Faculty of Engineering
COURSE CODE
CIVIL4810
LEVEL / SEMESTER
4/1
COURSE TITLE
PROJECT MANAGEMENT
ACADEMIC YEAR
2013-2014
DATE
TIME
09:00 am
DURATION
3 hours
MAXIMUM MARK
100
COURSE COORDINATOR :
STUDENT NAME
STUDENT ID
GROUP NO
INSTRUCTIONS TO CANDIDATES
This question paper consists of 4 pages.
Answer ALL questions as required.
Write your ID, NAME and GROUP NUMBER clearly on all
of your answer books.
Follow all examination rules.
Do not bring books or other related materials into the
examination room.
Page |2
Question 1:
[15 marks]
(a) Explain the project cycle with reference to the following Figure Q1a?
[5 marks]
Figure Q1(a)
(b) An Industrial Joint Venture has to allocate funds for the construction of a six-story factory
building.
[10 marks]
Sr. No.
1
2
3
4
Portion
Ground Floor
Other Floors
Top Floor
Parking
Area (m2)
2600
2375
2375
5075
Building
works (BW)
10.50
9.75
11.25
1.75
Sanitary and
sewerage
7.2% of BW
6.7% of BW
6.9% of BW
3.5% of BW
Page |3
Question 2:
[20 marks]
[6 marks]
Dependence
E, G
G, N, J
J
J, R
F, P, O
T
F, O
Q
V, O
D
A
Duration
5
5
4
3
5
3
5
2
2
5
3
7
Activity
M
N
O
P
Q
R
S
T
U
V
W
X
Dependence
B, X
O
H, T
V, I, O
K, C, D
G
O, Q
G, E
K, D, C
Duration
6
2
2
3
3
1
5
3
5
3
2
3
[7 marks]
[5 marks]
[2 marks]
Question 3:
[25 marks]
(a) What are the technical and sociocultural dimensions of project management process?
[5marks]
(b) On a small construction project, an excavator and hauling truck are purchased at an
interest rate of 3.5% and 3.2%, respectively. The present value of excavator is
13,500 OMR and its scrap value at the end of 9 years is 3,000 OMR. Hauling truck is
purchased for 16,000 OMR and the estimated scrap value after 8 years is 3,300 OMR. So
the total investment on construction equipment is 29,500 OMR.
Use Sum of the years digit method and sinking fund formula, to determine;
(i) Total depreciated cost at the end of 6 years for both the equipment
[10 marks]
[4 marks]
[6 marks]
Page |4
Question 4:
[10 marks]
[5marks]
(b) What are the advantages and disadvantages of Dispute Review Boards?
[5marks]
Question 5:
[30 marks]
For the construction of a small factory, activities, their dependences and durations, along with
the required resources are given below. Due to the local regulations, the number of
resources for each day is limited to 11.
Sr.
No.
1
3
4
5
6
7
8
Procurement of plant
Procurement of suction
pipe
Foundation of Plant
Roof
Procurement of crane
Excavation
Foundation
Masonry
Installation of Plant
10
Fixing of pipes
11
12
13
Commissioning of Plant
Plumbing
Electrification
14
Erection of crane
15
Internal plaster
16
Site clearance
17
18
Flooring
19
External plaster
20
No. of
resource per
day
0
10
Procurement of plant
Masonry
Excavation
Foundation
1. Foundation of Plant
2. Procurement of plant
1. Procurement of suction pipe
2. Internal Plaster
Fixing of Pipes
Internal Plaster
Internal Plaster
1. Procurement of crane
2. Roof
Roof
1. Flooring
2. External Plaster
1. Flooring
2. External Plaster
1. Commissioning of Plant
2. Plumbing
Roof
3
5
16
2
3
13
3
5
0
4
5
4
2
2
4
3
4
3
Activity
Dependence
Duration
[8 marks]
[8 marks]
[14 marks]