QC Turnover Index

1) Scope of Work
2) Provincial Documents (AB-83, AB-81, AQP, PP # & CWB Certs )
3) Inspection Test Plans (ITP)
4) Drawings (Plot Plan, GA, P&ID ISOs and Cut sheets)
5) As Built / Redlines Drawings
6) Welding Procedures
7) Welder Log with Qualification Records
8) Weld Map
9) Weld / NDE Log
10)

NDE Procedure Copies

11)

NDE Technicians Qualifications

12)

NDE Reports (RT, UT, PT, MT, FT, HT, PMI etc)

13)

PWHT Reports

14)

Pre-Hydro checklists

15)

Hydro Test Certificates

16)

Gauge Calibration Certificates

17)

Post Hydro check list (Reinstatement)

18)

Bolt Torque reports

19)

NCR Log and NCRs

20)

RFI Log and RFIs

21)

Punchlists / Deficiency lists

22)

MTRs / MRIRs

23)

Painting / Coating reports (If applicable)

24)

Miscellaneous