the initial, or design stage, but will cover later stages of the project as well. Some costs
will be concentrated during the construction period, while some will overlap into operation
of the project.These tasks have been identified in the preceding chapters. It is worth
mentioning here that most of the costs are tentative for feasibility level as more definitive
information will be collected during detailed design stage of the project.
The total environmental and social management cost of the project is estimated as PKR
1936 M (USD 15.07 M) shown in below.
The most significant component of environmental and social cost is the cost of acquisition
of the land and house compensation.
The other important component of environmental cost is the cost of damage to
infrastructure and to trees.
Page|150
Page|151
12.
12.1.
General
This chapter presents the main findings and conclusions drawn from the
Environmental Impact Assessment study of the Kaigah Hydropower Project together with
recommendations.
12.2.
Findings
Both positive and negative impacts are always associated with any development project.
The significant project impacts identified are presented under the following headings:
Socio-economic impacts.
Four complete village with a population of 900 persons will require resettlement
Approximately 327.4 Acre of land will need to be acquired permanently for various
uses by the project such as construction of colonies, offices, auxiliary services,
disposal of excavated material, area to be submerged in reservoir and area required
for realignment and construction of Kandiah valley road.
The potential benefit to the project of carbon credits under CDM is currently difficult to
estimate and estimate ranges from zero to around USD 60 million per year. Until the
post Kyoto international agreements are in place after 2012 it is very difficult to know
how projects such as Kaigah HPP will be treated under CDM
A significant deterioration in air quality (air and noise) is envisaged due to the
movement of large numbers of vehicles and movement of other machinery in the
project area especially during the construction phase.
The aquatic life (fish) in the 23 km length of the river from the dam to the confluence of
the Kandiah River and Dasu reservoir will be adversely affected due to reduction in
river discharge
No wildlife sanctuary, National Park, Game Reserve, Protected Area is located in the
project area or near to project area
12.3.
The most significant economic impact of the project is the benefit expected from
generation of power. The designed capacity of the project is over 500 MW
The potential benefit to the project of carbon credits under CDM is currently difficult to
estimate.
There are no archaeological or historic sites or monuments in the area which could be
affected by project activities
No indigenous or vulnerable groups of people were identified in the project area which
could be affected by the project
Construction operations could affect traffic, pedestrians, and school children on some
routes, during some specific periods of peak activities.
12.4.
Recommendations
Establishment of committees and unit: The constitution of various committees and unit
(as proposed in this report) such as the PEMC, PESMU and PGRC must be functional
before the start of the construction phase of the project to ensure delivery of their
responsibilities
Preparation of RAP: The project involves resettlement of four villages and population
of about 900 persons) and assessment of damages for varied infrastructure and trees.
Therefore, preparation of a comprehensive RAP is necessary before construction of
the project starts
Page|153
Approval of the Project EIA from EPA: The proponent will need to follow the
procedure for obtaining approval of the project EIA from the EPA before the start of the
project.
General Emergency Plan: To deal with all type of emergencies during construction
12.5.
Conclusions
The study of the environmental and social setting of the Kaigah Hydropower Project,
and the implications of the proposed interventions, i.e. construction of a dam,
excavation of tunnels, creation of the reservoir, and construction of underground
powerhouse and so on, do not indicate any significant negative impact of such nature
or magnitude that would suggest the project is environmentally unfriendly.
The study has identified some potential impacts, which are not of serious nature and
can be ameliorated or mitigated within normally acceptable levels through practicable
control and management measures.
Page|154
The overall findings of the EIA studies show that the Kaigah Hydropower Project is
environmentally and socially viable subject to the development and implementation of
a full Environmental Management Plan.
Page|155
13.
REFERENCES
IFC 2002. Handbook for Preparing a Resettlement Action Plan, Washington DC.
Pakistan Environmental
Assessment Procedures
Rafique, M. 2000. Fish Diversity and Distribution in Indus River and its Drainage
System., Pakistan. Journal of Zoology, 32(4): p 321-332.
PEPA. 2000. Review of IEE and EIA Regulations, in: Ameer, B. U, Manual of
Environmental Laws in Pakistan, Khyber Law Publishers, Lahore, 2005, p 64-84
PEPA. 1998. Statutory Notifications (S.R.O.) about delegation of power and function to
the provincial EPA
World Bank. 2007. Operational Policy (OP 4.12) Involuntarily Resettlement. Update.
Protection
Agency.
1997.
Guidelines
Pakistan
for
Financial
Environmental
Page|156
ANNEXURES
Annexure- A1
Location Map
Annexure- A2
Project Layout
Annexure- B
Photo-log
Annexure- C1
Sample Questionnaire
Annexure- C2
List of Respondents
Annexure- C3
Annexure- D1
NEQS
Annexure- D2
Annexure- D3
Annexure- E
Annexure- F1
Annexure- F2
Annexure- F3
Annexure- F4
Annexure- F5
Annexure- F6
Page|157
ANNEXURE A1
PROJECT LOCATION MAP
Page|158
ANNEXURE A2
PROJECT LAYOUT
Page|159
1:200
1:150
1:100
0
10
1:333.3
1:250
0
10
10
15
10
15
1:750
1:500
0
20
10
15
20
25
30
10
15
20
25
30
35
40
10
20
30
40
50
60
E= 3212 000
E= 3208 000
E= 3204 000
E= 3200 000
E= 3192 000
E= 3196 000
A
Intake 3
Canal L= 2290 m
Intake 2
N= 1258 000
Powerhouse
DONG
Adit 2
Surge tank
TI
THO
AH
NALL
KARRANG
Powerhouse
access tunnel
REST
HOUSE
Road
Dam
TAIL
RAC
E TU
NNE
HE
BAR
R
NAL AGO
LA
BIRTI
CE
RA
D
A
L
NE
N
TU
KANDIA
KAN
DI
H RIVE
AH
R
IVE
N= 1254 000
Adit 1
IVER
KANDIAH R
IVER
KANDIAH R
Road
N= 1250 000
Absc. 21554,00
Absc. 17200,00
Absc. 16894,00
Absc. 0,00
3500
3400
3300
3200
3100
3000
2900
2800
2700
2600
2500
2400
2300
2200
2100
2000
1900
1800
1700
1600
1500
1400
1300
1200
1100
1000
900
800
700
600
Absc. 10435,00
ELEVATION
(m.a.s.l)
PLAN
Surge tank
Penstock tunnel
L= 179 m
P= -1,00%
Intake
Headrace tunnel
L= 17200 m
1000
2000
3000
5000
4000
6000
7000
8000
9000
Powerhouse
10000
11000
12000
Tailrace tunnel
L= 4102 m
P= -0,20%
14000
15000
16000
17000
18000
19000
20000
21000
22000
DISTANCE (m)
KAIGAH
HYDROPOWER
CHARACTERISTICS
Design discharge (m3/s)
125.0
90.0
Tunnel
525
Canal
Design capacity(MW)
NOTE:
CONVENTIONS:
River
548.0
PROFILE
F
LAYOUT
David Angee M.
1:33333,33
Nombre A. Apellido A.
APPROVED :
No.
DATE
Gabriel J. Cano
DESCRIPTION
Associated Technologies
VERSIONS
JANUARY 2013
DRAWING No.
DRAFTSMAN :
CHECKED :
DATE:
SCALE:
VERIFIED :
DESIGNED :
LAYOUT
FILE:
Left Bank Layout.dwg
CODE:
Left Bank Layout
ANNEXURE B
PHOTO LOG
Page|160
KaigahHydropowerProjectEIAStudyReport
KandiahBridgeatIndusKandiah
confluence
AlongtheRiverinKandiahvalley
1|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
Agriculturalpraticeonmanmadeterrace
Soilsamplinginmaizefield
2|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
RedCrescentandRedCrossfundedrehabilitation
programme
KandiahvalleyrehabilitationprogrammeofRedCrossandRedCrescent
3|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
PlantationnearPowerhousesite
DamagedroadtobebuiltalongKandiahRiver
4|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
ThautiNallahconfluencewithKandiahRivernear
Powerhousesite
MicroHydropowerPlantinoperationatThautivillage
5|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
PolicepostatThautivillagenearPowerhousesite
BasicHealthUnit(BHU)atThautinearPowerhousesite
6|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
Karrangvillagetobesubmergedinreservoir
PlantationnearDamsite
7|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
TribulusTerristrisLinDamarea
ViewfromBirtitoKarrangvillageatReservoirLevelof1500masl
8|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
BridgeoverKandiahRivertoreachThautivillage
CablecrossingoverKandiahRivertoreachThautivillage
9|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
BridgeoverChapparNallah(TributaryofKandiahRiver)
BridgeoverJoshoiNallah(TributaryofKandiahRiver)
10|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
BridgecrossingnearThauti
FishofKandiahRiver
11|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
Localmarketunderconstruction
ShopsinThautimarket
12|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
DiscussionwithDamarearesidentsinProjectarea
DiscussionwithPowerhousearearesidentsinProjectarea
13|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
CollectionofSocioEconomicData
CollectionofSocioEconomicDatainDamarea
14|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
ConsultationwithlocaltribalheadinProjectarea
MeetingwithSSPKohistan
15|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
ConsultationwithRevenueDepartment
ConsultationwithForestDepartment
16|P a g e
PHOTOLOG
KaigahHydropowerProjectEIAStudyReport
MeetingwithRedCross
MaizecultivationinProjectarea(Birti)
17|P a g e
PHOTOLOG
ANNEXURE C1
SAMPLE QUESTIONNAIRE
Page|161
Annexure C1
Page 1 of 8
Kaigah Hydropower Project Feasibility Report
Form No - 01
__________________________
2. Union Council
__________________________
3. Valley / Nullah
__________________________
4. Village / Town
__________________________
Q.2
Q.3
Sex:
Q.4
Q.5
Q.6
Q.7
Q.8
__________________________________________
____________________________________
1. Male
2. Female
___________________Years
1. Single
2. Married
1. Illiterate
2. Primary
3. Middle
4. Secondary
5. Higher Secondary
6. Graduate
7. Professional Graduate
8. Post Graduate
9. Deeni Uloom
2. Gujars
3. Udin Khail
4. Narang Khail
5. Kashmiri
6. Mula Khail
7. Sheen
8. Shukar Khail
9. Swati
10.Shadi Khail
11.Sirkhan Khail
12.Durab Khail
13.Lohar
14.Pathan
15.Sheda Khail
16.Other
b. Milk Seller
c. Cattle Farming
d. Poultry
e. Trade
f. Wood Cutter
g. General Labor
h. Service
i. Unemployed
j. Gold Collection
k. Fishing
l. Other _______________________
Annexure C1
Page 2 of 8
Kaigah Hydropower Project Feasibility Report
Q.9
c. Hindko
d. Kalochi
e. Kashmiri
f. Kohistani
g. Pushtoo
h. Shina
i. Urdu
j. Other____________
Socio-economic Profile
Q.10
Sex
Less than 5
years
5 to 18
years
18 to 45
years
46 to 60
years
61 years and
above.
Total
Male
Female
Total
Q.11
Do your married family members live with you in the same house?
2. No (Nuclear Family)
2. No (Endogamy)
Q.13
Number of Child Births in the family during Last ONE Year ________________________
Q.14
Number of Deaths in the family during the last ONE year. _________________________
1. Cause of Death -------------------------------- 2. Cause of Death --------------------------------3. Cause of Death --------------------------------- 4. Cause of Death ---------------------------------
Q.15
Q.16
How many members of your family have any of the following educational qualifications?
Sex
Education Level
Illiterate
Male (18+)
Female (18+)
Total
Primary
Middle/
Matric
Intermediate/
Graduation
Professional/Post
Graduation
Deeni
Uloom
Annexure C1
Page 3 of 8
Kaigah Hydropower Project Feasibility Report
Q.17 What type of main vocational skills do your family members have?
Sex
Male
Female
Q.18
What type of (Additional) vocational skills would you like to impart to your family
members?
_______________________________________________________________________
_______________________________________________________________________
_______________________________________________________________________
Q.19
How many members of your family have the following working statuses?
Sr.No
Q.20
Employment Status
(a)
Govt. Employee
(b)
Private Employee
(c)
Self Employed
(d)
Unemployed
(e)
Household
Family Members
Adults (18+)
Male
Female
Total
c. Trade/Business
e. General labor
g. Service
h. Gold Collection
i. Fishing
j. Fruit Trees
Q.22
Q.23
Q.24
Annexure C1
Page 4 of 8
Kaigah Hydropower Project Feasibility Report
Q.25
a. Cash
Q.26
b. Credit / Deferred
c. In kind
2. Rented
5. Leased
2. Pacca
3. Semi-pacca
Q.30
Q.31
Q.32
Q.33
_________________Rs.
2. No
2. Pacca
3. Semi-pacca
Q.35
______________ (Years)
Q.34
_____________ (Number)
_____________ (Number)
2. No
2. Pacca
3. Semi-pacca
Q.36
Q.37
a. Electricity
b. Water Supply
d. Telephone
f. Sewerage
______________Rs.
c. Gas
Annexure C1
Page 5 of 8
Kaigah Hydropower Project Feasibility Report
Q.38
Q.39
What type of fuel do you use for illuminating, heating and cooking etc.?
1. Illumination
a. Electricity
b. Kerosene
c. LPG
d. Firewood
2. Heating
a. Electricity
b. Kerosene
c. LPG
d. Firewood
3. Cooking
a. Electricity
b. Kerosene
c. LPG
d. Firewood
Q.41
a. TV
b. Motor Vehicle
c. V.C.R./ V.C.D.
d. Cassette Player/Radio
e. Fridge/Freezer
f. Air Conditioner/Cooler
g. Motor Cycle
h. Bicycle
i. Sewing Machine
j. Washing Machine
k. Geezer
l. Power Generator
m. Iron
n. Fan
o. Furniture
p. Other ________________
q. Other____________
What are the sources of water for your domestic and agricultural use?
Sr.No
Nature of Use
Sources of Water
Spring Nullah Channel
(a)
Drinking
(b)
(c)
Agricultural Irrigation
(d)
Q.42
Sr.No
What is the size of your cultivated land with its approximate price?
Agricultural Land
Cultivated Area
Uncultivated Area
Cultivable Waste
Area of land
(in kanal)
(in acre)
Approximate
Price (Rs.)
Total
Q.43
b. Lessee
c. Owner-cum-tenant
d. Tenant
e. Lessor
f. Share cropper
Annexure C1
Page 6 of 8
Kaigah Hydropower Project Feasibility Report
Q.44
Q.45
Q.46
c. Tractor
e. Thresher
f. Other____________
b. Maize
c. Sorgrum
e. Fruits
f. Fodder
Please provide information about the inputs for growing various crops in your agricultural
land.
Sr.
No
Items
A
B
Seeds
Fertilizers
C
D
Pesticides
Manure
Q.47
d. Vegetable
Purchasing status
Yes
1
1
1
1
No
2
2
2
2
Animals
Buffalo Cow
Goat/
Sheep
Poultry
Donkey/
mule
Ox Horse
Other
(specify)
Number
Q.48
Q.49
2. No
If yes, estimated cost for purchasing feed / fodder for your animals:
Sr. No.
Dry fodder
Green fodder
Animal minders
Medicines
Total
Q.50
Estimate
Total cost
(Rs.)
1. Yes
2. No
Total
Annexure C1
Page 7 of 8
Kaigah Hydropower Project Feasibility Report
Q.51
2. Plain Paper
3. Personal Evidence
4. Other (specify)_________________________________________________________
Q.52
Q.53
amount Borrowed______________Rs.
II
III
Source:
IV
Q.54
2. No
1. Bank
2. Friend
3. Relative
4. Private organization
5. Other (specify)________________
Do you depend on localities across left and right banks of the River Indus for the
fulfillment of your various needs?
1. Yes
Q.55
2. No
If yes, what types of your needs are related with the localities located across the river?
Please provide the details as below:
a. Family Relations
c. Access to KKH
In your opinion, how will you be affected by the construction of Kaigah Dam?
_______________________________________________________________________
_______________________________________________________________________
Q.57
If your agricultural land / shop are to be acquired for Kaigah Hydropower Project, do you
have any other source of income?
1. Yes
2. No
Q.58
Q.59
Q.60
_________________________________________
2. No
If yes;
a. Name of locality_______________________________________________________
b. Distance from present residence _______________________________________Km
Annexure C1
Page 8 of 8
Kaigah Hydropower Project Feasibility Report
Q.61
Q.62
2.
Dasu
4. Dont know
Cash
Alternative Land
Building
Other (specify)
ANNEXURE C2
LIST OF RESPONDENTS
Page|162
EIASTUDYREPORT
Sr. #
LISTOFRESPONDENTS
548MWKAIGAHHYDROPOWERPROJECT
Name
Father's Name
Village
Sex
Age
Status
Qualification
Caste
Deeli Malik
Birti
Male
51 Years
Married Middle
Shahbaz Khel
Sikandar
Syed Jalal
Birti
Male
46 years
Married Primary
Shahbaz Khel
Rehmat Wali
Malik Amin
Birti
Male
35 years
Married Matric
Shahbaz Khel
Arastoo Mullah
Kaskar
Birti
Male
70 Years
Jandal Kheil
Shamran
Birti
Male
58 Years
Married Middle
Shahbaz Khel
Haider Ali
Deeli Malik
Birti
Male
22 Years
Married Primary
Shahbaz Khel
Akram Shah
Bahdur Khan
Birti
Male
47 Years
Married Illiterate
Shahbaz Khel
Deeli Malik
Birti
Male
20 Years
Shahbaz Khel
Fazeel-e-Haq
Deeli Malik
Birti
Male
35 Years
Married Primary
Shahbaz Khel
10
Nader Khan
Deeli Khan
Birti
Male
47 Years
Married Illiterate
Shahbaz Khel
11
Asim Shah
Birti
Male
28 Years
Married Primary
Shahbaz Khel
12
Rajander
Akbar
Birti
Male
60 Years
Married Illiterate
Sui-Khel
13
Rehmat ullah
Birti
Male
30 Years
Married Primary
Shahbaz Khel
14
Nazeem
Shehzad Mir
Birti
Male
45 Years
Gujar
15
Anwar Shah
Birti
Male
20 Years
Shahbaz Khel
16
Adil Shah
Birti
Male
22 Years
Married Illiterate
Higher
Married Secondary
Higher
Married Secondary
17
Dadi Malik
Birti
Male
25 Years
Married Primary
Shahbaz Khel
18
Mr. Fazil
Dena
Birti
Male
60 Years
Married Illiterate
Gujar
19
Birti
Male
25 Years
Married Primary
Shahbaz Khel
20
Dadi Malik
Birti
Male
60 Years
Married Illiterate
Shahbaz Khel
21
Mr. Satbar
Noor Baz
Birti
Male
50 Years
Married Illiterate
Taliq Khail
22
Daide Malak
Birti
Male
50 Years
Married Primary
Shahbaz Khel
23
Bahudur Khan
Birti
Male
25 Years
Married Illiterate
Shahbaz Khel
24
Mr. Malang
Arastoo Mullah
Birti
Male
32 Years
Jandal Kheil
25
Saeed Azeem
Lo Malik
Birti
Male
50 Years
Shabaz Kheil
26
Sardar Ali
Shah Alam
Birti
Male
30 Years
Married Matric
(2)
Married Matric
Page1of4
Shahbaz Khel
Shabaz Kheil
Occupation
Languages
Agriculture Kohistani,
Farming
Pashtu, Urdu
Kohistani,
Labour
Pashtu
Kohistani,
Shop keeper Pashtu, Urdu
Agriculture/ Kohistani,
Labour
Pashtu
Agriculture/ Kohistani,
Labour
Pashtu
Kohistani,
Labour
Pashtu
Agriculture Kohistani,
Farming
Pashtu
Agriculture Kohistani,
Farming
Pashtu
Kohistani,
Labour
Pashtu, Urdu
Kohistani,
Labour
Pashtu
Kohistani,
Labour
Pashtu, Urdu
Kohistani,
Labour
Pashtu, Urdu
Kohistani,
Labour
Pashtu
Hindko,
Milk Seller
Kohistani
Kohistani,
Student
Pashtu, Urdu
Kohistani,
Student
Pashtu, Urdu
Kohistani,
Labour
Pashtu
Gujri, Kohistani,
Milk Seller
Pashtu
Kohistani,
Labour
Pashtu
Kohistani,
Milk Seller
Pashtu
Kohistani,
Labour
Pashtu
Kohistani,
Labour
Pashtu
Kohistani,
Labour
Pashtu
Agriculture
Kohistani,
Farming
Pashtu
Kohistani,
Labour
Pashtu
Agriculture
Kohistani,
Farming
Pashtu, Urdu
Family
Members
Total Members
M- 09 F-04
15 Nos.
M- 03 F-04
09 Nos.
M- 03 F-08
13 Nos.
M- 10 F-03
15 Nos.
M- 03 F-11
16 Nos.
M- 01 F-01
04 Nos.
M- 03 F-06
11 Nos.
M- 01 F-01
04 Nos.
M- 03 F-05
10 Nos.
M- 06 F-04
12 Nos.
M- 01 F-01
04 Nos.
M- 03 F-01
06 Nos.
M- 02 F-04
08 Nos.
M- 01 F-03
06 Nos.
M- 02 F-01
05 Nos.
M- 02 F-01
05 Nos.
M- 04 F-03
09 Nos.
M- 05 F-04
11 Nos.
M- 02 F-02
06 Nos.
M- 08 F-02
12 Nos.
M- 10 F-
12 Nos.
M- 04 F-08
14 Nos.
M- 03 F-01
06 Nos.
M- 06 F-05
13 Nos.
M-0
F-1
03 Nos.
M-4
F-1
07 Nos.
EIASTUDYREPORT
Sr. #
LISTOFRESPONDENTS
548MWKAIGAHHYDROPOWERPROJECT
Name
Father's Name
Village
Sex
Age
Status
Qualification
27
Zardardan
Shah Alam
Birti
Male
30 Years
Married Primary
28
Shahid Data
Birti
Male
30 Years
29
Mahkam
Birti
Male
100 Years
Married Primary
(2)
Married Illiterate
30
Wakeel Khan
Ronaq Khan
Birti
Male
35 Years
Married Matric
31
Ishaq
Wakeel Khan
Birti
Male
20 Years
Married Illiterate
32
Yaqoob Khan
Wakeel Khan
Birti
Male
20 Years
Married Primary
33
Badshah Malik
Karrang
Male
60 Years
34
Badshah Malik
Karrang
Male
50 Years
Married Illiterate
Higher
Married Secondary
35
Ghazan Malik
Karrang
Male
80 Years
Married Illiterate
36
Kasgar Malik
Karrang
Male
80 Years
37
Malik Sulman
Karrang
Male
70 Years
Married Illiterate
38
Raheem Shah
Muhammad Rasool
Karrang
Male
69 Years
Married Illiterate
39
Saiful Malook
Abdullah
Karrang
Male
50 Years
Married Illiterate
40
Mobashir Khan
Samandar
Karrang
Male
24 Years
Married Illiterate
41
Akbar Khan
Samandar
Karrang
Male
29 Years
Married Qari
42
Lal Khan
Aurangzaib Malik
Karrang
Male
60 Years
Married Illiterate
43
Mubarak Shah
Aurangzaib Malik
Karrang
Male
50 Years
Married Primary
44
Abdul Shakoor
Bindi Khan
Karrang
Male
60 Years
Married Primary
45
Akhtar Munir
Abdul Shakoor
Karrang
Male
30 Years
Married Primary
46
Bahadur Shah
Rozi Khan
Karrang
Male
70 Years
Married Illiterate
47
Badar Munir
Abdul Shakoor
Karrang
Male
25 Years
Married Illiterate
48
Fadar Munir
Abdul Shakoor
Karrang
Male
25 Years
Married Primary
49
Abrahim Khan
Bahadur Shah
Karrang
Male
20 Years
Married Primary
50
Aurangzaib
Bahadur Shah
Karrang
Male
30 Years
Married Qari
51
Umar Khan
Ghazar Khan
Karrang
Male
50 Years
52
Ghazar Khan
Karrang
Male
70 Years
Married Primary
Page2of4
Caste
Occupation
Languages
Agriculture
Kohistani,
Shabaz Kheil Farming
Pashtu, Urdu
Kohistani,
Shabaz Kheil Driver
Pashtu, Urdu
Kohistani,
Shabaz Kheil Labour
Pashtu
Kohistani,
Shabaz Kheil Trade
Pashtu, Urdu
Agriculture
Kohistani,
Pashtu
Shabaz Kheil Farming
Kohistani,
Shabaz Kheil Labour
Pashtoo, Urdu
Kohistani,
Trade
Pashtoo, Urdu
Mula Khail
English,
Teacher
Pushtoo, Urdu
Mula Khail
Agriculture
English,
Farming
Pushtoo, Urdu
Mula Khail
Teacher
Kohistani,
(religious)
Pashtu
Sui Khel
Agriculture
Kohistani,
Farming
Pashtoo, Urdu
Mula Khail
Agriculture
Kohistani,
Farming
Pashtoo, Urdu
Mula Khail
Kohistani,
Trade
Pashtoo, Urdu
Mula Khail
Kohistani,
Labour
Pashtu
Mula Khail
Kohistani,
Labour
Pashtoo, Urdu
Mula Khail
Agriculture
Kohistani,
Farming
Pashtoo, Urdu
Mula Khail
Kohistani,
Labour
Pashtoo, Urdu
Mula Khail
Kohistani,
Labour
Pashtoo, Urdu
Mula Khail
Kohistani,
Labour
Pashtoo, Urdu
Mula Khail
Kohistani,
Labour
Pashtu
Mula Khail
Kohistani,
Labour
Pashtu
Mula Khail
Kohistani,
Labour
Pashtoo, Urdu
Mula Khail
Kohistani,
Driver
Pashtoo, Urdu
Mula Khail
Kohistani,
Pashtoo, Urdu
Mula Khail
Kohistani,
Labour
Pashtoo, Urdu
Mula Khail
Kohistani,
Contractor
Pashtoo, Urdu
Mula Khail
Family
Members
Total Members
M-1
F-2
05 Nos.
M-0
F-1
03 Nos.
M-2
F-1
05 Nos.
M-5
F-2
09 Nos.
M-1
F-1
04 Nos.
M-2
F-1
05 Nos.
M- 06 F-02
12 Nos.
M- 03 F-02
09 Nos.
M- 04 F-02
09 Nos.
M- 06 F-01
09 Nos.
M- 02 F-03
07 Nos.
M- 05 F-03
10 Nos.
M- 04 F-04
10 Nos.
M-1
F-1
04 Nos.
M-1
F-1
04 Nos.
M-3
F-1
06 Nos.
M-5
F-1
08 Nos.
M-7
F-5
14 Nos.
M-8
F-2
12 Nos.
M-10 F-1
13 Nos.
M-2
F-1
05 Nos.
M-4
F-1
07 Nos.
M-3
F-3
08 Nos.
M-0
F-1
03 Nos.
M-3
F-2
07 Nos.
M-4
F-2
08 Nos.
EIASTUDYREPORT
Sr. #
LISTOFRESPONDENTS
548MWKAIGAHHYDROPOWERPROJECT
Name
Father's Name
Village
Sex
Age
Status
Qualification
Caste
Occupation
53
Mazdob Khan
Ghazar Khan
Karrang
Male
30 Years
Married Illiterate
Mula Khail
54
Azam Khan
Ghazar Khan
Karrang
Male
35 Years
Mula Khail
Labour
55
Athar Khan
Ghazar Khan
Karrang
Male
25 Years
Mula Khail
Labour
56
Shah Alam
Log Malik
Karrang
Male
50 Years
Married Primary
Mula Khail
Labour
57
Umar Hayat
Shamsir Gun
Karrang
Male
40 Years
Married Illiterate
Mula Khail
Labour
58
Jan Muhammad
Shamsir Gun
Karrang
Male
35 Years
Married Illiterate
Mula Khail
Labour
59
Jan Alam
Shamsir Gun
Karrang
Male
50 Years
Married Primary
Mula Khail
Birozgar
60
Mahar Alam
Shamsir Gun
Karrang
Male
60 Years
Married Primary
Mula Khail
Labour
61
Shar Alam
Shamsir Gun
Karrang
Male
50 Years
Married Illiterate
Mula Khail
Labour
62
Muhamad Saleem
Shamsir Gun
Karrang
Male
35 Years
Married Matric
Birozgar
63
Ghulab
Shah Ji
Thauti
Male
65 Years
Married Illiterate
64
Samandar Khan
Dilon
Thauti
Male
54 Years
65
Chapat
Thauti
Male
52 Years
Married Illiterate
66
Haji Biniameen
Haji Aftab
Thauti
Male
57 Years
Married Primary
67
Haji Kiftan
Malik Charyal
Thauti
Male
48 Years
Married Illiterate
Mula Khail
Shahdam
Kheil
Shahdam
Kheil
Shahdam
Kheil
Shahdam
Kheil
Shahdam
Kheil
68
Mashkara
Bari
Thauti
Male
55 Years
Lohar
69
Mollah Ayaz
Yaya
Thauti
Male
70 Years
Married Illiterate
(2)
Married Deeni Uloom
70
Hassan
Mollah Ayaz
Thauti
Male
45 Years
Married Illiterate
Lohar
71
Rustam
Fazal Raheem
Thauti
Male
40 Years
Married Matric
Lohar
72
Mr. Taj
Mashkara
Thauti
Male
38 Years
Married Illiterate
Lohar
73
Mr. Iqbal
Mollah Ayaz
Thauti
Male
35 Years
Married Illiterate
74
Muhammad Saifallah
Alam Zaib
Thauti
Male
30 Years
Married B.Sc
75
Abdul Latif
Haji Aftab
Thauti
Male
36 Years
Married BA
76
Shakar Zaib
Haji Aftab
Thauti
Male
40 Years
Married Matric
77
Alam Zaib
Haji Aftab
Thauti
Male
45 Years
Married Middle
Lohar
Shahdam
Kheil
Shahdam
Kheil
Shahdam
Kheil
Shahdam
Kheil
78
Rahmat Wali
Adam Khor
Thauti
Male
60 Years
Married Illiterate
Page3of4
Lohar
Labour
Labour
Agriculture
Farming
Agriculture
Farming
Agriculture
Farming
Agriculture
Farming
Agriculture
Farming
Agriculture
Farming
Birozgar
Agriculture
Farming
Labour
Birozgar
shopkepeer
Agriculture
Farming
Contractor
Agriculture
Goshah Khel Farming
Languages
Kohistani,
Pashtu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtu
Kohistani,
Pashtu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtu
Kohistani,
Pashtu
Kohistani,
Pashtu
Kohistani,
Pashtu
Kohistani,
Pashtu
Kohistani,
Pashtu
Kohistani,
Pashtu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtu
Family
Members
Total Members
M-2
F-3
07 Nos.
M-2
F-1
05 Nos.
M-2
F-1
05 Nos.
M-2
F-1
05 Nos.
M-2
F-1
05 Nos.
M-1
F-0
03 Nos.
M-2
F-0
04 Nos.
M-2
F-1
05 Nos.
M-2
F-1
05 Nos.
M-0
F-0
02 Nos.
M-8
F-4
14 Nos.
M-5
F-4
11 Nos.
M-08 F-01
11 Nos.
M-03 F-02
07 Nos.
M-04 F-04
10 Nos.
M-08 F-0
10 Nos.
M-05 F-4
11 Nos.
M-02 F-3
07 Nos.
M-02 F-2
06 Nos.
M-02 F-1
05 Nos.
M-02 F-1
05 Nos.
M-01 F-1
04 Nos.
M-01 F-1
04 Nos.
M-04 F-2
08 Nos.
M-04 F-4
10 Nos.
M-04 F-3
09 Nos.
EIASTUDYREPORT
Sr. #
LISTOFRESPONDENTS
548MWKAIGAHHYDROPOWERPROJECT
Name
Father's Name
Village
Sex
Age
Status
79
Rahmat Wali
Rehman
Thauti
Male
45 Years
Married Middle
80
Afridi
Yaya
Thauti
Male
55 Years
Married Primary
Occupation
Agriculture
Lohar
Farming
Agriculture
Goshah Khel Farming
81
Abdul Sabor
Abdul Samad
Thauti
Male
70 Years
Married Illiterate
Lohar
82
Abdul Wakeel
Afridi
Thauti
Male
40 Years
Married Middle
83
Abdul Malak
Abdul Shakoor
Thauti
Male
35 Years
84
Manoo
Khamari
Thauti
Male
65 Years
Married Matric
(2)
Married Illiterate
85
Ishaq
Abdul Shakoor
Thauti
Male
35 Years
Married Matric
86
Ihsan
Haji Jakha
Thauti
Male
23 Years
Married BSc
Page4of4
Qualification
Caste
Labour
Languages
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtu
Kohistani,
Pashtoo, Urdu
Kohistani,
Pashtoo, Urdu
Family
Members
Total Members
M-04 F-3
09 Nos.
M-05 F-4
11 Nos.
M-02 F-2
06 Nos.
M-02 F-1
05 Nos.
M-01 F-1
04 Nos.
M-03 F-3
08 Nos.
M-01 F-1
04 Nos.
M-01 F-0
03 Nos.
ANNEXURE C3
QUESTIONNAIRE FOR WOMEN SURVEY
Page|163
Annexure- C3
Women Survey
II
Questionnaire No._______________________
LOCATION
1.1
Village ___________________________
1.3
U.C. _____________________________
1.5
District ___________________________
BIOGRAPHICAL DATA
2.1
2.2
Name of Respondent
_______________________________________________________
Father /Husbands Name_______________________________________________________
2.3
2.6
Age__________________________
2.4 Cast/Tribe ____________________
Marital Status________________________________________________________________
1.
2.7
Literacy Status
2.8
2.9
2.10
2.11
2.12
2.13
2.14
Age
Sex
Years
Education
EPI Coverage
If yes,
1-
Yes _____________________
2. No. _________________
2-
Trained __________________
2. Un-Trained __________
Page 1 of 4
2.15
2.16
2.17
2.18
Annexure- C3
Women Survey
2 ____________________________________
3______________________________
4 ____________________________________
2 ____________________________________
3______________________________
4 ____________________________________
____________
2.19
2.20
2 Dispensary _____________________________
3 BHU___________________________
2.21
2.22
Are you interested to do any work other than house hold activities?
1 Yes________________________2 No___________________________________
2.23
III
____________________________________________________________________
2-
____________________________________________________________________
3.2
3.3
Page 2 of 4
3.4
Annexure- C3
Women Survey
____________________________________________________________________
2-
____________________________________________________________________
3-
____________________________________________________________________
3.5
3.6
3.7
3.8
3.9
2 Husband___________________________
IV
____________________________________________________________________
2-
____________________________________________________________________
3-
____________________________________________________________________
SKILL DEVELOPMENT
4.1
4.2
4.3
____________________________________________________________________
2-
____________________________________________________________________
Would you like to learn some additional skill under this Project?
1 Yes________________________2 No___________________________________
4.4
INCOME GENERATION
5.1
Page 3 of 4
5.2
5.3
Annexure- C3
Women Survey
____________________________________________________________________
2-
____________________________________________________________________
3-
____________________________________________________________________
5.4
VI
1-
Activity
_________________________________
2.
_________________________________
______________________________
3.
_________________________________
______________________________
PROJECT BENEFITS
6.1
Are you aware about the construction of Kaigah Hydro Power Project?
1 Yes________________________2 No___________________________________
6.2
Are you agreed with the construction of Kaigah Hydro Power Project?
1 Yes________________________2 No___________________________________
6.3
6.4
____________________________________________________________________
2-
____________________________________________________________________
What adverse impacts of projects do you anticipate with reference to women & children movement & safety?
12-
____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
2-
____________________________________________________________________
Name of Interviewer___________________________________________
Date: ______________________
Page 4 of 4
ANNEXURE D1
NEQS
Page|164
ANNEXURE D2
METEONORM DATA
Page|165
35.488
72.894
Location name
Latitude [N]
Longitude [E]
1673
III, 10
Altitude [m a.s.l.]
Climate region
Standard
Standard
Perez
Radiation model
Temperature model
20002009
19862005
Temperature period
Radiation period
Additional information
Uncertainty of yearly values: Gh = 10%, Bn = 19%, Ta = 2.3 C
Trend of Gh / decade: -5.4%
Variability of Gh / year: 5.2%
Radiation interpolation locations: Satellite data
Temperature interpolation locations: Srinagar (236 km)
H_Gh
H_Dh
H_Bn
Ta
[kWh/m2]
[kWh/m2]
[kWh/m2]
[C]
January
77
33
109
2.5
February
92
40
105
5.2
March
126
60
112
10.2
April
125
68
86
14.6
May
159
75
122
18.4
June
212
70
211
21.9
July
164
84
117
23.8
August
154
70
128
23.1
September
148
60
149
19.2
October
138
42
177
13.6
November
93
30
142
7.3
December
71
32
97
3.6
1559
662
1556
13.6
Month
Year
H_Gh:
H_Dh:
H_Bn:
Ta:
1/3
Monthly radiation
Monthly temperature
2/3
Daily temperature
Precipitation
Sunshine duration
3/3
ANNEXURE D3
WATER QUALITY ANALYSIS OF RIVER KANDIAH
Page|166
SR #
PARAMETER
VALUE
EPA STANDARDS
REMARKS
Temperature (0C)
6.9
No Standard
Value
Odour
Odour
Less
Taste
No Taste
pH
8.4
6.5-9.0 pH
Complies
DO (mg/l)
7.3
>5.0
Complies
Conductivity
(S/cm)
46.0
Turbidity (NTU)
9.2
15 NTU.
Hardness as
CaCO3 (mg/l)
59
BOD (mg/l)
2.7
10
COD (mg/l)
3.9
No Standard
Value
11
TDS (mg/l)
23.8
No Standard
Value
12
Chloride (mg/l)
4.8
1.0-35.0
No Standard
Value
Complies
No Standard
Value
No Standard
Value
Complies
13
Chlorine (mg/l)
ND
19
No Standard Limit
14
Sodium (mg/l)
2.60
Complies
15
Fluoride (mg/l)
Complies
16
Iodine (mg/l)
17
Sulphate (mg/l)
33
50-2700
0.91
44.2
No Standard
Value
No Standard
Limit
18
Sulphide (g/l)
72.5
200-40000
Complies
19
Nitrogen Ammonia
(mg/l)
6.1
6.12 - 6.67
Complies
20
Nitrate (mg/l)
0.80
Complies
21
Cyanide (mg/l)
ND
5.2 (Chronic)
22 (Acute)
Complies
22
23
Coliforms, Fecal
Organism/100 ml
22
200
Complies
24
Suspended Solids
(mg/l)
38
No Standard
Value
25
2.33
0.2 30*
Complies
26
1.92
0.01 3*
Complies
27
0.1 6*
Complies
15.1
0.06 120*
Complies
ND
0.01 - 3.5*
Complies
0.75
0.2 100*
Complies
28
29
30
Lead (Pb)
Silver (Ag)
Zinc (Zn)
Complies
g/l
g/l
g/l
31
12.22
0.02 27*
Complies
32
1.78
0.2 - 230*
Complies
33
0.09
0.02 1*
Complies
0.23
No Standard
Value
0.17
0.95
Complies
0.09
1.1
Complies
34
35
36
37
ND
No Standard
Value
38
Phenolic
Compounds
(n-Octylphenol)
Manganese (g/l)
32.7
0.02-130
Complies
39
Iron (g/l)
161.2
10-1400
Complies
40
Mercury (g/l)
ND
0.0001-2.8
Complies
41
Barium (g/l)
10.6
<3-150
Complies
42
Boron (g/l)
13.7
7-500
Complies
ANNEXURE E
POPULATION OF KANDIAH VALLEY (HOUSEHOLD)
Page|167
SR
#
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
VILLAGE
NUMBER OF HOUSES
POPULATION
Kot Gul
Nat Bel
Salachh
Beer
Oshel
Thauti
Kool
Aleel
Thor
Chappar
Dheri
Joshoi
Azgul
Beer II
Gansh
Jhamra
Khat
Zambeel
Birti
Karrang
Dong
Karas
20-25
8
15
7
12
25
35
40
20
12
12
40
36
5
22
12
22
8
58
112
18
6
91
30
55
31
51
101
129
145
76
44
51
155
140
16
79
45
91
26
257
520
58
20
ANNEXURE F1 & F2
RESERVOIR AREA LAND USE CLASSIFICATION AND
INFRASTRUCTURE TO BE SUBMERGED
Page|168
ANNEXURE F3 & F4
AUXILIARY FACILITIES NEAR POWERHOUSE AREA
Page|169
ANNEXURE F5
POTENTIAL SITE FOR RELOCATION
Page|170
ANNEXURE F6
LAND USE MAP FOR POWERHOUSE AREA
Page|171