Professional Documents
Culture Documents
Abstract
In 2009, ADCO implemented the first ever CO2 EOR pilot in the Middle. The pilot project is part of the Company overall strategy
evaluate the feasibility of CO2 injection as an EOR process and in order to address key technical and business uncertainties as well
as the risks associated with CO2 injection The pilot project includes three wells, a CO2 injection well, an observation well and an
oil producing well. The pilot has been operated for one year now to achieve a set of pre-defined objectives. During this period, a
comprehensive data acquisition program was conducted and collected data from wells and reservoir performance was analyzed to
address key uncertainties related to miscible CO2-EOR injection process.
Upon the completion of the project objectives in June 2010, a decision was taken to expand the project scope and target with new
objectives that will help understanding another challenging anomaly in the oil fields (CO2 performance in the transition zones).
This paper shares the challenges faced, lessons learnt and experience gained during the implementation, operation, and monitoring
of the First Miscible CO2-EOR pilot project in a heterogeneous carbonate oil reservoir in Abu Dhabi, UAE.
1. Background
Carbon Dioxide (CO2) is considered to be the most serious Green House Gas (GHG) in the atmosphere and the key contributor to
the Climate Change [1]. In 2006, the Government of the UAE launched Abu Dhabi Future Energy Company (MASDAR) to
implement a large-scale carbon capture project to reduce greenhouse gas emission by capturing and transporting the CO2 to
oilfields for sequestration and/or Enhanced Oil Recovery (EOR) processes
In November 2009, Abu Dhabi Company for Onshore Oil Operations (ADCO), in collaboration with Abu Dhabi National Oil
Company (ADNOC), Industry Shareholders (BP, Shell, Total, ExxonMobil, and Partex) and MASDAR, implemented ADCOs
first CO2 Enhanced Oil Recovery (EOR) Pilot Project by injecting CO2 in a complex carbonate oil reservoir.
ADCO initiated the CO2 EOR study during mid 2008 with the main objective being to develop a CO2 EOR portfolio based on
detailed laboratory studies, simulation studies, and field pilot studies. The ADCO CO2 pilot project started with a company-wide
screening study identifying both the most appropriate EOR option and most likely reservoir candidates. The preparation phase
started early April 2008 with the in-house studies commencing August 2008. In November 2008, the project was reviewed by key
stakeholders and was approved in January 2009.
SPE 142665
The pilot was originally planned to operate for one year, from November 2009 to November 2010. However, upon the completion
of the approved project objectives in June 2010, a decision was taken to expand the project scope to evaluate the CO2 performance
in the transition zones.
The pilot design aspects were addressed in a previous paper [2]. Design of the pilot facilities and the various studies on the surface
facilities were discussed in references [3], [4]. The emphasis in this paper is on the experience gained to date from the pilot
implementation, operation, and monitoring.
2. Pilot design and implementation
ADCO CO2 pilot was designed to achieve the stated objectives. The pilot is located within an undeveloped area where the
reservoir is above Minimum Miscibility Pressure (MMP) of CO2. It consists of three vertical wells; single producer, single
injector and one observer between the producer and injector. The injector well is perforated in a lower sub zone while the producer
is perforated in three sub zones (lower and upper). The well spacing between producer and injector is about 70 meter.
The simulation model was used to assess the well spacing and the perforation selection. Based on different perforation scenarios,
the model result indicates that CO2 breakthrough can occur in 20 to 130 days as shown in Figure [1], which represents the GOR
predictions with CO2 injection. The pilot history match study is addressed in another paper [5].
SPE 142665
cemented with a CO2 resistant cement to ensure long term casing integrity and good zonal isolation during CO2 injection. A
schematic diagram for the pilot wells is shown in Figure [2].
CO2Injector
Observer
OilProducer
MPFM+CO2
2.7/8CarbonSteelTBG
2.7/8CarbonSteelTBG
3.1/2Chrome13TBG
33Meters
Module
DTS/PDHG
37Meters
SPE 142665
x
x
x
Budget, tendering, single sourcing, labs availability, and resources are to be considered as constrains if not well handled
The small team approach allows a project team to remain flexible and effective
Simulation model is important in designing and interpreting pilot performance
The following is recommended for future CO2 pilot design and implementation projects:
x Set pilot objectives that are easily measurable and design the pilot accordingly
x Select the pilot location in a well controlled area with minimum uncertainties in structure and reservoir rock and fluid
properties description
x Allocate resources and requirements according to pilot objectives and size
x Delegate by using the team approach whenever possible for planning and execution, guided by the project lead
x Perform frequent technical review sessions with Shareholders to keep the project team focused on the correct path
1400
100
600
400
70
60
50
40
30
20
200
10
0
Nov-09
Dec-09
Jan-10
Feb-10
Mar-10
Apr-10
May-10
Jun-10
Jul-10
Jul-10
Aug-10
Date
0
Sep-10
800
1000
80
Operational Activities
Operational Activities
90
1200
SPE 142665
1600
700
WHFP (psi)
1400
600
1200
500
1000
400
800
300
600
200
400
100
200
0
Nov-09
Dec-09
Feb-10
Apr-10
May-10
Jul-10
Aug-10
0
Oct-10
Date
WHFP (psi)
1800
2.00
2,500
1.60
2,000
1.20
1,500
0.80
1,000
0.40
500
0.00
Dec-09
SPE 142665
Feb-10
Apr-10
May-10
Jul-10
Date
Aug-10
Qinj
WHIP
kh
skin
08-Oct-09
09-Nov-09
21-Dec-09
04-Apr-10
[mD*ft]
83
98
88
90
mD
1.2
1.47
1.32
1.34
[-]
-3.6
-4.3
-3.9
-4
Two Pressure Fall-Off tests were conducted at the pilot injector, in December 2009 and April 2010 to measure the average
permeability and skin factor. Table 2 represents the summary results for the CO2 injector pressure transient tests analysis which
showed that the skin factor almost doubled after the breakthrough occurrence.
Table 2: Summary Results of Pressure Transient Tests Analysis for Pilot injector
Date
kh
04-Apr-10
25-Dec-09
[md*ft]
30
38
md
1.38
1.73
[-]
-3.4
-5.6
SPE 142665
4. Surveillance Program
The physics, chemistry and simulation of miscible CO2 EOR process are very challenging, as the process introduces major changes
in the reservoir fluid and possibly rock properties, which should be monitored and effectively managed (e.g. asphaltene
precipitation management). For ADCO CO2 Pilot, a comprehensive surveillance plan was designed to collect consistent and
representative static and dynamic data. The strategy was to establish a base line data repository, prior to start up of the CO2
injection and to conduct a time-lapsed monitoring surveys post CO2 injection.
The CO2 pilot wells were connected at surface to an automation system in which the production and injection data can be received
on a daily basis (e.g., fluid rates, WHIP, WHIT, WHFP, and Choke settings). Moreover, a comprehensive data collection activities
was selected for monitoring the project performance including the conventional monitoring activities (PBU, PFO, multi-rate tests,
communication test, and production and cased hole saturation logs ) and the advanced logging tools like cross well seismic, fiber
optics (Distributed Temperature Sensor, DTS) and CO2 saturation detector around well bore. Permanent Multi-Phase Flow Meter
(MPFM) and CO2 analyzer are connected to the producer at surface, where the CO2 concentration and rate changes with time are
measured on a daily basis. Also, retrievable down hole gauges (corrosion resistant gauges) are used for continuous pressure
measurements. Moreover, wellhead surface samples (gas and liquid samples) from producer well, are collected and analyzed to
evaluate fluid compositional changes during CO2 injection.
Time Lapsed Logging Techniques
Two types of saturation logs from two different service providers were carried out to monitor the saturations change during the
injection and production:
x Reservoir Performance Monitoring, RPM-C
x Reservoir Saturation Tool, RST.
All saturation logs showed that CO2 remained in the injection sub zone and partially migrated to the above sub zone which is not
perforated in the injector, while no CO2 was detected in the most upper sub zone of reservoir. This result is consistent with the
field observations, core data, MDT measurements and simulation studies, where well developed dense layers or baffles between
sub zones, particularly upper and lower sub zone, are expected.
However, for the residual oil saturation to CO2, different results obtained for each well and from each log type. For the injector and
observer wells, the RST saturation logs showed very low residual oil saturation (almost Zero% oil saturation), at the
good/permeable intervals while it reached 5-7% in the less permeable interval. The RPM-C logs showed high residual oil
saturation in the injector and observer wells, in excess of 10%.
Borehole environment has a significant impact on the measurement particularly at the producer well; many aspects were reviewed
that have a potential impact on the measurement including the well history, completion, drill fluid and invasion profiles at various
times, stimulation of perforated intervals by acid, fluid loss during cement squeeze operation and cross flow anomaly that was
observed between producing perforations.
Both RST and RPM-C faced difficulties in interpreting the fluids saturation in the producer well due to mentioned challenges at
this particular environment. RST showed relatively good and reasonable analysis in the producer as a function of the predetermined interpretation approach including the environmental correction (borehole CO2 correction), and integrated approach of
interpreting data including Capture count-rate (Sigma), Hydrogen Index (HI), and the elemental yield particularly the carbon (CYield).
The following is recommended for future CO2 saturation logging:
x Base run logs (pre-injection) are essential
x In order to mitigate the effect of completion fluids; mud must be designed properly to minimize the filtration loss, ensure
good cementation, and allow sufficient time between drilling and commencing injection in order to allow adequate filtrate
dissipation.
x Integration of data is essential particularly the direct measurement of the flow profile (spinner measurement) with other
production logging tools, it would help a lot in pulsed neutron interpretation and understanding of the flow and hold-up
distribution.
SPE 142665
Daily Wellhead Samples (WHS): samples that are obtained manually from a specific wellhead sampling point on the
producer. Field lab chromatograph is used to conduct limited compositional gas analysis (CO2% and C1-C6+). The lab
chromatograph is calibrated every three months. In the WHS technique, if the sampling point changed, the CO2% will not
be comparable to the previous readings.
It was found that both CO2 analyzer module and WHS were consistent in CO2% measurements except in the period starting from
July 2010 where WHS showed higher CO2% than that measured in CO2 analyzer by 5% to 7%, as shown in Figure [7]. This
difference was looking very minor and within measurements error, but with the attempts to history match the CO2% and GOR, it
was observed that difference is dramatically affecting the GOR history match and prediction. The GOR can vary from 3000 to
4000 with CO2% equal to 74% and 81% respectively.
CO2% - Analyzer vs. WHS
1
0.9
0.8
CO2 (fraction)
0.7
0.6
CO2 - WHS
0.5
CO2 - Analyzer
0.4
0.3
0.2
0.1
0
14-Oct-09
3-Dec-09
22-Jan-10
13-Mar-10
2-May-10
21-Jun-10
10-Aug-10
29-Sep-10
DATE
SPE 142665
10
SPE 142665
5000
4500
Pressure, psi
4000
3500
3000
2500
2000
1500
1000
0
20
40
60
80
100
120
140
Temperature, C
Figure 8: Reservoir Asphaltene stability; Onset T-dependence different 17 wt% ~ 29 mol% CO2
The following is recommended for Asphaltene deposition monitoring and management during CO2 injection:
x Producing the well at high rate could be a solution to avoid the Asphaltene deposition in the tubing and move the
deposition to surface which will be easier to handle.
x Introducing Asphaltene inhibitor may delay the process of Asphaltene deposition but will not eliminate it.
x Frequent cleaning program could be executed, if the Asphaltene deposition occurred in limited number of wells.
SPE 142665
11
12
SPE 142665
SPE 142665
13
trapped CO2. Because of its peculiar thermodynamic properties of the super-critical carbon dioxide, the pressure will exceed the
pressure rating of the Christmas tree.
The tree was modified such and the master valve was made manual. The control panel logic was modified so that:
x The subsurface safety valve is only activated in the event of an external fire.
x The outer wing valve is actuated only in the event of low pressure signal from the flow line (i.e. line rupture).
(New producer)
4 km
Cluster
Central Processing
Plant (CPP)
Material performance
Carbon steel was used for the producing well and the flow line. The well was completed using L80 tubing and the flowline
material is API 5 L Grade B. The rationale for using carbon steel was:
x Short Pilot duration (two years only)
x Minimize costs
x Obtain data on the performance of carbon steel tubing & flow lines, which can be used if & when larger projects are
implemented
x Project implementation on a fast track basis
Such high levels of CO2 are outside the boundary of the corrosion rate prediction models and unrealistically high rates are
predicted. Corrosion inhibition relies on establishing a good corrosion protective film. Then, continuous treatment is necessary to
maintain the integrity of that film. Consultations were made with the various suppliers of corrosion inhibitors. The dosing rates of
inhibitors were initially increased from 10 to 100 ppm for 6 days. After that, the dosing rates were reduced to 40 ppm. Such high
levels of CO2 are outside the boundary of the corrosion rate prediction models and unrealistically high rates are predicted.
14
SPE 142665
Strong management support, maximum delegation to the team and multi-discipline integration between, surface,
subsurface and operation is the key to successful and fast track design and implementation.
2.
Continuous monitoring and data acquisition on well and operations integrity, reservoir performance, in-situ saturation and
static and transient pressure behavior, and conformance (injection and production profiles) are the key for understanding
and interpretation of the pilot performance.
3.
Distributed Temperature Sensing (DTS) is a powerful monitoring tool, but must be carefully designed for your reservoir
conditions. It is recommended to have a secondary mitigation plan, e.g. conventional production logging, in place in case
of DTS failure.
4.
Cross Well Seismic should be avoided in case of similar fluid densities between the injected and in-place fluids; e.g.
secondary CO2 injection in a dry oil column where the CO2 and oil densities are similar, and not having the minimum
well spacing required to obtain a pickable (above noise) time lapse between the base and repeat surveys (the ADCO CO2
EOR pilot well spacing was about 70 meters).
5.
6.
A combination of different techniques is being adopted as part of the corrosion mitigation plan in the oil producing
facilities. Continuous monitoring is key to the success of this plan
7.
Corrosion experienced in the tail pipe of the tubing of the producing well below the chemical injection point.
8.
Finally, the pilot project provided an excellent opportunity for ADCO to develop in-house expertise in the various aspects
of CO2-EOR technology.
Acknowledgement
The authors would like to thank ADNOC and ADCO Managements for their support and permission to publish this paper. In
addition, the authors would like to acknowledge the CO2 team in ADCO and its affiliates who have contributed in the development
and implementation of the first CO2 Pilot in ADCO.
SPE 142665
15
References
1.
2.
Al-Hajeri, S., Negahban, S., Al-Yafei, G., Al Basry, A.: Design and Implementation of the First CO2-EOR Pilot in Abu
Dhabi, SPE paper no. 129609, presented at the SPE West Asia EOR Conference, Muscat, Oman, 11-13 April 2010.
3.
Saadawi, H.: Surface Facilities for a Pilot CO2-EOR Project in Abu Dhabi, SPE paper No. 127765, presented at the
SPE West Asia EOR Conference, Muscat, Oman, 11 - 13 April 2010.
4.
Saadawi, H., Johns, A., and Walter, K.:A Study to evaluate the Impact of CO2-EOR on Existing Oil Field facilities,
SPE paper no. 141629, presented at the SPE Projects and Facilities Conference, Doha, Qatar, 13-16 February 2011.
5.
Al-Hajeri, S., Ghedan, S., Negahban, S., Al-Yafei, G., Al Basry, A.: Integrated History Matching Simulation Study of
the First Miscible CO2-EOR Pilot in Abu Dhabi Heterogeneous Carbonate Oil Reservoir" SPE paper No. 142623,
Submitted to SPE Middle East Oil and Gas Show and Conference held in Manama, Bahrain, 2023 March 2011.