B. LOADINGS:
i.
Deadload:
a. 150mm thick CHB----------------------------------------------------------3.00KPa
b. WSLAB = 0.10x24------------------------------------------------------------2.40KPa
ii.
iii.
iv.
Live Load:
a. Private Room----------------------------------------------------------------2.40Kpa
b. Office, Lobbies, Hallways, Stairs----------------------------------------4.80Kpa
c. Storage---------------------------------------------------------------------- 6.00Kpa
Seismic Load:
In accordance with NSCP and UBC 1997 loadings.
v.
Wind Load:
In accordance with NSCP, 2001 edition.
vi.
Design Stresses:
a. Concrete Mixtures (Class A) (1:2:4)
fc = 20.7 MPa strength @ 28th days
b. Reinforcing Steel Bars
viii.
Construction Procedure:
a. Reinforcing Steel:
Reinforcing steels shall conform to ASTM A615. Bar splices, bendings,
hooks and placing shall be in accordance to NSCP and ACI codes.
b. Concrete Works:
Concrete Mix and placing shall be in accordance with NSCP and ACI
codes.
c. Falseworks and Formworks:
Stripping of forms recommendations:
Shoring under beams/girders------------------------------------------14days
Suspended slab----------------------------------------------------------14days
Columns-------------------------------------------------------------------7days
Side beams----------------------------------------------------------------2days
d. Curing:
Curing of concrete shall be done within 28 days or as instructed by the
Engineer.
e. Embankment/Backfill:
All embankment materials shall be granular in nature and shall be
compacted thoroughly (layer by layer) as per ASTM recommendations in
order to attain the required density of the fill. Provide well compacted
aggregate base coarse over filling materials.
f. Embedment of Footing:
___________O0O___________
Plans should be signed and sealed by the authorized Engineer. Any changes on
the plans should be verified by the authorized Engineer and must be thoroughly
reviewed and
Unit Conversions
1 in.525.4 mm
1 kip54,450 N
1 k in.5113 Nmm
1 ksi56.9 MPa