Professional Documents
Culture Documents
SL. N O .
DESCRIPTION
01.
CO L D ST AR T - U P
02.
03.
H O T AN D WA RM S TA RT U PS.
04.
05.
IN T E GRA T E D ST AR T U P PR O C EDU R E H O T ST AR T U P .
06.
10.
11.
07.
08.
09.
COLD START UP
(With Aux Steam available)
A cold start up is by definition, one of which the maximum of HP casing and HP shaft is
less than 1500C. This normally means that the unit is shut down from the maximum load
for more than five days. If machine is started from ambient temperature (HPC/HP shaft
temp approx. 400C), heating up of casting is required. This is accomplished by soaking
the machine at 360 rpm at warming up steam parameters (40kg/cm2, 3600 C), till the
TSE margin are satisfactory.
The rifle construction of the water wall combined with the boiler circulating water
pumps permits very high rate of pressure rising of boiler. An upper limit of 2000C/hr
saturation temperature gradient can be allowed, i.e. approximately the boiler pressure
can be brought to 20 kg/cm2 within an hour of cold start up. But actual temperature
gradient is limited by the thick walled Y piece provided in the main steam and HRH lines.
A main steam line heating is to be started as early as possible (at approx. 4 kg/cm 2) as
maximum differential temperature allowed between inner (98%) and mid wall
temperature (50%) is 400C. So boiler loading is accordingly regulated. It may be
preferably to start only two CC pumps in order to minimise flashing in down comers (and
subsequent vibration) when the boiler water is in range of 85 0C to 1250C. The third
pump should be started before drum pressure reaches 7 kg/cm2 to minimise the
temperature transients experienced by the pump casing (this is to avoid fast load out
back on the boiler in the event of any CC pump tripping).
To get the rolling parameters, normally two elevation oil guns are taken with
approx. 70 to 80t/hr flow through HP-LP bypass. At that time M.S. parameters would be
40 kg/cm2 and 3600C, HRH parameters would be 12 kg/cm2 and 3600C.
As soon as the turbine loading has started, HP/LP bypass closes and gets completely
closed as the turbine reaches the boiler load. First mill is put into operation around 10%
of generator load. Second mill is put into operation around 25% while third mill is at
40% of generator load. Fourth and fifth mills are put into operation at 60% and 80% of
generator load respectively. Sixth mill is taken to reach full generator load.
During loading the RH outlet steam temperature has to be kept as close as possible
to SH outlet steam temperature Burner tilt, SH spray, RH spray controls has to be
adjusted accordingly. The turbine-loading rate is decided by a selection circuit which
compares the external load gradient, TSE margin and time dependant gradient (set
internally) and frequency influence.
TIME
UNIT CONDITION
OPERATION
NOTES
..
Generator protection
panel ready in all
respects.
Generator H2 gas
pressure is 4 kg/cm2
Check purity of
generator stator water
is normal.
H2 cooling water
system ready in all
respects with SLC on.
--
--
The sequential
operation narrated
above on Lub oil
system stopped is
achieved by SGC
mode.
M/c on barring.
+200 mm.
The sequential
operation narrated
above in FRF system
stopped condition is
achieved by SGC-FRF
system on starting
programme mode.
01
oo
Start 4 burners in AB
elevation with LSHS.
Ensure atomising
Regulate oil pressure to
steam pressure about 6
2
8-10 kg/cm .
kg/cm2.
Insert furnace probe
and ensure that the
temperature is below
5350C.
Start condensate
pumps and feed to
Check hotwell level.
deaerator as and when
required.
--
CW system is charged.
CW boxes to ensure
ventilating of water
boxes.
--
02
60'
03
100
Switch on automatic
control interface of LP
bypass.
Automatic control
interface gets switched
off when the hot reheat
steam pressure reaches
13kg/cm2 i.e. after
synchronisation.
Open HP by pass.
Boiler pressure:15
kg/cm2
04
150
Temperature:1802000C
HRH Pressure:812Kg/cm2
M. S. Pr. 50 kg/cm2
M.S. temp. 3500C
05
-300
H. R. H. Pr. 12 kg/cm2
06
-360
Monitoring bearing
temperature and
vibrations, shaft
vibrations, TSE margins
and Turbovisory
readings, Seal oil,
Primary water and gas
temperatures &
Generator winding
temperature.
MS Pr. 50 kg/cm2.
Temperature:
Put AVR on Auto.
3500C Turbine running
at 3000 rpm.
07
370
Synchronise the
generator with grid.
-
Pick up 50 MW load by
operating speeder gear.
04
150'
MS Pressure: 50
kg/cm2
MS
Temperature:3500C
05
300'
HRH Pressure:
12kg/cm2
HRH Temperature:
3500C.
Turbine Ready for
rolling
If tracking device is
Raise the speed set
switched ON, starting
point to 360 rpm and
device position will
watch the actual speed. automatically track the
EHC position
MS Pressure:50
kg/cm2
06
360'
MS
Temperature:3500C
Monitoring bearing
vibrations, bearing
temperatures, shaft
vibrations, TSE margins
and Turbovisory
readings.
Ensure tripping of
jacking oil pump at 540
rpm.
Monitor bearing
vibration and
temperatures, shaft
vibrations, Turbovisory
readings and TSE
margins
MS Pressure: 50
kg/cm2
07
370'
MS Temperature:
3500C
Synchronise the
generator with grid.
150'
MS Temp.:180-2000C
HRH Pressure: 12
kg/cm2
If the programme
interrupts the particular
step and criteria to be
checked and corrected
for the programme to
proceed further.
All operations as
explained under EHC
rolling will be carried
out by SHC Turbine
programme
sequentially.
MS Pressure: 50
kg/cm2
MS Temperature:
3500C
05
300'
HRH Pressure: 12
kg/cm2
Monitor bearing
vibration, bearing
temperature, shaft
vibration, TSE margins
and Turbovisory
readings.
To achieve the
programme as per the
starting curve, the
main steam
temperature should be
maintained steadily till
loading upto 50 MW.
MS Pressure: 50
kg/cm2
06
360'
MS Temperature:
3500C
MS Pressure: 50
kg/cm2
07
370'
MS Temperature:
3500C
Turbine
speed:3000rpm.
Load : 55 MW
08
390'
M.S. :
54kg/cm2/3500C
HRH : 12
kg/cm2/3400C
-
Ensure switching on of
load controller above
60MW.
Load : 55 MW
M.S. :
54kg/cm2/3500C
HRH : 12
kg/cm2/3400C
Ensure energizing of
solenoid in trimming
device at and above
100 MW load.
Raise the pressure set
point of Deaerator
pressure controller
gradually.
Peg Deaerator
gradually to 4 kg/cm2.
Load : 160 MW
M.S. :
90kg/cm2/3800C
10
440'
HRH : 20
kg/cm2/3800C
Steam flow : 580t/hr.
Charge Deareator
pegging steam flow
CRH to Extraction
around 200 MW load.
Ensure Deareator
Pressure controller
remains as auto.
Load : 250 MW
M.S. :
120kg/cm2/4200C
11
480'
HRH : 26
kg/cm2/3400C
Load : 320 MW
M.S. :
125kg/cm2/3500C
12
510'
HRH : 28-30
kg/cm2/3400C
Steam flow : 1040t/hr.
Ensure healthiness of
fire ball scanners.
Load : 405 MW
M.S. :
145kg/cm2/4600C
13
550'
HRH : 33
kg/cm2/4600C
Load : 500 MW
14
590'
M.S. : 170
kg/cm2/4750C
HRH : 40.5
kg/cm2/4750C
RH spray controllers
such that rated
parametes are
achieved gradually.
Load : 405 MW
M.S. :
145kg/cm2/4600C
15
670'
HRH : 33
kg/cm2/4600C
constraints i.e., 40 C). In both the cases, curves are given to derive the rolling
parameters. In case when machine is rolled through EAST, curve generators, calculate
and give permissive for rolling.
TIME IN
MINUTES
UNIT CONDITION
OPERATION
NOTES.
Turbine on bearing
gear with AOP, JOP
and seal oil pumps in
operation.
Generator gas
system, seal oil
system and primary
water system in
operation.
HT and LT auxiliaries
power supply
available.
HP bypass system
ready in all respects.
Generator protection
panel and exciter
panels ready in all
respects.
1. Charge auxiliary
steam header from
existing units. Pr.
16ata temp. 2600C.
2. Charge steam to
fuel oil pump house,
atomising steam and
tracing steam.
Ensure running of
motor driven BFP
Start second CC Pump. continuously for
maintaining drum
level.
Start 4 burners in AB
elevation with LSHS.
01
oo
Ensure atomising
steam pressure of
about 6 kg/cm2
Ensure motor
operated BFP is in
service.
Switch Automatic
control interface of LP
bypass.
Ensure condenser
vacuum of 0.8
kg/cm2.
synchronisation.
Put HP bypass
controller on auto and
vary the set point
according to the
gradient of pipeline
temperatures.
02
180'
HRH: 12
kg/cm2/3250C
By pass steam flow:
170t/hr.
MS: 60 kg/cm2/4000C
03
210'
HRH: 12
kg/cm2/3500C
04
215'
Turbine running at
360 rpm.
Monitor bearing
vibrations, shaft
vibrations, TDE
margins, bearing
temp. & Turbovisory
readings at 360rpm.
Ensure tripping of
AOP at 2950 rpm.
05
220'
Turbine running at
3000 rpm
Synchronise the
generator with grid.
Pick up 50 MW load by
operating speeder
gear.
Ensure closure of
HPBP steam valves &
spray valves.
start up curve.
02
180'
HRH: 12
kg/cm2/3250C
By pass steam flow:
170t/hr.
MS: 60 kg/cm2/4000C
HRH: 12
kg/cm2/3500C
03
210'
If tracking device is
switched on starting
device position will
automatically track
the EHC position
Monitor bearing
vibrations bearing
temperatures, shaft
vibrations, TSE
margins & turbovisory
readings.
Ensure tripping of
Jacking oil pump at
340 rpm.
04
215'
Turbine running at
360rpm.
Monitor bearing
vibrations and temps,
shaft vibration,
turbovisory readings
and TSE margins.
Ensure tripping of
AOP at 2950 rpm.
05
225'
Set manually
generator voltage to
grid voltage.
Synchronise the
generator with grid.
Ensure closure of
HPBP steam valves
and spray valves.
02
180'
HRH: 12
kg/cm2/3250C
If the programme
interrupts the
particular step and
criteria to be checked
and corrected for the
programme to
proceed further.
All operations as
explained under EHC
rolling will be carried
out by SGC Turbine
programme
sequentially.
MS: 50 kg/cm2/3650C
HRH: 12
kg/cm2/3250C
03
210'
Monitor bearing
vibration, bearing
temp, shaft vibration,
TSE margins and
Turbovisory readings.
To achieve the
programme as per the
starting curve, the
main steam
temperature should
be maintained
steadily till loading
upto 50 MW.
MS: 60 kg/cm2/4000C
04
215'
05
225'
Turbine running at
360 rpm.
Ensure closure of
HPBP steam valves
and spray valves.
Load: 60 MW
MS: 60 kg/cm2/4100C Cut in L.P. heaters 2
and 3.
HRH: 14
kg/cm2/3600C
Ensure switching on
of load controller at
60 MW.
06
230'
Load: 110 MW
MS: 80 kg/cm2/4200C
07
245'
HRH: 19
kg/cm2/3800C
Peg Deaerator
gradually upto 4
kg/cm2.
Load: 200 MW
MS: 100
kg/cm2/4350C
08
270'
HRH: 19
kg/cm2/4000C
Main steam flow:
750t/hr.
Ensure healthiness of
fire ball scanners.
Change Deaerator
pegging steam from
CRH to Extraction
steam.
Ensure Deaerator
pressure controller
remains on auto.
Before starting P.A.
fan ensure that air
and gas dampers of
PAPH are open.
Load: 320 MW
MS: 125
kg/cm2/4500C
09
300'
HRH: 30
kg/cm2/4300C
Main steam flow:
1080t/hr.
Ensure healthiness of
fire ball scanners.
Load: 500 MW
MS: 170
kg/cm2/4800C
10
340'
HRH: 40.5
kg/cm2/4800C
Main steam flow:
1620t/hr.
Load: 500 MW
MS: 170
kg/cm2/5350C
11
420'
HRH: 40.5
kg/cm2/5350C
STEP
TIME IN
UNIT CONDITION
MINUTES.
OPERATION
NOTES.
be kept running
continuously.
Turbine on barring
gear with AOP, JOP
and seal oil pumps in
operation.
Generator gas
system, seal oil
system and primary
water system in
operation.
Condenser circulating
water system in
operation.
LSHS pump in
operation on long
recirculation upto
boiler front with
heaters control set on
HP bypass system
ready in all respects.
Generator protection
panel and exciter
panels ready in all
respects.
Ensure condenser
vacuum of 0.8 kg/cm2.
Switch Automatic
control interface of LP
bypass.
Ensure condenser
vacuum of 0.8
kg/cm2.
Automatic control
interface gets
switched off when the
hot reheat steam
pressure reaches 13
kg/cm2(i.e.) after
synchronisation.
Ensure differential
temp. is within
permissible limits.
Ensure running of
motor driven BFP
continuously for
maintaining drum
level.
01
oo
Start 4 burners in AB
elevation with LSHS.
Ensure atomising
steam pressure of
about 6kg/cm2.
Ensure motor
operated BFP is in
service.
Put HP bypass
controllers on auto and
vary the set point
according to the
gradient of pipeline
temperatures.
02
40'
HRH: 12
kg/cm2/4400C
MS Pressure: 85
kg/cm2
MS Temperature:
5000C
03
50'
HRH Pressure: 12
kg/cm2
HRH Temperature:
4500C.
Bypass steam flow:
360t/hr.
04
Turbine running at
360rpm.
52'
Monitoring bearing
vibrations, shaft
vibrations, TSE
margins, bearing
temp & Turbovisory
readings at 360 rpm.
Ensure tripping of
AOP at 2950 rpm.
05
56'
Turbine running at
3000rpm
Synchronise the
Generator with grid.
Pick up 50 MW load by
operating speeder
gear.
Ensure closure of
HPBP steam valves &
spray valves.
40'
HRH Pressure: 12
kg/cm2
HRH Temperature:
4400C.
Bypass steam flow:
280t/hr.
-
MS Pressure: 85
kg/cm2
MS Temperature:
5000C
03
50'
HRH Pressure: 12
kg/cm2
If tracking device is
switched on starting
device position will
automatically track
the EHC position.
HRH Temperature:
4500C.
Turbine Ready for
rolling. Bypass steam
flow: 360t/hr.
04
52'
Turbine reading at
360 rpm.
-
Monitor bearing
vibrations, bearing
temperatures, shaft
vibrations, TSE
margins and
turbovisory readings.
Ensure tripping of
Jacking oil pump at
540 rpm.
The rate of
acceleration will be
600 to 800 rpm2.
Monitor bearing
vibrations and
temperatures, shaft
vibration, turbovisory
readings and TSE
margins.
05
56'
Ensure tripping of
AOP at 2950 rpm.
Synchronise the
generator with grid.
Synchronise the
generator with grid.
Ensure closure of
HPBP steam valves
and spray valves.
40'
HRH: 12kg/cm2.
programme to
proceed further.
All operations as
explained under EHC
rolling will be carried
out by SGC-Turbine
programme
sequentially.
50'
04
52'
Turbine reading at
360 rpm.
-
Monitor bearing
vibration, bearing
temperature, shaft
vibration, TSE
margins and
Turbovisory readings.
To achieve the
programme as per the
start up curve, the
main steam
temperature should
be maintained
steadily till loading of
50 MW.
Ensure tripping of
AOP at 2950 rpm.
Monitor bearing
temperature and
vibrations, shaft
vibrations, TSE
margins, Turbovisory
readings, seal oil,
primary water,
Hydrogen gas and
Generator winding
temperatures.
Ensure SGC-start up
programme is
completed.
05
56'
Ensure closure of
HPBP steam valves &
spray valves.
Ensure switching on
of load controller at
60 MW.
LOAD: 60 MW.
06
60'
MS: 85 kg/cm2/5000C
HRH: 16kg/cm2/4700C
Ensure healthiness of
fire ball scanners.
65'
Trimming device is in
OFF.
-
Change deaerator
pegging steam from
CRH to Extraction
steam.
Ensure Deaeator
pressure controller
remains on auto.
70'
HRH: 20kg/cm2/4950C
Main steam flow:
820t/hr.
Ensure healthiness of
fire ball scanners.
86'
HRH:
40.5kg/cm2/5000C
Main steam flow:
1620t/hr.
135'
HRH: 40.5
kg/cm2/4800C
********************