Particulars
Unit
Cum
Total Qty
A EARTHWORK
Jungle Clearance
Supply and filling in foundations and the area whereever specified
with approved good quality filling materials in plinths, area
development etc. wherever specified in layers of not exceeding
150 mm thick including breaking clods,storing,transportation
,double handling, watering, compacting each layer with vibratory
compactor and at unaccessible places with wooden/steel rammers
to achieve 90 to 95% proctor density at optimum moisture
content, all leads and lifts, bailing/ pumping out of water to keep
site dry while backfilling; cost shall include conveyance of all
materials, labour, machinery etc. complete as directed.The rate to
includes loading,unloading, hire and fuel charges for tools and
plants and other incidental charges etc., complete.
855.08
Sft
41,860.00
Cum
2,802.42
B CONCRETE
Providing and laying Plum concrete1: 5: 10. wherever specified
using river sand, 40mm and down size metal and boulders of
150mm (proportion 60: 40 for concrete : boulder ) including sub
grade preparation, leveling, all leads and lifts, rough finishing at
the top surface, curing,and shuttering if necessary etc.,
Cum
P.C.C. 1:4:8 as per above using 20mm and down size graded
granite aggregate 75mm thk below footing, raft slab, over plinth,
to make up level wherever necessary etc., as directed and
specified.
Cum
52.83
P.C.C. 1:3:6 as per above using 20mm and down size graded
granite aggregate 75mm thk below footing, raft slab, over plinth,
to make up level wherever necessary etc., as directed and
specified.
Cum
86.99
Page 1 of 6
Sl. No.
Particulars
Unit
Total Qty
Cum
200.82
Plinth Beams
Cum
34.46
Retaining walls
Cum
Columns Concrete
Cum
62.74
Cum
5.00
Lintels,Chejjas/Lofts
Cum
4.60
Cum
3.00
Cum
5.00
Cum
530.44
Cum
13.00
Sqm
556.55
Retaining walls
Sqm
Columns formwork
Sqm
767.02
Plinth Beams
Sqm
299.64
Sqm
4,373.90
Sqm
89.01
Sqm
35.70
Lintels,Chejjas/Lofts
Sqm
66.30
Sqm
15.00
Sqm
20.00
RMC
D FORM WORK
Providing, fabricating and erecting form work at all levels and
places wherever needed/specified as per drawing including
striking with 12mm Plastic coated, marine resistant waterproof
ply/Smooth finished MS plates with adjustable steel props of
acceptable Staging system and with sufficient bracing as approved
by consultant. Cost to include designing of proper form work and
staging system to suit the requirements,Submission of design
calculations and shop drawings for approval,sealing the joints
with heavy duty brown self adhesive tape, aligning to line and
levels including M.S. Ties, PVC Spacer, Providing openings/
cutouts/ pockets, applying deshuttering chemical, Deshuttering as
approved by the consultant etc., complete at all levels,
double/tripple heights and profiles for
Page 2 of 6
Sl. No.
Particulars
Unit
Total Qty
E STEEL FABRICATION
Fabricating & fixing in position reinforcement for RCC work with
high yield strength ribbed cold twisted tor steel (HSD) bar of
various diameters and grade of steel as specified below
conforming to IS specification including cutting, providing,
supplying & bending, hoisting, fabricating and placing in position
according to drawings and binding the reinforcement with
galvanised annealed binding wire of double fold of 18 gauge and
providing PVC cover blocks for placing the reinforcements in
position and for maintaining the cover specified and/or according
to relevant IS.
Note : Unless noted otherwise the measurements in accordance
with IS 1200. However reinforcement shall be measured only in
lengths of bars as actually placed in position on standard weight
basis, no allowance being made in the weight for rolling margin.
Authorised laps and splices only will be measured. Chairs of any
shape & profile, Spacer bar of any shape & profile, cover block,
wastage and binding wire will not be measured and shall be
included in the quoted rates.Quoted rate shall be deemed to have
considered the above stipulation.Quoted rate to include lead, lift,
placing at all levels and as directed.
Fe 500
MT
103.33
All Floors
Sqm
2,241.43
Sqm
64.41
Sqm
190.97
Cum
35.16
F MASONRY
Providing and constructing 150mm thick solid concrete block
masonry in CM 1:4 for walls/pillars/supports using
400x200x150mm with minimum crushing strength of 35
kg/sq.cm., including raking of joints, scaffoldings etc., complete as
per drawings and specifications.
G PLASTERING WORKS
Page 3 of 6
Sl. No.
Particulars
Unit
Total Qty
Sqm
2,523.62
Sqm
3,742.81
External Plastering
Sqm
3,140.43
Prepare single Coat surface and Rough plastering for toilets with
15mm thk CM 1:4 including finishing with necessary tools &
Tackles.
Sqm
763.72
Nos
34.00
Nos
30.00
Windows
Sft
1,670.00
Ventilators
Sft
90.00
J FLOORING WORKS
Providing & fixing machine cut, Granite Slab Flooring over 20mm
thick and including cement plaster C.M. 1:4 ,15mm backing with
neat cement including filling joints with white cement added with
pigments,curing, mirror polishing & acid washing etc. completeas
directed to the satisfaction of Engineer.
All Class Rooms & Corridors
Sqm
3,208.24
Staircase Flooring
Sqm
106.67
Sqm
159.94
Providing and laying Anti Skid Ceramic tile flooring for Toilets
of approved size, make and shade over a bed of CM 1:4 in cluding
finishing joints with matching colour , curing, acid wash cleaning
etc., complete as per drawing details and instructions
All Floors
Page 4 of 6
Sl. No.
Particulars
Unit
Total Qty
Sqm
507.22
Sqm
9.90
Sqm
Rft
103.32
Kg
2,023.32
Nos
1.00
Nos
1.00
Kg
100.00
Providing and fixing of M.S. ladders for Over Head Water Tank
Kg
250.00
LS
1.00
Supplying and fixing in position of M.S. bright bars for grills for
windows all welded together as per design and detailed drawing,
with two coats of enamel painting with a coat of red oxide primer,
etc complete. (not exceeding 13 kgs/sqm. )
All Floors
Page 5 of 6
Sl. No.
Particulars
Supplying and fixing in position of M.S. bright bars for grills for
windows @ Corridor as per design and detailed drawing, with
two coats of enamel painting with a coat of red oxide primer, etc
complete. (not exceeding 13 kgs/sqm. )
Unit
Kg
Total Qty
938.00
L PAINTING WORKS
Providing and painting with Plastic Emulsion paint of approved
make and shade thoroughly sand papering the surfaces, removing
loose burrs, dust, dirt, repairing dents, holes, cracks, etc, applying
2 coats of luppum+1 coat primer+2 coat asian plastic emulsion as
per specifications, including the cost of materials, labour,
scaffolding etc., all complete as directed in internal Walls in Flats.
All Floors
Sqm
6,440.96
Sqm
3,140.43
Sqm
81.97
Sqm
129.65
Sft
150.00
Ltrs
35,000.00
TOTAL AMOUNT
BUA
Total Cost\Sft
Page 6 of 6