Professional Documents
Culture Documents
In the Beginning
TERMINATIONS
15
76
40-50
25
108
49-56
35
121
49-59
69
142
62-93
138
160
97-101
230
178
159-173
345
196
500
219
LEAD SHEATH
Large conductor
XLPE insulation - maximum stress design
Insulation operates at much higher stress
than distribution cable
Metallic sheath, moisture barrier
Overall jacket
CORRUGATED
COPPER SHEATH
Voids in insulation
Voids between extruded layers
Inclusions & contaminants
Effects of moisture in insulation (treeing)
semicon
insulation
semicon
insulation
insulation
semicon
semicon
insulation
semicon
insulation
insulation
semicon
Dirt
Metal
Contaminant
Water
Porcelain or polymer
housing
Filled with fluid dielectric
Pre-molded stress cone
Proper connection
between termination and
cable metallic shield
CONNECTOR
HEAT SINK
uniform heat:
Heat-shrink layers must shrink tightly and uniformly against cable core.
Insufficient heat:
Heat-shrink layers do not shrink tightly against cable core.
Non-uniform heat:
Layers may shrink off-center. Over heating may
crack layers.
Defective surge
arrester
Diagnostic Technique
CableWISE Technique (Frequency Resolved)
Custom sensors can detect low energy (<1 pC), high frequency
(300 MHz) signals.
TP #1 at Riser Pole
TP #3 at Halfway Manhole
TP #2 at Substation
Level 1
Level 2
Level 3
Level 4
Level 5
Component is at the end of economic life and has a high probability of failure within
two years. Recommend immediate attention.
Level 4 :
Level 5:
MANHOLE
SUBSTATION
20
(A)
Signals (mV
July 1999
10
0.0
0.0
20
(B)
January 2000
Signals(mV)
800
400
Distance (ft)
10
0.0
0.0
400
Distance (ft)
800
3.5 circuit miles, new 138 kV XLPE cable circuit with eight fieldmolded joints per phase.
Joint failures within 2 months from being energized. The joints in first
manhole were replaced with pre-molded splices.
Condition Levels
1 2 3 4 5
Field-molded splices
Re
pla
ce
d
PD (mV)
12.0
0.0
Splice, PD level 2
1.0
PD (mV)
Splice, PD level 5
0.0
After repairs, CableWISE assessed the circuit as follows: one Level 5 joint, 6
Level 4 joints and 3 Level 3 joints. No activity was detected in the cable and
terminations (Level 1).
Examination of the Level 5 joint by an independent laboratory revealed
voids within one inch of the area where the Level 5 reading was measured
in the field.
New installation
1.5 mile 60 kV XLPE 1/C
4 x 3 splices
Single point bonding at both ends
Cross bonding for center joints
A
View of joints in vault TV-127.
Phase A joint (bottom) is
showing significant level signals.
View A, shows two sensors
placed at equal distance from
possible source location as
detected with time trace as
shown in view B. View C,
further pinpoints most likely
longitudinal location of source in
joint structure
VAULT TV-127
VAULT TV-127
JULY 2004 SPECTRUM
(ENLARGED)
VAULT TV-137
APRIL 2004
SPECTRUM
APRIL 2004
ZERO SPAN
VAULT TV-137
JULY 2004 SPECTRUM
(ENLARGED)
Summary
The online technology described here is a non-destructive
diagnostic technique that can:
Check the new cable system installation
Increase electrical system reliability
Avoid unplanned outages
Reduce maintenance costs
Prioritize cable system maintenance
Assess entire cable system & components,
regardless of insulation or circuit configuration
NOTE:
Pipe type cable does not require cross-bonding
because the metallic shields of the phase cables
are in continuous contact with each other and the
induced shield voltages are continuously canceled.
Electrostatic flux
lines
overall jacket
Semi-conducting
bedding tape
Equipotential Lines
ELD
SHI TAGE
E
L
L
CAB ED VO
C
U
IND
Cable shield
Cable length
Cable shield
Conductor load current
Cable ampacity and heat flow out of cable: Effect of shield current
He
a
cur t from
ren
t (la load
rge
)
Conductor
temperature
Insulation
thermal
resistance
Shield
temperature
Ri
Tc
Wc
Heat
fr
diele om insula
ctric
losse tion
s (sm
a
Jacket
thermal
resistance
Rj
Ts
Wd
Composite
thermal
resistance
from jacket
Cable jacket to earth
temperature
Earth ambient
temperature
Tj
Re
Ta
Ws
ll)
shield
inducted
Heat from e)
arg
current (l
Ri
Tc
Wc
Rj
Ts
Wd
Tj
Re
Ta
Ws
Cross-bonded shield
Connecting the cable shield in a cross-bonded pattern significantly reduces
the heat losses in the shield and allows a higher conductor temperature.
Thus, load current can be increased.
VOLTS
CABLE SHIELD
INDUCED VOLTAGE
with CROSS
BONDING
CABLE
LENGTH
0
The lengths of the minor
sections must be equal to
completely cancel shield
voltages.
CABLE
CONDUCTOR
MINOR SECTION
MINOR SECTION
MINOR SECTION
MAJOR TRI-SECTION
CABLE SHIELD
MANHOLE
MANHOLE
MANHOLE
MANHOLE
Defective surge
arrester
TERMINATION
COMPONENTS
CABLE PULL-IN
DAMAGE
SENSOR PLACEMENT
SUBSTATION
MANHOLE