You are on page 1of 292

Environmental Assessment Report

Environmental and Social Impact Assessment


Project Number: 37231
May 2010

Pakistan: Punjab Irrigated Agriculture Investment


Program, Tranche 2

Prepared by the Government of Punjab, Irrigation and Power Department for the Asian
Development Bank (ADB).

The environmental and social impact assessment is a document of the borrower. The views expressed
herein do not necessarily represent those of ADBs Board of Directors, Management, or staff, and may be
preliminary in nature. Your attention is directed to the Terms of Use section of this website.

GOVERNMENT OF THE PUNJAB


IRRIGATION & POWER DEPARTMENT
PUNJAB IRRIGATED AGRICULTURE INVESTMENT PROGRAM-PIAIP

UPDATINGFEASIBILITYSTUDYFORREHABILITATION
ANDUPGRADATIONOFSULEIMANKIBARRAGE

ENVIRONMENTAL&SOCIALIMPACTASSESSMENT(ESIA)REPORT

May2010

NESPAKAABDMCJOINTVENTURECONSULTANTSFORPIAIP

NationalEngineering
ServicesPakistan
(Pvt.)Limited

AAB(Pvt.)
Limited

DevelopmentandManagement
Consultants

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

TABLE OF CONTENTS
EXECUTIVESUMMARY...................................................................................................................1
CHAPTER1: INTRODUCTION.........................................................................................................1
1.1

GENERAL................................................................................................................................1

1.2

BACKGROUND.......................................................................................................................2

1.3

PROJECTOBJECTIVE...............................................................................................................3

1.4

PORJECTDESCRIPTION..........................................................................................................4

1.5

PROJECTLOCATION...............................................................................................................5

1.6

PROJECTAREAOFINFLUENCE...............................................................................................5

1.7

REVIEWOFPREVIOUSSTUDIES.............................................................................................6

1.8

APPROACHESADOPTEDFORTHESTUDY..............................................................................6

CHAPTER2: LEGALANDADMINISTRATIONFRAMEWORKPOLICY................................................11
2.1

GENERAL..............................................................................................................................11

2.2

REGULATORYREQUIREMENTSINPAKISTAN.......................................................................11

2.3

NATIONALCONSERVATIONSTRATEGY................................................................................11

2.4

NATIONALENVIRONMENTALPOLICY..................................................................................11

2.5

GUIDELINEFORENVIRONMENTALASSESSMENT...............................................................12

2.6

ENVIRONMENTALINSTITUTIONSANDTHEIRRESPONSIBILITIES........................................12

2.7

ENVIRONMENTRELATEDSTATUTES...................................................................................13

2.8

FIDICClauses........................................................................................................................15

2.9

ASIANDEVELOPMENTBANKGUIDELINES...........................................................................15

2.10

NATIONALENVIRONMENTALQUALITYSTANDARDS(NEQS)2000.....................................16

2.11

INTERNATIONALCONVENTIONS.........................................................................................17

CHAPTER3: THEPROJECT............................................................................................................18
3.1

HISTORY...............................................................................................................................18

3.2

EXISTINGBARRAGESTRUCTURE..........................................................................................18

3.3

THEPROBLEM......................................................................................................................21

3.4

DESCRIPTIONOFTHEPROJECT............................................................................................21

3.5

LABOURCAMP.....................................................................................................................22

3.7

MATERIALREQUIREMENTS.................................................................................................23

3.8

SOURCEOFMATERIAL.........................................................................................................24

3.8

EQUIPMENTANDMACHINERYYARD..................................................................................25

CHAPTER4: BASELINECONDITION..............................................................................................27
4.1

GENERAL..............................................................................................................................27

4.2

PHYSICALENVIRONMENT....................................................................................................27

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.3

BIOLOGICALENVIRONMENT...............................................................................................45

4.4

SOCIOECONOMICCONDITIONS.........................................................................................54

CHAPTER5: STUDYOFPROJECTALTERNATIVES...........................................................................74
5.1

NOPROJECTOPTION(WORSTCASESCENARIOOPTION)...................................................74

5.2

ADDITIONOFNEWBAYS.....................................................................................................75

5.3

OPTION 2: PROVISION OF FUSEPLUG WEIR AND FLOOD BYPASS CHANNEL (SELECTED

OPTIONFORDETAILDESIGN)..............................................................................................76

CHAPTER6: IMPACTASSESSMENT,MITIGATIONANDENHANCEMENTMEASURES......................78
6.1

POTENTIALIMPACTSOURCES.............................................................................................78

6.2

IMPACTS AND MITIGATIION MEASURES ASSOCIATED WITH THE IMPLEMENTATION OF

THEPROJECT........................................................................................................................78

6.3

IMPACTSANDMITIGATIONMEASURESDURINGDESIGNPHASE.......................................83

6.4

IMPACTANDMITIGATIONMEASURESDURINGCONSTRUCTIONPHASE...........................84

6.5

OPERATIONALANDMANAGEMENT(O&M)PHASE............................................................99

CHAPTER7: ENVIRONMENTALMANAGEMENTPLAN.................................................................101
7.1

MITIGATIONPLAN.............................................................................................................101

7.2

MITIGATIONOFADVERSEIMPACTSATDESIGNPHASE....................................................102

7.3

MITIGATIONADVERSEIMPACTATCONSTRUCTIONPHASE.............................................102

7.4

MONITORINGPLAN...........................................................................................................104

7.5

INSTITUTIONALARRANGEMENT.......................................................................................160

7.6

CHANGEMANAGEMENT...................................................................................................166

7.7

COMMUNICATIONANDDOCUMENTATION.....................................................................167

7.8

WASTEDISPOSALPLAN.....................................................................................................171

7.9

ILLUSTRATEDTRAFFICMANAGEMENT..............................................................................175

7.10

OUTLINEOFEMERGENCYRESPONSEANDCONTINGENCYPLAN.....................................177

7.11

HEALTH,SAFETY&ENVIRONMENT(HSE)PLAN................................................................179

7.12

TREEPLANTATION.............................................................................................................180

7.13

BORROWAREASRESTORATION........................................................................................181

7.14

LANDACQUISITIONPROCEDURE.......................................................................................181

7.15

RISKMANAGEMENTPLAN.................................................................................................182

7.16

TRAININGPLAN.182

7.17

ENVIRONMENTALMANAGEMENTCOST...........................................................................188

7.18

CONCLUSION..199

CHAPTER8: PUBLICCONSULTATION..........................................................................................201
8.1

GENERAL............................................................................................................................201

8.2

LEGALREQUIREMENTFORPUBLICCONSULTATION.........................................................201

8.3

CONSULTATIONMETHODOLOGY......................................................................................201

NESPAK-AAB-DMC

ii

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

8.4

OBJECTIVESACHIEVEDWITHTHEPUBLICCONSULTATION..............................................202

8.5

CONSULTATIONANDDISCUSSIONDURINGIMPLEMENTATION.......................................204

APPENDICES
Appendix2.1

NationalEnvironmentalQualityStandards(NEQS)

Appendix3.1

ConstructionSchedule

Appendix4.1

SamplingProcedureandTestResults

Appendix4.2

WaterQualityGuidelinesandStandards

NESPAK-AAB-DMC

iii

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

List of Figures
Figure-1.1:

Project Location Map

Figure-1.2

Overall Environment Study Area Map

Figure-1.3:

Suleimanki Barrage Environment Study Area Map

Figure-3.1:

Project Layout of Selected Works Scheme

Figure-4.1:

Seismic Zoning Map of Pakistan

Figure-4.2:

Flood Plan near Suleimanki Barrage

Figure-4.3:

Tree Count Falling in Proposed Flood Bypass Channel Map

Figure-7.1:

Proposed Traffic Management Map

List of Tables
Table-2.1:

Effluent Discharge Standards Applicable to the Works

Table-2.2:

Gaseous Emission Levels

Table-2.3:

Noise Emission Levels

Table-3.1:

Source of Raw Material

Table-4.1:

Surface Salinity Statistics

Table-4.2:

Average River Flows Upstream of the Sulemanki Barrage (MAF

Table-4.3:

Peak Discharge of Prominent Years in River Sutlej at Suleimanki Barrage

Table-4.4:

Laboratory Analysis Report of Surface Water Samples

Table-4.5:

Laboratory Analysis Report of Surface Water Samples (FAO limits

Table-4.6

Groundwater Test Results

Table-4.7:

Groundwater Quality for Irrigation Purpose

Table-4.8:

Shallow Ground Water Quality within Canal Command Areas

Table-4.9:

Settlement Structure

Table-4.10:

Religion

Table-4.11:

Languages

Table-4.12:

Demographic Characteristics

Table-4.13:

Age Distribution of Sample Respondents by household Categories

Table-4.14:

Households Distribution According to Caste

Table-4.15:

Education Level of Sample Population

Table-4.16:

Occupation

Table-4.17:

Habitation

Table-4.18:

Source of Drinking Water

Table-4.19:

Source of Light

Table-6.1:

Project Evaluation of Environmental Impacts

NESPAK-AAB-DMC

iv

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table-7.1:

Traffic Survey Conducted at Suleimanki Barrage

Table-7.2:

Environmental Monitoring Plan for the Construction Phase

Table-7.3:

Environment & Management Cost

Table-8.1:

Employment Opportunity at Suleimanki Barrage Rehabilitation Work

Table-8.2:

Public Consultation

List of Plates
Plate 4.1:

A view of Female Participation in Household Relating Task

Plate 4.2:

A view of females participation for livestock activities

Plate 4.3:

A view of Kacha Affected House

Plate 4.4:

Right Side Divide Wall and Fish Ladder Upstream

Plate 4.5:

Left Side Divide Wall and Fish Ladder Upstream

Plate 4.6:

Fazillka Drain entering Barrage Pond from India

Plate 4.7:

Bela Developed in Left Pocket of Pond Area

Plate 4.8:

Consultation with Wildlife Staff at Wildlife Public Park

Plate 4.9:

Consultation with Fishing Department at Suleimanki Barrage

Plate 5.1

Collected During the Consultation with Wildlife Staff

Plate 5.2

Collected During the Consultation with Fishery Staff

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

List of Abbreviation

ADB

Asian Development Bank

amsl

Above Mean Sea Level

AOI

Area of Influence

BOD

Biological Oxygen Demand

BC

Before Construction

CCA

Cultivable Command Area

CMS

Conservation of Migratory Species

COD

Chemical Oxygen Demand

COSHH

Control of Substances Hazardous to Health

DC

During Construction

EC

Electrical Conductivity

EIA

Environmental Impact Assessment

EMMP

Environmental Management & Monitoring Plan

EMP

Environmental Management Plan

EPA

Environmental Protection Agency

EPAs

Environmental Protection Agencies

ESIA

Environmental & Social Impact Assessment

FAO

Food and Agriculture Organization

GCA

Gross Cultivated Area

GoP

Government of Punjab

IPD

Irrigation and Power Department

LMB

Left Marginal Bund

LRE

Left Retaining Embankment

IEE

Initial Environmental Examination

IWT

Indus Water Treaty

M&E

Monitoring and Evaluation

NCS

National Conservation Strategy

NEQS

National Environmental Quality Standards

NOC

No-Objection Certificate

O&M

Operation and Maintenance

P&D

Planning and Development Department

PEPA

Pakistan Environmental Protection Act

PEPC

Pakistan Environmental Protections Council

NESPAK-AAB-DMC

vi

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

PMO

Project Management Office

PPC

Pakistan Penal Code

PPE

Personal Protective Equipment

RSC

Residual Sodium Carbonate

RD

Reduced Distance

RMB

Right Marginal Bund

RRE

Right Retaining Embankment

SAR

Sodium Adsorption Ratio

SCARP

Salinity Control and Reclamation Project

SEMU

Social & Environmental Management Unit

SFA

Social Frame Work Agreement

SMO

SCARPS Monitoring Organization

SOP

Survey of Pakistan

SSOP

Soil Survey of Pakistan

TDS

Total Dissolved Solids

US-EPA

United States Environmental Protection Agency

WAPDA

Water and Power Development Authority

WHO

World Health Organization

WWF

Worldwide Fund for Nature

NESPAK-AAB-DMC

vii

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

UNITS AND CONVERSION FACTORS

Length

1 inch

25.4 millimeters

1 meter

3.281 ft

1 mile

1609 meters =

1760 yards

1 sq. m

10.76 sq. ft

1.196 sq. yd

1 hectares

2.47 Acres

10,000 sq. m

1 sq. km

100 hectares

5280 ft

Area

Volume

1 US wet gallon

0.833 imperial gallon =

3.785 liters

1 US dry gallon

0.967 imperial gallon =

4.404 liters

1 cu. meters

35.28 cu. ft

NESPAK-AAB-DMC

viii

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

EXECUTIVE SUMMARY
S-1

Introduction

Government of Punjab is planning to undertake the rehabilitation of Punjab Barrages and


improvement and modernization of the irrigation and water management system in the
Punjab Province which involve the rehabilitation and up-gradation of the Sulemanki Barrage.
Governemnt of Punjab is looking for ADB fund for ulemanki Barrage Rehabilitation & Upgradation work. The Environmental & Social Impact Assessment study of the proposed
project has been carried out in compliance with Pakistan statutary requirement and Asian
Bank Environment Policy.

Suleimanki Barrage was constructed on Sutlej River during 1924 1926 under the Sutlej
Valley Project (SVP). The barrage was designed for 325,000 cusecs discharge. The barrage
is located about 20km (12miles) from Haveli Lakha Town, Tahsil Depalpur, District Okara.
The barrage is about 150km (94miles) from Lahore, the capital of Punjab Province and
about 450km (281miles) from Islamabad, the federal capital. It is situated on Sutlej River
112km (70miles) downstream of Ferozpur Barrage and 184km (115miles) upstream of Islam
Barrage. Three irrigation canals Pakpattan, Fordwah and Eastern Sadiqia Canals are fed
from this barrage. The total canal command area of all the three canals is 2.5 million acres,
which is 9.25% of the total irrigated area of Punjab (27 million acres). The total canals
command area spread over the six districts of Punjab Province Bahawalpour,
Bahawalnagur, Okara, Pakpattan, Vehari and Lodhran. Thus this barrage has considerable
contributions in the agricultural production of Punjab.

In 1960, under the agreement of Indus Water Treaty, India was given the rights of three
eastern rivers water of Ravi, Sutlej and Beas. Consequently upon the construction of dams
and barrages on river Sutlej and Beas; the discharge in Sutlej was reduced significantly.
Ferozepur Barrage on Sutlej River lies in India just before the river enters Pakistan. India
diverts almost all the river water from this barrage to its own irrigation system and the river
reach at Suleimanki in Pakistan is perpetually bone dry for about 10 months of the year. In
order to feed the three canals that off-take from Suleimanki Barrage inter river link canal
Baloki-Suleimanki Link (B.S Link) was constructed with an initial discharge capacity of
15,800 cusecs for delivery into Sutlej River upstream of Suleimanki Barrage. The BS Link
was later remodeled a few times to the current discharge capacity of 25000 cusecs.

NESPAK-AAB-DMC

ES-1

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Ever since its construction, the structure of Suleimanki Barrage has suffered heavily from
flooding during the monsoon periods. The barrage is about 84 years old now and aging
process together with inadequate/deferred maintenance has also contributed towards
general deterioration of the different components of the Barrage. Irrigation & Power
Department (IPD) engaged National Development Consultants (NDC) in June 1998 for the
safety evaluation of Suleimanki Barrage. The study recommended that rehabilitation of the
barrage be undertaken to ensure safe operation of the barrage. Based on these
recommendations, a Feasibility Study for Rehabilitation & Modernization of the barrage was
conducted and prepared in May 2005. This study is carried out on the basis of the up-dating
of feasibility and detail design of the project. The report updating the previous EIA report and
also address the additional impacts identified during the up-dating feasibility and detail
design of Sulemanki Barrage R&U.

In 2009 with the funding from Asian Development Bank (ADB), the IPD initiated a project
Punjab Irrigated Agriculture Investment Program (PIAIP). The consultancy of the project
was awarded to a joint venture of NESPAK, AAB and DMC. One component of PIAIP is
updating of the Feasibility Study and detailed design for the Rehabilitation and Up-gradation
of Suleimanki Barrage.

S-2

Legal and Administration Framework Policy

The Pakistan Environmental Protection Act (1997) makes it manadatory the project
proponent to undertake (Initial Environmental Examination) IEE or Environmental Impact
Assessment (EIA). For this project it is manadator to prepare and obtain approval of EIA
from EPA under Pak-EPA 1997. The ADBs Safegaurad Policies also required that
Environmental and Social assessment to be conducted for the project which could have
potentially adverse impacts.

Under ADB Environment Policy, projects are to be categorized in to the three environmental
categories; A, B and C according to significance of the adverse environmental impacts. This
Project has been judged to have some adverse environmental impacts, but of lesser degree
and/or significance than those for category A projects. B category is applicable in case of
projects with localized and mitigable impacts. Sulemanki Barrage is not a new mega scale
project. It is a rehabilitation and repair of an already existing structure without causing
change even in storage of water behind the barrage. All impacts shall be local, limited and
mitigable. Such projects according to ADB require an IEE only but the EPA of Pakistan
requires such class B projects to have an EIA. Since the project has to be cleared by EPA
NESPAK-AAB-DMC

ES-2

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

under Environmental Act of 1997, an EIA shall have to be produced for a B category
projects to fulfill the local legal requirement. This makes it more responsive to ADB
Safeguards of category A, which by all means is a superior response to ADB Safeguards.

S-3

Project Details and Alternatives

The studies of structural and mechanical components of the Barrage have envisaged some
structural and hydrological problem together with mechanical defects. If not corrected, the
consequances could be devestrated with the consequent risk of the faliur of the whole
system. Such a faliur could have catastrophic effect on the economy of the farming
community in the command area, result in changes of morphology of the Sutlej River
resulting into inundation and significant erosion of agriculture land.

The scope of work will include but not be limited to repair the barrage structure including
barrage floor as well as floor extension, enhancing the barrage discharge capacity,
replacement of road bridge deck across the barrage, repair/replacement of regulation gates
gearing and hoisting devices, modernization of barrage structure, installation of new
vibrating wire piezometers and physical removal of the shoals (bela) in the pond area, which
is masking the left half of the barrage.

In order to improve the barrage resistance against the uncontrolled breaches, the
embankments will be strengthened leaving adequate free board against 100 year flood. The
bela upstream of the pond area will be partially trimmed to restore the approach conditions
and the capacity of the barrage pond. Upstream and downstream floor of the barrage will be
inspected and necessary repair works will be carried out. In addition, the substrata and voids
underneath the floors will be grouted under pressure. Existing Public Park along the
downstream right guide bank will be further developed under this project.

It is also concluded that the barrage capacity is approximately 100,000 cusecs less than the
100 year return period flood. Two options have been considered to handle the 100 year flood
at Suleimanki Barrage;

Option 1:

Addition of six (6) new bays along the right flank of the barrage to increase
the barrage discharge capacity.

Option 2:

Provision of a spill channel with a spillway and fuse plug guarded spill weir at
RMB, a road bridge across the spill channel for Haveli Lakha-Sulemanki
Road, level crossing at Pakpattant Canal .

NESPAK-AAB-DMC

ES-3

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Neither of these options has any significant or permanent adverse environmental impact and
both options qualify for execution from the environmental point of view. However, option 1
was rejected on technical basis and option 2 has been recommended in the updating
feasibility study for detailed design and implementation.

The project construction acitivities will be completed in three years in such a way that the
river flows will not intrupted in the construction phase. The canal gate repair work will be
undertaken during annual 3 weeks canal closure period. Alternative arrangement will be
provided at Pakpattan Canal during the construction of spillway to maintain the canal supply.
Therefore no extended canal closure will require for the project.

S-4

Environmental Baseline Condition

Baseline Conditions of the project area have been established through the data collected
from the field and unstructured interaction with the local community and officials from varies
department. Previous studies (secondary data) have also used in the development of the
baseline. The report covers the prevailing physical, biological and social environmt of the
area.

The information utilized for the EIA obtained by using GIS technology, stakeholder

consultation including Wildlife, Fishery Department etc field visits carried out by the
environment team and laboratory based testing of the physical environmental parameters.
The objectives of the these consultation were to explaine the project intervention and their
potentioal impacts to the local people and also share the mitigation measures with the local
community and to promote among these communities a genral good will towards the project.

The IPD land available in the close vicinity of the Project site would be utilized for
Contractors facilities and consultants offices and residences. The river water is mainly used
for agricultural purpose. Groundwater is the major source of drinking water for the local
community. It is very important to protect the water sources during the construction phase
from accidental spills of diesel or any chemical, as any spill could percolate to the
groundwater through the sandy stratum at site. Surface water testing at the barrage
indicates that the river water does not meet the WHO standards and is not fit for human
consumption. But the water does meet the NEQS level and FAO standards for agriculture
purposes and fit for irrigation and recreational purpose. Groundwater samples were collected
and tested from the existing hand pump at the barrage and found unsatisfactory for drinking.
It is concluded from the test results that if the groundwater is to be used for the water supply
in the Labour Camp then it is the responsibility of the Contractor to abstract water from
sufficient depth and confirm that it meets the WHO standards.
NESPAK-AAB-DMC

ES-4

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

It was found from ambient air quality monitoring that air is reasonably clean at present as all
the monitored parameters are within the limits of NEQS level. The climate of the area is arid
characterized by long hot summer and short mild winter. Wind speed varies significantly over
the year. Peak values were recorded during May during year 2007. The typical wind
direction is south to north in most of the part of the year.

The barrage pond area provides the habitat of water fowl and many migrating birds visit the
site during winter, while the left guide bank is a habitat of mammals including blue bull, hog
dear and local birds e.g. peacock and partridge. Fish ladders are provided along both the
divide walls at Suleimanki Barrage. Both the fish ladders are in working condition. However
there is significant amount of vegetation and silt deposit found at the upstream end of the
fish ladders, which obstructs the fish movement and need to be removed.

The Socio Economic Survey was conducted with the objectives to assess prevailing socioeconomic conditions of the related communities and to predict the effects of the proposed
different alternatives of rehabilitation works. Simple Random Sampling Technique was used
to draw representative sample. The average household size is 6.3 and the sex ratio (female:
male) is 100:107. There are 5 Primary, 2 Middle and 1 High School for boys, 4 Primary, 1
Middle School and 1 High School for girls found in the area. The average literacy level of the
area is 47%. It was found that 77% of the household engaged in agriculture. It was found
that 100% of the respondent speak Punjabi language and carry Islam as a religion. The
major castes of the area are Maher and Watto. Rice, Wheat and Cotton are the most popular
crops cultivated in the study area. Females participation for the betterment of the family is
more as compared with the males. In fact, rural women in the study area work 14 hours a
day. Women participate in agriculture activities such as sowing, hoeing, harvesting,
threshing, storage of crops and feeding the livestock.

S-5

Potential Impacts, Mitigation Measures and EMP

The environmental and social impact assessment was carried out and it was revealed that
the project activities will not cause any significant disturbance and inconvenience to local
community and natural environment of the area. Construction related impacts such as air
pollution, noise etc will be mitigated by the implementation of the EMP. All the solid waste
and wastewater generated from the project activities and labour camp should be disposed of
according to the waste disposal plan, which is a component of the EMP. About 309 numbers
of trees, mainly Sufaida (Eucalyptus Camaldulensis) will require uprooting for the
construction of flood bypass channel. This will be compensating by planting minimum 1550
NESPAK-AAB-DMC

ES-5

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

new trees in the surrounding area of the proposed flood channel. On the other hand the
development of lake in the existing public park will enhance the environment condition of the
area

During construction, the Contactors work force is expected to be largely from the local
population, which will enhance the economic opportunities for the locals of working age
group. The improvement in existing Public Park is also recommended to enhance the
biodiversity of the project area. This will also raise the aesthetic value of the area and attract
more visitors.

Socioeconomic conditions of the project area will generally be positively impacted due to the
project implementation. The few negative impacts will be insignificant impacts. 11 houses
will be require to re-locate from the RMB, fall in the work area. Resettlement Action Plan will
be prepared and submitted under separate cover. No any private land acquisition involve for
the construction of the spillway channel and rehabilitation of barrage components. The land
nominated for the batching plant and labour camp as shown in the figure 1.3 will be arranged
by IPD. Further enhance the project acceptance by the locals, some socioeconomic
development schemes for the improvement of education, health, employment, infrastructure
facilities etc should be included in the project.

The total estimated cost of the implementation of the EMP is Rs. 25.1 Million ($. 295,298).

S-6

Conclusion

The potential impacts of the project are associated with only the construction phase of the
project and all of these impacts are temporary and reversible in nature. These impacts can
be mitigated through the proper implementation of the EMP. Therefore it is concluded that
the project is environmentally friendly, financially viable, economically sustainable,
genderally neutral and pro-poverty alleviation.

NESPAK-AAB-DMC

ES-6

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

CHAPTER 1:

INTRODUCTION

1.1

GENERAL

The province of Punjab is only one fourth of the total area of Pakistan yet its fertile land
yields more than 50% of the total national agricultural produce. One of the reasons for such
high agricultural production is the efficient use of water resources through Punjabs irrigation
network. Punjab irrigation network comprises of 24 canal fed by 14 barrages/Barrage and 9
major inter-river link canals, irrigating more than 27 million acres of land. There are two
barrages on Sutlej River, Suleimanki and Islam Barrage. Suleimanki is the first barrage on
Sutlej after this river enters into Pakistan. Major part of the Left Marginal Bank virtually forms
the international boundary between Pakistan and India.

Pakpattan Canal with a design discharge of 6,594 cusecs at head, off-takes from the right
flank; and Sadiqia and Fordwah Canals with designed discharges of 6,080 cusecs and 3,366
cusecs respectively, off-take from left bank of the river. Sadiqia and Fordwah irrigate
Bahawalnagar and Bahawalpur districts. Pakpattan Canal irrigates the land in the districts of
Pakpattan, Okara, Vehari and Lodhran. The total canal command area (CCA) of all three
canals is approximately 2.5 millions acres, which is about 9% of the 27 millions acres of the
total area irrigated area of Punjab Province. Thus, the barrage contributes valuable 9% of
the agricultural production of Punjab.

Ferozepur Barrage on Sutlej River lies in India just before the river enters Pakistan. India
diverts almost all the river water from this barrage to its own irrigation system and the river
reach at Suleimanki in Pakistan is perpetually bone dry for about 10 months of the year. In
order to feed the three canals that off-take from Suleimanki Barrage inter river link canal
Baloki-Suleimanki Link (B.S Link) was constructed with an initial discharge capacity of
15,800 cusecs for delivery into Sutlej River upstream of Suleimanki Barrage. The BS Link
was later remodeled a few times to the current discharge capacity of 25000 cusecs. The
barrage is located about 20km (12miles) from Haveli Lakha Town, Tahsil Depalpur, District
Okara. It is situated on Sutlej River 112km (70miles) downstream of Ferozpur Barrage and
184km (115miles) upstream of Islam Barrage. The barrage is about 150km (94miles) from
Lahore, the capital of Punjab Province and about 450km (281miles) from Islamabad, the
federal capital.

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

1.2

BACKGROUND

Suleimanki Barrage was constructed during 1924-1926 on Sutlej River under the Sutlej
Valley Project (SVP). The barrage feeds Pakpattan, Fordwah and Eastern Sadiaqa Canals.
The barrage was formally commissioned on April 12, 1926. The barrage was designed for
325,000 cusecs discharge. Sadiqia and Fordwah Canals commenced water supply on 1st
May 1926 and Pakpattan Canal on 1st June 1926.

Ever since its construction, the structure of Suleimanki Barrage has suffered heavily from
flooding during the monsoon periods. The barrage is about 84 years old now and aging
process together with inadequate/deferred maintenance has also contributed towards
general deterioration of the different components of the Barrage. Irrigation & Power
Department (IPD) engaged National Development Consultants (NDC) in June 1998 for the
safety evaluation of Suleimanki Barrage. The study recommended that rehabilitation of the
barrage be undertaken to ensure safe operation of the barrage. Based on these
recommendations, IPD awarded the work of carrying out Feasibility Study for Rehabilitation
& Modernization of the barrage to the joint venture (JV) of NDC and NESPAK in association
with ATKINS of UK, called Punjab Barrages Consultants (PBC). The Consultants submitted
the Feasibility Study Report in May 2005.

In 1960, under the agreement of Indus Water Treaty, India was given the rights of three
eastern rivers water of Ravi, Sutlej and Beas. Consequently upon the construction of
Bhakra/Nangal Dam on river Sutlej and Pandoh & Pong Dam on Beas; the discharge in
Sutlej was reduced significantly. The Ferozepur Barrage built in India on Sutlej River
immediately before the river enters Pakistan, stops almost all the water and the river remains
bone dry for about 10 months of the year. This forced Pakistan to carry a significant amount
of works for transporting water from western rivers through link canals to feed the canals off
taking from the eastern river. Inter-river link canal Baloki-Suleimanki Link (B.S Link) offtaking from Ravi River at Balloki barrage was constructed with a discharge of 15,800 cusecs
to be delivered upstream of Suleimanki in 1958. The canal was later remodeled for a
discharge of 18,500 cusecs, again to 22,000 cusecs and finally to 25000 cusecs.

Historic discharge data of the Sutlej River at Suleimanki Barrage from 1922-2008 indicates
that the flood discharge in the river exceeded the designed capacity of the barrage four
times; in 1947 (325,000 cfs), 1950 (332,000 cfs), 1955 (597,000 cfs) and 1988 (499,000 cfs).

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Number of controlled and uncontrolled breaches occurred in 1988 in both the left and right
marginal bunds.

1.3

PROJECT OBJECTIVE

Since signing of the IWT in 1960, India has construction two storage dams on Sutlej River
and almost all of the flows of the river, except the floods that cannot be stored in the dams,
are being used in India. The construction of storage dams in India has significantly reduced
the flood discharges in the river. However, the flood of 1988 has somewhat signified that the
storage capacity of eastern rivers barrages are not enough for significant mitigation or
synchronization of high flows of the rivers and its tributaries

Most of the 14 barrages in Punjab are now more than 80 years old and are in acute distress
owing to aging, design deficiencies, constructional defects, hydraulic and mechanical
problems, inadequate operation and maintenance, and drastic changes in river morphology
as a result of the implementation of the IWT. During the recent past several serious
damages have also been reported. Serious damage to any of these barrages resulting in an
interruption of irrigation supplies can have disastrous implications on the countrys economy
and the population of the area. The rehabilitation and modernization of these barrages has
therefore been considered by the Government as an urgent necessity.

This project aims to modernize water resources and irrigation infrastructure at the Sulemanki
Headwork. Because of the very low negligible flows during non-monsoon period
(approximately 10 months of the year) the morphology of the river channel has drastically
changed and there is general aggradation in the main stream due to sand drifting. The pond
area of the barrage has also heavily silted up especially in the right half where the high shoal
has come very close to the divide wall. The main problems which need to be addressed in
this project are:

The barrage capacity is about 100,000 cusecs less than the calculated 100 years
return flood. Increase the barrage capacity or provide the alternative arrangement
e.g. flood bypass channel to handle the 100 years flood at the barrage.

The oblique approach of the river channel to the barrage and sedimentation
problems in the canals with a consequent reduction in the discharge capacity of the
barrage is an important issue.

Exceptionally high floods caused heavy damages through breaches in the marginal
bunds because the barrage capacity is considerably less than the 100 years return

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

flood. The flood embankments are deficient with respects to the highest flood level of
1988 and need strengthening.

River training works especially pertaining to pitched island constructed about 4km
upstream of the barrage to keep the river approach straight is not providing the
anticipated results and the main channels strikes the right bank.

Bela formation and masking upstream of the barrage. This reduce the barrage
capacity.

The decking of the road bridge has been deteriorated and become risky for present
traffic requirements.

Repairing / modernization of barrage machinery for the smooth operation of the


barrage.

1.4

Need for the enhancement of barrage capacity for severe floods.

Need for improving the road communication system.

PORJECT DESCRIPTION

This Project envisages updating of feasibility and detailed design of rehabilitation and up
gradation works at Sulemanki Barrage. In updating of feasibility study the following two
options were considered and option 2 was recommended for detail design.

Option 1:

Increasing Barrage Capacity by Addition of Bays

This option requires addition of six bays (360 ft water way) along the right flank of the
barrage. The head regulator of Pakpattan canal will have to be dismantled and new regulator
will have to be constructed. The entire upstream and downstream guide banks along the
right side of the barrage will have to be dismantled and reconstructed at the new location at
the end of the extended portion of the barrage. Part of the public park on the downstream
side will be utilized and made part of the barrage.

Option 2:

Proposed Flood Bypass Arrangement

Provision of flood bypass arrangement requires Spillway on RMB, level crossing at the
Pakpattan Canal and a Road Bridge on Haveli Lakha-Sulemanki road.

The environmental and social aspects associated with both options are described in detail in
chapter 6 Study of Project Alternatives. Option 2 was selected on environmental, social
and technical basis for detail design. The scope of work of selected option includes the
following components:

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Provision of flood bypass channel, spillway/fuse plug, level crossing at Pakpattan


Canal and a road bridge on Haveli Lakha - Sulemanki Road.
Repairs of cracks, contact grouting underneath the floors.
Raising and strengthening of river control embankments and spurs to withstand flood
pressure liable to be exerted on them.
Installation of instrumentation and control system for uplift pressure monitoring.
Rehabilitating and upgrading the operational capability of the gates and hoisting
mechanism at the barrage.
Inspection of the stilling basin and repair or re-design if require.
Taming of the upstream bela (shoal).
Improve the existing wildlife park to enhance the aesthetic value and biodiversity of
the area.
A detailed description of the project is included in chapter 3.

1.5

PROJECT LOCATION

The barrage is located at latitude of 30-33 North and longitude 73-52 East. It is about 12
miles East of Haveli Lakha Town. The barrage is about 70 miles below Ferozepur Barrage
(India) and 115 miles upstream of Islam Barrage. The barrage falls in Tahsil Depalpour,
District Okara. The barrage location is indicated on Figure-1.1. It is connected to other parts
of the country through roads and is about 94 miles from the provincial capital Lahore and
about 281 miles from Islamabad. Other main cities near the barrage include Okara at about
31 miles, Pakpatan at about 37.5 miles and Kasur at about 60 miles.
1.6

PROJECT AREA OF INFLUENCE

The area of project influence referred to as the area of influence (AOI) is the area likely to be
affected by the project, including all its ancillary aspects such as power transmission lines,
pipelines, canals, access roads, waste disposal areas, batching plant and Labour camp as
well as any unplanned developments induced by the project.
The major features of the area and proposed locations of the contractors facilities are
indicated on the overall environmental study area map and Sulemanki Barrage environment
map are shown in Figure-1.2 and 1.3 respectively. The map prepared using GIS technology
and satellite image.

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

1.7

REVIEW OF PREVIOUS STUDIES

The barrage experienced substantial retrogression of up to 6 feet in the very first flood
season, which continued during 1927. The barrage is now 84 years old and in the aging
process and normally the maintenance is either inadequate or deferred. A distorted flow
pattern and an oblique entry into the guide bank zone has put the bed configuration into a
drastic imbalance causing severe masking close to the structure which has contributed to
general deterioration of the barrage. The Irrigation & Power Department (IPD) engaged
National Development Consultants (NDC) in June 1998 for a safety evaluation of Suleimanki
Barrage. This study recommended that rehabilitation of the barrage be undertaken to ensure
its safe operation besides further investigation for sub-surface flow and model study for river
training works. Based on these recommendations, IPD awarded the work of carrying out
Feasibility Study for Rehabilitation & Modernization of the Suleimanki, Tanusa & Khanki
Barrages to the joint venture (JV) of NDC and NESPAK in association with ATKINS of UK
called Punjab Barrages Consultants (PBC). The Consultants submitted the Feasibility Study
Report in May 2005. The study made recommendations to repair the barrage structure
including barrage floor in main weir as well as undersluice section, road bridge deck across
the barrage, regulating gates and hoists, modernize barrage structure, install new vibrating
wire piezometers and physically remove the large bela masking the left half of the barrage in
the pond area. The study also conclude that the barrage capacity is approximately 100,000
cusecs less than the 100 years return flood and need to be raised by redesigning of barrage
or provision of flood escape channel.

1.8

APPROACHES ADOPTED FOR THE STUDY

The environmental and social data were collected and analyzed for the overall
environmental study area. Primary data, including sampling and testing of the physical
environmental parameters were collected during site visits conducted from September 2009
to November 2009. The test results will be included and analyzed in the final EIA at the
completion of the detail design. Secondary data for the overall study area was reclaimed
from other institutions e.g. Wildlife department, Fishery, Irrigation & power department,
SCARPS Monitoring Organization, SEMU and Directorate Land Reclamation etc.

The base line data was developed and analyzed to identify potential environmental impacts
of the Project. A risk based methodology was adopted to identify the high risk activities and
suggest their mitigation measures. Where possible, eliminating the risk by altering the scope
or method of execution of work was preferred rather than minimizing the risk with control

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

measures. Public consultations were also undertaken inclusive of gender study, to take into
account the public point of view about the project.

1.9

OBJECTIVE OF THE REPORT

This report comprises the Environmental & Social Impact Assessment (EIA) study of the
project area. Environment Assessment (EA) takes into account of the natural environment
(air, water, land, flora & fauna); human health and safety. This study evaluates the projects
potential environmental risks and impacts on its areas of influence, planning, designing and
implementation to preventing, minimizing, mitigating or compensating for adverse
environmental impacts and enhancing positive impacts throughout project implementation.

The Social Assessment (SA) has been conducted to evaluate the projects potential positive
and adverse effects on the affected people and to examine project alternatives where
adverse effects may be significant. The breadth, depth and type of analysis in the social
assessment are proportional to the nature of the project and scale of its potential effects,
positive or adverse, on the affected people. The Socio- Economic Survey was conducted by
an experienced and qualified team of sociologists.

This report updating the previous EIA submitted in 2005 and covering all the impacts
identified during updating fesibility and detail design of the Sulemanki Barrage R&U.

1.10

STRUCTURE OF THE REPORT

This report is divided into following chapters.


Chapter # 1

Introduction

Chapter # 2

Legal and Administrative framework policy

Chapter # 3

Project Description

Chapter # 4

Environmental and Social Baseline Conditions

Chapter # 5

Analysis of Alternatives

Chapter # 6

Impact Assessment, Mitigation and Enhancement Measures

Chapter # 7

Environmental Management Plan

Chapter # 8

Public Consultation and Information Disclosure

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Figure 1.1 Project Location Map

NESPAK-AAB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Figure 1.2:
NESPAK-AAB-DMC

Overall Environment Study Area Map


9

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Figure 1.3: Suleimanki Barrage Environment Study Area Map


NESPAK-AAB-DMC

10

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

CHAPTER 2:

LEGAL AND ADMINISTRATION FRAMEWORK


POLICY

2.1

GENERAL

This chapter provides an overview of the policy framework and national legislation and
international obligations that apply to the proposed Project. The Project is expected to
comply with all national legislations and Asian Bank Safeguards Polices relating to
environmental and social issues, and to obtain all regulatory clearances required.

2.2

REGULATORY REQUIREMENTS IN PAKISTAN

Pakistan Environmental Protection Act 1997 is the primary legislation which applies in
Environmental Assessment studies in Pakistan. Under section 12 of the Act a project falling
under any category specified in Schedule II (SRO 339(1)/2000) require the proponent to file an
EIA with the concerned Environmental Agency, which in case of Sulemanki Barrage is EPA
Punjab.

2.3

NATIONAL CONSERVATION STRATEGY

The Pakistan National Conservation Strategy (NCS) was approved by federal cabinet in
March 1992 and is the principle policy document on environmental issues in the country. The
NCS outlines the countrys primary approaches towards encouraging sustainable
development, conserving natural resources and managing resources. The NCS has 68
specific programmers in 14 core areas in which policy intervention is considered crucial for
the preservation of Pakistans natural and physical environment. The core areas that are
relevant in the context of the proposed Project are pollution prevention and abatement,
conserving biodiversity and preservation of cultural heritage.

2.4

NATIONAL ENVIRONMENTAL POLICY

The National Environmental Policy provides an overarching framework for addressing the
environmental issues facing-Pakistan, Particularly pollution of fresh water bodies and coastal
waters, air pollution, lack of proper waste management, deforestation, loss of biodiversity,
desertification, natural disasters and climate change. It also gives directions for addressing
the cross sectoral issues as well as the underlying causes of environmental degradation and
meeting international obligations. The policy provides broad guidelines to the Federal

NESPAK-AAB-DMC

11

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Government, Provincial Government, Federally Administrated Territories and Local


Government for addressing environmental concerns and ensuring effective management of
their environmental resources.
2.5

GUIDE LINE FOR ENVIRONMENTAL ASSESSMENT

The Pak-EPA has published a set of environmental guidelines for conducting environmental
assessments and the environmental management of different types of development projects.
The guidelines relevant to the proposed Project are listed below:
2.5.1

Guidelines for the Preparation and Review of Environmental Reports, Pakistan


Environmental Protection Agency, 1997
The guidelines, targeted at project proponents, specify:

The nature of the information to be included in environmental reports

The minimum qualification of the EIA conductors appointed

The need to incorporate suitable mitigation measures at every stage or project


implementation

The need to specify monitoring procedures

The report must contain baseline data relating to the project area, an interpretation of the
data and mitigation measures.

2.5.2

Guidelines of Public Consultation, Pakistan Environmental Protection Agency,


May, 1997
These guidelines deal with possible approaches to public consultation and techniques for
designing an effective program of consultation that reaches out to all major stakeholders and
ensure their concerns are incorporated in any impact assessment study.

2.6

ENVIRONMENTAL INSTITUTIONS AND THEIR RESPONSIBILITIES

i.

Provincial EPA

The IPD will be responsible for providing the complete environmental documentation
required by the provincial EPA and remain committed to the approved project design. No
deviation is permitted during project implementation without the prior and explicit permission
of the EPA.

ii.

Provincial Departments of Forestry and Wildlife

The rehabilitation works are expected to involve some clearing of vegetation that exist on
IPDs land where labour camp and batching plant are to be constructed. Widening and
strengthening of the embankments may also involve uprooting of trees. The contractor will
NESPAK-AAB-DMC

12

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

inform formally to the Punjab Forest Department and IPD, even if these trees fall in the area
of IPD before undertake any cutting/uprooting.

iii.

Local Government and Municipalities

The IPD and its contractors must ensure that the project meets the criteria of district
governments as related to the establishment of construction camps and plants, and the safe
disposal of wastewater, solid waste, and toxic materials. The IPD will coordinate and monitor
environment-related issues.

iv.

Social & Environmental Management Unit (SEMU)

Irrigation and Power Department (IPD), Government of Punjab under Punjab Irrigation and
Drainage Authority (PIDA) established the Social and Environmental Management Unit
(SEMU) in December 2006 to enable it to address the environmental and social issues in a
timely and effective manner during operation, maintenance, rehabilitation, construction of
new canals and drains etc. SEMU could be involved as an independent environmental
monitoring organization during construction phase of this Project.

2.7

ENVIRONMENT-RELATED STATUTES

This section outlines statutes apart from the Pakistan Environmental Protection Act, 1997,
which are relevant to the project.

The Forest Act, 1927 (and Provincial Acts and Rules)


The Act, inter alia, deals with the matters related with protection and conservation of natural
vegetation/habitats. In that regard it empowers the concerned agency to declare protected
and reserved forest areas and maintaining these. In spite of the fact that it recognizes the
right of people for access to the natural resources for their household use, it prohibits
unlawful cutting of trees and other vegetation. Cutting trees will require for provision of flood
bypass channel and strengthening the embankments work in this Project. The permission is
required prior to undertake any tree cutting from the area under the charge of Forest
Department of Punjab province. The tree belts along canal sides are protected Forest under
the Forest Act 1927 and are managed under Canal Side Plantation Rules 1960.

Government of Punjab, Forestry, Wildlife, Fisheries and Tourism Department


(Notification No. FOFT (EXT) VIII. 17/96 Dated 1998
In Punjab, should the number of trees to be felled for a project exceed 100, or if the project
falls within the jurisdiction of more than one district, a committee comprising the

NESPAK-AAB-DMC

13

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Commissioner of the division covering the districts, the Conservator of Forests, and the
Superintending Engineer of the IPD must accord their approval.

Provincial Wildlife (Protection, Preservation, Conservation and Management) Act,


Ordinances and Rules
In addition to empowering provincial wildlife department to establish game reserves, parks,

and wildlife sanctuaries, these acts regulate the hunting and disturbance of wildlife. This law
Will help in eliminating any tresspassing into Protected Areas.

Antiquities Act, 1975

The Antiquities Act relates to the protection, preservation and conservation of


archaeological/historical sites and monuments. There are no archeological sites or cultural
heritage site inside or near the project area. Nevertheless if there is chance find during the
construction phase this law would provide due guidance.

Provincial Local Government Ordinances, 2001

These ordinances, issued following the devolution process, establish regulations for land
use, conservation of natural vegetation, air, water, and land pollution, the disposal of solid
waste and wastewater effluents, as well as matters related to public health and safety. This
law will help as and when a participatory management of irrigation system becomes the
order of the day.

Factories Act, 1934

The clauses relevant to the project are those that are related with the health, safety and
welfare of workers, disposal of solid waste and effluent, and damage to private and public
property. The Factories Act also provides regulations for handling and disposing of toxic and
hazardous materials. There are no factories / industries inside or around the Project area.
However, indirectly the factories and industries contributing pollution into Ravi and Sutlej
rivers become a matter of concern for water behind the rehabilitated Sulemanki Barrage.

Land Acquisition Act 1894

Land Acquisition Act (LAA), 1894 is the primary law governing land acquisition in Pakistan.
For the acquisition of land, the above-mentioned Act, rules and regulations are followed
whether the acquisition is for Government of Punjab or any other agency. Up to this stage no
permanent land acquisition has been anticipated in the design of the project. Should there
be a need for temporary acquisition, this law would be of help.

NESPAK-AAB-DMC

14

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

2.8

FIDIC CLAUSES

The size and nature of the work to be undertaken for rehabilitation and modernization of
Sulemanki Barrage is such that it is expected to involve international contractor therefore
following FIDIC clauses have been considered to address the environmental aspects of the
project:

Clause 8.2

Site operation and methods of construction

Clause 19.1

Safety, security of environment in general

Clause 27.1

Fossils

Clause 42.1

Possession of site and access thereto

Clause 42.2

Right of ways and facilities in the project area

2.9

ASIAN DEVELOPMENT BANK GUIDELINES

The Asian Development Banks Environmental Safeguard Policy requires that environmental
considerations be incorporated in to ADB operations to ensure that the project will have
minimal environmental impact and be environmentally sound.
The following guidelines shall be adopted:

Environmental Category

According to ADB Environment Policy, projects are to be categorized in to the following


environmental categories; A, B, or C as given in the table below. At any stage the category
can be changed with the approval of the chief compliance officer if further studies and
investigations reveal that the projects potential impacts are worse, minimal or negligible.

ADB Environmental Categories

Category A:

Projects with potential for significant adverse environmental impacts.


This is applicable in case maga projects causing global or at least regional impacts. This
types of project require a first class EIA to be produced and implemented. This category
consider with Category A of the EPA 1997.

NESPAK-AAB-DMC

15

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Category B:

Projects judged to have some adverse environmental impacts, but of lesser degree and/or
significance than those for category A projects.

Category C:
Projects unlikely to have adverse environmental impacts.

Category B is applicable in case of projects with localized and mitigable impacts. Sulemanki
Barrage is not a new mega scale project. It is a rehabilitation and repair of an already
existing structure without causing change even in storage of water behind the barrage. All
impacts shall be local, limited and mitigable. Such projects according to ADB require an IEE
only but the EPA requires such class B projects to have an EIA. Since the project has to be
cleared by EPD under Environmental Act of 1997, as an EIA shall have to be produced for a
B category projects to fulfill the local legal requirement. That makes it responsive to ADB
Safeguards of category A, which by all means is a superior response to ADB Safeguards.

2.10

NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS) 2000

The NEQS 2000 of EPA under Environmental Protection Act 1997 specify the following
standards:
1

Maximum allowable concentration of the Pollutants, (32 parameters) in emission and


liquid industrial effluents discharge to inland water.

2. Maximum allowable concentration of pollutants (two parameters) in gaseous


emission from vehicle exhaust and noise emission from vehicles.
3. Maximum allowable noise level from vehicles
These standards apply to the gaseous emission and liquid effluents discharged by batching
plants, campsite and construction machinery. The standards for vehicles will apply during
the construction as well as operation phase of the project. Precise standards for air quality
are not available under NEQS, 2000. The National Environmental Quality Standards (NEQS)
2000 is included in Appendix 2.1.

NESPAK-AAB-DMC

16

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

2.11

INTERNATIONAL CONVENTIONS

Pakistan is signatory to a number of International Conventions, Protocols and


Understandings relating to the environment. Those relevant to the project are described in
the following paragraphs.

Convention on Biological Diversity

The Convention of Biological Diversity was the outcome of the Earth Summit held in Riode-Janeiro in 1992. The Convention binds the signatories to respect, protect and conserve
the earth environment and bio-diversity through sustainable use of natural resources. In all
development projects in Pakistan the protocols of this convention are respected in letter and
spirit.

Ramsar Convention

The Convention on Wetland of International Importance, especially as Waterfowl Habitats


held in Iran in 1972 at village Ramsar in Iran, places an obligation on the signatories to
protect habitats of migratory waterfowl. Sulemanki Barrage is not a notified Ramsar site but
as additional measures, Ramsar spirit shall be maintained during the construction phase of
the project.

Bonn Convention

The Convention on the conservation of migratory species of wild animals was held in Bonn
in 1979. The Convention broadens the scope of Ramsar to include migratory species other
than water fowl. Not being a Ramsar site, this protocol is not obligatory for Sulemanki
Barrage. But it will be respected during construction phase to the extent that no damage is
caused to habitat of any species.

NESPAK-AAB-DMC

17

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

CHAPTER 3:

3.1

THE PROJECT

HISTORY

Suleimanki Headworks located at about 12 miles east of Haveli Lakha Town. The barrage
was constructed near the village Suleimanki during 1924-26 as a component of Sutlej Valley
Project. Soon after its commissioning in 1926, the Barrage experienced substantial
regression, in fact in the very first flood season, which necessitated some modifications and
alternations in 1930. Over the past eighty years or so the Barrage has facilitated an efficient
flow of irrigation water in three major canals; Sadiqia (design discharge: 6080 cusecs) and
Fordwah (design discharge: 3366 cusecs) canals which off take from the left bank and
irrigate areas in Bahawalnagar and Bahawalpur Districts while the Pakpattan Canal (design
discharge 6594 cusecs) off take from the right bank meeting irrigation demands in the area
in Okara, Pakpattan, Vehari and Lodhran Districts. The three canals collectively command
an area of 2.5 million acres. Barrage Engineers opine that ordinarily, barrages like
Suleimanki have an efficient life of about 50 years and beyond which at some point old age
symptoms start showing up.
3.2

EXISTING BARRAGE STRUCTURE

At the time of completion of Barrage structure in 1927 the barrage comprised of:
Waterways

A main weir consisting of 24 bays of 60ft each with crest level 560ft amsl.

Right and left pocket, each consisting of 8 bays of 30ft each with crest level 8ft lower
than the main weir i.e. 552ft amsl.

Stilling Basin
The stilling basin for both main weir and under sluices is placed at RL 549.0 ft amsl. The
corresponding length for main weir and under sluices is 35 ft and 80 ft respectively. Two
rows of friction blocks of 2 ft high have been provided in the main weir.
Divide Wall
There are two divide walls at Suleimanki Barrage separating the central weir from the right
and left undersluices. Both the divide walls are 700 ft (213.36 m) long, which are extending
much beyond the Canal Regulators (Sadiqia Canal along left flank and Pakpattan Canal
along right). The top of the divide wall is 572ft amsl.
Fish Ladder
Two fish ladders exist at Suleimanki Barrage along both divide walls. During the course of
floods fish ladders function well and during low flow these remain dry.
NESPAK-AAB-DMC

18

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Guide Bank
The guide banks at Suleimanki Barrage are unique as compared to any other barrage as
they are of converging type. The abutment to abutment width of the barrage is 2223 ft, while
the width between guide banks at the nose is 1600 ft.
Road Bridge
Existing Structural Steel Bridge over the barrage is in bad condition and its deck needs
immediate replacement. Structural analysis of this bridge, as carried out during feasibility
design, has revealed that main steel members of the supporting system of the bridge are in
good condition and quite serviceable for future use except the deck.
Canal Head Regulator
There are three head regulators of off-taking canals from the barrage namely Pakpattan
Canal, Fordwah Canal and Sadiqia Canal. There are 8 bays in Pakpattan Canal head
regulator, while Sadiqia Canal and Fordwah Canal have 7 and 5 bays respectively. All canal
regulators have 20 ft clear bays separated by 4 ft wide masonry piers. Bifurcating pier
between Fordwah and Sadiqia Canal is 8 ft wide. Masonry arches of the bridges are
supported by these piers. Piers are supported by plain concrete floor, which is locally thicken
at pier locations and serves as foundation support for the pier. The steel gates are rusted
and need immediate repair or replacement.
Flood Retaining Bunds
Right and Left Marginal Bunds extending either side to a distance of about 10 miles
upstream of the weir. LMB of the barrage virtually forms the border between Pakistan and
India and controlled by the Pakistan Army and Rangers.
3.2.1

Barrage Components

(a) Main Weir

Design discharge

325,000 Cusecs

Total width between the guide wall

2223 ft

Water way including undersluices

1920 ft

Highest flood level upstream (u/s)

RL 572.00

Highest flood level downstream (d/s)

RL 569.00

No. of Bays

24

Width of each Bay

60

Pier thickness

7 ft

Crest width

13.5 ft

Crest level

RL 560.00

NESPAK-AAB-DMC

19

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

(b) Left and Right Under sluices

No of bays

16

Width of each bay

30 ft

Pier thickness

5 ft

Crest level

RL 552

8+8

(c) Divide Wall

Top Level

RL 572

Top Width

5 ft

(d) Guide Banks

Left

Length U/S (ft)

3500

3500

Length D/S (ft)

1200

1200

Top level (RL)

579

579

Top Width

56

56

Free Board (ft)

Front side slope

2:1

2:1

Rear side slope

3:1

3:1

(e) Marginal Bund

(f)

Right

Left

Right

47,500

Length (ft)

63,000

Canal Head Regulator


Item

CANALS
Pakpattan

Capacity (Cusecs)

Sadiqia

Fordwah

6594

6200

3465

Crest level RL

559.00

559.00

561.50

Floor RL

552.00

552.00

552.00

Full supply level RL

567.30

567.50

567.50

No. of Bays

Width of each Bay

20

20

20

Pier thickness (ft)

555.30

557.50

559.50

D/S Floor level

NESPAK-AAB-DMC

20

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

3.3

THE PROBLEM

Suleimanki barrage is now 84 years old and in the aging process along with inadequate or
deferred maintenance has resulted in general deterioration and damages of its different
components like the regulation gates and hoisting equipment. The distorted flow pattern
oblique entry into the guide bank zone has provoked many problems, any further damage to
this barrage can result in colossal losses in the form of total or partial disruption of irrigation
supplies, agricultural crops, loss of government revenue, and rehabilitation cost of
emergency repairs. The barrage has therefore been identified as a structure requiring
repairs.
The wind system, the wooden deck, the road bridge all are at least 83 years old. Though the
brick masonry not showing any apparent sign of deterioration but it needs to be examined
closely and will be appropriately repaired if required. After the Indus Water Treaty, the pond
behind the headworks receives water from B.S. link canal and feed to Eastern Sadiqia,
Fordwah and Pakpattan canals. The water received from B.S. link canal is too little to fully
occupy the whole span of the river and therefore leads to bela formation and reduce the
pond capacity. Plates 3.1 to 3.4 are shown the different components of the barrage.
The results of frequency analysis for the estimated flood peak for the 100 years return period
is 422,000 cusecs but the discharge calculation based on water level gate opening data of
1988 flood shows that 330,000 cusecs passed through the barrage and as reported in FFP
at 2009, a discharge of 100,000 cusecs passed through breaches. Therefore a discharge of
430,000 cusecs has been adopted as design flood for R&U works of the barrage.
Realizing the gravity of the situation of this barrage Punjab Government has given due
attention to Sulemanki Barrage and has included it in the Phase-I program of rehabilitation of
barrages in Punjab.
3.4

DESCRIPTION OF THE PROJECT

The project aims to modernize water resources and irrigation infrastructure at the Suleimanki
Barrage. The project is designed to address the following issues:

The oblique approach of the river channel to the barrage encourages sedimentation
in the Barrage pond and reducing pond capacity is an important issue to address.

Exceptionally high floods caused heavy damages through breaches in the marginal
bunds because the barrage capacity is less than the 100 years return flood value.
The flood embankments are deficient with respects to the highest flood level of 1988.

NESPAK-AAB-DMC

21

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

River training works especially pertaining to pitched island constructed about 4km
upstream of the barrage to keep the river approach straight is not providing the
anticipated results and the main channels strikes the right bank.

The decking of the road bridge has been deteriorated and become risky for present
traffic requirements.

Repairing / modernization of regulation machinery for the smooth operation of the


barrage.

Need for the enhancement of barrage capacity for 100 years return flood.

3.4.1 COMPONENTS OF THE PROJECT


The works include both Civil and Mechanical/Electrical works. A construction schedule is
included in Appendix 3.1. The components of work are as follows:
Civil Works
Provision of Flood Bypass arrangement, including construction of fuse plug weir,
level crossing at the Pakpattan Canal, Road Bridge on Haveli Lakha-Suleimanki
Barrage road.
Strengthening of Embankments.
Grouting the Cavities and Cracks
Repair the Barrage floor where aggregate has been exposed and floor thickness
reduced
Trimming / partial removal of the bela.
Improvement in existing Public Park.
Mechanical/Electrical Works

3.5

Repair of Barrage and canal Gates, Installing electric motors for Hoisting System

Installation of Pressure Monitoring Instruments.


LABOUR CAMP

It is envisaged that the Project will attract about 1000 skilled/unskilled labour. It should be
ensured that maximum labour arranged locally however the majority of the skilled labour
working on site likely to be migrated from other part of the country. It is a contractors
contractual obligation to provide a labour camp and consultants and employer offices on
site. The IPDs land is available for consultants and contractors offices and officer residence
and no private land will be acquired for this purpose. Private land may require for labour
camp and batching plant. The contractors camp and labour camp will be a permanent
structure which could be used by other institutions e.g. irrigation, police, forces etc at the
completion of the Project. The suitable locations for the contractors facilities are indicated on

NESPAK-AAB-DMC

22

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

figure 3.1. The land for the suggested locations for labour camp and batching plant will be
arranged by the IPD.
3.6

WORK BASE AREA

The area near the left guide wall at downstream of barrage can be use as a work base area,
as indicated on figure 3.1. However the available area may not be sufficient for all the plant
and machinery use in the project. Therefore the area could be used as work base for only
those activities undertaken at the barrage. The other option for work base area is on the
Sulemanki-Haveli Lakha road next to the proposed location for batching plant. The area will
be more appropriate to use as work base area for the equipment and machinery involve in
working at the embankments. The Work base area and all the access roads are located
within the IPDs land therefore no any private land acquisition is anticipated due to the
establishing the work base area and access road. Modification and maintenance of the
surface of the bunds and access roads will be undertaken to ensure the dust free
environment of the area.
3.7

MATERIAL REQUIREMENTS

The main type of materials require for the execution of the work are:
3.7.1

Civil Works

Concrete Work will include the handling of following material


Cement, Crush, Sand, Plasticizer, Air Entraining Agent, Steel Reinforcement, Epoxy and
Grouting Material. Earthwork will require of handling clay material (soil). The anticipated
quantities of the material require are

Material

Units

Approximate Quantity Require

Concrete

100 cft

21,393

Stone

100 cft

80,907

Steel

100 kg

51,566

Sheet Piles

100 kg

16,998

1000 cft

204,951

Clayey Soil
(Fill Material)
3.7.2

Electrical/Mechanical Works

Generally following material and equipments will be used in electrical/mechanical work in


this project
NESPAK-AAB-DMC

23

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Gates, Hoisting Systems, Cable, Electrical Cables, Motors, Gear Box, Welding Material and
Sensors & Other Electronic Devices
3.8

SOURCE OF MATERIAL

The common source of the material require for civil work are described in Table-3.1.
Table 3.1:

Source of Raw Material

Sr. #

Raw Material
Availability

Earth Material

Available locally, borrowed from


temporarily acquired for the purpose.

Aggregate

Available at many sources, such as:


Quarries at Sakhi Sarwar (240 miles), Margalla Hills
(330 miles) and Sikhanwali (220 miles), Sargodha
(230 miles).
The choice will however will depend upon the quality
and suitability of the rock material of the
construction of the hydraulic structures.

Rip-rap material

Available from the three locations indicated above.

Sand

Sand is available in barrage area. At times


contractor may prefer to bring superior quality sand
from other sources too. Final decision will be taken
RE and the contractor jointly.

Water for preparation of Ample fresh groundwater aquifer is available along


concrete
the river. The contractor will install tube well within
IPD land with the agreed location with consultants
environmentalist and Project Management Staff.

Water for compaction of River water can be used for this purpose
embankments

Cement

Source
the

lands

Portland cement is locally available from the two


factories situated at Daud Khel (340 miles).
However, the cement of other grades is available
within the country for the factories at D.G.Khan (260
miles), Karachi (900 miles), Chakwal (250 miles),
Islamabad (320 miles), Wah (330 mile) etc.

Reinforcement steel

Mechanical parts of the Could be manufactured at Heavy Mechanical


Gates
Complex at Taxilla (340 miles), Factories at Lahore
(130 miles) and Gujranwala (160 miles) and /or
imported from abroad.

NESPAK-AAB-DMC

Available from re-rolling mills at Lahore (130miles).

24

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

3.8

EQUIPMENT AND MACHINERY YARD

It is envisaged that the following equipments and machineries will be required for
construction activities:1. Concrete Batching plant
2. Transit mixer
3. Concrete Pumps
4. Motor Graders
5. Excavators
6. Dozers
7. Dumpers
8. Compaction Roller
9. Water bouzers
10. Crane
11. Transport Buses
12. Front End Loaders
The equipment will be kept in a plant & equipment yard. The suitable site for the yard is
indicated on figure 3.1.

NESPAK-AAB-DMC

25

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Figure 3.1: Project Layout of Selected Works Scheme

NESPAK-AAB-DMC

26

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

CHAPTER 4:
4.1

BASE LINE CONDITION

GENERAL

The purpose of this chapter is to establish the baseline conditions for the Physical, Biological
and the Social aspects of Environment of the project area. This chapter assesses the extent
of the Area of Influence (AOI) and describes the relevant environmental conditions of the
Study Area. This will assist in impact assessment and suggesting the appropriate mitigation
measures required.

4.2

PHYSICAL ENVIRONMENT

The physical environment includes soil quality, water quality, ambient air quality and climatic
conditions.

4.2.1

Physiography and Soil

The major land form units of the area include Active/Recent flood plains, sub recent flood
plains and Piedmont Plains.

Active flood plains are narrow strips along the river and its tributaries. The plains are
inundated almost every year, covered with rich alluvium and are suitable for agriculture. Sub
recent flood plains also called alluvial terraces are depositional and are separated from the
adjoining active flood plains by the river cut bluffs ranging in height from 2m to 10m. The
sediments are called old alluvium and are composed of compact calcareous silty clay.
Piedmont plains develop between the mountain and river. The Piedmont plains of River
Sutlej fall in the Indian Territory. The river rolling down the mountains become active only
when rainfall takes place. It flows down the slopes swiftly. On reaching the foothills, it looses
speed and drops part of the load within the streams, which split into a number of narrow
channels. The gravel, sand and silt thus deposited, form the alluvial fans. The Piedmont
plains, dominated by the alluvial fans, provide good soils and suitable topography for
agriculture.

4.2.1.1

Soil Types

The Project area forms a part of the vast Indus plain, which is a part of the Indo-Gangetic
depression. This depression is of a synclinal nature. Synclinorium depression is a fore deep
downward of the Himalayan foreland of variable depth, converted into flat plains by simple

NESPAK-AAB-DMC

27

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

process of alleviation. The alluvial deposits consist on silty sand to silty clay are underlain by
rocks of Precambrian age i.e. Sandstone.

4.2.1.2

Surface Salinity

In the event of extended canal closure the saline area will be most vulnerable area in the
canal commands. Extended canal closure will not be require in this project, however to deal
with any accidental canal closure impacts the saline area in the canal commands are
identified. A study of surface salinity of the canal command areas of Pakpattan Canal,
Fordwah Canal and Sadiqia Canal was undertaken by the SCARPS Monitoring Organisation
(SMO) and presented in their reports references: S&R Publication No. 29, No. 33 and No.
35. The main parameters tested in the field were EC and pH.

SMO arranged auger holes at suitable sites up to 180 cm depth or to the sloughing material
for the study within the canal command area. All the three canals irrigate a considerable
area of Southern Punjab. The canal command areas for Pakpatan Canal, Sadiquia Canal
and Fordwah Canal extend up to 1,058,000 acres, 1,260,000 acres and 474,000 acres
respectively. The percentages of strongly saline (EC > 15ds/m) area found within each canal
command areas are summarized in Table 4.1. Considerable area was identified as strongly
saline within the Fordwah Canal command area.

Table 4.1:

Surface Salinity Statistics


Non-Saline

Strongly Saline

Canal

Total

Command

Acreage

Acreage

Percentage

Acreage

Percentage

Pakpattan

1,058,330

947,637

90%

1,082

< 1%

Fordwah

474,000

386,537

82%

20,123

4%

Sadiqia

1,260,000

1,083,600

86%

12,600

1%

Source:

SMO reports publication No. 29, 33 and 35

NESPAK-AAB-DMC

28

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.2.1.3

Seismic Data

Due to the continental plate drift of Indian Plate and Asian Plate, Pakistan has been suffered
from the devastating earthquakes in past. NESPAK has been developed a Seismic Zoning
Map for Pakistan. The whole country is
divided into following 5 zones:
Seismic

Peak Horizontal

Zone

Ground Acceleration

0.05 to 0.08g

2A

0.08 to 0,16g

2B

0.16 to 0.24g

0.24 to 0.32g

>0.32g

Where g is the acceleration due to gravity

Figure 4.1. Seismic Zoning Map of Pakistan

The project area falls within zone 2A as indicated in figure 4.1. Zone 2A represents area of
negligible damage from the earthquake. Design team has been consider the possible
impacts of earthquake on the barrage structure.

4.2.2

Climate

No meteorological station is located within the project study area. The data and analysis
provided is based on yearly record from the monitoring station at Okara managed by
Pakistan Metrological Department (PMD). The climate of the area is arid characterized by
long hot summer and short mild winter. The summer extends from April to October.

4.2.2.1 Temperature
The mean temperature ranging between 39oC to 42oC in summer. May and June are the
hottest months during which maximum temperature may rise up to 50oC. The winter lasts
from December to February with minimum temperature ranging from between 2oC to 5oC.
January is the coldest month and chill prevails during the winter when cold wave from
Himalaya, lashes the area.

NESPAK-AAB-DMC

29

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Average Maximum Monthly Temperatures, Okara (2007)

Average Minimum Monthly Temperatures, Okara (2007)

4.2.2.2 Rainfall & Humidity


The average annual rainfall in the area is 150 to 180mm. Nearly 60% of the Precipitation is
received during July to September whereas the rest is unevenly spread over the remaining
months. On the whole the rainfall is too scant and unreliable to be of any agricultural use.
The general evapo-transpiration is very high and the irrigation requirements are met through
the well organized (weir controlled) canal irrigation system.

NESPAK-AAB-DMC

30

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The average relative humidity was obtained from the Meteorological Department for Okara
during 2007. Relative Humidity varied between 45% and 85%, peaking during the month of
September.

Average Relative Humidity, Okara (2007)

Average Monthly Rainfall, Okara (2007)

The monthly rainfall varies significantly. The highest rainfall was recorded during the
monsoon months (June and July).

NESPAK-AAB-DMC

31

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.2.2.3

Wind

The wind speed significantly varied over the twelve month period. Peak values were
recorded during the month of May while the minimum wind speed occurred in the months of
October and January. The typical wind direction is south to north.

Average Monthly Wind speed, Okara (2007)

4.2.3
4.2.3.1

Water Quality
Surface Water Quality

The natural surface water resources of the project area include Sutlej River, the canals
which off-take from the barrage, Pakpattan Canal, Fordwah Canal and Sadiqia Canal, and
the BS Link Canal that has its outfall at the Sutlej River at the RME. The river water
discharge at Ferozpour Barrage by the Indian government is negligible except during the
monsoon period. The design discharge capacity of the canals off take from Sulemanki
Barrage are as follows;

Pakpattan Canal

6,594 Cusecs

Sadiqia Canal

6,080 Cusecs

Fordwah Canal

3,366 Cusecs

The design discharge capacity of the canal brings water from Baloki Barrage to Sulemanki
Barrage (BS Link Canal) is 22,000 Cusecs.

NESPAK-AAB-DMC

32

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sutlej River is now a non-perennial river as a result of the diversion of its water by India,
under the Indus Water Treaty of 1960. Presently, its flow constitutes of water mostly
released from the BS Link Canal and occasional releases by India from Ferozpour Barrage,
mostly occurring during high flow season. Pakpattan and Sadiqia canals are perennial
canals where as Fordwah is non-perennial at the barrage. A drain bringing wastewater from
India converges with Sutlej River at about 6 km upstream of the Barrage as shown on
Figure-1.2. The drain called Fazilaka drain in Pakistan and Gandahi drain in India.

4.2.3.2

Hydrological Characterization

The average river flows upstream of the Sulemanki Barrage is shown in Table 4.2. Average
flows were determined for the year 1981, 1997, 1998, 1999 and 2000 during the months
between May and October when river flow is significant. This indicates the peak flow usually
occurs in August of due to the the monsoon season in the area.

Table 4.2: Average River Flows Upstream of the Sulemanki Barrage (MAF)
Months

Average flow in each year


1981

1997

1998

1999

2000

May

12,930.42

9,756.90

20,064.58

10,869.00

11,422.77

June

13,219.67

6,800.65

18,519.47

13,277.27

11,846.83

July

15,293.45

9,851.71

32,954.42

18,307.52

17,997.13

August

15,408.45

23,083.90

20,320.06

24,385.10

15,445.97

September

12,590.53

22,025.17

29,482.47

17,038.87

13,558.60

October

9,433.23

11,254.42

36,688.97

10,486.23

4,658.94

Following are the salient features of the Sutlej River and Hydrological Regime of Suleimanki
Barrage:-

Beas River joins Sutlej near Harike where India has built a Barrage to take out Rajasthan
Canal. Ferozpur Barrage has been built on Sutlej near Ferozpur (India) to take out Bikaner

NESPAK-AAB-DMC

33

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

and Eastern Canals. After the Indus Water Treaty, only surplus water of the above two
barrages is allowed to flow down to Suleimanki Barrage.

Design Capacity of the Barrage = 325,000 Cusecs

Maximum discharge of pre-construction period a discharge of 249,482 cusecs was


computed from the flood marks existing in the vicinity of proposed weir site in 1920.

4.2.3.3 Flood Record


Under Second Flood Protection Sector Project (FPSP-II), flood risk maps for 5 year and 50
year return period were developed for Sutlej River, as indicated in Figure-4.2. This map will
be used to prepare the flood protection plan during construction and project implementation
phase. The historical record of major flood pass through the barrage are summarized in
Table-4.3.

Table 4.3:

Peak Discharge of Prominent Years in River Sutlej at Suleimanki


Barrage

Years
1942

Discharge through
weir (Cusecs)
325,000

Through Breeches in
Flood Embankment
Nil

Total
(Cusecs)
325,000

1943

309,000

Nil

309,000

1947

360,000

Nil

360,000

1950

332,000

Nil

332,000

1955

422,000

175,000

597,000

1988

400,000

100,000

500,000

1995

301,865

Nil

301,865

The most recent flood caused the breaching in LMB and RMB occurred in 1988. According
to the data received from irrigation department a discharge of 500,000 cusecs was received
upstream of Suleimanki Barrage out of which 100,000 cusecs escaped through the breaches
in the marginal bunds and 400,000 cusecs passed through the Barrage with a raised
upstream barrage level. As per report of the Punjab Government 28 people lost their lives,
10,263 cattle heads were lost, about 209 acres of cropped area were damaged during 1988
floods.

NESPAK-AAB-DMC

34

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The Punjab Irrigation Department generally defines flood limits as low, medium, high, very
high, and exceptionally high at key control points. River Sutlej flood limits revised and fixed
in 1974 by the Punjab Flood Commission for Suleimanki Barrage are given below:

Normal Flood

Up to 50,000 cusecs

Low Flood

50,000 to 80,000 cusecs

Medium Flood

80,000 to 120,000 cusecs

High Flood

120,000 to 175,000 cusecs

Very High Flood

175,000 to 220,500

Exceptionally High Flood

Above 220,500 cusecs

As per Flood Fighting Plan prepared by the Executive Engineer Suleimanki Barrage (2009) a
list of villages and Abadies likely to be inundated at the event of high flood (cause breaching)
is included in the Plan and listed below:

Villages around the barrage and likely to be inundated at the event of high flood

Thakarka Maneki

12

Ghura Ismail Maneki

Stia Jhanghar

13

Ghura Mehtab Rai

Dharanga

14

Chak Davi Ditta

Alika Rohals

15

Bukkan Guddar Ka

Rakh Bulewal

16

Boola Chishti

Mehtab Garh

17

Rakh Jawaya Baluch

Meneka Nikki

18

Kaluwah

Gurwala Mehtab Garh

19

Noor Shah

Mathila Bhidal

20

Chak Haiderabad

10

Maneki

21

Bareet

11

Mahant Darshan

NESPAK-AAB-DMC

35

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment
Legend

Figure 4.2:

NESPAK-AAB-DMC

Flood Plan near Suleimanki Barrage

36

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.2.3.4 Surface Water Testing


To assess baseline conditions of surface water in the project area, three grab samples were
obtained on 11th November 2009. The purpose of the surface water testing is to determine
the suitability of the water for irrigation purposes as well as for drinking. The three locations
were selected are indicated on Figure 4.4. Two of the locations, on Sutlej River, were near
the barrage (left and right undersluice) and one close to the out fall of BS Link Canal. It is
important to monitor water quality at the undersluices as water is diverted from the river into
the canals at that point. The contractor is obligated to ensure that in case of an extended
canal closure, water of comparable quality must be supplied to the areas directly affected by
the closure. Determining the quality of water close to the outfall of the BS Link Canal is
imperative since it is the main source of water in the Sutlej River. The comparison of test
results also indicate the impact of the Fazlika Drain, brings the wastewater from India in the
Sutlej River. Furthermore, during project implementation comparative analysis of water
quality at the site of on-going activities near the barrage and water quality coming in from the
BS Link Canal will assist in establishing the source of any contamination if present.

The samples were collected and tested by an EPA authorized laboratory SGS Laboratory.
Standard sampling procedures were followed at each site to ensure the integrity of the
samples collected and validity of test results. The details of sampling procedure and test
results are included in Appendix 4.1.
Results
The test results are summarized in table 4.4. The water quality parameters were compared
against WHO and NEQS levels. The WHO standards strictly adhere to water quality for
drinking purposes and are thus very stringent. Though the canals and river water is largely
used for irrigation, it is used in some areas for drinking purposes. Therefore WHO standards
have been used. The NEQS standards have been drafted for the contamination of water
quality by heavy metals and other industrial toxins.

However, since the water that flows towards the barrage and into the canals that off-take
from it is primarily used for irrigational purposes, the parameters were compared against the
United Nation Organizations (UNO) Food and Agriculture Organization (FAO) guidelines for
irrigation livestock and poultry in Table 4.5. These guidelines are included in Appendix 4.2.

NESPAK-AAB-DMC

37

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 4.4: Laboratory Analysis Report of Surface Water Samples


Results
Parameter

Sr.
No

Unit

Right
Under
Sluice
(11/11/09)

Left
Under
Sluice
(11/11/09)

Just after
BS link
fall into
Sutlej
River
(11/11/09)

WHO

NEQS

01

Odor

Odorless

Odorless

Odorless

02

pH

7.12

7.06

6.90

6.5 9.5

69

03

Turbidity

NTU

21

22

41

04

BOD5

mg/l

10

80.00

05

COD

mg/l

12

20

21

150.00

06

Total Coli Form

57

70

23

mg/l

28

30

48

200

mg/l

273

280

219

1000

3500

07
08

Total
Suspended
Solids (TSS)
Total Dissolved
Solids (TDS)

MPN/100
ml

09

Chloride (Cl)

mg/l

31.98

34.88

23.26

250

1000

10

Sulphate (SO4)

mg/l

34.78

44.86

29.64

250

600

11

Nitrates (NO3)

mg/l

1.4

1.7

0.9

50

12

Fluoride (F)

mg/l

0.33

0.36

0.39

1.50

10.00

13

Ammonia

mg/l

0.8

0.91

0.6

1.50

40

14

Grease & Oil

mg/l

<1.0

<1.0

<1.0

10.00

15

Chromium (Cr)

mg/l

<0.01

<0.01

<0.01

0.05

1.00

16

Copper (Cu)

mg/l

<0.01

<0.01

<0.01

2.00

1.00

17

Lead (Pb)

mg/l

0.02

0.02

0.04

0.01

0.50

18

Mercury (Hg)

mg/l

<0.001

<0.001

<0.001

0.001

0.01

19

Selenium (Se)

mg/l

<0.01

<0.01

<0.01

0.010

0.50

20

Nickel (Ni)

mg/l

<0.01

0.02

0.02

0.020

1.00

21

Silver (Ag)

mg/l

<0.1

<0.1

<0.1

1.00

22

Zinc (Zn)

mg/l

0.02

0.02

0.02

3.00

5.00

23

Barium (Ba)

mg/l

<0.5

<0.5

<0.5

0.7

1.50

24

Iron (Fe)

mg/l

0.54

0.62

0.94

0.3

8.00

mg/l

0.02

0.02

0.04

0.50

1.50

mg/l

<0.1

<0.1

<0.1

1.00

25
26

Manganese
(Mn)
Chlorine

NESPAK-AAB-DMC

38

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 4.5: Laboratory Analysis Report of Surface Water Samples (FAO limits)
Results
Just after
Sr.

Parameter

Unit

No

Right

Left

BS link

Under

Under

fall into

Sluice

Sluice

Sutlej

FAO

(11/11/09) (11/11/09) River


(11/11/09)
01

02

Electrical
Conductivity
Total Dissolved
Solids (TDS)

420

438

352

0 - 3000

mg/l

273

280

219

0 2000

03

Chloride (Cl)

mg/l

31.98

34.88

23.26

0 1060

04

Sulphate (SO4)

mg/l

34.78

44.86

29.64

0 960

05

Nitrates (NO3)

mg/l

1.4

1.7

0.9

0 10

meq/l

2.69

2.74

2.09

0 15

Sodium
06

Absorption
Ratio (SAR)

07

Magnesium

mg/l

9.0

9.96

9.37

0 60

08

Calcium

mg/l

36

36.48

34.56

0 400

09

Sodium

mg/l

70

72.5

53.75

0 910

10

Potassium

mg/l

4.9

4.9

4.2

11

Bicarbonates

mg/l

150.52

150.52

143.35

12

Carbonates

mg/l

<0.5

<0.5

<0.5

02
0 610
03

Analysis of Results

WHO Standards:

The water quality test results indicate that four parameters exceed WHO standards;
Turbidity, Total Coli Form, Lead and Iron in all three surface water sampling points. The
water is therefore clearly unsuitable for drinking purposes. However, according to the
Pakistan Environmental Protection Agency (PAK-EPA) 2003, the maximum limit of E-coil is
126 per 100ml in freshwater for recreational use. The numbers of E-coil in the samples are
less than 126/100ml therefore the river water is fit for recreational use.
NESPAK-AAB-DMC

39

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

FAO Standards:

The water quality testing results were compared with the FAO standards for irrigation water
as shown in Table-4.5. From the salinity point of view, Sodium Absorption Ratio (SAR) in all
three samples of the surface water was detected within the marginal criteria. Laboratory
results for Electrical Conductivity also showed that it was within the usable range. Almost all
other parameters tested within the defined limits, except for Potassium which exceeded the
limits.

The water quality testing results are consistent with the analysis of River Sutlej carried out by
IPD in 2007 and tabulated in their Annual 2007 report on water quality. 8 water quality
parameters were tested for during the months of December to October 2007 with the
conclusion that water quality of Sutlej remains within the safe limits of FAO standards.

NEQS Standards:

The results have been compared with NEQS 2000 as shown in Table 4.4. All water quality
parameters tested were within the defined ranges set by NEQS.

4.2.3.5 Ground Water


Tubewells and hand pumps are the two most common sources of groundwater within the
project area. The Unconfined aquifer can be found as shallow as 3 m depth from the ground
level near the barrage and is mainly used for drinking and agricultural purpose. The aquifer
constitutes of a stratum of loose sand of high permeability.

Groundwater Testing
To assess baseline conditions of ground water in the project area, one sample was obtained
from an existing hand pump at the barrage on 11th November 2009 for analysis. The hand
pump was located near the right guide bank, upstream of the barrage. It has been observed
that the local population uses this water source for drinking and domestic washing by a
nearby restaurant. The sampling point is indicated on Figure-4.1. The approximate depth of
the bore of the hand pump is 10m from ground level.

The sample collected was tested by an EPA authorized laboratory SGS Laboratory.
Standard sampling procedures used for surface water sampling were followed for the

NESPAK-AAB-DMC

40

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

groundwater sample to ensure the integrity of the samples collected and validity of test
results.

Results of Groundwater Testing


The water quality parameters tested for the groundwater sample are summarized in
Table 4.6 and Table 4.7. The parameters were compared against WHO, NEQS and FAO
standards. Since groundwater in the area is used for drinking purposes as well, it is
important to determine the quality of the water in terms of the WHO Guidelines for drinking
water.

NESPAK-AAB-DMC

41

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 4.6:
Sr.
No

Groundwater Test Results


Results

Parameter

Unit

GW

WHO

NEQS

(11/11/09)

pH

7.29

6.5-8.5

69

Odour

Odorless

Total Dissolved Solids (TDS)

mg/l

415.0

1000.0

3500

Total Suspended Solids (TSS)

mg/l

34

200

Turbidity

NTU

27

5.0

Ammonia

mg/l

0.05

1.50

40

10

E-coli

No./100ml

39.0

11

Flouride

mg/l

1.2

1.5

10

12

Chloride

mg/l

21.0

250.0

1000

13

Chlorine*

mg/l

< 0.1

1.0

14

Oil and Grease

mg/l

<1.0

10

15

Arsenic

mg/l

<0.005

0.01

1.0

16

Barium

mg/l

< 0.5

0.7

1.5

17

Chromium

mg/l

< 0.01

0.05

1.0

18

Cyanide

mg/l

<0.01

0.07

1.0

19

Sulphate

mg/l

35.0

250.0

600

20

Iron

mg/l

2.50

0.3

8.0

21

Selenium

mg/l

< 0.01

0.01

0.5

22

Mercury

mg/l

< 0.001

0.001

0.01

23

Cadmium

mg/l

<0.01

0.003

0.1

24

Copper

mg/l

<0.01

1.0 2.0

1.0

25

Lead

mg/l

0.02

0.01

0.5

26

Nickel

mg/l

0.02

0.02

1.0

27

Silver

mg/l

<0.1

1.0

28

Zinc

mg/l

<0.01

3.0

5.0

29

Manganese

mg/l

0.41

0.5

1.5

30

Color

Pale Yellow

31

Sodium

mg/l

70

200.0

32

Nitrate

mg/l

5.30

50.0

NESPAK-AAB-DMC

42

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 4.7

Sr.
No

Groundwater Quality for Irrigation Purpose


Results

Parameter

Unit

FAO
Standards

GW
(11/11/09)

Electrical Conductivity (EC)

S/cm

594

0- 3x105

Sodium Absorption Ratio (SAR)

meq/l

1.92

0 15 (meq/l)

mg/l

ND

Residual Sodium Carbonate


(RSC)

Total Dissolved Solids (TDS)

mg/l

415.0

0 2000

Calcium Hardness

mg/l

183.15

Magnesium Hardness

mg/l

66.80

Magnesium

mg/l

16.3

0 60

Ammonia

mg/l

0.05

05

10

Sulphate

mg/l

35.0

0 960

11

Sodium

mg/l

70

0 910

12

Chloride

mg/l

21.0

0 1060

Analysis of Results

WHO Standards
The suite of contaminants and test results are summarized in Table-4.6. The test results
indicate that the groundwater quality is unsuitable for drinking purposes. 3 parameters,
Lead, Turbidity and Iron exceeded the defined WHO limits for drinking water. It is envisaged
that the higher concentrations of contaminants in shallow groundwater is due to the recharge
of groundwater from contaminated river water. However, groundwater from a higher depth is
likely to achieve the WHO drinking water standards.

FAO Standards
The water quality test results were also compared against FAO standards to determine the
groundwaters suitability to be used for irrigation as well. The analysis of the single
groundwater sample shows that all parameters necessary for irrigation water are within the
safe FAO limits.

NESPAK-AAB-DMC

43

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

NEQS Standards
The groundwater quality parameters all tested within the safer limits of NEQS standards.

Groundwater Quality in Canal Command Areas


The secondary data for groundwater quality has been collected from the Directorate of Land
Reclamation and SMO offices for canals command areas. The groundwater was classified
on the basis of laboratory analysis arranged by SMO for Electrical Conductivity (EC),
Sodium Adsorption Ratio (SAR) and Residual Sodium Carbonate (RSC) during 2005. For
ease in description, the groundwater has been expressed as usable, marginal and
hazardous for irrigation as determined by the adverse value of any of the above mentioned
three parameters. The classification criteria used is not intended to be strict in relation to the
effects of irrigation waters on soil and crop growth and can be truly adjusted according to
environmental factors such as climate, type of soil, crops grown and management practices.
SMO also carried out testing for pH and EC in the filed by using digital pH and EC meters
and sent all the water samples to the laboratory for detailed chemical analysis. The samples
were analyzed for EC, SAR and RSC. These parameters are used for the classification of
water as usable, marginal and hazardous.

Usable

Marginal

Hazardous

EC x 106 S/cm

0 1500

1500 3000

> 3000

RSC (meq/l)

0 2.5

2.5 5.0

> 5.0

SAR (mg/l)

0 10

10 18

> 18

The groundwater quality within the canal command areas are summarized in table 4.8.

Table 4.8:
Command
Area of

No.

Shallow Ground Water Quality within Canal Command Areas


Shallow Water Quality

of
Usable

Water

Marginal

Hazardous

Samples

No.

No.

No.

Pakpattan

592

393

66

158

27

41

Sadiqia

292

131

45

97

33

64

22

Fordwah

600

223

37

169

28

208

35

Source:

SMO reports publication No. 29, 33 and 35

The overall shallow ground water quality in Fordwah Canal Command Area when compared
to a survey done in 1977-79 indicates that the usable category of present survey has

NESPAK-AAB-DMC

44

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

decreased by 16%, whereas marginal and hazardous water quality have increased by 12%
and 4%, respectively. Likewise for Sadiqia, the usable category has decreased by 14% while
the marginal and hazardous have increased by 4% and 10 % respectively, as compared to
the 1977-79 survey. This might be due to heavy pumpage of private tubewells which were
installed and operated by the farmers in the command area to meet with the crop water
requirements of the area. The drought conditions prevailing in the country since 1960 after
the Indus Water Treaty also played role in the deterioration of shallow water quality as fresh
water recharge remained comparatively less than pumpage. No survey in 1977-79 was done
for Pakpattan Canal Command Area.
4.3

BIOLOGICAL ENVIRONMENT

The existing habitats within the project area include the agricultural land, wetland (including
the reservoir, canal system and small water impoundments) of these the agricultural land
occupied most of the area. The wetland is an important ecological feature of the site and is a
repository to a number of birds species. The area is open for shooting under the shooting
permit issued by the Wildlife Department.
4.3.1
Flora
The Flora can be divided into two parts:

Riverian Tract

Adjacent Inland Area

Riverian Tract
In riverian tract, especially in pond area the succession of vegetation, first colonizes are
grasses and Typha followed by Tamarix as the soil become consolidated and is raised by
the new silt deposition in the scrub, so that the vegetation is no longer completely
submerged and erect tree growth becomes possible.

As the soil gets stabilized and drained the forest community normally progresses to Acacia
nilotica and Dalbergia sissoo. In its present state, the flora of Riverian Alluvial deposits can
be listed as follows:Trees
1. Lai (Tamarix dioca)
2. Pilchi (Tamarix gallica)
3. Babool (Acacia nilotica)
4. Shisham (Dalbergia sissoo)
5. Beri (Zizyphus yujuba)
NESPAK-AAB-DMC

45

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

6. Jand (Prospis spicigera)


7. Mesqette (Prosopis juliflora)
8. Mesquette (Prosopis glandulosa)
9. Bhen/Poplar (Populus euphratica)
10. Khabbal (Cynodon dactylon)
11. Kanwal (Melolotus oralifolia)
12. Munj (Erianthus munja)
13. Kia (Sacchrum spontaneum)
14. Kunder (Typha elephantine)
Whereas the trees provide a habitat for birds the solid ground below is the houses of
mammals. The margin line of Typha and grasses becomes a good habitat for reptiles while
the fish occupy the adjacent waters.
Adjacent Inland Area
Adjacent area is either on the river banks or on risen parts of the consolidated alluvial
deposits within the pond. The natural flora of inland area is as follows:Trees: Salvadora oleoides (Peelo), Prosopis juliflora (Jangli kiker), Tamarix aphylla
(Farash), Dalbergia sisso (Shishm), Acacia nilotica (Kiker), Albizzia lebbec (Sars)
Kiker, Shishm, Sufaida and Tarmail were the main type of trees found along the
embankments.

Shrubs:

Calotropis procera (Aik), Prosopis glandulosa (Jangli kiker), Zizyphus

nummularia, Capparis aphylla (Karir),

Herbs:

Boerhavia diffusa(Itsit), Fomaria indica (Pitpapra), Carthamus oxycantha

(Pohli), Peganum harmala (Hermal), Alhagi camelorue (Jawann).

Grasses:

Cynodom dacylon, (Khabal), Desmostachya bipinnata (Dab), Dicanthium

annulatum (chimber), Sporobolus sp. Imperata cylindrica (Seer).

Exotics Trees in Adjacent Area

Near the banks some exotic tree species have been introduced over the time. Some of these
are:-

NESPAK-AAB-DMC

46

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

1. Mulberry (Morus alba)


2. Bakain (Melia azadarach)
3. Shirin/siris (Albizzia lebeck)
4. Sufaida (Eucalyptus camaldulensis)
5. Ipal ipal (Minosifolia)
6. Burr (Ficus bengalensis)
7. Pipal (Ficus religiosa)
8. Mango (Mangifera indica)
9. Jaman (Eugenia Jambolana)
10. Toot (Moris Alba)

The tree density at the barrage is medium and high along the embankments. Shishm and
kiker are the most common trees found on site. There are total 309 numbers of matured
trees (more than 80% are Sufaida) found within the recommended location of flood bypass
channel, requiring uprooting for the construction activities; Figure-4.3 indicates the tree
counting on site imagery.

Economic Ecological Value of the Flora


The above listed flora consist of trees-shrubs-herbs and grasses. The flora on the whole
has following economic and ecological values:

1.

Production Value:
Timber, fuel wood and non-timber produce.

2.

Protection Values
Soil conservation, wind breaks and protection and habitats for fauna.

3.

Environmental Values
Production of oxygen, carbon absorption, cooling of air temperature.

4.

Aesthetic Values
Trees as green dimension tool of landscape the other vegetation supplements that.

5.

Cultural Values
Various produce available out of the flora shape the habits and culture of the
adjacent population.

NESPAK-AAB-DMC

47

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

6.

Strategic Value
Near the project area there is Rangers out post and the scale vegetation on the site
provides camouflage as well as obstacle value to the area.

7.

Rehabilitation Value
Succession of vegetation on alluvial soil in the river builds up the soil at advance
stage this process can add more lands to agriculture use.

The total removable trees are 309 which are almost all Eucalyptus. It is inevitable to remove
these trees. Replacement plantations are arranged at alternate sites as given in the
plantation plan in EMP up to 5 plants every one plant uprooted. The estimated cost of a
mature tree of Eucalyptus is Rs.1000. So the total economical value of the uprooted trees is
Rs. 309,000. The Eucalptus tree does not have any positive ecological and environmental
value and is not a recommended plant for new plantation.

NESPAK-AAB-DMC

48

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Figure 4.3: Tree Count Falling in Proposed Flood Bypass Channel Map

NESPAK-AAB-DMC

49

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.3.2
Terrestrial Fauna
The rich Fauna of Sutlej River at Sulemanki Barrage, upstream in the barrage head pond
and downstream in the released waters, is as follows: the data collected from the Wildlife
department and from the EIA study conducted for Islam Barrage Rehabilitation &
Upgradation

Mammals
Species

Scientific Name

Status

Mongoose

Herpestes edwardsi

Common

Mongoose

Herpestes anropunctatous

Common

Porcupine

Hystrise indica

Common

Hedge Hog

Hemiechinus spp.

Common

Fox

Valpes bengalensis

Less Common

Jackal

Canis aureus

Common

Wild Boar

Sus scrofa

Common

House Rat

Rattus rattus

Common

Yellow House Bat

Scotphilus

Common

Hare

Lepus nigricollis

Common

Nilgai

Boselaphus tragocamelus

Rare

Hog Deer

Axis porcinus

Rare

Black Buck

Disambiguation

Rare

Scientific Name

Status

Reptiles & Amphibian


Species
Frogs

Common

Toads

Common

Marsh crocodiles

Crocodylus palustris

Now extinct

Sand Boa or Du-muhi

Erys Johnii

Common

Chequared
Snake

keel

back Natrix piscator

Common

Dark-bellied marsh Snake

Xenochrophis cerasogaster

Common

Striped river Snake

Enhydris pakistanica

Rare

Gecko

Hemidactylus

Common

Dhaman

Ptyas mucosus

Rare

Striped Keel back

Amphiosma estolata

Rare

Indian Cobra

Naja naja

Common

Indian Monitor Lizard

Veranus bengalensis

Common

Variety of lizards, krait and


viper

NESPAK-AAB-DMC

Common

50

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Turtles Hard shelled


Species

Scientific Name

Status

Common River Turtle

Hardella Thurjii

Common

Brahminy River Turtle

Hardella thurgi

Common

Species

Scientific Name

Status

Indian Flapshell Turtle

Lissymes punctata

Common

Brown River Turtle

Kachuga Smithin

Common

Scientific Name

Status

Flap Shells

True Soft Shells


Species

Narrow Headed soft shell Chitra indica


turtle

Rare

Indian soft shelled turtle Trionysc gangeticus


(Sunworshippens)

Rare

Common Tortois

Common

4.3.3
Birds
The barrage pond area provide the habitat of many rare species of migrating and protected
species of the local birds. Partridge and Peacock are the local protected species of the birds
found in project area. Many rare species of waterfowl also visit this site during winter. The list
of birds is prepared during the consultation of wildlife department.

Species

Scientific Name

Status

White breasted kingfisher

Halcyon smyrnensis

Common

Pied kingfisher

Ceryle rudis

Common

Little egret

Egretta garryetta

Common

Cattle egret

Bubulcus ibis

Common

Pond heron

Areleola grayii

Common

Little bittern

Ixobrychus minutes

Common

Red-vented bulbul

Pyenonotus cafer

Common

Black drongo

Dicrurus macrocercus

Common

Rosy starling

Sturnus vulgaris

Common

Common myna

Acridotheres tristis

Common

Bank myna

Acridotheres ginginianus

Common

House crow

Corvas splendens

Common

Large pied wagtail

Motacilla maderaspatensis

Common

NESPAK-AAB-DMC

51

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Ring dove

Streptopelia decaocto

Common

Little brown dove

Streptopelia senegalensis

Common

Indian roller

Coracias benghalensis

Common

Plain prinia

Prinia inornata

Common

Purple sunbird

Nectarinia asiatica

Common

Indian robin

Saxicoloides fulicata

Common

Coppersmith barbest

Megalaima rubricapilla

Common

Rose-ringed parakeet

Psittacula krameri

Common

Black-crowned night heron

Nycticorax nycticorax

Common

Greater coucal

Centropus sinensis

Common

Asian koel

Eudynamys scolopacea

Common

Golden-back woodpecker

Dinopium javanense

Common

Dendrocopos mahrattensis

Common

Barn owl

Tyto alba

Common

Spotted owlet

Athene brama

Common

Blue-rock pigeon

Columba livia

Common

Yellow-throated sparrow

Petronia xanthocollis

Common

Sind sparrow

Passer pyrrhonotus

Common

River tern

Sterna aurantia

Common

White spoon bill

Platalea leucorodia

Rare

White tailed plover

Vanellus leucurus

Rare

Black Winged stilt

Himantopus himantopus

Common

Cattle egret

Bubulcus ibis

Common

Common coot

Fulica atra

Common

Common pochard

Aythya ferina

Common

Common sand piper

Actitis hypaleucus

Common

Black Headed goose

Anser indicus

Rare

Red crested pochard

Netta rufina

Rare

Tufted duck

Aythy fuligula

Rare

Pond heron

Ardeola Grayti

Common

River tern

Sterna aurantia

Common

Yellow-crowned
woodpecker

NESPAK-AAB-DMC

52

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.3.4

Fish

The most important typies of game fish found in Indus valley are Palla (Tenua losa ilisha)
and Mahasheer (Torputitora spp.) which are an exceptional species. But due to construction
of a series of barrages Palla cannot migrate from sea upwards and is almost extinct from
river waters. Upward breeding movement of Mahasheer is also restricted due to barrages.

The data included in this section is collected during the site meeting with the fishing
contractors and visit at the local office of Fisheries Department. Mainly the fish is exported to
big cities like Multan, Lahore, Karachi etc, however small quantity of fish is sold by the
vendors along the road near the barrage. Fishing is not allowed within 500m of the barrage
upstream and downstream. The contractor(s) can go up to 6 to 7 km from both side of the
barrage to catch the fish. Specially designed net (Jal) by the fishermen are the common tool
of catching fish. It has been found that more than 90% of the people live around the barrage
are connected with the fishing industry during the fishing season. The most common type of
fish found at the barrage are Mali, Gulfam, Sangari, Raho, Talapi, Mori and Soul.

Fisheries play a significant role in Pakistan economy and contribute towards full filling the
food requirement of the country. There are also handful numbers of fish shops at the
Barrage where both raw and fried fish are sold. People from the surrounding big cities and
towns i.e. Okara, Kasor, Pakpattan, Depalpour etc visit at the barrage to enjoy the fresh fried
fish during the fishing season. The fishing season commence on October and finish by mid
of February. During off season local people get involve with agricultural work or temporarily
move to the cities to avail money earning opportunities.

Fishes Commonly Found in River Sutlej Upstream and Downstream Sulemanki


Barrage
Local Name
Scientific Name
Daula

Channa marulius

Dumbra

Labeo rohita

Dumbro

Labeo rohita

Gulfam

Cyprinus carpio

Khagga

Mystus (Mystus) bleekeri (Day)

Khagga

Rita rita

Mori

Barilius Vagra

Mullee

Wallago attu

Rohu

Labeo rohita

NESPAK-AAB-DMC

53

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Saul

Channa marulius (Ham)


Channa striatus (Bloch)

Singhara

Mystus (Osteobagrus) seenghala

Singhari

Mystus (Osteobagrus) aor

Singhi

Heteropneustes fosslis

Theil

Catla Catla

Thaila

Catla catla

Theili

Catla catla

IUCN Status of identified species


Status of each species is indicated in column three of the list. No IUCN red list is available
for particular reference to Sulemanki Barrage and surrounding area, however the listed
species have been broadly categorized in IUCN list on global basis as follow;
Endangered: Hog Deer (mammal) and Narrow Headed soft shell turtle (Turtle)
Vulnerable: common River Turtle (Turtle), Gulfam (fish), Singhi (Fish)
All other species are of Least Concern or Not Evaluated in IUCN List
It can be concluded from the above data that as long as there is no drastic change in the
general river habitat there can hardly any impact on Fish habitats. In anyway, the biological
interbalance in the ecosystem is healthy that all minor changes do not cross the limits of
ecological shock absorbers.

4.4
4.4.1

SOCIO-ECONOMIC CONDITIONS
General

A survey was carried out to appraise prevailing socio-economic conditions of the related
community in the project areas and to assess the impacts of envisaged rehabilitation and upgradation of Sulemanki Barrage on local settlements to cover all the possible options of work
scheme. To achieve the project objectives, it is imperative to study the prevailing socioeconomic and socio cultural aspects of their livelihood. For this purpose a socioeconomic
survey was conducted to assess the socio-economic condition of the people. The study was
completed by December 2009.
4.4.2
Study Area
Sulemanki Barrage is located in Tehsil Depalpur, District Okara. Okara derived its name
from a tree known as OKAAN which was standing on the embankment of a water tank,

NESPAK-AAB-DMC

54

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

being maintained by a person known as RANA. Prior to colonization, that was the only
place for rest and drinking water in an otherwise, barren tract. The Okara district is
composed of three Sub Divisions/Tehsils Okara, Renala Khurd and Depalpur. The Okara
district is bounded by district Faisalabad and Sheikhupura on the north-west where river
Ravi forms the natural boundary for the whole length of Okara district which is about 40
kilometers.
Okara has a wide variety of culture reflecting the traditions and customs of the area. Fairs,
Festivals and Sports Melas (Public congregations) held here. People from different places
visit these fairs. Temporarily shops put up for visitors shopping. Items of entertainment which
attract the people are tent pegging, horse races, donkey race, fight between hounds with a
bear, dog race, cock fighting, wrestling bouts, kabaddi, circus, Theatre, touring cinemas,
volley ball and foot ball matches etc. Folk singers thrill the crowds. All these items are the
sources of enjoyment for all age groups.
Depalpur has a great historic past and is a very ancient town. The fortified town of Depalpur
is built on an old Kashan site (40 A.D. to 172 A.D.). Depalpur fell on the way to Dehli and, as
such, was considered to be a place where an invader could be engaged. Depalpur,
therefore, was one of the 3 lines of defence: the other 2 being Uch Sharif/Multan and
Samana/Sunam and Hansi. (Aaeen-e-Akbari. Vol 1 Part II, Page 1042, by Abul Fazal). Main
castes of the area are Kharrals, Sials, Wattos, Mohars etc. Total area is 2502 sq. Kms.
4.4.3
Data Source/Methodology
Findings/conclusion of the present socio-economic study of the Project Area based on
sample survey, discussion and meetings with the stakeholders and published data.
4.4.3.1 Secondary Data
Secondary data was collected from various sources as given below:

District Population Census Report, 1998

Provincial Population Census Report of Punjab 1998

Pakistan 2003 Mouza Statistics (Settled Areas)

4.4.3.2 Primary Data


It was difficult to interview every household from the Project Area as the time and cost
involved in such data collection and analysis was enormous. Thus for the selection of
respondents simple random sampling technique was adopted. According to ADB guidelines,
20percent of the total households residing in the vicinity of Sulemanki Barrage was
calculated to determine the sample.

NESPAK-AAB-DMC

55

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The sample size was 66 households. Another very important section of the society i.e.
gender analysis was also covered in the study. The numerical reality that women constitute
about half of the total population of Pakistan ideally assigns to them equal participation role
in the economic life of the country. Therefore 46 female respondents were interviewed by
female Sociologist.
Totally 112 questionnaires were filled at different locations in the study area. Among the
respondents 66 were males for household survey and 46 were females for gender survey.
The respondents were from all walks of life having different professional backgrounds.
4.4.3.3. Questionnaire Design
Following Questionnaires were designed and administered for the study:

Questionnaire for Village Profile

Questionnaire for Households

Questionnaire for Gender Analysis

All the questionnaires were pre-tested in the field and required modifications were made
before the initiation of actual survey.
A survey team consisting of three experienced Sociologists was constituted (two males &
one female). Briefing sessions were held for the survey team members to explain the
objectives of the study. Questionnaires were also discussed in detail in the briefing session.
To ensure that each interviewer understood the meaning of each question.
4.4.4
Culture
Concept of culture can provide ways of explaining and understanding human behavior, belief
systems, values and ideologies, as well as particular culturally specific personality types.
Culture is the full range of learned human behavior patterns. Culture is a powerful human
tool for survival, but it is a fragile phenomenon. It is constantly changing and easily lost
because it exists only in our minds (Edward B Tyler 1832-1917).
4.4.4.1 Settlement Structure
The information regarding settlements is given in Table 4.9 There are two major types of
settlements in rural study area.
Farm Village
It is the type where farmers are assembled in a village in the center of the farmland of the
mouza/village. They cultivate outlying fields. Table 4.9 reveals that 36 percent, 45 percent
and 55 percent villages have one settlement in Tehsil Depalpur, District Okara and Punjab
province respectively.

NESPAK-AAB-DMC

56

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Nebulous Farm
This is the type where some of the farmers live in a village and till the surrounding fields,
while other are scattered beyond the village to live on the isolated farms. Data presented in
table 4.1 shows that 63 percent, 53 percent and 42 percent villages comprises more than
one settlements in Tehsil Depalpur, District Okara and Punjab province respectively. About 1
percent, 2 percent and 3 percent mouzas / villages are unpopulated in Tehsil Depalpur
District Okara and Punjab province respectively.

Table 4.9:

Settlement Structure
Number of Settlements

Area

Depalpur
Tehsil
Okara
District
Punjab
Province

Total
Rural
Mouza
s

One
Nos.

Nos.

Nos.

Nos.

545

191

36

171

31

126

23

36

922

410

45

257

28

165

18

57

12

21

55

5595

22

15

1041

181

783

25394

1387
9

2-3

4-5

391
5

6-9

Rural
10
&
Unpopulat
Above
ed Villages
Nos
Nos
%
%
.
.

Source: Mouza statistics (Settled Areas) Government of Pakistan Statistics Division.


Agriculture Census Organization.

4.4.4..2

Religion

Religion is instinctive to man. It is inseparable from human society. Man is only a religious
being. Religion affects human behavior deeply. Religion helps to knit the social values of a
society into cohesive whole. It is the ultimate source of social cohesion. The primary
requirement of society is the common possession of social values by which individuals
control the actions of self and others and through which society is perpetuated. These social
values emanate from religious faith. Religion is the foundation upon which these values rest.
It is religion that asks man to renounce unsocial activities and requires him to accept
limitations upon his wants and desires. All the religions have preached love and nonviolence. They have emphasized sacrifice and forbearance. Table 4.10 shows percentage
distribution of the total population of the study area is 100percent Muslim. They constitute 98
percent in District Okara and 97.70 percent in Punjab Province. Percentage of Christian
population is 1.80 percent in District Okara and 1.90 percent in Punjab Province.

NESPAK-AAB-DMC

57

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 4.10:

Religion
(Percent)

Area
Study
Area
Okara
District
Punjab
Province

Schedule

Muslim

Christian

Hindu

Qadiani/Ahmadi

100.0

--

--

--

--

--

98.1

1.8

0.1

97.7

1.9

0.1

0.2

0.1

Caste

Others

*Very small number (not significant)


Source: i)
District Census Report 1998
ii)
Provincial Census Report of Punjab Population Census Organization

4.4.4.3 Language
Punjabi language is spoken by 95.7 percent in Okara District. Punjabi is very important
language which is very common in study area. About 3.5 percent individuals are speaking
urdu in Okara District and 4.5 percent in Punjab province as given in Table 4.11.
Table 4.11:
Area
Study
Area
Okara
District
Punjab
Province

Urdu

Punjabi

Sindhi

Languages
Balochi

Pushto

Siraiki

(Percent)
Others

--

100.0

--

--

--

--

--

2.8

96.7

0.2

0.1

0.2

2.0

73.6

0.2

0.9

0.9

21.4

1.0

*Very small number (not significant)


Source: i) District Census Report
ii) Provincial Census Report of Punjab Population Census Organization

4.4.4.4 Baradri
The baradri (brotherhood) is an important aspect of the rural society. Various branches of
baradri may not be living in the same locality. Mostly baradries form on the basis of blood
relation, caste and occupation. Baradri plays an important role in the farm events e.g. birth,
death, marriage etc. in the study area. If a ceremony is done properly it adds prestige to the
baradri and enhances the beauty of the occasion. People of the same baradri usually have
sympathetic feelings for each other. Vartan Bhaji, a custom in which they exchange gifts on
special occasions, is a very common affair of the baradri in the study area. Baradri is a sign

NESPAK-AAB-DMC

58

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

of solidarity and unity. It is the evidence of an integrated and pleasant social order
relationship.
4.4.5
Demographic Characteristics
The demographic characteristics of study area comprising Depalpur Tehsil and comparison
with the statistics of Okara District and Punjab Province are shown in Table 4.12. According
to the 1998 census the population of the Depalpur Tehsil 1.03 million inhabitants. The
annual population growth rate of Depalpur Tehsil Okara district and Punjab province is
estimated as 2.58, 2.42 and 2.64 percent respectively on the basis of intercensal period of
1981-1998. Population is projected by using annual population growth rate of 1981-1998 for
Depalpur Tehsil, Okara District and Punjab Province as given in Table 4.12.
The table indicates that current population is 1.37 million in Depalpur Tehsil. The population
density based on the projected figure for 2009 is calculated as 547 persons per sq.km in
Depalpur Tehsil whereas 666 and 479 persons per sq. km in Okara district and Punjab
province respectively. The population density Depalpur Tehsil and in Okara District is higher
as compared to Punjab Province.
Household size may also effects the economic situation of the household. Bigger household
size may mean more hands to do farm work or non farm work. It can also mean more
mouths to feed. Table No. 4.12 reveals that the average household size 6.8, 6.2, 6.5 and 6.9
in study area, Depalpur Tehsil, Okara District, and Punjab province respectively is almost the
similar. The relative proportion of two sexes in the total population is an important
demographic feature. Sex composition profoundly affects the social and economic behavior
of population. It gives the proportion of males to females and is commonly expressed as the
number of males per 100 females. The male female ratio in the study area (107:100) is
higher as compared to the ratio in Depalpur Tehsil and Okara District.
The dependency ratio of any area have negative effect on socio-economic aspects of life i.e.
especially on per capita income and ultimately on the standard of living. Table 4.12 indicates
that the dependency ratio (63 percent) in the study area is lower as compared rural
population of Depalpur, Okara District and Punjab province.

NESPAK-AAB-DMC

59

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 4.12:
Area

Area

Annual

(Sq.

Growth

Kms)

Rate

Demographic Characteristics

Population
1998

2009

(1998)
Depalpur
Tehsil

2502

2.58

4377

2.42

Okara
District
Punjab

20534

Province

2.64

Populati

House

Sex

Rural

Depende

on

-hold

Ratio

Propor

ncy Ratio

Density

Size

(1998)

tion

(2009)

(2009)
103083

136912

223299

291404

736212

984288

90

79

--

--

(2009)

547

6.2

108.5

79.7

91.0

666

6.5

109.6

77.0

90.0

479

6.9

107.0

69.0

87.0

--

6.8

107.0

100

63.0

Project
--

Area
Source:

i)
ii)

--

District Census Report 1998


Provincial Census Report of Punjab 1998, Population Census Organization

4.4.6
Age Distribution of Respondents
Age is another important demographic characteristic which has a bearing on the
employment and mobility. A study of distribution of heads of households by age will throw
some light on the type of strategies which may be helpful in raising their income and
employment. The data about age of household head (respondent) in study area as
presented in Table 4.13. Indicates that relatively more sample respondents fall in age group
of 45-54 years. The average age of sample respondents in Study area is 50 years.
Table.4.13:

Age Distribution of Sample Respondents


by household Categories

Age Group Years

(Percent)
Overall

Farm
Household
4
4
22
33

Non Farm Household


7
20
13
13

04
08
20
29

55-64

23

27

24

65 & above

14

20

15

Upto 24
25-34
35-44
45-54

Source:

Sample Survey

NESPAK-AAB-DMC

60

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.4.7
Caste / Baradries
The word caste comes from the Portuguese casta, meaning lineage. The male respondents
belong to different castes. Majority of the sample households (44 percent) belong to Mohar,
30 percent Watoo, 9 percent Kharal, 8 percent Rajpoot family whereas 9percent belong to
other castes like Arain, Dhool, Bhandara etc. as detailed in Table 4.14.
Table 4.14.

Households Distribution According to Caste

Sr. No

Caste/Baradri

Nos.

Percent

Mohar

29

44

Wattoo

20

30

Kharal

Rajpoot

Arain

1.5

Dhool

1.5

Bhandara

1.5

Phulerwan

1.5

Kalia

1.5

10

Kumhar

1.5

66

100

Total
Source:

Sample Survey

4.4.8
Disputes And Their Resolution
About 23 percent of the households informed that they had disputes with other i.e. land, live
stock, fodder stealing, house, water turn, women and children related and resolved through
Biratheries, Religious Leader, MPAs and at Police Station. While 77percent respondents
revealed that they dont have any disputes with others.
4.4.9
Education
A study of educational status not only provides guidelines to policy makers but also help in
understanding the demographic behavior of the population (Malik 1967). The literacy level is
one of the factors which determine the quality of the human resources. The low percentage
of literacy gives the indication of cultural barriers to the spread or innovations and scientific
methods. The data given in Table 4.15 indicates that the proportions of literate sample
respondents are 47percent in study area. Furthermore literacy rate in the large B farmers (73
percent) is more as compared with all categories of farm size. The literacy level of
respondents of medium, large A and large B farm size is 49 percent, 52 percent and 73
percent respectively, whereas literacy level of non-farm household respondents is
NESPAK-AAB-DMC

61

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

39percent. Data reveals that an increase in size of holding was found to have positive
impact on the literacy rate.The number of education institutions reflect the status of literacy
and education level in particular area. There are 5 Primary School for boys, 4 Primary
School for girls 2 Middle School for boys and 1 Middle School for girls at villages Nahal
Mahar, Dullayke Mahar, Qasimke Mahar and Basirpur Town. There is also one High School
for boys and one High School for girls in the study area at the distance of 7 km to 23 Kms.
There are 2 Degree Colleges one for boys and one for girls in Basirpur at the distance of
7Kms.
Table 4.15:

Education Level of Sample Population


(Percent)

Literacy

Small

Small B

Medium

Large A

Large B

Non

Less than

5 to Less

12.5 to

25 to

50 Acres

Farm

than 12.5

Less than

Less

& Above

Househo

Acres

Acres

25 Acres

than 50

Total

lds

Acres
Literate

25

33

49

52

73

39

47

Illiterate

75

67

51

48

27

61

53

100

100

100

100

100

100

100

Total
Source:

Sample Survey

4.4.10 Occupation
It is useful to have information about occupational distribution of members of the sample
households. Such information will facilitate better planning and execution of the project. The
rural community in the study area consists of two groups. Farmers and those who are
landless / non farm households. Farmers, who own or lease / encroach land, derive their
living by cultivating the farm land. This community may also supplement the farms income by
raising animals and off farm work. The members of non farm community generally do
agriculture labour, business, services, operating small shops, daily wage work, milk
processing and sales and other services to earn the income to fulfill their living necessities.
They conduct such business in their own village and nearby villages and in urban areas.
About 77 percent and 23 percent of the sample head of households of the area are engaged
in agriculture and non farm activities respectively (Table- 4.16)

NESPAK-AAB-DMC

62

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 4.16:

Occupation
(Percent)

Occupation

Major

Minor I

Minor II

Agriculture

77

--

Labour

15

25

67

Business

--

Milk Selling

--

39

--

Service

21

33

Fish Farm

--

--

Black Smith

--

--

--

--

--

--

100

100

100

Grind
(Chakki)

Mechine

Imam Masjid
Total
Source:

Sample Survey

4.4.11 Habitation
Housing facilities of the households reflect their financial position and living standard.
Habitation is identified as a space occupied for develling purposes and is further classified
according to the type of structure into three categories i.e. pucca, kacha and wood. Pucca
houses are constructed with baked bricks/ blocks / stones with cement and concrete
bounded. Kacha houses are made of unbaked bricks / earth bounded whereas wood houses
are made of wood / bamboos. As shown in Table 4.17 the average numbers of rooms per
household are 1.9 and 2.3 in the Okara District and Punjab Province area respectively. The
numbers of rooms in both cases are not sufficient.
Table 4.17:

Habitation
(Percent)

Wall Material

Okara District

Punjab Province

Overall

Rural

Overall

Rural

Baked Bricks / Blocks /


Stones

51.3

43.7

68.0

58.4

Unbaked Bricks / Earth


Bounded

46.9

54.4

30.4

39.7

Wood / Bamboo

0.8

0.8

0.7

0.8

Other

1.0

1.1

0.9

1.1

Rooms per house

1.9

--

2.3

--

Persons / Rooms

3.4

--

3.0

--

Source:

i)

District Census Report 1998

ii)

Provincial Census Report of Punjab 1998, Population Census Organization


Statistic Division, Government of Pakistan

NESPAK-AAB-DMC

63

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.4.12 Health
The population settle on embankment have no proper access to health facilities in the area
and have to travel Nehal Mohar , Basirpur and Haveli Lakha for their treatment at the
distance of 1Km, 7 kms and 23 kms respectively. All population takes treatment from
Doctors. Health condition of the people generally very poor due to commonly prevalent
health issues i.e. male nutrition, due to high rate of child birth, typhoid , cholera, malaria, and
skin diseases etc.
4.4.13 Drinking Water Facilities
The main cause of most of the communicable and abdominal disease is non availability of
clean drinking water. Bradley (1976) has dwelt on a number of tropical diseases relating to
water supply. About 20-30 different diseases may be caused by water supply for example,
viral, bacterial, protozal and helminthic diseases. According to him these diseases may be
water borne (infectious) water- bases (due to lack of water) and water related (from insects
in water).
From the above, it can be concluded that suitable safe drinking water is important factor
promoting human health and productivity.
During survey it was found that all families had installed hand pumps and electric motors
inside and outside their houses. The proportion of hand pumps for drinking water in the rural
areas of district Okara and Punjab Province households is estimated as 76 percent and 78
percent respectively which is also quite high as compared to other sources (Pipe, Well,
Pond, etc) of drinking water (Table 4.18)
Table 4.18:
Sources

Source of Drinking Water

Okara District

Punjab Province

All Areas

Rural

All Areas

Rural

INSIDE

87.8

85.7

86.7

83.4

Pipe (Nul)

14.6

10.0

24.3

11.0

Hand Pump

72.8

75.2

60.4

70.6

Well

0.4

0.5

2.0

1.8

OUTSIDE

12.2

14.3

13.3

16.6

Pipe (Nul)

1.5

1.5

2.2

1.7

Hand Pump

7.2

0.6

5.3

7.1

Well

0.7

0.9

2.2

3.1

Pond

0.2

0.2

1.1

1.5

Others

2.6

3.1

2.5

3.2

Source:

i)

District Census Report 1998

iii)

Provincial Census Report of Punjab 1998, Population Census Organization


Statistic Division, Government of Pakistan

NESPAK-AAB-DMC

64

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.4.14 Energy Sources


Energy is vital for Socio-economic development. Unluckily, due to isolation living of the
scattered population, rural electrification is missing at the Dharanga spur area i.e. 6
households resulting in the alternative use of kerosene oil for lighting. According to
District/Province census 1998, electricity is used by 65percent, and 63percent households in
Okara District and Punjab Province rural areas respectively (Table 4.19).
Table 4.19

Source of Light
(Percent)

Sources

Okara District

Punjab Province

All Areas

Rural

All Areas

Rural

Electricity

69.4

64.5

72.5

63.3

Kerosine Oil

29.2

34.2

26.6

35.8

Others

1.4

1.3

0.9

0.9

Source:

i)
iv)

District Census Report 1998


Provincial Census Report of Punjab 1998, Population Census Organization
Statistic Division, Government of Pakistan

4.4.15 Vulnerable Groups


There are two numbers of affected families which are vulnerable due to low income. Due to
the affect that these people do not have opportunities elsewhere to work for their livelihood;
thats why they are having abode along the right marginal bund of Suleimanki Barrage for
doing their petty labour. In addition to the compensation for their assets, the vulnerable
households will have an additional allowance of one month income/wages.
4.4.16 Gender Issues
Gender problems are critical and are connected to a sustainable development process,
which is usually perceived as women specific issues. In order to assess socio-economic
impact of running project on women of the project area, 46 females respondents were
interviewed by female sociologist.
Generally, the women carry out household work and look after the family and children. But
such family labor is unpaid and is assigned no imputed value which calculated the Gross
National Product (GNP) of the country. In the rural areas, women do carry out agricultural
activities such as sowing, harvesting, threshing and storage of crops, collection of fodder
and livestock care. In addition, women are engaged in non-farm activities such as sewing,
knitting and cottage industry etc. Although, such activities provide supplementary income for
their household, these are not fully captured in the computation of GNP.

NESPAK-AAB-DMC

65

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The numerical reality that women constitute about half of the total population of Pakistan
ideally assigns to them equal participation role in the economic life of the country and
through this approach; we cannot ignore their role in development sector. Therefore survey
was conducted by Gender Specialist. Focus group discussions were also held with the
women residing along the RMB as well as Dhranaga spur. Ensure representation and
presence of women from different socio-economic groups in all meetings. The study has
identified a range of positive and negative impacts of resettlement. Some of the positive
impact of the rehabilitation and upgrading of the Suleimanki barrage are enhanced economic
growth of the surrounding of those particular areas through increasing water efficiency. It is
the beacon of economic survival for those families who are often disturbed during flood
season in the shape of their livelihood, houses and standing crops losses. The flood also
becomes a cause of livestock loss, which supplements their income. The implementation of
the project will play important role to save human lives and economic resources of the area.
Social impacts of resettlement activities tend to affect women more than men. Breakdown of
social interaction with community is a direct result of dislocation which can affect women
badly.
4.4.16.1
i)

Socio-economic and cultural aspects

Marital Setup

The survey results indicate that 94 percent women get married within their families. The
custom of inter family marriages is very common in the project area. Such marriages are as
not only a link between man and a woman but it also play role to unite their parents' families.
ii)

Women Marriage Age

Women age at marriage also contributes a lot in terms of their health (particularly
reproductive), education and in the role of development. It is common trend in the study area
to marry the daughters at early age especially when they grow up/ reach at working age.
Survey results show that overall 46 percent of the women married at the age group of 14 to
19 years, 33percent at the age group of 20 to 22 years, 15 percent at the age group of 23 to
25 years and only 7percent at the age group of 26 years and above but not more than 30
years.
iii) Women Role in Decision Making
It is observed in the field that women have a insignificant role in decision making. Women
are actively participated in farm and non-farm activities but have little contribution in making
decision in these areas. .About 59percent women reported their participation in decision
making regarding domestic affairs. However, their participation in respect of property matters
or in business affairs is about only 22 percent.
NESPAK-AAB-DMC

66

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

4.4.16.2

Position of Women

Women role in development is not a simple one; it relates to a complete range of socio
economic activities. Involuntary dislocation may disturb their livelihood. According to the field
information it is found that female participation for the betterment of family is more as
compared to male. In economic side women participate in agriculture activities. They also
work as casual hired labor. Resettlement activities can have direct impact on women,
because they are responsible for collecting wood for fuel ,feeding livestock and participate a
lot for agricultural activities. Unless this impact is addressed in resettlement planning and
execution, it could result in women spending more time and resources accessing to fulfill
their needs. The field data indicates that 46 percent, 71 percent and 100 percent women
participate in agriculture, livestock and domestic activities respectively.

Women Participation in Household Tasks

Women also play vital role in maintaining domestic function such as cooking, cleaning the
house, washing the clothes & pots and looking after the family. Data indicates that almost
100% women involved in cooking, cleaning pots and in family caring activities.

Women Participation in Agriculture Activities

Women of the study area, undertake much of the work in the fields. Results of the data
indicates that 46 percent of families involved in agricultural activities. An increase in size of
holding is found to have a negative impact on the participation of women in agricultural
activities. All 46 percent women participated in various farming operation for crops of wheat,
rice, corn, cotton and fodder. These include cotton seed preparation, irrigation, land
preparation, applying manure, sowing, weeding, hoeing, picking cotton & vegetables and
collecting chaff and hey etc fodder cutting and livestock rearing. They are also working as a
casual hired labor for agriculture. They are working for both season Rabi and Khraif also. It
is also observed that wheat, rice, cotton, corn and fodder are the major crops.

Women Participation in Livestock Related Tasks

Livestock production is an important and integral component of farming systems in the study
area. Livestock also contributes a large proportion of the income of farmers with smalllandholdings. Results of the survey indicate that 100 percent families have livestock in their
houses. Many of the livestock caring jobs are considered womens work. About 71 percent
respondents (women) participated in livestock relating tasks such as cutting/chopping of
fodder, feeding, watering, cleaning the shed, bathing etc.

NESPAK-AAB-DMC

67

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Other Economic Activities

The rate of women participation in economic activities is very low in Pakistan especially in
rural areas. Women participation in economic activities will be increased to remove
inequities and imbalances in all sectors of socio-economic development and to ensure
women's equal access to all development benefits and social services. Women are working
as a causal hired labor in project area but their role in other economic activities is very low
due to lack of education and vocational skills. During survey, it is found that only one female
is conducting classes in Government High School for girls at village Jamalkot.

Existing Women Skills and Needs

Generally, the women carry out household work and look after the family and children. In the
project area women are also involved in traditionally activities such as sewing, knitting,
embroidery, preservation of vegetables and kitchen gardening. But such family labor is
unpaid because all such activities which result in direct income generation at home have
been classified for unpaid. The survey data indicates that 100% females show their interest
in the education of women, and specially interested in vocational/technical training activities
such as sewing, embroidery, knitting, soap making and painting etc. In fact, the activities that
they could carry out from the home and so not disturb the male patriarchy.
4.4.16.3

Socio-economic Impact of the Project on Women

A strategy has been developed to minimize involuntary dislocation impacts on women. No


female-headed households will be affected due to project activities .Efforts have been made
to minimize resettlement effects on females. Design engineers kept this in their mind and
avoided their dislocation to save four females headed households with other option of the
strengthening of the Right Marginal Bund.
During the survey, the female respondents gave range of positive and negative perception of
the project as follow;

Positive Impacts of the Project

The rehabilitation and upgrading of Suleimanki Barrage has a major positive impact of flood
control. Respondents (women) shared their perception regarding new employment
opportunities due to the project. Majority of the women in the area worked as a causal hired
labor as well as serve as a domestic maid and they show their interest to work during
construction activities. Some of the other positive impacts of project are rise in living
standard, generally better educational facilities and access to education for girls,
transportation facilities and better road infrastructure in remote areas.

NESPAK-AAB-DMC

68

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Negative Impacts of the Project

The adverse impacts on women are related to their day to day activities. Generally, women
are responsible for carrying food in the field, wood collection for fuel, and carrying &
preparing fodder in the family. Project activities could be restricted for female mobility during
construction period. They are largely engaged in the agricultural activities as a causal hired
labor and dislocation can result in loss of livelihood. During shifting period, they can not work
as a causal hired labor and this will add to womens economic hardships.
4.4.17 Resettlement Issues
The inventory survey reveals that all project activities would be operating on public lands
under use by the Punjab Irrigation and Power Department and the project would not require
any land acquisition. However, the embankment Right Marginal Bund (RMB) and Dhranga
Spur strengthening works would affect 11 residential structures that would need to be
relocated. These houses are scattered and located along the Right Marginal Bund and
Dhranga Spur on the land of Irrigation & Power Department. All these 11 affected families
are squatters. The affected population associated with these families is 99 persons. All the
structures are on government land. A resettlement Plan will be prepared according to the
ADB Safegaurd Policies and will be submitted under different cover

Plate 4.2: A View of Female Participation in Household Relating Task

NESPAK-AAB-DMC

69

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Plate 4 4: A view of females participation for livestock activities

Plate 4.6: A view of Kacha Affected House

NESPAK-AAB-DMC

70

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Plate 4.8: Right Divide Wall and Fish Ladder Upstream of Barrage

Plate 4.9: Left Divide Wall and Fish Ladder Upstream at Barrage

NESPAK-AAB-DMC

71

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Plate 4.10: Fazilka Drain entering Barrage Pond from India

Plate 4.11: Bela Developed in Left Pocket of Pond Area

NESPAK-AAB-DMC

72

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Plate 4.12 :

Plate 4.13 :

NESPAK-AAB-DMC

Consultation with Wildlife Staff at Wildlife Public Park

Consultation with Fishing Department at Suleimanki Barrage

73

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

CHAPTER 5:

STUDY OF PROJECT ALTERNATIVES

The analysis of alternatives for the project is a vital part of the EIA process as it gives the
opportunity to review and assess different ways of meeting the project objectives so that the
environmental impact of the project is minimal. The following options/alternatives were
analyzed for strengths and weaknesses of the proposed project:
Addition of six new bays along the right flank of the barrage.
Provision of flood bypass arrangement. The safe barrage capacity is adopted as
330,000 cusecs, as it was achieved in 1988 flood. The remaining 100,000 cusecs
needs to be bypassed through bypass channel.

5.1

NO PROJECT OPTION (WORST CASE SCENARIO OPTION)

Analysis:
Strength and Opportunities

There will be no adverse social impacts as no land will be required from private/illegal
settlers and for immigrating new settlers.

The recurring cost of the Project will be avoided.

The irrigation systems downstream of the canals command area (CCA) of Pakpattan
Canal, Sadiqia Canal and Fordwah Canal shall not be interrupted due to project
activities.

Loss of the agriculture land which may be required for the borrowing area and
contractors facilities (labour camp, batching plants, plant depot etc), will be avoided.

The efforts and investments will be saved and will be allocated to another project in
case this project is not taken up at all.

Weakness and Threats

The no project alternative is undesirable as it would mean continued economic,


social and environmental losses.

There will be loss of property and agricultural land due to uncontrolled breaching
along the weakened and damaged embankments in the event of a flood.

The local population shall be denied employment and training during project
construction phase and later through escalated economic activities.

About 100 to 150 cusecs of water will leak through the gates and less water will be
available for the canals off take from the barrage. This will adversely impact crop
intensity in canal command areas.

NESPAK-AAB-DMC

74

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The aging process along with inadequate/deferred maintenance has contributed to a


general deterioration of different components/structures and heavy damages to the
regulating gates and hoisting equipment. Any serious damage to this barrage can
result in colossal losses in the form of total or partial disruption of irrigation supplies,
non/less-production of agricultural crops within the canals command area, loss of
government revenue, rehabilitation cost of emergency repairs, thus adversely
affecting the national economy in additional to human sufferings beside multitude of
social and environmental hazards. The minimum duration require for the construction
of similar barrage will be easily 5 years plus.

Around 13,900 Acres of land, property and infrastructure may be flooded in the event
of high flood such as the one that occurred in 1988.

5.2

ADDITION OF NEW BAYS

Option 1:
The following components are included in this option

Strengthening of RMB and LMB by raising heights up to 5ft above HFL.

Construct 6 new water bays of 60ft each at the right end of the barrage, as shown in
figure 5.1.

Necessary alteration in the barrage structure associated with the addition of bays i.e.
relocation of guide wall(s), canal head regulators, marginal bunds etc.

Increase the barrage capacity by developing cunnet within the bella and flush the
bella during high flow.

Gate Repair Work

Improvement in Wildlife Public Park

Strength and Opportunities

Minimize the requirement of breach at the event of high flood.

Gates repair work will rectify leakage losses through the damage gates and more
water will be available for irrigation purpose in the canals.

Employment and training opportunities for the local population which will provide
them life time benefits.

Rehabilitation of Wildlife Park involve plantation of hundreds of new trees, which will
improve the aesthetic value and enhance the biodiversity of the area.

Formation of cunnet within the bela will allow the bela to be washed in the event of
flood and the barrage will become capable of passing discharge to its maximum
capacity.

NESPAK-AAB-DMC

75

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Weaknesses and Threats

Higher adverse social impacts as the numbers of existing shops and houses,
including Rangers rest house situated along right guide wall will be required to
relocate for the construction of new bays.

Temporary adverse environmental impacts on wildlife habitat during construction


phase.

Higher project cost compare to option 2.

Hundreds of matured trees will be uprooted to clear the area for the construction of
new bays and relocating the existing structure e.g. canal head regulator, right guide
wall etc.

Construction phase will consist on longer duration and therefore elongated adverse
environmental impacts i.e. dust pollution, noise pollution etc are envisaged.

Higher environmental management cost, mainly due to the higher environment


monitoring cost during the construction phase.

5.3

OPTION 2: PROVISION OF FUSEPLUG WEIR AND FLOOD BYPASS CHANNEL


(SELECTED OPTION FOR DETAIL DESIGN)

The main components in this option include

Strengthening RRE and LRE by raising heights up to 5ft above HFL.

Flood water bypass channel of capacity 100,000 cusecs. The anticipated channel
dimensions are 1100ft bed width and 16ft flow depth with side slope 2H:1V,
Figure3.1 shows the layout.

Road Bridge over flood bypass channel.

Provision of spillway/fuse plug at RMB.

Level crossing across Pakpattan Canal.

Increase the barrage capacity by developing cunnet within the bela and flush the bela
during high flow.

Gate Repair Work

Improvement in existing Wildlife Public Park

Strength and Opportunities

Strengthening of embankments will minimize uncontrolled breaching, occur in the


event of high flood.

Main town and villages and thousands of agricultural land will be saved from flood
damages at the event of high flood by diverting the flood water with flood bypass
channel.

Lesser disturbance of the wetland from the construction activities.

NESPAK-AAB-DMC

76

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Employment and training opportunities for the local population which will provide
them life time benefits.

Enhance Bio-diversity with new plantation and re-modeling of the existing Public
Park.

Gates repair works will rectify leakage losses through the damage gates and more
water will be available for irrigation purpose in the canals.

Provision of road bridge maintain the link of the barrage with other town through road
network.

Lower cost compare to other option 1.

Weaknesses and Threats

Temporary adverse environmental impacts on wildlife habitat during construction


phase.

11 No. of houses falling within the work area along the embankments need to be relocated.

309 No. of trees found within the proposed escape channel location will be uprooted.

acres of agricultural land will be acquired for escape channel.

Temporary adverse environmental impacts from construction activities of road bridge


and spillway construction i.e. air pollution, dust pollution, noise pollution etc.

5.4

CONCLUSION

No project option is rejected because the feasibility study conducted in 2005 concludes that
the Sulemanki Barrage is an unsafe structure. The structural failure of the barrage could
cause the colossal losses in the form of human life, wildlife, land, property and irrigation set
up.
Option 1 has been rejected on the basis of higher adverse environmental and social impacts
including inundation of agricultural land and resettlement of the people and business units
(shops) situated at the western end of the barrage. Also the option technically ruled out as it
disturb the symmetry of the barrage which could encourage shoaling (bela formation) and
reduce the barrage capacity.
Option 2 considered to be the best option in respect of environmental & social aspects. The
work scheme also provides the most cost effective solutions, of the issues identified in
feasibility and design calculation, as compare to the other options. Lower part of the
proposed flood bypass channel is recommended to develop as a lake, which will enhance
the biodiversity of the area.

NESPAK-AAB-DMC

77

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

CHAPTER 6:

IMPACT ASSESSMENT, MITIGATION AND


ENHANCEMENT MEASURES

This chapter discusses the potential impacts of barrage rehabilitation works which have
been identified through the use of standard checklists, and expert knowledge and
experience. The impacts identified for the selected option of work scheme were assessed for
their significance keeping in mind their consequences, reversibility, occurrence, duration,
location, timing etc. The evaluation of the environmental & social impacts has been
summarized in Table-6.1.
6.1

POTENTIAL IMPACT SOURCES

Environmental impacts and social impacts attributed to the Project can be broadly classified
into three main groups

Impacts during design phase

Impacts during construction phase

Impacts during operational/post construction phase

Some of the impacts can be anticipated and avoided at design stage with appropriate
adjustment in the Project Design some can be mitigated by good implementation technique
and others by following the operational manual.
6.2

IMPACTS AND MITIGATIION MEASURES ASSOCIATED WITH THE


IMPLEMENTATION OF THE PROJECT

The following impacts are anticipated in case of the implementation of the Project

The project will not have any significant adverse impact on the existing residential
area other than as a result of increase in noise and dust levels and movement of the
additional machinery and traffic.

There will be no major loss or damage to livelihood. The temporary employment to


the local communities will be given. This will be a significant positive impact.

There is no historical monument or archeologically sensitive site hence no apparent


impact on such sensitive sites is expected.

As far as tree cutting is concerned, survey of the existing trees on the site shows that
309 no. trees will be uprooted on site during construction activities.

There will be no permanent and significant adverse impacts on the aquatic ecology
of the river and wildlife habitat of the area as seasonal flow regime of the river will

NESPAK-AAB-DMC

78

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

remain unchanged. To facilitate the works on the barrage the cofferdams will be
built. The environmental impact of cofferdams will be localized and short term
(during operation), and which can be mitigated with good engineering practice.
Potential adverse environmental impacts of selected work schemes on the physical,
biological and socio-economic environment during design, construction and operational
phases have been identified. Measures to mitigate these impacts and their residual impact
are discussed below.
(i)

(ii)

Physical Environment

Land Resources

Hydrology and Water Resources

Air Quality

Noise level

Biological Environment

Flora

Fauna

Fish

Endangered species

(iii)

Culture and Heritage

(iv)

Socio-economic

Table 6.1 summarizes the potential impacts associated with the barrage rehabilitation
project. The physical, biological, cultural and social impacts have been discussed under preconstruction (design phase), construction and operational phase. Each sub component has
been assessed as slight, moderate or significant. The impacts have then been marked as
avoidable, mitigable and irreversible. The components so assessed have been discussed
and explained after the assessment Table 6.1.

NESPAK-AAB-DMC

79

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 6.1 (Sheet 1 of 3):

Project Evaluation of Environmental Impacts

Impact
Category

Impact Assessment

Slight
1*

Moderate

2** 3*** 1*

Significant

2** 3*** 1*

2** 3***

1. Design Phase
1.1

Damage
Retrogression

from

1.2

Damage to flood retain


embankments

1.3

Obstruction
to
migration in the river

fish

Obstruction
to
gate
Operations and leakage
from the damaged gates
2. Construction Phase

1.4

Physical

Impacts of location of
Labour Camp, Batching
Plant and equipment &
material yard
Impacts
of
Waste
Disposal site

Environment

2.1

Land

2.2

Resources

2.3

Impacts of Borrowing Site

2.4

Damage to Paths, Access


Roads and Cross Drains
Impacts of Crushed Stone
Transportation
Impacts of oil, chemical
Spill or Dumping out near
Building or House
Damage the agricultural
landorcropdestruction

2.5
2.6
2.7

9
9

*Avoidablethroughdesign
**
Mitigation through contractors obligation or by communities through social framework
agreement(SAF)
***
Nonreversible,Permanentchange(tobeadopted)

NESPAK-AAB-DMC

80

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 6.1 (Sheet 2 of 3):

Project Evaluation of Environmental Impacts

Impact
Category

ImpactAssessment

Slight
1*

Moderate

Significant
1*

2**

3***

1*

2**

3***

2**

3***

2.ConstructionPhase
Physical
Environme
nt

Hydrology
and Water
Resources

AirQuality

Noise

Biological
Environm
ent

*
**
***

2.8

2.9

2.10
2.11

Impacts of using groundwater as


drinking Water & Wastewater
disposalImpacts
Contamination
of
Surface
water due to construction
dismantling of Cofferdam
Contamination
of
surface
water
due
to
Electrical
Mechanical Work
Impact of Extended Canal
Closure
Road

9
9
9

2.12

Impact
of
Construction

Bridge

2.13

Impact of Fuse Plug and Flood


Escape Channel Construction

2.14

Impact
of
Source
Construction Water

of

2.15

Dust
Smoke
and
other
Pollutants from Plants &
Equipments

2.16

Smoke from Burning of Waste


material or Burning Firewood

2.17

Impact on Air Quality from


Earth Work Activities

2.18

Noise
Pollution
Construction Activities

2.19

Damage
Resources

2.20

Disturbance to Wildlife

to

from

Biological

9
9

Avoidable through design


Mitigation through contractors obligation or by communities through social
framework agreement (SAF)
Non-reversible, Permanent change (to be adopted)

NESPAK-AAB-DMC

81

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 6.1 (Sheet 3 of 3):

Project Evaluation of Environmental Impacts

IMPACT
Category

Slight

Impact Assessment

1*

Moderate

2** 3*** 1*

Significant

2** 3*** 1*

2** 3***

2. Construction Phase
Socio
Economic

2.21

Impacts due to Land Acquisition

2.22

HIV/AIDS
and
communicable diseases

2.23

Impacts on Existing Services;


education, health, electricity and
water supply etc.

2.24

2.25

other

Impacts
of
finding
Archaeological site, Graveyard
etc
Impact on Public Health &
Safety due to Construction
activities

2.26

Impact on Employment

2.27

Tribal Tension and local rivalries


9
on canal and aquatic life

3. Post Construction
Monitoring
Impacts due to non -application
3.1
and
of the prescribed O&M plan
Evaluation
as
per
Operational
Continuous evaluation of design
Manual
3.2
efficiency
and
Monitoring
Plan
*
**
***

9
9

9
9

Avoidable through design


Mitigation through contractors obligation or by communities through social
framework agreement (SAF)
Non-reversible, Permanent change (to be adopted)

NESPAK-AAB-DMC

82

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

6.3

IMPACTS AND MITIGATION MEASURES DURING DESIGN PHASE

6.3.1

Damage from Retrogression

Adverse Environmental Impact


Accompanied by pulsating Hydraulic jump, damage to friction blocks and upstream floor of
the barrage.

Mitigation Measures
Repair and grouting the damaged floor and blocks.

6.3.2

Damage to Flood Retain Embankments

Adverse Environmental Impacts


The aging process along with inadequate / deferred maintenance has been contributed to
general deterioration of the structural integrity of the embankments. This could trigger
uncontrolled breaches at the event of flood and cause significant damages of the
surrounding area.

Mitigation Measures

Increase the embankments height and width to increase their resistance against floods.

6.3.3

Fish Migration Obstruction

Design Adequacy of the Fish Ladder


Existing fish ladder design is appropriate but obstructions were found in the form of
vegetation. There was also some structural damage to stop smooth movement of fish across
the ladder.

Adverse Environmental Impact


The minimum water discharge required to operate the fish ladder is 500 cusecs, which is not
feasibly available during the low flow season and therefore the fish ladder is out of order for
about 9 to 10 months a year. This triggers the growth of vegetation inside the ladder and
obstructs the water flow through the ladder during the couple of months of high flow.
Mitigation Measures
The structural component of the ladders will be repaired during project implementation.
Inspect the fish ladder on a regular basis to make sure that the ladder is in working condition
over the whole year and operates effectively during high flow.

NESPAK-AAB-DMC

83

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

6.4

IMPACT AND MITIGATION MEASURES DURING CONSTRUCTION PHASE

6.4.1

Physical Environment

(a) Land Resources

6.4.1.1 Impacts of Labor Camp, Batching Plant and Material & Equipment Yard
Adverse Environmental Impact:
Because of the availability of the ample IPD land near the barrage, this will not cause any
serious problem. IPD will arrange the land suggested on figure 1.3 for labour camp and
batching.

Mitigations Measures:
The contractor will, in consultation with residence engineer, resolve the exact location
of all these facilities.
IPD will arrange the land for the contractor camp and batching plant as indicated on
Figures 3.1 and 1.3. If the contractor prefers anyother location then the contractor
will be responsible for the additional payment to the land owner(s), responsible for
the developing the social & environmental baseline condition and agreed the new
proposed location with consultants environmentalist and PMO.

6.4.1.2 Impacts of Waste Disposal Site


Adverse Environmental Impacts:
There is sufficient IPD land available on site for the Waste Disposal Site and no private land
will be required for this purpose. Inadequate disposal of waste could contaminate the land. If
the waste is not handled properly it could be a nuisance and cause diseases in the local
community. Domestic waste contains a high percentage of readily degradable hydrocarbon
which releases a bad odor when it undergoes decomposition, especially in hot and humid
conditions. Construction waste classified as inert waste which could be a problem to dispose
off.
Mitigation Measures
Domestic waste generated at the labor camp and site offices should be collected and
temporarily stored at the designated bonded area within the camp area before being
disposed off the site by the specialize contractor.

NESPAK-AAB-DMC

84

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

A temporary domestic waste storage area should be prepared, maintained and


visually inspected on a regular basis by the contractor to prevent the land adjacent to
the waste disposal site from contaminating.
The location of construction waste disposal site should be such that no tree cutting,
crop destruction or private land acquisition occurs. The proposed location indicated
in figure 1.3.
Construction waste should not be mixed with domestic waste as the construction
waste could be reused as a fill material or disposed off separately.
The temporary waste storage area for domestic waste site will be rehabilitated at the
completion of the project and photographic record will be kept as an eveidance.
There should be burning pit on site where the combustible waste could be burnt. The
recommended dimensions of the burning pit are 15ft x 12ft x 4ft (length x width x
height).
Residual Adverse Impact:
The waste storage area will attract animals and spread a foul odor in the surrounding area.
6.4.1.3 Impacts of Borrowing Site
Adverse Environmental Impact:
Additional soil required for the strengthening the embankments will be acquired from the
other activities of the project i.e. construction of spill way involving excavating work. If the
contractor desires to excavate the soil from other areas than approval must be obtained from
the Consultants Environmental Specialist and PMO. Quarrying and cutting land is not
required in this project. The excavating activities could have adverse environmental impacts
including soil erosion, drainage problem, threaten existing structure stability, and impact the
health and safety of the workers and local population.
Mitigation Measures:

The earth required for revamping of retired embankment and other works would be
used out of the available government land where possible. If there is lot of
transportation involve in using IPD land and earth is required to be lifted from private
own land, then the owner(s) of the land will be duly compensated by the contractor.

The contractor will not leave the borrow pits in an unusable condition such that it
could be filled with rain water and cause the problems for the community e.g.
breeding place for mosquitoes etc.

The contractor will ensure that the selected borrow areas are clearly demarcated,
and indicate the maximum allowable depth of the pit before the soil is excavated.

NESPAK-AAB-DMC

85

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

No soil will be excavated outside the demarcated area. If unexpected soil or strata is
found during excavation at the site then the excavation must be stopped immediately,
and the environmentalist and site manager must be informed as soon as possible.

The edges of the pits should be given flat slopes and area should be leveled as far
as possible when the excavation is complete.

Barren or unfertile land will be preferred for use as a borrowing area than agricultural
land.

If the agricultural land along the embankments needs to be used as a borrowing area
then the following additional measurements will be undertaken by the contractor:
Excavate at least 50m away from the toe of the embankments
Remove 6 inches of the topsoil and store on a separate site for its re-spread back
on the leveled borrow area
Excavate up to maximum of 3 feet
Level slops as far as possible
Place the topsoil back on reasonably leveled area

Residual Adverse Impact:


Uneven topography will be generated due to excavating land.

6.4.1.4 Damage to Paths, Access Roads and Cross Drains


Adverse Environmental Impact:
Infrastructure (road, drains etc) could be damaged through carelessness of the
drivers/operators of heavy machinery. Such carelessness can cause considerable damage
to paths, road and drains if the drivers/operators are not made aware, trained and bound to
protect the infrastructure.
Mitigation Measures:

An effective signology can reinforce the instructions to the drivers for example
maximum load limit, type of vehicle allowed, speed limit etc.

It is a Contractors contractual obligations to impose strict control over operators and


drivers of all types of vehicles.

Should any damage take place due the site traffic movement, the contractor must be
bound to carry out the repair immediately.

Enforce the maximum speed limit for site traffic to 20 km/hour.

6.4.1.5 Impacts of Oil/Chemical Spill or Dumping out any Building or House near the
Project Area
Inadequate storage and mobilizing of material on site could cause accidental spills or
leakages. Dumping of waste material or spillage at the private land or outside the designated
NESPAK-AAB-DMC

86

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

area will contaminate the land and water resources as the unconfined aquifer consist on
sandy stratum on site.

Mitigation Measures:

It is a Contractors Contractual obligation to design, construct and maintain material


storage areas.

All the material mobilization should be controlled and carried out by the competent
staff.

All loading and unloading of the materials should be carried out with an appropriate
plant

& equipment.

The material storage area should be bounded.

Spill kits, including absorbing pad, sand bags etc, should be available at material
storage

area to handle any accidental spill.

In case of damage to private land, the land owner(s) should be compensated.

6.4.1.6 Impacts of Crushed Stone and Fine Aggregate Transport


Adverse Environmental Impact:
Stones shall be brought from Sargodha District or Margalla hills, so no quarrying has to be
done locally. But the vehicles carrying the stones shall exert additional traffic load on the
roads leading to the project area. By keeping the road dust free and repaired even the
slightest impact shall stand mitigated.

Mitigation Measures:

It is a Contractors contractual obligation to use the roads and paths carefully and in
case

of any damage, repair the damaged roads and paths immediately.

Undertake regular spraying of water on traffic routes and places prone to cause dust
pollution.

Lorries should cover with the cloth or fine net to minimize the dust pollution and
accidental drop of stones.

6.4.1.7 Impacts of Finding Graveyard and Burials


No graveyard is identified within the direct area of influence of the project activities. However
if unrecorded graveyards and/or burials are found during the courses of construction
activities, the supervising agency will contact and work with local religious authorities within
the immediate project area to allow for possible identification of the remains and where
appropriate, properly undertake relocation and burial.

NESPAK-AAB-DMC

87

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

6.4.1.8 Contamination from Oil & Diesel and Other Spill from Construction Machinery
The dumping site for waste material or empty containers can damage the land with
associated physical, biological and social losses. The impacts can be mitigated through
effective application of the maximum spill regulations, general criteria for oil and breakage at
construction sites, as per standards set forth by Oil Spill Contingency Plan of PKP
Exploration Ltd, Guidelines for Oil Spill Waste Minimization and Management issued by
International Petroleum Industry, Environmental Conservation Association and with
mitigation measures described below.

(i)

Minor Spills

Soil contaminated by minor spills/leakages (defined as leaks from vehicles, machinery,


equipment or storage containers such that the area and depth of soil contaminated is less
than one (1) sq.ft and three (3) inches respectively) is to be scraped and sent to a burn pit
(incinerator).
(ii)

Moderate Spills

Moderate spills are defined as spills of volume less than or equal to 200 liters. These are to
be contained and controlled using shovels, sands, absorbing mat and native soil. These
equipments and materials are to be made available at camp sites during the operation (Spill
Kit). The contaminated soil will be excavated and sent to the treatment site such as
bioremediation or solidification/stabilization (S/S). The excavated area will be lined with an
impermeable base before being filled with clean soil.
(iii)

Major Spills

Major spills are defined as spills of volume much greater than 200 liters. This would require
indication of Emergency Response Procedure and Oil Spill Contingency Plan to be prepared
by the Contractor in consultation with the Engineer. These spills are to be handled and
controlled by a specialize contractor to clean the site.
Mitigation Measures:

All the oil based material should be stored in the designated bounded area.

The Spill Kit should be available on site to handle small spills on site.

Good house keeping will minimize accidental spills.

All loading and unloading of material should be supervised and carried out with
appropriate plant.

Empty drums of the fuel should be handled with care as some material may be left
over in the drums or container.

NESPAK-AAB-DMC

88

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

All the liquid material or fuel should be stored well away from any control water body
i.e. river, canal, wetland etc.

(b) Hydrology and Water Resources


6.4.1.9 Water Supply System & Wastewater Treatment Impacts
Adverse Environmental Impact:
Pumping groundwater from the major aquifer for water supply for the labor camp shall
neither cause any significant change in the groundwater reservoir, nor in the river or canals,
which in fact recharge the reservoir. There will be no any residual adverse impact on
groundwater. The impact can be considered as slight and mitigable. The contractor should
tap the underground reservoir and install hand pumps or tube wells with an overhead water
tank to supply drinking water to the labours and workers at appropriate pressure.
Groundwater test results indicate the shallow groundwater quality is not fit for human
consumption because of elevated concentration of E-Coli, as shown in table 4.6.

It is envisaged that a considerable volume of wastewater will be generated from labour


camp. There are plenty of examples of successful systems of using wastewater for
agriculture. Domestic wastewater is expected to be contaminated with pathogens. Many
factors affect the degree to which the potential risk due to the presence of pathogen in
wastewater can become actual risk of disease transmission and pose a health risk to
consumers and workers (farmers). The following situation can have an adverse impact on
human health:

1. Either an infective dose of an active pathogen reaches the field or pond or the pathogen
multiplies in the field or pond to form an infective dose.
2. The infective dose reaches a human host.
3. The host become an infected
4. The infection causes disease or further transmission.

Mitigation Measures:

It is the responsibility of principal contractor to test and confirm the suitability of the
groundwater before its supply for domestic use.

NESPAK-AAB-DMC

89

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The depth of the extraction well should be increased until the quality of groundwater
meets the WHO standards or the Filtering Unit can be installed by the contractor to
achieve WHO standards.

Four main measures are recommended to be considered to protect health;


wastewater reuse, wastewater treatment, crop restriction, control of wastewater
application and exposure, and promotion of hygiene of those wastewater treatment.

It is the responsibility of the contractor to set up a suitable and appropriate


wastewater collection and disposal system.

Method and level of treatment of wastewater depends upon the anticipated use of the
effluent. In view of the expected use of treated water for agriculture purposes,
treatment at primary level will be cost effective. It is therefore proposed that waste
stabilization ponds or underground septic tank with bypass arrangement for rainwater
be provided in the labour camp with about three days storage capacity of waste
water.

To keep the cost to a minimum it is recommended to install a partial wastewater


treatment system, using waste stabilization ponds or underground septic tanks, as
well as crop restriction control measure for reuse of wastewater in agriculture. The
stabilization pond should not be deeper than 4m to avoid anaerobic degradation of
the organic compound of wastewater. Treatment by waste stabilization pond system
or underground septic tank for about 3 to 4 days retention removes most of helminth
eggs sufficiently to protect the health of agriculture workers and consumers.

If the wastewater is discharged into the control water body i.e. river or canal then it is
a contractors contractual obligation to confirm that the effluent meets the NEQS
levels. Provision of underground septic tank is a preliminary treatment and reduces
the total suspended solids (TSS) concentration to the acceptable level however it may
not reduce the BOD level up to the required level. Therefore it is suggested that, if
required, an aeration treatment system should be emplaced to meet the BOD level
before discharge of the effluent into the river. Aeration of wastewater can be achieved
from number of treatment methods including mechanical aeration, providing steps in
the open channel, aerobic stabilizing pond (maximum depth up to 4 feet) etc. The
selection of treatment method depends on the availability of space and initial
concentration of the BOD.

The treated domestic sewage should be tested on regular basis before it is pumped
into the river or used for agricultural purposes.

Residual Adverse Impact:

NESPAK-AAB-DMC

90

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Bacterial removal with three days retention of wastewater in the stabilization pond will
only be sufficient to reduce but not completely eliminate the risk to consumers of
vegetable crops. Crops restriction will therefore be essential.

Stabilizing pond could cause odor and nuisance problems in the surrounding area.
The pond should therefore be at an appropriate distance from the living area and the
direction of wind flow should be kept in view.

Treatment of wastewater with the

underground septic tank will not cause any odor except during the occasional
cleaning of the chambers.

6.4.1.10 Contamination of Surface Water Due to Construction/Dismantling of


Cofferdam
Adverse Environmental Impact:
During the construction and subsequent removal of coffer dams, the soil material can
contaminate river water and affect aquatic life, particularly downstream fisheries.
Mitigation Measures:

The material used for the construction of cofferdam should not contaminate river
water in terms of suspended solids, pH, oil etc. The contractor will use good
engineering practices to minimize contamination of river water.

6.4.1.11 Contamination of Surface Water Due to Electrical/Mechanical Works


Adverse Environmental Impacts
As most of the electrical / mechanical work is to be performed at the barrage structure, any
accidental spill of material could be devastating for the river environment. The work may also
involve the building of temporary structures like the cofferdam, scaffolding etc. Failure of the
temporary structure could cause serious injuries to the workers and pollute the river.
Mitigation Measures

All temporary structure should be designed and build by a specialized contractor.

The temporary structure should be approved by a competent person before its use.

Daily Inspection should be carried out at the work area before the start of every
working shift.

Good housekeeping should be maintained to avoid any accidental spill or falling of


objects in to the river.

Oil based material should be kept in bunded bowser or container.

Electrical equipment should be handled with extra care.

NESPAK-AAB-DMC

91

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Provide proper PPE (personal protected equipment) for all the workers as a
precaution against any mishap, and interlink various parts of the construction
complex.

6.4.1.12 Impacts of Extended Canal Closure


Adverse Environmental Impacts
Gate repair work and the installation of the hoisting system and electric motors will require
the closure of canals. Non availability of the canal water could adversely affect crops and
people living along the canal. The canal water is primarily used for agricultural purposes and
at a few places within the canal command area for domestic use e.g. cloth washing, kitchen
washing and for even cooking purpose specially along the Fordwah Canal.

Mitigation Measures:

All the activities that require canal closure will only be undertaken during the annual
routine closure of the canals.

If the extended canal closure is required then alternate water supply should be
arranged in affected canal command area.

The work of construction of level crossing over Pakpattan canal shall need dry area
and a temporary diversion channel shall be provided during construction phase to
fulfill the water requirement of Pakpattan Canal Command area.

6.4.1.13 Impact on Source of Construction Water


The contractor could use river water as a source of water for sprinkling on kacha (unpaved)
path for dust control and for vehicle washing purposes.

Groundwater could be used as a source of water supply for the contractors camp and the
batching Plant. The contractor should tap the underground reservoir and install hand pumps
or tubewells with overhead tanks to supply drinking water to the labour camp, and to the
batching plant for concrete preparation. Withdrawing water from the aquifer shall not cause
any significant change in the storage of the aquifer nor the river and canals, which eventually
recharge it. The impact can be considered as slight and mitigable.

Mitigation Measures:

The contractor is obligated under the contract to pay for water obtained from private
sources.

NESPAK-AAB-DMC

92

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The contractor is obligated under the contract to supply running tap water, flush
latrines and stabilization ponds or underground septic tanks for the disposal of
wastewater through the sewerage system.

All the wastewater generated from vehicle washing and site set ups e.g. batching
plant, plant & equipment yard etc should be tested to meet the NEQS standards for
effluents before being disposed off.

(c) Air Quality


6.4.1.14 Dust, Smoke and other Pollutants from Plant & Equipment
Adverse Environmental Impact:
From previous work experience (rehabilitation of Taunsa Barrage etc) it has been observed
that the emission or dust from the batching plant can be very harmful for the site workers
and the local population. The emission/dust could cause skin and respiratory disease e.g.
skin rashes, lungs problem etc. Roads and traffic will be affected due to the movement of
heavy vehicles in the area. The possible location has been proposed for the Batching Plant.
Contractor should select the suitable location provided the following control measures are in
place:

Mitigation Measures:

Air quality should be monitored on regular basis near the plant.

The plant should be located at least 500m away from any living area, as one of the
suggested site on Figure 1.3.

The plant should not be operated outside working hours.

Regular spraying of water should be undertaken to minimize dust pollution.

All vehicles, machinery, equipment and generators used during construction activities
will be kept in good working conditions to minimize exhaust emissions.

Proper PPE should be issued to the site workers and measures should be adopted to
ensure that the workers will wear the PPE properly when working on site.

If contractor select any other site than the site suggested on figure 1.3 than the site
has to be agreed with the consultants environmentalist and PMO. The following
additional control measures may need to be implemented for different location
The plant has to be a Zero Emission Plant. This will include using washed
aggregated and enclosed cylose with automatic injection system of the material in
to the mixing chamber. Recently a zero emission plant has been established and
is working successfully at Jinnah Barrage, and could be visited for getting details
before installation.

NESPAK-AAB-DMC

93

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The plant area should be constructed and maintained on an impermeable layer to


prevent contamination of river water from surface run off.
The access roads for the delivery Lorries pass through the living area. These
roads/paths should be sprayed with water on regular basis to minimize dust
pollution.
Residual Impacts:

Deterioration of air quality.

Although the recommended plant consists of an enclosed cylose, the plant activities
will generate some dust especially in consistently dry weather.

6.4.1.15 Smoke from Burning of Waste Material or Burning Firewood


Adverse Environmental Impacts
A large number of big and small fires in the labor camp can produce smoke and smog which
can cut off visibility, reduce traffic ability and cause suffocation along with causing diseases
of the respiratory tract.
Mitigation Measures:

It is the contractors contractual obligation to use and provide clean and smoke free
fuel in the labor camp.

Cutting and burning trees or shrubs for fuel shall be prohibited.

Gas Cylinders should be used in the labor camp for cooking purposes.

6.4.1.16 Impact on Air Quality of Earth Work Activities


Adverse Environmental Impacts
Excavating activities will generate dust and pollute the surrounding area. Emissions from the
plants used in earth work activities will also degrade the air quality of the site.

Mitigation Measures

Regular spraying of water should be undertaken to minimize the dust pollution.

All vehicles, machinery, equipment and generators used during construction activities
will be kept in good working condition to minimize the exhaust emissions.

(d) Noise
6.4.1.17 Noise Pollution from Construction Activities
Adverse Environmental Impact:
It has been proposed to raise the embankment height and width to maintain the stability of
the slopes. The embankments farm the boundary of the wetland and trees along the

NESPAK-AAB-DMC

94

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

embankments provide habitat of many species of birds. Construction activities along the
embankments could generate noise and air pollution and disturb the natural habitat.
Mitigation Measures:

Suitable equipment and plant should be used in execution of the work to minimize
noise pollution.

The noise level should be monitored on a regular basis and levels should be
maintained within the NEQS level. At the start of the work activities noise levels
should be monitored on hourly basis for at-least the first 2 days of work, after which
the monitoring interval could increase to daily basis.

If required, the work area should be cordoned off with noise absorbing panels to
segregate the work area from the barrage pond area.

The contractor will regularly spray water on the site traffic routes to minimize the dust
pollution.

All vehicles, machinery, equipment and generators used during construction activities
will be kept in good working conditions and will be properly tuned and maintained in
order to minimize noise pollution, exhaust emission and minimum land disturbance.

It is the contractors obligation to stop unnecessary traffic and workers from entering
into the barrage pond area.

All working activities should be restricted within the allowed working hours.

The maximum speed limit of 20km/h should be enforced for vehicles using the
embankments and access road.

The Traffic Management Plan will be included in EMP and should be implemented
during construction phase.

Movement of the site traffic and tree cutting will generate some noise.

6.4.2
Biological Environment
The anticipated biological impacts can be on the following:

Damage to Flora

Damage to Fauna

Damage to Endangered Species

Damage to Fish

6.4.2.1 Damage to Biological Resources and Disturbance of Wildlife


Adverse Environmental Impacts
About 10 acres of land will be required for each Labor Camp & Batching Plant. The labor
camp and batching plant location should be carefully selected to minimize tree cutting. The
NESPAK-AAB-DMC

95

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

approximate total number of trees requiring uprooting is counted to 309, as shown in Figure
4.5. There is a risk of the destruction of habitat of the area due to the noise and dust
generated from the movement of site traffic and work activities along the embankments. Bela
trimming activities could also adversely impact the wildlife.

Mitigation Measures

The proposed area for labor camp and batching plant will not require any tree cutting.

The outside boundary of the camp should be fenced or walled to keep camp activities
inside the camp area.

It is the contractors obligation to ensure that unnecessary and out of bound


activities/movements are not done outside the area allotted to him for setting-up the
labor camp, material depots and machinery yard.

No fire arms should be carried by any of the workers.

All forest, wildlife and fisheries laws should be fully respected and abided by the
contractor and his work force.

Limits and norms of wildlife, forestry and fishery should be fully respected and
implemented.

Necessary sign boards should be displayed to remind the obligation of labour,


visitors and members of public towards Biota.

Inspections by wildlife, forest and fisheries officers are facilitated in camps to facilitate
the proper implementation of relevant laws.

24 hours security should be provided by the contractor at the Labor Camp and
Batching Plant.

Every tree cut on site for the execution of work should be replaced with the plantation
of minimum of 5 new trees. Therefore minimum of 1550 trees will need to be planted
and protected until maturation by the contractor, in place of 309 trees that will be
uprooted during construction of bypass channel and associated structure.

All vehicles, machinery, equipment and generators used during construction activities
will be kept in good working condition and be properly tuned to minimize the adverse
impact on waterfowl habitat by reducing noise, exhaust and land disturbance.

Communities are given awareness and are involved in the proper protection of the
Biota inside and around the project area.

No unauthorized tree or bush cutting will be allowed. Should it be necessary, it must


not be done without the permission of the The Engineer and must follow the change
management process.

NESPAK-AAB-DMC

96

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

If possible, the nests of birds on trees that need to be uprooted should be shifted to
other nearby trees.

Walk over survey should be conducted before excavating the bela and any ground
nest or particular habitat (rabbit whole etc) should be relocated.

Excavating work within the bela should not be arranged during the fish breeding
season (April to June) to avoid the adverse impact due to a possible increase in the
turbidity of the river.

Residual Impacts

Nests of some of the birds shall be destroyed when the trees and bushes are cleared
along the embankments within the purposed location of flood bypass channel.

Disturbance of wildlife by the site traffic and noise from tree cutting/uprooting.

6.4.3
Socio-Economic Impacts
The overall impacts of the Project on the social and economic activities in the project area
will be positive. A Resettlement Action Plan (RAP) has been also prepared to compensate
the people living along the embankments as squatters on government land and need to be
removed, of course with due compensation. RAP will be submitted under different cover.
The adverse environmental impacts and their mitigation measures are discussed as follow:

6.4.3.1 Impacts of Land Acquisition


Adverse Environmental Impacts
Generally land acquisition is required for work activities such as widening of the
embankments, access road, Labor Camp, Batching Plant, work base area, structural waste
disposal site and Contractors Camp. To facilitate these activities, the I & P Department is
already in possession of enough land where these works can be executed. Proposed
locations for labor camp and batching plant site would also be accommodated in the
Irrigation Department land.
Mitigation Measures

All the activities requiring land acquisition are to be planned by IPD. Private land is to
be acquired under the 1894 Land Acquisition Act and the cost of the land is to be
paid to the owners. An appropriate framework agreement should be completed and
signed by all the concerned parties.

Social Action Plan (SAP) has been prepared to restore the livelihood of the affectees
(encroachers).

NESPAK-AAB-DMC

97

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

6.4.3.2 Social Impacts on Local Population due to Migrating Labor from other Parts
of the Country
Adverse Environmental Impacts
There is a risk of adversely affecting the social life of the local population due to the arrival of
a large number of laborers from outside the area. Extra burden on the local infrastructure
and services e.g. medical facility, shops, restaurants, mosque, public transport etc. is also
anticipated.

Mitigation Measure

The outside boundary of the camp should be fenced or walled for security reasons.

Locating a labour camp at least 500m or ideally 1km away from the villages (local
settlement).

Leisure facilities including play grounds, restaurant etc should be provided inside the
labour camp.

All the unskilled labour and where possible skilled labour should be arranged locally.

Pick and drop facilities should be arranged.

6.4.3.3 HIV/AIDS and other Communicable Diseases


The Labor Camp, their interaction with truck drivers and like personnel are potential places
for the spread of HIV/AIDS if the incidence exists. Majority of the people living in the
surrounding of the Project, and potential Labor are not aware of the source, mode of
communication or consequences of HIV/AIDS. Although their religious and cultural value
system, to a large extent excludes the outbreak or rapid communication of HIV/AIDS, yet its
occurrence in such a situation cannot be precluded. It is necessary that along with other
communicable diseases like Cholera, Typhoid and Tuberculosis, awareness and preventive
campaigns are run from time to time in the Labor campus and the field offices of the Project
on Communicable diseases.

Mitigating Measures:
The Contractor shall:
Arrange to run a proper campaign, in the labour camp, to make people aware of the
cause, mode of transmission and consequences of HIV/AIDS.

Strengthen the existing local health & medical services for the benefit of the
labourers as well as the surrounding villages.

NESPAK-AAB-DMC

98

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Ensure proper cleanliness and hygienic conditions at labour camp by ensuring a


clean mess, proper drainage and suitable disposal of solid waste. Inoculation against
Cholera will be arranged at intervals recommended by Health Department.

Keep all the camps, offices, material depots, machinery yards and work site open for
the inspection of health and safety measures, and related documents.

6.4.3.4 Existing Services & Employment (Positive Social Impacts)


The economic analysis shows high economic benefits compared to costs. Salient economic
benefits of the project are:

Improvement of available services in the area and opportunities for employment,


education, healthcare, transportation, especially for women and children.

Easy marketing of agricultural products.

Availability of jobs during construction phase shall employ and train a large number
of unemployed youth. They will receive a life time of benefits through skill training,
capacity building and poverty alleviation. A large number of semi-skilled and unskilled
workers in the project area will be hired.

Greater awareness about Healthcare including HIV/AIDS and Hepatitis amongst the
labourers and the local community shall be created.

At micro level, economic activities may bring the cost of living down by making
essential commodities available in greater bulk and at cheaper rates. This combined
with better employment opportunities will bring poverty line rate lower.

Improvement in public parks will raise the aesthetic value of the area and will attract
tourism. Rehabilitation of the barrage structure will also have a positive impact on the
local tourism industry.

6.5

Boost to agriculture through ensured and enhanced irrigation water.

Increased economic activity with improved irrigation.


OPERATIONAL AND MANAGEMENT (O&M) PHASE

Rehabilitation & Up-gradation of Suleimanki Barrage will not make any alteration in the
Barrage operational process and therefore no any adverse impact is anticipated to induce
due to the implementation of the project. The flood bypass channel will be activated during
high flood only and less area will be inundated than the area usually inundated during high
flood after the completion of the project.

At operational phase of the proposed Project a comprehensive Operation and Management


Manual (O&M) shall be prepared by the Project Manager at the completion of the work as
NESPAK-AAB-DMC

99

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

per ISO Standards. An effective monitoring and evaluation has to be done as per O&M and
monitoring plan. Mistakes at operational level or handling the operations by untrained staff
can prove very risky and costly. Important points to be attended at the operational stage are
as follows:

(i)

Develop comprehensive O&M Rules

(ii)

Strict implementation of prescribed Environmental Management Plan (EMP).

(iii)

Continuous evaluation of design efficiencies

(iv)

Understanding and training of staff on Operation and Maintenance Manual

(v)

Annual Environmental Audit

(vi)

Regular maintenance of engineering works

(vii) Continued public consultation and feed back on it


(viii) Continued attention towards gender issues and women consultation
(ix)

Irrigation system to run up to its design capacity and not beyond

(x)

Refresher Training Courses for operational staff.

On the basis of the impact assessment, the project will improve environmental and social
condition of the area. No permanent adverse environmental impacts have been identified
due to the project implementation. All the adverse impacts resulting from the construction
activities are mitigable.

NESPAK-AAB-DMC

100

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

CHAPTER 7:

ENVIRONMENTAL MANAGEMENT PLAN

This chapter comprises a detailed Environmental Management Plan (EMP) for the project.
The EMP proposes an effective plan of action that will indicate responsibilities and required
measures to minimize the negative environmental & social impacts at various stages of the
project.
The Environmental Management Plan for the Project has been discussed under three main
components:

Mitigation Plan

Monitoring Programme

Institutional Arrangements

Most of the mitigation activities planed in the EMP will be executed & cover under provisions
in the construction contract and with necessary agreement with the communities.
7.1

MITIGATION PLAN

The mitigation plan is a key component of EMP. The mitigation plan includes measures to
mitigate potential negative impacts and enhance its positive impacts during initial physical
works and normal operation of Irrigation System. This section outlines the potential impact of
rehabilitation works on the physical, biological and socioeconomic environment and their
associated mitigation measures as already identified in ESIA report of the Suleimanki
Barrage Project. It also assigns the responsibilities for implementing these measures.

Lists of mitigation measures which will be directly covered by the environmentalist


and contractors and not those mitigation measures which are covered under civil or
mechanical work.

The person(s) responsible for ensuring the implementation of the measures.

The person(s) responsible for the monitoring.

Parameters to be monitored for the effective implementation of measures.

A time scale for the implementation of measures to ensure that the objective of
mitigation plan are fully met.

The Mitigation and Monitoring Plan for the activities likely to have a direct impact on the
environment is presented in EMP table.

NESPAK-ABB-DMC

101

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

7.2

MITIGATION OF ADVERSE IMPACTS AT DESIGN PHASE

Majority of negative impacts can be avoided (eliminated) through the use of adequate and
environmentally sound technical design. The Project has however been designed on the
basis of the lessons learnt from similar projects and major design initiatives undertaken to
avoid any major negative impacts are as follows:
1.

Necessary measures should be taken to exclude any big deposits of soil or debris
anywhere.

2.

To ensure the availability of water at the tail ends of canals off take from Sulemanki
Barrage.

3.

As far as possible appropriate indigenous technology and knowledge should be


utilized while planning and designing the project.

4.

Improve flood fighting plan by strengthening embankments, provision of flood bypass


channel and Barrage structure.

7.3

MITIGATION ADVERSE IMPACT AT CONSTRUCTION PHASE

To reduce the potential impacts of the construction activities there will be a monitoring
programme to assess contractors compliance/performance with the project EMP during
construction phase.
The contract document will contain requirements for:
(i)

Proper management of construction waste.

(ii) Control measures for waste fuel disposal.


(iii) Reduction of oil/lubricants, spill or leakage, noise and dust level.
(iv) Rehabilitation of areas used for construction detours and sites used for temporarily
storage of construction materials.
(v) Proper use and maintenance of equipment with appropriate noise and smoke
abatement.
(vi) Restoration of borrow areas (whether on state land or private land).
(vii) Other requirements as obligation of the contractor emanating from the EMP.
(vii) Specific provisions will also be included to make it mandatory to use formal health
and safety measures including protection against Communicable diseases and
Hepatitis. Group insurance measures to minimize accidents and avoiding fatalities
during the construction process.
(viii) Advisory element to address a number of other issues will also be included in the
contract. These will include:

NESPAK-ABB-DMC

102

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Road Closure

For transporting construction material or conveying heavy machinery to the site, the rural
roads passing near or through village(s) may have to be closed temporarily and access of
public for certain period may have to be blocked. The dates, timings and duration of such
period will need to be agreed with authorities and communities.

Cultural and Historical Resources

Communities shall be requested to identify in the field, all known sites of cultural and
historical value that may be affected by the Project, for protective actions by the contractor.

Archaeological Field Support

The Government of the Punjab will make available (on demand) a qualified archaeologist to
conduct field investigations when important search work and new material sites area
opened. No such site is yet in view but just in case it does, the services of archaeologist will
be obtained.

Graveyard and Burials

If unrecorded graveyards and/or burials are found during the courses of construction
activities, the supervising agency will contact and work with local religious authorities within
the immediate Project area to allow for possible identification of the remains and where
appropriate, properly undertake relocation and burial.

Local Employment

The contractor will be advised to arrange locals as unskilled labour and skilled workers are
easily available from local communities as and when required. It is desirable that maximum
employment benefits are made available to local communities.

Land Acquisition and other Compensations

During the community consultation, in the Project area, it was made clear by the
communities that they would expect due compensation, if their buildings, trees or land were
affected or destroyed during construction activities or any of its allied structures. Social
Action Plan has been prepared to address the social impacts of the Project.

Resource use Agreement Construction Materials

Earth is commonly available in abundance around the Barrage area. Stones are available
from District Sargodha and Margalla hills. Yet there may be a need for additional agreement
with public to obtain certain materials. In that case the farmland should be given the last

NESPAK-ABB-DMC

103

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

priority in procuring the fill material when inevitable, however, due compensation should be
paid. Whenever the borrow pits are dug, considerable care should be taken in their location.
The site may invariably be rehabilitated after use. Ideal situation would be that the site is
made good to a condition similar to that prior to the project. It will be helpful if Plategraphs of
pre-project condition are used for the purpose of comparison.

Resource Use Agreements Water

Although ample quantity of groundwater is available in the Project area, yet the contractor
will be required to confirm the quality and demand detail and indicate source of water prior to
the start of construction. Disposal plan for wastewater without polluting the fertile soil, river
water or ambient air, shall be produced by the contractor for approval of The
Engineer/Project Director.
7.4

MONITORING PLAN

Monitoring Plan is an essential component of the Environment Management Plan (EMP).


Implementation of the EMP shall be the contractual obligation of the Contractor. For that the
Contractor shall engage full time technical staff capable of carrying out the suggested
measures in the EMP as contractual obligations under the contract agreement. The
construction supervision consultant shall also have a full time Environmental specialist to
provide an overall professional cover to the environmental monitoring process and the
procedures and initiate required reports and point out any gaps in the implementation of the
mitigation measures or enforcement of the measures of the EMP. Environmental unit (EU)
under PMO will be responsible of the overall implementation of EMP and provide technical
guidance to the construction supervision consultants and contractors.
The Parameters, frequency, responsibility and mitigation measures for monitoring have been
described in comprehensive Environmental Mitigation and Monitoring Plan (EMMP).

NESPAK-ABB-DMC

104

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Environmental Mitigation & Monitoring Paln


Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Cost

Monitoring
Executor

A-

Parameters for Frequency

Monitor

LAND
RESOURCES

1.1

Ensure

that CEnv

Borrow

Barrow Material:

materials from

Soil

earth borrowing

the designated area of are clearly demarcated

site.

the site will be required with barricading fenced

excavation

from selected borrow areas

CSCEnv

Records of clear BC

PMO-

boundary marker Once before start of

EU

demarked

BOQ

in excavation

place

for the strengthening of before starting any soil


the embankment and removing and no soil
construction of coffer removal is undertaken
dams. Construction of outside the demarcated
flood bypass channel area.
will

generate

soil 1.2

Ensure

that CEnv

CSCEnv

Plategraphs

material which could be Photographs are taken

PMO-

records

used as fill material of the area before and

EU

BC, DC, AC

BOQ

SFA

provided it meets the after the restoration of


engineering

the borrowing site

parameters. Contractor 1.3 Ensure that the

CSCEnv

Compliances

DC

has to get approval of excavation for fill

PMO-

with

Check once a week

the borrowing area from material is restricted to

EU

Specification

on typical working

Consultants

NESPAK-ABB-DMC

specified depth.

CEnv

day

105

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Control in place. BC, DC

Specialist and EU of surface drainage is

PMO-

Their

PMO before commence provided to control the

EU

effectiveness

Environmental

1.5 Ensure that the

excavation on site

surface run off

Once

BOQ
before

in construction

case of rain

Once a week on a
typical working day

Excavation and earth 1.6 Ensure that the


movement

CEnv

CSCEnv

activities movement of earth

may generate the dust moving machinery is

PMO-

and affect the air quality limited to the work

EU

of the surrounding area.

Compliance

DC:

BOQ

Site inspections

Daily
Once a month

area.
1.7 Ensure that Erosion

CEnv

CSCEnv

Visible signs of DC

Material to be used for protection measures

PMO-

any soil erosion

the construction of the are taken, such as

EU

BOQ

Monthly basis
Once after rain

coffer dams will include retaining wall (if


silt for core filling, soil require), avoidance of
material
filling.

for

random steep cut


1.8 If agricultural land

CEnv

CSCEnv

is used as borrowing
area then the land will

PMO-

be restored by the

EU

contractor and follow

detailed DC, AC

protocol

in Daily

checklist

At

completion

BOQ
of

excavation
When required

the following steps


NESPAK-ABB-DMC

106

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Plategraphs

DC, AC

borrow area to be

PMO-

record

When required

levelled as far as

EU

Records

BC, DC

Remove first 15cm


top soil and keep it
on site to re-spread
after completion of
the excavation.

Excavation of the
earth fill be limited
to an approximate
depth of 90cm.

Stabilized the slope


during the
excavation.

1.9 Ensure that the

BOQ

possible and top soil


restored.
1.10 Ensure that

CEnv

CSCEnv

complete

PMO-

At the start of the

documentation for the

EU

excavation.

BOQ

borrow areas is
NESPAK-ABB-DMC

107

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

maintained i.e. volume


excavated, date,
levelling date after
completion of
excavation
1.11 Ensure that

Compliance

DC

regular water sprinkling

PMO-

Daily

carry out during

EU

When required

BOQ

executing of excavation
to mitigate the dust
pollution.
2

Construction of

New roads will not

2.1 Contractor will

new Access

require providing the

Road and

CSCEnv

Compliance with BC, DC

furnish the traffic

PMO-

specification

When required

access to the

management plan,

EU

Widening of

contractors facilities i.e.

according to the

Existing Roads

batching plant, material

recommendations

yard, labour camp etc.

made in ESIA and must

Access roads for the

be implemented in

approach to the boat

order to control the

bridge will require.

traffic.

There is ample IPD

2.2 Ensure that the

Compliance

BC, DC

land available on site

temporary rout(s) are

NESPAK-ABB-DMC

CEnv

CEnv

CSCEnv
PMO-

Direct Cost

BOQ

Daily
108

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

the suggested layout of

adequate for the

the access roads does

existing traffic plus the

not require private land

site traffic.

acquisition.

2.3 Ensure that regular

The general mobility of

water sprinkling is

PMO-

local community their

carried out to mitigate

EU

livestock as well as

the dust pollution.

their business activities

2.4 Ensure that the

and clientele in and

EU

CEnv

CEnv

CSCEnv

When required

System in place

DC
When required

CSCEnv

Compliance

DC

traffic sign board

PMO-

Plategraphs

Daily

around the construction

regarding revised road

EU

area may be hindered.

layout and change in

Unchecked speeding

speed limit or new

may cause human and

speed breakers are

livestock injuries and

placed at least one Km

fatalities as a result of

from the alteration.

highway accidents.

2.5 Ensure that the

CEnv

CSCEnv

BOQ

Direct Cost

When required

Compliance

BC

alternative route is

PMO-

Once at start of the

designed on the basis

EU

allied work

Direct Cost

of the traffic survey


conducted by the
contractor.
2.6 Ensure that mobility
NESPAK-ABB-DMC

CEnv

CSCEnv

Compliance

DC

BOQ
109

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

of the men and animal

PMO-

is not hindered due to

EU

Social Survey

Daily
When required

the construction
activity.
2.7 Any damage to the

CEnv

CSCEnv

Record

DC

land, property or

PMO-

Plategraphs

Once at the start of

existing roads from the

EU

SFA

the work

contractors activities

When required

will be remediated by
the contractor at the
earliest possibility.
3

Site for

It has generally been

3.1 Ensure that the

Disposal of

observed that at

selected disposal site is

PMO-

Construction

completion of

marked and fenced

EU

Waste Material

construction the waste

before starting the work

material is dumped at

3.2 Ensure that

the site without proper

Photographs are taken

planning. The material

of the area before and

PMO-

from the coffer dams

after dumping the

EU

will be in significant

waste

quantity and will require

3.3 Ensure that all

proper disposal site.

trucks used for the

NESPAK-ABB-DMC

CEnv

CEnv

CEnv

CSCEnv

CSCEnv

CSCEnv

Record

BC

BOQ

Plategraphs

BC, DC

BOQ

record

Once before start


When required

System in Place

BC, DC

BOQ

Once at the start of


110

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

transportation of waste

work

construction material

PMO-

are covers and

EU

When required

watertight
3.4 Ensure contractors

CEnv

CSCEnv

obligations define in

PMO-

contract document are

EU

Compliance

DC

BOQ

Daily

followed.
3.5 Ensure that the

CEnv

CSCEnv

System in Place

movement of lifting

DC

BOQ

Daily

machinery and vehicles

PMO-

is limited to the

EU

When required

disposal site.
3.6 Ensure that waste

CEnv

CSCEnv

Compliance

DC

properly disposed off,

Daily

compacted and cover

After every rain fall

in a manner that does

PMO-

not affect the natural

EU

BOQ

When required

drainage.
3.7 Ensure dumping

CEnv

CSCEnv

and levelling on site


only as agreed per
NESPAK-ABB-DMC

Follow Contract DC

BOQ

Documents and Daily


PMO-

complete SFA

When required
111

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor
contract agreement

Monitor
EU

and SFA (in case


private land used)
4

Installation

of Land Requirement:

Batching Plant

4.1 Ensure that no

CEnv

CSCEnv

Compliance

BC

Ample waste land is

private land is used to

PMO-

Once at the time of

available near barrage

establish the Batching

EU

installation of

to establish batching

plant. Contractor needs

plant.

to get approval from

SFA

Batching Plant

CSCEnv and PMO-EU


if he/she uses any
private land for this

NESPAK-ABB-DMC

Land Contamination

purpose. Contractor will

Dumping of waste fresh

pay for the private land.

concrete may

4.2 Ensure that the

contaminate the land

CEnv

CSCEnv

Compliance with BC

location of the batching

PMO-

specification

Raw material:

plant is at least 500 m

EU

Raw material for the

from the villages (main

construction work

settlement) and out of

mainly include cement,

the prevailing wind. If

sand, aggregate, steel,

the selected location is

water lubricants, fuel

less than 500m from

and additives. The

the living area than it

SFA

Once before
installation of
Batching Plant

112

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

material will be stock

has to be zero

pilled at the area

emission plant.

provided by IPD near

4.3 Ensure that land

the batching plant.

contamination from the

PMO-

Daily

Wind direction

batching plant, during

EU

When required

While installing the

transportation and

batching plant the

dumping of the wasted

direction of the wind

fresh concrete is

should be consider.

controlled through

System in place

DC

SFA

careful working of the


Contractors crews to
avoid spillage of
concrete and dumping
of waste concrete on
private land. Carry
fresh concrete in
mobile concrete drums
4.4 If the selected

NESPAK-ABB-DMC

CEnv

CSCEnv

Design and

BC

location is next to the

prepare the

At the stage of

control water body i.e.

Batching Plant

establishing

Sutlej River or active

area by a

batching plant

canal then the area for

competent

DC

BOQ

113

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

batching plant should

person.

Weekly inspection
When required

be bunded with an

PMO-

Plategraphs

impermeable layer to

EU

record

CSCEnv

Compliance

stop contaminating the


river or canal water
from the surface run off
in case of rain or
otherwise. The area
should be maintained
on regular basis.
4.5 Ensure that leak /

CEnv

DC

spill record is

PMO-

Daily

maintained for each

EU

When requiredd

BOQ

incident of spill or
damaged vehicles.
Damaged/defected
vehicles will not be
operated unless
repaired.
4.6 Ensure that the

NESPAK-ABB-DMC

CEnv

CSCEnv

Compliance with BC/DC

material is stocked

PMO-

specification

pilled at the designated

EU

BOQ

At the time of
establishment of

114

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

area provided by IPD

Batching Plant

near the construction


site.
4.7 Ensure that surface

CEnv

CSCEnv

System in place

DC

drainage is not blocked

PMO-

Daily

due to the pilling of the

EU

Once a month after

raw material.
4.8 Ensure that the

BOQ

each rain.
CEnv

CSCEnv

Compliance

BC

location of the batching

PMO-

Once at the time of

plant is such that the

EU

installation of

wind direction may be

BOQ

Batching Plant.

away from the


settlement
5

Contractors

Land Requirement:

5.1 Ensure that no

CEnv

CSCEnv

Compliance

BC

Camp Location There is ample IPD

private land is used to

PMO-

Once at the Time

and Workshop.

land available around

construct the contractor

EU

of camp

the project area for the

camp and workshop.

contractors camp,

5.2 Ensure that the

officer hostel, work

NESPAK-ABB-DMC

BOQ

establishment
CEnv

CSCEnv

Measured

BC

location of the labour

PMO-

distance

Once before the

shop etc. So no private

camp will be at a

EU

land will be acquired for

distance of 500m from

the construction of

the major local

BOQ

establishment of the
camp.

115

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

NESPAK-ABB-DMC

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

these facilities. IPD will

settlement.

arrange land for the

5.3 IPD will provide

labour camp

space near the barrage

PMO-

Once before the

construction and

to establish contractors

EU

establishment of the

batching plant.

camp and workshop.

Disposal of Waste

5.4 Ensure that

water. The unmanaged

Compliance

BC

BOQ

camp
CEnv

CSCEnv

Plategraph

BC:

Photographs of

PMO-

records

Once before

disposal of wastewater,

adjacent area of camp

EU

generated from labour

site and other features

camp & vehicle

are taken prior to any

washing area, will

activity which will be

contaminate land. The

used as a reference

contractor can use the

when restoring of site

existing disposal

5.5 Ensure that room

system (for offices and

CEnv

construction activity

CSCEnv

Compliance per BC:

size is as per standard

PMO-

specification

official residence) after

specification.

EU

making necessary

5.6 Ensue that

renovation / expansion

domestic washing

of the system. However

areas are demarcated

PMO-

the existing disposal

and water from

EU

system can not cope

washing areas and

with the wastewater

kitchen is released in

CEnv

CSCEnv

BOQ

BOQ

During camp design


phase

System
places

in DC

BOQ

Daily
When required

116

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Cost

Monitoring
generated from labour

sumps

camp.

5.7 Ensure septic tank

Executor

Monitor

CEnv

CSCEnv

of appropriate design

System
places

in BC, DC

are used for sewage

share with IPD for the

treatment and outlets

PMO-

facilities of water

released into sumps,

EU

supply, telephone lines

further treatment

and electricity on

system or used for

payment basis.

agriculture.

Disposal of solid

5.8 Ensure that

waste. Unmanaged

latrines, septic tanks,

PMO-

During design

disposal of waste will

and sumps are built at

EU

phase of camp set

contaminate land.

a safe distance from

up and waste

Existing disposal

water hole (tube wells

treatment system

arrangement can be

or hand pump), stream,

used after making

or dry streambed and

necessary renovation /

the bottom of the sump

expansion of the

is above the ground

system by the

water level.

contractor.

5.9 Ensure that Sumps

In absorbent

BOQ

Once before start of

Utilities: Contractor will

are:

NESPAK-ABB-DMC

Parameters for Frequency

work

CEnv

CEnv

CSCEnv

When required

Compliance

BC

CSCEnv

Compliance per BC

PMO-

specification

EU

BOQ

BOQ

Once at the Time


of camp
117

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

soil

establishment

Down slope
and away from
the camp

Downstream
from the camp
water source
and above the
high watermark
of any nearby
water body (if
any)

5.10. Ensure that

CEnv

CSCEnv

System in place

BC

effective drainage

PMO-

Once at the start of

system is in place at

EU

work

BOQ

site
5.11 Ensure that

CEnv

CSCEnv

System analysis

DC

existing wastewater

PMO-

On-going

Monthly basis

disposal system is not

EU

consultation with

overstressed, if used.
5.13. Contractor make
assessment and carry
NESPAK-ABB-DMC

BOQ

local authorities
CEnv

CSCEnv
PMO-

System in place

DC

Direct Cost

When requiredd
118

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor
out renovation /

Monitor
EU

expansion works of
existing facilities in
consultation with IPD.
IPD to assist the
contractor in this regard
5.14 Ensure the

CEnv

CSCEnv

Implementation

application of Solid

of

Waste Management

Disposal Plan

Plan, as described in

BC, DC

BOQ

Waste Once before


establishing
Contractors Camp

ESIA:
- Material suitable for

CSCEnv

recycling, collect

Daily during
Construction Phase

separately in three
bin system and sold
- Combustible waste
burnt at burn pit

When required
PMOEU

only
- Non- combustible,
non recyclable
garbage sent to the
designated landfill

NESPAK-ABB-DMC

119

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

site in an area.
- Medical waste

Direct Cost

transported to any
hospital incineration
plant
- Solid residue from the
septic tank will be
transported to
municipal sewage
facilities at the
nearest place
- Contaminated soil
sent to burn pit or
landfill.
6

Relocation of

Land Requirement:

6.1 If happened

Camps, Material

The recommended

Storage area,

CSCEnv

Compliance with BC

contractor obligations

PMO-

SFA

When requiredd

locations for Batching

defined as per Contract

EU

Batching Plant

Plant, Labour Camp

documents and SFA

and Special

site and contractors

agreement

Approaches

camp are approachable

6.2 If the contractor

Compliance

BC

Routes and

through provincial

selects different

PMO-

At the set up of the

Roads.

roads. Therefore no

location for the

EU

Batching Plant,

NESPAK-ABB-DMC

CEnv

CEnv

CSCEnv

SFA

BOQ

120

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor
private land will require

Batching Plant, labour

for access roads.

camp etc from the

Monitor
Labour Camp etc

recommended
locations than the
contractor will develop
base line data for the
new location on his
own cost, resources
and get approval from
the CSCEnv and PMO.
7

Access Tracks

NESPAK-ABB-DMC

Damage paths roads

7.1 No specific action is CEnv

and linear fixtures

required except that the

crossed/damaged by

contractor has to

PMO-

moving machinery

remain vigilant that the

EU

moving to and from

moving machinery

the construction site:

should remain within

Heavy traffic may

the boundary of I&P

damage the existing

Department land

roads or private

7.2 After completion of

property. Contractor will

construction work all

PMO-

carry out necessary

the damaged roads will

EU

repair work.

be restored by the

CEnv

CSCEnv

CSCEnv

Compliance with

DC

map

Daily

Site inspections

Once a month

Compliance

AC

BOQ

When requiredd

121

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Compliance

is dumped only on

PMO-

civil drawing

Once at the start of

locations allowed by

EU

Site Inspections

work

contractor, as it is
involved in contractors
obligations.
7.3 Ensure that gravel

to DC

the Consultants and

BOQ

On monthly basis

dumping of gravel does


not result in blocking of
traffic or damaging
vegetation.
7.4 Ensure that

CEnv

CSCEnv

Compliance

DC

BOQ

construction corridors

PMO-

Daily

along the access road

EU

Monthly basis

are marked
7.5 Ensure that the

CEnv

CSCEnv

Control in place

DC

BOQ

access roads do not

PMO-

Once at the start of

block the natural

EU

work

drainage and culverts


7.6 Ensure that surface

NESPAK-ABB-DMC

CEnv

CSCEnv

Control in place

DC

BOQ

run-off controls are

PMO-

Once

after

installed and

EU

rain storm

every

122

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

maintained so as to
minimize soil erosion
and ponding of area
with rain water
7.7 Ensure adherence
to the speed limit of 40

PMO-

km/hr at the access

EU

Compliance

DC

BOQ

When requiredd

roads
7.8 Ensure that

CEnv

CSCEnv

System in Place

DC

BOQ

construction corridor is

PMO-

Daily

monitored and repairs

EU

When requiredd

are undertaken when


required
7.9 Ensure that

CEnv

CSCEnv

vegetation clearing will

Compliance with DC
EIA/EMMP

be minimized and no

PMO-

tree will uprooted

EU

When

BOQ
requiredd

Once a month

without prior
permission of
consultant.
7.10 Ensure that the
disposal of cleared
NESPAK-ABB-DMC

CEnv

CSCEnv

Site Inspections

DC

PMO-

Implementation

Daily

BOQ

123

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor
vegetation is not in a

Monitor
EU

manner that may affect

of

Waste Once a month

Disposal Plan

the blockage of natural


drainage
8

Waste Disposal This component


Management

8.1 Ensure that the

CEnv

CSCEnv

Compliance

BC/DC

BOQ

describes the waste

selected construction

PMO-

disposal plan that will

waste disposal site is

EU

be employed during the

demarked before

construction and

starting the work

restoration period. The

8.2 Ensure that

main types of waste to

Photographs of the

be disposed of will be:

area of the nominated

Fuel, oils, and

waste disposal site are

PMO-

When

chemicals (empty

collected to restore the

EU

Once a month

drums, contaminated

site at the completion

soil etc); Sewage;

of the construction

Campsite waste;

phase

Medical waste;

8.3 Ensure that all the

Demolition waste; and

waste generated from

PMO-

As

Packing waste, Excess

different locations must

EU

required

construction material.

be disposed off

CEnv

CSCEnv

When required

Plategraphs

BC/DC

BOQ

record

Once at the start of


work

CEnv

CSCEnv

System in Place

required

DC

BOQ
and

When Direct Cost

according to the waste


NESPAK-ABB-DMC

124

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Disposal Plan.
8.4 Ensure that all
trucks used for the

PMO-

transportation of waste

EU

System in Place

DC

BOQ

When required

construction material
must be covered and
watertight
8.5 It is a contractors

CEnv

CSCEnv

contractual obligation
to complete and follow

PMO-

the SFA if any private

EU

SFA

DC

SFA

Environmental

Once a week When

Audit

required

Compliance

DC

land damage due to


disposal of waste
generated from the
construction activities
8.6 Ensure that the

CEnv

CSCEnv

BOQ

movement of lifting

PMO-

Daily

machinery and vehicles

EU

When required

is limited to the work


area.
8.7 Ensure that soils
properly disposed of in
NESPAK-ABB-DMC

CEnv

CSCEnv
PMO-

Site Inspections

DC
As

BOQ
and

When
125

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

Description

No.

component

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor
a manner that does not

Monitor
EU

required

affect the natural


drainage
9

Land

The construction

9.1 Ensure that the

contamination

machinery includes

CSCEnv

Compliance

DC

maintenance of vehicle

PMO-

System in place

Daily

due to spill of cranes, trucks, loaders/

and other plant takes

EU

lubricants, fuel, dumber and batching

place only in

chemicals
other

and plants will be used


waste during the construction

material

CEnv

As

BOQ
and

When

required

designated areas
underlined with

period. There are

concrete slabs and a

chances of

system to catch surface

contaminating of the

runoff.

land due to release of

9.2 Ensure effluents

contaminated effluents,

from rig washing and

PMO-

accidental spill, leaks,

other potentially

EU

run of from the material

contaminated effluents

storage yard etc.

are released in mud pit


9.3 Ensure that fuels,

CEnv

CEnv

CSCEnv

CSCEnv

System in place

DC

BOQ

When required

System in Place

DC

oils, and other

PMO-

Once in week When

hazardous substances

EU

required

BOQ

are handled and stored


according to standard
NESPAK-ABB-DMC

126

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

safety practices such


as secondary
containment bunded
area. Fuel tanks should
be labeled accordingly
9.4 Ensure that fuels,

System in place

DC

oils, and chemical are

PMO-

Once

stored in areas lined by

EU

days

an impermeable base

BOQ
every 15-

Once a month

and containing dykes.


9.5 Ensure spills are

CEnv

CSCEnv

avoided during fuel and

PMO-

oil transfer operations.

EU

Appropriate

System in place

DC

BOQ

Daily
Arrangements in When required
place

arrangements, such as
minimize carrying
around site, if require
carry in proper
container or vehicles.
9.6 Keep spillage kit

NESPAK-ABB-DMC

CEnv

CSCEnv

System in place

DC

including shovels,

PMO-

Daily

plastic bags, absorbent

EU

Once a month

BOQ

127

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

materials and sand


bags are kept available
near fuel and oil
storage areas.
9.7 Ensure that
refueling of vehicles is

PMO-

planned on daily basis

EU

Work Planning

DC

BOQ

Daily

to minimize travel and


chances of spill
9.8 Ensure that

CEnv

CSCEnv

Compliance

DC

operating vehicles are

PMO-

Daily

checked for any fuel,

EU

When required

BOQ

oil, or battery fluid


leakage regularly
9.9 Ensure that

CEnv

CSCEnv

incidents of leak / spill

PMO-

record is maintained for

EU

each vehicle and

System in place

DC

BOQ

Daily
Maintain Record

When required

repairs affected
vehicles at the earliest
opportunity. Leaking
vehicles will not be
NESPAK-ABB-DMC

128

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

operated unless
repaired.
9.10 Soil contaminated
by minor spill (covering

PMO-

an area up to 0.1 m

EU

Compliance

DC

BOQ

When required

and 75 mm deep) will


be collected and
disposed at burn pit.
9.11 Ensure that soil

CEnv

CSCEnv

Compliance

DC

BOQ

contaminated by

PMO-

When

moderate spills or leaks

EU

Once a month

required

(up to 200 lifters) is


contained using
shovels, sand and soil.
The contaminated soil
will be removed from
the site and send it to
landfill site or burn pit
as require. Major spills
of volume exceeding
200liters will be
handled and controlled
NESPAK-ABB-DMC

129

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Implementation

destruction of

PMO-

of

involved for the

agricultural land is

EU

contractual

establishing of the

avoided by controlling

contractors facilities i.e.

the work activities and

batching plant, labour

vehicles movement by

camp, contractors

the trained banksman.

camp, material yard,

10.2 If it is absolutely

workshop etc.

unavoidable and

PMO-

Accidental damage to

private land or crop

EU

the crop or agricultural

damage from the

land may happen due

contractors activities

to mistake of

then the affecties will

contractors vehicle

be compensated and

driver or labour.

SFA completed by the

by a specialized
contractor as
suggested in Waste
Disposal Plan
10

Agricultural

It is envisage that no

land and crop agricultural land is


destruction.

10.1 Ensure that

DC

SFA

Contractors Daily
When required

obligation

CEnv

CSCEnv

Compliance SFA

DC

SFA

When required

contractor
11

Any discharge

No graveyard /

11.1 If during

or diversion of

archeological site are

construction such sites

NESPAK-ABB-DMC

CEnv

CSCEnv
PMO-

Site Inspections

DC

Direct Cost

Daily
130

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

water to a

found in the project

are found and

graveyard or

area so no such

discharge or diversion

archeological

situation may occur in

of water likely to

site.

the area.

damage the site then it

Monitor
EU

When required

is a contractors
obligation not to let it
happen.
11.2 Solve the problem

CEnv

CSCEnv

by collaboration with

PMO-

the communities as per

EU

Compliance SFA

DC

SFA

When required

SFA.
12

Electric &

Renovation of electric

Mechanical

and mechanical

Works.

installations of the

No action is required

existing barrage will be


carried out in situ so
there will be no impact
on the land resources
due to this activity.
13

Extended Canal

The construction

13.1. Ensure that the

Closure.

activities require canal


closure will be

NESPAK-ABB-DMC

CEnv

CSCEnv

Compliance

extended canal closure

PMO-

Work Plan

is avoided by planning

EU

of DC

BOQ

When required
Once a month
131

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

scheduled in such a

the work activities.

way that it must be

13.2 In case of

finished within normal

emergency avoid full

PMO-

canal closure period

closure of canal by

EU

and avoided extended

setting up cofferdam.

canal closure. If require

13.3 Cofferdams or

construct cofferdam or

CEnv

Compliance

DC

Direct Cost

When required

CSCEnv

Site Inspections

DC

temporary diverted

PMO-

Appointment

When requiredd

temporary structure to

routes of canals will be

EU

process

maintain routine

constructed by a

discharge into the all

competent staff or sub-

three canals

contractor to keep

CSCEnv

Compliance with DC, AC

BOQ

running the canals


during work activities, if
required.
B-

WATER
RESOURCES

14

Construction of Contamination:
Coffer Dams.

NESPAK-ABB-DMC

14.1 Ensure that soil

CEnv

Contamination of the

material used for the

method

During

river water from soil

construction/dismantlin

statement

construction/disma-

material during

g of the coffer dam

Site Inspections

ntling of the coffer

construction and

should not contaminate

BOQ

dam
132

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

removal of the coffer

the river water in terms

dams may

of suspended solids,

PMO-

consequently affecting

pH, oil based material

EU

the aquatic life,

to impact adversely on

particularly downstream

the aquatic life,

fisheries.

particularly

Once a month

downstream fisheries
by adopting good
engineering practice.
14.2 Carry out water

CEnv

CSCEnv

Laboratory

testing to ensure the

PMO-

based

setting up /dismantling

EU

site

DC

and

Direct Cost

on Monthly basis of on

Water site testing

and operation of the

testing of control

cofferdam do not

water

Quarterly basis of

adversely impacting of

laboratory

control water bodies

testing

base

(river, canals).
14.3 The Contractor

CEnv

CSCEnv

Compliance

BC/DC

will consult with the

PMO-

At the set up and

environmentalist from

EU

dismantling

the supervising

BOQ

Cofferdam

consultant to get the

NESPAK-ABB-DMC

133

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

approval of
construction/dismantlin
g process and location
of the cofferdam.
15

Batching Plant

Use of water:

15.1 Ensure that

Preparation of concrete

pumping of the ground

PMO-

Before establishing

at the batching plant

water will not affect the

EU

new tube well

would need water free

private or public tube

from sediments and

well in the near vicinity

high salt

15.2 Ensure that

concentrations,

contractor use the

PMO-

When required

particularly sulphates.

water free from

EU

Daily

Ground water in vicinity

sediments and high salt

of the river will meet

concentration for the

this requirement.

preparation of concrete

Therefore, the

at the batching plant.

contractor will install

15.3 Ensure that

tube well at the site to

wastewater or surface

meet this requirement.

runoff generating

Water

may

also

be during rain from the

CEnv

CEnv

CSCEnv

CSCEnv

Compliance

Compliance

Site Inspections

BC

DC

DC

BOQ

BOQ

BOQ

Daily
PMO-

When required

EU

needed for curing the batching plant should


concrete. For this the not enter in to the river
NESPAK-ABB-DMC

134

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Compliance with DC

contractor will use river without treatment.


water.

15.4 Ensure the

Disposal of waste

effluent meet the

PMO-

contractual

water: Waste water

NEQS level through

EU

obligation.

generated from the

impounding or other

Effluent

batching plant will be

type of treatment

(if generated)

loaded with cement and

before this is disposed

fine aggregate.

off in to the river.

Disposal of this water

15.5 Ensure that

into the river will affect

Engineer to oversee

PMO-

the water quality and

that the contract

EU

consequently affecting

clauses are complied

the aquatic life.

by the contractor.

CEnv

CSCEnv

BOQ

When required

testing Monthly basis

Compliance

DC

BOQ

Daily

The suitable site for the


batching

plant

is

indicated on figure 3.1.


16

Drinking Water Water Consumption:


Supply
Wastewater

& The contractor will


require arranging water

Generated from supply at the camp for


Contractors
Camp

NESPAK-ABB-DMC

consumptive as well as
& for the use at work

16.1 Ensure water

CEnv

CSCEnv

System in place

DC

source for domestic

PMO-

Water testing

Quarterly basis

use i.e. camp site

EU

Direct Cost

tab(s) or extraction well


will be monitored.
16.2 Ensure that

CEnv

CSCEnv

Compliance with DC

BOQ

135

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

NESPAK-ABB-DMC

Cost

Monitoring
Executor

Workshop

Parameters for Frequency

Monitor

shop for washing and

drinking water standard

PMO-

WHO

otherwise. This may be

should be maintained

EU

water standards

required from the

while supplying water

existing water resource

to the labour camp and

available with IPD for

also regular water

the use at the colony or

testing and monitoring

install a new tube well.

should be done.

The arrangement will

16.3 Ensure that local

CSCEnv

Compliance

be made in consultation

water supplier is

PMO-

with Consultant and

compensated for the

EU

PMO.

water if extracted from

Disposal of Waste

the existing water

water and other waste

supply system for the

effluents: The

community.

contractors camp will

16.4 the contractor will

generate wastewater

provide wastewater

from two sources, viz.,

treatment facilities

PMO-

residential area and

separately for both

EU

workshop. Both the

types of wastewater

wastewaters will have

(domestic wastewater

different types of

& construction

contaminants, i.e.

wastewater)

CEnv

CEnv

CSCEnv

drinking Quarterly testing

DC

Direct Cost

BOQ

When required

Compliance with DC
contractual

Daily

obligation

When required

BOQ

136

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Compliance

domestic wastewater

16.5 Ensure that

contains human excreta

sewage and other

PMO-

contractual

At the design stage

while the latter will have

waste effluents are

EU

obligation

of waste treatment

oil and grease.

handled properly to

Disposal of untreated

avoid contaminating

wastewater in to the

the control water

river may pollute river

bodies.

of BC, DC

BOQ

system
Effluents testing

Quarterly Basis

water and affect the


aquatic life.
17

C-

Electrical

& Renovation of electrical

17.1

Ensure

good CEnv

CSCEnv

Site

inspection DC

Mechanical

and mechanical

house keeping to avoid

PMO-

by the technical When

Work

installations of the

any accidental spill or

EU

staff

Daily

existing barrage will be

leakage into the river.

carried out in situ.

17.2 The contractor will

CSCEnv

Compliance

DC

Accidental spill or

provide suitable

PMO-

Site inspection

When

leakage of chemicals or

working platform e.g.

EU

oil based material could

scaffolding or mobile

contaminates the river

working tower, if

water and adversely

require to avoid

affect the aquatic life.

accidental spill.

AIR

CEnv

BOQ
requiredd

BOQ
required

Daily

QUALITY

NESPAK-ABB-DMC

137

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component
AND

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Monitoring

DC
Quarterly basis

NOISE

POLLUTION
18

Dust, smoke

A vast variety of

18.1 Ensure that all

and other

construction plant and

equipment, generator

PMO-

gaseous

potential

machinery including but

and vehicles used

EU

emission

pollutants from

not limited to

during the project are

from

Plants &

bulldozers, dumpers

properly tuned and

and

equipments

generators, Batching

maintained in good

equipment

Plant and vehicles will

working condition, in

be used during the

order to minimize the

construction phase.

exhaust emissions

These construction

18.2 If the selected

activities will generate

site for batching plant is

PMO-

Once at start of the

dust, smoke and other

closer than 500m from

EU

work

potential pollutants in

the build-up area than

the air.

ensure that zero

CEnv

CSCEnv

BOQ

rates Noise level When

generator required
other

key

System in place

BC

BOQ

emission plant is
installed.
18.3 Ensure that dust

CEnv

CSCEnv

emissions due to

NESPAK-ABB-DMC

Visible dust:

DC

Visible

Daily

vehicular traffic are

PMO-

observation

minimized by reducing

EU

size

of

of During

BOQ
peak

dust Construction
138

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

speed, vehicular traffic

clouds

Period.

minimized through

Surprise visit

good journey

Once a week

management and water


sprinkling on nonmettle road When
required.
18.4 Ensure that

CEnv

CSCEnv

periodic Ambient air

PMO-

quality is monitoring to

EU

Compliance

DC

Direct Cost

Quarterly basis

assess the
concentration of
Carbon Monoxide (
CO), Carbon Dioxide
(CO2), Nitrogen Dioxide
(NO2), Sulphur Dioxide
(SO2) and Particulate
Matter / (PM10) in the
atmosphere.
19

Smoke from

It is a Contractors

19.1 Contractors

burning of

responsibility to provide

waste material

clean source of fuel i.e.

NESPAK-ABB-DMC

CEnv

CSCEnv

Compliance

BC

obligations to provide

PMO-

contractual

Once at the start of

gas to the labour and

EU

obligations

work

BOQ

139

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

or burning of

sui gas such that the

not allow them to use

DC

firewood in the

site worker do not burn

wood as fuel.

Once a week

labour camp

wood as fuel. Burning

19.2 Ensure that all the

special waste (clinical

combustible non-

PMO-

Daily

waste, packing waste

hazardous waste

EU

When required

etc) may emit

material should be

poisoness or hazardous

burnt in the burn pit.

emission.

19.3 Ensure that the

CEnv

CEnv

CSCEnv

CSCEnv

quantity of waste burnt

PMO-

at one time is managed

EU

System in place

Maintain record

DC

DC

BOQ

BOQ

When required

so as to minimize
smoke emission
19.4 control fuel

CEnv

CSCEnv

consumption and

PMO-

minimize its waste or

EU

Maintain record

DC

BOQ

When required

leakage by regular
monitoring
20

Noise Pollution The use of old/outdated

20.1 Contractors

CEnv

CSCEnv

from

machinery may raise

obligation is to use

Construction

the noise level during

appropriate and fit for

PMO-

Activities

the construction phase.

purpose machinery

EU

The contractor will use

20.2 Ensure the

NESPAK-ABB-DMC

Compliance with DC
the contract

CEnv

CSCEnv

BOQ

Daily
When required

Compliance

DC

BOQ
140

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

the appropriate

minimum use of vehicle

machinery to carry out

horns particularly

PMO-

the work.

during embankments

EU

Daily
When required

strengthening work
along the pond area
20.3 Ensure the

CEnv

CSCEnv

Compliance

DC

implementation of the

PMO-

Daily

20km/h speed limit on

EU

When required

BOQ

site.
20.4 Ensure that

CEnv

CSCEnv

Noise Monitoring

DC

periodic noise

PMO-

Monthly basis

monitoring is

EU

When required

Direct Cost

undertaken to access
the noise pollution
during working hours.
D-

BIOLOGICAL
RESOURCES

21

Damage

to The pond area at the

21.1 When aligning the

CEnv

CSCEnv

Compliance

BC

biological

upstream of the

access road ensure

PMO-

Once at the time of

resources

barrage consists on

that the chosen route

EU

aligning of access

during

wetland and provide

require minimum

construction.

habitat of wildlife

vegetation loss and no

NESPAK-ABB-DMC

BOQ

road

141

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

including water fowl,

tree cutting

otters and soft-shell

21.2 Ensure wood and

turtles. Al-most all the

shrubs are not used as

work activities are

fuel during construction

PMO-

outside the Barrage

phase

EU

pond area.

21.3 Ensure that there

EIA/EMMP

CEnv

CSCEnv

is no open defecating
in the vicinity of camps

PMO-

activities contractor

or construction site.

EU

may require to clear

21.4 Ensure that no fire

vegetation from the

arms are carried out by

areas to be used for:

any of the employees

Daily
Once a month

Compliance with DC

BOQ

CSCEnv

Plan

When required

Compliance

DC

Site inspection

Daily

PMO-

BOQ

When required

EU

designated security

- Establishing

staff if require.

Construction Camp
- Erecting

CEnv

soil or labour, except

material

BOQ

Waste Disposal Daily

For other project

- Borrowing

Compliance with DC

21.5 Ensure that safe


Batching driving practices is

Plant

observed so that the

- Haulage

Tracks accidental killing of


Including Guide banks reptiles or small

CEnv

CSCEnv

Compliance with DC
EIA/EMMP

PMO-

Endorse

EU

limit

BOQ

Daily
speed When required

animals crossing the


Bela trimming / partial

NESPAK-ABB-DMC

road could be avoided


142

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Compliance with BC/DC

removal may adversely

21.6 Ensure that

impact the wildlife of

damage to the natural

PMO-

Environmental

Daily

the area due to noise

topography and

EU

protection Act

When required

and heavy machinery

landscape is kept

movements

minimum as possible
CSCEnv

Compliance with BC/DC

21.7 Ensure that no-

CEnv

hunting, trapping and

wildlife

or harassing wildlife.

protection

The wildlife policy will

& regulation

be strictly observed.

BOQ

BOQ

Daily
rules

PMO-

When required

EU
21.8 Ensure that

CEnv

CSCEnv

fishing in the river by

BOQ

Fishery roles & Daily

the project staff is

PMO-

prohibited

EU

21.9 Ensure that the

Compliance with DC

CEnv

CSCEnv

regulation

When required

Compliance with DC

general awareness of

Environmental

the crew is enhanced

and

regarding the wildlife,

Protection laws

through environmental

PMO-

training and notice

EU

Direct Cost

Daily

Wildlife
When required

boards.
NESPAK-ABB-DMC

143

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
21.10 Ensure that no

Executor

Monitor

CEnv

CSCEnv

project vehicle or staff

Site inspections
Fenced

DC

BOQ

the Daily

is allowed to access in

PMO-

contractors

the restricted areas due

EU

facilities

CSCEnv

Consultation with DC

shouting permit should

PMO-

Wildlife

not be given by the

EU

Department

CSCEnv

Compliance with DC

When required

to security and wildlife


habitat.
21.11 Ensure that

CEnv

BOQ

When required

Wildlife Department for


the shooting in Barrage
pond area during the
construction phase.
21.12 Ensure that site CEnv
workers are protected

mitigation

from harmful species of

PMO-

measures

animals.

EU

explain in EIA

CSCEnv

Include

21.15 Ensure that river

CEnv

ecology is monitored

Daily
as When required
a BC

BOQ

At the preparation

prior to the start of the

PMO-

ecologist in the of EIA

project, during

EU

environmental

DC

team

Quarterly basis

construction and post


NESPAK-ABB-DMC

specialize

BOQ

144

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

construction

21.16 Ensure that


excavating activities for

Site

inspection DC

and

the bela trimming

PMO-

purpose are carried out

EU

BOQ

work When required

planning

preferably during fish


non-breading season
(April to June). Monitor
turbidity on regular
basis during excavating
activities.
E-

SOCIOECONOMIC
AND
CULTURAL
ISSUES

22

Health & Safety

Population at Risk:

22.1 The contractor will

Impacts on Site

The main settlement

impart to the training to

PMO-

Work Force and

being located far from

the workers on safety

EU

Local

the project site,

matter.

NESPAK-ABB-DMC

CEnv

CSCEnv

As per contract

BC/DC

Direct Cost

When required

145

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component
Population

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Maintain Record

DC

Compliance

Daily

therefore it is unlikely to

22.2 Ensure Compliant

emplace any health &

Management Register

PMO-

safety hazards for the

and Accident Record

EU

local population due to

Register is maintained

the project activities.

at Camp site office.

However there will be

22.3 Ensure no

safety and health

machinery is left

hazards for the work

unattended at working

PMO-

force, particularly for

site

EU

CEnv

CSCEnv

BOQ

When required

Maintain

plants DC

log sheet

Daily

Site inspections

When required

the people working on

BOQ

Once a month

the repair/ renovation of

PMO-

gates and hoists and

EU

installing electric

22.4 Ensure PMO

equipments under a

representative visits

condition of full

monthly to gather

impoundment of the

complaints from

barrage pond.

Social/Environment

PMO-EU

CSCEnv
PMO

Maintain

DC

Complain

Daily

Management

Monthly basis

BOQ

Register

Complaints
Management Register
and provide feedback
to the community on
the status of the
NESPAK-ABB-DMC

146

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

previous complaints to
the community elders.
22.5 Ensure the use of
horns is prohibited ,
except when necessary

PMO-

Display

sign DC

boards

Daily

Compliance

When required

Compliance

DC

BOQ

EU
22.6 Ensure all entry CEnv
points

in

to

CSCEnv

the

BOQ

Provision of 24h Daily

construction area are to

PMO-

be staffed 24 hours a

EU

security

When required

Implementation

DC

day.
22.7 Ensure that safe

CEnv

CSCEnv

driving practices are

of

BOQ

traffic Daily

adopted, particularly

PMO-

management

while passing close to

EU

plan

CSCEnv

Contractors

DC

obligation

Daily

When required

settlements. This
includes a speed limit
of 40km/h within build
up (residential area)
and 20km/h on site.
23

Existing service

Social consultation will

23.1 Service facilities

facilities like

be done and all impacts

may be leagalized

NESPAK-ABB-DMC

CEnv

SFA

147

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

education,

influencing the

health,

communities will be

electricity,

defined and all these

Compliance

drinking water

factors will be added

SFA

supply and

and incorporated in the

23.2 Ensure that

public

contract document of

women of the area

At the preparation

gathering,

the contractor and SFA

consulted and their

of EIA

religious

of the communities

point of view

DC

through SFA.

CEnv

PMO-

defined

EU

contract

CSCEnv

congregations

incorporated regarding

PMO-

etc

the project activities

EU

in When required
data
of

Gender Analysis

BC,

BOQ

Quarterly basis

and community
development projects
23.3 Ensure that

CEnv

CSCEnv

religious congregations

Public

BC

BOQ

Consultation

At the preparation

must be observed

of EIA

carefully in order to

DC

avoid conflicts with

PMO-

tribal leaders and local

EU

When required

communities.
23.5 Contractors camp

NESPAK-ABB-DMC

CEnv

CSCEnv

Contractors

BC

BOQ

should include but not

PMO-

Contractual

At

limited to the following

EU

Obligation.

contract document

preparation

of

148

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

facilities
Mosque, Restaurant
Leisure centre, Health
& Safety centre and
Welfare facilities.
24

Tribal tension

Just one month before

24.1 Ensure that

local rivalries

the start of the

on running

Public

BC

polices with direct

consultation

Once at the start of

construction work social

bearing on project

Compliance

canals and use

frame work agreement

activities are culturally

SFA

of aquatic life

will be done between

sensitive, in order to

PMO-

the community

avoid conflicts with

EU

members and the

tribal leaders and local

resident engineer. In

communities and to

order to avoid conflicts

offset any impact on

with tribal leaders and

the local social

local communities

structure.

mutual consents will be

24.2 Ensure women

discussed in SFA.

CEnv

BOQ

of work
DC
When required

CSCEnv

Compliance

BC,

are informed through

PMO-

Gender Analysis

At the preparation

traditional means of

EU

BOQ

of EIA

communication of the

DC

presence of foreign

When required

men (migrated labour

NESPAK-ABB-DMC

149

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Compliance

individuals holding titles

PMO-

SFA & Land Act

to private property used

EU

etc) in their area


24.3 Ensure that

of BC

SFA

Once at the start of


the work

in the project (if any)

DC

are compensated in

When required

accordance with the


market rates and all
payment are recorded
24.4 Focus on water

CEnv

CSCEnv

Group meetings, BC/DC

related issues related

PMO-

Public

to project

EU

consultation

CSCEnv

Compliance with BC

BOQ

When required

implementation in
regular group meeting
with local community
25

Adverse effects

No important cultural 25.1 If any

on

and archaeological site archaeological,

PMO-

law indicated in At the completion of

archaeological

has been found

EU

chapter 2 of EIA

sites any grave

reported in the area,

or historical, cultural,

CEnv

EIA

religious or grave yard

DC

yards and burial

found during the project

Daily

sites

implementation then

When required

NESPAK-ABB-DMC

Direct Cost

150

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

the contractor will


ensure that no damage
to any such sites is
caused due to the
project activities.
However no such site
is indicated in the
project area currently.
25.2 Ensure that if any

Compliance

such sites are found

DC

BOQ

Daily

during the construction


stage informed to the
site office immediately.
26

Public Health & Due precautions shall

26.1 Ensure that a

Safety services be taken by the

proper Ambulance

PMO-

Daily

at construction contractor, and at his

(preferably a four-

EU

When required

site.

NESPAK-ABB-DMC

own cost, to ensure the

wheel drive vehicle) is

safety of his staff and

available on site on a

labour and, in

24-hour basis during

collaboration with and

construction phase.

to the requirement of

26.2 Ensuring that all

the local health

materials, gears and

CEnv

CEnv

CSCEnv

CSCEnv
PMO-

Compliance

Compliance

DC

BC/DC

BOQ

BOQ

Once at the start of


151

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Cost

Monitoring
Executor

Monitor

authority ,to ensure that

equipment (including

medical staff headed by

personal protective

DC

qualified medical

equipment) require

Daily

doctor, first add

carrying out the work

equipment and stores

safely are provided to

,sick bay and suitable

the staff.

ambulance service are

26.3 Ensure that

available at the campus

employees must have

, housing, and on the

access to running

PMO-

site at all times through

potable water at their

EU

out the period of the

place of work and also

contract and that

shaded area is

suitable arrangements

provided for rest during

are made for the

working shift.

prevention of epidemics

26.4 Ensure use of

and for all necessary

horns is prohibited ,

well fare and hygiene

except when necessary

EU

CEnv

CSCEnv

work

System in place

DC

BOQ

Daily

CEnv

CSCEnv

When required

Compliance

DC

BOQ

Daily
PMO-

requirements.

When required

EU.
26.5 Ensure that safe

CEnv

CSCEnv

driving practices are

NESPAK-ABB-DMC

Parameters for Frequency

Compliance

DC

Traffic

Daily
When required

adopted, particularly

PMO-

Management

while passing close to

EU

Plan

BOQ

152

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

Compliance with BC

settlements. This
includes a speed limit
of 40km/h within builtup
area and 20km/h max.
speed limit on site.
27

Employment

The project will open

27.1 Ensure maximum

opportunities

new jobs opportunities

(upto 100%) unskilled

PMO-

labour

which the local

and possible semi

EU

contract

employment

population could avail.

skilled and skilled jobs

documents

DC

IPD may request the

are to be provided to

contractor to hire labour

people from local

from the local

communities, provided

community

the suitable competent

It is believed that

person with required

substantial amount of

qualifications/experienc

unskilled work force for

e is available.

construction could be

27.2

Ensure

recruited from the local

staff

interaction

population near the

local

project site. Therefore

minimized

NESPAK-ABB-DMC

in At

the

stage

of

When required

project CEnv

community

laws

BOQ

with
is

CSCEnv

Land

PMO-

for labour camp During

EU

should
least

selection BC
be

BOQ
preparation

at of EIA

500m

Barrage construction

away,

will have a positive

barrier between When required

physical DC

153

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Cost

Monitoring
Executor

NESPAK-ABB-DMC

Parameters for Frequency

Monitor

impact on the socio-

work area and

economic fabric of the

public places

local society. The

27.3 Ensure that inter

Contractor will evaluate

CSCEnv

Public

BC

tribal balance is

PMO-

Consultation

At

the available manpower

maintained when giving

EU

taking into

employment to the

DC

consideration the level

local population.

When required

(skilled or unskilled)

Preference to be given

and numbers of the

to the people directly

workers who could be

affected by the project.

inducted in the labour/

27.4

work force of the

Ensure

CEnv

that CEnv

Public

BC

guidelines are prepared

PMO-

Consultation

at

Project. The Contractor

and

EU

will give preference to

sensitize

employing suitable

labour to local norms

personnel living close

and customs in order to

to the Project area on

minimize

the conditions which

tensions

will be in accordance

27.5 Ensure that field CEnv

CSCEnv

Compliance with BC

with the National Law

crew

PMO-

PHS Act

ensuring that the

screened

working conditions for

employed

is

to

the

stage

of

employment

CSCEnv

implemented

BOQ

BOQ
the

stage

of

employment

non-local

DC
Quarterly

cultural

medically
before

EU

At

BOQ
the

stage

of

employment

154

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

the labour / work force


at the site take due
care of the health,
safety and ambient
conditions conducive to
appropriate
working/living
standards applicable to
a work site.
28

Communicable

The labour camp, their

28.1 Ensure that

Diseases.

interaction with truck

periodic awareness

drivers and alike

campaign for HIV/AIDS

PMO-

&

personnel are potential

are undertaken for the

EU

awareness

places for spread of

project staff

Communicable

28.2 Ensure that a risk

Diseases if the

NESPAK-ABB-DMC

Compliance with DC

Direct Cost

PHS Acts, health Quarterly


safety When required

courses
CEnv

CSCEnv

Medical

testing BC

assessment of the

PMO-

of site worker

incidence exists.

spread of HIV/AIDS is

EU

Almost 100% of the

undertaken in the

people of project area

project area on the

and the potential labour

basis of data from the

are not aware of the

Punjab HIV/AIDS

source, mode of

program.

BOQ

At the employment
DC
Quarterly basis

155

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

CEnv

CSCEnv

communication or

28.3 The medical staff

consequences of

ensure periodical

PMO-

Hepatitis, HIV/AIDS.

checks of the cooking

EU.

Although their religious

staff and cooking

and cultural value

practice particularly for

system, to a large

symptoms of hepatitis

extent excludes the

A.

Medical Testing

DC

BOQ

When required

outbreak or rapid
communication of
HIV/AIDS, yet its
occurrence in such a
situation cannot be
precluded. It is
necessary that along
with other
communicable
diseases like Cholera,
Typhoid and
Tuberculosis,
awareness and
preventive campaigns
are run from time to

NESPAK-ABB-DMC

156

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

time in the labour


camps and the field
offices of the project on
HIV/AIDS.
29

Restoration/reh

It will be the

29.1 Ensure that all CEnv

CSCEnv

Compliance

After completion of BOQ

abilitation

requirement of the

barrow

excavating work

contract that restoration

remediate

of borrow areas will be

contract requirements

done at completion of

29.2 Camp site is

the work. All borrow

restored and changed

PMO-

areas will be levelled as

to tourist resort if

EU

far as possible, graded

possible and agreed by

and brought in a level

the I&P Department

form resembling to

29.3 All extra products / CEnv

CSCEnv

Compliance with After completion of BOQ

natural condition prior

material, solid and

PMO-

Waste Disposal- work

extraction / borrowing.

liquid will be disposed

EU

Plan

Campsite and

off in accordance with

temporary facilities will

the requirement of the

be restored in

EIA / EPA and contract

accordance with

document.

contractual obligations

29.4 All fencing and

CSCEnv

Compliance with After completion of

and requirements. All

access gates relevant

PMO-

restoration

NESPAK-ABB-DMC

sites

are

PMO-

Plategraph

as

per

EU

record

CSCEnv

Compliance

CEnv

CEnv

After completion of BOQ


work

work
157

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

the community roads

to construction

and bridge roads which

activities will be

were under contractor

removed

use will be restored to

29.5 All pits (including

its original shape or

burn pits, sumps and

PMO-

better.

depression) will be

EU

CEnv

EU

guidelines

CSCEnv

Compliance

At

completion

of BOQ

work

backfilled unless
agreed with the
CSCEnv
29.6 The portion of the

CEnv

CSCEnv

access track likely to

PMO-

be of no use for other

EU

Compliance

After completion of BOQ


work

activities will be
restored by removing
culverts and gravel
topping
29.7 While abandoning

CEnv

CSCEnv

Compliance with After completion of BOQ

sumps the extra cap of

PMO-

restoration

soil will be placed over

EU

guidelines

CSCEnv

Compliance with After completion of SFA

work

them to allow for


compaction.
29.8 Ensure that no
NESPAK-ABB-DMC

CEnv

158

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr.

Project

No.

component

Description

Measures / Actions

Responsibility

Parameters for Frequency

Cost

Monitoring
Executor

Monitor

potential conflicts

PMO-

should emerged with

EU

SFA

work

landowners during the


restoration of the
borrow areas.
BC -

Before Construction; DC - During costruction;

PMO-EU -

CEnv -

Project Management Office- Environmental Unit;

NESPAK-ABB-DMC

Contractors Environmentalist

CSCEnv

Construction Supervision Consultants Environmentalis

159

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

7.5

INSTITUTIONAL ARRANGEMENT

7.5.1
Management Responsibilities
Overall responsibility for environmental management will rest on Head PMO of the Irrigation
and Power Department, Government of the Punjab.
i.

The Executing Agency

PMO of Irrigation and Power Department


(IPD)

ii.

Supervising and Monitoring :

Environmental Unit of PMO.

Agency
iii.

General Assistance to all :

Head PMO/The Project Director, I & P

above

Department will facilitate communications,

agencies

in

their

respective tasks

logistics and data collection as and when


required.

iv.

Logistic Support

Head PMO/The Project Director, I & P


Department shall provide the logistic support
and

shall

be

the

focal

point

for

the

construction activity.
(i)

Project Management Office (PMO)

The overall responsibility for the implementation of Environmental Management/Monitoring


Plan rests with the Project Management Office (PMO) along with the assistance of
Environmental Unit (EU) of PMO. The EU consists of Director Environment & Sociology,
Deputy Director Environment and Deputy Director Sociology.
PMO will assume overall responsibility for ensuring:

That while executing the contract and undertaking the construction all environmental
norms, regulations and requirements promulgated by Pakistan Environmental
Protection Council (PEPC), Pakistan Environmental Protection Agency (PEPA),
Environmental Protection Agency (EPA) Punjab and environmental safeguard policies
of Asian Development Bank , with respect to the work site and adjacent areas are
fully respected and implemented.

Overall responsibility for implementation of EMP.

PMO will ensure that Contractor and Construction Supervision Consultants appoint a
dedicated environmental officer and allied staff. PMO will also ensure that all

NESPAK-ABB-DMC

160

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

environmental personnel are authorized to implement the socio- environmental


policies and requirements of the EMMP.

PMO will also coordinate with relevant government departments and stakeholders on
concerned socio-environmental issues.

PMO will inspect and monitor residual impacts of the rehabilitation work and observe
documentation of the impacts during the construction phase.

PMO will also inspect the significance of impact in case of unanticipated change in
the project.

Construction Supervision Consultants will assist and advise PMO in implementation of EMP.
(ii)

Environment Unit (EU) of PMO


-

The Environmental Unit (EU) within PMO will monitor Project performance.

The EU will function in coordination with the Construction Supervision Consultants


and will receive reports from them on behalf of PMO.

EU will prepare and submit periodical Progress and Monitoring Reports to all
stakeholders as per their schedules. In this task they will seek assistance/ guidance
from Construction Supervision Consultants as and when required.

(iii)

Head PMO/The Project Director

The Project Director shall provide or arrange the logistics including communication, transport
and accommodation to all visiting persons/teams experts from any of the above monitoring
units and shall coordinate with the contractor(s) to facilitate the visits/inspections. For all
Monitoring and Evaluation activities in the field the Engineers Representative shall act as a
focal point.
(iv)

Contractor

The contractor will be responsible for the implementation of the project EMP. The contractor
will ensure that EMP for the project is implemented fully and must be integrated into the
Project implementation and make integral part of the contract document. For any default
damages so caused will be remediated by the contractor at his own cost and expenses. In
case the contractor fails to rectify the damage the employer will do the need full at risk and
cost of the contractor. The amount will be determined by the Construction Supervision
Consultants which will be adjusted from amount due to the contractor. The contractor will
also be responsible for communicating with and training of his staff in environmental aspects
and implementation of the EMP. The contractor will develop and get approved Health, Safety
NESPAK-ABB-DMC

161

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

& Environment (HSE) Plan from Construction Supervision Consultants before the
commencement of the Physical works on site.
(v)

Construction Supervision Consultants

The construction supervision consultants will be responsible to ensure quality of work and
fulfilment of contractual obligations. Environmental Specialist of the construction supervision
consultants will ensure that all the environmental and social provisions comply with the
applicable standards. He / She will confirm that the day-to-day construction activities are
carried out in environment friendly manner and organize periodic environmental training
programmes and workshops for the consultants and contractors staff.
Project Organizational Structure
The organizational structure for the environment management / monitoring implementation is
shown below. The role of the organization are described in exhibit 1.

Secretary to Government of Punjab


Irrigation and Power Department

Head
Project Management Office

Environment
Unit

Director Social
/ Environment

Deputy Director
Environment

Construction
Supervision
Consultants

Environmental
Specialist &
Sociologist

Contractor

Environmental
officer / Team

Deputy Director
Sociology

Organization Chart for Environment Management / Monitoring Implementation

Exhibit 1 - Responsibilities of PMO Environmental Unit, Contractors, Monitoring and


Environmental Specialist of the Construction Supervision Consultants
NESPAK-ABB-DMC

162

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Organization

Designation

Responsibilities

Operating Documents

Project
Management
Office (PMO)

Director Socio
/ Environment

NESPAK-ABB-DMC

Overall in charge of the


environmental unit.
Oversee the works of
environmental and social
aspects related to the
project(s)
for
Punjab
barrages rehabilitation.
Provide
environmental
and social guidance to
environmental staff in
project preparation and
approval
/
sanctions,
constructions,
implementation, to attain
optimum efficiency and
success
in
the
management
and
operation of the project.
Assist Project Director in
active inter-action with
donors,
consultant,
contractors and other
stake holders on monthly
review, progress of the
project or any other
situation
required
immediate action.
Time management for
successful completion of
the
project
and
its
scheduling according to
approved budget.

Contract with I&P


Department
Relevant Asian Bank
documents
on
environmental
and
other laws discussed
in EIA of Sulemanki
Barrage
EIA for the Sulemanki
Barrage
The present EMMP of
Sulemanki Barrage
Social
Framework
Agreement (SFA).
Consultants
Environmental
Reports
Comply
with
National, International
and Punjab Public
Health and Safety
(PHS) Acts

Preparation
of
all
necessary
reports
required to be submitted
to Govt. or donor agency.
Ensure compliance and
implementation of rules
and regulations issued by

163

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Organization

Designation

Responsibilities
the

Operating Documents

Federal

Agencies

especially regarding social


and
environmental
aspects.
Project
planning,
monitoring and evaluation
specifically
in
environmentally & social
related matters in the
project.
Socio,

Project

Deputy

Management

Director

environment

Office (PMO)

Environment

assignment and field as

Relevant Asian Bank

well.

documents

Full fill the obligation as

environmental

laid out in his/her contract

other laws discussed

with I&P department.

in EIA. of Sulemanki

Ensures

Barrage

Assist

Director
in

office

environmental

protection
project

the

during

implementation
to

according
Environmental

laws,
and

policies guidelines
technical standards

Liaison
and

consultants

environmental team

Conduct

site

with

I&P

Department
on
and

EIA for the Sulemanki


Barrage
The present EMMP of
Sulemanki Barrage
Social

Framework

Agreement (SFA).

contractor

with

Contract

Consultants
Environmental
Reports

visits

to

Comply

with

ensure compliance with

National, International

EIA and EMMP

and

Coordinate

with

stakeholders,

including

Punjab

Health

and

Public
Safety

(PHS) Acts

general community, EPA,


WWF,
contractor,

Asian

Bank,

consultants

and others

NESPAK-ABB-DMC

Support DD Sociology in

164

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Organization

Designation

Responsibilities
fullfillment

Operating Documents
of

his/her

responsibilities

Deputy

Management

Director

environment

Office

Sociologist

assignment and field as

Relevant Asian Bank

well.

documents on social

Assist

Socio,

Project

Director
in

Carried

office

out

the

aspects

other

spokesperson

of

of

the

Sulemanki

Barrage.

Deals

social

with

Socio-economic survy

mobilization and emerging

as a baseline for EIA

socio-economic issues.

of

Coordinate

Barrage

WWF,

with
including

consultants

and others.
Review

Sulemanki

The present EMMP of


Sulemanki Barrage

Bank,

Asian

contractor,

PHS Acts
Social

Framework

Agreement (SFA).
socio-

all

Consultants

environmental reports and

Environmental

ensure implementation of

Reports

corrective

measures,

if

any

and

laws discussed in EIA

general community, EPA,

I&P

responsibilities of official

stakeholders,

with

Department

PMO.

Contract

Documentation
received

Conduct

site

visits

to

Socio-

from

field

ensure compliance with

Comply

EIA and EMMP

Acts

Support DD Environment

Social

in

Agreement (SFA

fulfilment

of

the

his/her

with

HSE

Framework

responsibilities
Construction

Environmental

Supervision

Specialist

Consultant

Ensure the implementation


of

the

mitigation

Contract with PMO

EIA

measures suggested in
Monitor
activities

construction
as

per

the

for

Sulemanki

Barrage

the EMMP

NESPAK-ABB-DMC

The

EMMP

of

Sulemanki Barrage

Comply

with HSE

165

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Organization

Designation

Responsibilities

Operating Documents

compliance

monitoring

Plan

program
Monitor the impacts of the
project activities (effects
monitoring,

discussed

later in this document)


Liaison with environmental
officers and HSE officer

Manage and implement


environmental

mitigation

measures, as well as I&P


Department
contractors

and
health

and

safety Policies
Manage operation of the
contractors
environmental
management staff

Contractor

Environmental

Train the staff as required

Manage

and

officer / HSE

environmental

officer

measures

implement
mitigation

with

supervision

contractors

consultants

Cause and effects, and

for

Sulemanki

EMMP of Sulemanki
Comply

with PHS

Acts

Train the staff as required


Implementation of EMMP

EIA

Barrage

Manage operation of the


field environmental staff

I&P

Barrage

consultant

environmental specialist.

with

Department

health and safety Policies


Liaison

Contract

Consultants
environmental reports.

Social

Framework

Agreement (SFA)

compliance monitoring.

7.6

CHANGE MANAGEMENT

An environmental assessment of the proposed project has been made during the
preparation of EIA. However it is possible that change in project design may be required
NESPAK-ABB-DMC

166

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

when the project is implemented. This section describes the mechanism to handle Changes
that might affect the project environmental impact. The changes in the project design may
be:
First Order Change is one that leads to a significant departure from the project described in
the EIA such as change in location, project design. The change management statement
(CMS) will be submitted to EPA for approval with a copy to the Asian Bank.
Second Order Change is one that is not significantly different from those described in the
EIA such as;

Increase in project personnel by 25%

Changes in the documentation and communication, stakeholders consultation


program

The change management statement (CMS) will be submitted to EPA for information with a
copy to the Asian Bank.
Third Order Change is one that is of little consequence to the EIA findings, such as;

Re-aligning a particular section of road to avoid cutting tree

The assessment report will be compiled and recorded.


7.7

COMMUNICATION AND DOCUMENTATION

Communication and documentation is an essential feature of EMMP. The key features of


such mechanism are:
7.7.1
Data Recording and Maintenance
All forms to be used for recording information during the environmental monitoring will follow
a standard format which will correspond to the data base in to which all the gathered
information will be placed. Check boxes will be used as much as possible to facilitate data
entry. Tracking system will be developed for each form.
7.7.2
Storage of Information
The database may include the following information
Training programs;
Staff deployment;
Non-compliance;
Corrective actions
List of environmental data and
List of environmental data to be maintained:
NESPAK-ABB-DMC

167

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Soil and land pollution


Disposal of excavated silt and earth
Disposal of waste

Water resource

Quality
Quantity
Fuel oil and chemical spills

Vegetation record

Record of wildlife

Noise pollution

Air and dust pollution

Socio-economic data

7.7.3
Meetings
The following environmental meetings during the project will take place
Primary meeting for setting out the requisite end frame sounding for the regular
meetings.
Scheduled meetings between Contractor and Supervising Consultant.
Progress review meeting among EU of PMO, Environmental Specialist and
Environment Officer.
The purpose of the meeting will be to discuss the conduct of the operation, non
compliances noted by the consultants environmental team and measures for their remedy.
The meeting will be recorded in the form of a daily/monthly environmental report.
7.7.4
Reports
The Environmental Specialist of the Supervision Consultant shall produce periodical reports
as well as inspection notes based upon the visits to the Project site. This information shall
make a basis for EU for their further reporting or visiting the site. All reports shall be location
and activity specific. The reports shall especially identify areas of contractors noncompliance with the EMP and provide guiding remarks on actions to be taken. The
significance of the non-compliance shall also be noted. Copies of these reports shall be sent
to the Resident Engineer (RE) who shall forward them to the Team Leader, Head PMO,
Irrigation & Power Department and the Contractor for their action(s).
The RE will include in his routine reports a summary status of activities relating to the EMP.
Supplemental reports on issues should also be prepared as and when required.

NESPAK-ABB-DMC

168

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The consultant s environmental team will produce daily ,monthly, and annually reports, as
well as a final report of the project based on the information collected. The list of distribution
reports is given in Exhibit-2.
Exhibit-2 Periodic Reports
Report

Prepared by

Reviewed by

Distribution

Daily

Contractors

Reviewed

by Resident

HSE officers

contractor

Engineer

environmental
officer

and

the

Consultants
Environmental
Specialists
Monthly

Environmental

Reviewed by EU of Resident

team of the

PMO.

Engineer

Construction

PMO

Supervision

I&P Department

Consultants

Asian Bank
EPA

Annually

Environmental

Reviewed by EU of Resident

team of the

PMO.

Engineer

Construction

PMO

Supervision

I&P

Consultants

Department
EPA
Asian Bank

Effects Monitoring

Environmental

Reviewed by & EU Resident

team of the

of PMO and Punjab Engineer

Construction

EPA

PMO

Supervision

I&P

Consultants

Department
EPA
Asian Bank

NESPAK-ABB-DMC

169

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Report

Prepared by

Reviewed by

Distribution

Change

Environmental

Reviewed by EU of Resident

Management

team of the

PMO.

Engineer

Construction

EPA

PMO

Supervision

I&P

Consultants

Department
EPD
World Bank

Final

Environmental

Reviewed by EU of Resident

team of the

PMO.

Engineer

Construction

PMO

Supervision

I&P

Consultants

Department
EPA
Asian Bank

7.7.5
Plategraphic Record of the Project Area
This will include:
Identifying key locations for taking Plategraphs
Using digital camera to Plategraph of the project area before the construction start and
Recording the following information for each shot on a form
Shot number
Name of Plategraph
Date
Time
Featured Plategraph
Other observations
Repeating the above after completion of all activities for selected location
7.7.6
Social Complaints Register
The consultants environmental team will maintain a social complaint register at camp site
office to document all complaints received from the local communities. The register will also
record the measures taken to mitigate these concerns. The final report will be communicated
to Environmental section of PMO. The details of Grievance Redress Mechanism are
provided in the RAP. The Project Monitoring team shall carry out the monitoring of the
implementation of social and environmental mitigation measures as per ADB Safegaurd
Policy Statement.

NESPAK-ABB-DMC

170

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

7.7.7
Record Register
The environmental specialist of the construction supervision consultants will be responsible
to maintain and update all environment related data, record and documents. The results
from environment monitoring and sampling program should be fully documented and
recorded. The results will be available for inspection by the regulator, authorities and Asain
Bank on site. The record should provide the following quality assured monitoring and
sampling information.

Determinants monitored and sampled

Specified details of measurements/samples to support analytical and QA


requirements e.g. dates, times, location, other relevant parameters

Results of measurements/sample analysis, with error limited.

Interpretation and review of results against specified trigger level.

This will be maintained at a site to document any change in the project design as well. These
changes will be handled through the change management mechanism if any. The final report
will be communicated to EU. Environmental issues Tracking Report form will be completed
and maintained by the Contractor.
7.8

WASTE DISPOSAL PLAN

This component describes the waste disposal plan that will be employed during the
construction and restoration period. The main types of waste to be disposed off include
Waste generated during construction
Fuel, oils, and chemicals;
Sewage;
Campsite waste;
Medical waste;
Demolition waste;
Packing waste and
Excess construction material.
Domestic waste and construction waste will be the main type of waste generated from
Labour Camp and construction activities. Domestic waste contains high percentage of
readily degradable hydrocarbon which gives bad smell on decomposition, especially in hot
and humid environment. Construction waste classified as inert waste which could be a
problematic to dispose off. It is recommended to collect the domestic waste and construction
waste separately.

NESPAK-ABB-DMC

171

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

7.8.1

Domestic Waste
All the waste generated at Labour Camp should be collected and temporarily stored
at the designated bonded area within the labour camp.

The area should be prepared, maintained and visually inspected and recorded on
regular basis by the Environment Officer of the contractor.

The waste storage area should be fenced to stop animals direct contact with the
waste. The site must be decontaminated to keep the building free from foul smells,
spreading of diseases and healthy working environment on regular basis.

It is a responsibility of Contractor to arrange the waste collection from the Labour


Camp with local authority or waste disposed cooperation on regular basis.

Waste Chute should be provided within the Labour Camp. Chute will enable the
collection of thrown solid in the covered storage site.

Bags should be provided to the occupants and resident of the labour camp for
collecting their waste.

Implement resource conservation and recover recyclable waste e.g. paper, steel
cane, glass bottles etc from the collected waste and divert the filtered waste to the
area landfill site.

A burning pit should be built on site to burn the combustible waste on site. The
suggested dimension of the pit in feet is 15 x 12 x 4 (length x width x height)

7.8.2

Construction Waste
Construction waste could be reused as a fill material or construction material.
However the detail testing should be undertaken to confirm the suitability of the
waste, if is used as a construction material. .

If the construction waste disposed of on site in the form of landfill then once the hole
filled with the construction waste the top of the fill should be capped with clayed
material and compacted to minimize water infiltration.

The waste disposal system is summarized in Exhibit-3 below


Exhibit-3 Waste Disposal Plan
Types
of Description
waste
Construction
Crushed
waste
Concrete &
Excavated soil

NESPAK-ABB-DMC

Construction
phase
Road Bridge
and Barrage
structure
repair work

Disposal methods
Dumping and levelling of waste only
on
site
agreed
with
the
Environmental Specialist and EU as
indicated on figure 1.3. Waste will be
properly disposed of in a manner that
does not disturb the natural drainage.
The dumped material will be

172

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Types
waste

of Description

Construction
phase

Disposal methods
strengthened by stone pitching.

fuel, oils, and Contaminated


soil or water
chemicals
spills
contaminated
soil
or
wastewater

NESPAK-ABB-DMC

All phases

soil contaminated by minor spills /


leakages (defined as leaks from the
vehicles, machinery, equipment, or
storage containers such that the
areas and depth of soil contaminated
is less than 1sqft and 3 inches
respectively) will be scraped and sent
to the burn pit where it will be burned
along with other combustible wastes.
Contaminated water will be dispersed
with pressure.
Moderate spills defined as spills of
volume less than or equal to 200
litres will be contained and controlled
using shovels, sand, and native soil.
these materials and equipment will
be made available at campsite and
construction site during operation.
The contaminated soil will be
excavated and stored in a bonded
area lined with impermeable base.
Depending on the volume of the
contaminated soil, the disposal may
involve of sending to burn pit or by
specialized treatment such as
bioremediation or
solidification/stabilization (s/s)
Major spills of volume exceeding 200
litres will require the initiation of PMO
emergency response procedures.
These spills will be handled and
controlled
according
to
the
specialized measures and special
treatment as suggested by the spills
removal experts. The contaminated
water should be collected in separate
container and sent them to the
suitable treatment site after the
mutual agreement with environment
consultant and PMO.

173

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Types
waste

of Description

Construction
phase

Construction
Sewage and Wastewater
from
kitchen /Operation
gray
and washing Phase
wastewater
areas, sewage

Campsite
waste

Medical waste

Animal, fruit or Construction


/Operation
vegetable
Phase
residue,
domestic
garbage

Syringes, glass
bottles, soiled
bandages,
expired drugs,
dressing
Used
oil,
ferrous
/non
Workshop
waste,
and ferrous
materials,
fluid waste
batteries,
oil
etc
Demolition
Concrete,
Waste
bricks,
other
building
materials
Packing
waste

NESPAK-ABB-DMC

Construction
/Operation
Phase

Disposal methods

Sewage to be disposed of using


septic tanks and soak pits, solid
residue to be disposed of in nearby
sewage
treatment
facilities.
Wastewater
from
kitchen
and
washing areas to be disposed of in
soak pits
Colour coded waste collection drums
will be placed at the appropriate
locations to segregate different types
of waste. Recyclable waste to be
given away for recycling; non
recyclable, combustible waste to be
burned at burn pit and non
combustible waste to be buried in
designated landfill as agreed with EU
and Environmental Specialist. Green
waste will be disposed off at the
composting
unit
having
same
dimension as burning pit.
To be incinerated at nearby hospital
incinerator, if any, or an equivalent
facility

Construction / The collection of waste should be


arranged with specialized certified
Operation
contractor.
Phase

Construction / Reusable material to be given away


for use. Remaining waste to be
Operation
buried in designated landfill or
Phase
designated
construction
waste
disposal site.
Paper, plastic, Construction / Combustible waste to be burned in
burn pit, recyclable waste to be
Operation
textiles,
handed over to recycling contractorsPhase
cardboard,
rubber, wood,
glass,
tin,
174

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Types
waste

of Description

Excess
construction
material

7.9

Construction
phase

Disposal methods

cans,
aluminum cans
Construction / To be sold back or given to the
Sand,
supplier or other users
Operation
aggregate,
cement, bricks, Phase
reinforcement
steel
bars,
paints
and
other
construction
materials

ILLUSTRATED TRAFFIC MANAGEMENT

Mechanical works at the barrage might require partial or full closure of the road bridge during
construction. Therefore traffic management would be required during such time periods
spanning long hours in a day. It is a contractors contractual obligation to prepare a Traffic
Management Plan, get its approval from traffic police, XEn Irrigation and HSE Officer and
implement on site. The plan should be available for public in local library and published in
news paper. The suggestions made in this section should be incorporated by the contractor
in preparation of the Traffic Management Plan.
The purpose of traffic management plan is to cope with traffic distribution that call for coordinate actions from several services responsible for road/traffic management on a given
road or network.
Barrage Structure Repair Work
There is a single carriage way bridge on top of the main weir at Sulemanki Barrage for public
transport. If part of the road needs to be used to undertake the barrage structural repair work
then the working area should be clearly marked with separating fence. No unauthorized
person should be allowed to enter the working area. Following measures should be taken
during the construction of the bridge

The adjacent land on both side of the road at the suggested location of the road
bridge belongs to IPD, therefore no private land acquisition require

Contractor should provide a temporary route during the bridge construction if require.

The temporary route should be adequate for the existing traffic plus the site traffic and
designed and build by a specialized contractor.

NESPAK-ABB-DMC

175

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

The rural roads leading to or passing near the construction site could be used to
convey men and materials to the construction sites.

It is a Contractors contractual obligation to use the roads and paths carefully and in
case of any damage, repair the damaged roads or paths.

Closing one Lane: When closing down the one lane of the road then the traffic light system
should be set up and allow only one side traffic at a time. Sign posts about the new traffic
light and/or proposed new road layout should be placed at least one km from both sides of
the Barrage. Sign boards about the expected delay in traffic and queue build up should be
placed in Havali Lakha and Michna Abad (about 45 km from Sulemanki Barrage).

Complete Closure of the Road: There is an active river creek at downstream of the
barrage and road bridge will be required for alternative route. A boat bridge could be
assembled for temporary alternative route for the traffic during the refurbishment of the
existing bridge, the suggested location of the Boat Bridge and access roads (currently are
kacha path need to be strengthened for the main traffic) are indicated in figure 7.1.
If the road need to be closed completely without provision of alternative route then it is
suggested that the closure should not be more than continuous 4 hours. Local traffic police
should be informed at-least a week before the closure required. Traffic sign board regarding
the closure time and suggestion for alternative routes should be placed at the exit of main
city i.e. Pakpattan, Depalpour, and Bahawalnager towards the Sulemanki Barrage. Where
possible the closure should be arranged outside the off peak times (consider peak time from
6am to 10am and 3pm to 7pm). The traffic should be stopped before it enters the build up
area near the barrage i.e. settlements near the barrage to avoid the distraction of the local
community and damage the infrastructure from the accumulated traffic. The following traffic
survey conducted over a week provides the estimate of the daily average traffic flow can be
used for the preparation of the traffic management plan by the contractor.
Table 7.1:

Traffic Survey Conducted at Sulemanki Barrage


Car/Jeep/

Hiace

Mini Bus/

cycle

Taxi/Pajero

Wagon

Coaster

2009

1176

589

155

117

50

38

460

2014*

1405

655

161

122

52

47

487

2020

1635

722

168

126

54

56

515

*First Year after Proejct Completion


NESPAK-ABB-DMC

Bus

Loader

Truck/

Motor-

Pickups

Trailer/
tractor

ADT : Average Daily Taffice


176

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Strengthening Embankments Works


The existing embankments can be used for transporting soil, material and plant and
equipment. However the approximate width of the bunds is 20 ft which may not cope with
the traffic on both directions (depending upon the type of vehicles use in earth moving). The
crossing/waiting bays should be provided, if require along the embankments to avoid any
accidental slip of vehicles. The soft barricading fence should be provided at the edges of the
path/roads etc.
7.10

OUTLINE OF EMERGENCY RESPONSE AND CONTINGENCY PLAN

If any of the results of the environmental monitoring/sampling exceed specified trigger levels
for the determinant, the appropriate actions will be undertaken to prevent hazard to human
life, property and the environment outside the operating site bounding control and minimize
any immediate risks of pollution of the environments, ensure the immediate initiation of
necessary investigation and management actions to identify, mitigate and remediate the
cause of the accident. Initiate training and periodic testing/checking when necessary.
The probabilities of accident such as oil spills, accidental habitat destruction, water or air
pollution, breach in cofferdam and hit with unexpected high flow are very low. However, such
accidents can occur and overall environmental emergency response method may be used:

Obtain an early warning of the emergency conditions so as to avoid adverse impacts


on the environment

Safeguard personnel to prevent injuries or loss of life

Minimize the impact of such event on the environment and facilities by mitigating the
potential for escalation and containing of the hazards

Site in charge should have permanent mode of contact (e.g. mobile phone or walki
talki) with the HSE officer.

Contact name and number of HSE officer should be available in site office and
displayed on site office notice board.

It is a responsibility of the contractor to provide at least one First Aider during working hours.
The First Aid provider will perform the following duties.
i.

Keeping all necessary first aid medicines and bandages in the first aid box at every
time.

ii. Replace the medicines before their expiry dates to avoid any health hazard to the
people.
iii. Provide first aid to the injured at the event of accident.

NESPAK-ABB-DMC

177

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

iv. Report any accident / incident to the environmental manager immediately for
necessary action.
v. Call ambulance in case of any serious emergency.
Emergency siren should be installed at the barrage to inform the site worker about any
emergency situation. The operation of the siren will be controlled by the HSE officer or his
nominated person. The designate assembly area also should be marked and informed to
site worker.
An outline of a contingency plan for the accidental spill is shown in Exhibit 4
Exhibit-4 Accidental Spill Contingency plan
Step

Diesel spill

Chemical and Oil Spill

Alert / Mobilize

Alert emergency

Alert emergency

(by work supervisor)

coordinator and team

coordinator and team

Initial action

Start log of event

Start log of event

(by HSE Officer)

Determine

appropriate Determine

appropriate

strategy

strategy

Notify PMO in Lahore

Notify PMO in Lahore

Notify relevant authority

Notify relevant authority

On-going actions

If there is a containment If there is a containment

(Site Incharge)

breach, use earth moving breach, use earth moving


equipment

to

construct equipment

to

construct

ditch or berm to contain ditch or berm to contain


spill. Use pump / absorbent spill. If it contaminates the
to

recover

Handle

the

the

product. river use pump / absorbent


recovered pad to recover the product.

product according to the Handle


COSHH sheets.

the

recovered

product according to the


COSHH sheets.

Stand Down
(Site

Incharge

Engineer)

Once
/

the

incident

has Once

the

incident

has

The ended the emergency team ended the emergency team


and authorities will stand and authorities will stand
down and commence as full down and commence as full
investigation

NESPAK-ABB-DMC

investigation

178

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Waste disposal

Collect all contaminated soil Incinerate

(Contractor)

or

absorbing

or

pads

and bioremediation

or

treat

with collected

bioremediation

at

incinerate

treat

with
the

product

at

a controlled access area at

controlled access area. In the burn pit. Collect all


case of contaminated water contaminated

soil

and

the water should be treated incinerate it at the burn pit.


and reuse or pump it back
in to the river.
7.11

HEALTH, SAFETY & ENVIRONMENT (HSE) PLAN

It is a contractors obligations to provide and implement the Health, Safety & Environment
(HSE) Plan. The Plan should be divided into three main parts Health, safety and
environment. Each part should include but not limited to the following elements;
SAFETY
1

HSE Responsibilities

Site HSE Rules

Orientation, Site HSE Induction and Other Training Activities

Communication and HSE Meetings

Workforce Involvement, Motivation and HSE Incentive

Performance Monitoring

Hazard Analysis and Risk Management

Safe Work Practices

Personal Protective Equipment

10

Fire Prevention

11

Emergency Response Plan (ERP)

12

Transportation

ENVIRONMENTAL MITIGATING AND MOINTORING PLAN (EMMP)


1.

HSE Policy

2.

Scope and Objectives

3.

Mitigation Measures, Implementation Plan & Compliance Monitoring

4.

Waste Management

5.

Hazardous Material

6.

Night Working

NESPAK-ABB-DMC

179

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

7.

House Keeping

8.

Noise

HEALTH & HYGIENE


1. Purpose
2. Scope
3. Medical Personnel
4. First Aid (Medical) Facilities
5. Heat Stress
6. First Aid Training
7. Living Camp
8. Welfare of Personnel
9. Use of Narcotics And Drugs
10. Drainage, Sewerage and Septic Tank
SITE SECURITY
1. Purpose
2. Scope
3. Method and Responsibilities
ATTACHMENTS
1. HSE Policy
2. List of HSE SOPs, MS & Formats
3. Typical Site HSE Organization
4. Injury Statistics for the last four years
5. Honours and Awards
7.12

TREE PLANTATION

The Tree Plantation Plan will be prepared and implement by the contractor and verified by
The Engineer. In order to construct the flood escape channel about 310 numbers of woody
trees are required to be uprooted. All these trees are on the government land.
To mitigate this environment loss the only way out is the re-plantation with at least fifteen
hundred new trees in the adjacent area of the flood escape channel.

NESPAK-ABB-DMC

180

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

To raise the aesthetic value and enhancing positive environmental impacts it is also planned
to plant additional 3000 number of woody, fruit and flower plants at the different location of
the barrage and along the existing embankments.
New plantation will be undertaken as an avenue plantation along the newly built bypass
channel and the available locations at the existing embankments, according to the tree
plantation plan prepared by the contractor.
7.13

BORROW AREAS RESTORATION

Construction of bypass channel will generate sufficient soil material to fulfil the requirement
of the fill for strengthening of embankments. If during construction further material is required
or contractor need to borrow material from anyother site then the contractor can acquire
private land in according to the lease agreement with the land owner. Photographs record
will be kept before and after the land use as borrowing area. The contractor will not leave
borrowing pit in such a condition that they are unusable and could be filled with rain water
and provide breeding place for mosquitoes or cause any health and safety issues.
Agriculture land should be restored such that it can be re-use for the agricultural purpose.
The restoration of agricultural land includes but not limited to the following steps.

Remove of 6 inches of the topsoil and keep it separate on site for its re-spread back
on the levelled borrow area

Excavate up to maximum 3 feet

Level slops as far as possible

Place the topsoil back on reasonably levelled area

7.14

LAND ACQUISITION PROCEDURE


Land Acquisition Act (LAA) 1894 is the primary law governing land acquisition in
Pakistan. The rules and regulation of above law will be followed for the acquisition of
private land.

It is envisaged that no private land acquisition will require for the project
implementation and contractors facilities set up. However temporary acquisition of
private land may require for borrowing material. If the contractor proposed different
locations of labour camp, batching plant etc and require any private land then he/she
need to follow the LAA 1894 to compensate the land owner.

Land valuation will be carried out with the help of district officer and agree with the
private land owner.

NESPAK-ABB-DMC

181

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Cut of date will be announced at the day of compensation value agreed and signed
with land owner and authorities.

The compensation will be paid to the affectee(s) prior to possession of the land being
taken by the Government of Punjab.

7.15

RISK MANAGEMENT PLAN

The outline of the Risk Management Plan is provided in this section. The detailed and more
precise plan should be prepared and implemented by the contractors Project Manager. The
following Plan identify the possible hazards associated with the project activities,
consequences of the occurrence, probability of the occurrence and action to reduce the risk
to acceptable level i.e. low to medium.
Hazards

Consequences

Probability

of occurrence of

Risk

Action to Manage Residual

(L, M, H)

the Risk

-Select the location L

Risk

(Severity-

occurrence

L,M,H)

(L, M, H)

Oil,

Contaminate

Chemical

land and control

of material storage

Spill

water bodies

yard away from the

(M)

water bodies
-Store material on
bunded area with
impermeable layer
-Good
housekeeping
-loading

and

unloading

of

material should be
manage

by

competent person
-spill kit should be
available

to

deal

with small spills

NESPAK-ABB-DMC

182

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Hazards

Consequences

Probability

of occurrence of

Breach

(Severity-

occurrence

L,M,H)

(L, M, H)

in Fatality

Cofferdam

or M

Risk

Action to Manage Residual

(L, M, H)

the Risk

-The

Risk

construction L

serious injury of

and maintenance of

the worker

cofferdam

Adversely

be

impact

on

should

mange

by

competent person

aquatic life

-Findings of daily

(H)

inspection
be

should

recorded

and

analysis
-sand bags should
be available on site
to deal with small
damages

in

the

cofferdam
-monitor

river

quality

at

downstream of the
cofferdam

on

regular basis.
Adverse

Deteriorate

environment

natural

al

habitat

impacts of pond area

on Barrage
pond

(L)

-Implementation of L
the

control

measures

mitigate impact on

area

biological

to

resources

due

to

construction

-Select appropriate

activities

plant

and

equipment

and

enforce the speed


limit for site traffic
to

minimize

noise

and

the
dust

pollution

NESPAK-ABB-DMC

183

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Hazards

Consequences

Probability

of occurrence of
(Severity-

occurrence

L,M,H)

(L, M, H)

Failure

in Fatality

plant

& serious injury

equipment
e.g.

or M

Risk

Action to Manage Residual

(L, M, H)

the Risk

-Inspect

Risk

all

the L

equipment

(H)

including

lifting

lifting

chains & ropes at

gears etc

the start of the work


-A

competent

person

should

mange the work on


site.
Extended

Damage

the L

Canal

crop within the

Sadiqia Canals are

Closure

canal command

perennial

area

and close only for

(H)

canal

Pakpattan

and L
canals
cleaning

work. All the work


requires

canal

closure should be
arranged

during

available

canal

closure

time.

require

If
use

cofferdam

or

construct
temporary

bypass

arrangement
continue
water

to
canal

supply

as

routine.

NESPAK-ABB-DMC

184

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Hazards

Consequences

Probability

of occurrence of
(Severity-

occurrence

L,M,H)

(L, M, H)

Batching

Deteriorate

plant

ambient

Risk

Action to Manage Residual

(L, M, H)

the Risk

-Select

air

Risk

batching L

plant location away

quality

from the living area

(M)

or construct zero
emission plant
-should not operate
outside

working

hours i.e. night time


or early morning
-All

the

workers

working at the plant


should wear proper
PPE

(breathing

masks, gloves, eye


protection etc)
Smoke from Cause
Burning

-Provide

smoke L

suffocation and

free fuel at labour

diseases

camp

respiratory tract

-Cutting

(H)

burning

and
of

trees

shall be prohibited
Road

Casualty,

accidents

serious

due

M
injury,

to damage

to

-prepared
implement

and L
Traffic

Management Plan

construction

infrastructure

as

work

(H)

EIA.

suggested

in

activities

NESPAK-ABB-DMC

185

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Hazards

Consequences

Probability

of occurrence of
(Severity-

occurrence

L,M,H)

(L, M, H)

Adverse

Extra burden on M

Social

existing welfare

impacts due facilities.


to migrating Can

Cause

Risk

Action to Manage Residual

(L, M, H)

the Risk

Improve

and L

increase

the

capacity

of

available

existing

Risk

labour from communicable

service to cope with

other part of diseases

the requirement of

the country

additional users.

(H)

Run

campaign

within

the

camp

and

labour
local

community to make
people aware of the
cause,

mode

transmission
consequences

of
and
of

communicable
diseases

e.g.

HIV/AIDS etc
L: Low;
7.16

M: Medium;

H: High

TRAINING MODULE

The training will be given to the different professional groups separately such as manager
level group, work supervisors, skilled/unskilled labour etc. The training will helps to insure
the Project worker understood and followed the EIA and EMP. A Trainging plan of 10
sessions which will be finalized before the commencement of the project is given below

NESPAK-ABB-DMC

186

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Training Plan
Trainee

Trainer

Contents

Schedule

Selected field staff of

EU Specialists;

Environmental and social

Before

PMO and Supervision

Environmentalist

aspects,

construction

Consultatnt

of

sensitivities of the project;

Supervision

Consultatnt

particularly

activities

Key finding of the ESIA


Social and cultural values
of the area;
Leadership dynamics.

All site personnel

Environmentalist

Environmental and social

Before

of

aspects,

during

Contractor:

Managerial

staff,

Supervision

Consultant

engineers,

particularly

the

sensitivities of the project;

construction

Wildlife

stage

and

vegetation

Environment,

social,

related sensitivities of the

health

safety

project;

and

staff.

Key finding of the ESIA;

Mitigation measures;

Consultants:

and

Managerial staff and

Contingency plan;

engineers

Community issues;
Social and cultural values
of the area

Construction crew

Environmentalist

EMMP;

Before

of

Waste disposal plan; HSE

during

plan

construction

Supervision

Consultant

and

Environmental
Officer

and

stage
of

Contractor
Drivers

Environmental
Officer

of

Contractor

HSE plan; Road safety;

Before

and

Road restrictions;

during

the

Vehicle restrictions;

construction

Defensive driving;
Waste disposal;
Social and cultural values
of the area.
Camp staff

Environmental
Officer
Contractor

of

HSE plan;

Before

and

Camp operation

during

the

Waste disposal

construction

Natural resource

NESPAK-ABB-DMC

187

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Trainee

Trainer

Contents

Schedule

conservation
Housekeeping
Restoration team

Environmentalist

Waste disposal;

Before

of

Site restoration;

start

Leveling and restoration of

restoration

borrow area

activity

Supervision

Consultatnt

7.17

the

of the

ENVIRONMENTAL MANAGEMENT COST

The cost provided in this section is based on the information available at up-dating feasibility
level, which may be amended at detail design stage.
7.17.1 Environmental Monitoring Cost
River water should be tested on quarterly basis at the barrage during barrage structure
repair, motorization for gate operating system and bela excavation activities. Samples
should be collected from upstream and downstream of the barrage during the construction
phase. The samples should be tested for all the parameters of WHO drinking water
standard, NEQS and FAO water quality standards. The approximate cost of monitoring of
river water quality, assuming 3 years of construction phase is Rs. 1500,000.00. Dissolve
Oxygen, pH and Electric Conductivity (EC) of the river water should be monitored on
monthly basis during construction phase the approximate cost of the equipment are
EC, TDS, DO & pH meter

Rs. 150,000.00 (Modern Technology, Lahore, HANNA


Sole distributor)

Groundwater should be tested at quarterly basis. Testing is also required at the start of the
project before using the groundwater as a source of water supply. The samples should be
collected from all the sources of groundwater use by the contractor onsite i.e. hand pumps,
tubewell etc. The parameters need to be tested include WHO drinking water standard and
FAO agriculture standards. The approximate cost of monitoring the groundwater over 3
years of construction phase at quarterly basis (considering one source only) is Rs.
300,000.00.
Air quality should be monitored at quarterly basis and When required at work activities. The
parameters for air quality monitoring include but not limited to carbon monoxide, NOx, SOx
and particulate matter. The approximate cost of Ambient Air Monitoring over 3 years of
construction phase is Rs. 300,000.00. Noise should be monitored 3 times on each working

NESPAK-ABB-DMC

188

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

day at every noise producing activity. The approximate cost of the Noise meter is Rs.
50,000.00.
The approximate total cost of the monitoring of the physical environmental parameters is
Rs.2.3million. The cost includes the man months of environmentalist for analyzing of the
results and report writing by an environmentalist.
The required environmental monitoring is summarised below in table 7.2.

NESPAK-ABB-DMC

189

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Table 7.2

Environmental Monitoring Plan for the Construction Phase

Environmental
Quality

Parameters

Air Quality

At 40m radius of
Batching
Plant
(determine
the
CO, dominate air direction
PM10,
USEPA, WHO
carry
out
CO2 NOx, SOx and
monitoring
at
downstream of air
flow)

Dust Monitoring

PM10

Details of Location

Noise Monitoring

Noise

NESPAK-ABB-DMC

At Borrowing area
At the barrage
At the Access
roads
Labour camp
At the barrage
At Barrage Pond
area,
approximately 5m
from the working
site/machinery
At the borrowing
site (s)

Standards /
Guidelines

USEPA, WHO

Frequency

Responsibility

Duration

Quarterly basis

Contractor

Construction for
24 hours or one
full working day

Quarterly
When required

Contractor

Full working day

3 times over 24 hour


(morning, afternoon
Maximum
allowable level and evening) at Contractor
is 80dB
Active
Construction site

190

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Environmental
Quality

Surface
Quality

Parameters

Details of Location

At
upstream
and
downstream of the
barrage / Work area
Full Suite of
and effluent from
contaminants
labour
camp
given in main
wastewater
before
Water report of ESIA
discharge into the
(in ch. 4)
river or other water
body

Standards /
Guidelines

Frequency

Responsibility

Duration

NEQS &
WAPDA
Irrigation
Standards

Quarterly Basis

Contractor

Monthly Basis

Contractor

Contractor

NEQS
At
upstream
and
WAPDA
DO, EC, pH
downstream of the
Irrigation
and TDS
Barrage / work area
Standards

Groundwater

NESPAK-ABB-DMC

&

Groundwater
All the groundwater
WHO drinking
(Suite
of
Quarterly Basis
extraction points use
water standard
Contaminants
by the contractor
given in ESIA)

191

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

7.17.2 Training Cost


Training is considered to be an important part of environment awareness and all site
management and work supervisors should undertake periodic training.
The Contractor will arrange to run a proper campaign among the workers to make people
aware of the causes, mode of transmission and consequences of HIV/AIDS.
Contractor will arrange briefing given to all workers regarding the biological resources and
wetland area. It should be cleared to the worker that unnecessary and out of bound activities
/ movements are strictly prohibited in the barrage pond area. All forest and fisheries laws
should be explained to the workers.
The approximate cost of training the site staff is Rs. 500,000. The cost includes 10 sessions
of environment awareness course each cost Rs. 50,000.
7.17.3 Plantation Cost
Strengthening of embankments and construction of flood escape channel and fuse plug will
require tree cutting of approximately 310 numbers of woody tree. 5 new trees will be planted
of every one tree uprooted on site. Therefore it is proposed that the contractor or hire the
services of concern department i.e. Forestry to plant minimum 1550 new plants and look
after them until their maturation i.e. arrange watering and install protection grill around new
plantation, if require. New plantation should be around the barrage and proposed flood by
pass channel. The total estimated cost of the plantation is Rs. 300,000.00.

7.17.4 Cost of Implementation of Emergency Plan


The emergency plan will be prepared and presented in the final EIA report. The plan will be
prepared to address any emergency conditions occur due to encounter unexpected flood,
breach in cofferdam or accidental spill of oil or chemical. The approximate cost of dealing
with unforeseen circumstances during construction phase is half a million rupees.
7.17.5 Solid Waste Management Cost
The approximate daily production of domestic waste at labour camp is estimated at
approximately 500kg (1/2 kg per person per day). The cost for disposal of domestic waste
for 3 years of construction phase including the preparation and maintenance of the
temporary storage area and burn pit on site is included in the contractors contractual
obligations.
Specialize contractor should be hired to dispose of the special waste i.e. cement bags,
clinical waste, electric batteries etc. The approximate cost of the disposal of special waste is
Rs. 500,000.00.

NESPAK-ABB-DMC

192

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

7.17.6 Water Supply & Wastewater Management Cost


It will be one of Contractors contractual obligations to arrange the supply of running drinking
water at appropriate pressure to the site workers. The access of the drinking water should be
available to every site worker. The cost of this item is included in the contractors contractual
obligations. Water sample should be collected and tested on quarterly basis to confirm its
suitability for drinking purpose. The approximate cost of this item is Rs. 250,000.00.
It is proposed to treat the domestic wastewater generated from the labour camp, which
should be collected with provision of underground sewer system and three chambers Septic
Tank connected in series. The capacity of each chamber should have minimum one day
waste water discharge from the site facilities. The cost of this item is included in the
contractors contractual obligations.
If collected wastewater from site setup i.e. Batching Plant, contractors camp, effluent
collected from waste storage area etc are discharge into the river then it should be tested for
NEQS standard and confirmed the levels of the contaminates are within the acceptable
level. The allocated cost for this testing is Rs. 250,000.00.
7.17.7 Site Visits by Authorities & Regulators
Inspections by stakeholder and concern bodies for example WWF, Wildlife, Forest or Fishery
Officers etc should be facilitated in camps to facilitate a proper implementation of relevant
laws. The approximate cost of this item is Rs. 500,000.00.

7.17.8 Traffic Management Cost


The Traffic Management Plan will be prepared by the contractor to manage the site traffic
and public traffic during construction phase of the project to minimise the interruption in the
flow of traffic. The approximate cost allocated for this item is 10 million rupees. The cost
include the provision of boat bridge at down stream of the barrage during the barrage repair
work.
7.17.9 Public Parks
The development of existing Public Park is also included in the scope of work of this project.
This will raise the aesthetic value and biodiversity of the area. The scope of work includes a
development of an artificial lake, plantation of woody, fruit and flower plants, install children
fun rides and Construct new canteen and restaurant area. The approximate cost of this item
is 10.0 million rupees.

NESPAK-ABB-DMC

193

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

7.17.10 Restoration Cost


The area being under the use of contractor during construction phase should be restored at
the completion of the project to the original level without any additional cost by the
contractor.
Table 7.3

Environment & Management Cost

Activity

Cost (millionRs)

Cost ($)
(1$ = 85Rs)

Environment Monitoring Cost

2.3

27,059

Training Cost

0.5

5,883

Plantation Cost

0.3

3,530

Emergency Plan

0.5

5,883

Waste Management Cost

0.5

5,883

0.5

5,883

Site Visits by Regulators & Authorities

0.5

5,883

Traffic Management Cost

10.0

117,647

Public Park Rehabilitation

10.0

117,647

Total

25.1

295,298

Water

Supply

&

Wastewater

Management Cost

The above cost will be covered for the project (as part of the loan money)
Contractors Obligation
The following conditions should be included in the Tender Document followed by the
Contract Document as essential clauses:

Clause regarding disposal of waste construction material

The Contractor shall in consultation with the supervising consultant and with the approval of
Supervision Consultant of the Project, select and abide by the selection, a site for disposal of
waste construction material as well as the material used for construction of coffer dam.
Contravention to this clause may tantamount to contravention to contract and the Contractor
will be responsible of removing the material dumped on a wrong site, at his own expense as
early as possible. In case of delay, the contractor will pay a fine, suggested by the
supervision consultant, for his negligence.

Clause

regarding

adjustment

with

unstable

locations

appearing

during

construction especially the foundation


In case an unstable location appears during construction, especially the foundation, the
contractor shall immediately inform the Supervision Consultant expressly providing full
technical details about the problem. The Supervision Consultant will inspect the site;
NESPAK-ABB-DMC

194

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

preferably the same day the report is received and will, if necessary, agree to make
modifications and changes in the design to stabilize the situation such as change in the
depth of foundation. Contractor will not make any changes in the specification without
express approval of Supervision Consultant. Contravention to this provision will mean
unauthorized construction carried out for which RE will issue dismantling orders.

Clause regarding Location of Labour Camps, Material

Dumps / Depots,

Equipment and Machinery Yards, approach roads and routes


Irrigation and Power Department land is available for location of Labour Camps, Material
Depots, Equipment and Machinery Yard, link roads or other activities related to these
matters and proposed sites have been shown on the environment baseline map. The
Contractor will choose particular sites within the overall campus with the consultation with
Supervision Consultant and PMO. If the Contractor chooses to locate his facilities on a
private land, he will himself be responsible for any compensation, resettlement or
rehabilitation process and costs and Supervision Consultant or Irrigation and Power
Department shall not be involved in acquiring or using the land in making any payments for
doing so. If the contractor selects different location for the Batching Plant, Labour Camp,
borrowing area etc then the contractor will develop base line data for the new location on his
own cost and resources.

Clause regarding Rehabilitation of Construction and Extraction Sites

The Contractor shall carry out construction work exactly on the same site and according to
the same design as provided in the Tender Documents. Also the camps site, the material
depot, the machinery and equipment yard, link roads, borrow areas and coffer dam shall,
after the completion of construction, be restored and rehabilitated and brought to at least the
same condition, in which these were handed over to the contract. A set of Plategraphs and a
video tape film shall be prepared to show the pre-construction sites and post construction
rehabilitated sites.

Clause Regarding Drainage, Paths, Roads, Linear Fixtures Crossed/Damaged By


Machinery Moving to and From the Construction Sites

During the construction, if the Contractors vehicles moving to and from the construction
site(s) cause any damage or disruption of services pertaining to drainage systems, paths,
roads linear fixtures e.g., transmission lines and fences, the Contractor shall get the damage
repaired and services restored within the shortest possible time of the damage, failing which
the Supervision Consultant will get an assessment of the damage and losses and debit that
amount to Contractors account and the next payment shall be made to Contractor after
deducting the debited amount.

NESPAK-ABB-DMC

195

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Clause Regarding Earthen Embankments or Concrete Work Vicinity Scouring on


The Protection Bunds or on the Main Sill Structure

All such spots where there is a possibility of scouring of earthen embankments or concrete
work edge as mentioned in the Tender Document and quality included in this Construction
Contract, the Contractor shall protect by protection walls and stone rip-rap work, failing
which the payment of the Contractor shall be with-held.

Clause regarding discharge spill or dumping on any building, House, graveyard,


archaeological site (established or newly Found), unstable slopes, un-compacted
embankment or leaking into construction area

The Contractor shall be contractually bound to not to allow or cause discharge spill or
dumping on any building house, graveyard, archaeological site (established or newly found),
unstable slopes, un-compacted embankment or leakage of material/waste into the
construction area. Any such failure shall be duly noted by Supervision Consultant during site
inspections and contractor shall immediately remedy the situation failing which the payment
of the contractor shall be with-held and the damage so caused shall be debited to
contractors account under the contractual provisions.

Clause regarding Diesel and other fluids spilling over to River water from
Construction Machinery

The Contractor shall ensure that his construction machinery is always in first class working
order and no spilling of Diesel or any other fluids into the River, is caused by the defective
machinery of the Contractor. For any such spill the Contractor shall pay the environmental
compensation to be assessed by Supervision Consultant and the said amount shall be
debited towards the payment of the Contractor.

Clause Regarding Protection of Construction Work From Floods

The Contractor shall, throughout the construction work, manage to keep an eye on the flood
position of the barrage and shall remain in touch with Flood Control Centre and remain
equipped with means and equipment for taking protective measures to protect the works
under construction. Irrigation and Power Department shall not be responsible for any
damage caused by floods and any works washed away shall be reconstructed by the
Contractor at his own cost within the tenure of the contract.

Clause regarding providing proper diversion of water from downstream

The Contractor shall, in consultation with Supervision Consultant provide proper diversion to
water flowing downstream and by requesting the Barrage Management opening and closing
the main barrage gates and by collaboration with local communities especially the
Fishermen community as per SFA and preparing them for any such diversions or closures.

NESPAK-ABB-DMC

196

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Losses caused to construction work due poor or mismanaged river flow diversion shall be
considered as negligence on the part of contractor any damages or losses caused due to
this negligence shall be borne by the contractor.

Clause regarding control on air quality by not allowing Machinery to cause dust,
smoke or noise pollution

The Contractor shall not cause deterioration of air quality by using old or ill maintained
machinery which raise excessive dust, produce excessive smoke or cause excessive noise
pollution. The Contractor shall follow strict standards of maintenance of machinery, provide
qualified and trained drivers and operations for the vehicles. The Contractor shall also
sprinkle water on kacha roads to be used as link roads, and sites where the earth is to be
dumped. The Contractor shall provide protective masks to his work force. Failure to do so
shall be taken as serious contravention of the contract and shall cause the payment to be
deferred till the correction of the situation.

Clause regarding control of dust or other pollutants from Stored materials,


material depots or spoil heaps

The Contractor shall:(a)

locate his material depots and spoil dump as far away from the villages/community
Deras as possible.

(b)

keep all such materials covered for effective control of the fugitive dust.

Failing to do the Contractor will bear the cost which may have to be incurred on arranging
remedy to defaults.

Clause regarding use of outdated machinery

The Contractor shall obtain a certificate from Vehicle Examiner working under the
Supervision Consultant but paid by the Contractor, that all the machinery employed is either
new or in first class fitness condition so as not to cause smoke or oil leakages. Supervision
Consultant will not allow the use of any outdated machinery.

Clause to Protect the Biological Resources

The Contract will ensure that:a) Unnecessary and out of bound activities/movements are not done outside the
campus allotted to him for setting-up the labour camp, material depots and
machinery yard etc.
b) No fire arms are carried by any of the employees or labour.
c) All Forest, Wildlife and Fisheries Laws are fully respected and abided by the
Contractor and his work force.

NESPAK-ABB-DMC

197

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

d) The Biodiversity is respected and saved on its terrestrial, aquatic and aerial habitats.
e) Necessary sign boards indicating boundaries of the barrage pond area are displayed
to make labour, visitors and members of public to remind them of their obligations
towards Biota.
f)

Inspections by Wildlife, Forest and Fisheries Officers are facilitated in camps to


facilitate a proper implementation of relevant Laws.

g) Communities are given awareness and are involved in proper protection of the Biota
inside and around the Project site.

Clause regarding respect for Socio-economic and Cultural Values and heritage

The Contractor shall be bound to:(a)

Ensure that no damage or disruption is caused to the social infrastructure or public


services being provided to the people e.g., education, health, electricity supply,
drinking water supply facilities for public gathering or religious congregations.

(b)

Ensure the Contractor or his employees remain above the local Tribal tensions
especially the disputes over distribution of canal water and use of aquatic life.

(c)

Ensure that existing ownership of land around the Project is respected.

(d)

Ensure that if some construction material has to be procured from or through a


member of local community, it must be by a proper Social Framework Agreement
signed by all the parties.

e)

Ensure that no damage or adverse effect is caused to archaeological sites (in case
find on site) graveyards and burial places.

Clause regarding Public Safety, Health and Safety at Construct Site, including
measures against HIV/AID and Life insurance.

The Contractor shall:a. Put up temporary but prominent sign boards in all of the project activity area warning
people against likely hazards which can be caused due to certain activities. (Also to
be reflected in SFA).
b. Arrange to run a proper campaign in the labour camp, to make people aware of the
causes, mode of transmission and consequences of HIV/AIDS.
c. Strengthen the existing Basic Health Unit (BHU) for the benefit of the labour as well
as the surrounding villages.
d. Ensure proper cleanliness and hygienic conditions at labour camps by ensuring a
clean mess, proper drainage and suitable disposal of solid waste. Inoculation against
Cholera will be arranged at intervals as recommended by Health Department.

NESPAK-ABB-DMC

198

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

e. Keep all the camps, offices, material depots, machinery yards and work site open for
the inspection of health and safety measures, and related documents and include in
the contract document the text regarding accessibility to the camps etc.
f. Provide proper overall, helmet and field boots and earplugs to work as a precaution
against any mishap, and interlink various parts of the construction complex with local
wireless telephones also fitted the vehicles.
g. Provide a group insurance cover to the workers and labour on study on site or in the
camp, against accidents, mishaps or loss of life on duty.

Clause regarding employment of Locals in the construction work

The Contractor as an obligation of the Contract will employ, subject to availability and work
ability, maximum number of local labour for construction work.

Clause regarding impact due to material and waste left behind when construction
or dismantling Cofferdam(s)

A careful planning of construction and dismantling is the Contractors contractual obligation.


It is his further obligation to remove all left over material and construction waste. The
contractor shall ensure that turbidity / dissolved oxygen will not exceed from the acceptable
levels during construction or dismantling of cofferdam(s). Contractor will consult with the
environmentalist from the supervising consultant to get approval of the process of
constructing / dismantling of cofferdam(s). It is also obligation of the contractor to remove at
least 70% of the cofferdam construction. Furthermore, all removable sheet piles, if any, will
be completely removed or at least underwater cut at river bed level after completing the
construction activities. Failure to complete the task will liable the contractor to deduct total
cost of the sheet pile left, as well as the cost of the construction of cofferdam left behind
lesser than 70%. Disposal site(s) for the dismantled cofferdam(s) will be finalized by RE and
EU.
7.18

CONCLUSION

The potential impacts of the project are associated with only the construction phase of the
project and all of these impacts are temporary and reversible in nature. These impacts can
be mitigated through the proper implementation of the EMP. Therefore it is concluded that
the project is environmentally friendly, financially viable, economically sustainable,
genderally neutral and pro-poverty alleviation.

NESPAK-ABB-DMC

199

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Figure 7.1

NESPAK-ABB-DMC

Proposed Traffic Management Map

200

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

CHAPTER 8:
8.1

Updating Feasibility Study for R&U Suleimanki Barrage

PUBLIC CONSULTATION

GENERAL

Timely and broad-based stakeholder involvement is an essential element for an effective


environmental assessment, as it is linked with Project Planning, appraisal and development
in general. Public involvement during Environmental impact Assessment (EIA) have a
tendency to improve project design environmental soundness and social acceptability.
Contrary, EIAs that fail to be inclusive lean to have less influence over planning and
implementation and resulted in high environmental and social cost. Considering more
stakeholder involvement in EIA process resulted in improving the quality of the
environmental assessment (EA). This is due to the prediction of the impacts using EIA often
requires many years information and good quality base line data. Environmental
Assessment that involves broad-base stakeholder consultation have greater potential to
assess wider information resource-base and generation of accumulating knowledge of the
local environment.
8.2

LEGAL REQUIREMENT FOR PUBLIC CONSULTATION

According to the IEE and EIA Review Regulations 2000, public consultation is mandatory for
EIA study. It is also mandatory for the projects classified as category B project and AOI
include environmental sensitive area under the ADB Environment Policy.
8.3

CONSULTATION METHODOLOGY

8.3.1
Stakeholder Identification
They are grouped into the following main categories
i.

Local Communities

ii.

Government & Local Government Bodies

iii.

Civil Societies

iv.

Private Sector Bodies

The groups or institutions identified as stakeholder under each category are listed below
I.

Local Communities
a) Local labour (landless)
b) Farmers of all land holding categories
c) Fishing communities
d) Female-head household
e) Small business owner

NESPAK-ABB-DMC

201

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

II.

Updating Feasibility Study for R&U Suleimanki Barrage

Government

There can be many departments who can be indirectly related to the project but those who
have high relevance include;
a) Punjab Irrigation Department (including both top and low ranked officers
and staff)
b) Punjab Forest Department, Wildlife, Fisheries Department
c) EPA
III.

Civil Society Institution that may have relevance to the Project includes various
NGOs working in the construction and social development

IV.

Private sector bodies can be commercial e.g. plantation manager, fishing contractors
etc

8.3.2
Consultation Process and Technology
Public Consultation has been conducted in two phase once during the early stage,
reconnaissance survey and once during the preparation of EIA. Consultation with
stakeholder will also be carried out throughout the Project cycle and by different member of
the team at different stages of the study. Consultation process includes focus group
discussion, village meetings and semi-structured interviews and one to one meeting or
interviewed in the case of government, private and civil society institutions. During the
consultation process, the stakeholders was briefed about the project objectives and scope.
Their fears and suggestions was recorded. Women consultations was undertaken, under
Gender analysis and explained about the benefits of the project.
All meetings and discussion were held during day time on working days to ensure the
availability and participation of the group/individual being consultant. The consultation is
sensitive to the local language and cultural needs and wherever expatriate staff is involved
local interpreters will be used, as the staff observed local norms.
Local community and Wildlife and Fishry department has been consulted under phase I
public consultation and their point of view and information provided are included in this
study. The details of the consultations are summarized in Table-8.2.
8.4

OBJECTIVES ACHIEVED WITH THE PUBLIC CONSULTATION


Eliminate the scare that the canals will remain closed outside the routine closure period
during the construction period. It was clarified that due measures will be taken that
canals would run as per usual program and canal closure will take place only under the
notified canal closure program as follow.

NESPAK-ABB-DMC

202

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Name of Canal

Updating Feasibility Study for R&U Suleimanki Barrage

Status of Canal

Periods when canal would


close

Pakpattan Canal

Perennial

31-Dec to 16-Jan

Fordwah Canal

Non-Perennial

15 Oct to 15 April

Sadiqia Canal

Perennial

31-Dec to 16-Jan

No change would ordinarily be made in existing capacity of canals during construction


phase, so no impact is anticipated on the canal command area. It was

explained

that project aimed at rehabilitating the Sulemanki Barrage and increase the capacity of
the barrage by strengthening embankments, Barrage structure and

dredging the silt

within the pond area of the barrage. The local community was informed about the
surface water quality and the water quality of the existing hand pump is not fit for
drinking purpose without any treatment as identified in the baseline study.
3

Resettlement Plan (RP) will be prepared to facilitate the affecties and submitted to the
authorities under different cover.

Eliminate the fears that the large number of workers and labour will be brought by the
contractor from outside the project area and ensure them that an opportunity of
employment generated by the project shall be availed by the people of the area.

It was clarified that no access roads or public paths damage or alter for the contractor(s)
activities i.e. labour camp, material depot, machinery yard etc.

It has been ensured to the local community that maximum employment will be offered to
the local labour/workers. They were given the following illustrative numbers of skilled
and unskilled labour that will be required for the project.

Table 8.1:

Employment Opportunity at Suleimanki Barrage Rehabilitation Work

Skilled Worker
Semi

Skilled

Labour
Unskilled
Labour
i.

Approximate Total No.

Minimum Percentage of Local

75

As much as possible

325

As much as possible

600

As much as possible

Fishermen of the community believe that the construction activities would not put
adverse effects on fishing industry as most of the Project activities schedule within
half kilometer of upstream and downstream of the barrage structure which is a
prohibited area for fishing. However the strengthening of the embankments work will

NESPAK-ABB-DMC

203

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

raise the noise level of the surrounding area and could effect the fishing activities
next to the embankments.
ii.

Question was passed by the community that presence of some 1000 male members
of labour from general locality of project will not only restrict the chances of women
employment, but also cause moral and social problems for the free movement of
local women folk in the area. It was clarified that strict discipline would be exercised
on the labour force by providing stringent clauses in the contract document. To cut
out the possibility of any moral issues or Communicable diseases spread, a well
organized campaign shall be run.

iii.

Road and kacha paths within the project areas would expose to the heavy traffic due
to Project activities. This could raise the road accident and deterioration rate of the
roads. It was clarified that due sinology and traffic management plan would be put
into operation to minimize the impacts.

iv.

With arrival of about 1000 additional persons, the price of accommodation in project
area and Sulemanki Barrage markets would go up, and price index would go
unfriendly for the local villagers. It was clarified that a Labour Camp will be
constructed to accommodate for workers. It was also explained to the local
community by some trade oriented people that instead of rise in price those would fall
because larger market activities reduce the profit margin and price. More economical
activities and better employment opportunities will be available for local community
due to the rehabilitation of the barrage. This will help in lowering the poverty line in
the area.

The following points came up in open acceptance of the project.


a) Greater employment opportunity was most welcome.
b) Greater economic activity will alleviate poverty.
c) Sulemanki barrage will be saved and given longer base of life and thus the
dependent agriculture.
d) Present level of services i.e. electricity, communication, schooling, water
supply etc. is likely to improve.
e) Wildlife Public Parks will attract visitors and tourism in the area and put
positive effects on the local economy.
8.5

CONSULTATION AND DISCUSSION DURING IMPLEMENTATION

8.5.1
Public Hearing
This public hearing paragraph is a dummy to indicate the type of text required in the report.
This will be replaced by actual text when EPA Punjab holds hearing. The public hearings will
provide a forum for the post submission consultation on the EIA. The Punjab EPA within 10
NESPAK-ABB-DMC

204

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

days of the submission of the EIA will publish a public notice in any English or Urdu national
newspaper and in a local news paper for general circulation of the area affected by the
project.
The EPA will fix the date (not be earlier than 30 days from the date of publication of the
public notice) and venue for the public hearing.
The circulation of the EIA report, gathering of comments on the EIA and ensuring public
participation during public hearing will be the responsibilities of the Punjab EPA. The public
hearing will preferably be held at the town/city nearest to the project area with representative
from the government agencies, academic and prominent NGOs attending.
During the project implementation the consultation of the local community will occur at many
forum by different members of the project. These consultations will be done during
construction & operational phase of the project, for capacity building and implementing
agricultural extension. These consultations will be provided the forum continuously gathering
concerns of the local communities during project implementation.
A Social Frame Work Agreement (SFA) will be signed through mutual open consent
between the local village leaders and designated official of I&P Department. An outline of
SFA is given below.
8.5.2

Epa Approval

The EIA report duly reconciled with PMO has been submitted to EPA Punjab for obtaining
No Objection Certificate (NOC). A cheque of Rs. 30,000.00 has been also deposited along
with the report by the consultant to EPA through PMO for conducting a Public Hearing. The
approval from EPA (NOC-No Objection Certificate) for the Project is mandatory requirement
before its commencement.
Social Framework Agreement
1. This is a Draft Social Framework Agreement between an official representing the
Irrigation and Power Department (I&P Department), Government of Punjab and the
villagers Committee, whose names have been inscribed below in their presence and
full consent.

NESPAK-ABB-DMC

205

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Sr. No.
of
Village

Village

Updating Feasibility Study for R&U Suleimanki Barrage

Name (Two from each


Village)

1.

Fathers Name
1.
2.

2.

1.
2.

3.

1.
2.

4.

1.
2.

5.

1.
2.

6.

1.
2.

7.

1.
2.

8.

1.
2.

9.

1.
2.

2. We the committee of village leader/elders have agreed unanimously to nominate


_______________________ S/O ______________________ as our Chairman and
authorize him to enter into an SFA with I&P on our behalf. We understand and
pledge that this SFA will be a binding on us and I&P throughout the currency of the
construction work as well as the operational phase.

NESPAK-ABB-DMC

206

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Signatures or Thumb Impression (TI) of the Chairman and the Members of the Villagers
Committee.
Sr.
No.

Name

Signatures/TI

1
2
3
4
5
6
7
8
9
10

3. By mutual consent it is agreed that I&P Department


i)

Shall not occupy any agriculture land or acquire any other land during the
construction of the project.

ii) Shall not cause any damage or reduction in the water supply in the canals during
the construction period of the project, except in case of force majeure e.g. high
floods, strong storms or any other act of God
iii) Shall not cause any disturbance to the wildlife, wetland, archeological heritage or
a place of worship
iv) Shall not interfere in the social political or tribal balance of the area.
v) Shall wherever possible, facilitate better services and supplies to the area e.g.
schooling, health, awareness on epidemic and communicable diseases,
electricity and road/rail communication.

NESPAK-ABB-DMC

207

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

4. Also, by mutual consent it is agreed that all the villagers residing in the area
influencing project (name of the villages listed in para 1 above), collectively and
severally:
i)

Shall not interfere in the location of labour camps, material depots, equipment
yards and all the approach roads to be used during project construction phase,
all of which will be located on the lands of I&P department

ii)

Shall not interfere if the I&P department decides to shift the construction of
works elsewhere on a more suitable site as long as the activity remains on I&P
departments own land

iii) Shall not receive any discharge of water slurry or oil spills to any graveyard or
archaeological site
iv) Shall not cause any damage to wildlife or forest resources of any wildlife reserve
and no villagers will be involved in killing, poaching or illegal hunting
v) Shall not allow reduction or official interference in our existing services and
facilities e.g. education, health, electricity, water supply, religious and social
congregations
vi) Agree that in case the contractor wishes to obtain some material from the private
lands or wishes to make use of any piece of land outside the I&P department
land that would invoke a new agreement between the villagers and the contractor
and I&P department or Govt. of the Punjab shall not be involved in that in any
way
vii) Agree to respect and observe the cautions on the sign boards displayed by
project authorities and shall not remove or cause to be removed any signboards
or installations put up by I&P or their representatives

(Add more conditions if required as per the prevailing circumstances).

This SFA has been signed this ________________ day of ______________, at __________

NESPAK-ABB-DMC

208

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Signatures

Signatures

Resident Engineer

Chairman Villagers Committee

(Full name and address)

(Name and Address)

Counter signed

Signature
Designated Official of I&P, Punjab
(full name and address)

NESPAK-ABB-DMC

209

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Table 8.2: Public Consultation


Sr. No

Meeting Place

Date

No. of Participants

Main Concern

Replies

The benefits from the project to the Protection from flood, Leakage of
local community

water through the gates will be

Arriving of possibly 1000 labour minimize and so there will be more


from other part of the country may water in canals
adversely impact the social life and Job
At the Barrage
1

opportunities

to

the

local

the local women movement in the community

(in the restaurant 11/7/09

10

area

area)

It was clarified that strict discipline


would be exercised on the labour
force to restrict the possibility of
any moral issues or spread of
communicable diseases.
Wildlife habitat adversely impacted It has been ensured to the local
due to the construction activities and community
illegally fishing by the outside labour

Local

Fishing

Department office

11/7/09

that

maximum

employment will be offered to the


local community
All fishing, wildlife and forest laws
are fully respected and abide by the
contractor and his work force

NESPAK-ABB-DMC

210

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Wildlife habitat adversely impacted It was explained that all the wildlife,

Wildlife

due to the construction activities

Department
3

Office

at 11/7/09

forestry &

fishry laws

implemented

on

site

will
to

be

avoid

adversely affecting the wildlife and

Suleimanki

flora of the area

Barrage

Extra burden on existing services It was explained that due sinology


e.g.

health

facility,

electricity etc

education, and traffic management plan would


be put into operation to minimise

Worries were expressed by the local the disruption of traffic. Regular


community regarding the extended spraying

of

water

would

be

canal closure during construction undertaken to minimize the dust


phase.
Chak Abdalka
4

Union
Jhindhka

Council 16/11/09

10

pollution.

Projects heavy traffic may damage It was clarified that due measures
the roads and kacha paths of the will be taken that canal will run as
area

per usual programme with no effect


on the discharge volume and will

Possible impact of water logging close only during routine annual


due to alteration in water level in closure
result of project activities
It was explained that there will be
no change in pond
therefore

NESPAK-ABB-DMC

inundation

water level,
or

water

211

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

logging will not be the issue due to


implementation of the project
The spillway channel area fall in The idea of developing the length
public park and wetland

of the spillway fall in wildlife public


park

area

as

lake

was

appreciated very much and agreed


that this will enhance the bioHead
5

Office

Wildlife
Departmen
Lahore

at

diversity of the area by the Wildlife


19/02/10

Department.
It was ensured that the wildlife,
Forestry & fishery rules & laws will
be implemented during design and
construction phase of the project to
minimize the adverse impacts on
the ecology of the area.

NESPAK-ABB-DMC

212

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Appendices

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

APPENDIX-2.1
NATIONAL ENVIRONMENTAL QUALITY
STANDARDS

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Appendix 2.1
National Environemntal Quality Standards

Determinant

Limit

Temperature

40 deg Centigrade

pH

6 and <10 pH

BOD

80 mg/l

Chemcial Oxygen Demand (COD)

150 mg/l

Total Suspended Solid (TSS)

200 mg/l

Total Dissolved solids

3500 mg/l

Grease and Oil

10 mg/l

An-ionic detergents (as MBAS)

20 mg/l

Ammonia

40 mg/l

Chlorine

1.00 mg/l

Chloride

1000 mg/l

Sulphate

600 mg/l

Manganese (Mn)

1.50 mg/l

Chromium (Cr)

1.00 mg/l

Copper (Cu)

1.00 mg/l

Lead (Pb)

0.50 mg/l

Mercury (Hg)

0.01 mg/l

Selenium (Se)

0.50 mg/l

Nickel (Ni)

1.00 mg/l

Silver (Ag)

1.00 mg/l

Zinc (Zn)

5.00 mg/l

Barium (Ba)

1.50 mg/l

Iron (Fe)

8.00 mg/l

Chlorine

1.00 mg/l

Phenol Compounds

0.1mg/l

Cyanide (Cn)

1.0mg/l

Cadmium (Cd)

0.1mg/l

Arsenic (As)

1.0mg/l

Total Toxic Metal

2.0mg/l

Boron

6.00mg/l

NESPAK-ABB-DMC

213

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

APPENDIX-3.1
CONSTRUCTION SCHEDULE

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Appendix 3.1
Construction Schedule

NESPAK-ABB-DMC

214

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

APPENDIX-4.1
SAMPLING PROCEDURE AND TEST RESULTS

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Monitoring Report
Environmental Assessment at Sulemanki Barrage

Our Ref.: Env-Lhr-435/09


Monitoring Date: November 10 to November 11, 2009

For

Environmental Services SGS Pakistan (Pvt) Ltd.

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

List of Contents
1.

Introduction
1.1. Sampling Location
1.2. Study Objectives
1.3. Scope of Services
1.3.1. Ambient Air Quality Monitoring
1.3.2. Noise Level Monitoring
1.3.3. Water Sampling
1 . 3. 3 . 1 A n a l y s i s P a r a m et e r s :

1.4. Work Plan

2.

Methodology
2.1. Ambient Air Quality
2.1.1. Sampling and Analysis of Particulate Matter

2.2. Meteorological Conditions


2.3. Noise Level Monitoring
2.4. Sampling of Ground and Surface Water
2.4.1. Sample Preservation
2.4.2 Sample Identification and Chain of Custody
2.4.3 Analysis Methods

3.

Results and Discussion

NESPAK-ABB-DMC

215

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

List of Tables:
Table 1: Ground Water
Table 2: Surface Water
Table 3: Work Plan
Table 4: Methodology of Ambient Air Quality Monitoring
Table 5: Summary of Special Handling Requirements for Ground / Surface Water Samples
Table 6: Methods Used for Analysis
Table 7: Average Obtained Concentrations of Priority Pollutants

NESPAK-ABB-DMC

216

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

List of Figures:
Figure 1: Project Location
Figure 2: Sampling Location
Figure 3: Ambient Air Quality Monitoring
Figure 4: Noise Level Monitoring at Irrigation
Figure 5: Noise Level Monitoring at Sulamanki Barrage
Figure 6: Ground Water Sampling from Haveli Lakha
Figure 7: Surface Water Sampling from Right Under Sluice

NESPAK-ABB-DMC

217

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

List of Annexes:
Annexure I

Meteorological Data

Annexure II

Ambient Air Quality Monitoring Data

Annexure III

Noise Level Monitoring Data

Annexure IV

Ground Water Analysis Report

Annexure V

Surface Water Analsyis Report

Annexure VI

Standards

NESPAK-ABB-DMC

218

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

1.

Updating Feasibility Study for R&U Suleimanki Barrage

Introduction

National Engineering Services Pakistan (Pvt) Limited (NESPAK) is one of the leading
engineering consultancies of the Pakistan. NESPAK is conducting project for
rehabilitation and up gradation of Sulemanki barrage funded by Asian Development Bank.
Services of SGS Pakistan (Pvt) Ltd were engaged to develop baseline of the project site
and surroundings. This report is prepared on the basis of field survey carried out from
November 10 to 11, 2009 for ambient air quality, weather conditions, noise level
monitoring, ground and surface water sampling from advised locations.
1. 1.

Sampling Location

The project location for Sulemanki barrage rehabilitation and up gradation is given as
Fi gu r e 1. The site selected for ambient air quality and noise level monitoring was at

Sulemanki Barrage. The monitoring was carried out at the selected sites for the duration of
24 hrs. Water samples were collected from advised sampling locations in order to
determine the water quality of the area. Three surface water samples were collected from
right under sluice, left under sluice and BS link fall into the Sutlj River respectively.
Ground water sample was collected from the village located in the vicinity of the project
site. The photographs of the sampling is given in Fi g ur e 6 an d 7.

NESPAK-ABB-DMC

219

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Figure:1 Project Location

NESPAK-ABB-DMC

220

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Figure:2 Sampling Location

NESPAK-ABB-DMC

221

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

1.2.

Study Objectives

The main objective of the study was to monitor ambient air quality, recording sound level
and analyze the ground and surface water samples to examine the environmental
conditions and water quality of the project site and its surroundings. The obtained data is
compared with standards attached as Annexure- VI of the report.

1.3.

Scope of Services

Scope of services covered following main components:




Ambient Air Quality Monitoring

Weather Conditions

Noise Level Monitoring

Ground Water Sampling and Analysis

 Surface Water Sampling and Analysis

1.3.1.

Ambient Air Quality Monitoring

In accordance to USEPA National Ambient Air Quality standards the following priority
pollutants would be monitored in the ambient air of the study area:


Carbon Monoxide (CO)

Nitrogen Dioxide (NO2)

Sulfur Dioxide (SO2)

Particulate Matter (PM1 0 )

In addition to above mentioned parameters, the weather conditions were also monitored in
order to interpret ambient air quality. For the purpose following parameters would be
monitored:


Ambient Temperature

Relative Humidity

Barometric Pressure

Wind Direction

Wind Velocity

NESPAK-ABB-DMC

222

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

1.3.2.

Updating Feasibility Study for R&U Suleimanki Barrage

Noise Level Monitoring

Noise level using portable digital sound meter was monitored at following advised sites:


At Barrage

Irrigation Colony

1.3.3

Water Sampling

Water samples were collected from advised sampling points and were submitted to SGS
chemical and microbiological labs for analysis according to parameters as per contract.
1.3.3 .1

Ana l ysi s Pa ramete rs:

The collected water samples were analyzed for following list of parameters according to US
EPA and APHA approved methods.
Table1:GroundWater
Test Type

Physical

Parameter

Odor
Color
Taste

NESPAK-ABB-DMC

Chemical

Total Dissolved Solids


(TDS)
Total Suspended
Solids (TSS)
Ca Hardness
Mg Hardness
Nitrate
Electrical Conductivity
(EC)
Chloride (Cl)
Sulphate
Turbidity
Fluoride
Nickel
Manganese
Zinc
Copper
Chromium
Mercury
Lead
Silver
Selenium
Barium
Magnesium
Iron
Sodium Absorption
Ratio (SAR)
Residual Sodium
Carbonate (RSC)

Biological

Total Colonial Count


Total Coliforms
Fecal E. Coli
Fecal Enterococci

223

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Table 2: Surface Water

Test Type

Parameter

Physical

Chemical

Biological

Odor
Color
Taste

Electrical Conductivity
(EC)
Total Dissolved Solids
(TDS)
Total Suspended Solids
(TSS)
Nitrate
Grease & Oil
Chloride (Cl)
Sulphate
Turbidity
Fluoride
Magnesium
Iron
Nickel
Manganese
Zinc
Copper
Chromium
Mercury
Lead
Silver
Selenium
Barium
BODs
COD
Sodium Absorption Ratio
(SAR)
Residual Sodium
Carbonate (RSC)

Total Colonial Count


Total Coliforms
Fecal E. Coli
Fecal Enterococci

NESPAK-ABB-DMC

224

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

1.4.

Work Pla n

In order to cover the above scope of work, following schedule was planned and followed:
Table 3: Work Plan
Monitoring
Haveli
Lakha
Sr.#

Intervention Date

Activity
Sulemanki
Barrage

Irrigation
Colony

and Sampling
Location
Right Under
Sluice

Left Under
Sluice
Just After the
BS Link Fall
into Sutlj River

Environmental Assessment at Sulemanki Barrage


1

Nov.10 to Nov.11,2009

Ambient Air
Quality
Monitoring

Nov.10 to Nov.11,2009

Weather
Conditions

Nov.10 to Nov.11,2009

Noise Level
Monitoring

Nov.11 ,2009

Ground Water
Sampling

Nov.11,2009

Surface Water

NESPAK-ABB-DMC

225

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

2.

Methodology

Following is the brief description of methodology adapted for this environmental


assessment:
2.1.

A m b i e n t Air Q u al i ty

Ambient air quality was monitored with the help of Mobile Air Quality Station equipped
with the state of the art ambient air analyzers.

Figure 3: Ambient Air Quality Monitoring at Suleimanki Barrage

Selection of sampling points was made considering the wind direction at the advised
sampling sites. The methodology adopted for ambient air quality monitoring is as follows:

NESPAK-ABB-DMC

226

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Table 4: Methodology of Ambient Air Quality Monitoring


Air
Pollutant
Carbon
Monoxide
(CO)

Monitoring Technique

Measurement
Range

Method

Gas Filter Correlation CO


Analyzer

USEPA
Designated
Method RFCA0981-054

Pulsed Fluorescent
Analyzer

USEPA
Designated
Method EQSA0486-060

0 50 ppb
0 1000 ppm

USEPA
Designated
Method RFNA1289-074

0 50 ppb
0 1000 ppm

Sulfur
Dioxide
(SO2 )
Nitrogen
Dioxide
(NO2 )

Chemiluminescent
Analyzer
High Volume Sampler

Particulate
Matter
(PM1 0)

40 CFR 50,
App. B
(US-EPA)

0 100

Lowest
Detection
Limit
0.01 ppm

1 ppb

1 ppb

2 750 g/m3

2 g/m3

2.1.1. Sampling and Analysis of Particulate Matter


Particulate matter concentration in terms of
the help of high Volume

PM10

PM10

was monitored in the ambient air with

Sampler. Reference method used for

PM10

determination in ambient air is 40 CFR 50, Appendix J (USEPA).


Air sample for detection of

PM10

concentration was drawn on fiberglass filter paper and

then the collected sample was preserved in protective holder which was transported to
SGS lab for further analysis under standard environmental conditions.
2.2.

Meteorological Conditions

In addition to the advised parameters for ambient air quality, weather conditions were
also monitored continuously for 24 hours with the help of mobile weather station.
Selection of sampling points was made considering the wind direction at the advised
sampling site.

NESPAK-ABB-DMC

227

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

2.3.

Noise Level Monitoring

Noise level was monitored at the advised sampling points for 24 hours with interval of 1
second and hourly average data is reported. The sound level was monitored with the help
of potable Digital sound meter (RION, Model NL 31, IEC60051 TYPE 1 IE60804 TYPE 1
JIS C 1505).

Figure4: Noise Level Monitoring at Irrigation


Colony

Figure5:Noise Level Monitoring at


Sulemanki Barrage

Noise level measurement was performed according to standard operating procedures.


2.4.

Sampling of Ground and Surface Water

One ground and three surface water samples were collected from advised sampling
points in the surroundings of the project site. Water samples were collected according to
the SOP based on the recognized methods of United State Environmental Protection
Agency (USEPA) and American Public Health Administration (APHA) for water sampling
and analysis.

NESPAK-ABB-DMC

228

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

2.4.1. Sample Preservation


The collected water samples were preserved in appropriate containers as per APHA
guidelines. A shipping container (Ice box with eutectic cold packs instead of ice) with
maintained temperature of 4 C 5 C was used for transporting the samples from the
collection site to the analytical laboratory.

NESPAK-ABB-DMC

229

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Table 5: Summary of Special Handling Requirements for Ground / Surface Water


Samples

Minimum
Determination

Container

Maximum Storage
Preservation

Sample
Size (ml)

BOD5

P, G

1000

COD

P, G

100

Recommended /
Regulatory

REFRIGERATE @ 4 oC

06 HRS / 48 DAYS

REFRIGERATE @ 4 oC ANALYZE
07 DAYS / 28 DAYS
ASAP OR ADD H2SO4 TO pH <2
CHLORINE, Residual

P, G

500

ANALYZE IMMEDIATELY

0.5 HR / 02 HRS

COLOR

P, G

500

REFRIGERATE

48 HRS / 48 HRS

CONDUCTIVITY

P, G

500

REFRIGERATE

28 DAYS / 28 DAYS

FLUORIDE

300

NONE REQUIRED

28 DAYS / 28 DAYS

ADD H2SO4 TO pH < 2,

G, wide mouth
1000

GREASE & OIL


calibrated
HARDNESS

P, G

METALS, General

P (A), G (A)

28 DAYS / 28 DAYS
REFRIGERATE

100

ADD HNO3 TO pH < 2

06 MON / 06 MON

FOR DISSOLVED METALS


-

06 MON / 06 MON
FILTER IMMEDIATELY

Mercury

P (A), G (A)

500

P, G

500

ADD HNO3 TO pH < 2.4 C

28 DAYS / 28 DAYS

ANALYZE ASAP OR ADD H2SO4

Nitrogen
Ammonia

07 DAYS / 28 DAYS
TO pH < 2, REFRIGERATE
ANALYZE ASAP OR

Nitrate

P, G

100

REFRIGERATE, OR FREEZE AT

48 HRS / 48 HRS

20 C
ADD H2SO4 TO pH < 2,
Nitrate + Nitrite

P, G

NONE / 28 DAYS

200
REFRIGERATE
ANALYZE ASAP OR

Nitrite

P, G

100

REFRIGERATE, OR FREEZE AT

NONE / 48 HRS

20 C

NESPAK-ABB-DMC

230

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Minimum
Determination

Container

Maximum Storage
Preservation

Sample
Size (ml)

Odor

pH

P, G

Solids

500

Recommended /
Regulatory

ANALYZE ASAP, REFRIGERATE

06 HRS

ANALYZE IMMEDIATELY

02 HRS / 02 HRS

P, G

REFRIGERATE

07 DAYS / 07-14 DAYS

Sulfate

P, G

REFRIGERATE

28 DAYS / 28 DAYS

Sulfide

P, G

100

REFRIGERATE, ADD 4 DROPS 2N


28 DAYS / 28 DAYS
ZINC ACETATE
Temperature

P, G

Turbidity

P, G

ANALYZE IMMEDIATELY

-/-

ANALYZE SAME DAY, STORE IN


48 HRS / 48 HRS
DARK UP TO 24 HRS

P : Plastic Container G
: Glass Bottle

2.4.2

Sample Identification and Chain of Custody

The collected water samples were labeled and assigned a unique sample identification
number, sampling date and time of collection to collected samples. All the relevant
information (sampling location, time of collection, sample identification, temperature, pH,
collected by, preservation techniques etc) was recorded immediately on the Chain of
Custody form signed by SGS field Analyst.

NESPAK-ABB-DMC

231

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

2.4.3

Analysis Methods

The collected ground and surface water samples were analyzed according to following
methods:
Table 6: Methods Used for Analysis
Sr.#

Parameter

Method / Technique

1 Temperature

Thermometer

2 pH

pH meter with 2 point calibration

Reference Method
USEPA, APHA

3 Chemical Oxygen Demand (COD) Wet chemistry


4 Biological Oxygen Demand (BOD5) Wet chemistry / Incubation

ASTM

5 Total Suspended Solids (TSS)

Wet chemistry/Air oven

ASTM

6 Total Dissolved Solids (TDS)

Wet chemistry/Digital determinator

7 Grease & Oil

Solvent extraction

8 Phenolic Compounds (as phenol)

Colourimetry

USEPA, APHA

9 Chloride

Wet chemistry

USEPA, APHA

10 Fluoride

Ion selective/colourimetry

USEPA, APHA

11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

Ion selective / colourimetry


Colourimetry
Wet chemistry
Wet chemistry
Wet chemistry / Ion Selective
AAS
AAS
AAS
AAS
AAS
AAS
AAS
AAS
AAS (Hydride generation)
AAS
AAS
Ion Selective
Spectrophotometer

USEPA, APHA
USEPA, APHA
APHA
ASTM
ASTM
USEPA, APHA
USEPA, APHA
USEPA, APHA
USEPA, APHA
USEPA, APHA
USEPA, APHA
USEPA, APHA
APHA
ASTM
ASTM
USEPA, APHA
USEPA, APHA
USEPA, APHA

Titrimitery

USEPA, APHA
APHA

Cyanide
Anionic detergents
Sulphate
Sulphide
Ammonia
Cadmium
Chromium
Copper
Lead
Mercury
Nickel
Silver
Zinc
Arsenic
Iron
Manganese
Nitrates
Turbidity

29 Dissolved Oxygen
30 Chlorine

Wet chemistry

APHA

USEPA, APHA
ASTM

APHA= American Public Health Association


ASTM=American Society for Testing and Materials
USEPA=United State Environmental Protection Agency

NESPAK-ABB-DMC

232

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

3.

Results and Discussion

Monitoring of ambient air quality, weather, noise level and water quality was carried out at
advised sampling points. The monitoring results are given in Annexure I to V. The results
of ambient air quality monitored for 24 hrs are given in Annexure II of the report. USEPA
(United State Environmental Protection Agency) and Draft National Environmental Quality
Standards (NEQS) of Pak EPA for ambient air quality were used for comparison. The
copy of USEPA and Pak-EPA ambient air quality standards is attached as Annexure VI
of the report. The average concentration of carbon monoxide (CO) for 8 hrs according to
the USEPA standard should not exceed from 9ppm while for Pak EPA 5 mg/m3. The
levels obtained at monitoring site for 24 hrs averages were 3.19 ppm and 3.98 mg/m3
which lie well within the limits specified in both the standards for CO. Similarly average
concentrations of nitrogen dioxide and sulphur dioxide was found at 8.48 ppb (29.18
g/m3) and 5.15ppb (14.72 g/m3) respectively which are well within the limits defined in
USEPA and Pak-EPA standards. The 24 hrs average particulate matter
found to be 117.32 g/m

against standards value of 150 g/m

was

PM10

for USEPA and 250

g/m3 for Pak-EPA standard.

Table7:AverageObtainedConcentrationsofPriorityPollutants
Average
Parameter

Unit

Obtained

Average
Unit

Concentration

Obtained

Duration

Concentration

Nitrogen Dioxide (NO2 )

ppb

8.48

g/m

29.18

24Hours

Sulfur Dioxide (SO2 )

ppb

5.15

g/m

14.72

24 Hours

3.98

24 Hours

117.32

24 Hours

Carbon Monoxide (CO)


Particulate Matter (PM1 0 )

ppm
3

g/m

3.19

mg/m

117.32

g/m

Noise level monitoring was conducted at sulamanki barrage and irrigation colony. Results
were attached as Annexure III of the report. The noise level was found in range of 43.4
62.7 dB (Le q . ) .

NESPAK-ABB-DMC

233

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

One ground water and three surface water samples were collected from advised sampling
points. The water samples were analyzed for chemical and microbiological parameters.
The WHO drinking water guidelines are given in Annexure VI of the report. Microbiological
analysis results of both ground and surface water samples show rich microbial
contamination which makes them unfit for human consumption. The results of ground
water analysis were attached as Annexure-IV while that of surface water are attached
Annexure V. All the parameters of ground water sample lie within the limits specified in

WHO guidelines except turbidity, lead and iron content which shows higher concentrations
than the values defined in WHO limits for drinking water. However, it is anticipated that the
concentration of turbidity and iron are high due to assimilation of soil in ground water.
Surface water samples were analyzed according to NEQS parameters. All the parameters
lie within the limits specified in NEQS for surface water. Results were attached as
Annexure-V of the report.

NESPAK-ABB-DMC

234

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Annexure I

Meteorological Data

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Meteorological Data
:
:
:

Client
Sampling Point
Date of Intervention

Time
13:00
14:00
15:00
16:00
17:00
18:00
19:00
20:00
21:00
22:00
23:00
24:00
01:00
02:00
03:00
04:00
05:00
06:00
07:00
08:00
09:00
10:00
11:00
12:00

Temp
OC
26
25
23
23
19
17
15
14
14
14
13
13
13
13
11
10
9
9
8
12
16
22
23
25

NESPAK (Pvt) Ltd.


Sulemanki Barrage
November 10 11, 2009

Wind Dir
E
SW
N
NW
S
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
SW
E
SE
SE
SW
SW
SW

Wind Speed
m/s
2.2
2.0
1.7
0.9
3.7
1.9
1.7
1.1
0.5
0.8
0.4
0.9
0.9
0.9
0.4
0.4
0.9
0.4
2.7
0.4
0.8
2.2
2.5
2.4

Hum
%
42
44
45
45
49
52
57
60
60
62
68
68
69
69
75
74
78
79
80
74
56
44
36
48

Pressure
756.7
756.5
756.5
756.1
755.9
755.7
755.5
755.1
755.2
755.1
754.8
754.6
754.3
754.2
754.0
754.1
754.2
754.4
754.9
754.9
755.2
755.1
754.8
754.6

NESPAK-ABB-DMC

235

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Annexure II

Ambient Air Quality Monitoring Data

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Ambient Air Quality


:
:
:

Client
Sampling Point
Date of Intervention

NESPAK (Pvt) Ltd.


Sulemanki Barrage
November 10 236, 2009

S r. #

T ime

CO (ppm)

NO
(ppb)

NO2
(ppb)

NOX
(ppb)

SO2
(ppb)

13:00

2.6

10.12

8.09

18.21

3.21

14:00

2.2

12.72

4.58

17.30

3.17

15:00

3.1

10.32

9.77

20.09

4.20

16:00

2.7

12.40

13.61

26.01

5.17

17:00

4.2

19.21

5.15

24.36

9.48

18:00

4.3

12.27

17.26

29.53

9.58

19:00

4.0

13.57

6.97

20.54

8.17

20:00

3.8

8.01

4.92

12.93

7.12

21:00

3.6

6.49

4.81

11.30

5.82

10

22:00

3.4

4.80

14.8

19.60

5.30

11

23:00

4.0

10.07

153.31

25.38

4.91

12

24:00

3.3

11.40

5.03

16.43

4.96

13

01:00

3.1

6.08

9.89

15.97

4.62

14

02:00

3.0

6.57

11.64

18.21

4.57

15

03:00

3.0

6.92

5.08

12.00

5.04

16

04:00

2.9

3.75

5.18

8.93

4.30

17

05:00

2.9

2.80

3.52

6.32

3.83

18

06:00

2.8

2.23

7.85

10.08

3.04

19

07:00

2.7

3.83

4.33

8.16

3.52

20

08:00

2.7

2.65

9.66

12.31

2.85

21

09:00

4.3

4.81

12.87

17.68

4.49

22

10:00

2.9

7.70

9.91

17.61

5.51

23

11:00

2.6

7.10

5.34

12.44

5.96

24

12:00

2.5

5.18

8.03

13.21

4.74

NESPAK-ABB-DMC

236

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Client
Sampling Point
Date of Intervention

Ambient Air Quality


: NESPAK (Pvt) Ltd.
: Sulemanki Barrage
: November 10 27, 2009
Average Obtained

Parameter

Unit

Duration

LDL
Concentration

Nitrogen Dioxide (NO2)

ppb

24Hours

0.01

8.48

Sulfur Dioxide (SO2)

ppb

24 Hours

0.01

5.15

Carbon Monoxide (CO)

ppm

24 Hours

1.0

3.19

Particulate Matter (PM10)

g/m3

24 Hours

117.32

g/m3: micrograms per cubic meter


ppm:

parts per million

ppb:

parts Per billion

LDL:

Lowest Detection Limit

NESPAK-ABB-DMC

237

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Client
Sampling Point
Date of Intervention

Ambient Air Quality


: NESPAK (Pvt) Ltd.
: Sulemanki Barrage
: November 10 28, 2009

Time

CO
(mg/m3)

NO
(g/m3)

NO2 (g/m3)

NOx
(g/m3)

SO2 (g/m3)

13:00

3.25

13.56

16.58

30.14

9.18

14:00

2.75

17.045

9.39

26.44

9.07

15:00

3.87

13.83

20.03

33.86

12.01

16:00

3.37

16.6

27.90

44.50

14.79

17:00

5.25

25.74

10.56

36.30

27.11

18:00

5.37

16.44

35.38

51.82

27.40

19:00

5.00

18.18

14.29

32.47

23.37

20:00

4.75

10.73

10.09

20.82

20.36

21:00

4.50

8.70

9.86

18.56

16.64

10

22:00

4.25

6.43

30.34

36.77

15.16

11

23:00

5.00

13.50

314.29

327.79

14.04

12

24:00

4.12

15.28

10.31

25.59

14.19

13

01:00

3.87

8.15

20.27

28.42

13.21

14

02:00

3.75

8.80

23.86

32.66

13.07

15

03:00

3.75

9.27

10.41

19.68

14.41

16

04:00

3.625

5.02

10.62

15.64

12.30

17

05:00

3.62

3.75

7.22

10.97

10.95

18

06:00

3.50

2.99

16.09

19.08

8.69

19

07:00

3.37

5.13

8.88

14.01

10.07

20

08:00

3.37

3.55

19.80

23.35

8.15

21

09:00

5.37

6.44

26.38

32.82

12.84

22

10:00

3.62

10.32

20.31

30.63

15.76

23

11:00

3.25

9.51

10.95

20.46

17.05

24

12:00

3.12

6.94

16.46

23.40

13.56

Sr. #

NESPAK-ABB-DMC

238

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Client
Sampling Point
Date of Intervention

Ambient Air Quality


: NESPAK (Pvt) Ltd.
: Sulemanki Barrage
: November 10 29, 2009
Average

Parameter

Unit

Duration
Concentration

Nitrogen Dioxide (NO2)

g/m

24 Hours

29.18

Sulphur Dioxide (SO2)

g/m3

24 Hours

14.72

Carbon Monoxide (CO)

mg/m3

24 Hours

3.98

PM

g/m3

24 Hours

117.32

10

g/m : micrograms per cubic meter


mg/m3: milligrams per cubic meter
LDL:
Lowest Detection Limit

NESPAK-ABB-DMC

239

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Annexure III

Noise Level Monitoring Data

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Noise Level Monitoring


Client
Sampling Point
Date of Intervention

:
:
:

NESPAK (Pvt) Ltd.


Sulemanki Barrage
November 10 11, 2009

Leq(dB)

Lmax(dB)

Lmin(dB)

13:00

60.2

65.1

54.1

14:00

62.7

67.4

56.2

15:00

58.1

64.0

52.1

16:00

60.2

68.2

56.0

17:00

55.5

62.3

50.3

18:00

56.0

60.1

53.1

19:00

53.1

59.2

50.0

20:00

54.7

59.0

51.1

21:00

53.4

58.2

49.2

10

22:00

54.0

62.1

50.0

11

23:00

49.1

57.2

43.7

12

24:00

52.1

58.0

49.1

13

01:00

51.0

59.3

47.3

14

02:00

55.2

63.7

52.4

15

03:00

53.7

60.2

49.7

16

04:00

50.0

58.0

46.0

17

05:00

50.2

57.4

45.1

18

06:00

53.0

62.2

49.2

19

07:00

56.1

64.0

53.4

20

08:00

60.4

67.1

55.1

21

09:00

59.2

68.7

56.7

22

10:00

57.0

65.3

54.2

23

11:00

57.3

64.0

55.3

24

12:00

55.1

63.2

54.0

Sr. #
1

Time

NESPAK-ABB-DMC

240

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Noise Level Monitoring


Client

NESPAK (Pvt) Ltd.

Graph 1: - Variation of Noise with Time

NESPAK-ABB-DMC

241

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Noise Level Monitoring


Client
Sampling Point
Date of Intervention
Sr. #

Time

:
:
:

NESPAK (Pvt) Ltd.


Irrigation Colony
November 10 11, 2009

Leq(dB)

Lmax(dB)

Lmin(dB)

13:00

60.0

65.0

53.0

14:00

62.1

67.1

55.2

15:00

55.7

62.0

57.0

16:00

52.3

60.7

48.3

17:00

59.4

63.9

53.0

18:00

57.0

64.5

52.5

19:00

55.3

59.2

47.2

20:00

49.2

55.1

46.0

21:00

57.2

60.3

57.3

10

22:00

46.1

52.2

44.4

11

23:00

44.0

50.5

42.0

12

24:00

44.7

51.3

40.1

13

01:00

43.4

50.2

39.7

14

02:00

47.5

52.7

41.0

15

03:00

45.4

53.1

40.5

16

04:00

52.2

57.0

45.0

17

05:00

54.0

59.1

49.7

18

06:00

58.1

63.0

50.0

19

07:00

60.3

64.3

52.1

20

08:00

62.2

65.7

53.3

21

09:00

59.1

63.0

50.0

22

10:00

57.3

60.1

49.2

23

11:00

59.2

62.1

53.7

24

12:00

61.1

64.0

56.2

NESPAK-ABB-DMC

242

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Graph 2: - Variation of Noise with Time

NESPAK-ABB-DMC

243

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Annexure IV

Ground Water Analysis Report

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

M I C R O B I O L O G I C A L ANALYSIS REPORT

Env Lhr 435 / 2009


Job No :
Client Name & Account :
Description Of Sample :
Marking (If Any) :

NESPAK (Pvt) Ltd.


Ground Water
Hand Pump near
Mosque

No. of sample :

01

Sample Condition Upon Receipt:

Satisfactory

Sample Collection Date :

11-11-09

Environmental Conditions:

Temperature :

Humidity:

NA

Sr. #

Parameters

Procedure

NA

Permissible

Results

Limits
01
02

Total Colony Count


Total Coli Forms

APHA:9215

< 500 cfu / ml

APHA:9222 B

0 / 1 00ml

APHA:9222 B

0 / 1 00ml

39

APHA: 9230 C

0 / 1 00ml

18

TNTC

67

Faecal
03
Coli Forms (E.Coli)
Faecal
04
Streptococci/ Enterococci

cf u : co lo ny formin g un it

N OT E:
WHO/USEPA Guidelines for Drinking Water states that T o t a l or F a e c a l Coli
forms m u st be ab se nt a n d ar e not t o l e r a t e d in Potab le w at er.

NESPAK-ABB-DMC

244

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

CHEMICAL LABORATORY
TEST REPORT

Env Lhr 435 / 2009


Job No :
Client Name & Account :
Description Of Sample :
Marking (If Any) :

NESPAK (Pvt) Ltd.


Ground Water
Hand Pump near
Mosque

No. of sample :

01

Sample Condition Upon Receipt:

Satisfactory

Sample Collection Date :

11-11-09

Environmental Conditions:

Temperature :

Humidity:

NA

Sr. #

Parameters

NA

LDL

Test
Results

WHO
Guidelines

Method

Unit

01 Color

Visual

Pale Yellow

02 Odor

Organoleptic

Odorless

03 Turbidity

APHA-2130 B

NTU

0.2

27

04 Conductivity

APHA-2150 B

0.1

594

5 NTU
-

05

Total Dissolved Solids


(TDS)

APHA-2540 C

mg/L

5.0

415

06

Total Suspended Solids


(TSS)

APHA-2540 D

mg/L

5.0

34

1000

07 Calcium Hardness

APHA-2340 B & C

mg/L

0.5

183.15

08 Magnesium Hardness

APHA-2340 B & C

mg/L

0.5

66.80

09 Magnesium

APHA-3500Mg B

mg/L

0.5

16.3

10 Chloride (Cl)

APHA-4500Cl- B

mg/L

0.5

21

250

11 Sulfate (SO4)

APHA-4500SO4 C

mg/L

5.0

35

250

12 Nitrates (NO3)

APHA-4500NO3 B

mg/L

0.003

5.3

50

13 Fluoride (F)

APHA - F- C

mg/L

0.01

1.2

1.5

14

Sodium Absorption Ratio


(SAR)

15 Residual Sodium Carbonate


(RSC)

NESPAK-ABB-DMC

In-House

In-House

10.46

ND

mg/L

245

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Sr. #

Parameters

Method

Unit

Test

WHO

Results

Guidelines

LDL

16

Chromium (Cr)

APHA-3500Cr B

mg/L

0.01

<0.01

0.05

17

Copper (Cu)

APHA-3500Cu B

mg/L

0.01

<0.01

1.0 2.0

18

Lead (Pb)

APHA-3500Pb B

mg/L

0.01

0.02

0.01

19

Mercury (Hg)

APHA-3500-Hg B

mg/L

0.001

<0.001

0.001

20

Selenium ( Se )

APHA-3500Se C

mg/L

0.01

<0.01

21

Nickel (Ni)

APHA-3500-Ni B

mg/L

0.01

0.02

0.02

22

Silver (Ag)

APHA-3500Ag B

mg/L

0.1

<0.1

23

Zinc (Zn)

APHA-3500Zn B

mg/L

0.01

<0.01

3.0
0.3

24

Iron (Fe)

APHA-3500Fe B

mg/L

0.01

2.50

25

Barium ( Ba)

APHA-3500Ba B

mg/L

0.5

<0.5

26

Manganese (Mn)

APHA-3500Mn B

mg/L

0.01

0.41

27

Chlorine

APHA-4500Cl G

mg/L

0.1

<0.1

LDL:

Lowest Detection Limit

<:

Less Than.

0.1 0.5
-

Not Defined

This r e ort is not valid f o r any negotiation.

The remaining ortion of the sam l e (s) will be dis osed off after one week unless otherwise instruct.

The sam le(s) to which the findings recorded herein ( t h e Findings) relate was (were) drawn and / o r rovided by the
p
p
p
Client or by a third arty acting at the Clients direction. The Findings constitute no waranty of the sam les re resentativeness
p
p
p
of any goods and strictly relate to the sam le(s). The Com any acce ts no liablity with regard to the origin o r source from
p
which the sam le(s) is/are said to be extracted.

NESPAK-ABB-DMC

246

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Annexure V

Surface Water Analysis Report

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

MICROBIOLOGICALANALYSISREPORT

J o b No:
ClientName&Account :
DescriptionOfSample:

EnvLhr435/2009
N E S P A K (Pvt)Ltd.
SurfaceWater

Marking(IfAny):

Righ tUnderSluice

SampleConditionUponReceipt:

Satisfactory

EnvironmentalConditions:

Temperature:

NA

Sr . #

Param e ters

Pr oc e d ure

Perm iss ibl e

Results

L i m i ts
01

Total Colony Count

APHA:9215

02

Total Coli Forms

APHA:9222 B

< 500 cfu / ml

0 / 100ml

1985

57

Faecal
03

APHA:9222 B

0 / 100ml

30

APHA: 9230 C

0 / 100ml

10

Coli Forms (E.Coli)


Faecal
04
Streptococci/ Enterococci

c f u : c o l o n y f o r m i n g u n i t

NESPAK-ABB-DMC

247

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

MICROBIOLOGICALANALYSISREP O RT

J o b No:
ClientName&Account :
DescriptionOfSample:

EnvLhr435/2009
N E S P A K (Pvt)Ltd.
SurfaceWater

Marking(IfAny):

Righ tUnderSluice

SampleConditionUponReceipt:

Satisfactory

EnvironmentalConditions:

Temperature:

NA

Sr . #

Pa ram e ters

Pr oc edure

Perm iss ibl e

R es ults

L i m i ts
01

Total Colony Count

APHA:9215

02

Total Coli Forms

APHA:9222 B

0 / 100ml

70

APHA:9222 B

0 / 100ml

37

APHA: 9230 C

0 / 100ml

16

< 500 cfu / ml

2392

Faecal
03
Coli Forms (E.Coli)
Faecal
04
Streptococci/ Enterococci

c f u : c o l o n y f o r m i n g u n i t

NESPAK-ABB-DMC

248

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

MICROBIOLOGICALANALYSISREP O RT

J o b No:
ClientName&Account :
DescriptionOfSample:

EnvLhr435/2009
N E S P A K (Pvt)Ltd.
SurfaceWater

Marking(IfAny):

Righ tUnderSluice

No.ofsample:

01

SampleConditionUponReceipt:

Satisfactory

SampleCollectionDate:

111109

EnvironmentalConditions:

Temperature:

Humidity:

NA

NA

S r . #

P a r a m e ter s

Proc edur e

P er miss i ble

R es ul ts

Li mits
01

Total Colony Count

APHA:9215

02

Total Coli Forms

APHA:9222 B

0 / 100ml

23

APHA:9222 B

0 / 100ml

13

APHA: 9230 C

0 / 100ml

< 500 cfu / ml

967

Faecal
03
Coli Forms (E.Coli)
Faecal
04

Streptococci/ Enterococci

c f u : c o l o n y f o r m i n g u n i t

NESPAK-ABB-DMC

249

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

CHEMICALLABORATORY
TESTREPORT

J o b No:
ClientName&Account:
DescriptionOfSample:

EnvLhr435/2009
N E S P A K (Pvt)Ltd.
SurfaceWater

Marking(IfAny):

RightUnd erSluice

No.ofsample:

01

SampleConditionUponReceipt:

Satisfactory

SampleCollectionDate :

111109

EnvironmentalConditions:

Temperature:

Humidity:

NA

NA

Test
Sr.#

P a r a m e te r s

Method

U ni t

LDL

01

Odor

Organoleptic

02

Turbidity

APHA-2130 B

NTU

03

Conductivity

APHA-2150 B

04

Biochemical Oxygen
Demand ( BOD5 )

05

Chemical Oxygen Demand


(COD)

APHA-5220 D

06

Total Suspended Solids


(TSS)

07

Total Dissolved Solids


(TDS)

08

Chloride ( Cl )

09

Limitsas

R e s u l ts p e r NE Q S

Odorless

0.2

21

0.1

420

5.0

80.00

mg/L

5.0

12

150.00

APHA-2540 D

mg/L

5.0

28

200.00

APHA-2540 C

mg/L

5.0

273

3500.00

APHA-4500Cl- B

mg/L

0.5

31.98

1000.00

Sulphate ( SO4 )

APHA-4500 SO4 C

mg/L

5.0

34.78

600.00

10

Nitrates (NO3)

APHA-4500NO3 B

mg/L

0.003

1.4

11

Fluoride ( F)

APHA - F- C

mg/L

0.01

0.33

12

Sodium Absorption Ratio


(SAR)

In-House

mg/L

14.77

13

Residual Sodium Carbonate


(RSC)

In-House

mg/L

ND

14

Magnesium

APHA-3500Mg B

mg/L

0.5

9.0

15

Grease & Oil

USEPA-1664

mg/L

1.0

<1.0

10.00

NESPAK-ABB-DMC

ASTM 5210

mg/L

10.00

250

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

CHEMICALLABORATORY
TESTREPORT

Test
Sr.#

P a r a m e te r s

Method

U ni t

L i m i ts a s

LDL
R e s ul ts p e r NE Q S

16

Chromium (Cr)

APHA-3500Cr B

mg/L

0.01

<0.01

01.00

17

Copper (Cu)

APHA-3500Cu B

mg/L

0.01

<0.01

01.00

18

Lead ( Pb )

APHA-3500Pb B

mg/L

0.01

0.02

00.50

19

Mercury ( Hg)

APHA-3500Hg B

mg/L

0.001

<0.001

00.01

20

Selenium ( Se )

APHA-3500Se C

mg/L

0.01

<0.01

00.50

21

Nickel ( Ni )

APHA 3500 Ni B

mg/L

0.01

<0.01

01.00

22

Silver ( Ag )

APHA-3500Ag B

mg/L

0.1

<0.1

01.00

23

Zinc ( Zn )

APHA-3500Zn B

mg/L

0.01

0.02

05.00

24

Barium ( Ba)

APHA-3500Ba B

mg/L

0.5

<0.5

01.50

25

Iron ( Fe )

APHA-3500Fe B

mg/L

0.01

0.54

8.00

26

Manganese ( Mn )

APHA-3500Mn B

mg/L

0.01

0.02

01.50

27

Chlorine

APHA-4500Cl G

mg/L

0.1

<0.1

1.00

LDL:

Lowest Detection Limit

-:

Not Defined

<:

Less Than.

NESPAK-ABB-DMC

251

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

CHEMICALLABORATORY
TESTREPORT

J o b No:
ClientName&Account:
DescriptionOfSample:

EnvLhr435/2009
N E S P A K (Pvt)Ltd.
SurfaceWater

Marking(IfAny):

LeftUnderSluice

No.ofsample:

01

SampleConditionUponReceipt:

Satisfactory

SampleCollectionDate :

111109

EnvironmentalConditions:

Temperature:

Humidity:

NA

NA

Test
Sr.#

P a r a m e te r s

Method

U ni t

LDL

01

Odor

Organoleptic

02

Turbidity

APHA-2130 B

NTU

03

Conductivity

APHA-2150 B

04

Biochemical Oxygen
Demand ( BOD5 )

05

Limitsas

R e s u l ts p e r NE Q S

Odorless

0.2

22

0.1

438

ASTM 5210

mg/L

5.0

80.00

Chemical Oxygen Demand


(COD)

APHA-5220 D

mg/L

5.0

20

150.00

06

Total Suspended Solids


(TSS)

APHA-2540 D

mg/L

5.0

30

200.00

07

Total Dissolved Solids


(TDS)

APHA-2540 C

mg/L

5.0

280

3500.00

08

Chloride ( Cl )

APHA-4500Cl- B

mg/L

0.5

34.88

1000.00

09

Sulphate ( SO4 )

APHA-4500 SO4 C

mg/L

5.0

44.86

600.00

10

Nitrates (NO3)

APHA-4500NO3 B

mg/L

0.003

1.7

11

Fluoride ( F)

APHA - F- C

mg/L

0.01

0.36

12

Sodium Absorption Ratio


(SAR)

In-House

mg/L

15.04

13

Residual Sodium Carbonate


(RSC)

In-House

mg/L

ND

14

Magnesium

APHA-3500Mg B

mg/L

0.5

9.96

15

Grease & Oil

USEPA-1664

mg/L

1.0

<1.0

10.00

NESPAK-ABB-DMC

10.00

252

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

CHEMICALLABORATORY
TESTREPORT

Test
Sr.#

P a r a m e te r s

Method

U ni t

Limitsas

LDL
R e s u l ts p e r NE Q S

16

Chromium (Cr)

APHA-3500Cr B

mg/L

0.01

<0.01

01.00

17

Copper (Cu)

APHA-3500Cu B

mg/L

0.01

<0.01

01.00

18

Lead ( Pb )

APHA-3500Pb B

mg/L

0.01

0.02

00.50

19

Mercury ( Hg)

APHA-3500Hg B

mg/L

0.001

<0.001

00.01

20

Selenium ( Se )

APHA-3500Se C

mg/L

0.01

<0.01

00.50

21

Nickel ( Ni )

APHA 3500 Ni B

mg/L

0.01

0.02

01.00

22

Silver ( Ag )

APHA-3500Ag B

mg/L

0.1

<0.1

01.00

23

Zinc ( Zn )

APHA-3500Zn B

mg/L

0.01

0.02

05.00

24

Barium ( Ba)

APHA-3500Ba B

mg/L

0.5

<0.5

01.50

25

Iron ( Fe )

APHA-3500Fe B

mg/L

0.01

0.62

8.00

26

Manganese ( Mn )

APHA-3500Mn B

mg/L

0.01

0.02

01.50

27

Chlorine

APHA-4500Cl G

mg/L

0.1

<0.1

1.00

LDL:

Lowest Detection Limit

<:

Less Than.

NESPAK-ABB-DMC

Not Defined

ND:

Not Detected

253

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

CHEMICALLABORATORY
TESTREPORT

JobN o :
ClientName&Account:
D e s c r i pt i o n O f S a m pl e :
Marking( I f Any):

EnvLhr435/2009
NESPAK(Pvt)Ltd.
SurfaceWater

S a m pl e C o n d i t i o n U po n R e c e i pt :

Satisfactory

EnvironmentalConditions:

JustaftertheB S link No.o f sam le:


f a l intoSutlijRiver
p

Tem erature:

NA

01

S a m pl e C o l e c t i o n D a t e :

111109

Humidity:

NA

Test
Sr.#

P a r a m e te r s

Method

U ni t

LDL

01

Odor

Organoleptic

02

Turbidity

APHA-2130 B

NTU

03

Conductivity

APHA-2150 B

04

Biochemical Oxygen
Demand ( BOD5 )

05

Limitsas

R e s u l ts p e r NE Q S

Odorless

0.2

41

0.1

352

ASTM 5210

mg/L

5.0

10

80.00

Chemical Oxygen Demand


(COD)

APHA-5220 D

mg/L

5.0

21

150.00

06

Total Suspended Solids


(TSS)

APHA-2540 D

mg/L

5.0

48

200.00

07

Total Dissolved Solids


(TDS)

APHA-2540 C

mg/L

5.0

219

3500.00

08

Chloride ( Cl )

APHA-4500Cl- B

mg/L

0.5

23.26

1000.00

09

Sulphate ( SO4 )

APHA-4500 SO4 C

mg/L

5.0

29.64

600.00

10

Nitrates (NO3)

APHA-4500NO3 B

mg/L

0.003

0.9

11

Fluoride ( F)

APHA - F- C

mg/L

0.01

0.39

12

Sodium Absorption Ratio


(SAR)

In-House

mg/L

11.47

13

Residual Sodium Carbonate


(RSC)

In-House

mg/L

ND

14

Magnesium

APHA-3500Mg B

mg/L

0.5

9.37

15

Grease & Oil

USEPA-1664

mg/L

1.0

<1.0

10.00

NESPAK-ABB-DMC

10.00

254

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Test
Sr.#

P a r a m e te r s

Method

U ni t

Limitsas

LDL
R e s u l ts p e r NE Q S

16

Chromium (Cr)

APHA-3500Cr B

mg/L

0.01

<0.01

01.00

17

Copper (Cu)

APHA-3500Cu B

mg/L

0.01

<0.01

01.00

18

Lead ( Pb )

APHA-3500Pb B

mg/L

0.01

0.04

00.50

19

Mercury ( Hg)

APHA-3500Hg B

mg/L

0.001

<0.001

00.01

20

Selenium ( Se )

APHA-3500Se C

mg/L

0.01

<0.01

00.50

21

Nickel ( Ni )

APHA 3500 Ni B

mg/L

0.01

0.02

01.00

22

Silver ( Ag )

APHA-3500Ag B

mg/L

0.1

<0.1

01.00

23

Zinc ( Zn )

APHA-3500Zn B

mg/L

0.01

0.02

05.00

24

Barium ( Ba)

APHA-3500Ba B

mg/L

0.5

<0.5

01.50

25

Iron ( Fe )

APHA-3500Fe B

mg/L

0.01

0.94

8.00

26

Manganese ( Mn )

APHA-3500Mn B

mg/L

0.01

0.04

01.50

27

Chlorine

APHA-4500Cl G

mg/L

0.1

<0.1

1.00

LDL:

Lowest Detection Limit

-:

Not Defined

<:

Less Than.

NESPAK-ABB-DMC

255

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Annexure VI

Standards

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

USEPA National Ambient Air Quality Standard


FollowingarethelimitsspecifiedinNAAQSforprimaryaswellassecondarypollutants.

POLLUTANT

STANDARD

STANDARD

VALUE *

TYPE

Carbon Monoxide (CO)


8-hour Average

9 ppm

(10 mg/m 3 )

Primary

1-hour Average

35 ppm

(40 mg/m 3 )

Primary

(100 g/m 3 )

Primary & Secondary

Nitrogen Dioxide (NO2)


Annual Arithmetic Mean

0.053 ppm

Ozone (O3)
1-hour Average

0.12 ppm

(235 g/m 3 )

Primary & Secondary

8-hour Average

0.08 ppm

(157 g/m 3 )

Primary & Secondary

Lead (Pb)
1.5 g/m 3

Quarterly Average

Primary & Secondary

Particles with diameters of 10 micrometers or less


Particulate (PM 10)
Annual Arithmetic Mean

50 g/m 3

Primary & Secondary

24-hour Average

150 g/m 3

Primary & Secondary

Particulate (PM 2.5)

Particles with diameters of 2.5 micrometers or less

Annual Arithmetic Mean

15 g/m 3

Primary & Secondary

24-hour Average

65 g/m 3

Primary & Secondary

Sulfur Dioxide (SO2)


0.030 ppm

(80 g/m 3 )

Primary

24-hour Average

0.14 ppm

(365 g/m 3 )

Primary

3-hour Average

0.50 ppm

(1300 g/m 3 )

Secondary

Annual Arithmetic Mean

NESPAK-ABB-DMC

256

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Draft National Environmental Quality Standards (NEQS) for Ambient Air


Concentration in Ambient Air

Pollutants

Time-weighted
average

Annual
Average*
Sulphur
Dioxide (SO2 ) 24 hours**

Oxides of
Nitrogen as
(NO)
Oxides of
Nitrogen as
(NO2 )
O3

Annual
Average*

Method of measurement
Effective
from 1st
January
2012

80 g/m3

80 g/m3

120 g/m3

120 g/m3

40 g/m3

40 g/m3

Ultraviolet Fluorescence
method

Gas Phase Chemiluminescence


24 hours**
Annual
Average*

40 g/m

40 g/m3

40 g/m

40 g/m3
Gas Phase Chmiluminescence

24 hours**
1 hour

Annual
Suspended Average*
Particulate
Matter (SPM) 24 hours**
Annual
Average*

Respirable
Particulate
Matter PM1 0 24 hours**
Respirable
Particulate

Effective from
1st January
2009

80 g/m3

80 g/m3

180 g/m3

130 g/m3

Non Dispersive UV absorption


method

400 g/m3

360 g/m3

High Volume Sampling,


(Average flow rate not less than
1.1 m3/minute).

550 g/m3

500 g/m3

200 g/m3

120 g/m3

Ray absorption method


250 g/m

150 g/m

Annual
Average*

25 g/m3

15 g/m3

24 hours**

40 g/m3

35 g/m3

1 hour
Annual
Average*

25 g/m3

15 g/m3

Ray absorption method

Matter. PM 2 . 5
1.5 g/m3

1 g/m3

Lead (Pb)
24 hours**
2 g/m3
Carbon
Monoxide
(CO)

8 hours **
1 hour

ASS Method after sampling


using EPM 2000 or equivalent
Filter paper

1.5 g/m3

5 mg/m3

5 mg/m3

10 mg/m3

10 mg/m3

Non Dispersive Infra Red


(NDIR) method

*Annual arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at
uniform interval.
** 24 hourly /8 hourly values should be met 98% of the in a year. 2% of the time, it may exceed but not
on two consecutive days.

NESPAK-ABB-DMC

257

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

Drinking Water Guidelines


Maximum permissible limits as defined by Various Countries
S/No

Parametric Tests *

EEC

Canada

USEPA

WHO

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38

Aluminum
Ammonium
Antimony
Arsenic
Barium
Boron
Cadmium
Chloride
Chromium
Coliforms, total /1 00ml
Coliforms,E.Coli/1 00ml
Color
Copper
Cyanide
Fluoride
Hardness
Iron
Lead
Manganese
Mercury
Molybdenum
Nickel
Nitrate/Nitrite, total
Nitrates(NO 3)
Nitrites(NO2)
Odor
pH
Phosphorous
Phenols
Potassium
Selenium
Silica Dioxide(SiO 2)
Silver
Solids, Total dissolved
Sodium
Sulfate
Turbidity(Non-microbial)
Zinc

0.2
0.5
0.01
0.05
NS
NS
0.005
25
0.05
0
0
20 Pt-Co
NS
0.05
0.7 - 1 .5
50
0.2
0.05
0.2
0.001
NS
0.05
NS
50
0.1
NS
6.2 - 8.5
5.0
0.0005
12
0.01
10
0.01
NS
75 -150
NS
4 JTU
NS

NS
NS
NS
0.025
1 .0
5.0
0.005
250
0.05
0
0
15cu
1. 0
0.2
1 .5
NS
0.3
0.01
0.05
0.001
NS
NS
NS
10 as N
3.2
NS
6.5 - 8.5
NS
0.002
NS
0.01
NS
0.05
500
NS
500
1 NTU
5.0

0.05 - 0.20
NS
0.006
0.05
2.0
NS
0.005
250
0.1
0
0
15cu
1. 0
0.2
2.0-4.0
NS
0.3
0.015
0.05
0.002
NS
0.1
10.0 as N
10.0 as N
1 .0 as N
3 TON
6.5 - 8.5
NS
NS
NS
0.05
NS
0.1
500
20
250
0.5 - 5.0 NTU
5.0

0.2
1.5
0.005
0.01
0.7
0.3
0.003
250
0.05
0
0
15cu
1 - 2
0.07
1.5
NS
0.3
0.01
0.1- 0.5
0.001
0.07
0.02

NS
50
3
NS
6.5 - 8.5
NS
NS
NS
0.01
NS
NS
1000
200
250
5 NTU
3.0

Abbreviations/Explanations:
NS=NoStandards|JTU=JacksonTurbidityUnits|NTU=NephelometricTurbidityUnits
cu=ColorUnits
|MPNColiforms,TotalorE.Coli/100ml|PtCo=PlatiniumCobalt
Standards|EEC=EuropeanEconomicCommunityforEnvironmentalLegislationUSEPA=
UnitedStatesEnvironmentalProtectionAgency|TON=ThresholdOdorNumber
mg/l(milligramsperlitre)exceptwherenotified
*

NESPAK-ABB-DMC

258

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

AnnexI(amended)

NATIONALENVIRONMENTALQUALITYSTANDARDSFORMUNICIPAL
ANDLIQUIDINDUSTRIALEFFLUENTS(mg/l,UNLESSOTHERWISEDEFINED)
S.No. Parameter

1 .Temperature or Temperature Increase*


2.pH value
3.Biochemical Oxygen Demand (BOD)5
0 (1)
at 20 C
4.Chemical Oxygen Demand (COD) (1)
5.Total suspended solids (TSS)
6.Total dissolved solids (TDS)
7.Grease and oil
8.Phenolic compounds (as phenol)

9.Chloride (as Cl )
10.Fluoride (as F)

11 .Cyanide (as CN ) total


12.An-ionic detergents (as MBAs) (2)
4
13.Sulphate (SO )

14.Sulphide (S )
15.Ammonia (NH3)
16.Pesticides (3)
17.Cadmium (4)
(4)
1 8.Chromium (trivalent and hexavalent)
19.Copper (4)
20.Lead (4)
21.Mercury (4)
22.Selenium (4)
23.Nickel (4)
24.Silver (4)
25.Total Toxic metals
26.Zinc
27.Arsenic (4)
28.Barium (4)
29.Iron
30.Manganese
31 .Boron (4)
32.Chlorine

Existing
Standards

Into Inland
Waters

Revised Standards
(6)
Into Sea
Into Sewage
(5)
Treatment

40 C
6-10
80

<3 C
6-9
80

<3 C
6-9
250

<3 C
6-9
**
80

150
150
3500
10
0.1
1000
20
2
20
600
1.0
40
0.15
0.1
1.0
1.0
0.5
0.01
0.5
1.0
1.0
2.0
5.0
1.0
1.5
2.0
1.5
6.0
1.0

150
200
3500
10
0.1
1000
10
1.0
20
600
1.0
40
0.15
0.1
1.0
1.0
0.5
0.01
0.5
1.0
1.0
2.0
5.0
1.0
1.5
8.0
1.5
6.0
1.0

400
400
3500
10
0.3
1000
10
1.0
20
1000
1.0
40
0.15
0.1
1.0
1.0
0.5
0.01
0.5
1.0
1.0
2.0
5.0
1.0
1.5
8.0
1.5
6.0
1.0

400
200
3500
10
0.3
***
SC
10
1.0
20
***
SC
1.0
40
0.15
0.1
1.0
1.0
0.5
0.01
0.5
1.0
1.0
2.0
5.0
1.0
1.5
8.0
1.5
6.0
1.0

Explanations:

1.

2.
3.
4.
5.

Assuming minimum dilution 1:10 on discharge, lower ratio would attract progressively stringent standards to be
determined by the Federal Environmental Protection Agency. By 1:10 dilution means, for example that for each one cubic
meter of treated effluent, the recipient water body should have 10 cubic meter of water for dilution of this effluent.
Modified Benzene Alkyl Sulphate; assuming surfactant as biodegradable.
Pesticides include herbicides, fungicides, and insecticides.
Subject to total toxic metals discharge should not exceed level given at S.No.25.
Applicable only when and where sewage treatment is operational and BOD5=80 mg/l is achieved by the sewage treatment
system.
Provided discharge is not at shore and not within 10 miles of mangrove or other important estuaries.

NESPAK-ABB-DMC

259

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

Updating Feasibility Study for R&U Suleimanki Barrage

APPENDIX-4.2

WATER QUALITY GUIDELINES AND STANDARDS

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage

260

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage

261

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage

262

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage

263

Updating Feasibility Study for R&U Suleimanki Barrage


Environmental & Social Impact Assessment

NESPAK-ABB-DMC

Updating Feasibility Study for R&U Suleimanki Barrage

264

You might also like