Professional Documents
Culture Documents
for individual projects. Discussion at training courses in Europe is confirming that most contracts
using 1999 FIDIC Contracts include the provision for an independent DAB, particularly contracts
under the MDB version and other contracts with provisions for international finance. Obviously
there are cost implications but the indications are that the cost of a DAB is less than the cost of a
lengthy dispute with other resolution procedures, including legal and other costs.
CONTRACTOR'S OBLIGATIONS
QUESTION
I am an engineer and I am involved in a litigation case where FIDIC was incorporated in a wood
waste power plant contract. It would be easier if the case is referred to arbitration where the
arbitrator is normally a person well verse in engineering contract and engineering matters.Normal
litigationtrial judge will be difficult to fathom the implications of each conditions contained in the
FIDIC. I was looking for legal cases to support my argument that under an engineering contract
involving a power plant, the performance and reliability of the power plant is clearly defined. The
plant will be accepted when it passes a performance test to show that the plant can generate
contract capacity and a 30 days non failed reliability run. As the operation of wood waste plant is
primitive and can easily go wrong unless it is operated with care. Any power plant can be easily
damaged if out of specification fuel is used. Because of this, the contractor is not required to
guarantee that the plant can produce the rated capacity throughout the defects liability period
which in this case is two years. Lawyers like to refer to pass cases as reference for their argument. I
feel that if can find some judgement in arbitration or litigation to show that performance test and
reliability run are sufficient to prove that the plant had complied to specification a large part of
litigation time can be saved. I am sure since the introduction of FIDIC in 1957 until now this kind of
argument should have been concluded, except I am unable to locate such case law easily. I would be
most grateful if you could shed some light on this matter and at the same time guide me to some
sites that I can get this information.
ANSWER
The FIDIC Conditions of Contract for Plant and Design-Build are very clear, at Clauses 9 to 12, about
the Contractor's obligations for Tests, Handing-Over and during the Defects Liability Period. Further
information for the particular project would be given in the Particular Conditions and the Employer's
Requirements or Specification. However, any additional obligations and the way in which these
documents are interpreted for a particular dispute will depend on the applicable law, which will be
different in different countries. FIDIC are not informed about Arbitral Awards or Judgements by the
Courts. For information about any Arbitral Awards you should consult an Arbitration Centre. The
best source is probably the International Chamber of Commerce in Paris