Professional Documents
Culture Documents
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 1 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Copyright 2010
REVISION NOTICE:
DATE
EXPLANATION
November 2008
New Document
December 2011
ETSA Utilities
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 2 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
CONTENTS
1.0
PURPOSE................................................................................. 6
2.0
SCOPE .................................................................................... 6
3.0
4.0
REFERENCES ........................................................................... 7
5.0
DEFINITIONS ........................................................................... 9
6.0
7.0
8.0
6.1
6.2
6.3
7.2
7.2.2
7.2.3
Ventilation ....................................................................... 14
7.2.4
7.3
7.4
7.5
COSTS ............................................................................. 15
8.2
8.3
8.3.2
8.3.3
8.3.4
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 3 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.0
8.4
HAZARDOUS LOCATIONS..................................................... 18
8.5
8.6
NOISE .............................................................................. 18
GENERAL.......................................................................... 19
9.2
9.3
9.3.2
9.3.3
9.3.4
Methods ........................................................................... 20
9.4
9.5
FLOORS ............................................................................ 20
9.6
VENTILATION ..................................................................... 21
9.7
9.8
9.9
9.6.1
9.6.2
9.6.3
9.6.4
FIRE ................................................................................. 23
9.7.1
9.7.2
9.7.3
General ............................................................................ 23
9.8.2
Buried Conduit:............................................... 24
9.8.2.2
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 4 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
8.3.5
10.0
11.0
9.10
9.11
ADDITIONAL REQUIREMENTS................................................. 26
10.2
APPROVAL ....................................................................... 27
10.3
INSTALLATIONS .................................................................. 27
10.4
INSPECTIONS ..................................................................... 27
11.2
EARTHS ............................................................................ 28
11.3
11.4
INSPECTIONS ..................................................................... 29
11.5
11.6
12.0
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 5 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
1.0
PURPOSE
This Technical Standard specifies the standard distribution equipment and
transformer rooms location, land tenure, access, construction and provision of
permanent supply requirements for a new or upgraded installation that will be
a component of ETSA Utilities distribution network.
It will assist ETSA Utilities customers/landowners (i.e. the registered proprietors of
land) in the planning of a development once it is established that a distribution
equipment and transformer room will be required within the customers/
landowners building or in a separate building on the property in order to meet
the electricity supply requirements.
Furthermore it will assist in clarifying the customers/landowners responsibilities,
agreements, approvals, construction and certificate of compliance process.
Appendix-A for this document provides compliance form check list that will
provide guidelines in carrying out duties in safe, reliable and cost effective way
with the activities associated with distribution equipment and transformer
rooms.
2.0
SCOPE
The specification in this technical standard is applicable (but not limited) for the
distribution transformers which are nominally 33kV/0.4kV or 11kV/0.4kV and with
a capacity of 2MVA or less. The construction of a transformer room is principally
governed by the requirements of the Electricity (General) Regulations 1997,
other statutory authority requirements and the Building Code of Australia.
Timely advice enables ETSA Utilities to outline the transformer room and
underground cable requirements, to assess the impact of the development on
the distribution system and to plan any associated work so that supply can be
made by the required date. The construction of the transformer room and
compliance to the technical standard is the customer/landowners (i.e. the
registered proprietors of land) responsibility.
For further assistance/information concerning this technical standard, please
contact the relevant ETSA Utilities Manager. This technical standard is available
at the ETSA Utilities websites below:
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 6 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
3.0
GRACE PERIOD
The maximum grace period acceptable by ETSA Utilities for implementing this
Standard is 3 months from the date of publication. Any new design submitted
for a Single Customer installation must reflect this current Standard immediately.
All projects that are not in receipt of Specification Compliance at the revised
date of issue for this technical standard will need to incorporate the latest
requirements. This is applicable to both the design and construction phases of
the project.
The validity period for a Specification Compliance is 60 days. On the expiry of
a Specification Compliance, any specification change without a
documented exemption must be incorporated into the design and
construction of ETSA Utilities infrastructure.
4.0
REFERENCES
The following listed documents are for additional information. It is advisable to
refer to the current publications before implementing them. Other
documentation may be required on a project specific basis.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 7 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
General Requirements
AS 2067 - Substations and High Voltage Installations exceeding 1 kV A.C.
AS/NZS 2648.1 - Underground Marking Tape - Non-Detectable Tape
AS 2885.1 - Pipelines - Gas and Liquid Petroleum - Design and Construction
AS/NZS 3000 - Electrical Installations (known as the Australian/New Zealand
Wiring Rules)
AS/NZS 3500 (Set) - Plumbing and Drainage Set
AS 3798 - Guidelines on earthworks for commercial and residential
developments
AS/NZS 4645.3 - Gas Distribution Networks - Plastics Pipe Systems
AS 4678 - Earth-Retaining Structures
AS 4799 - Installation of Underground Utility Services and Pipelines within
Railway Boundaries
AS/NZS ISO 31000 - Risk Management - Principles and Guidelines
AS/NZS ISO 14001:2004 Environmental Management System Standard
The construction must comply with the latest issue of the following ETSA Utilities
publications current at the time of commencement of the Works and the
following publications as determined by ETSA Utilities from time to time will be
considered to be incorporated in, and form part of, this Technical Standard.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 8 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
5.0
DEFINITIONS
Agreement to Grant Easement - An agreement letter signed by the registered
proprietor of land agreeing to allow ETSA Utilities to cross their property with our
equipment and that they will grant to ETSA Utilities a formal easement on
completion of the works. See Appendix C for Standard letter for use when the
Customer is required to obtain the required agreement to grant easement from
the affected property owner, NOT ETSA Utilities.
AS/NZS 3000 Wiring Rules - means the current version of the Wiring Rules
published by Standards Australia.
Authorised Person - the person in charge of the premises, or the registered
electrical worker or licensed electrical contractor or other person appointed or
selected by the person in charge of the premises, to perform certain duties
associated with the electrical installation on the premises.
Authorised Service Capacity - the demand capacity as detailed in the Offer
for Supply which was accepted by the customer. This is the maximum demand
capacity that the Service Protection Device, Consumers Terminals and
upstream Distribution System have been designed to provide for. When a
customer requests a reduction to their Agreed Maximum Demand the new
Agreed Maximum Demand will become the Authorised Service Capacity.
Connection Point - has the meaning given to that term in the Electricity
(General) Regulations 1997, namely a connection point to a transmission or
distribution network. For the purpose of this document connection point also
has the same meaning as Point of Supply as defined in AS/NZS 3000.
Consumers Mains - are the electrical cables/conductors, owned and
maintained by the customer, connecting the point of supply and the main
switchboard and form part of the customers/landowners installation.
Consumers Terminals - the junction at which the consumer main connects to
the ETSA Utilities service cable or main supply conductors.
CT Metering - a meter where electricity flow is measured by a meter using
current transformers (CTs). Note: CT meters are used where the maximum
demand of the installation is more than 100 amps.
Customer - has the meaning given to that term in the Electricity Act 1996,
namely a person who has a supply of electricity available from a transmission or
distribution network for consumption by that person and includes:
The occupier for the time being of a place to which electricity is supplied;
Where the context requires, a person seeking an electricity supply; and
A person of a class declared by regulation to be customers/ landowners.
Customer may or may not necessarily be the landowner.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 9 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Distribution Network - has the meaning given to that term in the Electricity Act
1996, namely the whole or a part of a system for the distribution of electricity,
but does not include anything declared by regulation not to be a distribution
network or part of a distribution network. For the purposes of these rules
references to Distribution Network means the network poles, wires, underground
cables, transformers, substations etc, operated by ETSA Utilities, which transports
electricity from the transmission system to a customers Connection Point.
Distribution Transformer - A transformer which forms a part of the distribution
network, typically with a secondary voltage of less than 1kV.
Easement - The right to enter private property, to erect, or lay and maintain
infrastructure subject to any condition stated in the easement document.
Electricity Distribution Code - means the Electricity
administered by the Essential Services Commission of S.A.
Distribution
Code
Electrical Installation - has the meaning given to that term in the Electricity Act
1996, namely a set of wires and associated fittings, equipment and accessories
installed in a place for the conveyance, control, measurement and/or use of
electricity that is, or is to be, or has been, supplied for consumption in the place,
but does not include:
A single parcel of freehold, leasehold and/or public land, and/or land held
under lease or licence on which the customer or controlling body has the
right to install their electrical installation;
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 10 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
6.0
Site Location
Most distribution transformer sites are likely to include a Padmount
transformer and associated switchgear / ring main units. Some sites
may require multiple Padmount transformers and ring main units
depending on the total required maximum demand.
ETSA Utilities preference is for Padmount transformers and associated
switchgear to be located outdoors at ground level with direct access
from the street. This is the customers least overall cost option. Refer to
NICC-802 - Padmounted T/F Brochure. However, an alternative to the
outdoor option is a transformer room within the customers building.
6.2
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
We strongly recommend that you liaise with the relevant ETSA Utilities
Manager when selecting a site within your development for the
transformer room. Transformer rooms located at ground level with direct
access and ventilation is ETSA Utilities preference for a transformer
room.
Alternatively, transformer rooms may be located in the following
locations by agreement from the relevant ETSA Utilities Manager:
Basement level;
Upper level - by negotiation at gantry level for temporary HV supply
only.
Notes:
Basement transformer rooms are only acceptable if there is a duct
system between associated equipment to enable the installation of
the required ETSA Utilities cables.
ETSA Utilities will not accept basement transformer rooms where they
are located at the lowest point of the building or below the flood
level.
6.3
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 12 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 13 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
7.0
LAND TENURE
Formal land tenure (by registration in the Lands Titles Registration Office) must
be provided to ETSA Utilities for the transformer room, together with rights of
access for personnel, related services and where necessary, vehicles.
7.1
Form of Tenure
Generally, registered easements (in a form determined by ETSA Utilities)
will be adequate but in some circumstances, where the facility has
wider implications for the electricity distribution network, tenure by
ownership may be sought. In those instances where ownership is
deemed necessary, ETSA Utilities will negotiate arrangements separate
to those set out in this Technical Standard.
7.2
7.2.2
7.2.3
Ventilation
As set out in clause 9.6 of this Technical Standard, the facility will
require adequate ventilation (and possibly external ventilation)
and the easement documentation will make provision for this.
7.2.4
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 14 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
7.3
7.4
Landowner Agreement
The owner of the land (not a tenant or informal third party
representative) must formally agree to grant an easement on such
terms and conditions as ETSA Utilities considers appropriate and
undertake to do all things necessary to obtain registration of the
easement in the Lands Titles Registration Office.
The landowner must also provide a plan delineating the easement and
do all things necessary to enable deposit/acceptance of the plan in
the Lands Titles Registration Office.
7.5
Costs
The owner of the land must agree to pay all reasonable costs
associated with the granting of the easements (including those
required over any third party land).
The easement will also require that the landowner meet the costs of
any equipment (including but not limited to cranes and forklifts)
required for installation and replacement of the subject electricity
infrastructure due to its location as requested by the landowner, rather
than a location deemed by ETSA to be more convenient and
accessible.
8.0
Access Requirements
Unless access to the transformer room is directly from any street frontage, the
following requirements shall be met by the customer.
8.1
8.2
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 15 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
8.3
Equipment Access
The transformer room requires suitable access to a clear equipment
handling area in front of the room. This equipment handling area is to
be large enough to manoeuvre all required equipment in to and out of
the room with a minimum width of 2.6m and length of 2.6m.
The grade of the handling area should not exceed 1:20. A 6.2m turning
circle is required for the mobile crane to navigate around corners.
A carriageway easement of 4.5m (H) x 4.5m (W) is required for the
installation or removal of the transformer. The width should be increased
on bends. The carriageway must have a maximum slope of 1:12. The
carriageway must be able to withstand the combined weight of the
transformer and crane of 23 tonnes.
8.3.1
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 16 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
8.3.2
8.3.3
8.3.4
Safety Signs
Safety signs that draw attention to the dangers of unauthorised
access to high voltage electrical equipment must be attached
to all doors to the transformer room. These signs are to be in
accordance with the requirements of AS1319 Safety Signs for
the Occupational Environment.
8.3.5
Hardware
8.3.5.1
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
8.4
Hazardous Locations
ETSA Utilities transformer room access routes must not be within an area
which is classified as a Hazardous Area.
8.5
8.6
Noise
The Environmental Protection Authority (EPA), local councils and other
authorities have the power to ensure that noise originating from any
premises is not the cause of reasonable complaint.
The customer is responsible for the design and construction of the
transformer room to ensure that noise does not exceed the limits
defined in Environmental Protection (Noise) Policy 2007 and is not a
source of complaint.
Furthermore the use of surrounding areas will impact on the level of
noise that is permissible. Noise measurements shall be as per AS2374.
Ventilation fans also are a source of noise and need to be silenced by
attenuator attachments and baffles. Fans installed in transformer rooms
must not exceed the db(A) requirements as specified in the
Environmental Protection (Noise) Policy 2007.
The attenuator attachment can protrude substantially within the
transformer room. However, as a result the dimensions of the
transformer room may need to be increased. Size and position of fans
within the transformer room must be acceptable to ETSA Utilities.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 18 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.0
CONSTRUCTION REQUIREMENTS
All construction drawings for transformer rooms are to be designed to comply
with the relevant clauses of the Building Code of Australia and relevant
Standards.
9.1
General
All construction materials used in the transformer room including walls,
ceilings and floors, doors and vents must be constructed from noncombustible materials.
Any wall, ceiling or floor shared with or adjoining another part of the
building must be treated as a fire wall as defined in the Electrical Safety
(Network Asset) Regulations 1999 and Building Code of Australia and
must have a minimum fire rating of three hours (180/180/180),
effectively segregating the transformer room from the rest of the
building.
It is essential that these ratings be maintained for any penetration of the
wall for cables or other services. The sealing of the penetration must be
done strictly in accordance with the manufacturers instructions and will
be subject to inspection by ETSA Utilities.
9.2
Foundation Requirements
The transformer room must be constructed on a stable foundation
which bears on soil or another part of a building. Where the foundation
bears on soil, the soil must be clear of any obstruction or rubble which
could interfere with the installation of the earthing electrode system
through the transformer room floor.
All transformers and HV switchgear must have a vault no lower than the
building basement with a minimum size of 1.2m deep x 0.9m wide x
1.8m long and sleeved appropriately for earthing requirements OR the
customer is to provide a transformer stand to ETSA Utilities specification.
For the site specific footings and vaults requirements, consult/discuss
with relevant ETSA Utilities Manager.
9.3
Site Drainage
The site shall be effectively drained to keep the area outside
the transformer room freely drained and dry. Stormwater
drainage systems shall be designed and provided to industry
best-practice standards. Site drainage shall be kept in working
order by the customer.
9.3.2
Area Drainage
The area in which the Transformer Room is to be located shall
be free of the risk of flooding and storm water damage and
any drains provided must be kept in working order by the
owner.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 19 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.3.3
Water Tightness
The enclosure housing the transformer room equipment has to
be watertight to protect all equipment within the transformer
room which may be subject to risk of damage from exposure to
water or dampness. ETSA Utilities will not accept handover of
the enclosure or install equipment if there is water or water
leakage within the transformer room or the potential for this.
9.3.4
Methods
Industry best practice construction methods shall be used at all
times to ensure the transformer room is waterproof.
9.4
9.5
Floors
The transformer room floor, including trenches, conduits, etc, is to be
formed in accordance with the positions and details shown on ETSA
Utilities drawings and specifications.
The floor is to be designed by a practicing structural engineer and be
capable of carrying the loads of the transformer room equipment. The
floor must carry a transformer load of 7900kg on 4 points anywhere in its
area. The floor must have a level non-slip finish. Provision is to be
incorporated in the floor slab for any floor hauling eyes/anchors.
A transformer landing area is to be provided in all cases. The
transformer loading area is to be constructed of reinforced concrete
and must have the same load bearing characteristics as the
transformer room floor. The equipment handling area is specified in
clause 7.3 and will be located immediately in front of the transformer
access door/s.
The landing area must be at the same relative level as the transformer
room floor to allow equipment to be rolled into the transformer room
directly from the landing area.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 20 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.6
Ventilation
Transformer rooms require special attention to ventilation in order to
dissipate heat losses from electrical equipment. Wherever possible,
natural air flow to the outside of the building will be used.
Forced ventilation should be used where natural ventilation is not
practicable. Forced ventilation by means of fan(s) must be designed,
supplied and installed by the customer to ETSA Utilities requirements.
In either case, the ventilation must be sufficient to maintain a maximum
temperature rise of 15 degrees Celsius above the external ambient
temperature when all transformers are operating at nameplate rating.
Air inlets and outlets must be arranged to achieve an even distribution
of air flow over the transformers.
Substantial vertical separation is required between inlet and outlet
openings. Inlet and outlet openings should preferably be clear of
pedestrian areas and must be located to prevent entry of noxious
gases such as vehicle exhausts, fuel exhausts, refrigeration plant gas
discharge valves, pollutants such as smoke, soot, dust, ash etc.
Air being removed from an internal transformer room must be directly
and independently ducted to outside air. A fire damper is required to
be installed in each duct-opening in a basement transformer room to
close off air supply in the event of a fire. It must have a fire rating of
three hours (180/180/180).
In special circumstances, the customer may be required to install an
exhaust fan with integral fire damper as part of the building work.
Exhaust air from the transformer room shall be ducted independently
and directly to outside air.
Note: As a guide heat losses are taken as 25kW per transformer.
9.6.1
Natural Ventilation
This type of ventilation is suitable for transformer room capacity
up to 1000kVA. The position of the vents must be directly to
outside air, if this is not achievable, such as in the case of a
basement type transformer room, then forced ventilation is
required.
The design calls for the customer to provide vermin proof,
weather proof louvered vents of a specified design in the walls
in order to achieve natural ventilation. Vents on personnel and
equipment doors are not acceptable. These areas outside the
louvers must not be subjected to fire risk.
In some cases, where the roof of the transformer room is
external, weatherproof roof ventilators may also be specified. It
is important where roof vents are installed that they are fixed
securely to the rod purloins. All vents are to be fitted with fire
shutters.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 21 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.6.3
9.6.4
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 22 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.6.2
9.7
Fire
ETSA Utilities transformer rooms are designed to contain any products of
a fire within the enclosure. Self containment has the added advantage
of also being self smothering and this ensures that there is no spread of
fire to other parts of the building.
You must ensure all walls, floors, ceilings and doors are 3-hour fire rated
(180/180/180). The customer will be responsible for providing these fire
ratings at his cost.
9.7.1
9.7.2
9.7.3
Fire Segregations
Where a transformer room is located within a building, a 3 hour
fire rated (180/180/180) enclosure and a fire rating level in
accordance with the Building Code of Australia must be
provided.
9.8
Cable Supports
9.8.1
General
All electrical conduits and cable enclosures, between the
transformer room and the property boundary shall be provide
by the customer as specified on the layout drawings to enable
ETSA Utilities to install HV and LV cables to the transformer room.
The location of the transformer room should be such that the
length of conduits or other cable enclosures is as short as
possible. Conduits and other cable enclosures should run in a
horizontal straight line from the transformer room to the
property boundary.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 23 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.8.2
9.8.2.1
Buried Conduit:
Heavy duty orange coloured un-plasticised Polyvinyl
Chloride (H.D. Electrical U.P.V.C. to AS2053 of solid
wall construction) and must be approved by
ETSA Utilities prior to installation direct in the ground.
The conduits shall be installed to a depth below the
finished ground level as specified in AS/NZS 3000 or
the minimum bending radius of the cable whichever
is greater.
Where the conduits are required to be installed in
public road reserve they are to be installed to the
requirements of ETSA Utilities TS-085 Trenching and
Conduit Standard for Underground Cable Networks.
These conduits may be buried at the specified depth
with appropriate bedding, without any further
mechanical protection. Cable pits may be required
external to the transformer room where a change in
direction or level occurs in the conduit run.
These cable pits will normally require a removable
cover of the Gatic type or approved equivalent.
9.8.2.2
Supported/Enclosed Conduit
(Basement Car Park)
There are two acceptable methods of encasing
conduits through buildings on route to the
transformer room from the property boundary.
Conduits must be securely fixed to prevent
movement when a 5 tonne pulling forced is applied
to them, and to support the weight of the cables.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 24 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
9.9
Hauling Eyes
Where required, anchors and/or pulling eyes (provided by the owner)
are to be installed in the floor, walls or ceiling in the position shown on
the layout drawings and in a manner to achieve the working load
specified.
Normally for a single cable going to a trench, single transformer room
two pulling eyes will be required - one for the cables and one for the
transformer. However further pulling eyes may be required for more
complex transformer rooms with multiple cable trenches or multiple
transformers, or where access to install cables or transformers is
restricted.
All anchors and pulling eyes shall be clearly and permanently stamped
to indicate its safe working load. Pulling eyes located in floors shall be
removable and, upon removal, the floor surface shall be level to avoid
a tripping hazard. Threaded recesses shall be provided with reusable
removable plugs to exclude ingress of foreign matter.
Normal pulling eye requirements are as follows:
9.9.1
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 25 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Heavy
9.10
Oil Containment
Provision must be made within the transformer room to contain any oil
spillage (in the unlikely event of a transformer tank failure) and slope to
a common point. Spillage from transformers needs to be contained
within the transformer room and be 110% of oil volume as per the
AS1940 and EPA Bunding Guidelines. Bunding requirements may be
relaxed should a 100% self oil contained transformers be utilised.
9.11
Additional Requirements
Additional requirements are as follows:
10.1
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 26 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
10.2
Approval
The design of the conduit route and formation is to be included on the
building construction drawing and is to be approved by ETSA Utilities
before construction commences.
Any subsequent alteration to design during construction must be
approved by the relevant ETSA Utilities Manager. When installation of
the conduits is complete, the customer shall arrange inspection by ETSA
Utilities, prior to backfilling or concrete pour.
10.3
Installations
All conduits are to be installed as per relevant ETSA Utilities Technical
Standard but specific designs need to be undertaken in conjunction
with the ETSA Utilities Manager. ETSA Utilities will inspect conduit location
and installation before backfilling.
10.4
Inspections
You must ensure the High Voltage switch room is completed to ETSA
Utilities standards and specifications prior to arranging an Electrical
Compliance Inspection.
OR
You must arrange for Electrical Compliance Inspection following the
completion of your works that are related to the provision of new high
voltage equipment on site.
11.1
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 27 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
11.2
Earths
The earthing arrangements for the Transformer Room are to be a CMEN
system which utilises common HV and LV earthing systems. The system
will require a value of the combined earth resistance to be one ohm or
less as prescribed in AS/NZS 3000.
For further advice on AS/NZS 3000 requirements, please contact the
Office of the Technical Regulator. This system must be used, with the
location of the earthing system and all conduits to be detailed on an
approved ETSA Utilities as constructed drawing/s.
Additional electrodes may need to be installed outside the transformer
room area and additional easements may be required if appropriate
earth resistance readings cannot be achieved.
Fault levels at specific locations can be obtained by consulting the
relevant ETSA Utilities Manager. Refer to Section 3 of the ETSA Utilities
Service & Installation Rules for contact details.
All unbounded exposed metal work within the transformer room must
be electrically bonded to the earthing system. This includes metal doors
and reinforcing in the floor. If a part cannot be adequately bonded, it
will be constructed from a suitable insulating material instead of metal.
The developer shall provide a connection point to the floor reinforcing
at a convenient location as advised by the ETSA Utilities representatives.
11.3
Standard Designs
The customer must provide drawings of the proposed site, planned
conduit route through the property and transformer room location.
Along with a floor plan, relevant sections through the transformer room
showing all levels, beams, columns, footpads and any other structures
within or outside the transformer room shall be shown. Ventilation details
that are submitted must show site and location of all vents, ducts and
fans.
The customers representative is required to prepare for the builders
guidance a building construction drawing and provide three (3) copies
of this drawing to ETSA Utilities representative for reference before
construction of the transformer room begins.
The approved For Construction drawing is to show:
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 28 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
11.4
Inspections
The builder will undertake regular dialogue with the relevant
ETSA Utilities Manager during the construction phase with on-site
meetings undertaken at critical milestones of the project.
For Example:
At the Pre-Construction Stage:
o
11.5
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Internet Website:
TS105 Test Standard Appendix A Forms
11.6
11.6.2 Permanent
The customer will supply and install within the transformer room
necessary light fittings including power outlets and all wiring as
per the Building Code of Australia. Where required, equipment
such as exhaust fans, pumps, and controls will be provided and
installed by the customer in accordance with this specification.
The customer will undertake the wiring to these units. All wiring
specified above shall be undertaken in accordance with
relevant Australian Standards.
TS-108
Issue: DEC 2011
Authorised: Jehad Ali
Date: 20/12/11
Page 30 of 30
The use of this Technical Standard is subject to the conditions stated in ETSA Utilities disclaimer.
WARNING: Printed copies of this document ARE DEEMED UNCONTROLLED. The most up-to-date version is located on the Intranet.
Intranet Website: