OBSERVATIONS
LP ROTOR
1. Minor rubbing on moving blades shroud fins and inter stage fins of stages 1 to 4 .- TO
BE LEFT AS IT IS.
2. Rubbing also observed in 5th stage blades tips(TS) TO BE DEBURRED AND CLEANED.
3. LPT rotor front 4th stage shroud gap (maximum 2 mm in one blade) NO GAP AT THE
CENTRE ZONE OF THE Z TYPE BLADE SHROUD. IT IS IN LINE WITH THE SPECIFICATION AT
THE CENTRE. MAXIMUM ALLOWABLE LIMIT IS 1.4 MM, HOWEVER IN THE OPINION OF
BHEL HWR, IT IS NOT GOING TO AFFECT THE PERFORMANCE.
2. HPT dismantling is under progress. Action Plan will be decided based on the
observations.
Root Cause Analysis by BHEL of LP Casing shifting to right side needs to be clearly
brought out to prevent repetition with support of BHEL-Haridwar.
Observations and protocols handed over to BHEL.
SCHEDULE
BHEL gave a schedule of 4 weeks and NTPC insisted on completing the job in 3
weeks.
BHEL agreed to check back at works and confirm based on the availability of LPT
casing blades.
MEMBERS PRESENT
NTPC
BHEL