06.01 Alcantarilla
06.01.01 Movimientos de tierras
06.01.01.01 Excavacion de terreno natural material suelto c/equipo
Descripcion
Und.
Medidas
Cant.
Largo
Ancho
Parcial
Observacion
Alto
Km 182+962 al Km 183+028
Fondo de canal
m3
1.00
60.00
2.85
0.30
51.30
Ua de anclaje de cimiento
m3
2.00
60.00
0.30
0.40
14.40
lateral de canal
m3
2.00
60.00
0.20
1.00
24.00
Fondo de canal
m3
1.00
60.00
2.85
0.30
51.30
Ua de anclaje de cimiento
m3
2.00
60.00
0.30
0.40
14.40
lateral de canal
m3
2.00
60.00
0.20
1.00
24.00
Km 183+074 al Km 183+134
Total metrado
179.40
m3
Parcial
Observacion
Und.
Medidas
Cant.
Largo
Ancho
Alto
Km 182+962 al Km 183+028
Fondo de canal
m2
1.00
60.00
2.85
171.00
Ua de anclaje de cimiento
m2
2.00
60.00
0.30
36.00
Km 183+074 al Km 183+134
Fondo de canal
m2
1.00
60.00
2.85
171.00
Ua de anclaje de cimiento
m2
2.00
60.00
0.30
36.00
Total metrado
414.00
m2
Parcial
Observacion
Und.
dimencion
Cant.
volumen
Ancho
Alto
Km 182+962 al Km 183+028
Fondo de canal
m3
1.00
60.00
2.85
0.30
51.30
Ua de anclaje de cimiento
m3
2.00
60.00
0.30
0.40
14.40
lateral de canal
m3
2.00
60.00
0.20
1.00
24.00
Fondo de canal
m3
1.00
60.00
2.85
0.30
51.30
Ua de anclaje de cimiento
m3
2.00
60.00
0.30
0.40
14.40
lateral de canal
m3
2.00
60.00
0.20
1.00
Km 183+074 al Km 183+134
24.00
Subtotal
179.40
20% de esponjamiento
35.88
Total metrado
215.28
m3
Parcial
Observacion
Und.
Medidas
Cant.
Largo
Ancho
Alto
Km 182+962 al Km 183+028
Fondo de canal
m2
1.00
60.00
2.85
171.00
Ua de anclaje de cimiento
m2
2.00
60.00
0.30
36.00
m2
1.00
60.00
2.85
171.00
m2
2.00
60.00
0.30
36.00
Km 183+074 al Km 183+134
414.00
m2
long.
elem.
cant.
Diam. Fierro
long.
veces
total
diam.
kg./m
Losa de fondo
Muros
Losa
60.00
6.00
2.00
720.00
1/2"
1.00
720.00
1.90
300.00
2.00
1,140.00
1/4"
0.25
285.00
3.20
300.00
1.00
960.00
5/8"
1.55
1,488.00
3.20
300.00
1.00
960.00
5/8"
1.55
1,488.00
60.00
11.00
2.00
1,320.00
1/2"
1.00
1,320.00
1.50
240.00
4.00
1,440.00
5/8"
1.55
2,232.00
60.00
4.00
4.00
960.00
1/2"
1.00
960.00
2.30
240.00
2.00
1,104.00
5/8"
1.55
1,711.20
60.00
6.00
2.00
720.00
1/2"
1.00
720.00
60.00
4.00
2.00
480.00
1/2"
1.00
480.00
1.25
240.00
4.00
1,200.00
1/2"
1.00
1,200.00
60.00
6.00
2.00
720.00
1/2"
1.00
720.00
1.90
300.00
2.00
1,140.00
1/4"
0.25
285.00
3.20
300.00
1.00
960.00
5/8"
1.55
1,488.00
Losa de fondo
Muros
Losa
3.20
300.00
1.00
960.00
5/8"
1.55
1,488.00
60.00
11.00
2.00
1,320.00
1/2"
1.00
1,320.00
1.50
240.00
4.00
1,440.00
5/8"
1.55
2,232.00
60.00
4.00
4.00
960.00
1/2"
1.00
960.00
2.30
240.00
2.00
1,104.00
5/8"
1.55
1,711.20
60.00
6.00
2.00
720.00
1/2"
1.00
720.00
60.00
4.00
2.00
480.00
1/2"
1.00
480.00
1.25
240.00
4.00
1,200.00
1/2"
1.00
1,200.00
25,208.40
Und.
dimencion
Cant.
Largo
Ancho
Parcial
Alto
m2
4.00
60.00
0.75
180.00
losa de alcantarilla
m2
1.00
60.00
1.55
93.00
m2
2.00
60.00
0.25
30.00
Observacion
m2
2.00
2.05
0.25
1.03
Muros de alcantarilla
m2
4.00
60.00
0.75
180.00
losa de alcantarilla
m2
1.00
60.00
1.55
93.00
m2
2.00
60.00
0.25
30.00
m2
2.00
2.05
0.25
1.03
608.05
m2
Parcial
Observacion
Und.
dimencion
Cant.
Largo
Ancho
Alto
m3
1.00
60.00
2.85
0.25
42.75
ua de losa de fondo
m3
2.00
60.00
0.30
0.40
14.40
Muros de alcantarilla
m3
2.00
60.00
0.25
0.75
22.50
Losa de alcantarilla
m3
1.00
60.00
2.05
0.25
30.75
Losa de fondo
m3
1.00
60.00
2.85
0.25
42.75
ua de losa de fondo
m3
2.00
60.00
0.30
0.40
14.40
Muros de alcantarilla
m3
2.00
60.00
0.25
0.75
22.50
Losa de alcantarilla
m3
1.00
60.00
2.05
0.25
30.75
220.80
m3