Professional Documents
Culture Documents
Introduction
The Sleipner Field development in the
North Sea is the key to the enormous
Troll gas contract which will meet up
Investigation Methodology
Based on underwater inspections, it
was very soon apparent that the structure had been so completely demolished by the accident that no physical
evidence would be found to clarify its
cause.
alytical calculations.
logically fit physical causes to the eyewitness observations. This methodology included identification of all possi-
The Accident
When the accident occurred, the platform was undergoing a controlled ballast test operation prior to deck mating, which was going to take place on
September 1. The purpose of such a
Fig. 2: D3 s/ia ft
Probable Cause
The investigation identified only one
area with significant weaknesses: the
tricell walls and their supports towards
the cell joints (Fig. 3). Calculations also
showed that the load at the time of the
accident was at or near the ultimate capacity of these walls. Upper and lower
boundary estimates of the capacity of
mist
initial crack.
could then develop in the haunch behind the T-headed bars, leading to ro-
tions in platform
the shaft
'waterfall'-like sound
little water ingress into the D3 shaft
probable leakage elements were performed based on a systematic investigation of possible locations of the leak
and all observed evidence. Both reports conclude that the most credible
areas for the leakage was in the tricell
walls.
tee arrived at the same conclusions, reported 15 October 1991. These conclusions were accepted as the cause of the
cell joint.
ing the failure, combined with improved shear capacity due to increased
The 'bottleneck' at the 500 mm diameter hole in the roof of the tricell most
likely restricted the water ingress CaStructural Engineering International 3/94
191
ture. and thus under atmospheric pressure all of a sudden became exposed
to the external water pressure, say, 15
which may have led to the final destruction. An upper bound estimate
tablished failure mode and to demonstrate that it logically fit the eyewitness
observations.
several possible water leakage scenarios which might have caused the sinking. A total of 14 tests were performed,
including water inflow through some
mograms. as well as the wide distribution of the structure's parts on the sea
cracks in the tricell walls. In all experiments with two cracks, it appeared that
been destroyed during sinking and before it hit the sea floor.
the two jets met each other. The position of this point was a function of the
failure loads for these tests when expressed as equivalent differential water pressure were: 71 m. 71 m and 76 m
of waterhead.
These agree excellently with the corresponding number for the real Sleipner
tests.
192
_____________________________
____________________
Conclusions
The failure mode described in October
1991 by two independent investigation
In the winter and spring of 1992 several tests, both hydrodynamic and structural. were performed. These tests fullv supported the findings of the investigating committees.
process.
Through close and positive cooperation with the Norwegian offshore in-
Acknowledgement
Order Form
to be returned to
forces on bridges and proposes appropriate bridge design criteria. Prevention measures, such as regulations and
management systems. and other protection measures are also described.
Quantity
Description/title of volume
Price (SFr.)
0 VISA
0 MASTERCARD
Total price for the book(s): SFr
LI AMERICAN EXPRESS
LI DINERS CLUB
Card valid until (month/year):
Signature:
Structural Engineering International 3/94
Panorama
193