Professional Documents
Culture Documents
NEW DELHI
Appellant
Respondent
Versus
M/s.DLF Universal Ltd.
Sansad Marg
New Delhi 110 001.
Through its Managing Director
AND
FIRST APPEAL NO. 683 OF 2003
(From the order dated 28.5.03 in C.No.61/2000 of the State Commission,
Haryana)
M/s.DLF Universal Ltd.
Sansad Marg
New Delhi 110 001.
Appellant
Respondent
Versus
Brig.(Retd.) Kamal Sood
W-112 Regency Park II
DLF Qutab Enclave
Phase IV
Gurgaon - 122 002
BEFORE :
HONBLE MR. JUSTICE M.B. SHAH, PRESIDENT
MRS. RAJYALAKSHMI RAO, MEMBER
In person
ORDER
M.B. SHAH, J., PRESIDENT
The main in questions which require consideration in the appeal are
(i).
(ii).
permissions such as zoning plan, layout plan and schematic building plan. It is
the duty of the builder to obtain the requisite permissions or sanctions such as
sanction for construction, etc., in the first instance, and, thereafter, recover the
consideration money from the purchaser of the flat/buildings.
It has been pointed out that despite the aforesaid statement in the
brochure, the DLF demanded an additional amount of Rs.4,02,617.69p. on the
pretext of increase in the area, escalation charges, external electrification etc. It
is further alleged that the DLF made an offer to sell parking spaces in November
1993 at the cost of Rs.63,000/- to each allottee which was to be paid in
instalment of Rs.22,000/- each. The complainant paid the parking space cost
within the stipulated time and was allotted the parking space. Despite this, an
additional amount of Rs.62,869/- was demanded by letter dated 4.3.1998 as
extra charges for parking space which was already allotted to him. It is also
contended that at the time of delivery of possession in September 1999, the
DLF demanded a sum of Rs.1,59,890/- for Stamp Duty and Registration
Charges for the apartment and Rs.15,265/- for parking space.
Rs. 4,02,617.19 p.
b)
Rs. 3,15,011.68 p.
c)
d)
Rs. 75,898.00 p.
e)
Rs. 2,00,000.00 p.
f)
Rs. 50,000.00 p.
______________
Total
Rs.12,78,395.87 p.
==============
(i).
bound to pay Escalation Charges, and hence rejected the prayer for refund of
the Escalation amount;
(ii).
which was recovered from the complainant for execution of the Conveyance
Deed, the State Commission directed the DLF to pay interest at the rate of 10%
p.a. on the amount deposited by the complainant from the date of deposit till the
date of execution of the Conveyance Deed;
(iii).
Thirdly, for the differential carpet area, the State Commission held
that the said dispute between the parties cannot be decided/sorted out in
summary proceedings.
(iv).
Submissions:
Learned senior counsel, Mr.Haksar, submitted that
Delay in construction was due to reasons beyond the control of the
DLF. For this purpose, he relied upon the statements made in Para-E of the
Memo of Appeal (First Appeal No. 683 of 2003), wherein it has been stated as
under:
(a).
(b).
the Appellant had taken steps to get the Zoning Plan in respect
of the said project approved and the Director, Town & Country
Planning had approved the same on 24.8.1992 ; copy annexed and
marked as Annexure - C.
(c).
with detailed site plan and schematic building plan etc., for the said
project; copy annexed and marked as
(d).
ANNEXURE-D.
again sought approval of the layout plan; copy annexed and marked
as ANNEXURE E .
(e).
ANNEXURE I.
30.05.1995
(a)
the instalments;
(b) as per the agreement between the parties, the complainant was
required to pay Escalation Charges; and
(c) for the Stamp Duty and Registration Charges, he contended that
as soon as the complainant approached the DLF, the document was executed
and hence the delay was on the part of the complainant and not on the part of the
DLF. He also submitted that the order passed by the State Commission directing
to pay interest on the said amount cannot be justified.
FINDINGS:
I.
that the submission made above by the learned senior counsel for the DLF is
totally baseless and inconsistent with the submission made by DLF in its written
arguments which were filed before the State Commission, wherein the DLF has
admitted the delay and offered to pay interest thereon, as under:
Charges for registration and stamp duty : These are statutory
duties, which are payable under the Registration Act and the Stamp
Duty Act.
Commission on 10.12.2002.
In view of the aforesaid specific admission, there is no necessity to
consider the allegation of the learned Senior Counsel Mr.Haskar that there was
some delay on the part of the Complainant.
Secondly, we would state that undisputedly the stamp duty and the
registration charges were collected by the DLF in November, 1999 and retained
with it approximately for two years. For that, the DLF is bound to pay interest
II.
(a).
There is also no dispute that the complainant was required to pay the
total consideration price within a period of 10 years. It is the contention of the
Complainant that despite having opted for a ten year payment plan at the time of
booking the apartment in the year 1993, the entire cost was paid within a period
of six years and before taking possession of the flat in the year 1999.
(b).
instalments:
Learned senior counsel, Mr.Haksar, submitted that all throughout
there was delay on the part of the complainant in paying the instalments.
Therefore, DLF is not liable to pay any compensation to the Complainant for
delay in delivery of possession of the apartment.
Interest Rate :
Grace Period : 0
Due Date
20.00
07 Sep.1993
Amount
Due
87807
07 Nov.1993
100076.00
07 Mar.1994
12269.00
07 Jun.1994
30 Aug.1994
08 Sep. 1994
07 Mar.1995
12269.00
1.00
12269.00
87087.00
07 Dec.1995
43904.00
07 Mar.1996
43904.00
07 Jun.1996
32344.00
07 Sep.1996
32344.00
07 Dec.1996
32344.00
80064 )
Receipt
Date
Receipt
Amount
Days
Delay
Interest
Amount
07 Sep.1993
87807.00
0.00
02 Nov.1993
100076.00
0.00
11 Mar.1994
11 Mar.1994
11 Mar.1994
11 Mar.1994
11 Mar.1994
08 Jun.1994
05 Sep.1994
15 Dec.1995
15 Dec.1995
23 Apr.1996
23 Apr.1996
18 Jul.1996
18 Jul.1996
13 Sep.1996
13 Sep.1996
04 Feb.1997
04 Feb.1997
12269.00
12269.00
1.00
12269.00
63268.00
12269.00
12269.00
1.00
43903.00
1.00
43903.00
1.00
32343.00
1.00
32343.00
1.00
32343.00
4
0
0
0
0
0
0
283
8
138
47
133
41
98
8
150
59
26.89
0.00
0.00
0.00
0.00
0.00
0.00
0.16
192.45
0.08
1130.65
0.07
726.61
0.05
106.33
0.08
1045.61
07 Mar.1997
32344.00
07 Jun.1997
32344.00
07 Sep.1997
07 Dec.1997
32344.00
32344.00
07 Mar.1998
32344.00
07 Mar.1998
32344.00
07 Sep.1998
32344.00
07 Dec.1998
03 Mar.1999
32344.00
32344.00
18 Mar.1997
18 Mar.1997
10 Jun.1997
10 Jun 1997
18 Sep.1997
18 Sep.1997
1.00
32343.00
1.00
32343.00
1.00
32344.00
101
11
95
3
103
11
0.06
194.94
0.05
53.17
0.06
194.95
17 Dec.1997
32344.00
10
177.23
12 Mar.1998
32343.00
88.61
16 Mar.1998
16 Mar.1998
14 Sep.1998
14 Sep.1998
25 Dec.1998
25 Dec.1998
03 May 1999
1.00
32343.00
1.00
32343.00
1.00
32343.00
101
9
99
7
109
18
0.06
159.50
0.05
124.06
0.06
319.00
4540.79
4540.79
5551.00
(c).
delay was due to obtaining sanctions for various plans, including the lay out plan,
zoning plan, and that the approval of building plan for the project was finally
sanctioned on 30.5.1995.
In this case, the Complainant had applied for allotment of the flat in
September 1993, and the agreement, i.e. Apartments Buyers Agreement was
executed in October 1993.
in
the builder.
permissions could have been contemplated by the builder before issuing the
brochure. It would be unfair trade practice, if the builder, without any planning
and without obtaining any effective permission to construct building/apartments,
invites offers and collects money from the buyers. If the construction of the
building/apartment is delayed, because of such delay, and the possession of
the apartment is not delivered within the stipulated time, the builder would be
liable to bear the escalation cost and not the buyer/consumer.
made in
Edition, which deals with commencement of the work by the Public Authority
including Private Corporations. Therein, it has been observed:
Cl. 16:
From the aforesaid terms of the contract, it is clear that Clause 16,
quoted above, firstly provides that from the date of booking the Company shall
deliver the possession of the Apartment within two and half to three years.
This clause, in our view, would not apply to the cases of delay in
obtaining necessary permissions for construction of the buildings. In this case,
the delay is in no way connected with the non-availability of steel, cement, etc.
nor it is the act of God, such as earthquake. As such, it was default on the part of
the builder in not obtaining such permission in advance before issuing
advertisement inviting the buyers to purchase the apartments and before
collecting money. Therefore, the reliance placed upon the said clause is without
any basis.
.III.
(a).
Escalation amount:
Now, escalation, Cl.4 provides that in case of increase of costs,
during the construction period, which were prevailing on 1.1.1993, then the
Company would be entitled to levy escalation charges from the allottee.
(b).
Further, this clause is to be read along with the promise given in the
brochure. It is settled law that brochure is part of the promise on which the
contract is based. In the brochure it has been specifically mentioned that:
And remember, now all prices are ESCALATION FREE. So, the
price you book at is the price you pay, irrespective of what it
might cost DLF.
The brochure issued by the Opposite Party which has bearing in
deciding whether escalation in cost is to be borne by the Complainant. Dealing
with the case of Ghaziabad Development Authority Vs. Union of India, (2000) 6
SCC 113, the Apex Court considered the term of the brochure that the
Development Authorities shall not be liable to pay any interest in the event of
occasion arising for return of amount and held as under:
The rate of interest awarded in equity should neither be too high nor too
low. In our opinion awarding interest at the rate of 12 per cent per annum
would be just and proper and meet the ends of justice in the cases under
consideration. The provision contained in the brochure issued by the
Development Authority that it shall not be liable to pay any interest
in the event of an occasion arising for return of the amount should
be held to be applicable only to such cases in which the claimant is
itself responsible for creating circumstances providing occasion for
the refund. In the cases under appeal the fault has been found with the
Authority. The Authority does not therefore have any jurisdiction for
resisting refund of the claimants amount with interest.
would only prevail and not the terms of the brochure which is an
alluring promise given by the builder. If the contention of the learned counsel
for the DLF is accepted that the terms of the agreement would prevail and not
what is stated in the brochure,
then
This
would also be unfair trade practice as provided under Section 2(1) (r ) of the
Consumer Protection Act. Such brochure also gives undue advantage to the
builder vis--vis other builders. Hence, the said contention cannot be accepted.
In any case, in the present case, the builder is not entitled to have
escalation charges because admittedly there was delay in starting construction
for no fault of the consumer/buyer of the Apartment. Therefore, the recovery of
Rs.4,02,617.69p., from the Complainant under the threat of cancellation of
allotment is totally unjustified.
(c).
Lesser area:
For the lesser area as contended in the complaint, the State
Commission has held that it would be open to the Complainant to approach civil
court. We do not think that this would be a fit case for interference at this stage,
because the relevant evidence is not led by the parties on the said aspect and
the Complainant has not raised any contention in support of this ground. Hence,
if the Complainant has any grievance on this ground, it would be open to him to
approach the Civil Court.
(d).
Conclusion:
In view of the aforesaid findings for delay in delivering the
possession to the Complainant, the State Commission awarded Rs.1 lakh as
compensation. Considering the fact that we are directing the builder to refund
the amount recovered on account of escalation, costs, the said amount would
compensate the Complainant properly.
(a)
is recovered on account of escalation cost, with interest at the rate of 12% p.a.
[No doubt, the Complainant has claimed the refund with interest at the rate of
20%, because that was the rate at which the builder recovered from the
Complainant for some delay in payment of instalment.];
(b)
(c).
to pay interest at the rate of 12% p.a. on the amount deposited by the
Complainant for the execution of the Conveyance Deed, from the date of deposit
till the date of conveyance of the deed.
In view of the aforesaid order Appeal No. 683 of 2003 filed by the
DLF is dismissed.