You are on page 1of 8

NO

DESCRIPTION

1.0

Road Crossing - 3m

1.1

Earth works
Excavation in all materials other than rock including cart away from site

1.2

Concrete Works
50mm thick lean concrete Grade 15P/20 as blinding.
Reinforced concrete of the folowing grades:

(b)

Grade 30/20
Formwork as described to Class F1 & U1 finish type including falsework

(c )

To sides and soffit of pile cap


Hot Rolled Type 2 Deformed steel reinforcement bars as described
16mm Diameter
12mm Diameter
10mm Diameter

1.3

Precast Concrete Piles


Pile / 200mm / 30 tonnes
Supply, handle & pitch 200mm x 200mm initial/head pile 6.00m long.
Supply, handle & pitch 200mm x 200mm extension pile 6.00m long.
Drive to set 200mm x 200mm pile.
Butt weld connection 0.60m girth between edges of and including mild steel
extension head, base cap plates, bars etc and including coated heavily with
bituminous compound for jointing 200mm x 200mm R.C piles.
Cut off and dump away surplus length of 200mm x 200mm precast concrete
pile and strip off pile head, bend back reinforcement for connection as specified.

UNIT

QTY

M3

2.00

1.00

M3

6.44

M2

43.78

kg

141.90

kg

106.60

kg

204.20

24

120

144

NO

20

NO

RATE

TOTAL

NO

DESCRIPTION

2.0

Road Crossing - 5m

2.1

Earth works
Excavation in all materials other than rock including cart away from site

2.2

Concrete Works
50mm thick lean concrete Grade 15P/20 as blinding.
Reinforced concrete of the folowing grades:

(b)

Grade 30/20
Formwork as described to Class F1 & U1 finish type including falsework

(c )

To sides and soffit of pile cap


Hot Rolled Type 2 Deformed steel reinforcement bars as described
16mm Diameter
12mm Diameter
10mm Diameter

1.3

Precast Concrete Piles


Pile / 200mm / 30 tonnes
Supply, handle & pitch 200mm x 200mm initial/head pile 6.00m long.
Supply, handle & pitch 200mm x 200mm extension pile 6.00m long.
Drive to set 200mm x 200mm pile.
Butt weld connection 0.60m girth between edges of and including mild steel
extension head, base cap plates, bars etc and including coated heavily with
bituminous compound for jointing 200mm x 200mm R.C piles.
Cut off and dump away surplus length of 200mm x 200mm precast concrete
pile and strip off pile head, bend back reinforcement for connection as specified.

UNIT

QTY

M3

22.00

11.00

M3

90.64

M2

602.58

kg

2349.60

kg

1172.60

kg

2841.30

264

1320

1584

NO

220

NO

44

RATE

TOTAL

NO

DESCRIPTION

UNIT

QUANTITY

3.0 Road Crossing - Horizontal Directional Drilling (HDD)


3.1 ADDITIONAL
(a)

Mobilised all HDD equipment and all necessary personel, setting up


and moving to each and every position at each location and
dismantling completion. Rate to include all supervision and the
provision of HDD equipment.

(b)

Supply and deliver to store/pipe dumps on site, pipes,


special, joints, fittings and valves.
STRAIGHT PIPES
HDPE Pipe (from MoF aproved panel of suppliers)
160mm OD HDPE Pipe PN 10

Lump
Sum

939.483

939.483

(c ) LAY AND INSTALL OF PIPES, SPECIALS, FITTINGS AND VALVES


Installation of HDPE pipe under existing road using the HDD method
a) 160mm OD HDPE PipePN 10

RATE

TOTAL

NO

DESCRIPTION

4.0

Cable Trench

4.1

Earth works

(a)

Excavation in all materials other than rock including stockpiling aside


for embankment construction.

(b)

Supply, lay, grade and compact in layers imported sand fill and cement (dry mix)
material to formation level.

( C)

Supply, lay, grade and compact in layers imported suitable fill material to
formation level.

4.2

Protective cover
Construct and lay protective cover including materialspecified below:

(a)

Reinforced concrete Grade 20/20

(b)

Formwork as described to Class F1 & U1 finish type including falsework to sides


and soffit of concrete cover

( C)

Stel Mesh Reinforcement Type A6 (minimum 2.22 kg/m2)

UNIT

QTY

M3

35,131.15

M3

8,438.90

M3

26,692.50

M3

126.58

4,303.84

M2

2,531.67

RATE

TOTAL

You might also like