Professional Documents
Culture Documents
Part C
Appendix G : Doosan Quality Requirement
CONTENTS
1
1.1
1.2
1.3
1.4
1.5
Non-Conformance/Corrective Action.......................................................................................... 4
5.1
5.2
5.3
5.4
5.5
5.6
1.1
2/5
c) The Quality Assurance Plan is a Subcontract specific document covering the scope of the works
which shall clearly embrace the materials, equipment and works to be provided under the project
by Subcontractor, and shall contain but not be limited to the following:
K hoch m bo cht lng l mt ti liu c th ng nh thu ph bao gm cc phm vi ca
cng vic. Ti liu th hin r vt liu, thit b v cng vic c quy nh trong cc d n do
cc nh thu ph, v phi bao gm nhng khng gii hn nh sau:
(a) Description of the scope of the work
Miu t phm vi cng vic
(b) Design control plan
K hoch kim sot thit k
(c)
Quality principles
Nguyn tc cht lng
1.3
Site Detailed Inspection and Test Plan K hoch kim tra th nghim Site
a) The Subcontractor shall submit to the Contractor Site Detailed Inspection and Test Plans for each
system or equipment or any others as required by the Contractor.
Cc nh thu ph phi np cho Nh thu Site Kim tra chi tit v k hoch kim tra cho mi h
thng hoc thit b hoc bt k yu cu khc ca nh thu.
b) Each Site Detailed Inspection and Test Plan shall provide details of the inspection and test to be
performed, procedures and standards to be followed, test equipment and materials to be used,
performance measures and acceptance criteria, etc. These Site Detailed Inspection and Test
Plans should be submitted within two (2) months after the Effective Date of the Subcontract.
c) The Subcontractor shall confirm the location and programmed for each inspection and test at
least forty eight (48) hours in advance of the inspection and test. The Contractor shall inform the
Subcontractor in due time of his decision to attend any of the inspection and test. When the
inspection and test are witnessed by the Contractor or his nominee, the relevant inspection and
test reports shall be countersigned by the Contractor and the Owner or his nominee.
1.4
Test Reports
a) Made and certified copies submitted to the Contractor. Log sheets and any other documents
necessary for these tests shall be provided by the Subcontractor before the testing.
b) A signed legible photocopy of all readings logged during tests, with all corrections, shall be
3/5
c) If the Plant fails during the tests to fulfill the guarantees, the Subcontractor should remedy the
failure and carry out a further series of tests at his own expense.
4/5
Description
2
3
4
5
1P/1E
S/N
6
Required
Description
1P/1E
2P/2E
1P/1E
1P/1E
Required
Due Date
As
As required
Any other documents required by the
required
Contractor
P : Prints/Hard Copy, E : Electronic Copy,
ED : Effective Date of the Subcontract
I : for Information/Reference, A : for Acceptance/Review/Comment, R : for Record
I
A
A
A
Submission
for
A or I
Non-Conformance/Corrective Action
a) The Subcontractor shall be advised by the Contractor of any non-conformances identified by the issue of a
Non-conformance Report or/and any other formal method agreed to by both the Contractor and the
Subcontractor. The Subcontractor shall give a written response to the Contractor about non-conformance.
b) The Subcontractor shall maintain formal records of all non-conformances and their disposition and/or
corrective action taken as well.
Quality Records
a) The Subcontractor shall maintain a system of records, which provide objective evidence that the
requirements of the Subcontract have been met. The Subcontractor shall ensure that Subcontractor's
records pertinent to the Subcontract.
b) All applicable records shall be available for audit and review by the Contractor during the duration of the
Subcontract and for seven (7) years after take-over by the Contractor.
5
5.1
5.2
5.3
5.4
Remedy Cost
The agreed cost upon Subcontract by both parties shall be applied for clearing Outstanding Items. If
there is no agreed cost, the Contractor shall reasonably determine the unit price of clearing
5.5
Penalty of Delay
At the Subcontractors option, either (i) the Subcontractor shall provide the Contractor an bank
guarantee, Outstanding Items Bond which is no less than one hundred and fifty (150) percent of
the agreed cost of Outstanding Items and reasonably accepted by the Contractor, or;
(ii) the Contractor shall make retention from the Subcontract price which is equal to one
hundred and fifty (150) percent of the agreed cost of Outstanding Items until Clearance of
Outstanding Items.
Upon clearance of Outstanding Items, the bank guarantee shall be returned to the
Subcontractor.
The Performing cost for the clearing Outstanding Items will be deducted on progress payment
when the Subcontractor make delay, abandonment or rejection to complete Outstanding Items for
each List Items passed thirty (30) days from first issue date.
5.6