Professional Documents
Culture Documents
Prepared By:
1. Jagadish Chandra Sutradhar
ID # 112-0070-511
ID # 112-0164-511
ID # 112-0011-511
ID # 112-0135-511
ID # 122-0197-511
ID # 112-0070-511
ID # 112-0164-511
ID # 112-0011-511
ID # 112-0135-511
ID # 122-0197-511
Supervised By:
Marzia Hoque
Signature :
Date:
Declaration
It is here by declared that no part of this thesis bearers the copyright violation and no plagiarism
opted during the course of material preparation. The entire works has been planned and carried
out under the thesis supervisor of the honorable faculty member Marzia Haque department of
Electrical and Electronic Engineering, Atish Dipankar Biggayan O Projokti Bishawbiddaloy,
Dhaka, Bangladesh.
The content of this thesis is submitted by the group Name : Jagadish Chandra Sutradhar, ID #
112-0070-511, Name : Md. Sharif Hossain ID # 112-0164-511, Name : Syed Shawkat Aziz ID
# 112-0011-511, Name : Mohammad Ali Hasan ID # 112-0135-511, Name : Md. Jakir
Hossain ID # 122-0197-511.
Only for the fulfillment of the course of STUDY OF ELECTRICAL POWER
GENERATION, TRANSMISSION & DISTRIBUTION IN BANGLADESH . And no part
of this is used anywhere for the achievement of any academic Degree or Certificate.
Certificate
This is to certify that the B.Sc. thesis entitled STUDY OF ELECTRICAL POWER
GENERATION, TRANSMISSION & DISTRIBUTION IN BANGLADESH . submitted by
following group:
This is to certify that the B.Sc thesis entitled STUDY OF ELECTRICAL POWER GENERATION,
TRANSMISSION & DISTRIBUTION IN BANGLADESH
: Jagadish Chandra Sutradhar, ID # 112-0070-511, Name : Md. Sharif Hossain ID # 1120164-511, Name : Syed Shawkat Aziz ID # 112-0011-511, Name : Mohammad Ali Hasan ID
# 112-0135-511, Name : Md. Jakir Hossain ID # 122-0197-511.
The thesis represents an independent and original work on the part of the
candidates. The research work has not been previously formed the basis for the
award of any Degree, Diploma, Fellowship or any other discipline.
The whole work of this thesis has been planned and carried out by this group
under the supervision and guidance of the faculty members of Atish Dipankar
Biggayan O Projokti Bishawbiddaloy, Bangladesh.
Marzia Hoque
Lecturer
Department of Electrical and Electronic Engineering
Atish Dipankar Biggayan O Projokti Bishawbiddaloy
Transmittal
Date: 26/05/2014
Faculty of Engineering
Department of EEE
Atish Dipankar Biggayan O Projokti Bishawbiddaloy
Dhaka, Bangladesh.
Subject: letter of transmittal.
Dear Sir,
With due respect, we should like to inform you that is a great pleasure for us to submit the final
project on STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION &
DISTRIBUTION IN BANGLADESH for Department of Electrical and Electronic Engineering
as requirement bachelor degree/ program. This project provided us with a practical exposure to
the overall working environment and very good experience which is prevailing in to professional
life. We came to know about many things regarding the current world on the concept of
Electronic Development. We have tried to our best to put through effort for the preparation of this
report. Any short coming or fault may arise as our unintentional mistake we will whole heartily
welcome for any clarification and suggestion about any view and conception disseminated
through this project.
We hope and strongly believe that this project will meet the requirement as well as satisfying your
purpose. We will available for any further classification in this regard.
Sincerely Yours,
ID # 112-0070-511
ID # 112-0164-511
ID # 112-0011-511
ID # 112-0135-511
ID # 122-0197-511
APPORAVAL SHEET
ID # 112-0070-511
ID # 112-0164-511
ID # 112-0011-511
ID # 112-0135-511
ID # 122-0197-511
..
Marzia Hoque
Md.Imam Hossain
ACKNOWLEDGEMENT
At
first
we
would
like
to
thank
our
Supervisor
Marzia
Haque
(Lecturer) for giving us the opportunity to work to under his supervision, the endless hours of
help, Suggestions, Advice and Support to keep us on track during the development of this thesis.
We also want to express gratitude to Mr. Md. Imam Hossain for his support during our work on
this thesis.
Last, but not the least, we would like to thank our parents and family for making it possible for us
to study and for their constant help and support.
May, 2014
1. Jagadish Chandra Sutradhar
ID # 112-0070-511
ID # 112-0164-511
ID # 112-0011-511
ID # 112-0135-511
ID # 122-0197-511
ABSTRACT
In this modern world, the dependence on electricity is so much that it has become a part and
parcel of our life. The development of any country of the world is based on electricity and its
proper generation, transmission and distribution. For the proper utilization, it is required to
transmit and distribute the generating electrical power through the proper way.
For proper power generation, we have to consider the selection of power station according to the
site selection of the different power station and their advantage and disadvantage.
In this thesis work, we have discussed about different types of power station, their merits &
demerits, power generation in Bangladesh, power demand, installed capacity deficiency of power,
power plant under construction.
We have also discussed about the transmission and distribution system. Where has been included
mechanical design of transmission system, electrical design of transmission system, different
types of transmission loss, remedy of loss. For distribution system, we have included the bhurulia
distribution sub-station.
We think that, this study will be very helpful for better understanding about generation and
transmission system of Bangladesh.
LDC
A.C
: Alternating Current
D.C
: Direct Current
KVA
Km
: Kilometer
KV
: Kilo Volt
KW
: Kilo Watt
KWH
: Circuit Breaker
GS
: Generation Station
NPS
IPP
EHV
CONTENTS
TABLE OF CONTENTS
Contents
Cover Page
Initial Page
Declaration
Certificate
Transmittal
Approval Sheet
Acknowledgement
Abstract
Abbreviation & Notations
Table of Contents
List of Table
List of Figure
Page No.
1
2
3
4
5
6
7
8
9
10
11
12
CHAPTER-1: Introduction
1.1
Background
19
1.2
Objective of thesis
19
Generation Station
20
2.2
20
2.3
20
20
10
2.4
2.5
2.6
2.7
21
21
21
22
24
34
34
35
35
36
36
37
37
38
38
38
40
40
40
40
41
41
41
41
42
42
11
44
3.2
Power demand
44
3.3
44
3.4
Installed capacity
44
3.5
45
46
12
Transmission System
52
4.2
Primary Transmission
52
52
52
4.3
Secondary Transmission
53
4.4
53
4.5
53
4.6
54
4.7
55
4.8
55
55
56
56
57
58
5.2
Conductors materials
58
5.3
Types of conductor
59
5.4
Line support
61
5.5
61
5.6
Insulators
62
5.7
Types of Insulators
62
13
6.10
65
65
71
76
77
77
78
78
79
80
81
82
83
83
84
84
84
85
85
85
86
86
86
87
87
87
88
88
88
88
89
6.11
90
Definition of Substation
91
7.2
Importance of Substation
91
14
7.3
91
7.4
Classification of Substation
91
7.5
92
7.5.1 Transformer
93
93
93
7.5.4 Isolator
94
95
7.5.6 Insulator
95
7.5.7 Bus-Bar
97
7.5.8 Circuit-Breaker
99
100
100
100
101
102
7.7
104
7.8
104
7.9
106
7.9
107
7.6
108
8.2
108
8.3
108
22
Figure : 2.2
24
Figure : 2.3
Steam Generator
25
15
Figure : 2.4
Turbo Generator
29
Figure : 2.5
30
Figure : 2.6
A Ranking cycle with a two stage steam turbine and a single feed
31
water heater.
Figure : 2.7
32
Figure : 2.8
35
Figure : 2.9
39
Figure : 2.10
41
Figure : 2.11
42
Figure : 5.1
59
Figure : 5.2
60
61
Figure : 5.3
Steel Tower
62
Figure : 5.4
63
Figure : 5.5
64
Figure : 6.1
67
Figure : 6.2
68
69
Figure : 6.4
70
Figure : 6.5
72
Figure : 6.6
72
Figure : 6.7
73
Figure : 6.8
Nominal T representation.
74
Figure : 6.9
Nominal representation.
74
Figure : 6.10
74
Figure : 7.1
Transformer.
93
Figure : 7.2
93
Figure : 7.3
Isolator
94
Figure : 7.4
Lightning arrestor
95
Figure : 7.5
96
Figure : 7.6
96
Figure : 7.7
Strain insulator
97
Figure : 7.8
98
16
Figure : 7.9
99
Figure : 7.10
100
Figure : 7.11
101
Figure : 7.12
102
Figure : 7.13
103
Figure : 7.15
106
Figure : 7.16
Power triangle
107
LIST OF TABLE
Table List
Description
Page No
3.5
45
3.5.1
46
3.5.2
th
47
3.5.3
48
4.8.2
56
6.9
79
6.10
80
6.10.1
81
6.10.2
82
83
83
84
84
6.10.7
84
6.10.8
85
85
Substations
17
6.10.10
85
6.10.11
86
6.10.12
86
6.10.13
86
6.10.14
87
6.10.15
87
India(Baharampur)
6.10.16
87
interconnecting line
6.10.17
88
88
7.7
104
7.8
104
7.9
105
7.10
105
7.11
105
7.12
105
7.13
106
7.18
106
REFERENCES
109
18
CHAPTER-1
INTRODUCTION
1.1 BACKGROUND
For growing development of a country, electricity has a vital role in all sectors. For the proper
utilization, is required to transmit and distribute the electrical power through proper way. During
the early years small local generating station supplied power to respective local loads. Each
generating station needed enough installed capacity to meet the local peak loads. Bangladesh is an
underdeveloped country. Its socio- economic structure is gradually increasing. So the demand of
power is extending day by day and thus the importance of Generation, Transmission and
Distribution are becoming more complicated.
An electric power system consist of the three principal components are the generation system,
transmission system and distribution system. The increasing uses of electric power for domestic,
commercial and industrial purposes necessities to provide bulk electric power economically. This
is achieved with the help of suitable power generating units, known as power plant. An electric
power station is an assembly of equipments in which energy is converted from one form to
another into electric energy. Electrical equipments of power station include generators,
transformers, switch gears and control gears. The transmission lines are the connecting links
between the generating stations and the distribution system and lead to the power system over
interconnections. It is required to proper distribute the electric power to the consumer by a
network is called the distribution system.
1.2 OBJECTIVES OF THE THESIS
a) To study the different power stations such as hydro electric power station, thermal power
station, Nuclear power station, diesel power station and Gas turbine power station.
b) To study the comparative facilities of different power station.
c) To study the comparative productive ability of different power stations.
d) To study the power generation in Bangladesh.
e) To study the transmission system in Bangladesh.
19
CHAPTER-2
OVERVIEW OF POWER GENERATION SYSTEMS
2.1 GENERATING STATION
Bulk electric power is produced by special plant is known as the generating station or power
plants. A generating station essentially employs a prime mover coupled to an alternator for the
production of electric power. The alternator converts mechanical energy of the prime mover into
electrical energy. The electrical energy produced by the generating station is transmitted and
distributed with the help of conductors of various consumers.
2.2 TYPES OF GENERATING STATION
1) Steam power plant
2) Hydro-electric power plant
3) Nuclear power plant
4) Diesel power plant
2.3 STEAM POWER PLANT
A generating station that converts the heat energy of coal combustion into electrical energy is
known as a steam power station.
2.3.1 CHOICE OF SITE FOR STEAM POWER STATIONS
1. Supply of fuel: The steam power station should be located near the coal mines so that
transportation cost is minimum. However, if such a plant is to be installed taken that
adequate facilities exists for the transportation of coal.
2. Availability of water: As huge amount water is required for the condenser therefore, such
a plant should be located at the bank of a river or near a canal to endure the continuous
supply of water.
3. Transportation facilities: A modern steam power station often requires the transportation
of material and machinery. Therefore, adequate transportation facilities must exist. The
plant should be well connected to others part of the country by the rail road etc.
20
4. Cost and Type of Land: The steam power station should be located at a place where land
is cheap and further extension, if necessary is possible. More ever the bearing capacity of
the ground should be adequate so that heavy equipment could be installed.
5. Nearness to the Load Centre: In order to reduce the transmission cost the plant should be
located near the centre of load. This is particularly important if dc supply is adopted, this
factor becomes relatively less important with consequent reduced transmission cost. It
possible to install the plant away from the load centers provided other conditions are
favorable.
6. Distance from Populated Area: As huge amount of coal is burnt in a steam power
station, therefore smoke and fumes plant should be located at a considerable distance from
the populated areas.
2.3.2 ADVANTAGES OF STEAM POWER PLANT
a) The fuel is quite cheap
b) Less initial cost as compared to other generating stations
c) It can be installed at by place irrespective of the existence of coal. The coal can be
transported to the site of the plant by rail or road.
d) It required less space as compared to the hydro-electric power station.
e) The cost of generation is lesser than that of the diesel power station.
2.3.3 DISADVANTAGES OF STEAM POWER PLANT
a)
It pollutes the atmosphere due to the production of large amount of smoke and fumes.
21
22
It is worthwhile to give a passing reference to the amount of coal burnt and ash produced in a
modern thermal power station. A 100 MW station operating at 50% load factor may burn about
20000 tons of coal per month and ash produced may be to the tune of 10% to 15% of coal fired
i.e., 2000 to 3000 tons. In fact in thermal power station about 50% to 60% of the total operating
cost consists of a boiler for the production of steam and other auxiliary equipment for the
utilization of flue gases.
a) Boiler: The heat of combustion of coal in the boiler is utilized to convert water into steam at
high temperature and pressure. The flue gases the boilers makes their journey through super
heater economizer, air pre heater and are finally exhausted to atmosphere through the
chimney.
b) Super heater: The steam produced in the boiler is wet and is passed through a super heater
where it is dried and superheated water by the flue gases on their way to chimney.
Superheating provides two principal benefits. Firstly the overall efficiency is increased.
Secondly too much condensation in the last stages of turbine is avoided the supper heated
steam turbine through the main valve.
c) Economizer: An economizer is essentially a feed water heater and derives heat from flue
gases for this purpose. The fed to the economizer before supplying to the boiler. The
economizer extracts a part of heat of flues gassed to increase the feed water temperature.
d) Air pre-heater: An Air pre-heater increase the temperature of the air supplied from coal
burning by deriving heat from flue gases. Air is drown from the atmosphere by a forced
draught fan and is passed through air pre heater before supplying to the boiler furnace. The air
drowns from the atmosphere by a forced draught fan and is passed through air pre heater
before supplying to the boiler furnace. The pre heater extracts heat from flue gases and
increases the temperature of air used for coal combustion. The principal benefits of preheating
the air are increased thermal efficiency and increased steam capacity per square meter of
boiler surface.
e) Steam turbine: The dry and superheated steam from the super heater id fed to the steam
turbine through main valve. The heat energy of steam when passing over the blades of turbine
is converted into mechanical energy. After giving heat energy to the turbine the steam is
exhausted to the condenser which condenses the exhausted steam by means of cold water
circulation.
23
f) Alternator: The Steam turbine is coupled to an alternator. the alternator converts mechanical
energy of turbine into electrical energy. The electrical output from the alternator is delivered
to the bus bars through transformer circuit breaker and insulators.
g) Feed water: The condensate from condenser is used as feed water to the boiler some water
may lost in the cycle which is made up from external source. The feed water on its way to the
boiler is heated by water heaters and economizer. This helps in raising the overall efficiency
of the plant.
h) Cooling arrangement: In order to improve the efficiency of the plant. The steam exhausted
from the turbine is condensed by means of a condenser.
2.3.6: TYPICAL STEAM POWER PLANT
16. Economizer
7. Condenser
11. Deaerator
and temperature required or the steam turbine that drives the electrical generator. A fossil fuel
steam generator includes an economizer, a steam drum, and the furnace with its steam generating
tubes and super heater coils. Necessary safety valves are located at suitable points to avoid
excessive boiler pressure. The air and flue gas path equipment include forced draft fan, air pre
heater boiler furnace, fly ash collectors and the flue gas stack.
Geothermal plants need no boiler since they used naturally occurring steam source. Heat
exchangers may be used where the geothermal steam is very corrosive or contains excessive
suspended solids. Nuclear also boil water to raise steam, either directly generating steam from the
reactor (BWR) or else using an intermediate heat exchanger (PWR).
For units over about 200 MW capacity, redundancy of key components is provided by installing
duplicates of the FD fan, APH, fly ash collectors and ID fan with isolating dampers. On some
units of about 60 MW, tow boilers per uint may instead be provided.
2.3.6.2: Boiler furnace and steam drum:
Once water inside the boiler or steam
vaporization or enthalpy is underway. The boiler transfers energy to the water by the chemical
reaction of burning some type of fuel. The water enters the boiler through a section in the
convection pass called the economizer. From the economizer it passes to the steam drum. Once
the water enters the stream drum it goes down the down comers to the lower inlet water wall
headers. From the inlet headers the water rises through the water walls and is eventually turned
into steam and due to the heat being generated by the burners located on the front and rear water
walls. As the water is turned into steam in the water walls, the steam once again enters the steam
drum. The steam/vapor is passed through a series of the steam and water separators and then
dryers inside the steam drum . The steam separators and dryers remove water droplets from the
steam and the cycle through the water walls is repeated. This process is known as natural
circulation.
The boiler furnace auxiliary equipment includes coal feed nozzles and igniter guns, soot blowers,
water lancing and observation ports (in the furnace walls) for observation of the furnace interior.
Furnace explosions due to any accumulation of combustible gases after a trip-out are avoided by
flushing out such gases from the combustion zone before igniting the coal.
The steam drum (as well as the super heater coils and headers) have air vents and drains needed
for initial startup. The steam drum has internal devices that remove moisture from the wet steam
26
entering the drum from the steam generating tubes. The dry steam then flows into the super heater
coils.
2.3.6.3: Super heater:
Fossil fuel power plants can have a super heater and/or re-heater section in the steam generating
furnace. Nuclear-powered steam plants do not have such sections but produce steam at essentially
saturated conditions. In a fossil fuel plant, after the steam is conditioned by the drying equipment
inside the steam drum, it is piped from the upper drum area into tubes inside an area of the
furnace known as the super-heater, which has an elaborate set up of tubing where the steam vapor
picks up more energy from hot flue gases outside the tubing
superheated above the saturation temperature. The superheated steam is then piped through the
main steam lines to the valves before the high pressure turbine.
2.3.6.4: Re-heater:
Power plant furnaces may have a re-heater section containing tubes heated by hot flow gases
outside the tubes. Exhaust steam from the high pressure turbine is rerouted to go inside the reheater tubes to pickup more energy to go drive intermediate or lower pressure turbines. This is
what is called as thermal power.
2.3.6.5: Fuel preparation system:
In coal-fired power stations, the row feed coal from the coal storage area is first crushed into
small pieces and then conveyed to the coal feed hoppers at boilers. The coal is next pulverized
may be ball mills, rotating drum grinders, or other types of grinders. Some power station burn fuel
oil rather than coal. The oil must kept warm (above its pour point) in the fuel oil storage tanks to
prevent the oil from congealing and becoming unpumpable. The oil is usually heated to about
1000c before being pimped through the furnace fuel oil spray nozzles.
Boilers in some power stations use processed natural gas as their main fuel. Other power stations
may use processed natural gas as auxiliary fuel in the event that their main fuel supply (coal or
oil) is interrupted. In such cases, separate gas burners are provided on the boiler furnaces.
2.3.6.6: Air path:
External fans are provided to give sufficient air for combustion. The forced draft fan takes air
from the atmosphere and first warming it in the air pre-heater for better combustion, injects it via
27
the air nozzles on the furnace wall. The induced draft fan assists the FD fan by drawing out
combustible gases from the furnace, maintaining a slightly negative pressure in the furnace to
avoid backfiring through any opening.
2.3.6.7: Auxiliary Systems:
Fly ash collection: Fly ash is captured and removed from the flue gas by electrostatic
precipitators or fabric bag filters (or sometimes both) located at the outlet of the furnace and
before the induced draft fan. The fly ash is periodically removed from the collection hoppers
below the precipitators or bag filters. Generally, the fly ash is pneumatically transported to storage
silos for subsequent transport by trucks or railroad cars.
2.3.6.8 : Action and disposal:
Bottom ash collie: At the bottom of the furnace, there is a hopper for collection of bottom ash.
This hopper is always filled with water to quench the ash and clinkers falling down from the
furnace. Some arrangement is included to crush the clinkers and for conveying the crushed
clinkers and bottom ash to a storage site.
Boiler make-up water treatment plant and storage: Since there is continuous withdrawal of
steam and continuous return of condensate to the boiler, losses due to blow down and leakages
have to be made up to maintain a desired water level in the boiler steam drum. For this,
continuous make-up water is added to the boiler water system. Impurities in the raw water input to
the plant generally consist of calcium and magnesium salts which impart hardness to the water.
Hardness in the make-up water to the boiler will from deposits on the tube water surface which
will lead to overheating and failure of the tubes. Thus, the salts have to be removed from the
water, and that is done by water demineralising treatment plant (DM). A DM plant generally
consist of caution, anion, and mixed bed exchangers. Any ions in the final water from this process
consist essentially of hydrogen ions and hydroxide ions, which recombine to form pure water.
Very pure DM water becomes highly corrosive once it absorbs oxygen from the atmosphere
because of its very high affinity for oxygen.
The capacity of the DM plant is dictated by the type and quantity of salt s in the raw water input.
However, some storage is essential as the DM plant may be down for maintenance. For this
purpose, a storage tank is installed from which DM water is continuously withdrawn for boiler
make-up.the storage tank for DM water is made from materials not affected by corrosive water,
28
such as PVC. The piping and valves are generally of stainless steel. Sometimes, a steam
blanketing arrangement or stainless steel doughnut float is provided on top of the water in the tank
to avoid contact with air.DM water make-up is generally added at the steam space of the surface
condenser (i.e., the vacuum side). This arrangement not only sprays the water but also DM water
gets deaerated, with the dissolved gases being removed by an air ejector attached to the condenser
2.3.6.9: Steam turbine-driven electric generator: Rotor of the modern steam turbine, used in a
power station.
Turbo generator:
making the top half portion of the shaft hotter than the bottom half. The shaft therefore could
wrap or bend by millionths of inches.
This small shaft deflection, only detectable by eccentricity meters, would be enough to cause
damaging vibrations to the entire steam turbine generator unit when it is restarted. The shaft is
therefore automatically turned al low speed (about one percent rated speed) by the barring gear
until it has cooled sufficiently to permit a complete stop.
Condenser:
30
circulating cooling water from a cooling tower to reject waste heat to the atmosphere or oncethrough water from a river, lake or ocean
Feed water heater:
Fig: 2.6 A Ranking cycle with a two stage steam turbine and a single feed water heater.
In the case of a conventional steam-electric power plant utilizing a drum boiler, the surface
condenser removes the latent heat of vaporization from the steam as it changes states from vapor
to liquid. The heat content (btu) in the steam is referred to as Enthalpy. The condensate pump then
pumps the condensate water through a feed water heater The feed water heating equipment then
raises the temperature of the water by utilizing extraction steam from various stages of the
turbine, Preheating the feed water reduce the irreversibility involved in steam generation and
therefore improves the thermodynamic efficiency of the system,[9] This reduces plant operating
cost and also helps to avoid thermal shock to the boiler metal when the feed water is introduced
back into the steam cycle
2.3.6.11: Super heater:
As the steam is conditioned by the drying equipment inside the drum, it is piped from the upper
drum area into an elaborate set up of tubing different areas of the boiler. The areas known as super
heater and re-heater, the steam vapor picks up energy and its temperature is now superheated
31
above the saturation temperature. The superheated steam is then piped through the main steam
lines to the valves of the high pressure turbine
Deaerator:
32
Generator heat dissipation: The electricity generator requires cooling to dissipate the heat that it
generators. While small units may be cooled by air drawn through filters at the inlet, lager units
generally require special cooling arrangements. Hydrogen gas cooling, in an oil sealed casing, is
used because it has the highest known heat transfer coefficient of any gas and for its low viscosity
which reduces winding losses. This system requires special handling during start up, with air in
the chamber first displaced by carbon dioxide before filing with hydrogen ensures that the highly
flammable hydrogen does not mix with oxygen in the air.
The hydrogen pressure inside the casing is maintained slightly higher than atmospheric pressure
to avoid outside air ingress. The hydrogen must be sealed against outward leakage where the shaft
emerges from the casing. Mechanical seals around the shaft are installed with a very small annular
gap to avoid rubbing between the shaft and the seals. Sal oil is used to prevent the hydrogen gas
leakage to atmosphere.
The generator also uses water cooling. Since the generator coils are at a potential of about 22 KV
and water is conductive, an insulting barrier such as Teflon is used to interconnect the water line
and the generator high voltage windings. Dematerialized water of low conductivity is used.
Generator high voltage system: The generator voltage ranges from 11 KV in smaller unit to 22
KV in larger units. The generator high voltage leads are normally large aluminum channels
because of their high current as compared to the cables used in smaller machines. They are
enclosed in well-grounded aluminum bus ducts and are supported on suitable insulators. The
generator high channels are connected to step-up transformers for connecting to a high voltage
electrical substation (of the order of 115 KV to 520 KV) for further transmission by the local
power grid. The necessary protection and metering devices are included for the high voltage
leads. Thus, the steam turbine generator and the transformer from one unit. In smaller units,
generating at 11 KV, a breaker is provided to connect it to a common 11 KV bus system
2.3.6.13: Other Systems:
Monitoring and alarm system: Most of the power plant operational control is automatic.
However, at times, manual intervention may be required. Thus, the plant is provided with
monitors and alarm systems that alert the plant operators when certain operating parameters are
seriously deviating from their normal range.
Battery supplied emergency lighting and communication: A central battery system consisting
of lead acid cell units is provided to supply emergency electric power, when needed, to essential
33
items such as the power plants control systems, communication systems, turbine lube oil pumps,
and emergency lighting. This is essential for a safe, damage-free shutdown of the units in an
emergency situation.
Transport of coal fuel to site and to storage: Most thermal stations use coal as the main fuel.
Raw coal is transported from coal mines to a power site by trucks, barges, bulk cargo ships or
railway cars. The coal received at site may be off different sizes. The railway cars are unloaded at
site by rotary dumpers or side till dumpers to tip over onto conveyors conveyor belt below. The
coal is generally conveyed to crush the coal to about inch (6mm) size. The crushed coal is then
sent by belt conveyors to a storage pile. Normally, the crushed coal is compacted by bulldozers, as
compacting of highly volatile coal avoids spontaneous ignition.
2.3.7 EFFICIENCY OF STEAM POWER PLANT
There are two types of efficiency in thermal power plant.
I)
Thermal efficiency
34
a) Dam: A dam is a barrier, which stores water and creates water heads. Dams are building
of concrete or stone -masonry, earth or rock field. The type and arrangement depend
upon the topography of site. The type of dam also depends upon the type of foundation
conditions local materials and transportations available, occurrence of earthquakes and
other hazards.
b) Spillways: In order to discharge the surplus water the storage reservoir in to the river on
the down-steam side of the dam, spillways are used.
c) Head work: The head works consists of diversion structures at the head of an intake.
The generally include booms and racks for the diverting floating debris, sluices for by
passing debris and sediments and valves for the controlling the follow of water to the
turbine.
d) Surge tank: A surge tank is a small reservoir or tank in which water level rises or falls
to reduce the pressures swings in the conduit. A surge tank is located near the beginning
of the conduit. When the load on the turbine decreases, then increases the water level of
the surge tank and reversal.
e) Penstocks: Penstocks are conduits, which carry water to the turbines; they are generally
made of reinforced concrete or steel. Various devices such as automatic butterfly valve,
36
air valve and surge tank are provided for the protection of penstocks. Automatic
butterfly valve shuts off water flow through the penstocks promptly if it raptures. Air
valve maintains the air.
1. For high head.
2. Reaction turbine- for low and medium head
f)Electrical equipments: This includes alternators, transformers, circuit breaker and other
switching and protective devices.
2.5 NEUCLEAR POWER STATION
A generating station in which nuclear energy is converted into electrical energy is known as a
nuclear power station. In nuclear power station, heavy elements such as Uranium (U-235) or
thorium (Th-232) are subjected to nuclear fission in a special apparatus known as a reactor. The
energy thus related is utilized in raising steam at high temperature and pressure. The steam runs
the turbine which converts energy into mechanical energy. The turbine drives the alternator which
converts mechanical energy into electrical energy.
2.5.1 SELECTION OF SITE FOR NUCLEAR POWER STATION
1. Availability of water: as sufficient water is required for cooling purposes, therefore, the
plant side should be located where ample quantity of water is available, e.g., across a river
or by sea side
2. Disposal if water: the waste produce by the fission in a nuclear power station is generally
radioactive which must be disposed of properly to avoid health hazards. The waste should
either be buried in a deep trench or disposal off in sea quite away from the sea short.
Therefore, the site selected for such a plant should have adequate arrangement for the
disposal of radioactive waste
3. Steam turbine: the steam produce in the heat exchange is led to steam turbine through a
valve. After doing a useful work in the turbine, the steam is exhausted to condenser. The
condenser condenses the steam which is fed to the heat exchanger through feed water
pump.
4. Alternator: The steam turbine drives the alternator which converts mechanical energy
into electrical energy. The output from the alternator is delivered to the bus-bares through
transformer, circuit breaker and isolators.
37
considerable saving in
turbine
to
heat exchanger
39
40
41
e) Alternator: The gas turbine is coupled to the alternator. The alternator converts
mechanical energy of the turbine into electrical energy.
f) Starting Motor: Before starting the turbine, compressor has to be started. For this
purpose, an electrical motor is mounted on the same shaft of the turbine. This is
energized by the batteries. Once the unit starts, a part of mechanical power of the drives
the compressor and there is no need of motor now.
43
CHAPTER-3
POWER GENERATION IN BANGLADESH
3.1 GENERATING VOLTAGE OF DIFFERENT POWER STATION
15.75kv
11kv
10.5kv
6.6kv
44
Generation of 21/04/2014
PDB
3502.00
1648.00
1972.00
SBU,PDB
223.00
194.00
201.00
EGCB
622.00
235.00
417.00
APSCL
682.00
468.00
465.00
1617.00
1165.00
877.00
110.00
89.00
90.00
33.00
0.00
0.00
SIPP,REB
215.00
160.00
175.00
Q.Rental 3 Years
100.00
95.00
100.00
QRPP(5yrs)
200.00
181.00
192.00
Other
825.00
650.00
581.00
1069.00
740.00
780.00
QRPP (3 Yrs.)
416.00
335.00
380.00
169.00
140.00
146.00
9783.00
6100.00
6376.00
IPP
SIPP,PDB
RENTAL(3 yrs)
RPP (3 Yrs.)
Total
45
Capacity(Unit)
250.00 MW
Total(%)
2.44 %
FO
0.00 MW
Gas
6615.00 MW
64.59 %
HFO
1963.00 MW
19.17 %
HSD
683.00 MW
6.67 %
Hydro
230.00 MW
2.25 %
Imported
500.00 MW
4.88 %
10241.00 MW
100 %
Total
0%
Capacity(Unit)
Total(%)
Coal
200.00 MW
2.04 %
FO
52.00 MW
0.53 %
Gas
6224.00 MW
63.62 %
HFO
1926.00 MW
19.69 %
HSD
661.00 MW
6.76 %
Hydro
220.00 MW
2.25 %
Imported
500.00 MW
5.11 %
Total
9783.00 MW
100 %
46
47
Derated
Capacity(Unit)
Day Peak
Eve Peak
78.00 MW
42.00 MW
45.00 MW
Ghorasal ST :Unit-3,
180.00 MW
100.00 MW
100.00 MW
Ghorashal ST 4
180.00 MW
170.00 MW
170.00 MW
Ghorashal 100
100.00 MW
84.00 MW
99.00 MW
Ghorrashal ST 5
190.00 MW
190.00 MW
190.00 MW
Ghorashal ST 6
190.00 MW
0.00 MW
0.00 MW
Ghorashal 45 MW
45.00 MW
43.00 MW
46.00 MW
Ghorashal MAX
78.00 MW
76.00 MW
78.00 MW
Ghorashal Regent
0.00 MW
2.00 MW
0.00 MW
60.00 MW
0.00 MW
0.00 MW
Horipur NEPC
110.00 MW
93.00 MW
110.00 MW
360.00 MW
246.00 MW
325.00 MW
450.00 MW
440.00 MW
0.00 MW
0.00 MW
0.00 MW
0.00 MW
Meghnaghat IEL
100.00 MW
91.00 MW
100.00 MW
Madanganj 102 MW
100.00 MW
95.00 MW
100.00 MW
Karanigonj
100.00 MW
90.00 MW
90.00 MW
Narshingdi
22.00 MW
16.00 MW
18.00 MW
Shiddirganj ST
150.00 MW
0.00 MW
0.00 MW
Siddirgonj GT 1,2
210.00 MW
0.00 MW
0.00 MW
96.00 MW
56.00 MW
64.00 MW
100.00 MW
90.00 MW
92.00 MW
50.00 MW
40.00 MW
46.00 MW
0.00 MW
0.00 MW
0.00 MW
412.00 MW
235.00 MW
417.00 MW
146.00 MW
108.00 MW
116.00 MW
Meghnaghat Summit
Siddirgonj 100 MW
Dutch Bangla 100 MW
DPA Power 50 MW
Gahamagar
48
Gazipur RPCL
52.00 MW
33.00 MW
32.00 MW
Tongi GT
105.00 MW
0.00 MW
0.00 MW
Chittagong
RaozanST(Gas):Unit-1
180.00 MW
120.00 MW
120.00 MW
Raozan 25MW
25.00 MW
26.00 MW
26.00 MW
Patenga 50 MW
50.00 MW
3.00 MW
14.00 MW
Chittagong
RaozanST(Gas):Unit-2
180.00 MW
0.00 MW
0.00 MW
Kaptai Hydro:Unit-1,2,3,4,5
220.00 MW
41.00 MW
106.00 MW
40.00 MW
0.00 MW
0.00 MW
150.00 MW
110.00 MW
120.00 MW
98.00 MW
23.00 MW
88.00 MW
0.00 MW
0.00 MW
0.00 MW
Dohazari Sangu
102.00 MW
34.00 MW
51.00 MW
Julda
100.00 MW
80.00 MW
102.00 MW
0.00 MW
0.00 MW
23.00 MW
Barabkunda (Regent)
22.00 MW
17.00 MW
17.00 MW
110.00 MW
40.00 MW
40.00 MW
b) Ashuganj ST 3
140.00 MW
140.00 MW
140.00 MW
Ashugonj ST 4
150.00 MW
140.00 MW
140.00 MW
Ashugonj ST 5
140.00 MW
80.00 MW
80.00 MW
c) Ashuganj CCPP-146MW
91.00 MW
40.00 MW
40.00 MW
d) Ashuganj 50 MW
51.00 MW
28.00 MW
25.00 MW
Ashuganj (Precision)
55.00 MW
51.00 MW
57.00 MW
Ashuganj (Aggreko)
80.00 MW
77.00 MW
82.00 MW
Ashugonj Up-53 MW
53.00 MW
53.00 MW
53.00 MW
Ashuganj Midland
51.00 MW
0.00 MW
0.00 MW
Brahmanbaria (Agrico)
(Gas)
70.00 MW
70.00 MW
72.00 MW
Daudkandi 50 MW
52.00 MW
0.00 MW
49.00 MW
163.00 MW
155.00 MW
0.00 MW
Feni (Doreen)
22.00 MW
17.00 MW
18.00 MW
11.00 MW
8.00 MW
5.00 MW
Shikalbaha ST
b) Shikalbaha Peaking (GT)
Hathazari
Shikalbaha(Energis)
Chandpur CCPP
49
Jangalia (Summit)
33.00 MW
32.00 MW
32.00 MW
25.00 MW
18.00 MW
21.00 MW
197.00 MW
146.00 MW
145.00 MW
Tangail (Doreen)
22.00 MW
15.00 MW
18.00 MW
90.00 MW
66.00 MW
68.00 MW
Fenchuganj CCPP-2(New)
104.00 MW
84.00 MW
82.00 MW
Fenchuganj (BEDL)
51.00 MW
42.00 MW
42.00 MW
Fenchuganj Prima 50 MW
50.00 MW
46.00 MW
50.00 MW
Hobiganj (Confidence-EP)
11.00 MW
10.00 MW
10.00 MW
Shajibazar GT Unit-8, 9
66.00 MW
63.00 MW
68.00 MW
Shajibazar 86 MW
86.00 MW
74.00 MW
74.00 MW
Shajibazar - 50 MW
50.00 MW
45.00 MW
47.00 MW
Sylhet 150MW
142.00 MW
0.00 MW
108.00 MW
Sylhet GT (Gas)
20.00 MW
17.00 MW
19.00 MW
Sylhet 50 MW
50.00 MW
41.00 MW
44.00 MW
Sylhet 11 MW
10.00 MW
7.00 MW
9.00 MW
Shahjahanulla 25mw
25.00 MW
14.00 MW
24.00 MW
Bheramara GT (Unit-1,2,3)
46.00 MW
32.00 MW
32.00 MW
105.00 MW
0.00 MW
0.00 MW
55.00 MW
0.00 MW
58.00 MW
500.00 MW
403.00 MW
304.00 MW
30.00 MW
0.00 MW
0.00 MW
KPC, Khulna
110.00 MW
53.00 MW
100.00 MW
115.00 MW
99.00 MW
99.00 MW
Khulna 150 MW
150.00 MW
156.00 MW
158.00 MW
54.00 MW
19.00 MW
45.00 MW
Gopalganj 110 MW
109.00 MW
0.00 MW
32.00 MW
Noapara (105MW)
Quantam
101.00 MW
0.00 MW
0.00 MW
Noapara (40MW),KZA
40.00 MW
40.00 MW
40.00 MW
Khulna 40 MW
40.00 MW
0.00 MW
0.00 MW
Khulna 55 MW
55.00 MW
42.00 MW
53.00 MW
0.00 MW
0.00 MW
0.00 MW
RPCL,CCPP, Mymensingh
Bheramara
a)Khulna ST 110 MW
HVDC C/B. Interconnector
b)Khulna ST 60MW
Faridpur
Barisal Diesel(HSD)
50
Barisal GT 1& 2
32.00 MW
15.00 MW
15.00 MW
Bhola Venture
33.00 MW
0.00 MW
0.00 MW
a)Baghabari GT 1
71.00 MW
67.00 MW
69.00 MW
b)Baghabari GT 2
100.00 MW
95.00 MW
100.00 MW
Baghabari 50 MW
52.00 MW
32.00 MW
32.00 MW
Baghabari Westmont
70.00 MW
0.00 MW
0.00 MW
Bera 70 MW
71.00 MW
67.00 MW
70.00 MW
Amnura 50 MW
50.00 MW
51.00 MW
50.00 MW
50.00 MW
50.00 MW
50.00 MW
Katakhali PPP 50 MW
50.00 MW
18.00 MW
46.00 MW
150.00 MW
75.00 MW
72.00 MW
Santahar 50MW
50.00 MW
46.00 MW
46.00 MW
Bogra GBB
22.00 MW
17.00 MW
21.00 MW
Rajlanka 52MW
52.00 MW
52.00 MW
52.00 MW
Barupukuria ST 1
100.00 MW
90.00 MW
90.00 MW
Barupukuria ST 2
100.00 MW
92.00 MW
93.00 MW
Bogra 20 MW
20.00 MW
9.00 MW
9.00 MW
Summit Powser(Ullapara)
11.00 MW
8.00 MW
10.00 MW
Rangpur GT (HSD)
20.00 MW
10.00 MW
17.00 MW
Syedpur GT 20MW(HSD)
20.00 MW
18.00 MW
18.00 MW
Thakurgaon 47 MW((RZ)
47.00 MW
31.00 MW
28.00 MW
9783.00 MW
6100.00 MW
6376.00 MW
Sirajganj 150 MW
Total
51
CHAPTER 4
TRANSMISSION SYSTEM OF BANGLADESH
4.1 TRANSMISSION SYSTEM
The system by which the electrical power transmitted from generating station to distribution
system is known as transmission system. The transmission line divided in two parts:
1. Primary transmission
2. Secondary transmission
4.2 PRIMARY TRANSMISSION
The electric power at 132 KV is transmitted by 3-phase 3-wire over head system to the outskirts
of the city. This form is the primary transmission.
4.2.1 GRID SYSTEM
The entire AC network is interconnected network called national grid. Even neighboring national
grid are interconnected to from sub grid. In power system when all generating station line with the
operation of substation called grid system of electric power.
In the grid system of Bangladesh power development board, mainly two types of transmission
lines are used. These are 230KV and 132KV lines. Also there is another grid line of Bangladesh
i.e. 66KV.
4.2.2 GRID SUB-STATION
As in Bangladesh there are two types of grid transmission line, one 132KV line and other 230KV
line. So we have mainly two categories grid substation. The total number of grid substation
operated as of 2012 is 95, of which13 number are 230KV and 82 numbers are 132KV. Capacity
of 230KV grid substation is 6675MVA and 132KV is 8587MVA and their transmission length are
2647.3 circuit km and 6071.34 circuit km
52
53
6. Solid earth or effective earth line: Connecting to the neutral point to earth without
intentional resistance or reactance co-efficient earthling.
7. Resonant earthing: Earthing through a reactance of such as value that power frequency
current in the neutral to ground connection almost equal opposite to power frequency
capacitance current between unsalted line and earth.
8. Co-efficient of ear thing: it is defined as the ratio of highest r.m.s voltage of healthy line to
earth to the line r.m.s voltage.
9. Petersen coil, suppression coil, ground fault neutralized: All the three terms have the same
meaning the adjustable reactor connected between neutral to earth.
10. Underground system: The system whose neutral point is not earth.
11. Earth fault factor: It is calculated at the selected point of the system for a given system. It
is a ratio of fault factor =V1/V2.
Where,
V1 = highest r.m.s phase to phase power frequency voltage of sound
phase during earth fault on another phase.
V2= r.m.s phase to phase power frequency voltage at the same
location with fault on the faulty removed.
12. Bus coupling transformer: it is a special kind of transformer using in electric power
transmission line. It is a bidirectional device that makes injection or taking electric power
between two buses. It is also a matching or interfacing transformer between two buses.
13. Bus: There are three kinds of buses in power system
a) PQ bus
b) PV bus and
For studying and analyzing an electric bus, we have to need for important variables.They are:
a) P-active power
b) Q-reactive power
c) V-voltage and
d) -swing angle
4.7
ADVANTAGES
AND
DISADVANTAGES
OF
HIGH
VOLTAGE
DC
TRANSMISSION
Advantages:
i. It requires only two conductors as compared to three for ac transmission.
ii. There is no inductance, capacitance, phase displacement and surge problem in dc
transmission.
iii. A dc transmission. Line has better voltage regulation as compared to the line for same load
and sending voltage.
iv. There is no skin effect in dc system.
v. A dc line requires less insulation as compared to ac line for the same working voltage.
vi. A dc line has less corona loss and interference with communication circuit.
vii. The high voltage dc transmission is free from the dielectric losses, particularly in the case
of cables and
viii. In dc transmission, there is no stability problem and synchronizing difficulties.
Disadvantages:
i. Electric power cannot be generated at high voltage dc due to commutation problems.
ii. The dc voltage cannot be stepped up for transmission of power at high voltages and
iii. The dc switches and circuit breaker have their own limitations.
4.8 TRANSMISSION SYSTEM OF DIFFERENT COUNTRIES
4.8.1 TRANSMISSION SYSTEM OF INDIA:
Bulk transmission system has increased to more than 165000 Circuit km today. The entire country
has been divided into five regions for transmission systems. Namely:
1. Northern region
2. North Eastern region
3. Eastern region
55
4. Southern region
5. Western region
Indias transmission system comprises a 400KV network as the main and bulk transmission
system at each region, 132KV and 110KV network as the main and support transmission systems
in each state, 66KV, 33KV and 22KV network as sub transmission system, frequent power cuts,
unscheduled shut downs and severe restrictions on industrial usage during summer months are
constraint on industrial development and overall economic development of the country. In this
context, POWERGRID is involved in along term plan for the development of an Indian national
transmission network to make efficient usage of generating capacity. As part of this strengthening
of the national grid, POWERGRID had developed series of high voltage direct current (HVDC)
inter regional links between North, East, South and westerns of Indias power system.
4.8.2 TRANSMISSION SYSTEM OF SRILANKA
Transmission voltage levels:
a) 220KV
b) 132KV
Transmission lines
220 KV----------------331km
132KV-----------------1684km
Grid substations
NO.
MVA
132/33KV
40
2570
220/132/33KV
2205
132/11KV
306
57
CHAPTER-5
MECHANICAL DESIGN OF OVERHEAD TRANSMISSION LINE
5.1 PROPERTIES OF CONDUCTOR MATERIALS
Conductors are those substances which easily allow the passage of electric current through them.
It is because there are a large number of free electrons available in a conductor. In terms of energy
band, the valence and conduction bands overlap each other.
potential difference across a conductor causes the free electrons to constitute electric current.
Thus, electrical behavior of conductors can be satisfactorily explained by the band energy theory
of materials. The conductor is one of the important items as most of the capital outlay is invested
for it. Therefore proper choice of material and size of the conductor is of considerable important.
The conductor material use for transmission and distribution of electric power should have the
following properties:
a) High electrical conductivity.
b) High tensile strength in order to withstand mechanical stresses.
c) Low cost so that it can be used for long distances.
d) Low specific gravity so that weight per unit volume is small.
5.2 CONDUCTORS MATERIALS
The most commonly used conductor materials for overhead lines are: a) Copper.
b) Aluminum.
c) Steel-cored aluminum.
d) Galvanized steel.
e) Cadmium copper.
In the early days of the transmission of electric power, conductors were usually copper, but
aluminum conductors have completely replace copper because of the much lower cost and lighter
weight of an aluminum conductor compared with a copper conductor of the same resistance. The
fact that an aluminum conductor has a larger diameter than a copper conductor of the same
resistance is also an advantage. With a larger diameter the lines of electric flux originating on the
conductor will be farther apart at the conductor surface.
58
But in our countries in overhead transmission line copper materials are used because it is an ideal
material for overhead lines owing to its high electric conductivity and greater tensile strength. It is
always use in the hard drawn form as standard copper has high current density. The current
carrying capacity of copper per unit of cross-section area is quite large.
5.3 TYPES OF CONDUCTOR
There are four type of aluminum conductors used in transmission and distribution line. Symbols
identifying different types of aluminum conductors are as follows: (i)
(ii)
(iii)
(iv)
59
60
61
the A or H type are often used to obtain a higher transverse strength than could be
economically provided by means of single poles.
2) Steel Tubular Pole: - It is use instead of wooden pole in urban area of town for increasing
vision satisfactory. It is also stronger than the wooden pole. Such poles are generally used for
distribution purpose in the cities. In BPDB steel tubular poles are used distribution system.
3) Reinforced Concrete (RCC) Poles: - RCC poles have greater mechanical strength, linger life
and permit longer spans than steed poles. They require little maintenance and have good
insulating properties. In BPDB, RCC poles are used in 11kV and 33kV transmission systems.
4) Steel Tower: - For long distance transmission at higher voltages, steel towers are invariably
employed. Steel towers have greater mechanical strength, longer life, can withstand most
severe climatic conditions and permit the use of linger spans. In BPDB, steel towers are used in
single circuit and double circuit transmission line. This has voltage about 132 kV and 230 kV.
62
1) Pin Type Insulators: Pin type insulators are used for transmission and distribution of electric
power at voltage up to 33 kV. Beyond operating voltage of 33 kV, the pin type insulators become
too bulky and hence uneconomical.
2) Suspension type insulators: - This type of insulator is not economical beyond 33 kV. For high
voltage transmission line suspension type insulator used. This type insulator consists of a number
of porcelain discs connected in series by metal links in the form of strength. The conductor is
suspended at the bottom end of this string while the other end of the string is secured to the crossarm of the tower. Each unit or disc is designed for V. The number of discs in series would
obviously depend upon the working voltage.
63
64
CHAPTER-6
ELECTRICAL DESIGN OF TRANSMISSION LINE
6.1 ELECTRICAL DESIGN ASPECTS
The electrical design involves the following aspects
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
Neutral grounding.
ix)
x)
Sub-station grounding.
xi)
xii)
Telephone interference.
xiii)
Radio interference.
xiv)
Television interference.
xv)
Audible noise.
An A.C. transmission line has resistance, inductance and capacitance uniformly distributed along
its length. These are known constants of parameters of transmission lines.
6.2 CONSTANT OF TRANSMISSION LINE
The transmission lines having distributed constants. These constant are:(a) Resistance.
(b) Inductance.
(c) Capacitance.
A transmission line has resistance, inductance & capacitance uniformly distributed along the
whole length of the line. Before we pass on to the methods of finding these constants for a
transmission line, it is profitable to understand then thoroughly.
65
(1) Resistance: It is the opposition of line conductors to current flow. The resistance is
distributed uniformly along the whole length of the line. The performance of a
transmission line can be analyzed conveniently if distributed resistance is considered as
lumped. The resistance R is given by,
R
Where,
= Length of conductor.
= Resistivity.
(2) Inductance: When an alternating current flows through a conductor, changing flux is set
up which links the conductor. Due to these flux linkages, the conductor possesses
inductance. Mathematically, inductance is defined as the flux linkages per ampere,
Inductance L
henrys
Where,
= flux linkages in Weber-turns
I = current in amperes
(3) Capacitance: We know that any two conductors separated by an insulating material constitute
a capacitor. As any two conductors of an overhead transmission line are separated by air which
acts as an insulation therefore, capacitance exists between any two overhead line conductors. The
capacitance between the conductors is the per unit potential difference,
Capacitance, C
q
v
farad.
Where,
q = charge in the line in coulomb.
v = potential difference between the
conductors in volts.
66
Calculation of Constants:
(1) Resistance: The variation of resistance of metallic conductors with temperature is practically
linear over the normal range of operation. Suppose R1and R2 are the resistance of a conductor
t10C and t20C (t2 t1) respectively. It 1 is the temperature coefficient at t10C then,
R2 = R1 [1+ 1 (t2-t1)]
Where 1 =
0
1 0 t1
0 = temperature co-efficient at 0 0 C
a) In a single phase or 2 wire D.C lines, the total resistance is equal to double the
resistance of either conductor.
b) In case of a 3-phase transmission, resistance per phase is the resistance of one
conductor.
(2) Inductance:
(a) Equilateral Spacing: - Inductance of three phase lines with equilateral spacing. If we assume
balanced 3-phase phasor currents,
c
Ia + Ib + Ic = 0
D
a
a 2 10 7 I a ln
1
1
1
I b ln I c ln wb T m
Ds
D
D
67
a 2 10 7 I a ln
2 10 7 I a ln
1
1
I a ln wb T m
Ds
D
D
wb T m
Ds
D
H m
Ds
Therefore, La 2 10 7 ln
(b) Unsymmetrical: The calculation of inductance of three phase lines shown in figure with
unsymmetrical spacing. Assume that there is no neutral wire,
Ia + Ib + Ic = 0
Unsymmetrical spacing causes the flux linkages and therefore the inductance of each phase to be
different resulting in unbalanced receiving-end voltages even when sending-end voltages and line
currents are balanced. So there are introducing a problem. To remove these problem transposition
(i.e- Exchange the position of the conductors) process is apply. This is shown in figure
D12
a
Position
b
D23
D31
2
3
Section-1
Section-2
Section-3
(inductance).
(inductance).
To find the average inductance of each conductor of a transposed line, the flux linkages of the
conductor are found for each position.
For the first section,
a1 2 10 7 I a ln
1
1
1
wb T m
I
ln
I
ln
b
c
D12
D31
ra'
68
a 2 2 10 7 I a ln
1
1
1
wb T m
I b ln
I c ln
'
D23
D12
ra
a 3 2 10 7 I a ln
1
1
1
wb T m
I b ln
I c ln
'
D13
D23
ra
a1 a 2 a 3
3
1
1
1
I
ln
= 2 10 7 I a ln ' I b ln
c
13
13
r
D
D
D
D
D
D
a
12 23 31
12 23 31
But, I b I c I a , hence
a 2 10 I a ln
7
13
Then
La 2 10 7 ln
Deq
ra'
2 10 7 ln
Deq
Ds
H m
This is the same relation where Dm = Deq the mutual GMD between the three phase conductors. If
ra = rb = rc , we have
La = Lb = Lc
(3) Capacitance: (a) Equilateral Spacing: - Three phase line composed of three identical conductors of radius r
placed in equilateral configuration,
c
D
a
69
Vab
1
2k
D
r
D
q a ln r qb ln D q c ln D
Vac
1
2k
D
D
r
q a ln r qb ln D q c ln D
1
2k
D
r
2
q
ln
q
ln
a
b
c
r
D
3q a D
ln
2k
r
With balanced three phase voltages applied to the line, it follows from the phasor diagram.
Vab + Vac = 3Van.
So, we have
Van
qa
D
ln
2k
r
qa
2k
Van ln D r
(a) Unsymmetrical Spacing: - Assume that the line is fully transposed. So the conductors are
rotated cyclically in the three section of the transposition cycle.
For the first section of the transposition cycle,
b
D12
a
D23
D31
Vab1
D
D
1
r
q a1 ln 12 qb1 ln
qc1 ln 23
2k
r
D12
D31
D
D
1
r
q a 2 ln 23 qb 2 ln
qc 2 ln 31
2k
r
D23
D12
70
D
D
1
r
q a 3 ln 31 qb3 ln
qc 3 ln 12
2k
r
D31
D23
1
Vab1 Vab 2 Vab3
3
Vab
q
ln
q
ln
q a ln
b
c
D D D
6k
D
D
D
r3
12 23 31
12 23 31
=
Deq
1
r
q a ln
qb ln
2k
r
Deq
Where,
13
Similarly, Vac
Deq
1
r
q a ln
qc ln
2k
r
Deq
Vab Vac
Deq
1
r
qb qc ln
q a ln
2k
r
Deq
Deq
qa
ln
2k
r
The capacitance of line to neutral of the transposed line is then given by,
Cn
2k
F m to neutral
ln Deq r
71
IS
IR
VS
VR
B VR
D
I R
And AD BC = 1 be an identity.
(a) Short Transmission Line: The lengths of these lines are less than 100km. Only for resistance & inductance are the effective
parameters. Capacitance is very negligible.
IR
IS
Z=R+jX
VS
ZL
VR
72
Here,
Vs = VR + ZIR, Is= IR.
So the matrix,
Vs
1
I 0
Z VR
1 I R
IR
IS
Z=R+jX
VS
IC
Y
ZL
VR
VS 1 YZ
I Y
S
Z
1
VR A
I C
R
B
D
VR
I
R
73
1. Nominal T Representation:
Z/2
Is
Z/2
IR
IC
VR
VS
Load
VS 1 YZ
I Y
S
Z 1 YZ 4
1 YZ 2
VR A B
I C D
VR
I
R
AB DC = 1 be the identity.
2. Nominal Representation:
In this method total capacitance is divided into two equal parts which are lumped at the shedding
and receiving end resulting in the nominal representation as shown in fig.
Is
IL
Ic
Vs
Y/2
IR
Ic
Y/2
Load
VR
74
I
Y 1 YZ 2
1 YZ 2
Z
VR
I
R
IS
Zdx
IR
IX
ZL
VS
dx
VR
x
L
2 = YZ then,
D2Vx/dx2 Vx = 0.
The general solution is,
75
yx
x
Vx = C1e C 2 e ...(4)
Where Zc=(Z/Y)1/2 ]
The constant C1 & C2 may be evaluated by using the end conditions.i.e, when x = 0, Vx = VR &
Ix = IR. Substituting these values in equation (4) & (5) gives
VR = C1 + C2
IR = 1/ZC (C1 - C2)
Which upon solving yield;
C1 = (VR + ZCIR)
C2 = (VR -_ZCIR)
Substituting C1& C2 on (4) & (5)
VX = {(VR + ZCIR) /2}eYX + {(VR - ZCIR ) /2}e-YX
IX = {(VR/ZC + IR) 2}eYX {(VR/ZC - IR ) /2}e-YX
These can be written after introducing hyperbolic function as,
VX = VRcoshYx + IRZCsinhYx
IX = IRcoshYx + VR (1/ZC)sinhYx
The matrix,
coshYX
VX
I 1 Z sinh Y
C
X
X
Z C sinh YX VR
coshYX I R
Here, A = D = coshYx
B = ZC sinhYx
C = (1/ZC) sinhYx
The identity be the AD BC = 1
If X = L, then VX = Vs, IX = IS
6.4
a.
400 KV
b.
230 KV
c.
132 KV
d.
66 KV
e.
33 KV
76
a. Radio interference
b. Line insulation
c. Equipment insulation
6.7 PROTECTION SYSTEM OF TRANSMISSION LINE
There are several instances when the elements of power system ( i.e. generator, transformer
lines, insulator etc.) are subjected to over voltage. The over voltage on the power system may be
caused due to many reasons such as lightning, the opening of a circuit breaker, the grounding of a
conductor etc. An appreciable number of this over voltage are of sufficient magnitude to ease
insulation break down of the equipment in the power system. The protective devices use to these
problems minimized.
6.8 PROTECTION COMPONENTS
There are many components which are use in protection of high voltage overhead transmission
line. These are following: Circuit Breaker (CB).
Relay.
Fuse.
Lightning Arrester.
Isolator.
78
Sl.
No.
Name of Lines
Lenth in Route
kilometers
Lenth in
Ckt.
Conductor
No. of Ckt.
kilometers
Name
Size
178
356
Double
Mallard
795 MCM
Tongi - Ghorasal
27
54
Double
Mallard
795 MCM
Ghorasal - Ashuganj
44
88
Double
Mallard
795 MCM
Raojan - Hathazari
22.5
45
Double
79
158
Double
Finch
1113 MCM
Ghorasal - Rampura
50
100
Double
Twin Mallard
2x795 MCM
Rampura - Haripur
28
56
Double
Twin Mallard
2x795 MCM
Haripur - Meghnaghat
12.5
25
Double
Twin Mallard
2x795 MCM
Meghnaghat - Hasnabad
26
52
Double
Twin Mallard
2x795 MCM
10
150
300
Double
Finch
1113 MCM
11
2.4
4.8
Double
Finch
1113 MCM
12
58
116
Double
Twin Mallard
2x795 MCM
13
46.5
93
Double
Twin AAAC
37/4.176 mm.
14
1.5
1.5
Single
ACSR
15
286
Double
Twin AAAC
37/4.176 mm.
16
Khulna - Ishurdi
185
370
Double
Twin AAAC
37/4.176 mm.
17
Bogra-Barapukuria
106
212
Double
Twin AAAC
37/4.176 mm.
18
Sirajganj-Bogra
72
144
Double
Twin AAAC
37/4.176 mm.
19
Ishurdi-Baghabari
55
110
Double
Twin AAAC
37/4.176 mm.
20
Baghabari-Sirajganj
38
76
Double
Twin AAAC
37/4.176 mm.
Total
1324.4
2647.3
79
Lenth in
Name of Lines
Route
kilometers
Conductor
LenthinCkt. No. of
kilometers Ckt.
Name
Size
01 Siddhirganj - Shahjibazar
138
276
Double Grosbeak
636 MCM
02 Shahjibazar - Chatak
150
300
Double Grosbeak
636 MCM
03 Siddhirganj - Kaptai
273
546
Double Grosbeak
636 MCM
04 Kulshi - Halishahar
13
26
Double Grosbeak
636 MCM
61
122
Double
16
32
Double Grosbeak
636 MCM
07 Ashuganj - Jamalpur
166
332
Double Grosbeak
636 MCM
08 Madanhat - Sikalbaha
13
26
Double Grosbeak
636 MCM
09 Sikalbaha - Dohazari
35
70
Double Grosbeak
636 MCM
10 Sikalbaha - Halishahar
13
13
Single
804 sq.mm
11 Kulshi - Baraulia
13
26
Double Grosbeak
636 MCM
12 Madanhat - Kulshi
13
13
Single
Grosbeak
636 MCM
13 Madanhat - Kulshi
13
13
Single
Grosbeak
636 MCM
14 Kaptai - Baraulia
58
116
Double Grosbeak
636 MCM
87
174
Double Grosbeak
636 MCM
16 Feni - Chowmuhani
32
64
Double Grosbeak
636 MCM
Single
Grosbeak
636 MCM
18 Mymensingh - Netrokona
34
68
Double Grosbeak
636 MCM
19 Goalpara - Ishurdi
169
338
Double AAAC
804 MCM
20 Ishurdi - Bogra
103
206
Double AAAC
804 MCM
21 Bogra - Saidpur
140
280
Double AAAC
804 MCM
22 Saidpur - Thakurgaon
64
128
Double AAAC
804 MCM
23 Goalpara - Bagerhat
45
45
Single
AAAC
804 MCM
80
80
Single
HAWK
477 MCM
25 Bagerhat - Mangla
31
31
Single
HAWK
477 MCM
26 Barisal - Patuakhali
37
37
Single
Grosbeak
636 MCM
225
450
Double HAWK
477 MCM
28 Rajshahi - Natore
40
40
Single
HAWK
477 MCM
57
57
Single
HAWK
477 MCM
Linnet +
(336.4 + 636)
Grosbeak
MCM
AAAC
80
56
56
Single
Grosbeak
636 MCM
100
200
Double Grosbeak
636 MCM
32 Rajshahi - Nawabganj
47
94
Double Grosbeak
636 MCM
33 Rangpur - Lalmonirhat
38
38
Single
Grosbeak
636 MCM
34 Bogra - Noagaon
52
104
Double Grosbeak
636 MCM
35 Kabirpur - Tangail
51
102
Double Grosbeak
636 MCM
98
Double Grosbeak
636 MCM
40
80
Double Grosbeak
636 MCM
38 Siddhirganj - Ullon
16
32
Double Grosbeak
636 MCM
39 Siddhirganj - Maniknagar
10
10
Single
Grosbeak
636 MCM
56
112
Double Grosbeak
636 MCM
23
46
Double Grosbeak
636 MCM
42 Ghorasal - Joydebpur
26
52
Double Grosbeak
636 MCM
43 Baghabari - Shahjadpur
14
Double Grosbeak
636 MCM
44 Chandpur - Chowmuhani
75
150
Double Grosbeak
636 MCM
45 Barapukuria-Rangpur
45
90
Double Grosbeak
636 MCM
46 Barapukuria-Saidpur
36
72
Double Grosbeak
636 MCM
47 Madaripur-Gopalganj
45
45
Single
804 MCM
48 Khulna(C)-Khulna(S)
18
49 Khulna(S)-Satkhira
56
56
Single
AAAC
804 MCM
50 Rajshahi - Natore
40
40
Single
Grosbeak
636 MCM
3.3
6.6
Double XLPE
800 sq.mm
52 Sikalbaha-Bakulia
Double Grosbeak
636 MCM
53 Julda-Shahmirpur
14
Double Grosbeak
636 MCM
54 Kulshi-Bakulia
15
30
Double Grosbeak
636 MCM
55 Joydebpur-Kabirpur
15
30
Double Grosbeak
636 MCM
56 Sikalbaha-Shahmirpur
18
Double Grosbeak
636 MCM
13
Single
636 MCM
53
Single
Grosbeak
636 MCM
4.2
8.4
Double Grosbeak
636 MCM
61 Noagaon-Niamotpur
46
46
Single
804 MCM
62 Aminbazar-Savar
15.8
31.6
Double Grosbeak
AAAC
Grosbeak
AAAC
636 MCM
81
63 Jhenaidah-Magura
26
26
Single
Grosbeak
636 MCM
64 Jhenaidah-Chuadanga
39
39
Single
Grosbeak
636 MCM
65 Naogaon-Joypurhat
46
46
Single
Grosbeak
636 MCM
66 Thakurgoan-Panchagor
45
45
Single
AAAC
636 MCM
10
Double Grosbeak
636 MCM
68
2.4
2.4
sinlge
Grosbeak
636 MCM
11.1
44.4
Four
Grosbeak
636 MCM
10.26
41.04
Four
AAAC
636 MCM
19.5
78
Four
AAAC
636 MCM
2.4
2.4
single
73 Noapara PP to Noapara Ss
1.6
1.6
single
74 Daudkandi PP to Daudkandi ss
1.2
1.2
single
75 Gopalganj PP to Gopalganj ss
1.2
1.2
single
2.5
single
single
4.5
4.5
single
79 Amnura pp to Rajshahi-chapai
12.5
12.5
single
7.5
30
single
3424.96
6071.34
69
70
71
77
80
In-out of Hasnabad-kallayanpur
line to keraniganj pp
Total
Project cost:
Financed by:
ADB
Contractor Name:
Financial:
Status
Physical:
Contract sign on
Completion date
2010-2011
82
6.9.2 Hasnabad & Tongi 230 kV and Kalyanpur 132 kV S/s Construction
(Hasnabad-Aminbazar-Tongi & Haripur-Me
Objective:
Project cost:
Financed by:
ADB
Contractor Name:
Physical:
100%
Financial:
100%
Contract sign on
08/24/2003
Completion date
05/23/2005
Status
Financed by:
DANIDA Mixed
Credit
Contractor Name:
JV of MT Hoggard &
Lindpro, Denmark
Physical:
100%
Financial:
100%
Contract sign on
01/11/2005
Completion date
01/10/2007
Status
Contractor Name:
Physical:
100%
Financial:
100%
Contract sign on
06/30/2003
Completion date
03/29/2005
Financed by:
Status
83
Objective:
Project cost:
Financed by:
Contractor Name:
2% up to February'2014
Financial:1.25% up to
February'2014
Status
Physical:
Project Completion
Year:
Contract sign on
July'13-June'2017
Project cost:
Financed by:
Contractor Name:
14.33 % up to
February'2014
Financial:1050.60(Lac
Taka)
Status
Physical:
Contract sign on
Project Completion
June' 2015
Project cost:
Financed by:
ADB
Contractor Name:
98.78 % up to
Financial:39463.41(Lac
Status
Physical:
84
February'2014
Taka)
Project Completion
Year
Contract sign on
June'2014 (Revised)
Financed by:
Contractor Name:
99.99 % up to
February'2014
Financial:70213.22(Lac
Taka)
Status
Physical:
Project Completion
Year
Contract sign on
June'2014(Revised)
Project cost:
Financed by:
ADB
Contractor Name:
97.65 % up to
February'2014
Financial:59620.21(Lac
Taka)
Status
Physical:
Project Completion
Year
Contract sign on
June'2014 (Revised)
Project cost:
Financed by:
kfW, Germany
Contractor Name:
92% up to February'2014
Financial:12528.92(Lac
Taka)
Status
Physical:
Contract sign on
Project Completion
Year
June'2014 (Revised)
85
Project cost:
Financed by:
World Bank
Contractor Name:
98.04% up to
February'2014
Financial:23375.48(Lac
Taka)
Status
Physical:
Project Completion
Year
Contract sign on
June'2014 (Revised)
Project cost:
Financed by:
ADB
Contractor Name:
8.50% up to
February'2014
Financial:
Status
Physical:
Contract sign on
Project cost:
Financed by:
JICA
Contractor Name:
11.59% up to December
2013
Financial:
Status
Physical:
Project Completion
Year:
Contract sign on
Jan'13-June'2017
Project cost:
Financed by:
Contractor Name:
56.80% up to
February'2014
Financial:23403.60(Lac
Taka)
Status
Physical:
Contract sign on
Completion date
June' 2014
Project cost:
Financed by:
ADB
Contractor Name:
99.30 % up to
February'2014
Financial:124869.55(Lac
Taka)
Status
Physical:
Contract sign on
6.9.16 Two new 132/33 kV substations at Kulaura & Sherpur with interconnecting
lines.
Objective:
Project cost:
Financed by:
Contractor Name:
83.70 % up to
February'2014
Financial:10540.54(Lac
Taka)
Status
Physical:
87
Project Completion
Year:
Contract sign on
Feb 2014
Project cost:
Financed by:
Contractor Name:
60.25% up to
February'2014
Financial:62190.44(Lac
Taka)
Status
Physical:
Contract sign on
Completion date
Dec'2014 (Revised)
6.9.18 Haripur 360 MW Combined Cycle Power Plant and Associated Substation (PGCB
Part)
Objective:
Project cost:
Financed by:
JICA
Contractor Name:
99.76% up to
February'2014
Financial:17143.44(Lac
Taka)
Status
Physical:
Contract sign on
Project Completion
Year
June'2014 Revised
(a) Copper Losses: One type of copper loss is I2R loss. In transmission lines the resistance of the
conductors is never equal to zero. Whenever current flows through one of these conductors, some
energy is dissipated in the form of heat. This heat loss is a power loss. With copper braid, which
has a resistance higher than solid tubing, this power loss is higher. Another type of copper loss is
due to skin effect. Since resistance is inversely proportional to the cross-sectional area, the
resistance will increase as the frequency is increased. Also, since power loss increases as
resistance increases, power losses increase with an increase in frequency because of skin effect.
These losses can be minimized and conductivity increased in an transmission line by plating the
line with silver. Since silver is a better conductor than copper, most of the current will flow
through the silver layer. The tubing then serves primarily as a mechanical support.
(b) Dielectric Losses: These Losses result from the heating effect on the dielectric material
between the conductors. Power from the source is used in heating the dielectric. The heat
produced is dissipated into the surrounding medium. When there is no potential difference
between two conductors, the atoms in the dielectric material between them are normal and the
orbits of the electrons are circular. When there is a potential difference between two conductors,
the orbits of the electrons change. The excessive negative charge on one conductor repels
electrons on the dielectric toward the positive conductor and thus distorts the orbits of the
electrons. A change in the path of electrons requires more energy, introducing a power loss. The
atomic structure of rubber is more difficult to distort than the structure of some other dielectric
materials. The atoms of materials, such as polyethylene, distort easily. Therefore, polyethylene is
often used as a dielectric because less power is consumed when its electron orbits are distorted.
(c) Radiation and Induction Losses: These losses are similar in that both are caused by the
fields surrounding the conductors. Induction losses occur when the electromagnetic field about a
conductor cuts through any nearby metallic object and a current is induced in that object. As a
result, power is dissipated in the object and is lost. Radiation losses occur because some magnetic
lines of force about a conductor do not return to the conductor when the cycle alternates. These
lines of force are projected into space as radiation and these results in power losses. That is, power
is supplied by the source, but is not available to the load.
6.10.2 SKIN EFFECT
The tendency of alternating current to concentrate near surface of a conductor is known as skin
effect.
89
2)
3)
4)
90
CHAPTER-7
DISTRIBUTION SYSTEM
7.1 Definition of sub-station
The assembly of apparatus used to change some characteristic (e.g. voltage, ac to dc,
frequency, p.f. etc) is called the sub-station.
7.2 Importance of Substation
Substation is an important part of power system. The continuity of supply depends to a
considerable extent upon the successful operation of sub-station. It is therefore essential to
exercise utmost care while designing and building substation. The following parts are
important point which must be kept in view while laying out a substation.
1. It should be located at a proper site as far as possible it should be at the center of load.
2. It should be easily operated and maintenance.
3. It should involve minimum capital cost.
7.3 Equipments of substation
(1) Transformer
(2) CT,PT
(3) Bus bar
(4) Isolator
(5) Protective fuse
(6) Main switch
(7) Incoming feeder
(8) Outgoing feeder
(9) Energy meter
(10) P.F meter
(11) Maintenance tools
(12) Bus bar chamber
7.4 Classification of substation
According to constructional feature the substation are classified as:
1. Indoor substation.
2. Out door substation.
3. Underground substation.
4. Pole mounted substation.
91
1. Indoor substation
For voltage up to 11kv the equipment of the substation is installed indoor because of
economic consideration .However when the atmosphere is contain with impurities these
substation can be erected for voltage unto 66kv .
Advantage:
a. Less space is required.
b. Operation is easier than outdoor substation.
Disadvantage:
a. Future extension is difficult.
b. Capital cost is high.
c. More possibility of escalation.
2. Outdoor substation
For voltage beyond 66kv ,equipment is invariably installed out door .It is because for such
voltage the clearance between conductor and the space required for switch , circuit breaker and
equipment becomes so great it is not economical to install the equipment indoor
Advantages:
a. Easy to future extension.
b. Low capital cost.
c. Easy to fault location.
Disadvantage:
a. More space is required.
b. Operation is difficult.
3. Polemounted substation
This is an outdoor subs station with equipment installs over head on H-pole or 4-pole structure. It
is cheapest from of substation for over voltage not exceeding 11KV (or 33 KV in the some case.
Electric power is almost distributed in localities through such substation. For complete discussion
on pole mounted substation.
7.5 Definition of different equipments used in the distribution sub-station
92
7.5.1. Transformer
A transformer is a static device that transfer the electrical energy from one circuit to another
circuit at a constant frequency on the basis of mutual induction between two circuits linked by a
common magnetic flux
currents (about 5A). Therefore, they will not work satisfactorily if mounted directly on the power
lines. The function of these instrument transformers is to transfer voltages or currents in the power
lines to values which are convenient for the operation of measuring instruments and relays.
There are two types of instrument transformer as followes:
A)
B)
Fig:7.3 Isolator.
94
95
.
Fig: 7.5 Pin type insulator.
b) Suspension type insulators
For high voltage i.e. beyond 33KV transmission line, Suspension type insulators used. This type
insulator consists of a number of porcelain discs connected in series by the metal links in the form
of strength. The conductor is suspended at the bottom end of this string while the other end of the
string is secured to the cross-arm of the tower. Each unit or discs is designed for 11KV. The
number of discs in series would obviously depend upon the working voltage.
96
c) Strain insulators
When there is a dead end of the line or there is corner or sharp curve, the line is subjected to
greater tension. In order to relieve the line of excessive tension, strain insulators are used. For low
voltage lines shackle insulators are used as strain insulators. For high voltage transmission lines,
strain insulator consists of an assemble of suspension insulators.
The discs of strain insulators are used in vertical plane.
2.
3.
4.
2.
3.
4.
97
C
CB
CB
Isolator
Isolator
Single bus
CB
CB
Transformer
Transformer
98
CB
CB
CB
CB
Isolators
CB
CB
CB
CB
CB
Trip coil
C.T.
moving
Open
Close
Handle automatic
mechanism for
Fixed contact
opening and closing
the C.B.
Fig: 7.10 Basic operation of circuit breaker
The figure represents an elementary schematic diagram of CB. It consists of fixed contact and a
sliding contact in to which mores a moving contact. The end of the moving contact is attached to a
handle which can be manually or it can be operate automatically with the help of a mechanism
which has trip coil energized by the secondary of the current Transformer generally called current
transformer. The power supply is brought to the terminals the emf induced of the C.B. Under
normal working condition the emf induced in the secondary winding of CT is not sufficient to
energize the trip coil fully for the operation. But under fault condition the abnormally high value
of current on the primary circuit of CT induced a sufficient emf in the secondary circuit to
energized the trip coil so as to recluse the handle mechanism which open the CB.
Operation:
Under normal operating conditions, the fixed and moving contacts remain closed and the breaker
carries the normal circuit current. When a fault occurs, the moving contacts are pulled down by
the protective system and an arc is struck which vaporizes the oil mainly into hydrogen gas.
de
101
2.
3.
4.
5.
6.
102
which are ineffective as charge carriers. The result is that the medium between the contacts
quickly builds up high dielectric strength and cause the
The possibility to obtain the highest performances, up to 63 KA, with a reduced number of
interrupting chambers.
2.
3.
4.
5.
103
Rating
1250A
1250A
1250A,
630A,
800A,400A
630A,36KV,C.T(200:5)
630A
36KV
10MVA,33/11KV
668A
600:5,300:5,1000:5A
33/.10KV
33/.4KV,200KVA
1.Isolator (33KV)
2. Isolator(11KV)
3.SF6 CB (33KV)
4.Oil circuit breaker(33KV)
5. Vacuum circuit Breaker
6.ACR (33KV)
7. ACR (11KV)
8. Lightning Arrestor
9. Power transformer
10.Voltage regulator
11.Curent transformer (CT)
12.potential transformer(PT)
13. Station Transformer
14. 33KV sectional bus bar
15.11KV Bus bar
16.Incoming feeder( 33kv)
17.Out going feeder(11kv)
18.Insolator
19.Control Panel
Current
Voltage
Time
Oil circuit
Normal
Capacity Voltage=36
Braking time=5 c
breaker
Current=630 A
KV
Opening
Frequency= 50
Breaking
Restriking voltage=
time=0.045 sec
Hz
Current=25 KA
0.57kv/s
Closing time=0.15
Wieght= 400 kg
Making
Impulse withstand
sec
Current=62.5 KA
voltage=170kv
104
Current
Voltage
Normal Current=1200 A
Capacity Voltage=36 KV
Frequency= 50 Hz
Breaking Current=26.4
Weight= 400 kg
KA
Impulse withstand
Making Current=66 KA
voltage=170kv
Current
Voltage
Time
Vacuum circuit
Normal
Rated Voltage=12 KV
breaker
Current=400 A
3 sec
Frequency= 50 Hz
Breaking
V(dc)
Weight= 400 kg
Current=20 KA
Impulse withstand
voltage=75 kv
Voltage
Primary voltage 33 KV
Weight
Weight of oil 5300 Kg
Weight of core12102 Kg
Voltage
Weight
Primary Voltage=33Kv
105
Voltage
Weight
Primary voltage 33 KV
Voltage
Primary Voltage=66 Kv
Weight
Weight of oil= 882 Kg
Secondary Voltage=11 KV
Range of regulation= 10%
V
(KVAR)
(KVA)
107
CHAPTER-8
FUTURE PLAN
8.1 POWER GENERATION PLAN UP TO 2017
8.2 INDIA-BANGLADESH TRANSMISSION LINK
Objective:
(i) To Facilitate exchange of electricity between Bangladesh& India.
(ii) To establish a Grid interconnection with india.
(iii) To minimize the power crisis in Bangladesh to some extent.
Scope of Work: (i) Construction of 30 km 400kv double circuit ac transmission line
(ii) 400 kv Back-to-Back HVDC station at Bheramara
Developers: Power Grid Corporation of India Limited, India and Power Development Board,
Bangladesh.
ProjectCost: Local 35.71 M US$, Foreign 107.14 M US$
Financed by: ADB
Physical: 21% upto Nov 2011
Financial: 23318.45 Lac taka
Agreements:
i) In July 2010, BPDB signed a 35-year power transmission agreement with Power Grid
Corporation of India Limited (PGCIL) to import 250 MW of electricity from India.
Under the agreement, Bangladesh can begin the import of electricity from late 2012.
ii) In October 2010, Bangladesh and ADB signed the USD100 million loan deal for
interconnection.
8.3 400KV TRANSMISSION LINE
Frequent power cuts, unscheduled shutdowns and severe restriction on industrial usage during
summer months are a constraint on industrial development and overall economic development. In
this context, power grid is involved in a long term plan for the development of a Bangladeshi
national transmission network to make efficient usage of generating capacity. As part of this
strengthening of the national grid, PGCB is going to construct Bibiyana-Kaliakoir 400 KV and
Fenchuganj-Bibiyana 230KV Transmission Line.
108
Financial
109
CHAPTER-9
DISCUSSION AND CONCLUSION
The electrical energy has a vital rule in the development of civilization. There has been a
universal basic drive towards better living through expended utilization of energy. The
advancement of a country is measured in terms of capital consumption of electrical energy. The
study of generation and transmission system is
development board (BPDB) evolved on May 1,1972 as an integrated utility with responsibility of
power generation, transmission and distribution. BPDB supplies electrical power through
transmission and distribution system to the consumers of Bangladesh.
In this paper we have studied the electrical power a generation and transmission system of
Bangladesh. For the proper thesis work we have been studied the different type of electric power
generation system and transmission line. The major part of the power generation in Bangladesh is
generated by mainly two types of generation plants these are steam power plants and gas turbine
power plants. Most of these power plants are open loop type, so the efficiency of these plants is
low. If these two types of plants are used as a closed loop type the efficiency will increase up to
52.6%. So Bangladesh government should take proper steps (if possible) to combine these plants
as close loop type to increase the generating capacity by using the same resources.
In this thesis we have discussed about mechanical part of transmission system, which was consist
of various types of conductors, line supports, insulators, and also
transmission system including the existing (230 KV, 132 KV, 66 KV) transmission system in
Bangladesh. Among this transmission system 230 KV lines was more economical because it
reduced power loss and conductor size. Also 400KV transmission lines are in under construction.
We expect our thesis will be very helpful for better understanding about electrical power
generations and transmission system in Bangladesh
110
REFERENCES
[1]
[2]
[3]
[4]
[5]
Web Sites:
i) www.bpdb.gov.bd
ii) www.pgcb.org.bd
111