Professional Documents
Culture Documents
5
Present Worth Analysis
1.Present Worth Analysis
The PW is always less than the actual cash flow for any interest rate greater than
zero because all P/F factors have a value <1, therefore, present worth values are
often referred to as discounted cash flows, DCF.
The interest rate is referred to as the discount rate.
Extensions of PW are also covered:
o Future worth
o Capitalized cost
o Payback period
o Life-cycle costing and
o Bond analysis
Some projects are economically and technologically viable and others are not.
Once the viable projects are defined, it is possible to formulate alternatives.
Each project may be categorized as:
o Mutually exclusive. Only one of the projects can be selected, not both.
Each project is a stand-alone, viable alternative. These alternatives
compete with one another.
o Independent. More than one viable project may be selected by the
analysis. These alternatives do NOT compete with one another. The
comparison is between one project at a time and the do nothing
alternative. If there are m projects, zero, 1, 2 or more projects may be
selected yielding 2m mutually exclusive projects. If there are 3
independent alternatives, 23=8 possibilities exist: DN, A, B, C, AB, AC,
BC, ABC.
o DN, the do nothing alternative is usually understood to be an alternative
unless specifically excluded.
All the alternatives evaluated in one particular engineering economy study must
be of the same type.
o Revenue. Each alternative generates cost and revenue cash flow estimates
and possibly savings. Revenues are dependent upon which alternative is
selected.
o Service. Each alternative has only cash flow estimates. Revenues are NOT
dependent upon the alternative selected, so these cash flows are assumed
to be equal. Service evaluations may be legally mandated such as cutting
down sidewalk curbs for wheelchairs or safety considerations such as belts
and airbags.
In present worth analysis, the P value, now called PW, is calculated at the MARR,
minimum attractive rate of return, for each alternative.
The PW method is popular because future costs are transformed into equivalent
dollars now, which is straightforward. If both alternatives are used in identical
capacities for the same time period, they are termed equal-service alternatives.
A PW analysis requires a MARR for use as the i value in all PW relations.
Guidelines:
o One alternative. Calculate PW at the MARR. If PW0, the requested
MARR is met or exceeded and the alternative is financially viable.
o Two or more alternatives. Calculate the PW of each alternative at the
MARR. Select the alternative with the PW value that is numerically
largest, that is, less negative or more positive, indicating a PW of cost cash
flows or larger PW or net cash flows of receipts minus disbursements.
For one or more independent projects, select all projects with PW0 at the
MARR. This compares each project with the do nothing alternative.
Example p.5.1, p. 173.
Given: A civil engineering firm is considering 2 automobiles for company executives. The US model costs
$22,000, costs $2000 per year to operate and has a salvage value of 12 grand after 3 years. The Japanese
model is $26,000, cost $1200 per annum to operate and will be worth $15,000 after 3 years. Interest is 15%
per year.
Find: Which is the better deal?
PWus = -22,000 2000(P/A,15%,3) + 12,000(P/F,15%,3) =
PWus = -22,000 2000(2.2832) + 12,000(.6575)
PWus = $-18,676
PWjap = -26,000 1200(P/A,15%,3) + 15,000(P/F,15%,3) =
PWjap = -26,000 1200(2.2832) + 15,000(.6575)
PWjap = $-18,877
The US model is the better deal, lower cost.
Given: A chemical engineer is considering two styles of pipes for moving an alcoholic distillate from a
refinery to my wet bar. A small pipeline will be less to purchase but higher to operate, costing $1.7M and
$12,000/month to operate. The larger one costs $2.1M but only $9,000/month to operate. Interest is
1%/month. Assume a 10-year comparison period and a salvage value of 10%
Find: Which is the better deal?
PWsmall = -1,700,000-12,000(P/A,1%,120) + 170,000(P/F,1%,120)
PWsmall = -1,700,000-12,000(69.7005) + 170,000(.3030)
PWsmall = $-2,484,896
PWlarge= -2,100,000-9,000(P/A,1%,120) + 210,000(P/F,1%,120)
PWlarge = -2,100,000-9,000(69.7005) + 170,000(.3030)
First cost, $
Annual Cost, $/yr
Salvage, $
Life, years
PW
Land Application
-110,000
-95,000
15,000
3
$-525,506
Incineration
-800,000
-60,000
250,000
6
$-918,000
Contract
0
-190,000
0
2
$-719,055
The future worth, FW, may be determined directly by calculating the future worth
value or by multiplying the PW by F/P at the MARR. Therefore, FW is an
extension of PW analysis.
The n value in F/P depends upon which time period was used to determine PW:
the LCM value or a specified study period.
FW is useful when:
o Applicable to large capital investment decisions when a prime goal is to
maximize the future worth of stock.
o If the asset might be sold at some time after its start-up but before the
expected life is reached. FW value at an intermediate year estimates the
alternatives worth at the time of sale.
o Projects that will not come online until the end of the investment period
such as electrical generation, toll roads or hotels.
FW0 means the MARR is met or exceeded for one alternative. For two or more
mutually exclusive alternatives, select the one with the numerically largest FW
value.
Example 5.3, p.178
Given: The machines listed wrap candy. Interest is 20% per year.
Machine C
First cost, $
-40,000
Annual Cost, $/yr
-10000
Salvage, $
12000
Life, years
3
Find: Which machine should be selected on the basis of FW?
Machine D
-65,000
-12,000
25,000
6
3. Find the equivalent uniform annual, A, through one life cycle of all
recurring amounts. Add this to all other uniform amounts in years 1
through infinity. The result is a total AW.
4. Divide the AW by i to obtain CC.
5. Add the CC values in steps 2 and 4 for a total.
For the comparison of two or more alternatives, the alternative with the smaller
capitalized cost will represent the more economical one.
As in PW, it is only the difference in cash flow between the alternatives that must
be considered for comparative purposes. Whenever possible, the calculations
should be simplified by eliminating the elements of cash flow which are common
to both alternatives.
To determine capitalized cost for an alternative with a finite life, calculate the
equivalent A value for one life cycle and divide by the interest rate.
Examples 5.4, 5.5 and 5.6 p. 180.
Given: An alternative has a first cost of $32,000, an annual maintenance cost of $6000, a salvage value of
$8000 after its 4-year life and interest is 14% per year.
Find: What is the capitalized cost?
Find AW through one life cycle, then divide by i.
AW = -32,000(A/P,14%,4)-6000+8000(A/F,14%,4)
AW = -32,000(.34320)-6000+8000(.20320)
AW = $-15,356.80
CC = Pwcap=$-15,356.80/.14
CC = $-109,691
Given: An investment of $10,000/year for 100 years and an investment of $10,000/year forever at an
interest rate of 10% per year.
Find: Whats the difference.
PW100 = 10,000(P/A,10%,100) = 10,000(9.9993)
PW100 = $99,993
CC = Pwcap/i = 10,000/.01
CC = $100,000
Difference = $100,000-$99,993
Difference = $7
Given: Interest at 10%
Machine V
First cost, $
-50,000
Annual Cost, $/yr
-30,000
Salvage, $
10,000
Life, years
10
Find: Compare the alternatives on the basis of CC.
First find AW for V and divide by i.
AWv = -50,000(A/P,10%10)-30,000+10,000(A/F,10%,10)
AWv = -50,000(.16275)-30,000+10,000(.06275)
AWv = $-37,510
CCv = -37,510/.10
Machine W
-500,000
-1,000
500,000
o It neglects all net cash flows after time np including positive cash flows
that may contribute to the return of the investment.
Examples 5.7, 5.8 p. 187
Automatic
-90,000
-15,000
20
30,000
Find: Which alternatives should be retained. Alternatives must have a payback of 5 years, i=0% and i=10%
A.0%
Semiautomatic
n=40,000/10,000
n=4 years
Automatic
n=90,000/15,000
n=6years
Retain Semiautomatic
B.10%
Semiautomatic
0=-40,000+10,000(P/A,10%,n)
(P/A,10%,n)=4.0
From 10% table
Np = 5.4 years
Automatic
0 = -90,000+ 15,000(P/A,10%,n)
(P/A,10%,n) = 6.0
From 10% table
Np = 9.6 years
Neither alternative
Given: An ANCO imaging system costs $10,000 with a salvage value of $900 after 5 years. The system is
expected to save $1700/year.
Find: The payback time at 8% per annum. The manager wants a payback time of 6 years or less should
they go for it.
Set up a PW relationship, then us T&E or a spreadsheet for np.
0 = -10,000 + 1700(P/A,8%,n) + 900(P/F,8%,5)
np = 7.7 years
Do NOT purchase.
maintenance costs i.e. post-purchase costs such as labor, energy, upkeep and
materials.
LCC is required for most defense and aerospace industries where LCC is called
Design to Cost. LCC is usually not applied to public sector projects.
LCC may be divided into acquisition and operations:
o Acquisition: Definition of requirements, preliminary design, detailed
design.
o Operations: Construction, Usage, Phase out.
o
Given: A medium sized town plans to develop software that they will use for project selection for the next
10 years.
Find: Use life cycle analysis to identify the best alternative at 10% per year.
Alternative
Cost Component
Cost
A
Development
$100,000 now,
$150,000 year 1
Programming
$45,000 now, $35,000
year 1
Operation
$50,000/year, 1-10
Support
$30,000/year, 1-10
B
Development
10,000 now
Programming $45,000 year 0, $30,000
year 1
Operation
$80,000, 1-10
Support
$40,000, 1-10
C
Operation
$150,000, 1-10
PWA = -145,000-185,000(P/F,10%,1)-80,000(P/A,10%,10)
PWA = -145,000-185,000(.9091)-80,000(6.1446)
PWA = $-810,752
PWB = -55,000-30,000(P/F,10%,1)-120,000(P/A,10%,10)
PWB = -55,000-30,000(.9091)-120,000(6.1446)
PWB = $-819,625
PWC = -150,000(P/A,10%,10)
PWC = $-921,690
Alternative A
Given: A $50,000 bond that has quarterly interest payments of $1500 and a 20 year maturity rate.
Find: What is the bond interest rate?
i==
1500 = 50,000b/4
B=12% per year, payable quarterly
Given: A retiring engineer plans to buy a $50,000 bond that has an interest rate of 14% per year payable
semi-annually and maturity date 20 years from now. The rate now is 14%/per year compounded
semiannually.
Find: How much should he be able to sell the bond for in 15 if the market rate then is 8% compounded
semiannually. Secondly, if he did sell the bond after 15 years and if he earned a return of 10% per year,
compounded semiannually, on all his bond interest receipts, how much money would he have immediately
after he sold the bond.
The cost of the bond now is $50,000 because the bond interest rate and market interest rate are the same. In
15 years, there are 5 years of interest left, so sales price will be the PW then PW15.
i = 50,000(.14)/2
i = 3500 every 6 months
PW15 = 3500(P/A,4%,10)+ 50,000(P/F,4%,10)
PW15 = 3500(8.1109)+ 50,000(.6756)
PW15 = $62,168
F is the amount earned from bond interest payments+amount received from the sale of bond in part a.
F = 3500((F/A,5%,30)+62,168
F = $294,704