Professional Documents
Culture Documents
E J B Garnham
Private Consultant, U K
INTRODUCTION
This paper is intended to indicate the purpose
and intent of
the
initial and periodic
inspection and testing required by the IEE
Regulations for Electrical Installations (15th
It is
Edition) - the "Wiring Regulations".
not intended primarily to describe in detail
the testing methods but rather to consider the
logic, philosophy and purpose of the tests and
the order in which
they are done.
The
different considerations
relating
to the
initial and the
periodic
inspection and
testing are discussed
and
the differing
relative emphasis on inspection and on testing
in the two cases are considered.
Note: Particular
a s , e.g., R611-1.
regulations
are referred to
88
checked and it
should
be verified that
isolators and emergency switches are readily
accessible.
The
types
and
ratings
of
protective devices should be checked against
drawings or schedules.
Insulation tests.
The
integrity
of the
insulation between live conductors and between
them and earth must be verified before the
installation is energised: this is the purpose
of the insulation resistance tests ( R 6 1 3 - 5 to
R 6 1 3 - 8 ) . Although the primary
intent is to
measure the insulation resistance the fact
that the tests are conducted at an applied
voltage of 500V or l O O O V d.c. serves also to
verify that the insulation has not suffered
damage or contamination such as to render it
incapable of withstanding the rated voltage of
the installation.
R613-7
draws attention
to
the
need to
safeguard electronic devices by isolating them
from the circuit(s) under test. Such devices
are becoming more common, particularly in
89
.osures is verified
by physical rather
than electrical test, using standard test
fingers. This method of protection is likely
to be
found
mainly
in
industrial and
specialised commercial installations, such as
laboratories and electronic workshops. It is
important that verification is thorough.
Insulation of non-conducting floors and walls
(R613-13). This also is a method of shock
protection likely to
be
found
only in
specialised installations.
The resistance
between insulating
floors/walls
and
the
installation main protective conductor is to
be measured at not less than 3 points on each
surface. No test voltage is specified but it
would seem logical to apply the same voltages
as for the insulation resistance tests of
R613-5. The only requirement regarding the
location of the points of test is that at
least one of them shall be not less than lm
and not more than 1.2m from any extraneous
conductive part in the location.
Insulation of extraneous
conducting parts
(R413-31(a)(iii))
must
have
a
voltage
withstand test of 2kV applied, and the leakage
current must not
exceed
1mA
in normal
No duration is specified
conditions of use.
for the withstand test but in view of the
importance of this insulation it would seem
sensible to apply the test voltage for at
90
still
fit
for
there have
been
no
unauthorised
unrecorded additions or alterations;
its
or
devices for
isolation
and
switching
continue to function correctly and are
accessible.
It is very desirable that tests and inspection
of an installation in service are done in such
a way
as
to
minimise
disturbance and
disruption both to the installation and to the
user of it, otherwise it is probable that they
will not be done.
If a user knows that he
will suffer loss of use of his installation
(or part of it) for a considerable time, in
addition to having to pay for the cause of
such loss (i.e. the inspection and test) he is
unlikely to look favourably upon it in the
first instance.
Periodic Inspection
The inspection is probably of more value than
the tests in establishing the condition of the
installation and the degree (or lack) of
maintenance it has enjoyed. Before embarking
upon a periodic inspection every effort should
be made to obtain as much as possible of the
information which R514-3
requires
to be
provided for the
installation and R611-2
requires to be made available to the person
carrying out the inspection and testing. This
information, together with the Completion and
Inspection Certificates should
enable the
inspector to establish whether there have been
any additions
or
alterations
since the
previous inspection and, if so, whether they
have been properly inspected and tested in
compliance with Chapter 62.
The following points,
which
are neither
exhaustive
nor
exclusive,
nor
in
any
particular order of importance, might form the
basis of a checklist for the inspection of an
installation which is still in service:
- suitability of
91
evidence of alterations/additions
original installation;
to the
- identification of locations
and equipment
for which precautions may be necessary to
prevent danger and/or damage during tests;
- presence, accessibility
and
devices
for
electrical
isolation and switching;
condition of
protection,
of
than fuses;
overcurrent
devices
other
of
protective
monitoring devices;
and
any
- deterioration of or
damage to conductors
and their insulation, and their protective
coverings, if any;
by
barriers
provided during erection;
- protection of
- suitability
of wiring for
load,
environment
and
installation;
its present
method
of
conductors
labelling of circuits;
and correct
presence of danger
warning notices.
notices
non-conducting
enclosures
floors
and
walls.
Older Installations
- connections/terminations of conductors;
- identification of
or
Periodic Testing
Depending upon the thoroughness and results of
the inspection it may
not be considered
necessary to carry out all of the tests which
would be done on a new installation. For
instance, if there have been no alterations or
additions since the last inspection it may not
be necessary to test polarity at every point,
though as a general rule it would probably be
prudent to carry
out
a
check at main
distribution boards and on any circuits which
are not covered
by previous certificates
and/or appear to have been rewired since the
previous inspection.
ACKNOWLEDGEMENTS
polarity;
devices
for
isolation
and
switching;
- operation
of residual
where applicable.
current
devices,
...
...'I,